CON-IPR-BAC-CI-003 –A

S.C. OMV PETROM S.A.

Bacau Depots
METHOD STATEMENT FOR
DEMOLITION WORKS
CONCRETE PLATFORMS

06/08/2012
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

REVISION

Eremia Barboiu Cristian


A 06/08/2012 ISSUED FOR IDC VASILE DUMITRU SIMION

Rev. Date Issue, Modification Prepared Checked Approved

Page 1
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

DEMOLITION WORKS CONCRETE LUCRARI DEMOLARE PLATFORME


PLATFORMS BETONATE

1. SCOPE 1. SCOP

This procedure contains the conditions that Prezenta procedura contine conditiile ce
must be observed and required activities for trebuiesc respectate si activitatile necesare
demolition concrete platforms. demolarii platformelor betonate.

2. DOMAIN 2. DOMENIUL DE APLICARE

The procedure applies to the execution of Procedura se aplica la executia lucrarilor de


demolition concrete platforms, which are based demolare a platformelor betonate,care au la
on a technical project and a contract execution. baza un proiect tehnic si un contract de
executie.

3.REFERENCE DOCUMENTATION 3. DOCUMENTATIE DE REFERINTA

- ISO 9001- Quality management Systems. - ISO 9001- Sisteme de management al


Requirements; calitatii. Cerinte;
- ISO 9000- Quality management Systems. - ISO 9000- Sisteme de management al
Fundamental principles and vocabulary; calitatii.Principii fundamentale si vocabular
- ISO 14001-Environment management - ISO 14001- Sisteme de management de
Systems. Requirements and guides; mediu.Cerinte cu ghid de utilizare;
- OHSAS 18001-Occupational Health and - OHSAS 18001- Sisteme de management
Security Management Systems. al sanatatii si securitatii
Specification; upationale.Specificatie;
- HSEQM-01 –Quality, Environment and - HSEQM-01 – Manualul calitatii, mediului,
Occupational Health and Security Manual; sanatatii si securitatii;
- GD 766 - Regulation for conducting and - HGR 766- Regulament pentru conducerea
ensuring quality conditions in construction; si asigurarea calitatii in constructii;
- GD 399 – Regulation for issuing technical - HGR 399- Regulament privind elaborarea
regulations in construction for the quality reglementarilor tehnice in constructii
systems components; pentru componentele sistemului calitatii;
- GD 925 - Regulation of quality inspection - HGR 925- Regulamentul de verificare si
and technical expertise of projects, works expertizare tehnica de calitate a
execution and construction; proiectelor, a executiei lucrarilor si a
constructiilor;
- Guide for the execution of demolition works; - Ghid pentru exec. lucrarilor de demolare;
- G.O. 195 - Environmental Protection Law; - OUG 195- Legea protectiei mediului;
- Law 319/2006 – Occuppational Health and - Legea 319/2006 - Legea securitatii si
Security Law; sanatatii in munca;
- Law 426/2001 and G.O. 78 – Waste - Legea 426 si OG78- Regimul deseurilor;
Regime; - Plan general de securitate si sanatate in
- General Occupational Health and Safety munca;
Plan; - Planul de management al mediului,
- Environmental Management Plan, Bacau. Bacau;

Page 2
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

1 NOTE 1: At the date of current document NOTA 1: La data utilizarii prezentului


use, all the above-mentioned reference document se folosesc editiile si reviziile in
documents in force are used vigoare ale documentelor de referinta
mentionate mai sus.

4.DEFINITIONS 4. DEFINITII

- Works preparing – establish the labor - pregatirea lucrarii – stabilirea necesarului


requirements, technical equipment, quality de forta de munca, a dotarii tehnice, a
conditions required by the documentation, conditiilor de calitate impuse de
the material base and its supply under the documentatie, a bazei materiale si
terms of entire demolition documentation. aprovizionarea acesteia in conditiile impuse
de documentatia de demolare.
- Permanent joints – asamblari care pot fi - asamblari nedemontabile – asamblari
demontate numai prin metode distructive care pot fi demontate numai prin metode
distructive
- dismantling – overall operations of - demontare – ansamblu de operatiuni de
disassembly of the component parts of an dezasamblare a partilor componente ale
installation unei instalatii
- demolition – overall set of works and - demolare –ansamblu de lucrari si
special operations aimed at dismantling an operatiuni specializate care au ca scop
installation in safe conditions. dezafectarea unei instalatii in conditii de
siguranta.

4.1. Abbreviations 4.1. Prescurtari

CF – Team Leader - superintendant CF – Conducator formatie - superintendent


RSVTI – Responsible with technical RSVTI –Responsabil cu supravegherea si
surveiilance and inspection of installations. verificarea tehnica a instalatiilor
PO – Operational Procedure PO – Procedura operationala
PS – System Procedure PS – Procedura de sistem
AQ – Quality Assurance AQ – Asigurarea calitatii
QC – Quality Control QC – Controlul calitatii

5. QUALITY CONTROL 5. CONTROLUL CALITATII

1. Responsible person in the works area 1. Persoana responsabila in zona de lucru


will instruct subordinate staff to carry out va instrui personalul subordonat care va
activities under the execution lucra conform procedurii de executie;
procedure;
2. Technical Responsible will undertake 2. Responsabilul tehnic va face inspectii in
inspections in each stage of works fiecare etapa a executiei lucrarilor.
execution.

6. GENERAL RULES 6. REGULI GENERALE


1.Demolition / dismantling will be done 1. Lucrările de demolare/demontare se vor
with specific equipment. Before starting face cu ajutorul utilajelor specifice. Înainte
work all necessary measures will be de începerea lucrărilor se vor lua toate
taken to prevent accidental fall of various măsurile necesare pentru a preveni căderea

Page 3
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

parts of demolished buildings on other accidental a diferitelor părţi ale constructiilor


nearby buildings or pipelines; demolate pe alte constructii sau conducte
din apropiere;
2. The Site manager will instruct the staff 2.Seful de santier va instrui personalul cu
on the works chart, OH&S regulations as privire la graficul de execuţie al lucrărilor,
well as the Emergency Situations (ES) regulile de SSM si regulile SU;
rules;
3.All manholes, drainage systems 3. Toate căminele de vizitare, sistemele de
remaining in operation will be adequately drenaj care ramin in functie vor fi
protected; protejate in mod corespunzator;
4.Storage of materials will be made by 4. Depozitarea materialelor se va face
sorting them according to their destination: cu sortarea acestora, in functie de
recycling or disposal at waste dump. Sorting is destinatia lor: reciclare sau evacuarea
done on their types: metal, rubble (which lor la groapa de deseuri. Sortarea se
includes concrete, reinforced concrete, va face pe tipuri-le: metal, moloz (ce
masonry, etc.); cuprinde beton, beton armat, zidarie,
etc.);
5.Metallic material will be stored in the 5. Materialul metalic se va depozita in
established place, its evacuation is the locul stabilit, evacuarea lui fiind in
responsibility of another contractor. sarcina altui contractor.

7. DESCRIPTION of PROCEDURE 7. DESCRIEREA PROCEDURII


1.Preliminary Activities 1. Activitati preliminare
a. Before works start the Permit of Work will be a. Inainte de inceperea lucrarilor trebuie
already obtained as per the Project’s HSE obtinut Permisul de lucru in conformitate cu
Procedures; Project’s HSE Procedures;
b. Identify the area to be demolished / b. Identificarea zonei care va fi demolata/
dismantled; demontata;
The works will start only after the following Lucrarile vor incepe numai dupa verificarea
operations have been checked: whether all urmatoarelor: daca s-au debransat toate
utilities were disconnected (water, sewage, utilitatile (apa, canal, electric, gaz,
electric, gas, telephone); whether all telefonie), daca s-au evacuat toate
equipment and materials were evacuated; if echipamentele materialele; daca s-au
those items intended to be recovered were demontat acele obiecte care se doresc
dismantled and whether the electric cables, recuperate si daca s-a realizat devierea
pipes, etc. deviation was achieved, (if case, cablurilor electrice, conductelor , etc.(daca
in order to keep in operating parameters all este cazul , pentru a se mentine in stare de
the objectives in the close area). functionare a obiectivelor aflate in
vecinatate).
c.Preparing work area in compliance with c.Pregătirea zonei de lucru cu respectarea
OH&S and Emergency Situations (ES) rules, normelor de SSM si SU, conform “Planului
according to the “General Occupational Health General de securitate si sanatate in munca”;
and Safety Plan”; d.Imprejmuirea zonei in care se executa
d.Fencing the area where demolition is run – demolarea – imprejmuire cu gard organizare
site organization enclosed with fence / tape santier / banda avertizare;
warning;
e.Preparation of access to work area; e.Pregatirea accesului catre aria de lucru;
f.Equipment transport to work area; f.Transportul echipamentului in zona de lucru;
g.Preparation of access to the work area of g. Pregatirea accesului catre zona de lucru a
demolition equipment and identify areas where echipamentelor de demolare si identificarea

Page 4
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

there are objects that can be damaged and to zonelor in care se afla obiecte ce pot fi
protect them: manholes, drain inlets, pipes, deteriorate si protejarea acestora: camine
construction. vizitare, guri scurgere, conducte, constructii

2.Activities within demolition works 2.Activitati in cadrul lucrarilor de


demolare
a. Demolition shall be conducted under a a. Demolarea se va realiza conform unui
pre-established plan (grid), maintaining plan(caroiaj) prestabilit mentinind in
permanently free access routes for permanenta cai de acces libere pentru
equipment and personnel; utilaje si personal;
b. The areas to be demolished will be b. Zonele in care se demoleaza vor fi
fenced and signalized with warning tape; imprejmuite si semnalizate cu banda;
c. Before starting demolition will be c. Inainte de inceperea demolarii se vor
carried out random holes in the areas executa gropi de sondaj in zone indicate de
indicated by the Employer; beneficiar;
d. Possible routes of pipelines and d. Eventualele trasee de conducte si cabluri
cables that will remain in operation after electrice care vor ramine in functie dupa
demolition will be marked and protected demolare vor fi protejate si semnalizate in
during demolition; timpul demolarii;
e. Demolition is made by the excavator e. Demolarea se executa cu ajutorul
(provided with pickaxe and cup) as well excavatorului(echipat cu picon si cupa) si a
as the bulldozer; buldozerului;
f. Evacuation of scraps is done using the f. Evacuarea sparturilor se face cu ajutorul
front loader and tipping lorries; incarcatorului frontal si al
autobasculantelor;
g. Concrete scraps resulting from g. Sparturile de beton rezultate in urma
demolition will be transported in the demolarii se vor incarca in autobasculanta
ecological pit.; si transportate la groapa de gunoi
ecologica;
h. After execution of demolition works, h. Dupa executarea lucrarilor de demolare se
the work area will be cleaned from the va curata zona de lucru de deseurile
waste resulting from the demolition, and rezultate in urma demolarii si se vor evacua
the equipments used during the works will utilajele folosite pe perioada lucrarilor;
be disposed.

8. RESPONSIBILITIES 8. RESPONSABILITATI
1. The Site manager is responsible to 1. Seful de santier are responsabilitate de
check the works so that they might be a verifica lucrarile astfel incit sa fie
performed in compliance with the executate in conformitate cu prezenta
current procedure; procedura;
2. Personnel involved in the works shall 2. Personalul implicat in aceste lucrari
hold a valid certificate for the work they trebuie sa detina un certificat valid
are undertaking; pentru lucrarile pe care le efectueaza.
3. HSE Responsible will check and admit 3. Responsabilul SSM va verifica si va
to work only the machines that meet the admite la lucru numai utilajele care
technical requirements of the works to corespund din punct de vedere tehnic
be performed; lucrarilor ce se vor executa;
4. Environmental Protection Responsible 4. Responsabilui cu problemele de
is liable to observe the regulations in protectia mediului are responsabilitatea

Page 5
Depots Revamp CON-IPR-BAC-CI-003-A
Method Statement for Demolition Works Concrete Platforms

force concerning the transportation and respectarii legislatiei in vigoare privind


storage of waste resulting from transportul si depozitarea deseurilor
demolition works. rezultate in urma demolarii;

9.RISK PREVENTION AND 9. PREVENIRE RISC SI


HSE INSTRUCTIONS INSTRUCTIUNI SSM
1. Risks : 1. Riscuri:
a. Material shot; a. Improscarea cu material;
b. Objects fall from height; b. Cadere obiecte de la inaltime;
c. Inhalation of dust; c. Inhalare de praf;
d. Fall from same level, stumble; d. Cadere de la acelasi nivel,
impiedicare;
e. Traffic accident. e. Accident de circulatie;

2. Prevention and Protection Measures: 2. Masuri de prevenire si protectie :


a. There will be checked the way a. Se va verifica modul de debransare
how utilities were disconnected - a utilitatilor – curent, gaze, apa;
water, electric power, gas;
b. Direct contact with electric lines b. Se interzice contactul direct cu
even if disconnection has been conductorii electrici chiar daca
executed is forbidden; debransarea a fost executata;
c. Parking on the access roads and c. Se interzice stationarea pe caile de
within the work area of equipments acces auto si in raza de actiune a
and machineries is forbidden; utilajelor;
d. Carrier vehicles and machinery shall d. Mijloacele auto si utilajele de lucru
not be left unattended with engine nu se vor lasa nesupravegheate, cu
running; motorul pornit;
e. A worker will be trained for e. Un lucrator va fi instruit in vederea
conducting traffic; dirijarii circulatiei;
f. All workers will wear reflective vests, f. Toti lucratorii vor purta veste
overalls, helmet, safety shoes with reflectorizante, salopete, casca,
metallic toe cap, gloves and, if incaltaminte de protective cu
necessary, dust mask; bombeu metallic, manusi si dupa
caz, masca antipraf;
g. During loading the drivers of vehicles g. In timpul incarcarii in mijloace auto
will not stay in the cabin conducatorii auto nu vor sta in
cabina.