Professional Documents
Culture Documents
Subcon Itp
Subcon Itp
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s Orion systems DMCC
Security systems and
Work to be Performed: PABGM installation and Page 1 of 6
configuration
ACTIVITY: Provision of Security Systems, IT and Audio Systems for The Cove Area ALL AREA
Inspection Level
Sr. Inspection
Description Specification / Criteria Records / Remarks
No. Frequency
ITL Consultant ATS Client
1 SUBMITTALS
Manufacturer shall be
approved. All electrical
materials and equipment
shall have passed
adequate routine factory
Material approval
Verification of materials for test. All Materials and
1.1 F H A H request/ test
security systems and PABGM components/ accessories
certificates
shall comply with
applicable National and/ or
Local Codes, Standards
and Regulations and shall
be as per ISO standard.
Certificates of delivered
materials shall be
indicating
Material Approval while we (DTF) Document
1.2 compliance with
receive on site transmittal form
specifications. Date of
manufacturer
shall label on packages.
FOR CODE USE:
W – WITNESS POINT (OPTIONAL) H – HOLD POINT (MANDATORY) – WORK NOT TO PROCEED WITHOUT APPROVAL S – SURVEILLANCE OR MONITORING
E – EACH TIME CHECK F – FIRST TIME CHECK SD – SHOP DRAWINGS MA – MATERIAL APPROVAL
MIR – MATERIAL INSPECTION REQUEST CH – CHECKLIST WIR – WORK INSPECTION CHECKLIST LA – LOCAL AUTHORITY
X – SELF INSPECTION BY PERFORMER OF WORK A – APPROVAL ITL – Independent test laboratory SC- Sub-Contractor
QR.N-27B/R-002/Aug2017
INSPECTION AND TEST PLAN
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s XXXX
Work to be Performed:
(Block Work) Page 2 of 6
QR.N-27B/R-002/Aug2017
INSPECTION AND TEST PLAN
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s XXXX
Work to be Performed:
(Block Work) Page 3 of 6
QR.N-27B/R-002/Aug2017
INSPECTION AND TEST PLAN
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s XXXX
Work to be Performed:
(Block Work) Page 4 of 6
QR.N-27B/R-002/Aug2017
INSPECTION AND TEST PLAN
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s XXXX
Work to be Performed:
(Block Work) Page 5 of 6
identification and
unambiguous labelling to
avoid incorrect operation,
human error, accidents,
etc.
There are no sharp edges
throughout the run to
avoid damages of the
cable, and clamping bolts
present smooth heads
inside the trays.
2.3 Testing and Sequence Inspection and testing shall E H H H WIR
be conducted by the Site
Engineer. Verification of
inspection, Check
List and Test shall be
witnessed, recorded and
signed by QA/QC
Engineer/Officer
A visual inspection shall be
carried out on First Stage
Testing to verify that there
are no physical damages
to the installation of
Cables. Final inspection
shall take place
immediately after all
relevant works have
been completed.
Cable Sizes and Routes
installed will be according
to approved shop drawing.
FOR CODE USE:
W – WITNESS POINT (OPTIONAL) H – HOLD POINT (MANDATORY) – WORK NOT TO PROCEED WITHOUT APPROVAL S – SURVEILLANCE OR MONITORING
E – EACH TIME CHECK F – FIRST TIME CHECK SD – SHOP DRAWINGS MA – MATERIAL APPROVAL
MIR – MATERIAL INSPECTION REQUEST CH – CHECKLIST WIR – WORK INSPECTION CHECKLIST LA – LOCAL AUTHORITY
X – SELF INSPECTION BY PERFORMER OF WORK A – APPROVAL ITL – Independent test laboratory SC- Sub-Contractor
QR.N-27B/R-002/Aug2017
INSPECTION AND TEST PLAN
Main Contractor:
M/s Al Tayer Stocks LLC
AL TAYER STOCKS LLC
Subcontractor:
M/s XXXX
Work to be Performed:
(Block Work) Page 6 of 6
QR.N-27B/R-002/Aug2017