Professional Documents
Culture Documents
PMOEC CompositeProjectStatusDashboard
PMOEC CompositeProjectStatusDashboard
1 2
Solicited Member Input Reviewed Member Dashboards and Scorecards
3.0
2.5
2.0
1.5
1.0
0.5
0.0 0 2 4 6 8 10 12
8
7
6
5
4
3
2
1
0
Portfolio Dashboard
PMO Scorecard
Issues New Open Closed Risk Description Symptoms Risk Prob- Impact Action
Schedule Y Owner ability
Current Period 10 2 8
Because we may not have enough If three data • Detailed resource and test plans
Year to Date 25 10 15
people to manage the data migration analysts A. ahead of flexible migration tool
Issues/Risk G and clean-up, the full transition may leave Alpha Smith
High High
not be achieved in six months. Test Results
Open Issue Resolution Plan Due Date Owner
Staff G Development Provide June 10 T. Amicci
Because we may not fully Pilot test • Estimate/test/validate/prototype
understand the current network resulting pages weight including best page
cost exceeding updated cost– G. Medium High
limitations, we may not be able in 7% reduction techniques
expectation. benefit analysis Carter
Scope Y to properly plan the system. downtime • Find the six seconds boundary
to business
sponsors. and the population impacted
3
Budget G /Schedule Y
Project Overall Schedule Critical Chain Status
Work in Progress
Planned Earned Actual Project Measurements Work Stream Schedule
PV BAC EV AC SPI=EV/AC EAC=BAC/ in Progress
SPI (Only Tasks That EV PV SPI BAC EAC
Belong to Project (Hours) (Hours) (Hours) (Hours) (Hours)
(Hours) (Hours) (Hours) (Hours) (Hours) (Hours) Critical Chain) BAC/SPI
800 22,100 320 360 0.88 25,114 Business segment 5 5 1.0 104 104
support
Project Overall Budget
Beta system 17 20 0.85 173 204
Planned Earned Actual Project Measurements testing
AC = Actual Cost (Dollars or Hours).
PV BAC EV AC CPI=EV/AC EAC=BAC/
BAC = Budget at Completion (Dollars or Hours).
CPI CPI = Cost Performance Index (Determined Through Earned Value Analysis).
($) ($) ($) ($) N/A ($) EAC = Estimate at Completion (Dollars or Hours).
EV = Earned Value.
26,850 1,476,220 21,690 19,200 1.13 1,336,930 PV = Planned Value.
SPI = Schedule Performance Index (Determined Through Earned Value Analysis).
5 6
Scope Y Business Sponsor
Engagement
Deliverable Functionality Project Change Requests
Attendance of Steering
Committee Meetings
Actual/ Project Change Total Approved
50
Anticipated Forecasted Request # # $ Hours
Delivery Delivery Current 75
Functionality Date Date Status Current Period 2 2 540 10
Display value 06/02 06/08 Closed Life to Date 11 6 1,750 120 100
headers with Unresolved Project Change Requests Attendance Risk
or without 0–50% Very High
documentation. Project Change Impact if Implemented Requested 50–75% High
75–100% Moderate
Search for values 06/06 06/12 Open Request (Hours) $ By 100% Low
by name.
Add ability to search 11 335 A. Smith
Display value images. 06/08 06/15 Open by priority values.
Add a new section 25 502 J. Doe
for file repository.
Source: PMO Executive Council research.
5 6
Scope Y Business Sponsor
Engagement
Deliverable Functionality Project Change Requests
Attendance of Steering
Committee Meetings
Actual/ Project Change Total Approved
50
Anticipated Forecasted Request # # $ Hours
Delivery Delivery Current 75
Functionality Date Date Status Current Period 2 2 540 10
Display value 06/02 06/08 Closed Life to Date 11 6 1,750 120 100
headers with Unresolved Project Change Requests Attendance Risk
or without 0–50% Very High
documentation. Project Change Impact if Implemented Requested 50–75% High
75–100% Moderate
Search for values 06/06 06/12 Open Request (Hours) $ By 100% Low
by name.
Add ability to search by 11 335 A. Smith
Display value images. 06/08 06/15 Open priority values.
Providing cumulative and detailed value for
Project Change Requests enables managers to Add a new section for 25 502 J. Doe
make informed choices on future budget and file repository.
resource allocation decisions.