10 Construction Period Important 11 Nullifying Positive Change of Scope Order Important
12 Negative Change of Scope
Important Details 910 days for most of the projects
§ Concessionaire can nullify change of scope orders if their sum in
any 3 consecutive years exceeds 10% of bid cost and 25% overall at any times § These numbers were 5% and 20% respectively in earlier concessions § Reduction in Change of Scope would reduce the bid project cost by the % reduction in the civil cost § O&M payments will also be reduced or increased proportionate to the length reduced or increased § Earlier obligations for works under negative change of scope were deemed to be fulfilled by paying 80% of the cost savings from such reduction