BESI BETON ( P = 12 m ) BESI SIKU

UKURAN JENIS BERAT/m'


UKURAN
DIAMETER kg
f 6 mm polos 0.2217 20.20.3 mm
f 8 mm polos 0.3950 25.25.3 mm
f 10 mm polos 0.6167 25.25.5 mm
f 12 mm polos 0.8917 30.30.3 mm
f 13 mm ulir 1.0417 40.40.3 mm
f 14 mm polos 1.2083 40.40.4 mm
f 16 mm polos 1.5833 40.40.5 mm
f 16 mm ulir 1.5833 45.45.4 mm
f 19 mm ulir 2.2300 45.45.5 mm
f 22 mm ulir 2.9800 50.50.4 mm
f 25 mm ulir 3.8500 50.50.5 mm
f 32 mm ulir 6.3125 50.50.6 mm
60.60.5 mm
BESI PLAT HITAM 60.60.6 mm
65.65.6 mm
BERAT/lbr 70.70.6 mm
UKURAN
kg 70.70.7 mm
1,2 X 1200 X 2400 mm 28.00 75.75.6 mm
1,4 X 1200 X 2400 mm 33.00 75.75.7 mm
1,5 X 1200 X 2400 mm 35.00 75.75.8 mm
1,8 X 1200 X 2400 mm 42.00 75.75.9 mm
1,9 X 1200 X 2400 mm 44.50 80.80.8 mm
2 X 1200 X 2400 mm 46.70 90.90.7 mm
2,3 X 1200 X 2400 mm 54.00 90.90.9 mm
2,6 X 1200 X 2400 mm 60.70 90.90.10 mm
2,8 X 1200 X 2400 mm 65.30 100.100.7 mm
2,9 X 1200 X 2400 mm 67.60 100.100.10 mm
3 X 1200 X 2400 mm 70.00 120.120.11 mm
3,2 X 1200 X 2400 mm 74.70 120.120.12 mm
4 X 1200 X 2400 mm 93.30 125.125.12 mm
4,5 X 1200 X 2400 mm 105.00 130.130.9 mm
5 X 1200 X 2400 mm 117.00 130.130.12 mm
6 X 1200 X 2400 mm 140.00 150.150.10 mm
8 X 1200 X 2400 mm 187.00 150.150.12 mm
9 X 1200 X 2400 mm 210.00 150.150.15 mm
10 X 1200 X 2400 mm 233.00 2.88 200.200.15 mm
12 X 1200 X 2400 mm 280.00 80.90 200.200.20 mm
13 X 1200 X 2400 mm 303.00 200.200.25 mm
15 X 1200 X 2400 mm 350.00 250.250.25 mm
16 X 1200 X 2400 mm 373.00
18 X 1200 X 2400 mm 420.00
19 X 1200 X 2400 mm 443.00
20 X 1200 X 2400 mm 467.00
21 X 1200 X 2400 mm 490.00
22 X 1200 X 2400 mm 513.00
25 X 1200 X 2400 mm 583.00
28 X 1200 X 2400 mm 653.00
30 X 1200 X 2400 mm 700.00
32 X 1200 X 2400 mm 747.00
38 X 1200 X 2400 mm 887.00
42 X 1200 X 2400 mm 980.00
45 X 1200 X 2400 mm 1,050.00
50 X 1200 X 2400 mm 1,167.00
65 X 1200 X 2400 mm 1,516.00
75 X 1200 X 2400 mm 1,750.00
85 X 1200 X 2400 mm 1,983.00
100 X 1200 X 2400 mm 2,333.00

BESI KANAL UNP BESI KANAL "C" LIP

BERAT/6m
UKURAN UKURAN
kg
50.36.5 mm 33.50 60.30.10.1,2
65.42.5,5 mm 42.50 60.30.10.2,3
75.40.5 mm 41.50 75.35.10.1,6
80.45.5 mm 47.00 75.45.15.2,3
100.50.5 mm 56.20 100.50.20.2,3
120.55.6 mm 75.00 100.50.20.3,2
125.55.6 mm 80.40 125.50.20.2,3
140.60.7 mm 96.00 125.50.20.3,2
150.75.6,5 mm 112.00 150.50.20.2,3
160.66.7 mm 115.50 150.50.20.3,2
180.75.7 mm 132.00 150.65.20.2,3
200.80.7,5 mm 152.00 150.65.20.3,2
220.80.9 mm 187.50 200.75.20.3,2
240.85.9,5 mm 205.00
250.80.7,1 mm 182.50
250.90.9 mm 208.00
260.90.10 mm 114.00
300.90.9 mm 229.00
300.100.10 mm 278.00
380.100.10,5 mm 337.50
PIPA PERSE

UKURAN ( mm )

12,5 X 12,5
15 X 15
20 X 20
25 X 25
30 X 30
40 X 40
10 X 20
12,5 X 27,5
15 X 30
20 X 40
25 X 50
20 X 60
BESI SIKU

BERAT/6m LEBAR PANJANG BERAT/lbr


UKURAN
kg mm mm kg
20.20.3 mm 5.31 16 6000 2.3
25.25.3 mm 6.72 19 6000 2.7
25.25.5 mm 10.60 25 6000 3.53
30.30.3 mm 8.16 32 6000 4.52
40.40.3 mm 11.00 38 6000 5.37
40.40.4 mm 14.50 19 6000 4.03
40.40.5 mm 18.00 25 6000 5.4
45.45.4 mm 16.44 32 6000 6.8
45.45.5 mm 20.50 38 6000 8.3
50.50.4 mm 18.40 50 6000 10.6
50.50.5 mm 3.75 19 6000 5.4
50.50.6 mm 27.58 25 6000 7.1
60.60.5 mm 27.30 32 6000 9.2
60.60.6 mm 32.52 38 6000 10.7
65.65.6 mm 35.46 50 6000 14.5
70.70.6 mm 38.28 65 6000 18.5
70.70.7 mm 44.28 75 6000 21.5
75.75.6 mm 41.22 85 6000 25.5
75.75.7 mm 45.00 100 6000 28.5
75.75.8 mm 54.18 150 6000 44.5
75.75.9 mm 59.80 25 6000 10.6
80.80.8 mm 57.96 32 6000 14
90.90.7 mm 57.54 38 6000 16.1
90.90.9 mm 73.20 50 6000 21.2
90.90.10 mm 79.80 65 6000 27.5
100.100.7 mm 64.25 75 6000 32
100.100.10 mm 90.60 85 6000 38.3
120.120.11 mm 119.40 100 6000 42.5
120.120.12 mm 130.00 150 6000 64
125.125.12 mm 140.00 25 6000 14.2
130.130.9 mm 107.10 38 6000 21.5
130.130.12 mm 140.10 50 6000 28.5
150.150.10 mm 140.00 65 6000 37
150.150.12 mm 164.00 75 6000 42.5
150.150.15 mm 202.00 100 6000 56.5
200.200.15 mm 272.00 150 6000 85
200.200.20 mm 358.00 38 6000 29
200.200.25 mm 442.00 50 6000 38
250.250.25 mm 562.00 100 6000 76
150 6000 113
38 6000 34
50 6000 45
65 6000 58.5
75 6000 67.5
100 6000 89.5
125 6000 112
150 6000 134

BESI W.F

UKURAN TEBAL PANJANG


mm mm M'
100 X 50 X 5 7 12
125X 60 X 6 8 12
148X 100 X 6 9 12
150X 75 X 5 7 12
175X 90 X 5 8 12
198X 99 X 4.5 7 12
200X 100 X 3.2 4.5 12
BESI KANAL "C" LIP 200X 100 X 5.5 8 12
248 X 124 X 5 8 12
BERAT/6m 250 X 125 X 6 9 12
UKURAN
kg 298 X 149 X 6 8 12
60.30.10.1,2 7.44 300 X 150 X 6.5 9 12
60.30.10.2,3 346 X 174 X 6 9 12
75.35.10.1,6 13.90 350 X 175 X 7 11 12
75.45.15.2,3 19.50 396 X 199 X 7 11 12
100.50.20.2,3 24.40 400 X 200 X 8 13 12
100.50.20.3,2 33.00 446 X 1990 X 8 12 12
125.50.20.2,3 27.10 450 X 200 X 98 14 12
125.50.20.3,2 36.80 496 X 199 X 9 14 12
150.50.20.2,3 30.00 500 X 200 X 10 16 12
150.50.20.3,2 40.60 588 X 300 X 10 16 12
150.65.20.2,3 33.00 596 X 199 X 9 14 12
150.65.20.3,2 45.10 600 X 200 X 11 17 12
200.75.20.3,2 56.00 600 X 300 X 13 20 12
700 X 300 X 13 24 12
800 X 300 X 14 26 12

BESI I.N.P

UKURAN TEBAL PANJANG


PIPA PERSEGI cm mm M'
80 x 42 x 3.9 x 5.9 2.3 6
BERAT/6m 100 x 50 x 4.5 x 6.8 2.7 6
UKURAN ( mm ) TEBAL ( mm )
kg 120 x 58 x 5.1 x 7.7 3.1 6
12,5 X 12,5 0.90 0.3320 120 x 58 x 5.1 x 8.6 3.4 6
15 X 15 0.90 0.4030 160 x 74 x 6.5 x 9.5 3.8 6
20 X 20 0.90 0.5440 180 x 82 x 6.9 x 10.4 4.1 6
25 X 25 1.00 0.7590 200 x 90 x 7.5 x 11.3 4.5 6
30 X 30 1.00 0.9150 220 x 98 x 8.1 x 12.2 4.9 6
40 X 40 1.20 1.4680 240 x 106 x 8.7 x 13.1 5.2 6
10 X 20 0.90 0.4030 250 x 125 x 7.5 x 12.5 6
12,5 X 27,5 0.90 0.5440 260 x 113 x 9.4 x 14.1 5.6 6
15 X 30 0.90 0.6150 280 x 119 x 10.1 x 15.2 6.1 6
20 X 40 1.00 0.9150 300 x 125 x 10.8 x 16.2 6.5 6
25 X 50 1.40 1.5970 320 x 131 x 11.3x 17.3 6.9 6
20 X 60 1.40 1.9260 340 x 137 x 12.2x 18.3 7.3 6
360 x 143 x 13 x 19.5 7.8 6
380 x 149 x 13.7x 20.5 7.8 6
400 x 155 x 14.4 x 21.6 8.6 6
450 x 170 x 16.2 x 24.3 9.7 6
500 x 185 x 18 x 27 10.8 6

20
15
10
7.5
3.75
BERAT/Btg
kg
112
158.4
253.2
168
217.2
218.4
143
256
308.4
355.2
384
440.4
497
595.2
679.5
792
794.4
912
954
1075
1812
1135
1272
1992
2290
2520

BERAT/Btg
kg
38.5
50.6
67.5
87.5
108.5
270
315
373
435
460
503
580
661
760
833
926
1026
1136.5
1400
1707
C.1 PEKERJAAN STRUKTUR
Pengadaan tiang pancang segitiga minipil 25x25 cm M1

Pemancangan tiang pancang segitiga mini 32x32x32 cm (P2) M1

Pemotongan kepala tiang pancang Titik

1 Pekerjaan Galian tanah M3

2 Urugan tanah kembali M3

3 urugan tanah baru peninggian M3


4 Pekerjaan urugan pasir t. 5 cm M3

5 Pekerjaan lantai kerja t. 5 cm pondasi dan sloof M3

Pekerjaan pondasi batu kali M3

Pekerjaan Sloff Diatas batu kali 15 x 30 cm M3


a. Pembesian
b. Beton K.250
c. Bekisting

6 Pekerjaan Pondasi TIE BEAM uk. 1,3 m x 0,6 mx 0,6 m


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

7 Pekerjaan Pondasi TIE BEAM uk. 0,65 m x 0,6 mx 0,6 m


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

7 Pekerjaan Sloff SL.1 20 x 40 cm


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2
1 Pekerjaan Sloff SL.2 15 x 30 cm
a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan Kolom Pedestal Uk. 24 x 34 cm


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan Kolom Pedestal Uk. 30 x 30 cm


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan plat lantai dasar t. 8 cm


a. Pembesian warmes M.8 Kg
b. Beton K.250 M3
c. Bekisting M2
d. Plastik cor M2

Pekerjaan plat lantai 2 t. 12 cm


a. Pembesian warmes M.10 Kg
b. Beton K.250 M3
c. Bekisting plat bondeks M2
d. Bekisting kayu (pinggiran) M2
Pekerjaan plat lantai atap t. 12 cm dudukan toren
a. Pembesian warmes M.10 Kg
b. Beton K.250 M3
c. Bekisting plat bondeks M2
d. Bekisting kayu (pinggiran) M2

Pekerjaan beton penahan sher wall t. 10 cm


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan beton plat tangga


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan beton plat bordes tangga


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan beton anak tangga


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2

Pekerjaan beton ram pintu akses


a. Pembesian Kg
b. Beton K.250 M3
c. Bekisting M2
III. PEKERJAAN KONTRUKSI BAJA
1 Pekerjaan Base plat t. 20 mm kg

Tiang kolom baja WF 250.125.6 kg

Balok B.1 baja WF 250.125.6 Kg

Balok B.2 baja WF200.100.5.8 Kg

Balok B.3 baja WF 150.75.4.8 Kg

Pekerjaan Voute sambungan kolom balok Kg


Pekerjaan stifner plat t. 12 mm Kg

Baut A325 Ø 16 mm bh

PEKERJAAN KONTRUKSI BAJA RANGKA ATAP


Balok B.2 baja WF200.100.5.8

Pekerjaan plat sambungan t. 12 mm


Pekerjaan stifner plat t. 8 mm

Baut A325 Ø 16 mm

Pekerjaan Rangka Atap Besi Canal C uk.150.65.20.2,3

Plat dudukan Canal t. 8 mm

Pek. Trestang besi ulir d. 13 + watermur

Pek braccing besid. 10

Pekerjaan water mur M.10 bh

Pekerjaan Penutup Atap Spandek t=05 mm m2


Pas. Bata ringan / Hebel m2
UNIT LUAS JUMLAH
p.1 2.00 5.04 10.08
p.2 1.00 1.89 1.89
p.3 1.00 3.12 3.12
p.4 3.00 2.4 7.20
p.5 1.00 2.1 2.10
J.1 2.00 4.37 8.74
J.2 9.00 2.85 25.65
J.3 6.00 3.96 23.76
J.4 7.00 2.56 17.92
J.5 3.00 3.6 10.80
J.6 7.00 2.21 15.47
bv.1 3.00 0.36 1.08
bv.2 1.00 1.02 1.02

128.83
Pekerjaan Acian Kolom expouse m2

Pekerjaan dinding partisi 2 muka + di atas jendela kaca m2

Pekerjaan jendela kaca bening diatas partisi


Galian Pondasi

Urugan Pasir Bawah Pondasi h=10 cm


Beton Lantai Kerja Bawah Pondasi (K-100) h=10 cm
Pondasi Pasangan Batu belah campuran 1SP : 4PP
Sloof Atas Pondasi 15/20
Pagar panel Precas
504.00 lokasi panjang lebar titik segmen
PD.1 18 10 1
PD.2 18 9 2

504.00 28

28.00

21.44 lokasi panjang lebar tinggi jumlah


pondasi TIE BEAM PD.1 1.5 0.8 0.5 10
2pondasi TIE BEAM PD.1 0.75 0.8 0.5 9
sloof
pondasi PS.1 0.9 0.9 1.2 6
Pondasi PS.2 1.6 0.9 1.2 4

jumlah

6.86 lokasi panjang lebar tinggi jumlah


pondasi TIE BEAM PD.1 1.1 0.4 0.5 10
2pondasi TIE BEAM PD.1 0.55 0.4 0.5 9
sloof 3.7 0.35 0.3 12
pondasi PS.1 0.45 0.4 1.2 6
Pondasi PS.2 0.8 0.4 1.2 4
jumlah

343.00 lokasi panjang lebar tinggi jumlah


area r. Conveyor
area peninggian belakang ekisting 49 7 1 1

2.62 lokasi panjang lebar tinggi jumlah


pondasi TIE BEAM PD.1 1.1 0.6 0.05 10
2pondasi TIE BEAM PD.1 0.65 0.6 0.05 9
sloof sl.1 90.6 0.35 0.05 1
SLOFF SL.2

pondasi PS.1 0.9 0.9 0.05 6


Pondasi PS.2 1.6 0.9 0.05 4
jumlah

2.70 lokasi panjang lebar tinggi jumlah


pondasi tie beam 1.5 0.8 0.05 25
sloof 5.7 0.35 0.05 12

48.30 lokasi panjang lebar tinggi jumlah

sisi pagar belakang 46 1.05

lokasi panjang lebar tinggi jumlah


456.39 melintang 10.5 0.15 0.3 3
2.07 vertikal 2 0.15 0.3 6
27.66 1.3 0.15 0.3 2
beton
bekisting 46.1 0.3 2
pembesian 220 / m3 besi beton

968.76 lokasi panjang lebar tinggi jumlah


4.21 beton 1.3 0.6 0.6 9
20.52 bekisting 1.56 M2 0.72 9
pembesian 230 / m3 besi beton

lokasi panjang lebar tinggi jumlah


514.80 beton 0.65 0.6 0.6 10
2.34 bekisting 0.78 M2 0.72 10
15.00 pembesian 220 / m3 besi beton

1,449.60 lokasi panjang lebar tinggi jumlah


7.25 beton 90.6 0.2 0.4 1
72.48 bekisting 90.6 0.8 1 72.48
pembesian 200 / m3 besi beton
Uraian :
lokasi panjang /m 2.4 0.2 0.4 8 19.2
lokasi panjang /m 5.4 0.2 0.4 8 43.2
lokasi panjang /m 4.7 0.2 0.4 6 28.2

609.53 lokasi panjang lebar tinggi jumlah


2.90 beton 64.5 0.15 0.3 1
38.70 bekisting 64.5 0.6 1
pembesian 210 / m3 besi beton
Uraian :
setapak vertikal 1.45 0.15 0.3 6
setapak melintang 2.85 0.15 0.3 4
ruang loker 33 0.15 0.3 1
lokasi panjang /m 1.9 0.15 0.3 6

lokasi panjang lebar tinggi jumlah


359.04 beton 0.24 0.34 1 20
1.63 bekisting 0.24 0.45 1 20
27.60 pembesian 220 / m3 besi beton

lokasi panjang lebar tinggi jumlah


237.60 beton 0.3 0.3 1.2 10
1.08 bekisting 0.25 0.25 1 10
10.00 pembesian 220 / m3 besi beton

lokasi panjang lebar tinggi jumlah


4,649.05 beton 33.2 12.15 0.08 1
32.27 bekisting 33.2 0.3 0.08 1
5.36 pembesian 8.936 / m2 besi beton
520.29 Plastik cor 42.3 12.3 1

BERAT OVERSTEAK / M2 0.426 kg/m2


BERAT BESI M.8 / M2 8.510 kg/m2

567.40 lokasi panjang lebar tinggi luas


7.62 beton 0.12 63.5
63.50 bekisting 0 0 0.12 63.5
5.40 pembesian 8.936 / m2 besi beton 63.5
Bekisting kayu 12 15 0.1 5.4
BERAT OVERSTEAK / M2 0.426 kg/m2
BERAT BESI M.8 / M2 8.510 kg/m2
35.74 lokasi panjang lebar tinggi luas
0.40 beton 4 6 0.1 4
4.00 bekisting 4 6 0.1 4
1.60 pembesian 8.936 / m2 besi beton 4
Bekisting kayu 2 6 0.1 1.6
BERAT OVERSTEAK / M2 0.426 kg/m2
BERAT BESI M.8 / M2 8.510 kg/m2

255.30 lokasi panjang lebar tinggi luas jumlah


1.11 beton 3.7 0.1 1 3
22.20 bekisting 3.7 1 2 3
pembesian 230.000 / m2 besi beton 1.11
Bekisting kayu 2 6 0.1 1.6
BERAT OVERSTEAK / M2 0.426 kg/m2
BERAT BESI M.8 / M2 8.510 kg/m2

lokasi panjang lebar tinggi luas jumlah


240.24 beton 7 1.3 0.12 1
1.09 bekisting 7 1.3 1
9.10 pembesian 220 / m3

lokasi panjang lebar tinggi luas jumlah


77.06
0.41 beton 2.6 1.3 0.12 1
3.38 bekisting 2.6 1.3 1
pembesian 190 / m3

lokasi panjang lebar tinggi luas jumlah


105.59 beton 1.3 0.0225 19
0.56 bekisting 1.3 1.3 1
1.69 pembesian 190 / m3

lokasi panjang lebar tinggi luas jumlah


260.83 beton 2.6 2.2 0.12 2
1.37 bekisting 2.6 2.2 2
11.44 pembesian 190 / m3
309.00 lokasi panjang lebar jumlah luas
PS.1 0.3 0.2 25 1.5
Ps.2 0.26 0.26 6 0.4056

total luas 1.9056 M2


berat / m2 162.1528 Kg
total berat 308.9983 Kg

2,758.72 lokasi panjang lebar jumlah berat /m1 berat /total


SISI PINGGIR 5.68 10 29.6
sisi tengah 2.7 4 29.6
SISI 1 LT. 3.2 8 29.6

1,518.48
lokasi panjang lebar jumlah berat /m1 berat /total
vertikal
VERTIKAL 5.85 6 29.6
MELINTANG 2.7 6 29.6

1,561.60
lokasi panjang lebar jumlah berat /m1 berat /total
vertikal
MELINTANG 2.7 6 21.33333
2.85 4 21.33333
LANTAI ATAP 5.7 8 21.33333

412.59
lokasi panjang lebar jumlah berat /m1 berat /total
vertikal
PANJANG 2.87 6 21.33333
as B.1 s/d as B.10 2.12 1 21.33333

264.24
lokasi panjang lebar jumlah berat /m1 berat /total
melintang 0.6 12 36.7
722.17

lokasi panjang lebar jumlah berat /m1 berat /total


sambungan kolom
melintang 0.15 18 97.22222
vertikal 0.15 12 97.22222
sambungan wf 300 0.075 10 97.22222

sambungan wf. 200 0.027 18 97.22222

sambungan wf 150 0.0195 8 97.22222


plat stifner sisi kolom 0.024 19 97.22222
plat stifner sisi balok 0.024 45 97.22222

288.00

lokasi panjang lebar jumlah berat /m1 berat /total


sambungan kolom
melintang 6 18
vertikal 6 12

sambungan wf. 200 4 16

sambungan wf 150 4 11

1,855.92 lokasi panjang lebar jumlah berat /m1 dobel


horizontal 5.7 8 29.6
2.85 6 29.6
vertikal

663.54 lokasi panjang lebar jumlah berat /m1 dobel


melintang 0.15 18 97.22222
vertikal 0.15 12 97.22222
sambungan wf 300 0.075 31 97.22222
204.17 lokasi panjang lebar jumlah berat /m1 dobel
melintang 0.0375 31 97.22222
vertikal 0.0375 25 97.22222

124.00 lokasi panjang lebar jumlah berat /m1 berat /total


sambungan wf. 200 4 31

4,431.83 lokasi panjang segmen jumlah berat /m1total panjang

kuda lt.1 28.3 8 2 7.516667 452.8


kuda lt.2 8.55 8 2 7.516667 136.8

171.42 lokasi panjang lebar jumlah berat /m2 berat /total


kuda lt.1 0.015 128 64.93056
kuda lt.2 0.015 48 64.93056

212.89 lokasi panjang lebar jumlah berat /m1 berat /total


kuda lt.1 12 2 4 1.108809
kuda lt.2 8 2 6 1.108809

116.00 lokasi panjang segmen jumlah berat /m1 berat /total


kuda lt.1 1.3 8 12 0.6561
kuda lt.2 1.3 4 10 0.6561

121.00 lokasi bh segmen jumlah berat /m1 berat /total


kuda lt.1 1 11 9
kuda lt.2 1 11 2

582.23 lokasi panjang lebar jumlah berat /m1 berat /total


atap 1 28.3 7.9 2
atap 2 8.55 7.9 2

465.91 lokasi panjang jumlah tinggi berat /m1 berat /total


lantai 1 33 2 5.8
12 2 3.8

lantai 2 3 8 3.2

6 5 3.2

PENGURANGAN PINTU JENDELA 180.89 465.91


54.00 lokasi panjang titik tinggi segmen berat /total
0.45 36 1 2
0.3 36 1 2

10.95 lokasi panjang titik tinggi segmen berat /total


partisi 3 1 1
2 2.25 1
3.45 1 1

21.15 lokasi panjang titik tinggi segmen berat /total


dinding kaca 5.95 2.25 1
3.45 2.25 1
lokasi panjang titik tinggi segmen berat /total
sisi belakang
sisi samping kanan
sisi samping kiri
as E.4.1 s/d as E.9
volume
180.00
324.00

volume
6.00
2.70
-
5.83
6.91

21.44

volume
2.20
0.99
4.66
1.30
1.54
10.68

volume
343.00

343.00
volume
0.33
0.18
1.59

0.24
0.29
2.62

volume
1.50
1.20

volume

48.30
48.30
volume
1.42
0.54
0.12
2.07 m3
27.66 m2
456.39 kg/m3

volume satuan
4.21 m3
20.52 m2
968.76 kg/m3

volume satuan
2.34 m3
15.00 m2
514.80 kg/m3

volume satuan
7.25 m3
72.48 m2
1,449.60 kg/m3

1.54
3.46
2.26

volume satuan
2.90 m3
38.70 m2
609.53 kg/m3

0.39
0.51
1.49
0.51

volume satuan
1.63 m3
27.60 m2
359.04 kg/m3

volume satuan
1.08 m3
10.00 m2
237.60 kg/m3

volume satuan
32.27 m3
5.36 m2
4,649.05 kg/m3
520.29 m2

volume satuan
7.62 m3
7.62 m2
567.40 kg/m3
m2
volume satuan
0.40 m3
0.40 m2
35.74 kg/m3
m2

volume satuan
1.11 m3
22.20 m2
255.30 kg/m3
m2

volume satuan
1.09 m3
9.10 m2
240.24 kg

volume satuan

0.41 m3
3.38 m2
77.06 kg

volume satuan
0.56 m3
1.69 m2
105.59 kg

volume satuan
1.37 m3
11.44 m2
260.83 kg
berat /m2 satuan
162.15 kg
162.15 kg

berat /total satuan


1,681.28
319.68
757.76

2,758.72

berat /total satuan

1,038.96
479.52

1,518.48

berat /total satuan

345.60
243.20
972.80

1,561.60

berat /total satuan

367.36
45.23

412.59

berat /total satuan


264.24
264.24

berat /total satuan

262.50
175.00
72.92

47.25

15.17
44.33
105.00

722.17

berat /total satuan

108.00
72.00

64.00

44.00

288.00

berat /total satuan


1,349.76
506.16

1,855.92

berat /total satuan


262.50
175.00
226.04

663.54
berat /total satuan
113.02
91.15

204.17

berat /total satuan


124.00

berat /total satuan

3,403.55
1,028.28

4,431.83

berat /total satuan


124.67
46.75

171.42

berat /total satuan


106.45
106.45

212.89

berat /total satuan


81.88
34.12

116.00
berat /total satuan
99.00
22.00

121.00

berat /total satuan


447.14
135.09

582.23

berat /total satuan


382.80 UNIT LUAS JUMLAH
91.20 J.4 Err:509 3.42
J.5 11.00 2.7645 30.41
J.6 Err:509 3.9
76.80 bv.1 6.00 0.36 2.16

96.00 bv.2 2.00 0.972 1.94


prolling 1.00 8.55 8.55
646.80 pd. 1.00 9 9.00

52.06
berat /total satuan
32.40
21.60

54.00

berat /total satuan


3.00
4.50
3.45
10.95
berat /total satuan
13.39
7.76

21.15
berat /total satuan
BILL OF QUANTYTI

REKAP ENGGINERING ESTIMAT


URUSAN PEMERINTAHAN: 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019 / Lingkup Hidup

No. URAIAN PEKERJAAN JUMLAH HARGA TOTAL HARGA

I. PEKERJAAN PERSIAPAN 56,163,454.14 56,163,454.14


II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON 707,775,579.95 707,775,579.95
III. PEKERJAAN KONTRUKSI BAJA 366,809,674.42 366,809,674.42
IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP 470,732,261.81 470,732,261.81
V. PEKERJAAN ARSITEKTUR 760,046,450.76
A. PEKERJAAN PASANGAN DINDING 348,225,169.05
B. PEKERJAAN PASANGAN LANTAI 95,878,547.53
C. PEKERJAAN PASANGAN PLAFOND 19,003,947.50
D. PEKERJAAN KUSEN, PINTU DAN JENDELA 233,820,012.78
E. PEKERJAAN SANITAIR 6,477,104.32
F. PEKERJAAN PENGECETAN 56,641,669.58
VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 335,182,002.69
A. PEKERJAAN MEKANIKAL 183,888,117.66
B. PEKERJAAN ELEKTRIKAL 151,293,885.03

VII. PEKERJAAN PENUNJANG 1,280,913,257.56


A. PEKERJAAN SALURAN DAN PERKERASAN 408,502,288.28
B. PEKERJAAN POS JAGA 74,712,124.80
C. PEKERJAAN PEMAGARAN 493,154,439.07
D. PEKERJAAN GAPURA DAN PINTU GERBANG 70,049,748.67
E. PEKERJAAN RUMAH LOKER KM UMUM 234,494,656.73

JUMLAH HARGA 3,977,622,681.33


PPN 10 % 397,762,268.13
TOTAL HARGA 4,375,384,949.46
DIBULATKAN 4,375,384,000.00
TERBILANG : EMPAT MILYARD EMPAT RATUS DUA PULUH ENAM JUTA DELAPAN RATUS TUJUH PULUH DELAPAN RIBU RUPIAH

Jakarta, April 2019

Menyetujui :
Dibuat oleh :
Kepala Suku Dinas Cipta Karya
Tata ruang dan Pertanahan Konsultan Perencana
Kota Administrasi Jakarta Utara

KUSNADI HADIPRATIKNO, ST.MM Paruntungan Napitupulu, ST


NIP : 196405301985081001 Tenaga Ahli
Mengetahui :

Kuasa Pengguna Anggaran


Suku Dinas Lingkungan Hidup
Kota Administrasi Jakarta Utara
Selaku
Pejabat Pembuat Komitmen

SLAMET RIYADI, S.Sos, Msi


NIP : 197111191991011001

Page 39 of 162
BILL OF QUANTYTI

BILL OF QUANTYTI ENGGINERING ESTIMAT


URUSAN PEMERINTAHAN: 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019 / Lingkup Hidup

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek bh 1.00 600,000.00 600,000.00
2 Pek. Pengukuran dan bowplang m1 116.00 87,707.10 10,174,023.95
3 Alat bantu erektion baja ls 1.00 7,500,000.00 7,500,000.00
4 Kantor Direksi Keet m2 9.00 1,932,158.91 17,389,430.19
5 Pengadaan Sumber Air Kerja ls 1.00 6,000,000.00 6,000,000.00
6 Pengadaan Listrik Kerja ls 1.00 5,000,000.00 5,000,000.00
7 Pembuatan Asbuildrawing dan shop drawing Ls 1.00 4,500,000.00 4,500,000.00
8 Pembersihan Lokasi Ls 1.00 5,000,000.00 5,000,000.00
JUMLAH HARGA PEK. I 56,163,454.14
II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON
1 Pengadaan tiang pancang Square 25x25cm M1 504.00 289,100.00 145,706,400.00
2 Pemancangan Menggunakan Hydraulic (Jacking Pile) M1 504.00 92,301.41 46,519,909.13
3 Pemotongan kepala tiang pancang Titik 28.00 128,660.68 3,602,498.90
4 Handling dan Joint Titik 56.00 75,000.00 4,200,000.00
5 Pek. Test tekan tiang pancang PDA Titik 2.00 10,000,000.00 20,000,000.00
6 Pekerjaan Galian tanah M3 21.44 135,398.01 2,903,474.93
7 Urugan tanah kembali M3 6.86 48,694.36 334,140.70
8 urugan tanah baru peninggian M3 343.00 215,859.20 74,039,706.97
9 Pekerjaan urugan pasir t. 5 cm M3 2.62 332,283.20 871,246.56
10 Pekerjaan lantai kerja t. 5 cm pondasi dan sloof M3 2.70 1,196,449.20 3,226,823.50
11 Pekerjaan pondasi batu adukan 1pc : 6 ps kali sisi belakang M3 48.30 1,177,216.15 56,859,540.05
12 Pekerjaan Sloff Diatas batu kali 15 x 30 cm
a. Pembesian Kg 456.39 15,433.43 7,043,661.05
b. Beton K.250 M3 2.07 1,251,781.91 2,596,821.56
c. Bekisting M2 27.66 204,592.96 5,659,041.27
13 Pekerjaan Pondasi TIE BEAM uk. 1,3 m x 0,6 mx 0,6 m
a. Pembesian Kg 968.76 15,433.43 14,951,285.27
b. Beton K.250 M3 4.21 1,251,781.91 5,272,505.38
c. Bekisting M2 20.52 204,592.96 4,198,247.54
14 Pekerjaan Pondasi TIE BEAM uk. 0,65 m x 0,6 mx 0,6 m
a. Pembesian Kg 514.80 15,433.43 7,945,127.44
b. Beton K.250 M3 2.34 1,251,781.91 2,929,169.66
c. Bekisting M2 15.00 204,592.96 3,068,894.40
15 Pekerjaan Sloff SL.1 20 x 40 cm
a. Pembesian Kg 1,449.60 15,433.43 22,372,293.58
b. Beton K.250 M3 7.25 1,251,781.91 9,072,915.25
c. Bekisting M2 72.48 204,592.96 14,828,897.74
16 Pekerjaan Sloff SL.2 15 x 30 cm
a. Pembesian Kg 609.53 15,433.43 9,407,058.67
b. Beton K.250 M3 2.90 1,251,781.91 3,633,296.98
c. Bekisting M2 38.70 204,592.96 7,917,747.55
17 Pekerjaan Kolom Pedestal Uk. 25 x 35 cm
a. Pembesian Kg 359.04 15,433.43 5,541,217.08
b. Beton K.250 M3 1.63 1,251,781.91 2,042,908.07
c. Bekisting M2 27.60 331,989.13 9,162,899.99
18 Pekerjaan Kolom Pedestal Uk. 25 x 25 cm
a. Pembesian Kg 237.60 15,433.43 3,666,981.89
b. Beton K.250 M3 1.08 1,251,781.91 1,351,924.46
c. Bekisting M2 10.00 331,989.13 3,319,891.30
19 Pekerjaan plat lantai dasar t. 10 cm
a. Pembesian warmes M.8 Kg 4,649.05 15,433.43 71,750,786.71
b. Beton K.250 M3 32.27 1,251,781.91 40,395,502.79
c. Bekisting M2 5.36 204,592.96 1,096,618.27
d. Plastik cor M2 520.29 21,000.00 10,926,090.00
20 Pekerjaan plat lantai 2 t. 12 cm
a. Pembesian warmes M.10 Kg 567.40 15,433.43 8,756,991.21
b. Beton K.250 M3 7.62 1,251,781.91 9,538,578.12
c. Bekisting plat bondeks M2 63.50 198,638.39 12,613,537.73
d. Bekisting kayu (pinggiran) M2 5.40 204,592.96 1,104,801.98
21 Pekerjaan plat lantai atap t. 12 cm dudukan toren
a. Pembesian warmes M.10 Kg 35.74 15,433.43 551,621.49
b. Beton K.250 M3 0.40 1,251,781.91 500,712.76
c. Bekisting plat bondeks M2 4.00 198,638.39 794,553.56
d. Bekisting kayu (pinggiran) M2 1.60 204,592.96 327,348.74
22 Pekerjaan beton plat tangga

Page 40 of 162
BILL OF QUANTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


a. Pembesian Kg 240.24 15,433.43 3,707,726.14
b. Beton K.250 M3 1.09 1,251,781.91 1,366,945.84
c. Bekisting M2 9.10 336,279.13 3,060,140.08
23 Pekerjaan beton plat bordes tangga
a. Pembesian Kg 77.06 15,433.43 1,189,361.50
b. Beton K.250 M3 0.41 1,251,781.91 507,722.74
c. Bekisting M2 3.38 375,989.13 1,270,843.26
24 Pekerjaan beton anak tangga
a. Pembesian Kg 105.59 15,433.43 1,629,653.98
b. Beton K.250 M3 0.56 1,251,781.91 695,677.79
c. Bekisting M2 1.69 375,989.13 635,421.63
25 Pekerjaan beton ram pintu akses
a. Pembesian Kg 260.83 15,433.43 4,025,531.23
b. Beton K.250 M3 1.37 1,251,781.91 1,718,446.20
c. Bekisting M2 11.44 375,989.13 4,301,315.65
26 Pekerjaan kolom praktis M1 112.00 96,301.37 10,785,753.69
27 Pekerjaan Balok Intel M1 73.50 139,828.16 10,277,370.00

JUMLAH HARGA PEK. II 707,775,579.95

III. PEKERJAAN KONTRUKSI BAJA


1 Pekerjaan Angkur d. 19 Bh 124.00 50,000.00 6,200,000.00
2 Pekerjaan Base plat t. 20 mm Kg 309.00 38,670.72 11,949,187.35
3 Tiang kolom baja WF 250.125.6 Kg 2,758.72 38,670.72 106,681,682.61
4 Balok B.1 baja WF 250.125.6 Kg 1,518.48 38,670.72 58,720,711.56
5 Balok B.2 baja WF200.100.5.8 Kg 1,561.60 38,670.72 60,388,192.92
6 Balok B.3 baja WF 150.75.4.8 Kg 412.59 38,670.72 15,955,022.55
7 Pekerjaan Voute sambungan kolom balok Kg 1,387.26 38,670.72 53,646,339.98
8 Pekerjaan plat t. 12 mm sambungan Kg 722.17 38,670.72 27,926,703.37
9 Baut A325 Ø 16 mm Bh 288.00 21,000.00 6,048,000.00
10 Pengectan Kontruksi baja + zingkromat m2 346.79 55,635.10 19,293,834.08
JUMLAH HARGA PEK. III 366,809,674.42

IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP


1 Pekerjaan Kuda-kuda WF250.125.6 Kg 1,855.92 38,670.72 71,769,758.58
2 Pekerjaan plat sambungan t. 12 mm Kg 663.54 38,670.72 25,659,632.54
3 Pekerjaan stifner plat t. 10 mm Kg 204.17 38,670.72 7,895,271.55
4 Pekerjaan Rangka Atap Besi Canal C uk.150.65.20.2,3 Kg 4,431.83 38,670.72 171,381,918.37
5 Plat dudukan Canal t. 8 mm Kg 171.42 38,670.72 6,628,805.54
6 Pek braccing besid. 10 Kg 116.00 38,670.72 4,485,744.49
7 Pek. Trestang besi ulir d. 13 + watermur Kg 212.89 38,670.72 8,232,660.47
8 Baut A325 Ø 16 mm Bh 124.00 21,000.00 2,604,000.00
9 Pengectan Kontruksi baja + zingkromat M2 306.23 55,635.10 17,037,162.67
10 Pekerjaan water mur M.10 BH 212.89 15,000.00 3,193,369.92
11 Pekerjaan Penutup Atap Spandek t=05 mm M2 582.23 207,740.20 120,952,575.19
12 Pekerjaan Talang air rangka siku dan hollow + plat zinalum M1 40.59 435,000.00 17,656,650.00
13 Pekerjaan penutup talang air hujan dengan SPANDEK m2 48.71 207,740.20 10,118,609.54
14 Pekerjaan Lisplank Spandek + Rangka M2 15.00 207,740.20 3,116,102.96
JUMLAH HARGA PEK. IV 470,732,261.81

V. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
1 Pas. Bata ringan / Hebel M2 465.91 174,510.40 81,305,528.93
2 Plesteran Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 102,698.31 95,695,620.34
3 Acian Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 62,423.35 58,166,889.03
4 Plesteran Openingan Kusen dengan Mortar Instan M1 215.00 62,423.35 13,421,020.25
5 Pekerjaan Acian Kolom expouse M2 54.00 62,423.35 3,370,860.90
6 Pekerjaan dinding spandek warna + rangka besi CNP dan U Canal M2 178.00 435,000.00 77,430,000.00
7 Pekerjaan dinding partisi 2 muka m2 10.95 286,780.79 3,140,249.60
8 Pekerjaan hand railling selasar pipa gic dia. 3" finis cat m1 11.00 345,000.00 3,795,000.00
9 Pekerjaan railling tangga m1 14.00 850,000.00 11,900,000.00
JUMLAH HARGA PEK. VA. 348,225,169.05

B. PEKERJAAN PASANGAN LANTAI


1 Pasangan lantai Kamar Mandi keramik uk. 40x40 kasar M2 72.00 312,260.38 22,482,747.30
2 Pasangan dinding keramik uk. 20x40 halus M2 16.20 294,215.12 4,766,284.96
4 Pekerjaan lantai keramik tangga 30x60 cm m2 20.00 337,864.94 6,757,298.79
5 Pasang stef nozing M1 20.70 52,965.47 1,096,385.30
6 Floor hardener M2 275.60 184,010.64 50,713,331.17
7 Pekerjaan rabat beton M2 80.50 125,000.00 10,062,500.00
JUMLAH HARGA PEK. VB. 95,878,547.53

C. PEKERJAAN PASANGAN PLAFOND


1 pekerjaan Plafond GRC rangka hollow M2 5.44 241,482.54 1,313,665.01
2 pekerjaan Plafond Gybsum rangka hollow M2 60.80 232,044.12 14,108,282.50

Page 41 of 162
BILL OF QUANTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


3 Pekerjaan Liss plafond M2 79.60 45,000.00 3,582,000.00
JUMLAH HARGA PEK. VC. 19,003,947.50

D. PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pekerjaan Kusen P.1 Unit 2.00 12,272,681.90 24,545,363.81
2 Pekerjaan Kusen P.2 Unit 1.00 15,974,150.71 15,974,150.71
3 Pekerjaan Kusen P.3 Unit 1.00 4,588,656.13 4,588,656.13
4 Pekerjaan Kusen P.4 Unit 3.00 2,821,220.31 8,463,660.94
5 Pekerjaan Kusen P.5 Unit 1.00 3,516,546.62 3,516,546.62
6 Pekerjaan Kusen J.1 Unit 2.00 7,090,018.27 14,180,036.54
7 Pekerjaan Kusen J.2 Unit 9.00 4,749,922.61 42,749,303.50
8 Pekerjaan Kusen J.3 Unit 6.00 4,718,627.57 28,311,765.45
9 Pekerjaan Kusen J.4 Unit 7.00 6,609,092.05 46,263,644.32
10 Pekerjaan Kusen J.5 Unit 3.00 3,485,977.63 10,457,932.89
11 Pekerjaan Kusen J.6 Unit 7.00 4,516,829.31 31,617,805.18
12 Pekerjaan Kusen BV.1 Unit 3.00 525,191.12 1,575,573.35
13 Pekerjaan Kusen BV.2 Unit 1.00 1,575,573.35 1,575,573.35

JUMLAH HARGA PEK. V D. 233,820,012.78

E. PEKERJAAN SANITAIR
1 Pemasangan Closet duduk + asesoris BH 1.00 3,552,619.84 3,552,619.84
2 PemasanganUrinoir + asesoris BH 1.00 1,433,514.94 1,433,514.94
3 Pemasangan wastafel BH 1.00 1,148,430.72 1,148,430.72
4 Pemasangan Kran air BH 1.00 187,386.61 187,386.61
5 pemasangan Floor drain BH 1.00 155,152.21 155,152.21
JUMLAH HARGA PEK. V E. 6,477,104.32
F. PEKERJAAN PENGECETAN
1 Pengecetan Exterior Wethersield setara ICI / Dulux 465.91 52,563.26 24,489,566.13
2 Pengecetan Interior setara ICI / Dulux 465.91 61,536.62 28,670,312.88
3 Pengecetan Plafond setara Vinilex 66.24 52,563.26 3,481,790.57
JUMLAH HARGA PEK. V F. 56,641,669.58

TOTAL JUMLAH PEKERJAAN ARSITEKTUR 760,046,450.76


VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. PEKERJAAN MEKANIKAL
1 Pekerjaan Instalasi Air Kotor
- Instalasi Pipa Air Kotor 3 " PVC M1 15.00 186,986.13 2,804,791.97
- Instalasi Pipa Air Kotor 2" PVC M1 25.00 142,169.76 3,554,244.05
- Instalasi Pipa Air Kotor 4 " PVC M1 38.00 248,429.76 9,440,330.95
- Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Titik 1.00 18,000,000.00 18,000,000.00
- Bio Septictank Kapasitas 3 m3 + Instalasi + Dudukan Titik 1.00 35,000,000.00 35,000,000.00
PEKERJAAN POMPA
Jet Pump / Shallow Well set 1.00 20,600,000.00 20,600,000.00
Kap : 65 L / Jam
Head : 50 m
Power : 2.2 Hp ( 1650 Watt )
Daya Dorong : 50 m
Panjang Pipa Hisap : 50 m

PEKERJAAN PEMIPAAN
Pemipaan Air Bersih
a. Pipa PPR PN 16
dia. 1 1/2" m 12.00 203,835.60 2,446,027.15
dia. 1 1/4" m 12.00 173,475.60 2,081,707.15
dia. 1/2" m 14.00 74,805.60 1,047,278.34
b. Gate Valve dia. 11/2 bh 3.00 237,583.23 712,749.68
c. Elbow
dia. 1/2" bh 21.00 131,323.23 2,757,787.73
dia 1 1/2" bh 4.00 389,383.23 1,557,532.90
dia 1 1/4" bh 8.00 305,893.23 2,447,145.80
d. Tee
dia. 1 1/2" x 1 1/2" x 1 1/2" bh 3.00 69,085.23 207,255.68
dia. 1 1/4" x 1 1/4" x 1 1/4" bh 3.00 290,713.23 872,139.68
Soket dia. 1 1/2" x 1 1/4" bh 3.00 427,333.23 1,281,999.68

Pipa Talang tegak Air Hujan


Pipa PVC Wavin Aw
a.Ø 4" m 160.00 248,429.76 39,748,761.89
b.Ø 3" m 44.00 186,986.13 8,227,389.77
Elbow dia. 4"
a.dia. 4 " m 22.00 97,177.92 2,137,914.25

Page 42 of 162
BILL OF QUANTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


Clamp pipa PVC Ø 4" bh 44.00 92,623.92 4,075,452.50
Roof drain bh 22.00 303,982.21 6,687,608.53

Rumah pompa lengkap kunci Unit 2.00 5,000,000.00 10,000,000.00


tangki air kap 1,2m3 Unit 2.00 3,500,000.00 7,000,000.00
Switch otomatis Unit 2.00 600,000.00 1,200,000.00
JUMLAH HARGA PEK. MEKANIKAL 183,888,117.66

B. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Pemasangan Listrik PLN 10,6 KVA Kwh 10,600.00 1,500.00 15,900,000.00
2 Panel Utama LDP lengkap terpasang dengan MCB Unit 1.00 35,000,000.00 35,000,000.00
3 panel pembagi Unit 2.00 5,500,000.00 11,000,000.00
4 Penarikan kabel tofer dari gardu keruang panel utama NYFGBY 4 x 25 mm M1 65.00 404,722.15 26,306,939.95
5 Penarikan kabel NYY 4x 10 mm dari Panel utama ke panel pembagi M1 35.00 171,077.82 5,987,723.86
6 Instalasi Kabel NYM 3 x 2,5 mm² Lampu, dalam pipa konduit 20 mm titik 37.00 289,405.50 10,708,003.50
7 Instalasi Kabel NYM 3 x 2,5 mm² Stop Kontak, dalam pipa konduit 20 mm titik 26.00 305,961.60 7,955,001.60
8 Pekerjaan Armatur Listrik
- Lampu Down Light PLC 18 W BH 5.00 244,403.62 1,222,018.11
- Lampu LP HARR HLG 120 W BH 24.00 722,573.62 17,341,766.90
- Lampu LB T5 2X18 W BH 8.00 540,413.62 4,323,308.97
- Saklar Seri setara broco BH 7.00 183,353.62 1,283,475.35
- Saklar Tunggal setara broco BH 2.00 210,941.62 421,883.24
- Stop Kontak, 220 V, 1-ph, 10 A setara broco BH 14.00 210,941.62 2,953,182.69
- Stop Kontak AC, setara broco BH 3.00 430,193.62 1,290,580.86
- Mesin Pompa Air Kotor Ke Ipal + Instalasi BH 1.00 9,600,000.00 9,600,000.00
-
JUMLAH HARGA PEK. ELEKTRIKAL 151,293,885.03

TOTAL JUMLAH PEKERJAAN MEKANIKAL &ELEKTRIKAL 335,182,002.69

VII. PEKERJAAN PENUNJANG


A. PEKERJAAN SALURAN DAN PERKERASAN
1 Pekerjaan galian tanah saluran M3 23.40 135,398.01 3,168,313.43
2 Pekerjaan urugan pasir saluran M3 2.93 332,283.20 971,928.37
3 Pekerjaan lantai kerja saluran M3 2.93 1,196,449.20 3,499,613.92
4 Pekerjaan dinding saluran pasangan bata m2 163.80 157,468.49 25,793,338.17
5 Pekerjaan Plesteran dinding saluran m2 198.90 102,698.31 20,426,693.86
6 Pekerjaan Acian dinding saluran m2 198.90 62,423.35 12,416,004.32
7 Pekerjaan pipa PVC dia.4' crosingan ke saluran m1 45.00 254,993.26 11,474,696.87
8 Pekerjaan Kanstinn m1 89.00 211,143.70 18,791,788.86
9 Pekerjaan urugam Sirtu M3 51.05 341,002.43 17,408,174.29
10 Pekerjaan Lantai kerja BO. M3 51.05 1,196,449.20 61,078,731.89
11 Pekerjaan Perkerasan beton K.350 t. 15 cm -
a. Plastik cor M2 510.50 25,000.00 12,762,500.00
b. Pembesian Kg 4,900.80 15,433.43 75,636,131.59
c. Beton M3 76.58 1,296,830.87 99,304,823.49
d. Bekisting M2 76.58 204,592.96 15,666,705.91
12 Galian tanah sumur resapan m3 17.60 135,398.01 2,383,004.98
13 Pemasangan sumur resapan dia. 1m + asesoris+ tutup titik 16.00 1,350,000.00 21,600,000.00
14 Pemasangan pipa crosingan pipa PVC dia. 4" m1 24.00 254,993.26 6,119,838.33

JUMLAH HARGA PERKERASAN HALAMAN 408,502,288.28


B. PEKERJAAN POS JAGA
Pek. Galian dan Pondasi
1 Galian Pondasi m3 4.26 135,398.01 576,795.52
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.61 332,283.20 202,692.75
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.61 1,174,494.55 716,441.68
4 Pemasangan pondasi batu belah campuran 1SP : 6PP m3 2.74 1,177,216.15 3,225,572.25
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 107.25 15,433.43 1,655,234.88
b. Beton M3 0.49 1,387,961.89 676,631.42
c. Bekisting M2 8.67 204,592.96 1,773,138.99
6 Urug kembali bekas Galian pondasi m3 1.42 88,109.64 125,115.69

Pek. Pasangan dan Beton


1 Cor kolom praktis K-100 type Kp 12 x 12 cm m1 16.80 96,301.37 1,617,863.05
2 Pas. Dinding bata ringan t=10 cm dengan MSP m2 22.14 174,510.40 3,863,660.22
3 Plesteran dinding dengan MSP m2 44.27 102,698.31 4,546,454.18
4 Acian dinding m2 44.27 62,423.35 2,763,481.70
5 Plat beton tebal 8 cm -
a. Pembesian Kg 195.80 15,433.43 3,021,864.71
b. Beton K.250 m3 0.82 1,387,961.89 1,137,018.38
c. Bekisting M2 4.60 204,592.96 941,127.62
6 pekerjaan balok beton Uk 15x25 cm
a. Pembesian Kg 195.80 15,433.43 3,021,864.71

Page 43 of 162
BILL OF QUANTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


b. Beton K.250 m3 0.49 1,387,961.89 676,631.42
c. Bekisting M2 4.60 336,279.13 1,546,884.00
7 Plat Dak beton tebal 12 cm
a. Pembesian Kg 195.80 15,433.43 3,021,864.71
b. Beton K.250 m3 1.23 1,387,961.89 1,705,527.57
c. Bekisting M2 4.60 375,989.13 1,729,550.00
8 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 13.23 232,044.12 3,069,943.71
9 Pas. Kusen + Daun Pintu Type P1 Lengkap unit 1.00 12,272,681.90 12,272,681.90
10 Pas. Kusen + Daun Jendela Type J1 Lengkap unit 1.00 7,090,018.27 7,090,018.27
11 Pas. Kusen + Daun Jendela Type J2 Lengkap unit 1.00 4,749,922.61 4,749,922.61
14 Kalsiplank 8/300 m' 15.20 227,823.28 3,462,913.86

Pek. Finishing dan Water Proffing


1 Pengecatan Dinding dalam m2 22.14 52,563.26 1,163,750.65
2 Pengecatan dinding luar m2 22.14 61,536.62 1,362,420.84
3 Pengecatan Plafond m2 5.56 52,563.26 292,251.75

Pek. Mekanikal dan Elektrikal


1 Instalasi penerangan titik 2.00 289,405.50 578,811.00
2 Instalasi stop kontak titik 1.00 305,961.60 305,961.60
3 Saklar Doubel buah 1.00 183,353.62 183,353.62
4 Stop Kontak buah 1.00 210,941.62 210,941.62
5 Down Light LED BULB E27 7 W buah 2.00 244,403.62 488,807.24
6 Pipa Air Pembuangan Air Hujan dia 3" m' 5.00 186,986.13 934,930.66
-
JUMLAH HARGA PERKERASAN POS JAGA 74,712,124.80

C. PEKERJAAN PEMAGARAN
1 Galian Pondasi m3 200.45 135,398.01 27,140,260.31
2 Urugan Pasir Bawah Pondasi h=5 cm m3 8.35 332,283.20 2,775,229.32
3 Urugan tanah kembali m3 66.82 88,109.64 5,887,133.75
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 204.16 1,177,216.15 240,340,449.18
5 Sloof Atas Pondasi 20/30 - -
a. Pembesian Kg 2,338.56 15,433.43 36,091,991.49
b. Beton K.250 m3 11.14 1,387,961.89 15,456,343.64
c. Bekisting M2 111.36 204,592.96 22,783,472.03
6 Pagar panel Precas m1 185.60 768,747.63 142,679,559.35
JUMLAH HARGA PEMAGARAN 493,154,439.07

D. PEKERJAAN GAPURA DAN PINTU GERBANG


1 Galian Pondasi m3 2.40 135,398.01 324,955.22
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.10 332,283.20 33,228.32
3 Urugan tanah kembali m3 0.80 88,109.64 70,487.71
4 Lantai kerja pondasi setapak m3 0.05 1,174,494.55 58,724.73
5 Pekerjaan Pondasi setapak 0,6x0,6x0,2 -
a. Pembesian Kg 33.12 15,433.43 511,155.05
b. Beton K.250 m3 0.14 1,387,961.89 199,866.51
c. Bekisting M2 0.96 204,592.96 196,409.24
6 Pekerjaan Kolom pedestal uk. 25x25 cm
a. Pembesian Kg 26.25 15,433.43 405,127.42
b. Beton K.250 m3 0.13 1,387,961.89 173,495.24
c. Bekisting M2 2.00 331,989.13 663,978.26
7 Pekerjaan Kolomf uk. 25x25 cm
a. Pembesian Kg 210.00 15,433.43 3,241,019.35
b. Beton K.250 m3 1.00 1,387,961.89 1,387,961.89
c. Bekisting M2 16.00 331,989.13 5,311,826.08
8 Pekerjaan Balok uk. 30x60 cm
a. Pembesian Kg 316.80 15,433.43 4,889,309.19
b. Beton K.250 m3 1.44 1,387,961.89 1,998,665.13
c. Bekisting M2 9.60 336,279.13 3,228,279.65
9 Pekerjaan Plat lantai t. 12 cm
a. Pembesian Kg 158.40 15,433.43 2,444,654.60
b. Beton K.250 m3 0.72 1,387,961.89 999,332.56
c. Bekisting M2 6.00 52,400.37 314,402.22
10 Pekerjaan Kolom praktis M1 4.00 96,301.37 385,205.49
11 Pekerjaan Ring balok m1 20.00 139,828.16 2,796,563.26
12 Pekerjaan Pasangan bata ringan m2 12.00 174,510.40 2,094,124.78
13 Pekerjaan Plesteran m2 12.00 102,698.31 1,232,379.72
14 Pekerjaan Acian m2 12.00 62,423.35 749,080.20
15 Pekerjaan Pengecetan m2 12.00 61,536.62 738,439.48
16 Pekerjaan Papan Nama Stenliss t. 15 cm bh 65.00 155,000.00 10,075,000.00
17 Pekerjaan Logo unit 1.00 4,500,000.00 4,500,000.00
18 Pekerjaan Instalasi Penerangan titik 3.00 289,405.50 868,216.50
19 Pekerjaan Lampu tembak bh 3.00 585,953.62 1,757,860.86
20 Pekerjaan Pintu Gerbang rangka besi pipa terpasang + finis cat m2 16.00 1,150,000.00 18,400,000.00

Page 44 of 162
BILL OF QUANTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


JUMLAH HARGA GAPURA PINTU GERBANG 70,049,748.67

E. PEKERJAAN RUMAH LOKER KM UMUM


1 Galian Pondasi m3 5.58 135,398.01 755,520.90
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.93 332,283.20 309,023.38
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.93 1,174,494.55 1,092,279.93
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 5.58 1,177,216.15 6,568,866.12
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 195.30 15,433.43 3,014,148.00
b. Beton M3 0.93 1,387,961.89 1,290,804.56
c. Bekisting M2 12.40 204,592.96 2,536,952.70
6 Urug kembali bekas Galian pondasi m3 1.86 88,109.64 163,883.93
-
Pek. Pasangan dan Beton -
8 Pas. Dinding bata ringan t=10 cm dengan MSP m2 82.02 174,510.40 14,313,342.88
9 Plesteran dinding dengan MSP m2 164.04 102,698.31 16,846,630.77
10 Acian dinding m2 164.04 62,423.35 10,239,926.33
11 Plat beton diatas tanah tebal 10 cm -
a. Pembesian Kg 457.28 15,433.43 7,057,319.64
b. Beton m3 3.52 1,387,961.89 4,882,155.96
c. Bekisting M2 2.70 204,592.96 552,400.99
d. Plastik cor m2 35.18 25,000.00 879,375.00
12 Pekerjaan beton kolom 12/12
a. Pembesian Kg 101.61 15,433.43 1,568,134.80
b. Beton m3 0.48 1,387,961.89 671,551.48
c. Bekisting M2 16.13 331,989.13 5,354,320.69
13 Pekerjaan beton Ring Balok 15/25
a. Pembesian Kg 244.13 15,433.43 3,767,685.00
b. Beton m3 1.16 1,387,961.89 1,613,505.70
c. Bekisting M2 15.50 336,279.13 5,212,326.52
14 Pekerjaan Plat beton t. 12 cm
a. Pembesian Kg 790.02 15,433.43 12,192,714.80
b. Beton m3 4.16 1,387,961.89 5,771,145.55
c. Bekisting M2 35.70 336,279.13 12,005,164.94
15 Pasangan lantai Homogenus 40/40 m2 31.01 312,260.38 9,682,413.71
16 Pasang Plafond GRC + Rangka Hollow m2 12.00 241,482.54 2,897,790.46
17 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 19.01 232,044.12 4,410,578.61
18 Pekerjaan Kusen P.1 unit 2.00 12,272,681.90 24,545,363.81
19 Pekerjaan Kusen P.4 unit 3.00 2,821,220.31 8,463,660.94
20 Pekerjaan Kusen BV.1 unit 3.00 525,191.12 1,575,573.35
21 Pekerjaan Kusen J.2 unit 2.00 4,749,922.61 9,499,845.22
-
Pek. Finishing dan Water Proffing -
22 Pengecatan Dinding dalam m2 82.02 52,563.26 4,311,238.87
23 Pengecatan dinding luar m2 82.02 61,536.62 5,047,233.86
24 Pengecatan Plafond m2 31.01 52,563.26 1,629,855.39
-
Pek. Mekanikal dan Elektrikal -
25 Instalasi penerangan titik 7.00 289,405.50 2,025,838.50
26 Instalasi stop kontak titik 3.00 305,961.60 917,884.80
27 Saklar Doubel buah 2.00 183,353.62 366,707.24
28 Stop Kontak buah 4.00 210,941.62 843,766.48
29 Down Light LED BULB E27 7 W buah 7.00 244,403.62 1,710,825.35
30 Pipa Air Pembuangan Air Hujan dia 3" m' 15.00 186,986.13 2,804,791.97
31 - Instalasi Pipa Air Kotor 3 " PVC m' 12.00 186,986.13 2,243,833.57
32 - Instalasi Pipa Air Kotor 2" PVC m' 12.00 52,965.47 635,585.68
33 - Instalasi Pipa Air Kotor 4 " PVC m' 15.00 184,010.64 2,760,159.53
34 - Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Unit 1.00 125,000.00 125,000.00
35 Pemasangan Closet duduk + asesoris BH 3.00 3,552,619.84 10,657,859.52
36 Pasang Head Shower+fleksibel Komplit 1 buah BH 3.00 366,906.61 1,100,719.82
37 Pasang Jet Shower+fleksibel Komplit 1 buah BH 3.00 324,666.61 973,999.82
38 Pemasangan Kran air BH 3.00 187,386.61 562,159.82
39 pemasangan Floor drain BH 3.00 155,152.21 465,456.62
40 Sumur pantek + pompa + Rumah pompa lengkap kunci Unit 1.00 13,500,000.00 13,500,000.00
41 tangki air kap 1,2m3 Unit 1.00 1,650,000.00 1,650,000.00
42 Switch otomatis Unit 1.00 427,333.23 427,333.23

JUMLAH PEKERJAAN RUMAH LOKER UMUM 234,494,656.73

Page 45 of 162
BILL OFF QUANTTYTI

REKAP HARGA ESTIMASI ENGGINERING


Kegiatan : PEMBANGUNAN TPS 3R WADUK CINCIN
Lokasi : Jl. DANAU BISMA BLOCK E KAV. 12 B, KELURAHAN PAPANGGO, KEC. TANJUNG PRIUK
Sumber Dana : APBD
Tahun Anggaran : 2019

No. URAIAN PEKERJAAN JUMLAH HARGA TOTAL HARGA

I. PEKERJAAN PERSIAPAN 73,552,884.33 73,552,884.33


II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON 710,945,991.65 710,945,991.65
III. PEKERJAAN KONTRUKSI BAJA 4,133,940,750.15 4,133,940,750.15
IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP 3,788,263,889.21 3,788,263,889.21
V. PEKERJAAN ARSITEKTUR 717,312,170.57
A. PEKERJAAN PASANGAN DINDING 352,020,169.05
B. PEKERJAAN PASANGAN LANTAI 119,321,502.51
C. PEKERJAAN PASANGAN PLAFOND 19,003,947.50
D. PEKERJAAN KUSEN, PINTU DAN JENDELA 163,692,625.41
E. PEKERJAAN SANITAIR 6,632,256.52
F. PEKERJAAN PENGECETAN 56,641,669.58
VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 440,678,427.30
A. PEKERJAAN MEKANIKAL 266,664,717.11
B. PEKERJAAN ELEKTRIKAL 174,013,710.19
VII. PEKERJAAN PENUNJANG 1,067,105,207.09
A. PEKERJAAN SALURAN DAN PERKERASAN 281,769,069.10
B. PEKERJAAN POS JAGA 72,933,924.85
C. PEKERJAAN PEMAGARAN 377,367,980.96
D. PEKERJAAN GAPURA DAN PINTU GERBANG 75,001,565.52
E. PEKERJAAN RUMAH LOKER KM UMUM 260,032,666.66

JUMLAH HARGA 10,931,799,320.30


PPN 10 % 1,093,179,932.03
TOTAL HARGA 12,024,979,252.33
DIBULATKAN 12,024,979,000.00

TERBILANG : LIMA MILYARD DELAPAN RATUS TUJUH PULUH SEMBILAN JUTA LIMA RATUS ENAM PULUH TUJUH RIBU RUPIAH

Jakarta, Maret 2019


Kuasa Pengguna Anggaran
Suku Dinas Lingkungan Hidup
Kota Administrasi Jakarta Utara
Selaku
Pejabat Pembuat Komitmen

SLAMET RIYADI, S.Sos, Msi


NIP : 197111191991011001

Page 46 of 162
BILL OFF QUANTTYTI

BILL OF QUANTYTI ESTIMAT ENGGINERING


Kegiatan : PEMBANGUNAN TPS 3R WADUK CINCIN
Lokasi : Jl. DANAU BISMA BLOCK E KAV. 12 B, KELURAHAN PAPANGGO, KEC. TANJUNG PRIUK
Sumber Dana : APBD
Tahun Anggaran : 2019

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek bh 1.00 600,000.00 600,000.00
2 Pek. Pengukuran dan bowplang m1 116.00 87,707.10 10,174,023.95
3 Alat bantu erektion baja ls 1.00 7,500,000.00 7,500,000.00
4 Kantor Direksi Keet m2 9.00 1,932,158.91 17,389,430.19
5 Gudang dan Los Kerja m2 9.00 1,932,158.91 17,389,430.19
6 Pengadaan Sumber Air Kerja ls 1.00 6,000,000.00 6,000,000.00
7 Pengadaan Listrik Kerja ls 1.00 5,000,000.00 5,000,000.00
8 Pembuatan Asbuildrawing dan shop drawing Ls 1.00 4,500,000.00 4,500,000.00
9 Pembersihan Lokasi Ls 1.00 5,000,000.00 5,000,000.00
JUMLAH HARGA PEK. I 73,552,884.33
II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON
1 Pengadaan tiang pancang Square 25x25cm M1 504.00 289,100.00 145,706,400.00
2 Pemancangan Menggunakan Hydraulic (Jacking Pile) M1 504.00 73,500.00 37,044,000.00
3 Pemotongan kepala tiang pancang Titik 28.00 80,000.00 2,240,000.00
4 Handling dan Joint Titik 56.00 75,000.00 4,200,000.00
5 Pek. Test tekan tiang pancang PDA Titik 2.00 10,000,000.00 20,000,000.00
6 Pekerjaan Galian tanah M3 21.44 135,398.01 2,903,474.93
7 Urugan tanah kembali M3 6.86 48,694.36 334,140.70
8 urugan tanah baru peninggian M3 343.00 215,859.20 74,039,706.97
9 Pekerjaan urugan pasir t. 5 cm M3 2.62 332,283.20 871,246.56
10 Pekerjaan lantai kerja t. 5 cm pondasi dan sloof M3 2.70 1,196,449.20 3,226,823.50
11 Pekerjaan pondasi batu kali M3 48.30 1,177,216.15 56,859,540.05
12 Pekerjaan Sloff Diatas batu kali 15 x 30 cm
a. Pembesian Kg 456.39 15,433.43 7,043,661.05
b. Beton K.250 M3 2.07 1,251,781.91 2,596,821.56
c. Bekisting M2 27.66 204,592.96 5,659,041.27
13 Pekerjaan Pondasi TIE BEAM uk. 1,3 m x 0,6 mx 0,6 m
a. Pembesian Kg 968.76 15,433.43 14,951,285.27
b. Beton K.250 M3 4.21 1,251,781.91 5,272,505.38
c. Bekisting M2 20.52 204,592.96 4,198,247.54
14 Pekerjaan Pondasi TIE BEAM uk. 0,65 m x 0,6 mx 0,6 m
a. Pembesian Kg 514.80 15,433.43 7,945,127.44
b. Beton K.250 M3 2.34 1,251,781.91 2,929,169.66
c. Bekisting M2 15.00 204,592.96 3,068,894.40
15 Pekerjaan Sloff SL.1 20 x 40 cm
a. Pembesian Kg 1,449.60 15,433.43 22,372,293.58
b. Beton K.250 M3 7.25 1,251,781.91 9,072,915.25
c. Bekisting M2 72.48 204,592.96 14,828,897.74
16 Pekerjaan Sloff SL.2 15 x 30 cm
a. Pembesian Kg 609.53 15,433.43 9,407,058.67
b. Beton K.250 M3 2.90 1,251,781.91 3,633,296.98
c. Bekisting M2 38.70 204,592.96 7,917,747.55
17 Pekerjaan Kolom Pedestal Uk. 25 x 35 cm
a. Pembesian Kg 359.04 15,433.43 5,541,217.08
b. Beton K.250 M3 1.63 1,251,781.91 2,042,908.07
c. Bekisting M2 27.60 331,989.13 9,162,899.99
18 Pekerjaan Kolom Pedestal Uk. 25 x 25 cm
a. Pembesian Kg 237.60 15,433.43 3,666,981.89
b. Beton K.250 M3 1.08 1,251,781.91 1,351,924.46
c. Bekisting M2 10.00 331,989.13 3,319,891.30
19 Pekerjaan plat lantai dasar t. 10 cm
a. Pembesian warmes M.8 Kg 4,649.05 15,433.43 71,750,786.71
b. Beton K.250 M3 32.27 1,251,781.91 40,395,502.79
c. Bekisting M2 5.36 204,592.96 1,096,618.27
d. Plastik cor M2 520.29 21,000.00 10,926,090.00
20 Pekerjaan plat lantai 2 t. 12 cm
a. Pembesian warmes M.10 Kg 567.40 15,433.43 8,756,991.21
b. Beton K.250 M3 7.62 1,251,781.91 9,538,578.12
c. Bekisting plat bondeks M2 63.50 198,638.39 12,613,537.73
d. Bekisting kayu (pinggiran) M2 5.40 204,592.96 1,104,801.98
21 Pekerjaan plat lantai atap t. 12 cm dudukan toren
a. Pembesian warmes M.10 Kg 35.74 15,433.43 551,621.49
b. Beton K.250 M3 0.40 1,251,781.91 500,712.76

Page 47 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


c. Bekisting plat bondeks M2 4.00 198,638.39 794,553.56
d. Bekisting kayu (pinggiran) M2 1.60 204,592.96 327,348.74
22 Pekerjaan beton penahan sher wall t. 10 cm
a. Pembesian Kg 255.30 15,433.43 3,940,153.53
b. Beton K.250 M3 1.11 1,251,781.91 1,389,477.91
c. Bekisting M2 22.20 360,589.13 8,005,078.69
23 Pekerjaan beton plat tangga
a. Pembesian Kg 240.24 15,433.43 3,707,726.14
b. Beton K.250 M3 1.09 1,251,781.91 1,366,945.84
c. Bekisting M2 9.10 336,279.13 3,060,140.08
24 Pekerjaan beton plat bordes tangga
a. Pembesian Kg 77.06 15,433.43 1,189,361.50
b. Beton K.250 M3 0.41 1,251,781.91 507,722.74
c. Bekisting M2 3.38 375,989.13 1,270,843.26
25 Pekerjaan beton anak tangga
a. Pembesian Kg 105.59 15,433.43 1,629,653.98
b. Beton K.250 M3 0.56 1,251,781.91 695,677.79
c. Bekisting M2 1.69 375,989.13 635,421.63
26 Pekerjaan beton ram pintu akses
a. Pembesian Kg 260.83 15,433.43 4,025,531.23
b. Beton K.250 M3 1.37 1,251,781.91 1,718,446.20
c. Bekisting M2 11.44 375,989.13 4,301,315.65
27 Pekerjaan kolom praktis M1 119.00 96,301.37 11,459,863.29
28 Pekerjaan Balok Intel M1 73.50 139,828.16 10,277,370.00

JUMLAH HARGA PEK. II 710,945,991.65

III. PEKERJAAN KONTRUKSI BAJA


1 Pekerjaan Angkur d. 19 Bh 124.00 45,000.00 5,580,000.00
2 Pekerjaan Base plat t. 20 mm Kg 309.00 38,670.72 11,949,187.35
3 Tiang kolom baja WF 250.125.6 Kg 2,758.72 38,670.72 106,681,682.61
4 Balok B.1 baja WF 250.125.6 Kg 1,518.48 38,670.72 58,720,711.56
5 Balok B.2 baja WF200.100.5.8 Kg 1,561.60 38,670.72 60,388,192.92
6 Balok B.3 baja WF 150.75.4.8 Kg 412.59 38,670.72 15,955,022.55
7 Pekerjaan Voute sambungan kolom balok Kg 1,387.26 38,670.72 53,646,339.98
8 Pekerjaan plat t. 12 mm sambungan Kg 722.17 38,670.72 27,926,703.37
9 Baut A325 Ø 16 mm Bh 288.00 21,000.00 6,048,000.00
10 Perakitan kontruksi Kg 8,669.81 434,953.71 3,770,966,714.74
11 Pengectan Kontruksi baja + zingkromat m2 288.99 55,635.10 16,078,195.07
JUMLAH HARGA PEK. III 4,133,940,750.15

IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP


1 Pekerjaan Kuda-kuda WF200.100.5.8 Kg 1,855.92 38,670.72 71,769,758.58
2 Pekerjaan plat sambungan t. 12 mm Kg 663.54 38,670.72 25,659,632.54
3 Pekerjaan stifner plat t. 10 mm Kg 204.17 38,670.72 7,895,271.55
4 Pekerjaan Rangka Atap Besi Canal C uk.150.65.20.2,3 Kg 4,431.83 38,670.72 171,381,918.37
5 Plat dudukan Canal t. 8 mm Kg 171.42 38,670.72 6,628,805.54
6 Pek braccing besid. 10 Kg 116.00 38,670.72 4,485,744.49
7 Pek. Trestang besi ulir d. 13 + watermur Kg 212.89 38,670.72 8,232,660.47
8 Baut A325 Ø 16 mm Bh 124.00 21,000.00 2,604,000.00
9 Perakitan kontruksi Kg 7,655.76 434,953.71 3,329,901,825.66
10 Pekerjaan water mur M.10 BH 212.89 15,000.00 3,193,369.92
11 Pekerjaan Penutup Atap Spandek t=05 mm M2 582.23 207,740.20 120,952,575.19
12 Pekerjaan Roof Drain 4 " Bh 2.00 303,982.21 607,964.41
13 Pekerjaan Talang air rangka siku dan hollow + plat zinalum M1 40.59 535,000.00 21,715,650.00
14 Pekerjaan penutup talang air hujan dengan SPANDEK m2 48.71 207,740.20 10,118,609.54
15 Pekerjaan Lisplank Spandek + Rangka M2 15.00 207,740.20 3,116,102.96
JUMLAH HARGA PEK. IV 3,788,263,889.21

Page 48 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


V. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
1 Pas. Bata ringan / Hebel M2 465.91 174,510.40 81,305,528.93
2 Plesteran Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 102,698.31 95,695,620.34
3 Acian Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 62,423.35 58,166,889.03
4 Plesteran Openingan Kusen dengan Mortar Instan M1 215.00 62,423.35 13,421,020.25
5 Pekerjaan Acian Kolom expouse M2 54.00 62,423.35 3,370,860.90
6 Pekerjaan dinding spandek warna + rangka besi CNP dan U Canal M2 178.00 435,000.00 77,430,000.00
7 Pekerjaan dinding partisi 2 muka m2 10.95 286,780.79 3,140,249.60
8 Pekerjaan hand railling selasar pipa gic dia. 3" finis cat m1 22.00 345,000.00 7,590,000.00
9 Pekerjaan railling tangga m1 14.00 850,000.00 11,900,000.00
JUMLAH HARGA PEK. VA. 352,020,169.05

B. PEKERJAAN PASANGAN LANTAI


1 Pasangan lantai Kamar Mandi keramik uk. 40x40 kasar M2 72.00 312,260.38 22,482,747.30
2 Pasangan dinding keramik uk. 20x40 halus M2 16.20 294,215.12 4,766,284.96
3 Pekerjaan floor hardener lantai dasar M2 403.00 184,010.64 74,156,286.15
4 Pekerjaan lantai keramik tangga 30x60 cm m2 20.00 337,864.94 6,757,298.79
5 Pasang stef nozing M1 20.70 52,965.47 1,096,385.30
6 Pekerjaan rabat beton M2 80.50 125,000.00 10,062,500.00
JUMLAH HARGA PEK. VB. 119,321,502.51

C. PEKERJAAN PASANGAN PLAFOND


1 pekerjaan Plafond GRC rangka hollow M2 5.44 241,482.54 1,313,665.01
2 pekerjaan Plafond Gybsum rangka hollow M2 60.80 232,044.12 14,108,282.50
3 Pekerjaan Liss plafond M2 79.60 45,000.00 3,582,000.00
JUMLAH HARGA PEK. VC. 19,003,947.50

D. PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pekerjaan Kusen PD.1 Unit 1.00 15,974,150.71 15,974,150.71
2 Pekerjaan Kusen P.1 Unit 4.00 12,272,681.90 49,090,727.62
3 Pekerjaan Kusen P.2 Unit 2.00 3,516,546.62 7,033,093.23
4 Pekerjaan Kusen P.3 Unit 1.00 4,588,656.13 4,588,656.13
5 Pekerjaan Kusen P.4 Unit 1.00 2,821,220.31 2,821,220.31
6 Pekerjaan Kusen J.2 Unit 6.00 4,749,922.61 28,499,535.67
7 Pekerjaan Kusen J.3 Unit 1.00 4,718,627.57 4,718,627.57
8 Pekerjaan Kusen J.5 Unit 11.00 3,485,977.63 38,345,753.91
9 Pekerjaan jendela kaca bening diatas partisi m2 21.15 571,899.25 12,095,669.14
10 Pekerjaan Kusen BV.1 Unit 1.00 525,191.12 525,191.12
JUMLAH HARGA PEK. V D. 163,692,625.41

E. PEKERJAAN SANITAIR
1 Pemasangan Closet duduk + asesoris BH 1.00 3,552,619.84 3,552,619.84
2 PemasanganUrinoir + asesoris BH 1.00 1,433,514.94 1,433,514.94
3 Pemasangan wastafel BH 1.00 1,148,430.72 1,148,430.72
4 Pemasangan Kran air BH 1.00 187,386.61 187,386.61
5 pemasangan Floor drain BH 2.00 155,152.21 310,304.41
JUMLAH HARGA PEK. V E. 6,632,256.52
F. PEKERJAAN PENGECETAN
1 Pengecetan Exterior Wethersield setara ICI / Dulux 465.91 52,563.26 24,489,566.13
2 Pengecetan Interior setara ICI / Dulux 465.91 61,536.62 28,670,312.88
3 Pengecetan Plafond setara Vinilex 66.24 52,563.26 3,481,790.57
JUMLAH HARGA PEK. V F. 56,641,669.58

TOTAL JUMLAH PEKERJAAN ARSITEKTUR 717,312,170.57


V. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL

Page 49 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


A. PEKERJAAN MEKANIKAL
1 Pekerjaan Instalasi Air Kotor
- Instalasi Pipa Air Kotor 3 " PVC M1 15.00 186,986.13 2,804,791.97
- Instalasi Pipa Air Kotor 2" PVC M1 25.00 142,169.76 3,554,244.05
- Instalasi Pipa Air Kotor 4 " PVC M1 38.00 248,429.76 9,440,330.95
- Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Titik 1.00 18,000,000.00 18,000,000.00
- Bio Septictank Kapasitas 3 m3 + Instalasi + Dudukan Titik 1.00 35,000,000.00 35,000,000.00
PEKERJAAN POMPA
Jet Pump / Shallow Well set 1.00 20,600,000.00 20,600,000.00
Kap : 65 L / Jam
Head : 50 m
Power : 2.2 Hp ( 1650 Watt )
Daya Dorong : 50 m
Panjang Pipa Hisap : 50 m

PEKERJAAN PEMIPAAN
Pemipaan Air Bersih
a. Pipa PPR PN 16
dia. 1 1/2" m 12.00 203,835.60 2,446,027.15
dia. 1 1/4" m 12.00 173,475.60 2,081,707.15
dia. 1/2" m 14.00 74,805.60 1,047,278.34
b. Gate Valve dia. 11/2 bh 3.00 237,583.23 712,749.68
c. Elbow
dia. 1/2" bh 21.00 131,323.23 2,757,787.73
dia 1 1/2" bh 4.00 389,383.23 1,557,532.90
dia 1 1/4" bh 8.00 305,893.23 2,447,145.80
d. Tee
dia. 1 1/2" x 1 1/2" x 1 1/2" bh 21.00 69,085.23 1,450,789.73
dia. 1 1/4" x 1 1/4" x 1 1/4" bh 12.00 290,713.23 3,488,558.70
Soket dia. 1 1/2" x 1 1/4" bh 14.00 427,333.23 5,982,665.15
Soket dia. 1 1/2" x 1/2" bh 21.00 222,403.23 4,670,467.73
Soket dia 1 1/4" x 1/2" bh 13.00 146,503.23 1,904,541.93
Soket dia 2" x 1 1/2" bh 4.00 169,985.26 679,941.06

Pemipaan Air Kotor


a.Pipa PVC Class AW dia. 4" m 144.00 248,429.76 35,773,885.70
b.Elbow dia. 4" bh 46.00 97,177.92 4,470,184.34
c.Tee bh 14.00 25,000.00 350,000.00
d.Pipa PVC Class dia 1 1/2" dari urinoir bh 18.40 125,471.76 2,308,680.42
e.Soket dia 4" x 1 1/2" bh 8.00 300,803.31 2,406,426.44

Pemipaan Air Bekas


a.Pipa PVC Class AW dia. 3" m 88.00 186,986.13 16,454,779.55
b.Elbow dia. 3" bh 8.00 39,493.92 315,951.36
c.Tee dia. 3" bh 32.00 20,000.00 640,000.00
d.Clean Out dia. 3" bh 6.00 167,362.21 1,004,173.24
e.Pipa PVC Class AW dia 1 1/4", dari wastafel m 16.00 51,516.84 824,269.46
f.Elbow dia 1 1/4" bh 24.00 20,822.52 499,740.49
g.reducer 3" x 1 1/4" bh 10.00 191,293.92 1,912,939.20

Page 50 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


Pipa Talang tegak Air Hujan
Pipa PVC Wavin Aw
a.Ø 4" m 160.00 248,429.76 39,748,761.89
b.Ø 3" m 44.00 186,986.13 8,227,389.77
Elbow dia. 4"
a.dia. 4 " m 22.00 97,177.92 2,137,914.25
Clamp pipa PVC Ø 4" bh 44.00 92,623.92 4,075,452.50
Roof drain bh 22.00 303,982.21 6,687,608.53

Rumah pompa lengkap kunci Unit 2.00 5,000,000.00 10,000,000.00


tangki air kap 1,2m3 Unit 2.00 3,500,000.00 7,000,000.00
Switch otomatis Unit 2.00 600,000.00 1,200,000.00
JUMLAH HARGA PEK. MEKANIKAL 266,664,717.11

B. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Pemasangan Listrik PLN 10,6 KVA Kwh 10,600.00 1,500.00 15,900,000.00
2 Panel Utama LDP lengkap terpasang dengan MCB Unit 1.00 45,000,000.00 45,000,000.00
3 panel pembagi Unit 2.00 5,500,000.00 11,000,000.00
4 Penarikan kabel tofer dari gardu keruang panel utama NYFGBY 4 x 25 mm M1 65.00 404,722.15 26,306,939.95
5 Penarikan kabel NYY 4x 10 mm dari Panel utama ke panel pembagi M1 35.00 171,077.82 5,987,723.86
6 Instalasi Kabel NYM 3 x 2,5 mm² Lampu, dalam pipa konduit 20 mm titik 54.00 289,405.50 15,627,897.00
7 Instalasi Kabel NYM 3 x 2,5 mm² Stop Kontak, dalam pipa konduit 20 mm titik 31.00 305,961.60 9,484,809.60
8 Pekerjaan Armatur Listrik
- Lampu Down Light PLC 18 W BH 17.00 244,403.62 4,154,861.56
- Lampu LP HARR HLG 120 W BH 22.00 722,573.62 15,896,619.66
- Lampu LB T5 2X18 W BH 15.00 540,413.62 8,106,204.32
- Saklar Seri setara broco BH 9.00 183,353.62 1,650,182.59
- Saklar Tunggal setara broco BH 2.00 210,941.62 421,883.24
- Stop Kontak, 220 V, 1-ph, 10 A setara broco BH 17.00 210,941.62 3,586,007.56
- Stop Kontak AC, setara broco BH 3.00 430,193.62 1,290,580.86
- Mesin Pompa Air Kotor Ke Ipal + Instalasi BH 1.00 9,600,000.00 9,600,000.00
-
JUMLAH HARGA PEK. ELEKTRIKAL 174,013,710.19

TOTAL JUMLAH PEKERJAAN MEKANIKAL &ELEKTRIKAL 440,678,427.30


VI. PEKERJAAN PENUNJANG
A. PEKERJAAN SALURAN DAN PERKERASAN
1 Pekerjaan galian tanah saluran M3 23.40 135,398.01 3,168,313.43
2 Pekerjaan urugan pasir saluran M3 2.93 332,283.20 971,928.37
3 Pekerjaan lantai kerja saluran M3 2.93 1,196,449.20 3,499,613.92
4 Pekerjaan dinding saluran pasangan bata m2 163.80 157,468.49 25,793,338.17
5 Pekerjaan Plesteran dinding saluran m2 198.90 102,698.31 20,426,693.86
6 Pekerjaan Acian dinding saluran m2 198.90 62,423.35 12,416,004.32
7 Pekerjaan pipa PVC dia.4' crosingan ke saluran m1 45.00 248,429.76 11,179,339.28
8 Pekerjaan Kanstinn m1 89.00 211,143.70 18,791,788.86
9 Pekerjaan urugam Sirtu M3 26.87 341,002.43 9,162,735.42
10 Pekerjaan Lantai kerja BO. M3 26.87 1,196,449.20 32,148,590.12

Page 51 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


11 Pekerjaan Perkerasan beton K.350 t. 15 cm -
a. Plastik cor M2 268.70 25,000.00 6,717,500.00
b. Pembesian Kg 4,900.80 15,659.81 76,745,574.70
c. Beton M3 40.31 1,296,830.87 52,268,768.01
d. Bekisting M2 40.31 210,367.96 8,478,880.63

JUMLAH HARGA PERKERASAN HALAMAN 281,769,069.10


B. PEKERJAAN POS JAGA
Pek. Galian dan Pondasi
1 Galian Pondasi m3 2.64 135,398.01 357,450.75
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.33 332,283.20 109,653.46
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.33 1,078,290.92 355,836.00
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 2.97 1,177,216.15 3,496,331.97
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 57.20 15,659.81 895,740.87
b. Beton M3 0.33 1,251,781.91 413,088.03
c. Bekisting M2 4.40 210,367.96 925,619.02
6 Urug kembali bekas Galian pondasi m3 0.88 48,694.36 42,851.04

Pek. Pasangan dan Beton


1 Cor kolom praktis K-100 type Kp 12 x 12 cm m1 18.00 96,301.37 1,733,424.70
2 Pas. Dinding bata ringan t=10 cm dengan MSP m2 22.14 174,510.40 3,863,660.22
3 Plesteran dinding dengan MSP m2 44.27 102,698.31 4,546,454.18
4 Acian dinding m2 44.27 62,423.35 2,763,481.70
5 Plat beton tebal 8 cm -
a. Pembesian Kg 195.80 15,659.81 3,066,189.91
b. Beton K.250 m3 0.56 1,387,961.89 777,258.66
c. Bekisting M2 0.88 375,989.13 330,870.43

6 Pasangan lantai Homogenus 60/60 m2 6.48 344,707.14 2,233,702.25


7 Ring Balok 15/20 m1 13.00 139,828.16 1,817,766.12
Plat beton atap 12 cm
a. Pembesian Kg 352.80 15,659.81 5,524,779.37
b. Beton K.250 m3 1.68 1,387,961.89 2,331,775.98
c. Bekisting M2 14.00 375,989.13 5,263,847.82
8 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 13.23 232,044.12 3,069,943.71
9 Pas. Kusen + Daun Pintu Type P1 Lengkap unit 1.00 12,272,681.90 12,272,681.90
10 Pas. Kusen + Daun Jendela Type J1 Lengkap unit 1.00 2,137,780.54 2,137,780.54
11 Pas. Kusen + Daun Jendela Type J2 Lengkap unit 1.00 4,749,922.61 4,749,922.61
14 Kalsiplank 8/300 m' 15.20 222,877.62 3,387,739.85

Pek. Finishing dan Water Proffing


1 Pengecatan Dinding dalam m2 22.14 52,563.26 1,163,750.65
2 Pengecatan dinding luar m2 22.14 61,536.62 1,362,420.84
3 Pengecatan Plafond m2 5.56 52,563.26 292,251.75

Pek. Mekanikal dan Elektrikal


1 Instalasi penerangan titik 2.00 289,405.50 578,811.00
2 Instalasi stop kontak titik 1.00 305,961.60 305,961.60
3 Saklar Doubel buah 1.00 183,353.62 183,353.62
4 Stop Kontak buah 1.00 430,193.62 430,193.62
5 Down Light LED BULB E27 7 W buah 2.00 607,200.00 1,214,400.00
6 Pipa Air Pembuangan Air Hujan dia 3" m' 5.00 186,986.13 934,930.66
-
JUMLAH HARGA PERKERASAN POS JAGA 72,933,924.85

C. PEKERJAAN PEMAGARAN
1 Galian Pondasi m3 151.52 135,398.01 20,516,048.07
2 Urugan Pasir Bawah Pondasi h=5 cm m3 6.31 332,283.20 2,097,870.01
3 Urugan tanah kembali m3 50.51 48,694.36 2,459,454.73
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 147.32 1,177,216.15 173,421,597.14
5 Sloof Atas Pondasi 20/30 - -
a. Pembesian Kg 1,767.78 15,659.81 27,683,090.93
b. Beton K.250 m3 8.42 1,387,961.89 11,683,863.22
c. Bekisting M2 84.18 375,989.13 31,650,764.96
6 Pagar panel Precas m1 140.30 768,747.63 107,855,291.90
JUMLAH HARGA PEMAGARAN 377,367,980.96

Page 52 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


D. PEKERJAAN GAPURA DAN PINTU GERBANG
1 Galian Pondasi m3 4.80 135,398.01 649,910.45
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.20 332,283.20 66,456.64
3 Urugan tanah kembali m3 1.60 48,694.36 77,910.98
4 Lantai kerja pondasi setapak m3 0.05 1,078,290.92 53,914.55
5 Pekerjaan Pondasi setapak 0,6x0,6x0,2 -
a. Pembesian Kg 66.24 15,659.81 1,037,305.51
b. Beton K.250 m3 0.29 1,387,961.89 399,733.03
c. Bekisting M2 1.92 204,592.96 392,818.48
6 Pekerjaan Kolom pedestal uk. 25x25 cm
a. Pembesian Kg 52.50 15,659.81 822,139.79
b. Beton K.250 m3 0.25 1,387,961.89 346,990.47
c. Bekisting M2 4.00 331,989.13 1,327,956.52
7 Pekerjaan Kolomf uk. 25x25 cm
a. Pembesian Kg 210.00 15,659.81 3,288,559.15
b. Beton K.250 m3 1.00 1,387,961.89 1,387,961.89
c. Bekisting M2 16.00 331,989.13 5,311,826.08
8 Pekerjaan Balok uk. 30x60 cm
a. Pembesian Kg 316.80 15,659.81 4,961,026.38
b. Beton K.250 m3 1.44 1,387,961.89 1,998,665.13
c. Bekisting M2 9.60 336,279.13 3,228,279.65
9 Pekerjaan Plat lantai t. 12 cm
a. Pembesian Kg 158.40 15,659.81 2,480,513.19
b. Beton K.250 m3 0.72 1,387,961.89 999,332.56
c. Bekisting M2 6.00 360,589.13 2,163,534.78
10 Pekerjaan Kolom praktis M1 4.00 96,301.37 385,205.49
11 Pekerjaan Ring balok m1 20.00 139,828.16 2,796,563.26
12 Pekerjaan Pasangan bata ringan m2 12.00 174,510.40 2,094,124.78
13 Pekerjaan Plesteran m2 12.00 102,698.31 1,232,379.72
14 Pekerjaan Acian m2 12.00 62,423.35 749,080.20
15 Pekerjaan Pengecetan m2 12.00 61,536.62 738,439.48
16 Pekerjaan Papan Nama Stenliss t. 15 cm bh 65.00 155,000.00 10,075,000.00
17 Pekerjaan Logo unit 1.00 4,500,000.00 4,500,000.00
18 Pekerjaan Instalasi Penerangan titik 3.00 289,405.50 868,216.50
19 Pekerjaan Lampu tembak bh 3.00 722,573.62 2,167,720.86
20 Pekerjaan Pintu Gerbang rangka besi pipa terpasang + finis cat m2 16.00 1,150,000.00 18,400,000.00

JUMLAH HARGA GAPURA PINTU GERBANG 75,001,565.52

D. PEKERJAAN RUMAH LOKER KM UMUM


1 Galian Pondasi m3 5.58 135,398.01 755,520.90
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.93 332,283.20 309,023.38
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.93 1,078,290.92 1,002,810.55
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 5.58 1,177,216.15 6,568,866.12
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 195.30 15,659.81 3,058,360.01
b. Beton M3 0.93 1,251,781.91 1,164,157.17
c. Bekisting M2 12.40 210,367.96 2,608,562.70
6 Urug kembali bekas Galian pondasi m3 1.86 48,694.36 90,571.51
-
Pek. Pasangan dan Beton -
8 Pas. Dinding bata ringan t=10 cm dengan MSP m2 82.02 174,510.40 14,313,342.88
9 Plesteran dinding dengan MSP m2 164.04 102,698.31 16,846,630.77
10 Acian dinding m2 164.04 62,423.35 10,239,926.33
11 Plat beton diatas tanah tebal 10 cm -
a. Pembesian Kg 457.28 15,659.81 7,160,837.55
b. Beton m3 3.52 1,387,961.89 4,882,155.96
c. Bekisting M2 2.70 204,592.96 552,400.99
d. Plastik cor m2 35.18 25,000.00 879,375.00
12 Pekerjaan beton kolom 12/12
a. Pembesian Kg 101.61 15,659.81 1,591,136.46
b. Beton m3 0.48 1,387,961.89 671,551.48
c. Bekisting M2 16.13 331,989.13 5,354,320.69

Page 53 of 162
BILL OFF QUANTTYTI

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


13 Pekerjaan beton Ring Balok 15/25
a. Pembesian Kg 244.13 15,659.81 3,822,950.01
b. Beton m3 1.16 1,387,961.89 1,613,505.70
c. Bekisting M2 15.50 336,279.13 5,212,326.52
14 Pekerjaan Plat beton t. 12 cm
a. Pembesian Kg 790.02 15,659.81 12,371,559.53
b. Beton m3 4.16 1,387,961.89 5,771,145.55
c. Bekisting M2 35.70 336,279.13 12,005,164.94
15 Pasangan lantai Homogenus 40/40 m2 31.01 312,260.38 9,682,413.71
16 Pasang Plafond GRC + Rangka Hollow m2 12.00 241,482.54 2,897,790.46
17 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 19.01 232,044.12 4,410,578.61
18 Pekerjaan Kusen P.1 unit 2.00 12,272,681.90 24,545,363.81
19 Pekerjaan Kusen P.4 unit 3.00 2,821,220.31 8,463,660.94
20 Pekerjaan Kusen BV.1 unit 3.00 525,191.12 1,575,573.35
21 Pekerjaan Kusen J.2 unit 2.00 4,749,922.61 9,499,845.22
-
Pek. Finishing dan Water Proffing -
22 Pengecatan Dinding dalam m2 82.02 52,563.26 4,311,238.87
23 Pengecatan dinding luar m2 82.02 61,536.62 5,047,233.86
24 Pengecatan Plafond m2 31.01 52,563.26 1,629,855.39
-
Pek. Mekanikal dan Elektrikal -
25 Instalasi penerangan titik 7.00 289,405.50 2,025,838.50
26 Instalasi stop kontak titik 3.00 305,961.60 917,884.80
27 Saklar Doubel buah 2.00 183,353.62 366,707.24
28 Stop Kontak buah 4.00 430,193.62 1,720,774.48
29 Down Light LED BULB E27 7 W buah 7.00 607,200.00 4,250,400.00
30 Pipa Air Pembuangan Air Hujan dia 3" m' 15.00 186,986.13 2,804,791.97
31 - Instalasi Pipa Air Kotor 3 " PVC m' 12.00 186,986.13 2,243,833.57
32 - Instalasi Pipa Air Kotor 2" PVC m' 12.00 142,169.76 1,706,037.14
33 - Instalasi Pipa Air Kotor 4 " PVC m' 15.00 248,429.76 3,726,446.43
34 - Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Unit 1.00 18,000,000.00 18,000,000.00
35 Pemasangan Closet duduk + asesoris BH 3.00 3,552,619.84 10,657,859.52
36 Pasang Head Shower+fleksibel Komplit 1 buah BH 3.00 366,906.61 1,100,719.82
37 Pasang Jet Shower+fleksibel Komplit 1 buah BH 3.00 324,666.61 973,999.82
38 Pemasangan Kran air BH 3.00 187,386.61 562,159.82
39 pemasangan Floor drain BH 3.00 155,152.21 465,456.62
40 Sumur pantek + pompa + Rumah pompa lengkap kunci Unit 1.00 13,500,000.00 13,500,000.00
41 tangki air kap 1,2m3 Unit 1.00 3,500,000.00 3,500,000.00
42 Switch otomatis Unit 1.00 600,000.00 600,000.00

JUMLAH HARGA GAPURA PINTU GERBANG 260,032,666.66

Page 54 of 162
BILL OF QUANTITY

REKAP HARGA ESTIMASI ENGGINERING


Kegiatan : PEMBANGUNAN TPS 3R RAWA BADAK
Lokasi : Jl. INPEKSI RAWA BADAK UTARA RW 09 KEL. RAWA BADAK UTARA KECAMATAN KOJA
Sumber Dana : APBD
Tahun Anggaran : 2019

No. URAIAN PEKERJAAN JUMLAH HARGA TOTAL HARGA

I. PEKERJAAN PERSIAPAN 56,946,584.41 56,946,584.41


II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON 696,937,171.92 696,937,171.92
III. PEKERJAAN KONTRUKSI BAJA 4,117,862,555.08 4,117,862,555.08
IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP 3,775,478,924.80 3,775,478,924.80
V. PEKERJAAN ARSITEKTUR 387,582,725.02
A. PEKERJAAN PASANGAN DINDING 251,959,919.45
B. PEKERJAAN PASANGAN LANTAI -
C. PEKERJAAN PASANGAN PLAFOND -
D. PEKERJAAN KUSEN, PINTU DAN JENDELA 135,622,805.57
E. PEKERJAAN SANITAIR -
F. PEKERJAAN PENGECETAN -
VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 58,799,366.96
A. PEKERJAAN MEKANIKAL 58,799,366.96
B. PEKERJAAN ELEKTRIKAL -

VII. PEKERJAAN PENUNJANG 352,248,608.16


A. PEKERJAAN SALURAN DAN PERKERASAN 66,275,892.07
B. PEKERJAAN POS JAGA -
C. PEKERJAAN PEMAGARAN 140,869,164.76
D. PEKERJAAN GAPURA DAN PINTU GERBANG -
E. PEKERJAAN RUMAH LOKER KM UMUM 145,103,551.32

JUMLAH HARGA 9,445,855,936.35


PPN 10 % 944,585,593.63
TOTAL HARGA 10,390,441,529.98
DIBULATKAN 10,390,441,000.00
TERBILANG : DUA MILYARD TUJUH RATUS LIMA PULUH EMPAT JUTA DELAPAN RATUS DELAPAN PULUH ENAM RIBU RUPIAH

Jakarta, Maret 2019


Kuasa Pengguna Anggaran
Suku Dinas Lingkungan Hidup
Kota Administrasi Jakarta Utara
Selaku
Pejabat Pembuat Komitmen

SLAMET RIYADI, S.Sos, Msi


NIP : 197111191991011001

Page 55 of 162
BILL OF QUANTITY

BILL OF QUANTYTI ESTIMAT ENGGINERING


Kegiatan : PEMBANGUNAN TPS 3R RAWA BADAK
Lokasi : Jl. INPEKSI RAWA BADAK UTARA RW 09 KEL. RAWA BADAK UTARA KECAMATAN KOJA
Sumber Dana : APBD
Tahun Anggaran : 2019

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek bh 1.00 600,000.00 600,000.00
2 Pek. Pengukuran dan bowplang m1 116.00 87,707.10 10,174,023.95
3 Barak kerja M2 12.00 690,260.86 8,283,130.27
4 Kantor Direksi Keet m2 9.00 1,932,158.91 17,389,430.19
5 Pengadaan Sumber Air Kerja ls 1.00 6,000,000.00 6,000,000.00
6 Pengadaan Listrik Kerja ls 1.00 5,000,000.00 5,000,000.00
7 Pembuatan Asbuildrawing dan shop drawing Ls 1.00 4,500,000.00 4,500,000.00
8 Pembersihan Lokasi Ls 1.00 5,000,000.00 5,000,000.00
JUMLAH HARGA PEK. I 56,946,584.41
II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON
1 Pengadaan tiang pancang Square 25x25cm M1 504.00 289,100.00 145,706,400.00
2 Pemancangan Menggunakan Hydraulic (Jacking Pile) M1 504.00 73,500.00 37,044,000.00
3 Pemotongan kepala tiang pancang Titik 28.00 80,000.00 2,240,000.00
4 Handling dan Joint Titik 56.00 75,000.00 4,200,000.00
5 Pek. Test tekan tiang pancang PDA Titik 2.00 10,000,000.00 20,000,000.00
6 Pekerjaan Galian tanah M3 21.44 135,398.01 2,903,474.93
7 Urugan tanah kembali M3 6.86 48,694.36 334,140.70
8 urugan tanah baru peninggian M3 343.00 215,859.20 74,039,706.97
9 Pekerjaan urugan pasir t. 5 cm M3 2.62 332,283.20 871,246.56
10 Pekerjaan lantai kerja t. 5 cm pondasi dan sloof M3 2.70 1,196,449.20 3,226,823.50
11 Pekerjaan pondasi batu adukan 1pc : 6 ps kali sisi belakang M3 48.30 1,177,216.15 56,859,540.05
12 Pekerjaan Sloff Diatas batu kali 15 x 30 cm
a. Pembesian Kg 456.39 15,433.43 7,043,661.05
b. Beton K.250 M3 2.07 1,251,781.91 2,596,821.56
c. Bekisting M2 27.66 204,592.96 5,659,041.27
13 Pekerjaan Pondasi TIE BEAM uk. 1,3 m x 0,6 mx 0,6 m
a. Pembesian Kg 968.76 15,433.43 14,951,285.27
b. Beton K.250 M3 4.21 1,251,781.91 5,272,505.38
c. Bekisting M2 20.52 204,592.96 4,198,247.54
14 Pekerjaan Pondasi TIE BEAM uk. 0,65 m x 0,6 mx 0,6 m
a. Pembesian Kg 514.80 15,433.43 7,945,127.44
b. Beton K.250 M3 2.34 1,251,781.91 2,929,169.66
c. Bekisting M2 15.00 204,592.96 3,068,894.40
15 Pekerjaan Sloff SL.1 20 x 40 cm
a. Pembesian Kg 1,449.60 15,433.43 22,372,293.58
b. Beton K.250 M3 7.25 1,251,781.91 9,072,915.25
c. Bekisting M2 72.48 204,592.96 14,828,897.74
16 Pekerjaan Sloff SL.2 15 x 30 cm
a. Pembesian Kg 609.53 15,433.43 9,407,058.67
b. Beton K.250 M3 2.90 1,251,781.91 3,633,296.98
c. Bekisting M2 38.70 204,592.96 7,917,747.55
17 Pekerjaan Kolom Pedestal Uk. 25 x 35 cm
a. Pembesian Kg 359.04 15,433.43 5,541,217.08
b. Beton K.250 M3 1.63 1,251,781.91 2,042,908.07
c. Bekisting M2 27.60 331,989.13 9,162,899.99
18 Pekerjaan Kolom Pedestal Uk. 25 x 25 cm
a. Pembesian Kg 237.60 15,433.43 3,666,981.89
b. Beton K.250 M3 1.08 1,251,781.91 1,351,924.46
c. Bekisting M2 10.00 331,989.13 3,319,891.30
19 Pekerjaan plat lantai dasar t. 10 cm
a. Pembesian warmes M.8 Kg 4,649.05 15,433.43 71,750,786.71
b. Beton K.250 M3 32.27 1,251,781.91 40,395,502.79
c. Bekisting M2 5.36 204,592.96 1,096,618.27
d. Plastik cor M2 520.29 21,000.00 10,926,090.00
20 Pekerjaan plat lantai 2 t. 12 cm
a. Pembesian warmes M.10 Kg 567.40 15,433.43 8,756,991.21
b. Beton K.250 M3 7.62 1,251,781.91 9,538,578.12
c. Bekisting plat bondeks M2 63.50 198,638.39 12,613,537.73
d. Bekisting kayu (pinggiran) M2 5.40 204,592.96 1,104,801.98
21 Pekerjaan plat lantai atap t. 12 cm dudukan toren
a. Pembesian warmes M.10 Kg 35.74 15,433.43 551,621.49
b. Beton K.250 M3 0.40 1,251,781.91 500,712.76

Page 56 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


c. Bekisting plat bondeks M2 4.00 198,638.39 794,553.56
d. Bekisting kayu (pinggiran) M2 1.60 204,592.96 327,348.74
22 Pekerjaan beton plat tangga
a. Pembesian Kg 240.24 15,433.43 3,707,726.14
b. Beton K.250 M3 1.09 1,251,781.91 1,366,945.84
c. Bekisting M2 9.10 336,279.13 3,060,140.08
23 Pekerjaan beton plat bordes tangga
a. Pembesian Kg 77.06 15,433.43 1,189,361.50
b. Beton K.250 M3 0.41 1,251,781.91 507,722.74
c. Bekisting M2 3.38 375,989.13 1,270,843.26
24 Pekerjaan beton anak tangga
a. Pembesian Kg 105.59 15,433.43 1,629,653.98
b. Beton K.250 M3 0.56 1,251,781.91 695,677.79
c. Bekisting M2 1.69 375,989.13 635,421.63
25 Pekerjaan beton ram pintu akses
a. Pembesian Kg 260.83 15,433.43 4,025,531.23
b. Beton K.250 M3 1.37 1,251,781.91 1,718,446.20
c. Bekisting M2 11.44 375,989.13 4,301,315.65
26 Pekerjaan kolom praktis M1 112.00 96,301.37 10,785,753.69
27 Pekerjaan Balok Intel M1 73.50 139,828.16 10,277,370.00

JUMLAH HARGA PEK. II 696,937,171.92

III. PEKERJAAN KONTRUKSI BAJA


1 Pekerjaan Angkur d. 19 Bh 124.00 45,000.00 5,580,000.00
2 Pekerjaan Base plat t. 20 mm Kg 309.00 38,670.72 11,949,187.35
3 Tiang kolom baja WF 250.125.6 Kg 2,758.72 38,670.72 106,681,682.61
4 Balok B.1 baja WF 250.125.6 Kg 1,518.48 38,670.72 58,720,711.56
5 Balok B.2 baja WF200.100.5.8 Kg 1,561.60 38,670.72 60,388,192.92
6 Balok B.3 baja WF 150.75.4.8 Kg 412.59 38,670.72 15,955,022.55
7 Pekerjaan Voute sambungan kolom balok Kg 1,387.26 38,670.72 53,646,339.98
8 Pekerjaan plat t. 12 mm sambungan Kg 722.17 38,670.72 27,926,703.37
9 Baut A325 Ø 16 mm Bh 288.00 21,000.00 6,048,000.00
10 Perakitan kontruksi Kg 8,669.81 434,953.71 3,770,966,714.74
11 Pengecetan Kontruksi baja + zingkromat m2 346.79 55,635.10 tidak dikerjakan
JUMLAH HARGA PEK. III 4,117,862,555.08

IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP


1 Pekerjaan Kuda-kuda WF250.125.6 Kg 1,855.92 38,670.72 71,769,758.58
2 Pekerjaan plat sambungan t. 12 mm Kg 663.54 38,670.72 25,659,632.54
3 Pekerjaan stifner plat t. 10 mm Kg 204.17 38,670.72 7,895,271.55
4 Pekerjaan Rangka Atap Besi Canal C uk.150.65.20.2,3 Kg 4,431.83 38,670.72 171,381,918.37
5 Plat dudukan Canal t. 8 mm Kg 171.42 38,670.72 6,628,805.54
6 Pek braccing besid. 10 Kg 116.00 38,670.72 4,485,744.49
7 Pek. Trestang besi ulir d. 13 + watermur Kg 212.89 38,670.72 8,232,660.47
8 Baut A325 Ø 16 mm Bh 124.00 21,000.00 2,604,000.00
9 Perakitan kontruksi Kg 7,655.76 434,953.71 3,329,901,825.66
10 Pengecetan Kontruksi baja + zingkromat M2 255.19 55,635.10 tidak dikerjakan
11 Pekerjaan water mur M.10 BH 212.89 15,000.00 3,193,369.92
12 Pekerjaan Penutup Atap Spandek t=05 mm M2 582.23 207,740.20 120,952,575.19
13 Pekerjaan Talang air rangka siku dan hollow + plat zinalum M1 40.59 235,000.00 9,538,650.00
14 Pekerjaan penutup talang air hujan dengan SPANDEK m2 48.71 207,740.20 10,118,609.54
15 Pekerjaan Lisplank Spandek + Rangka M2 15.00 207,740.20 3,116,102.96
JUMLAH HARGA PEK. IV 3,775,478,924.80

V. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
1 Pas. Bata ringan / Hebel M2 465.91 174,510.40 81,305,528.93
2 Plesteran Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 102,698.31 95,695,620.34
3 Acian Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 62,423.35 58,166,889.03
4 Plesteran Openingan Kusen dengan Mortar Instan M1 215.00 62,423.35 13,421,020.25
5 Pekerjaan Acian Kolom expouse M2 54.00 62,423.35 3,370,860.90
6 Pekerjaan dinding spandek warna + rangka besi CNP dan U Canal M2 178.00 435,000.00 tidak dikerjakan
7 Pekerjaan dinding partisi 2 muka m2 10.95 286,780.79 tidak dikerjakan
8 Pekerjaan hand railling selasar pipa gic dia. 3" finis cat m1 11.00 345,000.00 tidak dikerjakan
9 Pekerjaan railling tangga m1 14.00 850,000.00 tidak dikerjakan
JUMLAH HARGA PEK. VA. 251,959,919.45

B. PEKERJAAN PASANGAN LANTAI


1 Pasangan lantai Kamar Mandi keramik uk. 40x40 kasar M2 72.00 312,260.38 tidak dikerjakan

Page 57 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


2 Pasangan dinding keramik uk. 20x40 halus M2 16.20 294,215.12 tidak dikerjakan
4 Pekerjaan lantai keramik tangga 30x60 cm m2 20.00 337,864.94 tidak dikerjakan
5 Pasang stef nozing M1 20.70 52,965.47 tidak dikerjakan
6 Floor hardener M2 275.60 184,010.64 tidak dikerjakan
7 Pekerjaan rabat beton M2 80.50 125,000.00 tidak dikerjakan
JUMLAH HARGA PEK. VB. -

C. PEKERJAAN PASANGAN PLAFOND


1 pekerjaan Plafond GRC rangka hollow M2 5.44 241,482.54 tidak dikerjakan
2 pekerjaan Plafond Gybsum rangka hollow M2 60.80 232,044.12 tidak dikerjakan
3 Pekerjaan Liss plafond M2 79.60 45,000.00 tidak dikerjakan
JUMLAH HARGA PEK. VC. -

D. PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pekerjaan Kusen PD.1 Unit 1.00 15,974,150.71 tidak dikerjakan
2 Pekerjaan Kusen P.1 Unit 4.00 12,272,681.90 49,090,727.62
3 Pekerjaan Kusen P.2 Unit 2.00 3,516,546.62 7,033,093.23
4 Pekerjaan Kusen P.3 Unit 1.00 4,588,656.13 4,588,656.13
5 Pekerjaan Kusen P.4 Unit 1.00 2,821,220.31 2,821,220.31
6 Pekerjaan Kusen J.2 Unit 6.00 4,749,922.61 28,499,535.67
7 Pekerjaan Kusen J.3 Unit 1.00 4,718,627.57 4,718,627.57
8 Pekerjaan Kusen J.5 Unit 11.00 3,485,977.63 38,345,753.91
9 Pekerjaan jendela kaca bening diatas partisi m2 21.15 571,899.25 tidak dikerjakan
10 Pekerjaan Kusen BV.1 Unit 1.00 525,191.12 525,191.12
JUMLAH HARGA PEK. V D. 135,622,805.57

E. PEKERJAAN SANITAIR
1 Pemasangan Closet duduk + asesoris BH 1.00 3,552,619.84 tidak dikerjakan
2 PemasanganUrinoir + asesoris BH 1.00 1,433,514.94 tidak dikerjakan
3 Pemasangan wastafel BH 1.00 1,148,430.72 tidak dikerjakan
4 Pemasangan Kran air BH 1.00 187,386.61 tidak dikerjakan
5 pemasangan Floor drain BH 1.00 155,152.21 tidak dikerjakan
JUMLAH HARGA PEK. V E. -
F. PEKERJAAN PENGECETAN
1 Pengecetan Exterior Wethersield setara ICI / Dulux 465.91 52,563.26 tidak dikerjakan
2 Pengecetan Interior setara ICI / Dulux 465.91 61,536.62 tidak dikerjakan
3 Pengecetan Plafond setara Vinilex 66.24 52,563.26 tidak dikerjakan
JUMLAH HARGA PEK. V F. -

TOTAL JUMLAH PEKERJAAN ARSITEKTUR 387,582,725.02


VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. PEKERJAAN MEKANIKAL
1 Pekerjaan Instalasi Air Kotor
- Instalasi Pipa Air Kotor 3 " PVC M1 15.00 186,986.13 2,804,791.97
- Instalasi Pipa Air Kotor 2" PVC M1 25.00 142,169.76 3,554,244.05
- Instalasi Pipa Air Kotor 4 " PVC M1 38.00 248,429.76 9,440,330.95
- Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Titik 1.00 18,000,000.00 18,000,000.00
- Bio Septictank Kapasitas 3 m3 + Instalasi + Dudukan Titik 1.00 25,000,000.00 25,000,000.00
PEKERJAAN POMPA
Jet Pump / Shallow Well set 1.00 20,600,000.00 tidak dikerjakan
Kap : 65 L / Jam
Head : 50 m
Power : 2.2 Hp ( 1650 Watt )
Daya Dorong : 50 m
Panjang Pipa Hisap : 50 m

PEKERJAAN PEMIPAAN
Pemipaan Air Bersih
a. Pipa PPR PN 16
dia. 1 1/2" m 12.00 203,835.60 tidak dikerjakan
dia. 1 1/4" m 12.00 173,475.60 tidak dikerjakan
dia. 1/2" m 14.00 74,805.60 tidak dikerjakan
b. Gate Valve dia. 11/2 bh 3.00 237,583.23 tidak dikerjakan
c. Elbow
dia. 1/2" bh 21.00 131,323.23 tidak dikerjakan
dia 1 1/2" bh 4.00 389,383.23 tidak dikerjakan
dia 1 1/4" bh 8.00 305,893.23 tidak dikerjakan
d. Tee

Page 58 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


dia. 1 1/2" x 1 1/2" x 1 1/2" bh 3.00 69,085.23 tidak dikerjakan
dia. 1 1/4" x 1 1/4" x 1 1/4" bh 3.00 290,713.23 tidak dikerjakan
Soket dia. 1 1/2" x 1 1/4" bh 3.00 427,333.23 tidak dikerjakan

Pipa Talang tegak Air Hujan


Pipa PVC Wavin Aw
a.Ø 4" m 160.00 248,429.76 tidak dikerjakan
b.Ø 3" m 44.00 186,986.13 tidak dikerjakan
Elbow dia. 4"
a.dia. 4 " m 22.00 97,177.92 tidak dikerjakan
Clamp pipa PVC Ø 4" bh 44.00 92,623.92 tidak dikerjakan
Roof drain bh 22.00 303,982.21 tidak dikerjakan

Rumah pompa lengkap kunci Unit 2.00 5,000,000.00 tidak dikerjakan


tangki air kap 1,2m3 Unit 2.00 3,500,000.00 tidak dikerjakan
Switch otomatis Unit 2.00 600,000.00 tidak dikerjakan
JUMLAH HARGA PEK. MEKANIKAL 58,799,366.96

B. PEKERJAAN ELEKTRIKAL
1 Pekerjaan Pemasangan Listrik PLN 10,6 KVA Kwh 10,600.00 1,500.00 tidak dikerjakan
2 Panel Utama LDP lengkap terpasang dengan MCB Unit 1.00 35,000,000.00 tidak dikerjakan
3 panel pembagi Unit 2.00 5,500,000.00 tidak dikerjakan
Penarikan kabel tofer dari gardu keruang panel utama NYFGBY 4 x 25
4 M1 65.00 404,722.15 tidak dikerjakan
mm

5 Penarikan kabel NYY 4x 10 mm dari Panel utama ke panel pembagi M1 35.00 171,077.82 tidak dikerjakan

6 Instalasi Kabel NYM 3 x 2,5 mm² Lampu, dalam pipa konduit 20 mm titik 37.00 289,405.50 tidak dikerjakan

Instalasi Kabel NYM 3 x 2,5 mm² Stop Kontak, dalam pipa konduit 20
7 titik 26.00 305,961.60 tidak dikerjakan
mm
8 Pekerjaan Armatur Listrik
- Lampu Down Light PLC 18 W BH 5.00 244,403.62 tidak dikerjakan
- Lampu LP HARR HLG 120 W BH 24.00 722,573.62 tidak dikerjakan
- Lampu LB T5 2X18 W BH 8.00 540,413.62 tidak dikerjakan
- Saklar Seri setara broco BH 7.00 183,353.62 tidak dikerjakan
- Saklar Tunggal setara broco BH 2.00 210,941.62 tidak dikerjakan
- Stop Kontak, 220 V, 1-ph, 10 A setara broco BH 14.00 210,941.62 tidak dikerjakan
- Stop Kontak AC, setara broco BH 3.00 430,193.62 tidak dikerjakan
- Mesin Pompa Air Kotor Ke Ipal + Instalasi BH 1.00 9,600,000.00 tidak dikerjakan
-
JUMLAH HARGA PEK. ELEKTRIKAL -

TOTAL JUMLAH PEKERJAAN MEKANIKAL &ELEKTRIKAL 58,799,366.96

VII. PEKERJAAN PENUNJANG


A. PEKERJAAN SALURAN DAN PERKERASAN
1 Pekerjaan galian tanah saluran M3 23.40 135,398.01 3,168,313.43
2 Pekerjaan urugan pasir saluran M3 2.93 332,283.20 971,928.37
3 Pekerjaan lantai kerja saluran M3 2.93 1,196,449.20 3,499,613.92
4 Pekerjaan dinding saluran pasangan bata m2 163.80 157,468.49 25,793,338.17
5 Pekerjaan Plesteran dinding saluran m2 198.90 102,698.31 20,426,693.86
6 Pekerjaan Acian dinding saluran m2 198.90 62,423.35 12,416,004.32
7 Pekerjaan pipa PVC dia.4' crosingan ke saluran m1 45.00 254,993.26 tidak dikerjakan
8 Pekerjaan Kanstinn m1 89.00 211,143.70 tidak dikerjakan
9 Pekerjaan urugam Sirtu M3 51.05 341,002.43 tidak dikerjakan
10 Pekerjaan Lantai kerja BO. M3 51.05 1,196,449.20 tidak dikerjakan
11 Pekerjaan Perkerasan beton K.350 t. 15 cm
a. Plastik cor M2 510.50 25,000.00 tidak dikerjakan
b. Pembesian Kg 4,900.80 15,433.43 tidak dikerjakan
c. Beton M3 76.58 1,296,830.87 tidak dikerjakan
d. Bekisting M2 76.58 204,592.96 tidak dikerjakan
12 Galian tanah sumur resapan m3 17.60 135,398.01 tidak dikerjakan
13 Pemasangan sumur resapan dia. 1m + asesoris+ tutup titik 16.00 1,350,000.00 tidak dikerjakan
14 Pemasangan pipa crosingan pipa PVC dia. 4" m1 24.00 254,993.26 tidak dikerjakan

JUMLAH HARGA PERKERASAN HALAMAN 66,275,892.07


B. PEKERJAAN POS JAGA
Pek. Galian dan Pondasi
1 Galian Pondasi m3 4.26 135,398.01 tidak dikerjakan

Page 59 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.61 332,283.20 tidak dikerjakan
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.61 1,174,494.55 tidak dikerjakan
4 Pemasangan pondasi batu belah campuran 1SP : 6PP m3 2.74 1,177,216.15 tidak dikerjakan
5 Sloof Atas Pondasi 15/20
a. Pembesian Kg 107.25 15,433.43 tidak dikerjakan
b. Beton M3 0.49 1,387,961.89 tidak dikerjakan
c. Bekisting M2 8.67 204,592.96 tidak dikerjakan
6 Urug kembali bekas Galian pondasi m3 1.42 88,109.64 tidak dikerjakan

Pek. Pasangan dan Beton


1 Cor kolom praktis K-100 type Kp 12 x 12 cm m1 16.80 96,301.37 tidak dikerjakan
2 Pas. Dinding bata ringan t=10 cm dengan MSP m2 22.14 174,510.40 tidak dikerjakan
3 Plesteran dinding dengan MSP m2 44.27 102,698.31 tidak dikerjakan
4 Acian dinding m2 44.27 62,423.35 tidak dikerjakan
5 Plat beton tebal 8 cm
a. Pembesian Kg 195.80 15,433.43 tidak dikerjakan
b. Beton K.250 m3 0.82 1,387,961.89 tidak dikerjakan
c. Bekisting M2 4.60 204,592.96 tidak dikerjakan
6 pekerjaan balok beton Uk 15x25 cm
a. Pembesian Kg 195.80 15,433.43 tidak dikerjakan
b. Beton K.250 m3 0.49 1,387,961.89 tidak dikerjakan
c. Bekisting M2 4.60 336,279.13 tidak dikerjakan
7 Plat Dak beton tebal 12 cm
a. Pembesian Kg 195.80 15,433.43 tidak dikerjakan
b. Beton K.250 m3 1.23 1,387,961.89 tidak dikerjakan
c. Bekisting M2 4.60 375,989.13 tidak dikerjakan
8 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 13.23 232,044.12 tidak dikerjakan
9 Pas. Kusen + Daun Pintu Type P1 Lengkap unit 1.00 12,272,681.90 tidak dikerjakan
10 Pas. Kusen + Daun Jendela Type J1 Lengkap unit 1.00 7,090,018.27 tidak dikerjakan
11 Pas. Kusen + Daun Jendela Type J2 Lengkap unit 1.00 4,749,922.61 tidak dikerjakan
14 Kalsiplank 8/300 m' 15.20 227,823.28 tidak dikerjakan

Pek. Finishing dan Water Proffing


1 Pengecatan Dinding dalam m2 22.14 52,563.26 tidak dikerjakan
2 Pengecatan dinding luar m2 22.14 61,536.62 tidak dikerjakan
3 Pengecatan Plafond m2 5.56 52,563.26 tidak dikerjakan

Pek. Mekanikal dan Elektrikal


1 Instalasi penerangan titik 2.00 289,405.50 tidak dikerjakan
2 Instalasi stop kontak titik 1.00 305,961.60 tidak dikerjakan
3 Saklar Doubel buah 1.00 183,353.62 tidak dikerjakan
4 Stop Kontak buah 1.00 210,941.62 tidak dikerjakan
5 Down Light LED BULB E27 7 W buah 2.00 244,403.62 tidak dikerjakan
6 Pipa Air Pembuangan Air Hujan dia 3" m' 5.00 186,986.13 tidak dikerjakan

JUMLAH HARGA PERKERASAN POS JAGA -

C. PEKERJAAN PEMAGARAN
1 Galian Pondasi m3 200.45 135,398.01 27,140,260.31
2 Urugan Pasir Bawah Pondasi h=5 cm m3 8.35 332,283.20 2,775,229.32
3 Urugan tanah kembali m3 66.82 88,109.64 5,887,133.75
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 89.25 1,177,216.15 105,066,541.39
5 Sloof Atas Pondasi 20/30 - -
a. Pembesian Kg 2,338.56 15,433.43 tidak dikerjakan
b. Beton K.250 m3 11.14 1,387,961.89 tidak dikerjakan
c. Bekisting M2 111.36 204,592.96 tidak dikerjakan
6 Pagar panel Precas m1 185.60 768,747.63 tidak dikerjakan
JUMLAH HARGA PEMAGARAN 140,869,164.76

D. PEKERJAAN GAPURA DAN PINTU GERBANG


1 Galian Pondasi m3 2.40 135,398.01 tidak dikerjakan
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.10 332,283.20 tidak dikerjakan
3 Urugan tanah kembali m3 0.80 88,109.64 tidak dikerjakan
4 Lantai kerja pondasi setapak m3 0.05 1,174,494.55 tidak dikerjakan
5 Pekerjaan Pondasi setapak 0,6x0,6x0,2
a. Pembesian Kg 33.12 15,433.43 tidak dikerjakan
b. Beton K.250 m3 0.14 1,387,961.89 tidak dikerjakan
c. Bekisting M2 0.96 204,592.96 tidak dikerjakan
6 Pekerjaan Kolom pedestal uk. 25x25 cm
a. Pembesian Kg 26.25 15,433.43 tidak dikerjakan

Page 60 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


b. Beton K.250 m3 0.13 1,387,961.89 tidak dikerjakan
c. Bekisting M2 2.00 331,989.13 tidak dikerjakan
7 Pekerjaan Kolomf uk. 25x25 cm
a. Pembesian Kg 210.00 15,433.43 tidak dikerjakan
b. Beton K.250 m3 1.00 1,387,961.89 tidak dikerjakan
c. Bekisting M2 16.00 331,989.13 tidak dikerjakan
8 Pekerjaan Balok uk. 30x60 cm
a. Pembesian Kg 316.80 15,433.43 tidak dikerjakan
b. Beton K.250 m3 1.44 1,387,961.89 tidak dikerjakan
c. Bekisting M2 9.60 336,279.13 tidak dikerjakan
9 Pekerjaan Plat lantai t. 12 cm
a. Pembesian Kg 158.40 15,433.43 tidak dikerjakan
b. Beton K.250 m3 0.72 1,387,961.89 tidak dikerjakan
c. Bekisting M2 6.00 52,400.37 tidak dikerjakan
10 Pekerjaan Kolom praktis M1 4.00 96,301.37 tidak dikerjakan
11 Pekerjaan Ring balok m1 20.00 139,828.16 tidak dikerjakan
12 Pekerjaan Pasangan bata ringan m2 12.00 174,510.40 tidak dikerjakan
13 Pekerjaan Plesteran m2 12.00 102,698.31 tidak dikerjakan
14 Pekerjaan Acian m2 12.00 62,423.35 tidak dikerjakan
15 Pekerjaan Pengecetan m2 12.00 61,536.62 tidak dikerjakan
16 Pekerjaan Papan Nama Stenliss t. 15 cm bh 65.00 155,000.00 tidak dikerjakan
17 Pekerjaan Logo unit 1.00 4,500,000.00 tidak dikerjakan
18 Pekerjaan Instalasi Penerangan titik 3.00 289,405.50 tidak dikerjakan
19 Pekerjaan Lampu tembak bh 3.00 585,953.62 tidak dikerjakan
20 Pekerjaan Pintu Gerbang rangka besi pipa terpasang + finis cat m2 16.00 1,150,000.00 tidak dikerjakan

JUMLAH HARGA GAPURA PINTU GERBANG -

E. PEKERJAAN RUMAH LOKER KM UMUM


1 Galian Pondasi m3 5.58 135,398.01 755,520.90
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.93 332,283.20 309,023.38
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.93 1,174,494.55 1,092,279.93
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 5.58 1,177,216.15 6,568,866.12
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 195.30 15,433.43 3,014,148.00
b. Beton M3 0.93 1,387,961.89 1,290,804.56
c. Bekisting M2 12.40 204,592.96 2,536,952.70
6 Urug kembali bekas Galian pondasi m3 1.86 88,109.64 163,883.93
-
Pek. Pasangan dan Beton -
8 Pas. Dinding bata ringan t=10 cm dengan MSP m2 82.02 174,510.40 14,313,342.88
9 Plesteran dinding dengan MSP m2 164.04 102,698.31 16,846,630.77
10 Acian dinding m2 164.04 62,423.35 10,239,926.33
11 Plat beton diatas tanah tebal 10 cm -
a. Pembesian Kg 457.28 15,433.43 7,057,319.64
b. Beton m3 3.52 1,387,961.89 4,882,155.96
c. Bekisting M2 2.70 204,592.96 552,400.99
d. Plastik cor m2 35.18 25,000.00 879,375.00
12 Pekerjaan beton kolom 12/12
a. Pembesian Kg 101.61 15,433.43 1,568,134.80
b. Beton m3 0.48 1,387,961.89 671,551.48
c. Bekisting M2 16.13 331,989.13 5,354,320.69
13 Pekerjaan beton Ring Balok 15/25
a. Pembesian Kg 244.13 15,433.43 3,767,685.00
b. Beton m3 1.16 1,387,961.89 1,613,505.70
c. Bekisting M2 15.50 336,279.13 5,212,326.52
14 Pekerjaan Plat beton t. 12 cm
a. Pembesian Kg 790.02 15,433.43 12,192,714.80
b. Beton m3 4.16 1,387,961.89 5,771,145.55
c. Bekisting M2 35.70 336,279.13 12,005,164.94
15 Pasangan lantai Homogenus 40/40 m2 31.01 312,260.38 tidak dikerjakan
16 Pasang Plafond GRC + Rangka Hollow m2 12.00 241,482.54 tidak dikerjakan
17 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 19.01 232,044.12 tidak dikerjakan
18 Pekerjaan Kusen P.1 unit 2.00 12,272,681.90 tidak dikerjakan
19 Pekerjaan Kusen P.4 unit 3.00 2,821,220.31 tidak dikerjakan
20 Pekerjaan Kusen BV.1 unit 3.00 525,191.12 tidak dikerjakan
21 Pekerjaan Kusen J.2 unit 2.00 4,749,922.61 tidak dikerjakan
-
Pek. Finishing dan Water Proffing -
22 Pengecatan Dinding dalam m2 82.02 52,563.26 tidak dikerjakan

Page 61 of 162
BILL OF QUANTITY

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


23 Pengecatan dinding luar m2 82.02 61,536.62 tidak dikerjakan
24 Pengecatan Plafond m2 31.01 52,563.26 tidak dikerjakan
-
Pek. Mekanikal dan Elektrikal -
25 Instalasi penerangan titik 7.00 289,405.50 tidak dikerjakan
26 Instalasi stop kontak titik 3.00 305,961.60 tidak dikerjakan
27 Saklar Doubel buah 2.00 183,353.62 tidak dikerjakan
28 Stop Kontak buah 4.00 210,941.62 tidak dikerjakan
29 Down Light LED BULB E27 7 W buah 7.00 244,403.62 tidak dikerjakan
30 Pipa Air Pembuangan Air Hujan dia 3" m' 15.00 186,986.13 2,804,791.97
31 - Instalasi Pipa Air Kotor 3 " PVC m' 12.00 186,986.13 2,243,833.57
32 - Instalasi Pipa Air Kotor 2" PVC m' 12.00 52,965.47 635,585.68
33 - Instalasi Pipa Air Kotor 4 " PVC m' 15.00 184,010.64 2,760,159.53
34 - Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Unit 1.00 18,000,000.00 18,000,000.00
35 Pemasangan Closet duduk + asesoris BH 3.00 3,552,619.84 tidak dikerjakan
36 Pasang Head Shower+fleksibel Komplit 1 buah BH 3.00 366,906.61 tidak dikerjakan
37 Pasang Jet Shower+fleksibel Komplit 1 buah BH 3.00 324,666.61 tidak dikerjakan
38 Pemasangan Kran air BH 3.00 187,386.61 tidak dikerjakan
39 pemasangan Floor drain BH 3.00 155,152.21 tidak dikerjakan
40 Sumur pantek + pompa + Rumah pompa lengkap kunci Unit 1.00 13,500,000.00 tidak dikerjakan
41 tangki air kap 1,2m3 Unit 1.00 1,650,000.00 tidak dikerjakan
42 Switch otomatis Unit 1.00 427,333.23 tidak dikerjakan

JUMLAH PEKERJAAN RUMAH LOKER UMUM 145,103,551.32

Page 62 of 162
REKAP ENGGINERING ESTIMAT
URUSAN PEMERINTAHAN: 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019 / Lingkup Hidup

No. URAIAN PEKERJAAN JUMLAH HARGA TOTAL HARGA

I. PEKERJAAN PERSIAPAN 77,012,454.14 77,012,454.14


II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON 701,601,343.40 701,601,343.40
III. PEKERJAAN KONTRUKSI BAJA 320,882,511.65 320,882,511.65
IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP 439,840,899.31 439,840,899.31
V. PEKERJAAN ARSITEKTUR 498,588,679.03
A. PEKERJAAN PASANGAN DINDING 248,589,058.55
B. PEKERJAAN PASANGAN LANTAI -
C. PEKERJAAN PASANGAN PLAFOND -
D. PEKERJAAN KUSEN, PINTU DAN JENDELA 243,522,516.16
E. PEKERJAAN SANITAIR 6,477,104.32
F. PEKERJAAN PENGECETAN -
VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL 185,510,432.69
A. PEKERJAAN MEKANIKAL 65,210,990.72

VII. PEKERJAAN PENUNJANG 256,619,809.44


A. PEKERJAAN SALURAN DAN PERKERASAN 38,020,553.46
C. PEKERJAAN PEMAGARAN -
E. PEKERJAAN RUMAH LOKER KM UMUM 218,599,255.97

JUMLAH HARGA 2,480,056,129.65


PPN 10 % 248,005,612.96
Penyambungan daya baru dan perizinan ke PLN daya 10.600 watt 26,500,000.00
TOTAL HARGA 2,754,561,742.61
DIBULATKAN 2,754,561,000.00
TERBILANG : DUA MILYARD TUJUH RATUS LIMA PULUH EMPAT JUTA LIMA RATUS ENAM PULUH SATU RIBU RUPIAH

Jakarta, April 2019

Menyetujui :
Dibuat oleh :
Kepala Suku Dinas Cipta Karya
Tata ruang dan Pertanahan Konsultan Perencana
Kota Administrasi Jakarta Utara

KUSNADI HADIPRATIKNO, ST.MM Paruntungan Napitupulu, ST


NIP : 196405301985081001 Tenaga Ahli
Mengetahui :

Kuasa Pengguna Anggaran


Suku Dinas Lingkungan Hidup
Kota Administrasi Jakarta Utara
Selaku
Pejabat Pembuat Komitmen

SLAMET RIYADI, S.Sos, Msi


NIP : 197111191991011001
BILL OF QUANTYTI ENGGINERING ESTIMAT
URUSAN PEMERINTAHAN: 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019 / Lingkup Hidup

No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA


I. PEKERJAAN PERSIAPAN
1 Papan Nama Proyek bh 1.00 600,000.00 600,000.00
2 Pek. Pengukuran dan bowplang m1 116.00 87,707.10 10,174,023.95
3 Alat bantu erektion baja ls 1.00 7,500,000.00 7,500,000.00
4 Kantor Direksi Keet m2 9.00 1,932,158.91 17,389,430.19
5 Pengadaan Sumber Air Kerja ls 1.00 6,000,000.00 6,000,000.00
6 Pengadaan Listrik Kerja ls 1.00 5,000,000.00 5,000,000.00
7 foto dokumentasi dan Pembuatan Asbuildrawing shop drawing Ls 1.00 3,500,000.00 3,500,000.00
8 Biaya SMK3 set 1.00 21,849,000.00 21,849,000.00
9 Pembersihan Lokasi Ls 1.00 5,000,000.00 5,000,000.00
JUMLAH HARGA PEK. I 77,012,454.14
II. PEKERJAAN PONDASI, SLOOF DAN KOLOM BETON
1 Pengadaan tiang pancang Square 25x25cm M1 504.00 289,100.00 145,706,400.00
2 Pemancangan Menggunakan Hydraulic (Jacking Pile) M1 504.00 92,301.41 46,519,909.13
3 Pemotongan kepala tiang pancang Titik 28.00 128,660.68 3,602,498.90
4 Handling dan Joint Titik 56.00 75,000.00 4,200,000.00
5 Pek. Test tekan tiang pancang PDA Titik 2.00 8,000,000.00 16,000,000.00
6 Pekerjaan Galian tanah M3 21.44 135,398.01 2,903,474.93
7 Urugan tanah kembali M3 6.86 48,694.36 334,140.70
8 urugan tanah baru peninggian M3 343.00 215,859.20 74,039,706.97
9 Pekerjaan urugan pasir t. 5 cm M3 2.62 332,283.20 871,246.56
10 Pekerjaan lantai kerja t. 5 cm pondasi dan sloof M3 2.70 1,196,449.20 3,226,823.50
11 Pekerjaan pondasi batu adukan 1pc : 6 ps kali sisi belakang M3 48.30 1,177,216.15 56,859,540.05
12 Pekerjaan Sloff Diatas batu kali 15 x 30 cm
a. Pembesian Kg 456.39 15,433.43 7,043,661.05
b. Beton K.250 M3 2.07 1,251,781.91 2,596,821.56
c. Bekisting M2 27.66 204,592.96 5,659,041.27
13 Pekerjaan Pondasi TIE BEAM uk. 1,3 m x 0,6 mx 0,6 m
a. Pembesian Kg 968.76 15,433.43 14,951,285.27
b. Beton K.250 M3 4.21 1,251,781.91 5,272,505.38
c. Bekisting M2 20.52 204,592.96 4,198,247.54
14 Pekerjaan Pondasi TIE BEAM uk. 0,65 m x 0,6 mx 0,6 m
a. Pembesian Kg 514.80 15,433.43 7,945,127.44
b. Beton K.250 M3 2.34 1,251,781.91 2,929,169.66
c. Bekisting M2 15.00 204,592.96 3,068,894.40
15 Pekerjaan Sloff SL.1 20 x 40 cm
a. Pembesian Kg 1,449.60 15,433.43 22,372,293.58
b. Beton K.250 M3 7.25 1,251,781.91 9,072,915.25
c. Bekisting M2 72.48 204,592.96 14,828,897.74
16 Pekerjaan Sloff SL.2 15 x 30 cm
a. Pembesian Kg 609.53 15,433.43 9,407,058.67
b. Beton K.250 M3 2.90 1,251,781.91 3,633,296.98
c. Bekisting M2 38.70 204,592.96 7,917,747.55
17 Pekerjaan Kolom Pedestal Uk. 24 x 34 cm
a. Pembesian Kg 359.04 15,433.43 5,541,217.08
b. Beton K.250 M3 1.63 1,251,781.91 2,042,908.07
c. Bekisting M2 27.60 331,989.13 9,162,899.99
18 Pekerjaan Kolom Pedestal Uk. 30 x 30 cm dudukan mesin
a. Pembesian Kg 237.60 15,433.43 3,666,981.89
b. Beton K.250 M3 1.08 1,251,781.91 1,351,924.46
c. Bekisting M2 10.00 331,989.13 3,319,891.30
19 Pekerjaan plat lantai dasar t. 10 cm
a. Pembesian warmes M.8 Kg 4,649.05 15,433.43 71,750,786.71
b. Beton K.250 M3 32.27 1,251,781.91 40,395,502.79
c. Bekisting M2 5.36 204,592.96 1,096,618.27
d. Plastik cor M2 520.29 21,000.00 10,926,090.00
20 Pekerjaan plat lantai 2 t. 12 cm
a. Pembesian warmes M.10 Kg 567.40 15,433.43 8,756,991.21
b. Beton K.250 M3 7.62 1,251,781.91 9,538,578.12
c. Bekisting plat bondeks M2 63.50 198,638.39 12,613,537.73
d. Bekisting kayu (pinggiran) M2 5.40 204,592.96 1,104,801.98
21 Pekerjaan beton plat tangga
a. Pembesian Kg 240.24 15,433.43 3,707,726.14
b. Beton K.250 M3 1.09 1,251,781.91 1,366,945.84
c. Bekisting M2 9.10 336,279.13 3,060,140.08
22 Pekerjaan beton plat bordes tangga
a. Pembesian Kg 77.06 15,433.43 1,189,361.50
b. Beton K.250 M3 0.41 1,251,781.91 507,722.74
c. Bekisting M2 3.38 375,989.13 1,270,843.26
23 Pekerjaan beton anak tangga
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
a. Pembesian Kg 105.59 15,433.43 1,629,653.98
b. Beton K.250 M3 0.56 1,251,781.91 695,677.79
c. Bekisting M2 1.69 375,989.13 635,421.63
24 Pekerjaan beton ram pintu akses
a. Pembesian Kg 260.83 15,433.43 4,025,531.23
b. Beton K.250 M3 1.37 1,251,781.91 1,718,446.20
c. Bekisting M2 11.44 375,989.13 4,301,315.65
25 Pekerjaan kolom praktis M1 112.00 96,301.37 10,785,753.69
26 Pekerjaan Balok Intel M1 73.50 139,828.16 10,277,370.00

JUMLAH HARGA PEK. II 701,601,343.40

III. PEKERJAAN KONTRUKSI BAJA


1 Pekerjaan Angkur d. 19 Bh 124.00 50,000.00 6,200,000.00
2 Pekerjaan Base plat t. 20 mm Kg 309.00 38,670.72 11,949,187.35
3 Tiang kolom baja WF 250.125.6 Kg 2,758.72 38,670.72 106,681,682.61
4 Balok B.1 baja WF 250.125.6 Kg 1,518.48 38,670.72 58,720,711.56
5 Balok B.2 baja WF200.100.5.8 Kg 1,561.60 38,670.72 60,388,192.92
6 Balok B.3 baja WF 150.75.4.8 Kg 412.59 38,670.72 15,955,022.55
7 Pekerjaan Voute sambungan kolom balok Kg 264.24 38,670.72 10,218,350.47
8 Pekerjaan plat t. 12 mm sambungan Kg 722.17 38,670.72 27,926,703.37
9 Baut A325 Ø 16 mm Bh 288.00 21,000.00 6,048,000.00
10 Pengectan Kontruksi baja + zingkromat m2 301.87 55,635.10 16,794,660.81
JUMLAH HARGA PEK. III 320,882,511.65

IV. PEKERJAAN KONTRUKSI BAJA RANGKA ATAP


1 Pekerjaan Kuda-kuda WF250.125.6 Kg 1,855.92 38,670.72 71,769,758.58
2 Pekerjaan plat sambungan t. 12 mm Kg 663.54 38,670.72 25,659,632.54
3 Pekerjaan stifner plat t. 10 mm Kg 204.17 38,670.72 7,895,271.55
4 Pekerjaan Rangka Atap Besi Canal C uk.150.65.20.2,3 Kg 4,431.83 38,670.72 171,381,918.37
5 Plat dudukan Canal t. 8 mm Kg 171.42 38,670.72 6,628,805.54
6 Pek braccing besid. 10 Kg 116.00 38,670.72 4,485,744.49
7 Pek. Trestang besi ulir d. 13 + watermur Kg 212.89 38,670.72 8,232,660.47
8 Baut A325 Ø 16 mm Bh 124.00 21,000.00 2,604,000.00
9 Pengectan Kontruksi baja + zingkromat M2 306.23 55,635.10 17,037,162.67
10 Pekerjaan water mur M.10 BH 212.89 15,000.00 3,193,369.92
11 Pekerjaan Penutup Atap Spandek t=05 mm M2 582.23 207,740.20 120,952,575.19
JUMLAH HARGA PEK. IV 439,840,899.31

V. PEKERJAAN ARSITEKTUR
A. PEKERJAAN PASANGAN DINDING
1 Pas. Bata ringan / Hebel M2 465.91 174,510.40 81,305,528.93
2 Plesteran Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 102,698.31 95,695,620.34
3 Acian Dinding Hebel/Celcon dengan Mortar Instan M2 931.81 62,423.35 58,166,889.03
4 Plesteran Openingan Kusen dengan Mortar Instan M1 215.00 62,423.35 13,421,020.25
JUMLAH HARGA PEK. VA. 248,589,058.55

B. PEKERJAAN PASANGAN LANTAI


C. PEKERJAAN PASANGAN PLAFOND

D. PEKERJAAN KUSEN, PINTU DAN JENDELA


1 Pekerjaan Kusen P.1 Unit 2.00 12,272,681.90 24,545,363.81
2 Pekerjaan Kusen P.2 Unit 1.00 15,974,150.71 15,974,150.71
3 Pekerjaan Kusen P.3 Unit 3.00 4,588,656.13 13,765,968.39
4 Pekerjaan Kusen P.4 Unit 3.00 2,821,220.31 8,463,660.94
5 Pekerjaan Kusen P.5 Unit 1.00 3,516,546.62 3,516,546.62
6 Pekerjaan Kusen J.1 Unit 2.00 7,090,018.27 14,180,036.54
7 Pekerjaan Kusen J.2 Unit 9.00 4,749,922.61 42,749,303.50
8 Pekerjaan Kusen J.3 Unit 6.00 4,718,627.57 28,311,765.45
9 Pekerjaan Kusen J.4 Unit 7.00 6,609,092.05 46,263,644.32
10 Pekerjaan Kusen J.5 Unit 3.00 3,485,977.63 10,457,932.89
11 Pekerjaan Kusen J.6 Unit 7.00 4,516,829.31 31,617,805.18
12 Pekerjaan Kusen BV.1 Unit 4.00 525,191.12 2,100,764.47
13 Pekerjaan Kusen BV.2 Unit 1.00 1,575,573.35 1,575,573.35

JUMLAH HARGA PEK. V D. 243,522,516.16

E. PEKERJAAN SANITAIR
1 Pemasangan Closet duduk + asesoris BH 1.00 3,552,619.84 3,552,619.84
2 PemasanganUrinoir + asesoris BH 1.00 1,433,514.94 1,433,514.94
3 Pemasangan wastafel BH 1.00 1,148,430.72 1,148,430.72
4 Pemasangan Kran air BH 1.00 187,386.61 187,386.61
5 pemasangan Floor drain BH 1.00 155,152.21 155,152.21
JUMLAH HARGA PEK. V E. 6,477,104.32
F. PEKERJAAN PENGECETAN
TOTAL JUMLAH PEKERJAAN ARSITEKTUR 498,588,679.03
VI. PEKERJAAN MEKANIKAL DAN ELEKTRIKAL
A. PEKERJAAN MEKANIKAL
1 Pekerjaan Instalasi Air Kotor
- Instalasi Pipa Air Kotor 3 " PVC M1 15.00 186,986.13 2,804,791.97
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
- Instalasi Pipa Air Kotor 2" PVC M1 25.00 142,169.76 3,554,244.05
- Instalasi Pipa Air Kotor 4 " PVC M1 38.00 248,429.76 9,440,330.95
- Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Titik 1.00 12,000,000.00 12,000,000.00
- Bio Septictank Kapasitas 3 m3 + Instalasi + Dudukan Titik 1.00 22,000,000.00 22,000,000.00

PEKERJAAN PEMIPAAN
Pemipaan Air Bersih
a. Pipa PPR PN 16
dia. 1 1/2" m 12.00 203,835.60 2,446,027.15
dia. 1 1/4" m 12.00 173,475.60 2,081,707.15
dia. 1/2" m 14.00 74,805.60 1,047,278.34
b. Gate Valve dia. 11/2 bh 3.00 237,583.23 712,749.68
c. Elbow
dia. 1/2" bh 21.00 131,323.23 2,757,787.73
dia 1 1/2" bh 4.00 389,383.23 1,557,532.90
dia 1 1/4" bh 8.00 305,893.23 2,447,145.80
d. Tee
dia. 1 1/2" x 1 1/2" x 1 1/2" bh 3.00 69,085.23 207,255.68
dia. 1 1/4" x 1 1/4" x 1 1/4" bh 3.00 290,713.23 872,139.68
Soket dia. 1 1/2" x 1 1/4" bh 3.00 427,333.23 1,281,999.68

JUMLAH HARGA PEK. MEKANIKAL 65,210,990.72

B. PEKERJAAN ELEKTRIKAL
1 Panel Utama LDP lengkap terpasang dengan MCB Unit 1.00 30,000,000.00 30,000,000.00
2 panel pembagi Unit 2.00 4,500,000.00 9,000,000.00
3 Penarikan kabel tofer dari gardu keruang panel utama NYFGBY 4 x 25 mm M1 45.00 404,722.15 18,212,496.89
4 Penarikan kabel NYY 4x 10 mm dari Panel utama ke panel pembagi M1 35.00 171,077.82 5,987,723.86
5 Instalasi Kabel NYM 3 x 2,5 mm² Lampu, dalam pipa konduit 20 mm titik 37.00 289,405.50 10,708,003.50
6 Instalasi Kabel NYM 3 x 2,5 mm² Stop Kontak, dalam pipa konduit 20 mm titik 26.00 305,961.60 7,955,001.60
7 Pekerjaan Armatur Listrik
- Lampu Down Light PLC 18 W BH 5.00 244,403.62 1,222,018.11
- Lampu LP HARR HLG 120 W BH 24.00 722,573.62 17,341,766.90
- Lampu LB T5 2X18 W BH 8.00 540,413.62 4,323,308.97
- Saklar Seri setara broco BH 7.00 183,353.62 1,283,475.35
- Saklar Tunggal setara broco BH 2.00 210,941.62 421,883.24
- Stop Kontak, 220 V, 1-ph, 10 A setara broco BH 14.00 210,941.62 2,953,182.69
- Stop Kontak AC, setara broco BH 3.00 430,193.62 1,290,580.86
- Mesin Pompa Air Kotor Ke Ipal + Instalasi BH 1.00 9,600,000.00 9,600,000.00
-
JUMLAH HARGA PEK. ELEKTRIKAL 120,299,441.97

TOTAL JUMLAH PEKERJAAN MEKANIKAL &ELEKTRIKAL 185,510,432.69

VII. PEKERJAAN PENUNJANG


A. PEKERJAAN SALURAN DAN PERKERASAN
Perkerasan sisi depan pintu gerbang k ruang sampah tercampur
9 Pekerjaan urugam Sirtu M3 6.00 341,002.43 2,046,014.61
10 Pekerjaan Lantai kerja BO. M3 6.00 1,196,449.20 7,178,695.23
11 Pekerjaan Perkerasan beton K.350 t. 15 cm
a. Pembesian Kg 768.00 15,433.43 11,852,870.77
b. Beton M3 12.00 1,296,830.87 15,561,970.38
c. Bekisting M2 6.75 204,592.96 1,381,002.48

JUMLAH HARGA PERKERASAN HALAMAN 38,020,553.46


B. PEKERJAAN POS JAGA

C. PEKERJAAN PEMAGARAN

D. PEKERJAAN GAPURA DAN PINTU GERBANG

E. PEKERJAAN RUMAH LOKER KM UMUM


1 Galian Pondasi m3 5.58 135,398.01 755,520.90
2 Urugan Pasir Bawah Pondasi h=5 cm m3 0.93 332,283.20 309,023.38
3 Beton Lantai Kerja Bawah Pondasi (K-100) h=5 cm m3 0.93 1,174,494.55 1,092,279.93
4 Pondasi Pasangan Batu belah campuran 1SP : 4PP m3 5.58 1,177,216.15 6,568,866.12
5 Sloof Atas Pondasi 15/20 -
a. Pembesian Kg 195.30 15,433.43 3,014,148.00
b. Beton M3 0.93 1,387,961.89 1,290,804.56
c. Bekisting M2 12.40 204,592.96 2,536,952.70
6 Urug kembali bekas Galian pondasi m3 1.86 88,109.64 163,883.93
-
Pek. Pasangan dan Beton -
8 Pas. Dinding bata ringan t=10 cm dengan MSP m2 82.02 174,510.40 14,313,342.88
9 Plesteran dinding dengan MSP m2 164.04 102,698.31 16,846,630.77
10 Acian dinding m2 164.04 62,423.35 10,239,926.33
11 Plat beton diatas tanah tebal 10 cm -
a. Pembesian Kg 457.28 15,433.43 7,057,319.64
No. URAIAN PEKERJAAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA
b. Beton m3 3.52 1,387,961.89 4,882,155.96
c. Bekisting M2 2.70 204,592.96 552,400.99
d. Plastik cor m2 35.18 25,000.00 879,375.00
12 Pekerjaan beton kolom 12/12
a. Pembesian Kg 101.61 15,433.43 1,568,134.80
b. Beton m3 0.48 1,387,961.89 671,551.48
c. Bekisting M2 16.13 331,989.13 5,354,320.69
13 Pekerjaan beton Ring Balok 15/25
a. Pembesian Kg 244.13 15,433.43 3,767,685.00
b. Beton m3 1.16 1,387,961.89 1,613,505.70
c. Bekisting M2 15.50 336,279.13 5,212,326.52
14 Pekerjaan Plat beton t. 12 cm
a. Pembesian Kg 790.02 15,433.43 12,192,714.80
b. Beton m3 4.16 1,387,961.89 5,771,145.55
c. Bekisting M2 35.70 336,279.13 12,005,164.94
15 Pasangan lantai Homogenus 40/40 m2 31.01 312,260.38 9,682,413.71
16 Pasang Plafond GRC + Rangka Hollow m2 12.00 241,482.54 2,897,790.46
17 Pasang Plafond gypsumboard T.9 mm + Rangka Hollow m2 19.01 232,044.12 4,410,578.61
18 Pekerjaan Kusen P.3 unit 2.00 4,588,656.13 9,177,312.26
19 Pekerjaan Kusen P.5 unit 3.00 3,516,546.62 10,549,639.85
20 Pekerjaan Kusen BV.1 unit 3.00 525,191.12 1,575,573.35
21 Pekerjaan Kusen J.2 unit 2.00 4,749,922.61 9,499,845.22
-
Pek. Finishing dan Water Proffing -
Pek. Mekanikal dan Elektrikal -
25 Instalasi penerangan titik 7.00 289,405.50 2,025,838.50
26 Instalasi stop kontak titik 3.00 305,961.60 917,884.80
27 Saklar Doubel buah 2.00 183,353.62 366,707.24
28 Stop Kontak buah 4.00 210,941.62 843,766.48
29 Down Light LED BULB E27 7 W buah 7.00 244,403.62 1,710,825.35
30 Pipa Air Pembuangan Air Hujan dia 3" m' 15.00 186,986.13 2,804,791.97
31 - Instalasi Pipa Air Kotor 3 " PVC m' 12.00 186,986.13 2,243,833.57
32 - Instalasi Pipa Air Kotor 2" PVC m' 12.00 52,965.47 635,585.68
33 - Instalasi Pipa Air Kotor 4 " PVC m' 15.00 184,010.64 2,760,159.53
34 - Bio Septictank Kapasitas 2 m3 + Instalasi + Dudukan Unit 1.00 8,500,000.00 8,500,000.00
35 Pemasangan Closet duduk + asesoris BH 3.00 3,552,619.84 10,657,859.52
36 Pasang Head Shower+fleksibel Komplit 1 buah BH 3.00 366,906.61 1,100,719.82
37 Pasang Jet Shower+fleksibel Komplit 1 buah BH 3.00 324,666.61 973,999.82
38 Pemasangan Kran air BH 3.00 187,386.61 562,159.82
39 pemasangan Floor drain BH 3.00 155,152.21 465,456.62
40 Sumur pantek + pompa + Rumah pompa lengkap kunci Unit 1.00 13,500,000.00 13,500,000.00
41 tangki air kap 1,2m3 Unit 1.00 1,650,000.00 1,650,000.00
42 Switch otomatis Unit 1.00 427,333.23 427,333.23

JUMLAH PEKERJAAN RUMAH LOKER UMUM 218,599,255.97


RAB K3 KONSTRUKSI

URUSAN PEMERINTAHAN : 1.11 / Lingkup Hidup


Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019 / Lingkup Hidup

NO URAIAN SAT VOL


1 Penyiapan RK3K terdiri atas
a Pembuatan manual, prosedur, Instruksi Kerja, Ijin Kerja dan Formulir Set 1
b Pembuatan Kartu Identitas Pekerjan (KIP) Lb 50

2 Sosialisasi dan Promosi K3 terdiri atas :


a Induksi K3 org 50
b Pengarahan K3:Pertemuan Keselamatan org 50
c Pelatihan K3 org 3
d Simulasi K3 org 20
e Spanduk Lb 12
f Poster Lb 12
g Papan Informasi K3 bh 4

2 Alat Pelindung Kerja Terdiri atas :


a Jaring Pengaman bh
b Tali Keselamatan bh
a Penahan Jatuh (Jaring pengaman) bh 10
b Pagar Pengaman bh 10
c Pembatas Area bh 5

3 Alat Pelindung Diri Terdiri Atas :


a Topi Pelindung (safety helm) Bh 50
b Tali Keselamatan/Body Hardness Psg 5
f Sepatu Keselamatan (safety boot) Bh 20
g Sarung Tangan (safety gloves) Psg 20
h Rompi Psg 20
i Penunjang Seluruh Tubuh Bh
j Jaket Pelampung Bh
k Rompi Keselamatan Bh
l Celemek Bh
m Pelindung Jatuh Bh

5 Asuransi dan Perijinan Terdiri atas :


a BPJS Ketenagakerjaan dan Kesehatan Kerja Kelas 2 Ls 1
b Siurat Ijin Kelayakan Alat bh 1
c Surat Ijin Operator bh 1
Surat Ijin Pengesahan Panitia Pembina Keselamatan Dan Kesehatan Kerja Ls 1
d
(P2K3)

6 Personil K3 terdiri atas :


a Ahli K3 OB 1
b Petugas K3 OB 1
c Petugas Tanggap Darurat OB
d Petugas P3K OB
e Petugas Pengatur Lalu Lintas OB
f Petugas Medis OB

7 Fasilitas Sarana Kesehatan


a Peralatan P3K (Kotak P3K, Tandu, Tabung Oksigen, Obat Luka, Perban, dll Ls 1
b Ruang P3K (Tempat tidur pasien, Stetoskop, Timbangan berat badan, Tensi Ls
c Peralatan Pengasapan Bh
d Obat Pengasapan Ls

8 Rambu - Rambu terdiri atas :


a Rambu Petunjuk Bh 3
b Rambu Larangan Bh 3
c Rambu Peringatan Bh 3
d Rambu Kewajiban Bh 2
e Rambu Informasi Bh 2
f Rambu Pekerjaan Sementara Bh
g Tongkat Pengatur Lalu Lintas Bh
h Kerucut Lalu Lintas Bh
i Lampu Putar Bh
j Lampu Selang Lalu Lintas Ls

9 Konsultasi Dengan Ahli Keselamatan Konstruksi


a Konsultasi Dengan Ahli Keselamatan Konstruksi ls 1.00

10 Lain - Lain Terkain Pengendalian Risiko K3


a Alat Pemadam Api Ringan (APAR) Bh 1
b Sirine Bh 2
c Bendera K3 Bh 2
d Jalur Evakuasi Ls
e Lampu Darurat Bh
f Program Inspeksi Audit Internal Ls
g Pelaporan dan Penyelidikan Insiden Ls
SI

n Transito sampah

HARGA SATUAN TOTAL HARGA

113,000.00 113,000.00
5,000.00 250,000.00

- -
- -
- -
- -
- -
- -
- -

180,000.00 -
135,000.00 -
45,000.00 450,000.00
45,000.00 450,000.00
36,000.00 180,000.00

30,000.00 1,500,000.00
165,000.00 825,000.00
65,000.00 1,300,000.00
10,000.00 200,000.00
50,000.00 1,000,000.00
150,000.00 -
55,000.00 -
5,000.00 -
50,000.00 -

4,590,000.00 4,590,000.00 7,650,000


500,000.00 500,000.00
500,000.00 500,000.00
1,000,000.00 1,000,000.00

3,300,000.00 3,300,000.00
2,500,000.00 2,500,000.00
2,700,000.00 -
2,700,000.00 -
2,700,000.00 -
2,700,000.00 -

500,000.00 500,000.00
1,800,000.00 -
900,000.00 -
720,000.00 -

41,000.00 123,000.00
41,000.00 123,000.00
41,000.00 123,000.00
41,000.00 82,000.00
41,000.00 82,000.00
41,000.00 -
41,000.00 -
41,000.00 -
41,000.00 -
1,080,000.00 -

1,000,000.00 1,000,000.00

850,000.00 850,000.00
113,000.00 226,000.00
41,000.00 82,000.00
350,000.00 -
120,000.00 -
1,000,000.00 -
1,250,000.00 -

21,849,000.00
HARGA BAHAN ARSITEKTUR DAN STRUKTUR

DAFTAR HARGA UPAH, BAHAN DAN ALAT

URUSAN PEMERINT: 1.11 / Lingkup Hidup


Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

NO URAIAN SATUAN HARGA (Rp.) KET


1 2 3 4 5
A UPAH PEKERJA
1 Mandor Hr 194,274.00
2 Kepala Tukang Hr 182,676.00
3 Tukang Hr 166,729.00
4 Pekerja Hr 157,643.00

B SEWA ALAT
1 Sewa Stamper Jam 75,000.00
2 Sewa Lift barang / goods crane 1 Ton + solar bln 7,500,000.00
3 Pompa dan conveyor beton (sewa) hari 1,500,000.00
4 Mesin Wales jam 250,000.00
5 Chain Block jam 250,000.00
6 Hydraulic jack jam 600,000.00

C MATERIAL
AGREGAT KASAR, BAHAN PEREKAT DAN
BAHAN JADINYA
1 Pasir Urug m3 210,700.00
2 Pasir Pasang m3 259,700.00
3 Pasir Beton Muntilan m3 274,400.00
4 Pasir Beton Muntilan Kg 196.00
5 Sirtu m3 235,200.00
6 Tanah Urug m3 122,500.00
7 Batu Belah m3 254,800.00
8 Batu Pecah 5/7 m3 240,100.00
9 Batu Pecah 3/5 m3 240,100.00
10 Batu Pecah Mesin/Stenslah 1/2 m3 249,900.00
11 kerikil Kg 185.11
12 Batu Pecah Mesin/Stenslah 2/3 m3 249,900.00
13 Bata Merah klas 1 bj 637.00
14 Bata Ringan Tb.7,5 cm bj 15,680.00
15 Bata Ringan Tb.10 cm bj 10,584.42
16 Beton Ready Mix (K-250) m3 823,200.00
17 Beton Ready Mix (K-350) m3 907,480.00
18 Portland Cement (PC) @ 50 kg zak 73,500.00
19 Portland Cement (PC) @ 50 kg kg 1,470.00
20 Semen Warna Kg 2,058.00
21 Mortar Siap Pakai kg 3,797.50
22 Minyak bekisting ltr 3,430.00
23 Air ltr 196.00
24 Floor harderner Kg 83,300.00
25 Membran bakar m2 122,500.00
26 Pondasi Jaring Rusuk Beton Pasak Vertikal (JRBPV) m2 122,500.00
27 Pagar Panel beton Precas Lbr 230,300.00
28 Tiang kolom pagar t. 3 m btg 401,800.00
29 Tiang pancang square 25x25 cm , beton k. 500 M1 289,100.00
30 Pemancangan mesin jeking pile hidrolit M1 73,500.00

Page 74 of 162
HARGA BAHAN ARSITEKTUR DAN STRUKTUR

NO URAIAN SATUAN HARGA (Rp.) KET


31 Kst. DKI, 15.30.40, K-300 Warna abu-abu bh 63,700.00
32 Sirtu m3 245,000.00
33 Tanah merah super m3 -

BAHAN KAYU DAN BAHAN JADI LAINNYA


1 Kayu papan meranti (2/20) m3 3,450,000.00
2 Kayu balok meranti (6/12) m3 2,950,000.00
3 Kayu balok meranti (5/7) m3 2,950,000.00
4 Kayu papan kruing (2/20) m3 1,300,000.00
5 Kayu balok kruing (5/7) m3 1,300,000.00
6 Kayu Papan (bekisting 2/20 ) m3 1,050,000.00
7 Kayu Kamper Usuk m3 1,900,000.00
8 Kayu Kamper reng (balok 3/5) m3 2,850,000.00
9 Kayu Kamper Papan m3 4,500,000.00
10 Dolken kayu gelam 5 x 10 x 400 cm btg 10,000.00
11 Plywood 120 cm x 240 cm x 9 mm m2 105,000.00
12 Plywood 120 cm x 240 cm x 4 mm m2 85,000.00
13 Serat fiber m2 25,000.00
14 Gypsumboard, t = 9 mm ex. Jayaboard Lembar 108,000.00
15 GRC board, t = 6 mm versaboard Lembar 108,000.00
16 Plywood 120 cm x 240 cm x 12 mm Lembar 225,000.00
17 hpl m2 110,000.00
18 Plywood 18 mm Lembar 325,000.00
19 Bambu dia 6-8 / 600 cm btg 22,000.00
20 Tali Ijuk kg 15,000.00
21 Plastik cor

BAHAN BAJA, BESI DAN PAKU


1 Besi Beton Polos (Besi BJTP-24) kg 10,584.00
2 Besi Beton Ulir (Besi BJTP-39) kg 10,780.00
3 Kawat Beton/ Bendrat kg 29,400.00
4 Kawat las kg 240,100.00
5 Besi baja profil WF kg 12,740.00
6 Besi baja profil kanal C kg 12,740.00
7 Besi baja siku kg 12,740.00
8 Besi plat kg 12,250.00
9 Besi baja Black Steel Pipe (BSP) kg 12,250.00
10 Rangka Metal stud btg 63,700.00
11 Rangka plafond hollow m2 112,700.00
12 Besi Hollow 40x40x2mm m' 15,925.00
13 Besi Hollow 20/40x0,9 Lonjor 11,025.00
14 Baut HTB Ø 10 - 16 mm bh 14,700.00
15 Jarum keras / Turnbuckle bh 11,760.00
16 Paku kayu 2-3" kg 28,420.00
17 Paku kayu 2" kg 28,420.00
18 Paku Sekrup Kg 28,420.00
19 Elektrode Baja kg 12,740.00
20 Plat galvalum M2 122,500.00
21 Sunscreen/Kisi-kisi aluminium M2 441,000.00
22 Folding gate standar tbl 0,4 mm M2 539,000.00
23 Rolling door M2 735,000.00
24 Jaring kawat baja dilas kg 9,310.00
25 Seng gelombang 3"-5" Lbr 181,300.00
26 Seng Plat m' 34,300.00
27 Kawat duri m' 24,500.00
28 Kawat jaring lbr 93,100.00
29 Jendela nako bh 441,000.00
30 Dynabolt M8 bh 20,000.00
31 Plat bondeks , 0,75 mm m2 125,000.00

Page 75 of 162
HARGA BAHAN ARSITEKTUR DAN STRUKTUR

NO URAIAN SATUAN HARGA (Rp.) KET


BAHAN PENUTUP LANTAI DAN DINDING
1 Keramik 40 x 40 m2 156,750.00
2 Keramik 20 x 40 m2 147,250.00
3 Keramik 20 x 20 m2 147,250.00
4 Keramik 25 x 50 m2 185,250.00
5 Granit tile 30 x 60 cm m2 204,250.00
6 Homogenus tile 60 x 60 niro granite GEA00/Elda m2 237,500.00
7 Homogenus tile 60x60 niro granite GSN02 m2 209,000.00
8 ACP (Alumunium Composite Panel) m2 237,500.00
9 HPL 120x240 cm Lbr 104,500.00
10 Wallpaper m2 42,750.00
11 Lem Kg 23,750.00
12 Lem Wallpaper bungkus 19,950.00
13 Lemkra TG 301 ltr
25,000.00
14 Lemkra DS 105 putih kg
23,000.00
15 Lemkra DS 105 abu kg
35,000.00
16 Lemkra FK 103 abu kg
20,000.00
17 Kain Kassa roll
10,000.00
18 Floor hardener Kg 25,000.00
19 stefnozhing bh
7,500.00
BAHAN FINISHING
1 Cat tembok exterior (wheatershield) kg 126,896.00
2 Cat dasar tembok kg 45,320.00
3 Cat tembok kg 80,752.00
4 Plamir tembok kg 69,216.00
5 Alkali resisting ltr 15,450.00
6 Zinchromate kg 22,660.00
7 Meni besi kg 21,630.00
8 Cat besi kg 95,790.00
9 Minyak cat / Thinner A ltr 97,850.00
10 Kuas cat uk. 4" bh 36,050.00
11 Solar (industri) ltr 15,450.00
12 Minyak pelumas las ltr 3,605.00
13 Residu ltr 6,695.00

BAHAN KACA
1 Kaca Bening t=5 mm m2 235,200.00
2 Kaca one way tebal 6 mm m2 542,400.00
3 Kaca stopsol biru tebal 8 mm m2 561,600.00
4 Kaca tempered tebal 10 mm m2 422,400.00
5 Kaca tempered tebal 12 mm m2 542,400.00
6 Kaca Nako bh 225,600.00

BAHAN KUSEN ALUMINIUM


1 Profil Alluminium 4" coating putih m 110,400.00
2 Slimar Jendela Aluminium 2" coating putih m' 91,200.00
3 Slimar Pintu Aluminium 3-5" coating putih m' 81,600.00
4 Aluminium strip m' 43,200.00
5 Karet kusen aluminium m' 24,000.00
6 Bracket 50x50x4mm Buah 12,000.00
7 Spygot 10/20. 2mm Buah 4,800.00
8 sealent tube 33,600.00
9 skrup fixer bh 12,000.00
10 Daun pintu WPC Duma 0,6X2,1 Finishing bh 684,000.00
11 Daun pintu kayu lapis HPL m2 748,800.00

BAHAN KUNCI DAN PENGGANTUNG


1 handle + kunci lengkap Dekson LHTR02.0022 SSS unit 432,000.00
2 Handle + kunci lengkap solid hre 61 41 unit 336,000.00

Page 76 of 162
HARGA BAHAN ARSITEKTUR DAN STRUKTUR

NO URAIAN SATUAN HARGA (Rp.) KET


3 Electronic Lock ex. Dekson bh 1,416,000.00
4 frame alluminium m1 120,000.00
5 Kunci tanam unit 144,000.00
6 Kunci Pintu PVC 2 x putar unit 206,400.00
7 Door Closer medium unit 624,000.00
8 Engsel pintu 4" Dekson ESS EL 2BP SSS bh 177,600.00
9 Engsel jendela 3" Dekson ESS EL 2BP SSS bh 148,800.00
10 Engsel kupu-kupu bh 115,200.00
11 Swing lockcase bh 105,600.00
12 Roller lockcase bh 225,600.00
13 Cylinder lock bh 139,200.00
14 Lever handle bh 124,800.00
15 Pull handle bh 235,200.00
16 Rambuncis bh 72,000.00
17 Flushbolt bh 81,600.00
18 Grendel bh 91,200.00
19 Hak angin bh 81,600.00
20 top patch fitting unit 72,000.00
21 bottom patch fitting unit 52,800.00
22 Lock fitting unit 33,600.00
23 Handle stainless steel unit 513,600.00
24 Floor hinge unit 432,000.00
25 Peralatan ls -
26 Resibon dia. 14" bh 14,400.00
27 Dynabolt M 10 x 120 mm bh 9,600.00
28 Mur + baut M 10 x 70 mm bh 4,800.00
29 Paku rivet dia 4mm bh 4,800.00
30 Skrup 8x3/4" bh 5,760.00
31 Fischer S 8 + skrup 12x2.5" bh 4,320.00
32 Spygot 10/20. 2mm bh 2,880.00
33 Bracket 50x50x4mm bh 4,800.00
34 Pintu roilling dorr m2 1,250,000.00

BAHAN SANITASI
1 Closet duduk Toto Monoblok CW-421J komplit Buah 2,352,000.00
2 Closet jongkok Toto CE-9 komplit kran flush Buah 907,200.00
3 Jet Showeer dan Fleksibel Toto THX20NBW komplit Buah 273,600.00
4 Shower set dan fleksible TotoTX433SD Komplit Buah 312,000.00
5 Wastafel Komplit (Kran + Sipon ) Toto LW247CJ Unit 417,600.00
6 Urinoir Toto U57M Buah 720,000.00
7 Handrail Stainless Steel Buah 417,600.00
8 Floor drain / Avour Stainless SUS304 Arcel Buah 120,000.00
9 Kran Air 1/2 " ex. Onda Buah 148,800.00
10 Sealtape Buah 20,160.00
11 bak cuci piring Buah 235,200.00
12 waterdrain Buah 43,200.00
13 Roof drain buah 215,000.00

BAHAN PENUTUP ATAP


1 Atap Zincalume, t = 0,4 mm (di roll) M2 129,600.00
2 Kalsiplank 8/300 m' 91,200.00
3 Waterproofing Mortar Kg. 72,000.00

BAHAN HALAMAN DAN LANSKAP


1 Paving block t. 8 cm m2 120,000.00
2 Paving block t. 6 cm m2 120,000.00
3 Kansten DKI bh 62,400.00
4 solar ltr 5,500.00

Page 77 of 162
HARGA BAHAN ARSITEKTUR DAN STRUKTUR

NO URAIAN SATUAN HARGA (Rp.) KET


5 Minyak pelumnas ltr 4,500.00

Page 78 of 162
ANALISA KUSEN PINTU JENDELA

ANALISA LINGKUP PEKERJAAN KUSEN PINTU JENDELA PARTISI

Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
0 0 (TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

Pemasangan 1 m kusen pintu alluminium


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)

A TENAGA
Pekerja OH 0.04 157,643.00 6,778.65
Tukang Alumunium OH 0.04 166,729.00 7,169.35
Kepala tukang OH 0.00 182,676.00 785.51
Mandor OH 0.00 194,274.00 407.98
JUMLAH TENAGA KERJA 15,141.48

B BAHAN
Profil alluminium m 1.10 110,400.00 121,440.00
Skrup fixer buah 2.00 12,000.00 24,000.00
Sealant Tube 0.06 33,600.00 2,016.00
JUMLAH HARGA BAHAN 147,456.00
C PERALATAN -

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) - 162,597.48
E Overhead & Profit 10% 0.10 16,259.75
F Harga Satuan Pekerjaan (D+E) - 178,857.23

Pemasangan 1 m selimar pintu/jendela kusen alluminium


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.04 157,643.00 6,778.65
Tukang Alumunium OH 0.04 166,729.00 7,169.35
Kepala tukang OH 0.00 182,676.00 785.51
Mandor OH 0.00 194,274.00 407.98
JUMLAH TENAGA KERJA 15,141.48
B BAHAN
Profil alluminium m 1.10 91,200.00 100,320.00

Skrup fixer buah 2.00 12,000.00 24,000.00


Sealant Tube 0.06 33,600.00 2,016.00
JUMLAH HARGA BAHAN 126,336.00
C PERALATAN -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) 141,477.48

E Overhead & Profit 10% 0.10 14,147.75


F Harga Satuan Pekerjaan (D+E) 155,625.23

1 Unit P.2
Pintu rolling dorr
9 m2 1,250,000.00 11,250,000.00
Pintu otomatis termasuk penggantung lengkap + pasang
1 set 4,250,000.00 4,250,000.00
Kunci
1 bh 474,150.71 474,150.71
JUMLAH 15,974,150.71
1 Unit P1
Kusen besi UNP 150.75.6,5 mm 128.8 kg 38,670.72 4,980,788.45
Daun Pintu pintu besi 2 muka rangka hollow
4.8 M2 650,000.00 3,120,000.00
Pengecetan pintu dan kusen
41.8 m2 55,635.10 2,325,547.24
Engsel pintu 6"
6 bh 228,699.25 1,372,195.50

Page 79 of 162
ANALISA KUSEN PINTU JENDELA

Handel + Kunci ex. Dekson


1 bh 474,150.71 474,150.71
JUMLAH 12,272,681.90
1 Unit P5
Kusen Allm. 4" powder coating putih 4.90 m1 178,857.23 876,400.41
Daun pintu alluminiumbesi t. 4 mm 1.47
m2 540,000.00 793,800.00
Engsel pintu 4" 6.00
bh 228,699.25 1,372,195.50
Handel pintu 1.00
bh 474,150.71 474,150.71
JUMLAH 3,516,546.62
1 Unit P3
Kusen Allm. 4" powder coating putih 5.40 m1 178,857.23 965,829.02
Daun pintu kayu lapis HPL 2.52
m2 748,800.00 1,886,976.00
Kaca mati bening 5 mm 1.80
m2 319,779.25 575,602.65
Engsel pintu 4" 3.00
bh 228,699.25 686,097.75
Handle+kunci ex Dekson 1.00
bh 474,150.71 474,150.71
JUMLAH 4,588,656.13

1 Unit P4
Kusen Allm. 4" powder coating putih 5.10 m1 178,857.23 912,171.85
Daun pintu kayu lapis HPL 1.00
bh 748,800.00 748,800.00
Handle+kunci ex Dekson 1.00
bh 474,150.71 474,150.71
Engsel pintu 4" 3.00
bh 228,699.25 686,097.75
JUMLAH 2,821,220.31

1 Unit P5
Kusen Allm. 4" powder coating putih 5.10 m1 178,857.23 912,171.85
Daun pintu plat alluminium 1.00
bh 450,000.00 450,000.00
slotan pintu 2.00
bh 139,200.00 278,400.00
Engsel pintu 4" 2.00
bh 228,699.25 457,398.50
JUMLAH 2,097,970.35

1 Unit J1
Kusen Allm. 4" powder coating putih 12.60 m1 178,857.23 2,253,601.05
Kaca bening 5 mm 11.70 m2 319,779.25 3,741,417.22
Selant 12.60
m2 25,000.00 315,000.00
Dinabol 12.00
bh 65,000.00 780,000.00

JUMLAH 7,090,018.27

1 Unit J2
frame kusen 6 m1 165,339.25 992,035.50
Engsel jendela 4 bh 149,017.40 596,069.60
Kait angin 2 bh 124,595.16 249,190.32
Jendela kaca bening 5 mm 4.41 m2 319,779.25 1,410,226.49
Kusen Allm. 4" powder coating putih 8.4
m1 178,857.23 1,502,400.70
JUMLAH 4,749,922.61
1 Unit J3
Jendela kaca tempered 10 mm 3.78 m2 543,294.95 2,053,654.91
Kusen Allm. 4" powder coating putih
14.9 m1 178,857.23 2,664,972.67
JUMLAH 4,718,627.57

1 Unit J4
frame kusen 9.2 m1 165,339.25 1,521,121.10
Engsel jendela 6 bh 149,017.40 894,104.40
Kait angin 3 bh 124,595.16 373,785.48
Jendela kaca bening 5 mm 3.78 m2 319,779.25 1,208,765.56
Kusen Allm. 4" powder coating putih
14.6 m1 178,857.23 2,611,315.50
JUMLAH 6,609,092.05

Page 80 of 162
ANALISA KUSEN PINTU JENDELA

1 Unit J5
Plat strip lobang angin 0.81 m2 750,000.00 607,500.00
dinabol 4 bh 75,000.00 300,000.00
Jendela kaca tbening 5 mm 1.62 m2 319,779.25 518,042.38
Kusen Allm. 4" powder coating putih
11.52 m1 178,857.23 2,060,435.24
JUMLAH 3,485,977.63

1 Unit J6
Plat strip lobang angin 3.9 m2 750,000.00 2,925,000.00
Kusen Allm. 4" powder coating putih
8.9 m1 178,857.23 1,591,829.31
JUMLAH 4,516,829.31

1 Unit J1 (POS JAGA)


Jendela kaca bening 5 mm 0.79 m2 319,779.25 252,625.61
Kusen Allm. 4" powder coating putih
4 m1 178,857.23 715,428.90
Selimar Pintu Allm. 3-5" powder coating putih
4 m1 155,625.23 622,500.90
Engsel Jendela 2 bh 149,017.40 298,034.80
Hak angin / Rambucik 2 bh 124,595.16 249,190.32
JUMLAH 2,137,780.54

1 Unit BV 1
Jendela kaca bening 5 mm 0.3 m2 319,779.25 95,933.77
Kusen Allm. 4" powder coating putih
2.4 m1 178,857.23 429,257.34
JUMLAH 525,191.12

1 Unit BV 2
Jendela kaca bening 5 mm 0.9 m2 319,779.25 287,801.32
Kusen Allm. 4" powder coating putih
7.2 m1 178,857.23 1,287,772.03
JUMLAH 1,575,573.35

Pekerjaan dinding partisi double GRC board steel stud partision


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.240 157,643.00 37,834.32
Tukang Alluminium OH 0.120 166,729.00 20,007.48

Kepala tukang OH 0.1200 182,676.00 21,921.12


Mandor OH 0.0525 194,274.00 10,199.39
JUMLAH TENAGA KERJA 89,962.31
B BAHAN
Metalstud 76 Aplus btg 1.25 63,700.00 79,625.00
Calsiboard 6mm lembar 0.70 108,000.00 75,600.00
Accessories ls 1.00 15,522.50 15,522.50

JUMLAH BAHAN 170,747.50

C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 260,709.81
E Overhead & Profit 10% 0.1000 26,070.98
F Harga Satuan Pekerjaan (D+E) - 286,780.79

Pekerjaan dinding partisi double Multiplek 12 mm rangka steel stud partision


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 0.240 157,643.00 37,834.32
Tukang Alluminium OH 0.120 166,729.00 20,007.48
Kepala tukang OH 0.1200 182,676.00 21,921.12

Page 81 of 162
ANALISA KUSEN PINTU JENDELA

Mandor OH 0.0525 194,274.00 10,199.39


JUMLAH TENAGA KERJA 89,962.31
B BAHAN
Metalstud 76 Aplus btg 1.25 63,700.00 79,625.00
Multiplek 12 mm lembar 0.70 225,000.00 157,500.00

Accessories ls 1.00 23,712.50 23,712.50

JUMLAH BAHAN 260,837.50


C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 350,799.81

E Overhead & Profit 10% 0.1000 35,079.98


F Harga Satuan Pekerjaan (D+E) - 385,879.79

Pekerjaan perbuatan dan pemasangan 1 m3 kusen pintu dan kusen jendela, kayu kelas II
No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja OH 6.000 157,643.00 945,858.00
Tukang Alluminium OH 18.000 166,729.00 3,001,122.00

Kepala tukang OH 1.8000 182,676.00 328,816.80


Mandor OH 0.3000 194,274.00 58,282.20
JUMLAH TENAGA KERJA 4,334,079.00
B BAHAN
Balok kayu M3 1.20 2,950,000.00 3,540,000.00
Paku biasa Kg 1.25 28,420.00 35,525.00

Lem Kayu / karet Kg 1.00 23,750.00 23,750.00

JUMLAH BAHAN 3,599,275.00


C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 7,933,354.00

E Overhead & Profit 10% 0.1000 793,335.40


F Harga Satuan Pekerjaan (D+E) - 8,726,689.40

Pekerjaan dinding partisikaca bening t. 5 mm steel stud partision


No Uraian Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA

Pekerja OH 0.015 157,643.00 2,364.65


Tukang Alluminium OH 0.150 166,729.00 25,009.35
Kepala tukang OH 0.0150 182,676.00 2,740.14
Mandor OH 0.0010 194,274.00 194.27
JUMLAH TENAGA KERJA 30,308.41
B BAHAN
kaca bening 5 mm m2 1.00 235,200.00 235,200.00
kusen alluminium m1 2.00 110,400.00 220,800.00
sealant tube 1.00 33,600.00 33,600.00

JUMLAH BAHAN 489,600.00


C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 519,908.41
E Overhead & Profit 10% 0.1000 51,990.84

F Harga Satuan Pekerjaan (D+E) - 571,899.25

Page 82 of 162
ANALISA ARSITEKTUR

ANALISA HARGA SATUAN BAHAN DAN UPAH


PEKERJAAN ARSITEKTUR
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

HARGA SATUAN PEKERJAAN PASANGAN DINDING


Pemasangan 1 m2 dinding bata ringan tebal 7,5 cm dengan mortar siap pakai B.
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 157,643.00 47,292.90
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 68,706.67
B BAHAN TENAGA KERJA
Bata ringan tebal 7,5 cm bh 8.4000 15,680.00 131,712.00
Mortar siap pakai Kg 0.4730 3,797.50 1,796.22
JUMLAH 133,508.22
C PERALATAN HARGA BAHAN
Peralatan Pasang Dinding Bata Ringan Ls 0.1000 1,000.00 100.00
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) - 202,314.89
E Overhead & Profit 10% 0.1000 20,231.49
F Harga Satuan Pekerjaan (D+E) - 222,546.38

Pemasangan 1 m2 dinding bata ringan tebal 10 cm dengan mortar siap pakai


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 157,643.00 47,292.90
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 68,706.67
B BAHAN TENAGA KERJA
Bata ringan tebal 10 cm bh 8.3300 10,584.42 88,168.25
Mortar siap pakai Kg 0.4400 3,797.50 1,670.90
JUMLAH 89,839.15
C PERALATAN HARGA BAHAN
Peralatan Pasang Dinding Bata Ringan Ls 0.1000 1,000.00 100.00
JUMLAH HARGA ALAT 100.00
D Jumlah (A+B+C) - 158,645.82
E Overhead & Profit 10% 0.1000 15,864.58
F Harga Satuan Pekerjaan (D+E) - 174,510.40

Pemasangan 1 M2 Pasangan Dinding Bata PC 1 :4 (1/2 Bata)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 157,643.00 47,292.90
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 68,706.67
TENAGA KERJA

Page 83 of 162
ANALISA ARSITEKTUR

B BAHAN
Batu Bata Bh 70.0000 637.00 44,590.00
PC Kg 18.9500 1,470.00 27,856.50
Pasir Pasang M3 0.0380 259,700.00
JUMLAH 72,446.50
C PERALATAN HARGA BAHAN
Alat bantu Ls 1.0000 2,000.00 2,000.00
JUMLAH HARGA ALAT 2,000.00
D Jumlah (A+B+C) - 143,153.17
E Overhead & Profit 10% 0.1000 14,315.32
F Harga Satuan Pekerjaan (D+E) - 157,468.49

HARGA SATUAN PEKERJAAN PLESTERAN


Pemasangan 1 m2 plesteran 1SP : 4PP tebal 15 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 157,643.00 47,292.90
Tukang Batu L.02.03 OH 0.1500 166,729.00 25,009.35
Kepala Tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 77,956.50
B BAHAN TENAGA KERJA
Semen portland Kg 6.2400 1,470.00 9,172.80
Pasir Pasang m3 0.0240 259,700.00 6,232.80
JUMLAH 15,405.60
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 93362.1
E Overhead & Profit 10% 0.1000 9,336.21
F Harga Satuan Pekerjaan (D+E) - 102,698.31

Pemasangan 1 m2 plesteran 1SP : 5PP tebal 15 mm


A TENAGA
Pekerja L.01.01 OH 0.3000 157,643.00 47,292.90
Tukang Batu L.02.03 OH 0.1500 166,729.00 25,009.35
Kepala Tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 77,956.50
B BAHAN TENAGA KERJA
Semen portland Kg 4.4160 1,470.00 6,491.52
Pasir Pasang m3 0.0270 259,700.00 7,011.90
JUMLAH 13,503.42
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 91,459.92
E Overhead & Profit 10% 0.1000 9,145.99
F Harga Satuan Pekerjaan (D+E) - 100,605.91

Pemasangan 1 m2 acian.
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 157,643.00 31,528.60
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0100 194,274.00 1,942.74
JUMLAH 51,971.00
B BAHAN TENAGA KERJA

Page 84 of 162
ANALISA ARSITEKTUR

Semen portland Kg 3.2500 1,470.00 4,777.50


JUMLAH 4,777.50
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 56,748.50
E Overhead & Profit 10% 0.1000 5,674.85
F Harga Satuan Pekerjaan (D+E) - 62,423.35

Pemasangan 1 m2 plesteran dengan mortar siap pakai (MSP)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 157,643.00 31,528.60
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0100 194,274.00 1,942.74
JUMLAH 51,971.00
B BAHAN TENAGA KERJA
Semen mortar pasangan Kg 6.3400 1,470.00 9,319.80
JUMLAH 9,319.80
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 61,290.80
E Overhead & Profit 10% 0.1000 6,129.08
F Harga Satuan Pekerjaan (D+E) - 67,419.88

Pemasangan 1 m2 Acian dengan mortar siap pakai (MSP)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 157,643.00 31,528.60
Tukang Batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0100 194,274.00 1,942.74
JUMLAH 51,971.00
B BAHAN TENAGA KERJA
Semen mortar Acian Kg 3.2500 1,470.00 4,777.50
JUMLAH 4,777.50
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 56748.5
E Overhead & Profit 10% 0.1000 5,674.85
F Harga Satuan Pekerjaan (D+E) - 62,423.35

Pemasangan 1m2 lantai granit HT (Polish) ukuran 60cm x60cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2500 157,643.00 39,410.75
Tukang Batu L.02.03 OH 0.1250 166,729.00 20,841.13
Kepala tukang L.03.01 OH 0.0130 182,676.00 2,374.79
Mandor L.04.01 OH 0.0130 194,274.00 2,525.56
JUMLAH 65,152.23
B BAHAN TENAGA KERJA
granit polish ukuran 60cm x60cm m2 1.0500 237,500.00 249,375.00
Semen portland kg 9.8000 1,470.00 14,406.00
Semen Warna Kg 1.3000 2,058.00 2,675.40
Pasir Pasang M3 0.0450 259,700.00 11,686.50
JUMLAH 278,142.90
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -

Page 85 of 162
ANALISA ARSITEKTUR

D Jumlah (A+B+C) - 343,295.13


E Overhead & Profit 10% 0.1000 34,329.51
F Harga Satuan Pekerjaan (D+E) - 377,624.64

Pemasangan 1m2 lantai granit HT (structure/rustic) ukuran 60cm x60cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2500 157,643.00 39,410.75
Tukang Batu L.02.03 OH 0.1250 166,729.00 20,841.13
Kepala tukang L.03.01 OH 0.0130 182,676.00 2,374.79
Mandor L.04.01 OH 0.0130 194,274.00 2,525.56
JUMLAH 65,152.23
B BAHAN TENAGA KERJA
granit rustic ukuran 60cm x60cm m2 1.0500 209,000.00 219,450.00
Semen portland kg 9.8000 1,470.00 14,406.00
Semen Warna Kg 1.3000 2,058.00 2,675.40
Pasir Pasang M3 0.0450 259,700.00 11,686.50
JUMLAH 248,217.90
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 313,370.13
E Overhead & Profit 10% 0.1000 31,337.01
F Harga Satuan Pekerjaan (D+E) - 344,707.14

Pemasangan 1m2 dinding granit HT (structure/rustic) ukuran 40cm x40cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.4050 157,643.00 63,845.42
Tukang Batu L.02.03 OH 0.1300 166,729.00 21,674.77
Kepala tukang L.03.01 OH 0.0130 182,676.00 2,374.79
Mandor L.04.01 OH 0.0135 194,274.00 2,622.70
JUMLAH 90,517.67
B BAHAN TENAGA KERJA
Keramik lantai ukuran 60cm x60cm m2 1.0500 156,750.00 164,587.50
Semen portland kg 9.8000 1,470.00 14,406.00
Semen Warna Kg 1.3000 2,058.00 2,675.40
Pasir Pasang M3 0.0450 259,700.00 11,686.50
JUMLAH 193,355.40
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 283,873.07
E Overhead & Profit 10% 0.1000 28,387.31
F Harga Satuan Pekerjaan (D+E) - 312,260.38

Pemasangan 1m2 dinding keramik ukuran 20cm x 40 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.4050 157,643.00 63,845.42
Tukang Batu L.02.03 OH 0.1300 166,729.00 21,674.77
Kepala tukang L.03.01 OH 0.0130 182,676.00 2,374.79
Mandor L.04.01 OH 0.0135 194,274.00 2,622.70
JUMLAH 90,517.67
B BAHAN TENAGA KERJA
Keramik ukuran 20cm x 25cm m2 1.0500 147,250.00 154,612.50
Semen portland kg 9.3000 1,470.00 13,671.00
Pasir Pasang M³ 0.0180 259,700.00 4,674.60
Semen Warna Kg 1.9400 2,058.00 3,992.52

Page 86 of 162
ANALISA ARSITEKTUR

JUMLAH 176,950.62
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 267,468.29
E Overhead & Profit 10% 0.1000 26,746.83
F Harga Satuan Pekerjaan (D+E) - 294,215.12

Pemasangan 1m2 Granit tile ukuran 30cm x 60 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2700 157,643.00 42,563.61
Tukang Batu L.02.03 OH 0.1350 166,729.00 22,508.42
Kepala tukang L.03.01 OH 0.0140 182,676.00 2,557.46
Mandor L.04.01 OH 0.0140 194,274.00 2,719.84
JUMLAH 70,349.33
B BAHAN TENAGA KERJA
Granit tile 30 x 60 cm m2 1.0500 204,250.00 214,462.50
Semen portland kg 9.3000 1,470.00 13,671.00
Pasir Pasang M³ 0.0180 259,700.00 4,674.60
Semen Warna Kg 1.9400 2,058.00 3,992.52
JUMLAH 236,800.62
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 307,149.95
E Overhead & Profit 10% 0.1000 30,714.99
F Harga Satuan Pekerjaan (D+E) - 337,864.94

Pemasangan 1m Step Nosing ukuran 10cm x40cm


A Bahan
Keramik Lantai Roman 10 x 40 Step Nosing Per Bh Bh 2.5 7500 18,750.00
Semen Tiga Roda 50 kg kg 0.0196 1470 28.81
Pasir Pasang m³ 0.0045 259700 1,168.65
Semen Warna Kg 0.437 2058 899.35

B Tenaga
Pekerja Oh 0.105 157,643.00 16,552.52
Tukang Batu Oh 0.0525 166,729.00 8,753.27
Kepala Tukang Oh 0.0053 182,676.00 968.18
Mandor Oh 0.0053 194,274.00 1,029.65
C PERALATAN
D Jumlah (A+B+C) - 48,150.43
E Overhead & Profit 10% 0.1000 4,815.04
F Harga Satuan Pekerjaan (D+E) - 52,965.47

Pemasangan 1 m2 wallpaper lebar 50 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0700 157,643.00 11,035.01
Tukang L.02.03 OH 0.0350 166,729.00 5,835.52
Kepala tukang L.03.01 OH 0.0034 182,676.00 621.10
Mandor L.04.01 OH 0.0004 194,274.00 77.71
JUMLAH 17,569.33
B BAHAN TENAGA KERJA
wallpaper lebar 50 cm m2 1.1000 42,750.00 47,025.00
Lem bungkus 0.0125 19,950.00 249.38
JUMLAH 47,274.38
C PERALATAN HARGA BAHAN - -

Page 87 of 162
ANALISA ARSITEKTUR

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) - 64,843.71
E Overhead & Profit 10% 0.1000 6,484.37
F Harga Satuan Pekerjaan (D+E) - 71,328.08

Pemasangan 1 m2 Waterfrofing
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1000 157,643.00 15,764.30
Tukang L.02.03 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0100 194,274.00 1,942.74
JUMLAH 45,456.53
B BAHAN TENAGA KERJA
Lemkra TG 301 ltr 0.1250 25,000.00 3,125.00
Lemkra DS 105 putih kg 2.5000 23,000.00 57,500.00
Lemkra DS 105 abu kg 2.0000 35,000.00 70,000.00
Lemkra FK 103 abu kg 0.3000 20,000.00 6,000.00
Kain Kassa roll 0.0250 10,000.00 250.00
JUMLAH 136,875.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 182,331.53
E Overhead & Profit 10% 0.1000 18,233.15
F Harga Satuan Pekerjaan (D+E) - 200,564.68

Pemasangan 1 m2 Floor hardener


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1200 157,643.00 18,917.16
Tukang L.02.03 OH 0.1200 166,729.00 20,007.48
Kepala tukang L.03.01 OH 0.0120 182,676.00 2,192.11
Mandor L.04.01 OH 0.0060 194,274.00 1,165.64
JUMLAH 42,282.40
B BAHAN TENAGA KERJA
Floor Hardener Mastercon Kg 5.0000 25,000.00 125,000.00
-
JUMLAH 125,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 167,282.40
E Overhead & Profit 10% 0.1000 16,728.24
F Harga Satuan Pekerjaan (D+E) - 184,010.64

Pemasangan 1 m2 HPL
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0700 157,643.00 11,035.01
Tukang L.02.03 OH 0.0350 166,729.00 5,835.52
Kepala tukang L.03.01 OH 0.0034 182,676.00 621.10
Mandor L.04.01 OH 0.0004 194,274.00 77.71
JUMLAH 17,569.33
B BAHAN TENAGA KERJA
HPL m2 1.1000 104,500.00 114,950.00
Lem bungkus 0.0125 23,750.00 296.88
JUMLAH 115,246.88
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -

Page 88 of 162
ANALISA ARSITEKTUR

D Jumlah (A+B+C) - 132,816.21


E Overhead & Profit 10% 0.1000 13,281.62
F Harga Satuan Pekerjaan (D+E) - 146,097.83

ANALISA PEKERJAAN HALAMAN


Pemasangan 1 m2 paving block natural tebal 6 cm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2500 157,643.00 39,410.75
Tukang Kayu L.02.04 OH 0.2500 166,729.00 41,682.25
Kepala tukang L.03.01 OH 0.0250 182,676.00 4,566.90
Mandor L.04.01 OH 0.0025 194,274.00 485.69
JUMLAH 86,145.59
B BAHAN TENAGA KERJA
Paving block 6 cm M
2 1.0100 120,000.00 121,200.00
Pasir beton M
3 0.0500 274,400.00 13,720.00
JUMLAH 134,920.00
C PERALATAN HARGA BAHAN -
Peralatan Kerja Paving Blok % 0.1000 134,920.00 13,492.00
JUMLAH HARGA ALAT 13,492.00
D Jumlah (A+B+C) - 234,557.59
E Overhead & Profit 10% 0.1000 23,455.76
F Harga Satuan Pekerjaan (D+E) - 258,013.34

Pemasangan 1 m2 paving block natural tebal 8 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2500 157,643.00 39,410.75
Tukang Kayu L.02.04 OH 0.2500 166,729.00 41,682.25
Kepala tukang L.03.01 OH 0.0250 182,676.00 4,566.90
Mandor L.04.01 OH 0.0025 194,274.00 485.69
JUMLAH 86,145.59
B BAHAN TENAGA KERJA
Paving block 8 cm natural M
2 1.0100 120,000.00 121,200.00
Pasir beton M
3 0.0700 274,400.00 19,208.00
JUMLAH 140,408.00
C PERALATAN HARGA BAHAN -
Peralatan Kerja Paving Blok % 0.1000 - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 226,553.59
E Overhead & Profit 10% 0.1000 22,655.36
F Harga Satuan Pekerjaan (D+E) - 249,208.94

Pemasangan 1 m1 Kansten DKI natural tebal 8 cm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0357 157,643.00 5,627.86
Tukang Kayu L.02.04 OH 0.0714 166,729.00 11,904.45
Kepala tukang L.03.01 OH 0.0071 182,676.00 1,297.00
Mandor L.04.01 OH 0.0036 194,274.00 699.39
JUMLAH 19,528.69
B BAHAN TENAGA KERJA
Kst. DKI, 15.30.40, K-300 Warna abu-abu bh 2.625 63,700.00 167,212.50
Semen Tiga Roda 50 kg kg 2.3766 1,470.00 3,493.60
Pasir Pasang m3 0.0066 259,700.00 1,714.02
JUMLAH 172,420.12
C PERALATAN HARGA BAHAN -

Page 89 of 162
ANALISA ARSITEKTUR

Peralatan Kerja Paving Blok - -


JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 191,948.81
E Overhead & Profit 10% 0.1000 19,194.88
F Harga Satuan Pekerjaan (D+E) - 211,143.70

Pemasangan 1 M3 Urukan sirtu padat


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.167 157,643.00 26,273.83
Tukang Kayu L.02.04 OH 0.016 166,729.00 2,667.66
Kepala tukang L.03.01 OH 0.016 182,676.00 2,922.82
Mandor L.04.01 OH 0.017 194,274.00 3,237.90
JUMLAH 35,102.21
B BAHAN TENAGA KERJA
Sirtu bh 1.020 245,000.00 249,900.00

JUMLAH 249,900.00
C PERALATAN HARGA BAHAN -
Mesin wales jam 0.1000 250,000.00 25,000.00
JUMLAH HARGA ALAT 25,000.00
D Jumlah (A+B+C) - 310,002.21
E Overhead & Profit 10% 0.1000 31,000.22
F Harga Satuan Pekerjaan (D+E) - 341,002.43

1 M3 Urukan tanah merah + Pemadatan tanah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.167 157,643.00 26,273.83
Tukang Kayu L.02.04 OH 0.016 166,729.00 2,667.66
Kepala tukang L.03.01 OH 0.016 182,676.00 2,922.82
Mandor L.04.01 OH 0.017 194,274.00 3,237.90
JUMLAH 35,102.21
B BAHAN TENAGA KERJA
Tanah merah super bh 1.020 - -

JUMLAH -
C PERALATAN HARGA BAHAN -
Sewa Stamper jam 0.1000 75,000.00 7,500.00
JUMLAH HARGA ALAT 7,500.00
D Jumlah (A+B+C) - 42,602.21
E Overhead & Profit 10% 0.1000 4,260.22
F Harga Satuan Pekerjaan (D+E) - 46,862.43

HARGA SATUAN PEKERJAAN LANGIT-LANGIT (PLAFOND)


Pemasangan 1 m2 langit-langit gypsum board ukuran (120x240x9) mm, tebal 9 mm
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1000 157,643.00 15,764.30
Tukang kayu L.02.04 OH 0.0500 166,729.00 8,336.45
Kepala tukang L.03.01 OH 0.0050 182,676.00 913.38
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 25,985.50
B BAHAN TENAGA KERJA
Gypsum board 9 mm (1200 x 2400 Lembar 0.3646 108,000.00 39,376.80
mm)
Paku skrup kg 0.1100 28,420.00 3,126.20
Rangka Hollow 4x2, 2x2 m2 1.0500 112,700.00 118,335.00
Assesoris Ls 1.0000 24,125.70 24,125.70

Page 90 of 162
ANALISA ARSITEKTUR

JUMLAH 184,963.70
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 210,949.20
E Overhead & Profit 10% 0.1000 21,094.92
F Harga Satuan Pekerjaan (D+E) - 232,044.12

Pemasangan 1 m2 Plafond GRC, tebal 4 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1000 157,643.00 15,764.30
Tukang kayu L.02.04 OH 0.0500 166,729.00 8,336.45
Kepala tukang L.03.01 OH 0.0050 182,676.00 913.38
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 25,985.50
B BAHAN TENAGA KERJA
grc Lembar 0.4600 108,000.00 49,680.00
Baund GRC kg 0.0100 28,420.00 284.20
Rangka Hollow 4x2, 2x2 m2 1.0500 112,700.00 118,335.00
Assesoris Ls 1.0000 25,244.88 25,244.88
JUMLAH 193,544.08
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 219,529.58
E Overhead & Profit 10% 0.1000 21,952.96
F Harga Satuan Pekerjaan (D+E) - 241,482.54

HARGA SATUAN PEKERJAAN PENUTUP ATAP


Pemasangan 1 m2 Penutup Atap Zincalume
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1500 157,643.00 23,646.45
Tukang Kayu L.02.04 OH 0.0750 166,729.00 12,504.68
Kepala tukang L.03.01 OH 0.0080 182,676.00 1,461.41
Mandor L.04.01 OH 0.0080 194,274.00 1,554.19
JUMLAH 39,166.73
B BAHAN TENAGA KERJA
Zincalume, t = 0,4 mm Lbr 1.0500 129,600.00 136,080.00
Assesoris Ls 1.0000 13,608.00 13,608.00
JUMLAH 149,688.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 188,854.73
E Overhead & Profit 10% 0.1000 18,885.47
F Harga Satuan Pekerjaan (D+E) - 207,740.20

Pemasangan 1 m' talang datar/ jurai seng BJLS 40


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 157,643.00 31,528.60
Tukang Kayu L.02.04 OH 0.2000 166,729.00 33,345.80
Kepala tukang L.03.01 OH 0.0200 182,676.00 3,653.52
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 68,722.19
B BAHAN TENAGA KERJA
Seng plat BJLS 40, lebar 2 m m 1.0500 34,300.00 36,015.00
Paku Rivet Kg 0.0150 28,420.00 426.30
JUMLAH 36,441.30
HARGA BAHAN

Page 91 of 162
ANALISA ARSITEKTUR

C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 105,163.49
E Overhead & Profit 10% 0.1000 10,516.35
F Harga Satuan Pekerjaan (D+E) - 115,679.84

Pemasangan Kasiplank m2
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.2000 157,643.00 31,528.60
Tukang kayu L.02.04 OH 0.0800 166,729.00 13,338.32
Kepala tukang L.03.01 OH 0.0800 182,676.00 14,614.08
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 60,452.37
B BAHAN TENAGA KERJA
Rangka hollow galvalume m' 3.0500 15,925.00 48,571.25
Kalsiplank uk 80 x 300 mm m' 1.0200 91,200.00 93,024.00
Paku pancing / sekrup Kg 0.0200 28,420.00 568.40
JUMLAH HARGA BAHAN 142,163.65
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 202,616.02
E Overhead & Profit 10% 0.1000 20,261.60
F Harga Satuan Pekerjaan (D+E) - 222,877.62

1 m2 Pemasangan Alumunium Composite Panel (ACP)


Upah
Tenaga
Pekerja Oh 0.15 157,643.00 23,646.45
Tukang Besi Oh 0.075 166,729.00 12,504.68
Kepala Tukang Oh 0.0075 182,676.00 1,370.07
Mandor Oh 0.0008 194,274.00 155.42

Bahan
ACP Merk Alucobond (tipe PE), 4 mm per m' - warna m2 1.05 237,500.00 249,375.00
Hollow alumunium 40.40.1 mm per m' m' 5 15,925.00 79,625.00
Screw Alumunium Bh 4 28,420.00 113,680.00
Perlengkapan (Stiffner/Spigod, Sealeant) 3% 442,680.00 13,280.40
Besi Siku 40x40 x 4 mm per kg Kg 8.225 12,740.00 104,786.50
Meni Besi Siku m2 0.48 1,500.00 720.00
Dynabolt M8 Bh 12 20,000.00 240,000.00

PERALATAN
Alat Bantu (Sewa Scaffolding, Gerinda, mesin Grovingls 10% 801,466.90 80,146.69

D Jumlah (A+B+C) - 919,290.20


E Overhead & Profit 10% 0.1000 91,929.02
F Harga Satuan Pekerjaan (D+E) - 1,011,219.22

HARGA SATUAN PEKERJAAN KAYU


Pembuatan 1 m2 daun pintu plywood rangkap, rangka kayu kelas II tertutup
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7000 157,643.00 110,350.10
Tukang kayu L.02.04 OH 2.1000 166,729.00 350,130.90
Kepala tukang L.03.01 OH 0.2100 182,676.00 38,361.96
Mandor L.04.01 OH 0.0350 194,274.00 6,799.59
JUMLAH 505,642.55
TENAGA KERJA

Page 92 of 162
ANALISA ARSITEKTUR

B BAHAN
kayu Papan m3 0.0250 4,500,000.00 112,500.00
Paku Biasa kg 0.0300 28,420.00 852.60
Lem Kayu/Karet kg 0.5000 23,750.00 11,875.00
Plywood 4 mm Lembar 1.0000 85,000.00 85,000.00
JUMLAH 210,227.60
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 715,870.15
E Overhead & Profit 10% 0.1000 71,587.02
F Harga Satuan Pekerjaan (D+E) - 787,457.17

HARGA SATUAN PEKERJAAN KUNCI DAN KACA


Pemasangan 1 buah handle + kunci lengkap solid hre 61 41
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang kayu L.02.04 OH 0.5000 166,729.00 83,364.50
Kepala tukang L.03.01 OH 0.0500 182,676.00 9,133.80
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 95,046.10
B BAHAN TENAGA KERJA
Handle + kunci lengkap solid hre 61 Bh 1.0000 336,000.00 336,000.00
41 JUMLAH 336,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 431,046.10
E Overhead & Profit 10% 0.1000 43,104.61
F Harga Satuan Pekerjaan (D+E) - 474,150.71

Pemasangan 1 buah engsel pintu


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0150 157,643.00 2,364.65
Tukang kayu L.02.04 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 30,308.41
B BAHAN TENAGA KERJA
Engsel pintu Bh 1.0000 177,600.00 177,600.00
JUMLAH 177,600.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 207,908.41
E Overhead & Profit 10% 0.1000 20,790.84
F Harga Satuan Pekerjaan (D+E) - 228,699.25

Pemasangan 1 buah engsel jendela kupu-kupu


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang kayu L.02.04 OH 0.1000 166,729.00 16,672.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 20,270.36
B BAHAN TENAGA KERJA
Engsel kupu-kupu Bh 1.0000 115,200.00 115,200.00
JUMLAH 115,200.00
HARGA BAHAN

Page 93 of 162
ANALISA ARSITEKTUR

C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 135,470.36
E Overhead & Profit 10% 0.1000 13,547.04
F Harga Satuan Pekerjaan (D+E) - 149,017.40

Pemasangan 1 buah kait angin


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0150 157,643.00 2,364.65
Tukang kayu L.02.04 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0080 194,274.00 1,554.19
JUMLAH 31,668.33
B BAHAN TENAGA KERJA
Kait angin Bh 1.0000 81,600.00 81,600.00
JUMLAH 81,600.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 113,268.33
E Overhead & Profit 10% 0.1000 11,326.83
F Harga Satuan Pekerjaan (D+E) - 124,595.16

Pemasangan 1 buah door closer


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0500 157,643.00 7,882.15
Tukang kayu L.02.04 OH 0.5000 166,729.00 83,364.50
Kepala tukang L.03.01 OH 0.0500 182,676.00 9,133.80
Mandor L.04.01 OH 0.0030 194,274.00 582.82
JUMLAH 100,963.27
B BAHAN TENAGA KERJA
Door closer set 1.0000 624,000.00 624,000.00
JUMLAH 624,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 724,963.27
E Overhead & Profit 10% 0.1000 72,496.33
F Harga Satuan Pekerjaan (D+E) - 797,459.60

Pemasangan 1 m1 Frame jendela


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0150 157,643.00 2,364.65
Tukang kayu L.02.04 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 30,308.41
B BAHAN TENAGA KERJA
Frame alluminium m1 1.0000 120,000.00 120,000.00
JUMLAH 120,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 150,308.41
E Overhead & Profit 10% 0.1000 15,030.84
F Harga Satuan Pekerjaan (D+E) - 165,339.25

Pemasangan 1 m2 kaca tebal 5 mm

Page 94 of 162
ANALISA ARSITEKTUR

No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0150 157,643.00 2,364.65
Tukang kayu L.02.04 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 30,308.41
B BAHAN TENAGA KERJA
Kaca tebal 5 mm m2 1.1000 235,200.00 258,720.00
Sealant Kg 0.0500 33,600.00 1,680.00
JUMLAH 260,400.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 290,708.41
E Overhead & Profit 10% 0.1000 29,070.84
F Harga Satuan Pekerjaan (D+E) - 319,779.25

Pemasangan 1 m2 kaca tampered tebal 10 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0250 157,643.00 3,941.08
Tukang kayu L.02.04 OH 0.2500 166,729.00 41,682.25
Kepala tukang L.03.01 OH 0.0250 182,676.00 4,566.90
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 50,384.50
B BAHAN TENAGA KERJA
Kaca tampered 10 mm m2 1.0500 422,400.00 443,520.00
JUMLAH 443,520.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 493,904.50
E Overhead & Profit 10% 0.1000 49,390.45
F Harga Satuan Pekerjaan (D+E) - 543,294.95

Pemasangan 1 m2 kaca tampered tebal 12 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0250 157,643.00 3,941.08
Tukang kayu L.02.04 OH 0.2500 166,729.00 41,682.25
Kepala tukang L.03.01 OH 0.0250 182,676.00 4,566.90
Mandor L.04.01 OH 0.0010 194,274.00 194.27
JUMLAH 50,384.50
B BAHAN TENAGA KERJA
Kaca tampered 12 mm m2 1.0500 542,400.00 569,520.00
JUMLAH 569,520.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 619,904.50
E Overhead & Profit 10% 0.1000 61,990.45
F Harga Satuan Pekerjaan (D+E) - 681,894.95

Pemasangan 1 m2 kaca one way 6 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0150 157,643.00 2,364.65
Tukang kayu L.02.04 OH 0.1500 166,729.00 25,009.35
Kepala tukang L.03.01 OH 0.0150 182,676.00 2,740.14
Mandor L.04.01 OH 0.0080 194,274.00 1,554.19

Page 95 of 162
ANALISA ARSITEKTUR

JUMLAH 31,668.33
B BAHAN TENAGA KERJA
Kaca one way 6 mm m2 1.0500 542,400.00 569,520.00
JUMLAH 569,520.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 601,188.33
E Overhead & Profit 10% 0.1000 60,118.83
F Harga Satuan Pekerjaan (D+E) - 661,307.16

Pemasangan 1 m2 kaca stopsol biru 8 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0170 157,643.00 2,679.93
Tukang kayu L.02.04 OH 0.1700 166,729.00 28,343.93
Kepala tukang L.03.01 OH 0.0170 182,676.00 3,105.49
Mandor L.04.01 OH 0.0090 194,274.00 1,748.47
JUMLAH 35,877.82
B BAHAN TENAGA KERJA
Kaca stopsol 8 mm m2 1.0500 561,600.00 589,680.00
JUMLAH 589,680.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 625,557.82
E Overhead & Profit 10% 0.1000 62,555.78
F Harga Satuan Pekerjaan (D+E) - 688,113.60

HARGA SATUAN PEKERJAAN PENGECATAN


Pengecatan 1 m2 tembok baru interior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0200 157,643.00 3,152.86
Tukang cat L.02.08 OH 0.0630 166,729.00 10,503.93
Kepala tukang L.03.01 OH 0.0060 182,676.00 1,096.06
Mandor L.04.01 OH 0.0030 194,274.00 582.82
JUMLAH 15,335.67
B BAHAN TENAGA KERJA
Plamuur Kg 0.1000 69,216.00 6,921.60
Cat dasar Tembok Kg 0.1000 45,320.00 4,532.00
Cat Penutup Tembok Kg 0.2600 80,752.00 20,995.52
JUMLAH 32,449.12
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 47,784.79
E Overhead & Profit 10% 0.1000 4,778.48
F Harga Satuan Pekerjaan (D+E) - 52,563.26

Pengecatan 1 m2 tembok baru exterior ( 1 lapis plamuur, 1 lapis cat dasar, 2 lapis cat penutup)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0200 157,643.00 3,152.86
Tukang cat L.02.08 OH 0.0630 166,729.00 10,503.93
Kepala tukang L.03.01 OH 0.0060 182,676.00 1,096.06
Mandor L.04.01 OH 0.0030 194,274.00 582.82
JUMLAH 15,335.67
B BAHAN TENAGA KERJA
Plamuur Kg 0.1000 69,216.00 6,921.60
Cat dasar Tembok Kg 0.1000 126,896.00 12,689.60

Page 96 of 162
ANALISA ARSITEKTUR

Cat Penutup Tembok Kg 0.2600 80,752.00 20,995.52


JUMLAH 40,606.72
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 55,942.39
E Overhead & Profit 10% 0.1000 5,594.24
F Harga Satuan Pekerjaan (D+E) - 61,536.62

1 m² Pengecatan Permukaan Baja dengan Meni Besi


A Bahan
Cat besi setara nippon Kg 0.1 95,790.00 9,579.00
Kwas Ukuran 3 Inchi Bh 0.01 36,050.00 360.50

B Tenaga
Pekerja Oh 0.02 157,643.00 3,152.86
Tukang Cat Oh 0.2 166,729.00 33,345.80
Kepala Tukang Oh 0.02 182,676.00 3,653.52
Mandor Oh 0.0025 194,274.00 485.69

C PERALATAN

D Jumlah (A+B+C) - 50,577.37


E Overhead & Profit 10% 0.1000 5,057.74
F Harga Satuan Pekerjaan (D+E) - 55,635.10

HARGA SATUAN PEKERJAAN SANITASI DALAM GEDUNG


(K3) Pemasangan 1 buah closet duduk/monoblock
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 3.3000 157,643.00 520,221.90
Tukang batu L.02.03 OH 1.1000 166,729.00 183,401.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.1600 194,274.00 31,083.84
JUMLAH 736,534.40
B BAHAN TENAGA KERJA
Closet duduk Toto Monoblok CW- Unit 1.0000 2,352,000.00 2,352,000.00
421J
Perlengkapan % 0.0600 2,352,000.00 141,120.00
JUMLAH - 2,493,120.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 3,229,654.40
E Overhead & Profit 10% 0.1000 322,965.44
F Harga Satuan Pekerjaan (D+E) - 3,552,619.84

Pemasangan 1 buah closet jongkok Toto CE-9


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.0000 157,643.00 157,643.00
Tukang batu L.02.03 OH 1.5000 166,729.00 250,093.50
Kepala tukang L.03.01 OH 0.1500 182,676.00 27,401.40
Mandor L.04.01 OH 0.1600 194,274.00 31,083.84
JUMLAH 466,221.74
B BAHAN TENAGA KERJA
Closet jongkok Toto CE-9 Unit 1.0000 907,200.00 907,200.00
Semen portland Kg 6.0000 1,470.00 8,820.00
Pasir pasang M3 0.0100 259,700.00 2,597.00
JUMLAH 918,617.00
C PERALATAN HARGA BAHAN - -

Page 97 of 162
ANALISA ARSITEKTUR

JUMLAH HARGA ALAT -


D Jumlah (A+B+C) - 1,384,838.74
E Overhead & Profit 10% 0.1000 138,483.87
F Harga Satuan Pekerjaan (D+E) - 1,523,322.61

(K3) Pemasangan 1 buah urinoir


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.0000 157,643.00 157,643.00
Tukang batu L.02.03 OH 1.0000 166,729.00 166,729.00
Kepala tukang L.03.01 OH 0.1000 182,676.00 18,267.60
Mandor L.04.01 OH 0.0500 194,274.00 9,713.70
JUMLAH 352,353.30
B BAHAN TENAGA KERJA
Urinoir Toto M-51 Unit 1.0000 720,000.00 720,000.00
Semen portland Kg 6.0000 1,470.00 8,820.00
Pasir pasang M3 0.0100 259,700.00 2,597.00
Perlengkapan % 0.3000 731,417.00 219,425.10
JUMLAH 950,842.10
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,303,195.40
E Overhead & Profit 10% 0.1000 130,319.54
F Harga Satuan Pekerjaan (D+E) - 1,433,514.94

(K4) Pemasangan 1 buah WASTAFELL


A TENAGA
Pekerja L.01.01 OH 1.2000 157,643.00 189,171.60
Tukang batu L.02.03 OH 1.4500 166,729.00 241,757.05
Kepala tukang L.03.01 OH 0.1500 182,676.00 27,401.40
Mandor L.04.01 OH 0.0600 194,274.00 11,656.44
JUMLAH 469,986.49
B BAHAN TENAGA KERJA
Wastafel Unit 1.2000 417,600.00 501,120.00
Semen portland Kg 6.0000 1,470.00 8,820.00
Pasir pasang M3 0.0100 259,700.00 2,597.00
Perlengkapan % 0.1200 512,537.00 61,504.44
JUMLAH 574,041.44
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,044,027.93
E Overhead & Profit 10% 0.1000 104,402.79
F Harga Satuan Pekerjaan (D+E) - 1,148,430.72

Pasang Head Shower+fleksibel Komplit 1 buah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 21,047.46
B BAHAN TENAGA KERJA
Head Shower dan fleksible Bh 1.0000 312,000.00 312,000.00
Sealtape Bh 0.0250 20,160.00 504.00
JUMLAH 312,504.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -

Page 98 of 162
ANALISA ARSITEKTUR

D Jumlah (A+B+C) - 333,551.46


E Overhead & Profit 10% 0.1000 33,355.15
F Harga Satuan Pekerjaan (D+E) - 366,906.61

Pasang Jet Shower+fleksibel Komplit 1 buah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 21,047.46
B BAHAN TENAGA KERJA
Jet Shower Bh 1.0000 273,600.00 273,600.00
Sealtape Bh 0.0250 20,160.00 504.00
JUMLAH 274,104.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 295,151.46
E Overhead & Profit 10% 0.1000 29,515.15
F Harga Satuan Pekerjaan (D+E) - 324,666.61

Pasang kran 1/2" 1 buah


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 21,047.46
B BAHAN TENAGA KERJA
Kran 1/2" Bh 1.0000 148,800.00 148,800.00
Sealtape Bh 0.0250 20,160.00 504.00
JUMLAH 149,304.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 170,351.46
E Overhead & Profit 10% 0.1000 17,035.15
F Harga Satuan Pekerjaan (D+E) - 187,386.61

Pemasangan 1 bh bak cuci piring stainleestel


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0300 157,643.00 4,729.29
Tukang batu L.02.03 OH 0.3000 166,729.00 50,018.70
Kepala tukang L.03.01 OH 0.0300 182,676.00 5,480.28
Mandor L.04.01 OH 0.0150 194,274.00 2,914.11
JUMLAH 63,142.38
B BAHAN TENAGA KERJA
Bak cuci piring Unit 1.0000 235,200.00 235,200.00
Waterdrain Bh 1.0000 43,200.00 43,200.00
JUMLAH 278,400.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 341,542.38
E Overhead & Profit 10% 0.1000 34,154.24
F Harga Satuan Pekerjaan (D+E) - 375,696.62

Page 99 of 162
ANALISA ARSITEKTUR

Pemasangan 1 buah floor drain


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 157,643.00 1,576.43
Tukang batu L.02.03 OH 0.1000 166,729.00 16,672.90
Kepala tukang L.03.01 OH 0.0100 182,676.00 1,826.76
Mandor L.04.01 OH 0.0050 194,274.00 971.37
JUMLAH 21,047.46
B BAHAN TENAGA KERJA
Floor drain Unit 1.0000 120,000.00 120,000.00
JUMLAH 120,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 141,047.46
E Overhead & Profit 10% 0.1000 14,104.75
F Harga Satuan Pekerjaan (D+E) - 155,152.21

Pemasangan 1 buah Roof drain


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0100 - -
Tukang batu L.02.03 OH 0.1000 157,643.00 15,764.30
Kepala tukang L.03.01 OH 0.0100 166,729.00 1,667.29
Mandor L.04.01 OH 0.0050 182,676.00 913.38
JUMLAH 18,344.97
B BAHAN TENAGA KERJA
Rooff drain Unit 1.0000 215,000.00 215,000.00
JUMLAH 215,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 233,344.97
E Overhead & Profit 10% 0.1000 23,334.50
F Harga Satuan Pekerjaan (D+E) - 256,679.47

Page 100 of 162


ANALISA STRUKTUR

ANALISA LINGKUP HARGA BAHAN DAN UPAH


PEKERJAAN STRUKTUR
URUSAN PEMERINTAHAN : 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

Pengukuran dan pemasangan 1 m’ Bouwplank


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.10 157,643.00 15,764.30
Tukang Kayu L.02.04 OH 0.10 166,729.00 16,672.90
Kepala Tukang L.03.01 OH 0.01 182,676.00 1,826.76
Mandor L.04.01 OH 0.01 194,274.00 971.37
JUMLAH 35,235.33
B BAHAN TENAGA KERJA - -
Kayu balok 5/7 m3 0.01 2,950,000.00 36,580.00
Paku 2”-3” Kg 0.02 28,420.00 568.40
Kayu papan bekisting 3/20 m3 0.01 1,050,000.00 7,350.00
JUMLAH 44,498.40
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 79,733.73
E Overhead & Profit 10% 0.10 7,973.37
F Harga Satuan Pekerjaan (D+E) - 87,707.10

(K3) Pembuatan 1 m2 kantor sementara lantai plesteran


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 2.00 157,643.00 315,286.00
Tukang Kayu L.02.04 OH 2.00 166,729.00 333,458.00
Tukang batu L.02.03 OH 1.00 166,729.00 166,729.00
Kepala Tukang L.03.01 OH 0.30 182,676.00 54,802.80
Mandor L.04.01 OH 0.05 194,274.00 9,713.70
JUMLAH 879,989.50
B BAHAN TENAGA KERJA - -
Dolken kayu Ø 8-10/400 cm Batang 1.25 10,000.00 12,500.00
Kayu balok 5/7 m3 0.18 2,950,000.00 531,000.00
Paku biasa Kg 0.08 28,420.00 2,273.60
Besi strip Kg 1.10 12,740.00 14,014.00
Semen portland Kg 35.00 1,470.00 51,450.00
Pasir pasang m3 0.15 259,700.00 38,955.00
Pasir beton m3 0.10 274,400.00 27,440.00
Koral beton m3 0.15 249,900.00 37,485.00
Bata merah Bh 30.00 637.00 19,110.00
Seng plat Lbr 0.25 34,300.00 8,575.00
Jendela naco Bh 0.20 441,000.00 88,200.00
Kaca polos m2 0.08 235,200.00 18,816.00
Kunci tanam Bh 0.15 144,000.00 21,600.00
Plywood 4 mm Lbr 0.06 85,000.00 5,100.00
JUMLAH 876,518.60
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,756,508.10
E Overhead & Profit 10% 0.10 175,650.81

Page 101 of 162


ANALISA STRUKTUR

F Harga Satuan Pekerjaan (D+E) - 1,932,158.91

Membuat 1 m2 Los kerja / Gudang


B BAHAN
Kayu Klas III 0.100 m³ 2,950,000.00 295,000.00
Paku 5 - 7 0.250 kg 28,420.00 7,105.00
Seng Glb BJLS 28 1.100 lbr 181,300.00 199,430.00
Triplex 4 mm 0.500 lbr 85,000.00 42,500.00
PC (50 kg) 0.100 zak 1,470.00 147.00
Peralatan 0.025 lot 544,182.00 13,604.55

Ongkos Pasang 0.125 ls 557,786.55 69,723.32

D Jumlah (A+B+C) - 627,509.87


E Overhead & Profit 10% 0.10 62,750.99
F Harga Satuan Pekerjaan (D+E) - 690,260.86

(K3) Pembersihan 1 m2 lapangan dan perataan


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA -
Pekerja L.01.01 OH 0.10 157,643.00 15,764.30
Mandor L.04.01 OH 0.05 194,274.00 9,713.70
JUMLAH 25,478.00
B BAHAN TENAGA KERJA -
JUMLAH
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 25,478.00
E Overhead & Profit 10% 0.10 2,547.80
F Harga Satuan Pekerjaan (D+E) - 28,025.80

HARGA SATUAN PEKERJAAN TANAH


Penggalian 1 m3 tanah biasa sedalam 1 m
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.75 157,643.00 118,232.25
Mandor L.04.01 OH 0.03 194,274.00 4,856.85
JUMLAH 123,089.10
B BAHAN TENAGA KERJA - -
JUMLAH -
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 123,089.10
E Overhead & Profit 10% 0.10 12,308.91
F Harga Satuan Pekerjaan (D+E) - 135,398.01

Penggalian 1 m3 tanah biasa sedalam 2 m


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.90 157,643.00 141,878.70
Mandor L.04.01 OH 0.05 194,274.00 8,742.33
JUMLAH 150,621.03
B BAHAN TENAGA KERJA - -
JUMLAH -
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 150,621.03
E Overhead & Profit 10% 0.10 15,062.10
F Harga Satuan Pekerjaan (D+E) - 165,683.13

Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedalam 1 M


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)

Page 102 of 162


ANALISA STRUKTUR

A TENAGA - -
Pekerja L.01.01 OH 0.25 157,643.00 39,410.75
Mandor L.04.01 OH 0.03 194,274.00 4,856.85
JUMLAH 44,267.60
B BAHAN TENAGA KERJA - -
JUMLAH -
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 44,267.60
E Overhead & Profit 10% 0.10 4,426.76
F Harga Satuan Pekerjaan (D+E) - 48,694.36

(K3) Pemadatan tanah 1 m3 tanah ( per 20 cm)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.50 157,643.00 78,821.50
Mandor L.04.01 OH 0.05 194,274.00 9,713.70
JUMLAH 88,535.20
B BAHAN TENAGA KERJA - -
JUMLAH -
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 88,535.20
E Overhead & Profit 10% 0.10 8,853.52
F Harga Satuan Pekerjaan (D+E) - 97,388.72

Pengurugan 1 m3 dengan pasir urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.30 157,643.00 47,292.90
Mandor L.04.01 OH 0.01 194,274.00 1,942.74
JUMLAH 49,235.64
B BAHAN TENAGA KERJA - -
Pasir urug M3 1.20 210,700.00 252,840.00
JUMLAH 252,840.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 302,075.64
E Overhead & Profit 10% 0.10 30,207.56
F Harga Satuan Pekerjaan (D+E) - 332,283.20

Pengurugan 1 m3 dengan tanah urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.30 157,643.00 47,292.90
Mandor L.04.01 OH 0.01 194,274.00 1,942.74
JUMLAH 49,235.64
B BAHAN TENAGA KERJA - -
tanah urug M3 1.20 122,500.00 147,000.00
JUMLAH 147,000.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 196,235.64
E Overhead & Profit 10% 0.10 19,623.56
F Harga Satuan Pekerjaan (D+E) - 215,859.20

Pengurugan 1 m3 dengan sirtu padat


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.25 157,643.00 39,410.75
Mandor L.04.01 OH 0.03 194,274.00 4,856.85
JUMLAH 44,267.60
TENAGA KERJA

Page 103 of 162


ANALISA STRUKTUR

B BAHAN - -
Sirtu m3 1.20 235,200.00 282,240.00
JUMLAH 282,240.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 326,507.60
E Overhead & Profit 10% 0.10 32,650.76
F Harga Satuan Pekerjaan (D+E) - 359,158.36

HARGA SATUAN PEKERJAAN PONDASI


1 m' Pasang Pagar Beton Precast, t = 2,00 m, 5 Panel, panjang kolom 3m, mutu beton K-225
Bahan
Pagar Beton Pracetak, t = 2M 1.042 Lbr 230,300.00 239,903.51
Kolom beton pracetak 160 x 120 x 3.000 mm 0.525 Btg 401,800.00 210,945.00
Pasir Beton 0.074 M3 259,700.00 19,217.80
Batu Pecah/Split (Pecah Mesin) ukr. 2 - 3 cm 0.146 M3 240,100.00 35,054.60
Semen Tiga Roda 50 kg 45.000 Kg 1,470.00 66,150.00

Tenaga 0.375 Oh 157,643.00 59,116.13


Pekerja 0.125 Oh 166,729.00 20,841.13
Tukang Batu 0.012 Oh 182,676.00 2,192.11
Kepala Tukang 0.019 Oh 194,274.00 3,691.21
Mandor

PERALATAN
Chain Block 0.167 Jam 250,000.00 41,750.00

D Jumlah (A+B+C) - 698,861.48


E Overhead & Profit 10% 0.10 69,886.15
F Harga Satuan Pekerjaan (D+E) - 768,747.63

Pemasangan 1 m3 pondasi batu belah campuran 1SP : 6PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.50 157,643.00 236,464.50
Tukang Batu L.02.03 OH 0.75 166,729.00 125,046.75
Kepala Tukang L.03.01 OH 0.08 182,676.00 13,700.70
Mandor L.04.01 OH 0.08 194,274.00 14,570.55
JUMLAH 389,782.50
B BAHAN TENAGA KERJA - -
Batu belah m3 1.20 254,800.00 305,760.00
Semen portland Kg 163.00 1,470.00 239,610.00
Pasir Pasang m3 0.52 259,700.00 135,044.00
JUMLAH 680,414.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,070,196.50
E Overhead & Profit 10% 0.10 107,019.65
F Harga Satuan Pekerjaan (D+E) - 1,177,216.15

Pemasangan 1 m' Pemancangan Menggunakan Hydraulic (Jacking Pile)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.05 157,643.00 7,882.15
Mandor L.04.01 OH 0.03 194,274.00 5,828.22
JUMLAH 13,710.37
B BAHAN TENAGA KERJA - -
JUMLAH
C PERALATAN HARGA BAHAN - -
Sewa hydraulic jack jam 0.12 600,000.00 70,200.00
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 83,910.37

Page 104 of 162


ANALISA STRUKTUR

E Overhead & Profit 10% 0.10 8,391.04


F Harga Satuan Pekerjaan (D+E) - 92,301.41

Pemasangan 1 titik Pemotongan kepala tiang pancang


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.43 157,643.00 67,786.49
Tukang las OH 0.26 166,729.00 43,349.54
Mandor L.04.01 OH 0.03 194,274.00 5,828.22
JUMLAH 116,964.25
B BAHAN TENAGA KERJA - -
JUMLAH
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 116,964.25
E Overhead & Profit 10% 0.10 11,696.43
F Harga Satuan Pekerjaan (D+E) - 128,660.68

Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95
Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48
Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93
Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 247.00 1,470.00 363,090.00
Pasir Beton kg 869.00 196.00 170,324.00
Kerikil (Maks 30 mm) kg 999.00 185.11 184,926.00
Air Liter 215.00 196.00 42,140.00
JUMLAH 760,480.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,087,681.10
E Overhead & Profit 10% 0.10 108,768.11
F Harga Satuan Pekerjaan (D+E) - 1,196,449.20

Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95
Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48
Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93
Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 276.00 1,470.00 405,720.00
Pasir Beton kg 828.00 196.00 162,288.00
Kerikil (Maks 30 mm) kg 1,012.00 185.11 187,332.44
Air Liter 215.00 196.00 42,140.00
JUMLAH 797,480.44
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,124,681.54
E Overhead & Profit 10% 0.10 112,468.15
F Harga Satuan Pekerjaan (D+E) - 1,237,149.69

Membuat 1 m3 beton mutu f’= 12,2 MPa (K 150)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95

Page 105 of 162


ANALISA STRUKTUR

Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48


Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93
Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 299.00 1,470.00 439,530.00
Pasir Beton kg 799.00 196.00 156,604.00
Kerikil (Maks 30 mm) kg 1,017.00 185.11 188,258.00
Air Liter 215.00 196.00 42,140.00
JUMLAH 826,532.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,153,733.10
E Overhead & Profit 10% 0.10 115,373.31
F Harga Satuan Pekerjaan (D+E) - 1,269,106.40
CATATAN
Bobot isi pasir = 1.400 kg/m3, Bobot isi kerikil = 1.350 kg/m3, Buckling factor pasir = 20 %
Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.20 157,643.00 189,171.60
Tukang Batu L.02.03 OH 0.20 166,729.00 33,345.80
Kepala Tukang L.03.01 OH 0.02 182,676.00 3,653.52
Mandor L.04.01 OH 0.06 194,274.00 11,656.44
JUMLAH 237,827.36
B BAHAN TENAGA KERJA
Semen portland kg 230.00 1,470.00 338,100.00
Pasir Beton kg 893.00 196.00 175,028.00
Kerikil (Maks 30 mm) kg 1,027.00 185.11 190,109.11
Air Liter 200.00 196.00 39,200.00
JUMLAH 742,437.11
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 980,264.47
E Overhead & Profit 10% 0.10 98,026.45
F Harga Satuan Pekerjaan (D+E) - 1,078,290.92

Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (12 ±2) cm, w/c = 0,66
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95
Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48
Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93
Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 326.00 1,470.00 479,220.00
Pasir Beton kg 760.00 196.00 148,960.00
Kerikil (Maks 30 mm) kg 1,029.00 185.11 190,479.33
Air Liter 215.00 196.00 42,140.00
JUMLAH 860,799.33
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,188,000.43
E Overhead & Profit 10% 0.10 118,800.04
F Harga Satuan Pekerjaan (D+E) - 1,306,800.47

Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95
Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48

Page 106 of 162


ANALISA STRUKTUR

Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93


Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 352.00 1,470.00 517,440.00
Pasir Beton kg 731.00 196.00 143,276.00
Kerikil (Maks 30 mm) kg 1,031.00 185.11 190,849.56
Air Liter 215.00 196.00 42,140.00
JUMLAH 893,705.56
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,220,906.65
E Overhead & Profit 10% 0.10 122,090.67
F Harga Satuan Pekerjaan (D+E) - 1,342,997.32

Membuat 1 m3 beton mutu f’= 21,7 MPa (K 250), slump (120 ± 20) mm, w/c = 0,56
A TENAGA
Pekerja L.01.01 OH 1.65 157,643.00 260,110.95
Tukang Batu L.02.03 OH 0.28 166,729.00 45,850.48
Kepala Tukang L.03.01 OH 0.03 182,676.00 5,114.93
Mandor L.04.01 OH 0.08 194,274.00 16,124.74
JUMLAH 327,201.10
B BAHAN TENAGA KERJA
Semen portland kg 384.00 1,470.00 564,480.00
Pasir Beton kg 692.00 196.00 135,632.00
Kerikil (Maks 30 mm) kg 1,039.00 185.11 192,330.44
Air Liter 215.00 196.00 42,140.00
JUMLAH 934,582.44
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,261,783.54
E Overhead & Profit 10% 0.10 126,178.35
F Harga Satuan Pekerjaan (D+E) - 1,387,961.89

1 m3 beton readymix (K 250), slump (120 ± 20) mm, w/c = 0,56 dan pompa beton
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.00 157,643.00 157,643.00
Tukang Batu L.02.03 OH 0.25 166,729.00 41,682.25
Kepala Tukang L.03.01 OH 0.03 182,676.00 4,566.90
Mandor L.04.01 OH 0.10 194,274.00 19,427.40
JUMLAH 223,319.55
B BAHAN TENAGA KERJA
Campuran beton readymix K250 m3 1.02 823,200.00 839,664.00
JUMLAH 839,664.00
C PERALATAN HARGA BAHAN
Pompa dan conveyor beton (sewa) M3 0.05 1,500,000.00 75,000.00
JUMLAH HARGA ALAT 75,000.00
D Jumlah (A+B+C) - 1,137,983.55
E Overhead & Profit 10% 0.10 113,798.36
F Harga Satuan Pekerjaan (D+E) - 1,251,781.91

1 m3 beton readymix (K 350), slump (120 ± 20) mm, w/c = 0,56 dan pompa beton
No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.00 157,643.00 157,643.00
Tukang Batu L.02.03 OH 0.25 166,729.00 41,682.25
Kepala Tukang L.03.01 OH 0.03 182,676.00 4,566.90
Mandor L.04.01 OH 0.10 194,274.00 19,427.40
JUMLAH 223,319.55
B BAHAN TENAGA KERJA
Campuran beton readymix K350 m3 1.02 907,480.00 925,629.60

Page 107 of 162


ANALISA STRUKTUR

JUMLAH 925,629.60
C PERALATAN HARGA BAHAN
Pompa dan conveyor beton (sewa) hari 0.12 249,900.00 29,988.00
JUMLAH HARGA ALAT 29,988.00
D Jumlah (A+B+C) - 1,178,937.15
E Overhead & Profit 10% 0.10 117,893.72
F Harga Satuan Pekerjaan (D+E) - 1,296,830.87

Pembesian 10 kg dengan besi polos


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.07 157,643.00 11,035.01
Tukang Besi L.02.05 OH 0.07 166,729.00 11,671.03
Kepala Tukang L.03.01 OH 0.01 182,676.00 1,278.73
Mandor L.04.01 OH 0.00 194,274.00 777.10
JUMLAH 24,761.87
B BAHAN TENAGA KERJA
Besi beton (polos) kg 10.50 10,584.00 111,132.00
Kawat beton kg 0.15 29,400.00 4,410.00
JUMLAH 115,542.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 140,303.87
E Overhead & Profit 10% 0.10 14,030.39
F Harga Satuan Pekerjaan (D+E) - 154,334.25
Pembesian 1 kg dengan besi polos 15,433.43

Pembesian 10 kg dengan besi ulir


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.07 157,643.00 11,035.01
Tukang Besi L.02.05 OH 0.07 166,729.00 11,671.03
Kepala Tukang L.03.01 OH 0.01 182,676.00 1,278.73
Mandor L.04.01 OH 0.00 194,274.00 777.10
JUMLAH 24,761.87
B BAHAN TENAGA KERJA
Besi beton (ulir) kg 10.50 10,780.00 113,190.00
Kawat beton kg 0.15 29,400.00 4,410.00
JUMLAH 117,600.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 142,361.87
E Overhead & Profit 10% 0.10 14,236.19
F Harga Satuan Pekerjaan (D+E) - 156,598.05
Pembesian 1 kg dengan besi ulir 15,659.81

Pemasangan 10 kg jaring kawat baja (wiremesh)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.03 157,643.00 3,941.08
Tukang Besi L.02.05 OH 0.03 166,729.00 4,168.23
Kepala Tukang L.03.01 OH 0.03 182,676.00 4,566.90
Mandor L.04.01 OH 0.00 194,274.00 194.27
JUMLAH 12,870.47
B BAHAN TENAGA KERJA
Jaring kawat baja dilas kg 10.20 9,310.00 94,962.00
Kawat beton kg 0.05 29,400.00 1,470.00
JUMLAH 96,432.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 109,302.47
E Overhead & Profit 10% 0.10 10,930.25

Page 108 of 162


ANALISA STRUKTUR

F Harga Satuan Pekerjaan (D+E) - 120,232.72


Pemasangan 1 kg jaring kawat baja (wiremesh) 12,023.27

(K3) Pemasangan 1 m2 bekisting untuk pondasi (2x pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.52 157,643.00 81,974.36
Tukang Kayu L.02.04 OH 0.26 166,729.00 43,349.54
Kepala Tukang L.03.01 OH 0.03 182,676.00 4,749.58
Mandor L.04.01 OH 0.03 194,274.00 5,051.12
JUMLAH 135,124.60
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.04 1,050,000.00 42,000.00
Paku 5 - 10 cm kg 0.30 28,420.00 8,526.00
Minyak bekisting Liter 0.10 3,430.00 343.00
JUMLAH 50,869.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 185,993.60
E Overhead & Profit 10% 0.10 18,599.36
F Harga Satuan Pekerjaan (D+E) - 204,592.96

(K3) Pemasangan 1 m2 bekisting untuk sloof (2x pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.52 157,643.00 81,974.36
Tukang Kayu L.02.04 OH 0.26 166,729.00 43,349.54
Kepala Tukang L.03.01 OH 0.03 182,676.00 4,749.58
Mandor L.04.01 OH 0.03 194,274.00 5,051.12
JUMLAH 135,124.60
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.05 1,050,000.00 47,250.00
Paku 5 - 10 cm kg 0.30 28,420.00 8,526.00
Minyak bekisting Liter 0.10 3,430.00 343.00
JUMLAH 56,119.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 191,243.60
E Overhead & Profit 10% 0.10 19,124.36
F Harga Satuan Pekerjaan (D+E) - 210,367.96

(K3) Pemasangan 1 m2 bekisting untuk kolom (2x pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 157,643.00 104,044.38
Tukang Kayu L.02.04 OH 0.33 166,729.00 55,020.57
Kepala Tukang L.03.01 OH 0.03 182,676.00 6,028.31
Mandor L.04.01 OH 0.03 194,274.00 6,411.04
JUMLAH 171,504.30
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.04 1,050,000.00 42,000.00
Paku 5 - 12 cm kg 0.40 28,420.00 11,368.00
Minyak bekisting Liter 0.20 3,430.00 686.00
Balok kayu kelas II m3 0.02 1,300,000.00 19,500.00
Plywood 9 mm Lbr 0.35 105,000.00 36,750.00
Dolken kayu Ø 8-10/400 cm Batang 2.00 10,000.00 20,000.00
JUMLAH 130,304.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 301,808.30
E Overhead & Profit 10% 0.10 30,180.83
F Harga Satuan Pekerjaan (D+E) - 331,989.13

Page 109 of 162


ANALISA STRUKTUR

(K3) Pemasangan 1 m2 bekisting untuk balok (2X Pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 157,643.00 104,044.38
Tukang Kayu L.02.04 OH 0.33 166,729.00 55,020.57
Kepala Tukang L.03.01 OH 0.03 182,676.00 6,028.31
Mandor L.04.01 OH 0.03 194,274.00 6,411.04
JUMLAH 171,504.30
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.04 1,050,000.00 42,000.00
Paku 5 - 12 cm kg 0.40 28,420.00 11,368.00
Minyak bekisting Liter 0.20 3,430.00 686.00
Balok kayu kelas II m3 0.02 1,300,000.00 23,400.00
Plywood 9 mm Lbr 0.35 105,000.00 36,750.00
Dolken kayu Ø 8-10/400 cm Batang 2.00 10,000.00 20,000.00
JUMLAH 134,204.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 305,708.30
E Overhead & Profit 10% 0.10 30,570.83
F Harga Satuan Pekerjaan (D+E) - 336,279.13

(K3) Pemasangan 1 m2 bekisting untuk lantai (2X Pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 157,643.00 104,044.38
Tukang Kayu L.02.04 OH 0.33 166,729.00 55,020.57
Kepala Tukang L.03.01 OH 0.03 182,676.00 6,028.31
Mandor L.04.01 OH 0.03 194,274.00 6,411.04
JUMLAH 171,504.30
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.04 1,050,000.00 42,000.00
Paku 5 - 12 cm kg 0.40 28,420.00 11,368.00
Minyak bekisting Liter 0.20 3,430.00 686.00
Balok kayu kelas II m3 0.02 1,300,000.00 19,500.00
Plywood 9 mm Lbr 0.35 105,000.00 36,750.00
Dolken kayu Ø 8-10/400 cm Batang 6.00 10,000.00 60,000.00
JUMLAH 170,304.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 341,808.30
E Overhead & Profit 10% 0.10 34,180.83
F Harga Satuan Pekerjaan (D+E) - 375,989.13

(K3) Pemasangan 1 m2 bekisting untuk dinding (2x pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 157,643.00 104,044.38
Tukang Kayu L.02.04 OH 0.33 166,729.00 55,020.57
Kepala Tukang L.03.01 OH 0.03 182,676.00 6,028.31
Mandor L.04.01 OH 0.03 194,274.00 6,411.04
JUMLAH 171,504.30
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.03 1,050,000.00 31,500.00
Paku 5 - 12 cm kg 0.40 28,420.00 11,368.00
Minyak bekisting Liter 0.20 3,430.00 686.00
Balok kayu kelas II m3 0.02 1,300,000.00 26,000.00
Plywood 9 mm Lbr 0.35 105,000.00 36,750.00
Dolken kayu Ø 8-10/400 cm Batang 3.00 10,000.00 30,000.00
Penjaga jarak bekisting / spacer Buah 4.00 5,000.00 20,000.00
JUMLAH 156,304.00
HARGA BAHAN

Page 110 of 162


ANALISA STRUKTUR

C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 327,808.30
E Overhead & Profit 10% 0.10 32,780.83
F Harga Satuan Pekerjaan (D+E) - 360,589.13

(K3) Pemasangan 1 m2 bekisting untuk tangga (2x pakai)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.66 157,643.00 104,044.38
Tukang Kayu L.02.04 OH 0.33 166,729.00 55,020.57
Kepala Tukang L.03.01 OH 0.03 182,676.00 6,028.31
Mandor L.04.01 OH 0.03 194,274.00 6,411.04
JUMLAH 171,504.30
B BAHAN TENAGA KERJA
Kayu kelas III m3 0.03 1,050,000.00 31,500.00
Paku 5 - 12 cm kg 0.40 28,420.00 11,368.00
Minyak bekisting Liter 0.15 3,430.00 514.50
Balok kayu kelas II m3 0.02 1,300,000.00 19,500.00
Plywood 9 mm Lbr 0.35 105,000.00 36,750.00
Dolken kayu Ø 8-10/400 cm Batang 2.00 10,000.00 20,000.00
JUMLAH 119,632.50
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 291,136.80
E Overhead & Profit 10% 0.10 29,113.68
F Harga Satuan Pekerjaan (D+E) - 320,250.48
HARGA SATUAN PEKERJAAN BESI DAN ALUMUNIUM

Pemasangan 1 kg besi profil


A TENAGA
Pekerja L.01.01 OH 0.0600 157,643.00 9,458.58
Tukang Las Konstruksi L.02.10 OH 0.0600 166,729.00 10,003.74
Kepala tukang L.03.01 OH 0.0060 182,676.00 1,096.06
Mandor L.04.01 OH 0.0030 194,274.00 582.82
JUMLAH 21,141.20
B BAHAN TENAGA KERJA
Besi Profil Kg 1.10 12,740.00 14,014.00
JUMLAH 14,014.00
C PERALATAN HARGA BAHAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 35,155.20
E Overhead & Profit 10% 0.10 3,515.52
F Harga Satuan Pekerjaan (D+E) - 38,670.72

Pemasangan 1 kg rangka kuda-kuda baja IWF


No Uraian Kode Satuan Koefisien Harga Satuan (Rp) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0600 157,643.00 9,458.58
Tukang Las Konstruksi L.02.10 OH 0.0600 166,729.00 10,003.74
Kepala tukang L.03.01 OH 0.0060 182,676.00 1,096.06
Mandor L.04.01 OH 0.0030 194,274.00 582.82
JUMLAH 21,141.20
B BAHAN TENAGA KERJA
Besi IWF Kg 1.10 12,740.00 14,014.00
JUMLAH 14,014.00
C PERALATAN HARGA BAHAN
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 35,155.20
E Overhead & Profit 10% 0.10 3,515.52
F Harga Satuan Pekerjaan (D+E) - 38,670.72

Page 111 of 162


ANALISA STRUKTUR

Pengerjaan 100 Kg Pekerjaan Perakitan


A Bahan
Solar ltr 1,000 5,500.00 5,500,000.00
Minyak Pelumas ltr 0,100 4,500.00 450,000.00

B Tenaga
Pekerja Oh 0,100 157,643.00 15,764,300.00
Tukang Las Oh 0,100 166,729.00 16,672,900.00
Kepala Tukang Oh 0,001 182,676.00 182,676.00
Mandor Oh 0,005 194,274.00 971,370.00

C PERALATAN

D Jumlah (A+B+C) - 39,541,246.00


E Overhead & Profit 10% 0.10 3,954,124.60
F Harga Satuan Pekerjaan (D+E) - 43,495,370.60
Pengerjaan 1 Kg Pekerjaan Perakitan 434,953.7060

1 M2 Pekerjaan Bondex, tebal 0,75 mm


A Bahan
Plat bondeks m2 1 125,000.00 125,000.00

B Tenaga
Pekerja Oh 0.15 157,643.00 23,646.45
Tukang Las Oh 0.15 166,729.00 25,009.35
Kepala Tukang Oh 0.03 182,676.00 5,480.28
Mandor Oh 0.001 194,274.00 194.27

C PERALATAN lot 0.01 125,000.00 1,250.00

D Jumlah (A+B+C) - 180,580.35


E Overhead & Profit 10% 0.10 18,058.04
F Harga Satuan Pekerjaan (D+E) - 198,638.39

Membuat 1 m’ kolom praktis beton bertulang (11 x 11) cm


A Bahan
Kayu kelas III m³ 0.002 1,300,000.00 2,600.00
Paku 5-12 cm kg 0.010 28,420.00 284.20
Besi beton polos kg 3.000 10,780.00 32,340.00
Kawat beton kg 0.045 29,400.00 1,323.00
Portland Cement kg 4.000 1,470.00 5,880.00
Pasir Beton m³ 0.006 274,400.00 1,646.40
Split Pecah mesin 2/3 m³ 0.009 249,900.00 2,249.10

- -

B Tenaga
Pekerja Oh 0.180 157,643.00 28,375.74
Tukang batu Oh 0.020 166,729.00 3,334.58
Tukang kayu Oh 0.020 166,729.00 3,334.58
Tukang besi Oh 0.020 166,729.00 3,334.58
Kepala tukang Oh 0.006 182,676.00 1,096.06
Mandor Oh 0.009 194,274.00 1,748.47

C PERALATAN -

D Jumlah (A+B+C) - 87,546.70


E Overhead & Profit 10% 0.10 8,754.67
F Harga Satuan Pekerjaan (D+E) - 96,301.37

Page 112 of 162


ANALISA STRUKTUR

Membuat 1 m’ ring balok beton bertulang (10 x 15) cm


A Bahan
Kayu kelas III m³ 0.003 1,300,000.00 3,900.00
Paku 5-12 cm kg 0.020 28,420.00 568.40
Besi beton polos kg 3.600 10,780.00 38,808.00
Kawat beton kg 0.050 29,400.00 1,470.00
Portland Cement kg 5.500 1,470.00 8,085.00
Pasir Beton m³ 0.009 274,400.00 2,469.60
Split Pecah mesin 2/3 m³ 0.015 249,900.00 3,748.50

B Tenaga
Pekerja Oh 0.297 157,643.00 46,819.97
Tukang batu Oh 0.033 166,729.00 5,502.06
Tukang kayu Oh 0.033 166,729.00 5,502.06
Tukang besi Oh 0.033 166,729.00 5,502.06
Kepala tukang Oh 0.010 182,676.00 1,826.76
Mandor Oh 0.015 194,274.00 2,914.11

C PERALATAN

D Jumlah (A+B+C) 127,116.51


E Overhead & Profit 10% 12,711.65
F Harga Satuan Pekerjaan (D+E) 139,828.16

Page 113 of 162


ANALISA ELEKTRIKAL

ANALISA HARGA BAHAN DAN UPAH


PEKERJAAN : ELEKTRIKAL
URUSAN PEMERINTAHAN : 1.11 / Lingkup Hidup
Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019 / Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


A PEKERJAAN LISTRIK

I PEKERJAAN KABEL FEEDER


1 NYFGBY 4 x 25 mm 1.000 Meter 295,000.00 295,000.00
- Perlengkapan 1.000 Meter 44,250.00 44,250.00
Jumlah - 339,250.00
Upah :
Pekerja Listrik 0.070 hr 157,643.00 11,035.01
Tukang Listrik 0.050 hr 166,729.00 8,336.45
Kepala tukang Listrik 0.035 hr 182,676.00 6,393.66
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 28,679.23
Total - 367,929.23
Overhead & Profit 10% 0.10 36,792.92
Total Harga Satuan Pekerjaan - 404,722.15

2 - NYY 4 x 35 MM² 1.000 Meter 277,200.00 277,200.00


- Perlengkapan 1.000 Meter 41,580.00 41,580.00
Jumlah - 318,780.00
Upah :
Pekerja Listrik 0.060 hr 157,643.00 9,458.58
Tukang Listrik 0.045 hr 166,729.00 7,502.81
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 25,355.78
Total - 344,135.78
Overhead & Profit 10% 0.10 34,413.58
Total Harga Satuan Pekerjaan - 378,549.35
2 - NYY 4 x 25 MM² 1.000 Meter 204,000.00 204,000.00
- Perlengkapan 1.000 Meter 30,600.00 30,600.00
Jumlah - 234,600.00
Upah :
Pekerja Listrik 0.060 hr 157,643.00 9,458.58
Tukang Listrik 0.045 hr 166,729.00 7,502.81
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 25,355.78
Total - 259,955.78
Overhead & Profit 10% 0.10 25,995.58
Total Harga Satuan Pekerjaan - 285,951.35
2 - NYY 4 x 6 MM² 1.000 Meter 44,400.00 44,400.00
- Perlengkapan 1.000 Meter 6,660.00 6,660.00
Jumlah - 51,060.00
Upah :
Pekerja Listrik 0.060 hr 157,643.00 9,458.58
Tukang Listrik 0.045 hr 166,729.00 7,502.81
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 25,355.78
Total - 76,415.78
Overhead & Profit 10% 0.10 7,641.58
Total Harga Satuan Pekerjaan - 84,057.35

3 - NYY 4 x 16 MM² 1.000 Meter 133,200.00 133,200.00


- Perlengkapan 1.000 Meter 19,980.00 19,980.00

Page 114 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah - 153,180.00
Upah :
Pekerja Listrik 0.050 hr 157,643.00 7,882.15
Tukang Listrik 0.035 hr 166,729.00 5,835.52
Kepala tukang Listrik 0.020 hr 182,676.00 3,653.52
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 20,285.30
Total - 173,465.30
Overhead & Profit 10% 0.10 17,346.53
Total Harga Satuan Pekerjaan - 190,811.82

4 - NYY 4 x 10 MM² 1.000 Meter 117,600.00 117,600.00


- Perlengkapan 1.000 Meter 17,640.00 17,640.00
Jumlah - 135,240.00
Upah :
Pekerja Listrik 0.050 hr 157,643.00 7,882.15
Tukang Listrik 0.035 hr 166,729.00 5,835.52
Kepala tukang Listrik 0.020 hr 182,676.00 3,653.52
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 20,285.30
Total - 155,525.30
Overhead & Profit 10% 0.10 15,552.53
Total Harga Satuan Pekerjaan - 171,077.82

5 - FRC 4 x 4 MM² 1.000 Meter 78,000.00 78,000.00


- Perlengkapan 1.000 Meter 11,700.00 11,700.00
Jumlah - 89,700.00
Upah :
Pekerja Listrik 0.050 hr 157,643.00 7,882.15
Tukang Listrik 0.035 hr 166,729.00 5,835.52
Kepala tukang Listrik 0.020 hr 182,676.00 3,653.52
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 20,285.30
Total - 109,985.30
Overhead & Profit 10% 0.10 10,998.53
Total Harga Satuan Pekerjaan Total - 120,983.82

6 - NYY 4 x 4 MM² 1.000 Meter 18,000.00 18,000.00


- Perlengkapan 1.000 Meter 2,700.00 2,700.00
Jumlah 20,700.00
Upah :
Pekerja Listrik 0.050 hr 157,643.00 7,882.15
Tukang Listrik 0.035 hr 166,729.00 5,835.52
Kepala tukang Listrik 0.020 hr 182,676.00 3,653.52
Mandor Listrik 0.015 hr 194,274.00 2,914.11
Jumlah - 20,285.30
Total - 40,985.30
Overhead & Profit 10% 0.10 4,098.53
Total Harga Satuan Pekerjaan Total - 45,083.82

5 - Cable Tray 10 x 5 Cm ( Hot Dip Galvanized) 1.000 Meter 90,000.00 90,000.00


- Perlengkapan 1.000 Meter 13,500.00 13,500.00
Jumlah 103,500.00
Upah :
Pekerja Listrik 0.350 hr 157,643.00 55,175.05
Tukang Listrik 0.150 hr 166,729.00 25,009.35
Kepala tukang Listrik 0.075 hr 182,676.00 13,700.70
Mandor Listrik 0.030 hr 194,274.00 5,828.22
Jumlah - 99,713.32
Total - 203,213.32
Overhead & Profit 10% 0.10 20,321.33
Total Harga Satuan Pekerjaan Total - 223,534.65

6 - Cable Tray 40 x 10 Cm 1.000 Meter 222,000.00 222,000.00


- Perlengkapan 1.000 Meter 33,300.00 33,300.00

Page 115 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah 255,300.00
Upah :
Pekerja Listrik 0.350 hr 157,643.00 55,175.05
Tukang Listrik 0.150 hr 166,729.00 25,009.35
Kepala tukang Listrik 0.075 hr 182,676.00 13,700.70
Mandor Listrik 0.030 hr 194,274.00 5,828.22
Jumlah - 99,713.32
Total - 355,013.32
Overhead & Profit 10% 0.10 35,501.33
Total Harga Satuan Pekerjaan Total - 390,514.65

7 Cable Tray Joint T100X100X50 1.000 Meter 547,200.00 547,200.00


- Perlengkapan 1.000 Meter 82,080.00 82,080.00
Jumlah 629,280.00
Upah :
Pekerja Listrik 0.350 hr 157,643.00 55,175.05
Tukang Listrik 0.150 hr 166,729.00 25,009.35
Kepala tukang Listrik 0.075 hr 182,676.00 13,700.70
Mandor Listrik 0.030 hr 194,274.00 5,828.22
Jumlah - 99,713.32
Total - 728,993.32
Overhead & Profit 10% 0.10 72,899.33
Total Harga Satuan Pekerjaan Total - 801,892.65

8 Cable Tray Joint L400X400X100 1.000 Meter 78,000.00 78,000.00


- Perlengkapan 1.000 Meter 11,700.00 11,700.00
Jumlah 89,700.00
Upah :
Pekerja Listrik 0.350 hr 157,643.00 55,175.05
Tukang Listrik 0.150 hr 166,729.00 25,009.35
Kepala tukang Listrik 0.075 hr 182,676.00 13,700.70
Mandor Listrik 0.030 hr 194,274.00 5,828.22
Jumlah - 99,713.32
Total - 189,413.32
Overhead & Profit 10% 0.10 18,941.33
Total Harga Satuan Pekerjaan Total - 208,354.65

9 Cable Tray Joint L100X100X50 1.000 Meter 547,200.00 547,200.00


- Perlengkapan 1.000 Meter 82,080.00 82,080.00
Jumlah 629,280.00
Upah :
Pekerja Listrik 0.350 hr 157,643.00 55,175.05
Tukang Listrik 0.150 hr 166,729.00 25,009.35
Kepala tukang Listrik 0.075 hr 182,676.00 13,700.70
Mandor Listrik 0.030 hr 194,274.00 5,828.22
Jumlah - 99,713.32
Total - 728,993.32
Overhead & Profit 10% 0.10 72,899.33
Total Harga Satuan Pekerjaan Total - 801,892.65

III ARMATURE , SAKLAR DAN STOP KONTAK


1 RMI (LED TUBE LAMP) 2x16 W Dimension 1200mm 1.000 bh 420,000.00 420,000.00
- Perlengkapan 1.000 bh 63,000.00 63,000.00
Jumlah 483,000.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 532,685.11
Overhead & Profit 10% 0.10 53,268.51
Total Harga Satuan Pekerjaan Total - 585,953.62

2 Lampu Down Light PLC 18 W 1.000 bh 150,000.00 150,000.00

Page 116 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


- Perlengkapan 1.000 bh 22,500.00 22,500.00
Jumlah 172,500.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 222,185.11
Overhead & Profit 10% 0.10 22,218.51
Total Harga Satuan Pekerjaan Total - 244,403.62

3 Lampu LP HARR HLG 120 W 1.000 bh 528,000.00 528,000.00


- Perlengkapan 1.000 bh 79,200.00 79,200.00
Jumlah 607,200.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 656,885.11
Overhead & Profit 10% 0.10 65,688.51
Total Harga Satuan Pekerjaan Total - 722,573.62

4 Lampu LB T5 2X18 W 1.000 bh 384,000.00 384,000.00


- Perlengkapan 1.000 bh 57,600.00 57,600.00
Jumlah 441,600.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 491,285.11
Overhead & Profit 10% 0.10 49,128.51
Total Harga Satuan Pekerjaan Total - 540,413.62

5 Wall Light 9x9 LED BULB E27 8 Watt 1.000 bh 258,000.00 258,000.00
- Perlengkapan 1.000 bh 25,800.00 25,800.00
Inbow Doos 1.000 bh 18,000.00 18,000.00
Jumlah 301,800.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 351,485.11
Overhead & Profit 10% 0.10 35,148.51
Total Harga Satuan Pekerjaan Total - 386,633.62

5 Saklar Tunggal 10 A 1.000 bh 54,000.00 54,000.00


- Perlengkapan 1.000 bh 5,400.00 5,400.00
Inbow Doos 1.000 bh 18,000.00 18,000.00
Jumlah 77,400.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 127,085.11
Overhead & Profit 10% 0.10 12,708.51
Total Harga Satuan Pekerjaan Total - 139,793.62

Page 117 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

6 Stop kontak 1.000 bh 112,800.00 112,800.00


- Perlengkapan 1.000 bh 11,280.00 11,280.00
Inbow Doos 1.000 bh 18,000.00 18,000.00
Jumlah 142,080.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 191,765.11
Overhead & Profit 10% 0.10 19,176.51
Total Harga Satuan Pekerjaan Total - 210,941.62

6 Saklar Seri 10 A 1.000 bh 90,000.00 90,000.00


- Perlengkapan 1.000 bh 9,000.00 9,000.00
Inbow Doos 1.000 bh 18,000.00 18,000.00
Jumlah 117,000.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 166,685.11
Overhead & Profit 10% 0.10 16,668.51
Total Harga Satuan Pekerjaan Total - 183,353.62

7 Stop Kontak AC 1.000 bh 294,000.00 294,000.00


- Perlengkapan 1.000 bh 29,400.00 29,400.00
Inbow Doos 1.000 bh 18,000.00 18,000.00
Jumlah 341,400.00
Upah :
Pekerja Listrik 0.150 hr 157,643.00 23,646.45
Tukang Listrik 0.100 hr 166,729.00 16,672.90
Kepala tukang Listrik 0.030 hr 182,676.00 5,480.28
Mandor Listrik 0.020 hr 194,274.00 3,885.48
Jumlah - 49,685.11
Total - 391,085.11
Overhead & Profit 10% 0.10 39,108.51
Total Harga Satuan Pekerjaan Total - 430,193.62

8 PJU LED 80 Watt IP66 C/W Pole 9 Meter 1.000 bh 13,800,000.00 13,800,000.00
- Perlengkapan 1.000 bh 1,380,000.00 1,380,000.00
Jumlah 15,180,000.00
Upah :
Pekerja Listrik 0.650 hr 157,643.00 102,467.95
Tukang Listrik 0.550 hr 166,729.00 91,700.95
Kepala tukang Listrik 0.200 hr 182,676.00 36,535.20
Mandor Listrik 0.100 hr 194,274.00 19,427.40
Jumlah - 250,131.50
Total - 15,430,131.50
Overhead & Profit 10% 0.10 1,543,013.15
Total Harga Satuan Pekerjaan Total - 16,973,144.65
Instalasi Penerangan :
9
- Kabel NYM 3 X 2,5 mm 8.000 meter 15,120.00 120,960.00
- Pipa Conduit PVC HI 20 mm 8.000 Meter 3,000.00 24,000.00

- Socket Pipa 2.000 Buah 6,600.00 13,200.00


- Tee Dos 2.000 Buah 3,840.00 7,680.00
- Klem Pipa 4.000 Buah 2,400.00 9,600.00
- Fhiser 8.000 Buah 1,800.00 14,400.00
- Las Doop 2.000 Buah 4,200.00 8,400.00
- Isolasi Ban 0.250 Buah 5,400.00 1,350.00

Page 118 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Ongkos pasang 1.000 titik 89,815.50 89,815.50
Jumlah 289,405.50

10 Instalasi Stop Kontak 1 phase :


- Kabel NYM 3 X 2,5 mm 8.500 meter 15,120.00 128,520.00
- Pipa Conduit PVC HI 20 mm 8.500 Meter 3,000.00 25,500.00

- Socket Pipa 2.130 Buah 6,600.00 14,058.00


- Tee Dos 2.000 Buah 3,840.00 7,680.00
- Klem Pipa 4.250 Buah 2,400.00 10,200.00
- Fhiser 8.500 Buah 1,800.00 15,300.00
- Las Doop 2.000 Buah 4,200.00 8,400.00
- Isolasi Ban 0.250 Buah 5,400.00 1,350.00
Ongkos Pasang 1.000 titik 94,953.60 94,953.60
Jumlah 305,961.60
11 Instalasi Exhaust FAN :
- Kabel NYM 4 X 1,5 mm 8.000 meter 16,320.00 130,560.00
- Pipa Conduit PVC HI 20 mm 8.000 Meter 3,000.00 24,000.00
- Socket Pipa 2.000 Buah 6,600.00 13,200.00
- Tee Dos 2.000 Buah 3,840.00 7,680.00
- Klem Pipa 4.000 Buah 2,400.00 9,600.00
- Fhiser 8.000 Buah 1,800.00 14,400.00
- Las Doop 2.000 Buah 4,200.00 8,400.00
- Isolasi Ban 0.250 Buah 5,400.00 1,350.00
Ongkos pasang 1.000 titik 94,135.50 94,135.50
Jumlah 303,325.50

B PEKERJAAN PENANGKAL PETIR DAN GROUNDING


1 - Head Penangkal petir modern non radio aktif R 100 M 1.000 unit - - -
- Perlengkapan 1.000 bh - -
Upah :
Pekerja Listrik 0.300 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.070 hr - -
Mandor Listrik 0.030 hr - -
Jumlah

2 Down Conductor Ericor Cable NYA 50 mm 1.000 Meter - -


- Perlengkapan 1.000 bh - -
Upah :
Pekerja Listrik 0.120 hr - -
Tukang Listrik 0.120 hr - -
Kepala tukang Listrik 0.015 hr - -
Mandor Listrik 0.005 hr - -
Jumlah

3 - Dudukan tiang Penangkal petir 1.000 Meter - -


- Perlengkapan 1.000 bh - -
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.090 hr - -
Mandor Listrik 0.030 hr - -
Jumlah

4 - Lightning Strike Counter 1.000 Meter - -


- Perlengkapan 1.000 bh - -
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.090 hr - -
Mandor Listrik 0.030 hr - -
Jumlah

5 - Obstruction lamp 1.000 Meter - -


- Perlengkapan 1.000 bh - -
Upah :

Page 119 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Pekerja Listrik 0.450 hr - -
Tukang Listrik 0.600 hr - -
Kepala tukang Listrik 0.100 hr - -
Mandor Listrik 0.040 hr - -
Jumlah

6 - Grounding Penangkal Petir NYA cable 50 mm 10.000 Meter - -


- Pipa 11/2" GIP 3,00 3 Meter - -
- Spit Tembaga 1,00 1.000 hr - -
- Klem tembaga 4,00 4.000 hr - -
- Materia Bantu 1,00 1.000 hr - -
- Upah pasang 1,00 ls 1.000 hr 0,00                             -  
- Jumlah - -
Jumlah

C PEKERJAAN TELEPON
1 Peralatan utama PABX , 16 Trunk line,144 Ext 1.000 unit -

Expandable to 144 Extension terdiri :


a.HiPath 1190 System Cabinet Ver. 7.0
b. Expand Board 2/10
c. Expand Board 0/12
d. Caller ID For External & Internal
e. Automatic Attendant
f. Fax Signal Detection
g. Memory Music Holding
h. 1 Port Series RS-232
i. 1 Port USB
j. 1 pcs Profiset 3030 telephone display
- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 1.500 hr - -
Tukang Listrik 2.500 hr - -
Kepala tukang Listrik 0.800 hr - -
Mandor Listrik 0.450 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

2 Buck up Battery 1.000 unit - -


- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 0.200 hr - -
Tukang Listrik 0.300 hr - -
Kepala tukang Listrik 0.050 hr - -
Mandor Listrik 0.180 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

3 MDF BOX 2X200 peir Solderiess 1.000 unit - -


- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 1.100 hr - -
Tukang Listrik 1.000 hr - -
Kepala tukang Listrik 0.800 hr - -
Mandor Listrik 0.450 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

Page 120 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


4 Pesawat telephone / profiset 3030 digital display telp for operat 1.000 unit 0,00 #VALUE!
- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 0.100 hr - -
Tukang Listrik 0.140 hr - -
Kepala tukang Listrik 0.015 hr - -
Mandor Listrik 0.004 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

5 AH-99-PN Single line telephone 1.000 unit 0,00 #VALUE!


- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 0.100 hr - -
Tukang Listrik 0.140 hr - -
Kepala tukang Listrik 0.015 hr - -
Mandor Listrik 0.004 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

10 AH-99-PN Single line telephone 1.000 unit 0,00 #VALUE!


- Perlengkapan 1.000 unit - -
Jumlah
Upah :
Pekerja Listrik 0.100 hr - -
Tukang Listrik 0.140 hr - -
Kepala tukang Listrik 0.015 hr - -
Mandor Listrik 0.004 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

11 Outlet Telephone lantai 1.000 unit 780,000.00 780,000.00


- Perlengkapan 1.000 unit 117,000.00 117,000.00
Jumlah 897,000.00
Upah :
Pekerja Listrik 0.100 hr 157,643.00 15,764.30
Tukang Listrik 0.140 hr 166,729.00 23,342.06
Kepala tukang Listrik 0.015 hr 182,676.00 2,740.14
Mandor Listrik 0.004 hr 194,274.00 777.10
Jumlah - 42,623.60
Total - 939,623.60
Overhead & Profit 10% 0.10 93,962.36
Total Harga Satuan Pekerjaan Total - 1,033,585.96

12 Terminal Box 20 peir 1.000 unit 0,00 #VALUE!


- Perlengkapan 1.000 unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 hr - -
Tukang Listrik 0.300 hr - -
Kepala tukang Listrik 0.050 hr - -
Mandor Listrik 0.018 hr - -
Jumlah - -
Total - -
Overhead & Profit 10% 0.10 -
Total Harga Satuan Pekerjaan Total - -

Page 121 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


17 Instalasi Telephone
- Kabel ITC 2 x 2 x 0,6 mm 20.00 Meter 7,800.00 156,000.00 -
- Pipa Conduit PVC 20 mm 18.00 Meter 1,500.00 27,000.00 -
- Fitting ( elbow ,male bush, Joint coupling) 4.00 Buah 3,600.00 14,400.00 -
- Saddle 5.00 Buah 18,000.00 90,000.00 -
- Fresher dan Scrup 6.00 Buah 3,000.00 18,000.00 -
- Juntion box 1.00 Buah 15,000.00 15,000.00 -
Ongkos pasang 0.150 hr 90,000 13,500.00
Jumlah 333,900.00

18 Kabel fedeer 4 peir TB lt 1 ke MDF 1.000 Meter ### -


- Perlengkapan 1.000 Meter - -
Jumlah
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.100 hr - -
Mandor Listrik 0.010 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

19 Kabel fedeer 10 peir TB lt 1 ke MDF 1.000 Meter 0 #VALUE!


,
- Perlengkapan 1.000 Meter - -
0
Jumlah 0
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.100 hr - -
Mandor Listrik 0.010 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

20 Kabel fedeer 20 peir TB lt 1 ke MDF 1.000 Meter 0 #VALUE!


,
- Perlengkapan 1.000 Meter - -
0
Jumlah 0
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.100 hr - -
Mandor Listrik 0.010 hr - -
-
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

20 IDF 4 peir solderless 1.000 Meter 0 #VALUE!


,
- Perlengkapan 1.000 Meter - -
0
Jumlah 0
Upah :
Pekerja Listrik 0.400 hr - -
Tukang Listrik 0.500 hr - -
Kepala tukang Listrik 0.100 hr - -
Mandor Listrik 0.010 hr - -
-
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan Total -

E PEKERJAAN FIRE ALARM


1 MCFA 10 Zone Addressable 1 Loop + Battery + Surge Protector Se 1,00 Unit 9,000,000.00 #VALUE!
- Perlengkapan 1.000 Meter 1350000 1,350,000.00

Page 122 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah 10,350,000.00
Upah :
Pekerja Listrik 3.500 h 157,643.00 551,750.50 -
r
Tukang Listrik 3.500 h 166,729.00 583,551.50 -
r
Kepala tukang Listrik 1.500 h 182,676.00 274,014.00 -
r
Mandor Listrik 0.600 hr 194,274.00 116,564.40
Jumlah 1,525,880.40
Total 11,875,880.40
Overhead & Profit 10% 0.10 1,187,588.04
Total Harga Satuan Pekerjaan Total - 13,063,468.44

2 Annunciator RLCD-C 1,00 Unit 784,800.00 #VALUE!


- Perlengkapan 1.000 Meter 117720 117,720.00
Upah : Jumlah 902,520.00
Pekerja Listrik 3.500 h 157,643.00 551,750.50
r
Tukang Listrik 3.500 h 166,729.00 583,551.50
r
Kepala tukang Listrik 1.500 h 182,676.00 274,014.00
r
Mandor Listrik 0.600 hr 194,274.00 116,564.40
Jumlah 1,525,880.40
Total 1,525,880.40
Overhead & Profit 10% 0.10 152,588.04
Total Harga Satuan Pekerjaan Total - 1,678,468.44

3 MI/DCZRM Conventional Zone Interface Module 1.000 Unit 1,440,000.00 1,440,000.00


- Perlengkapan 1.000 Unit 216000 216,000.00
Jumlah 1,656,000.00
Upah :
Pekerja Listrik 3.500 h 157,643.00 551,750.50
r
Tukang Listrik 3.500 h 166,729.00 583,551.50
r
Kepala tukang Listrik 1.500 h 182,676.00 274,014.00
r
Mandor Listrik 0.600 hr 194,274.00 116,564.40
Jumlah 1,525,880.40
Total 3,181,880.40
Overhead & Profit 10% 0.10 318,188.04
Total Harga Satuan Pekerjaan Total - 3,500,068.44

4 ROR Heat Detector 1.000 Unit 540,000.00 540,000.00


- Perlengkapan 1.000 Unit 81000 81,000.00
Jumlah 621,000.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 663,636.15
Overhead & Profit 10% 0.10 66,363.62
Total Harga Satuan Pekerjaan Total - 729,999.77

5 B801RA Detector Base, Suport remote annunciator output with 1.000 Unit 300,000.00 300,000.00
- Perlengkapan 1.000 Unit 45000 45,000.00
Jumlah 345,000.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 387,636.15
Overhead & Profit 10% 0.10 38,763.62
Total Harga Satuan Pekerjaan Total - 426,399.77

6 SSM24-6 Alarm Bell 6" 1.000 Unit 780,000.00 780,000.00


- Perlengkapan 1.000 Unit 117000 117,000.00
Jumlah 897,000.00

Page 123 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 939,636.15
Overhead & Profit 10% 0.10 93,963.62
Total Harga Satuan Pekerjaan Total - 1,033,599.77

7 SYS-ST Indicator lamp (STROBE) 1.000 Unit 300,000.00 300,000.00


- Perlengkapan 1.000 Unit 45000 45,000.00
Jumlah 345,000.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 387,636.15
Overhead & Profit 10% 0.10 38,763.62
Total Harga Satuan Pekerjaan Total - 426,399.77

8 M400K/T Break Glass Alarm ( Manual Call Point) 1.000 Unit 420,000.00 420,000.00
- Perlengkapan 1.000 Unit 63000 63,000.00
Jumlah 483,000.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 525,636.15
Overhead & Profit 10% 0.10 52,563.62
Total Harga Satuan Pekerjaan Total - 578,199.77

9 Visual Notification Appliance 1.000 Unit 150,000.00 150,000.00


- Perlengkapan 1.000 Unit 22500 22,500.00
Jumlah 172,500.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 215,136.15
Overhead & Profit 10% 0.10 21,513.62
Total Harga Satuan Pekerjaan Total - 236,649.77

10 End Of Line ( EOL ) 1.000 Unit 462,000.00 462,000.00


- Perlengkapan 1.000 Unit 69300 69,300.00
Jumlah 531,300.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 573,936.15
Overhead & Profit 10% 0.10 57,393.62
Total Harga Satuan Pekerjaan Total - 631,329.77

10 Terminal BOX FA 1.000 Unit 146,868.00 146,868.00


- Perlengkapan 1.000 Unit 22030.2 22,030.20
Jumlah 168,898.20

Page 124 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 211,534.35
Overhead & Profit 10% 0.10 21,153.44
Total Harga Satuan Pekerjaan Total - 232,687.79

10 BBS-X Back Box 1.000 Unit 252,000.00 252,000.00


- Perlengkapan 1.000 Unit 37800 37,800.00
Jumlah 289,800.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 332,436.15
Overhead & Profit 10% 0.10 33,243.62
Total Harga Satuan Pekerjaan Total - 365,679.77

10 MI/DCMO Output control module 1.000 Unit 252,000.00 252,000.00


- Perlengkapan 1.000 Unit 37800 37,800.00
Jumlah 289,800.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 332,436.15
Overhead & Profit 10% 0.10 33,243.62
Total Harga Satuan Pekerjaan Total - 365,679.77

12 Instalasi Fire Alarm Kabel NYM 2 x 1,5 mm² dalam conduit PVC HI
- Kabel NYM 2 X 1,5 mm 15.000 Meter 13,920.00 208,800.00
- Pipa Conduit PVC HI 20 mm 15.00 Meter 3,000.00 45,000.00
- Socket Pipa 3.75 Meter 6,600.00 24,750.00
- Tee Dos 2.00 Buah 3,840.00 7,680.00
- Klem Pipa 7.50 Buah 2,400.00 18,000.00
- Fhiser 15.00 Buah 1,800.00 27,000.00
- Las Doop 2.00 Buah 4,200.00 8,400.00
- Isolasi Ban 0.25 Buah 5,400.00 1,350.00
Pekerja Listrik 0.40 Buah 157,643.00 63,057.20
Tukang Listrik 0.300 hr 166,729.00 50,018.70
Kepala tukang Listrik 0.150 hr 182,676.00 27,401.40
Mandor Listrik 0.100 hr 194,274.00 19,427.40
Jumlah 500,884.70

13 Instalasi Manual Push Button, Alarm Bell, Indicator Lamp NYM 2 X 1,5 mm² da
- Kabel NYM 2 X 1,5 mm 15.000 Meter 13,920.00 208,800.00
- Pipa Conduit PVC HI 20 mm 15.00 Meter 3,000.00 45,000.00
- Socket Pipa 3.75 Meter 6,600.00 24,750.00
- Tee Dos 2.00 Buah 3,840.00 7,680.00
- Klem Pipa 7.50 Buah 2,400.00 18,000.00
- Fhiser 15.00 Buah 1,800.00 27,000.00
- Las Doop 2.00 Buah 4,200.00 8,400.00
- Isolasi Ban 0.25 Buah 5,400.00 1,350.00
Pekerja Listrik 0.50 hr 157,643.00 78,821.50
Tukang Listrik 0.350 hr 166,729.00 58,355.15
Kepala tukang Listrik 0.150 hr 182,676.00 27,401.40
Mandor Listrik 0.100 hr 194,274.00 19,427.40
Jumlah 524,985.45

Page 125 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

F PEKERJAAN CCTV

1 HEN16104 NVR 16PoE Port/16 Chanel/H.265/4K 1.000 Unit 4,200,000.00 4,200,000.00


Jumlah 4,200,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 4,241,733.35
Overhead & Profit 10% 0.10 424,173.34
Total Harga Satuan Pekerjaan Total - 4,665,906.69

2 HED2PER3 IP BALL 2MP H.265 IR TDN 2.8mm PoE IP 66 CCTV Ca 1.000 Unit 6,360,000.00 6,360,000.00
- Perlengkapan 1.000 Unit 954,000.00 954,000.00
Jumlah 7,314,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 7,408,178.03
Overhead & Profit 10% 0.10 740,817.80
Total Harga Satuan Pekerjaan Total - 8,148,995.84

3 HBD2PER1 IP BUL 2MP H.265 IR TDN 3.6mm PoE IP66 CCTV Came 1.000 Unit 7,800,000.00 7,800,000.00
- Perlengkapan 1.000 Unit 780,000.00 780,000.00
Jumlah 8,580,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 8,674,178.03
Overhead & Profit 10% 0.10 867,417.80
Total Harga Satuan Pekerjaan Total - 9,541,595.84

4 WD Purple 6 TB 1.000 Unit 294,000.00 294,000.00


Jumlah 294,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 335,733.35
Overhead & Profit 10% 0.10 33,573.34
Total Harga Satuan Pekerjaan Total - 369,306.69

4 Rack cabinet 1.000 Unit 4,320,000.00 4,320,000.00


Jumlah 4,320,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 4,361,733.35
Overhead & Profit 10% 0.10 436,173.34
Total Harga Satuan Pekerjaan Total - 4,797,906.69

Page 126 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


5 Switch Hub 8 Port 1.000 Unit 114,000.00 114,000.00
Jumlah 114,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 155,733.35
Overhead & Profit 10% 0.10 15,573.34
Total Harga Satuan Pekerjaan Total - 171,306.69

3 Switch Hub 16 Port 1.000 Unit 150,000.00 150,000.00


Jumlah 150,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 191,733.35
Overhead & Profit 10% 0.10 19,173.34
Total Harga Satuan Pekerjaan Total - 210,906.69

4 Monitor LCD 32" 1.000 Unit 5,400,000.00 5,400,000.00


Jumlah 5,400,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 5,441,733.35
Overhead & Profit 10% 0.10 544,173.34
Total Harga Satuan Pekerjaan Total - 5,985,906.69

5 SMC-1000I-2U APC Smart UPS 1KVA 2U Rackmountable 1.000 Unit 1,452,000.00 1,452,000.00
Jumlah 1,452,000.00
Upah :
Pekerja Listrik 0.100 h 157,643.00 15,764.30
r
Tukang Listrik 0.080 h 166,729.00 13,338.32
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 41,733.35
Total 1,493,733.35
Overhead & Profit 10% 0.10 149,373.34
Total Harga Satuan Pekerjaan Total - 1,643,106.69

6 Instalasi CCTV UTP Cable Cat 6 dalam conduit PVC 20 mm² UTP Cable Cat 20.000 Meter 16,200.00 324,000.00
- Pipa Conduit PVC HI 20 mm 20.00 Meter 3,000.00 60,000.00
- Socket Pipa 5.00 Buah 6,600.00 33,000.00
- Tee Dos 2.00 Buah 3,840.00 7,680.00
- Klem Pipa 10.00 Buah 2,400.00 24,000.00
- Fhiser 20.00 Buah 1,800.00 36,000.00
- Las Doop 2.00 Buah 4,200.00 8,400.00
- Isolasi Ban 0.25 Buah 5,400.00 1,350.00
Pekerja Listrik 0.65 hr 157,643.00 102,467.95
s 0.40 hr 166,729.00 66,691.60
Kepala tukang Listrik 0.25 hr 182,676.00 45,669.00
Jumlah 709,258.55
G PEKERJAAN LAN/INSTALASI DATA
1 19" Rack 42 RU depth 1100mm 1.000 Unit - -
- Perlengkapan 1.000 Unit - -
Jumlah
Upah :

Page 127 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Pekerja Listrik 0.400 h - -
r
Tukang Listrik 0.450 h - -
r
Kepala tukang Listrik 0.060 h - -
r
Mandor Listrik 0.007 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

2 APC Smart UPS 2000 VA 2U 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.400 h - -
r
Tukang Listrik 0.450 h - -
r
Kepala tukang Listrik 0.060 h - -
r
Mandor Listrik 0.007 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

3 Outlet Data, icl. Trimping Patch Cord RJ 45 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.400 h - -
r
Tukang Listrik 0.450 h - -
r
Kepala tukang Listrik 0.060 h - -
r
Mandor Listrik 0.007 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

4 Outlet Data, icl. Trimping Patch Cord RJ 45 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.100 h - -
r
Tukang Listrik 0.140 h - -
r
Kepala tukang Listrik 0.015 h - -
r
Mandor Listrik 0.004 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

5 Outlet Power UPS 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.100 h - -
r
Tukang Listrik 0.140 h - -
r
Kepala tukang Listrik 0.015 h - -
r
Mandor Listrik 0.004 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

6 JL253A Aruba 2930F 24G 4SFP + Switch 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :

Page 128 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Pekerja Listrik 0.200 h - -
r
Tukang Listrik 0.300 h - -
r
Kepala tukang Listrik 0.050 h - -
r
Mandor Listrik 0.050 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

7 J9773A Aruba 2530 24G PoE + Switch 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.055 h - -
r
Tukang Listrik 0.035 h - -
r
Kepala tukang Listrik 0.015 h - -
r
Mandor Listrik 0.005 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

8 JZ320A Aruba AP-303 RW Unified Access Point 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 0.055 h - -
r
Tukang Listrik 0.035 h - -
r
Kepala tukang Listrik 0.015 h - -
r
Mandor Listrik 0.005 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

9 Instalasi Power UPS

- Kabel NYM 3 X 2,5 mm2 6.00 Meter - -


- Pipa Conduit PVC 20 mm 6.00 Meter - -
- Fitting ( elbow ,male bush, Joint coupling) 4.00 Buah - -
- Saddle 5.00 Buah - -
- Fresher dan Scrup 6.00 Buah - -
- Juntion box 2.00 Buah - -
- Upah pasang 1.00 Titik - -

Jumlah

8 Instalasi data

- Kabel UTP CAT 6e 20.00 Meter 3,360.00 67,200.00


- Pipa Conduit PVC 20 mm 20.00 Meter 2,520.00 50,400.00
- Fitting ( elbow ,male bush, Joint coupling) 4.00 Buah 4,200.00 16,800.00
- Saddle 5.00 Buah 2,280.00 11,400.00
- Fresher dan Scrup 6.00 Buah 3,000.00 18,000.00
- Juntion box 2.00 Buah 13,200.00 26,400.00
- Upah pasang 1.00 Titik 120,000.00 120,000.00

Jumlah 310,200.00

J GENSET
1 Genset 250 KVA type Silent 1.000 Unit - - -
- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 9.000 h - -
r
Tukang Listrik 9.800 h - -
r
Kepala tukang Listrik 3.500 h - -
r
Mandor Listrik 1.500 hr - -
Jumlah

Page 129 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

2 Tanki Solar 250 liter (Tanki bulanan) 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah
Upah :
Pekerja Listrik 5.000 h - -
r
Tukang Listrik 5.500 h - -
r
Kepala tukang Listrik 0.150 h - -
r
Mandor Listrik 0.045 hr - -
Jumlah
Total
Overhead & Profit 10% 0.10
Total Harga Satuan Pekerjaan -

K PENYALUR PETIR
1 Head Penangkal petir Kurn non radio aktif R 100 M 1.000 Unit 10,200,000.00 10,200,000.00
- Perlengkapan 1.000 Unit 1,020,000.00 1,020,000.00
Jumlah 11,220,000.00
Upah :
Pekerja Listrik 1.350 h 157,643.00 212,818.05
r
Tukang Listrik 1.050 h 166,729.00 175,065.45
r
Kepala tukang Listrik 0.875 h 182,676.00 159,841.50
r
Mandor Listrik 0.550 hr 194,274.00 106,850.70
Jumlah 654,575.70
Total 11,874,575.70
Overhead & Profit 10% 0.10 1,187,457.57
Total Harga Satuan Pekerjaan Total - 13,062,033.27

2 Down Conductor cable N2XSY 70 mm 1.000 Meter 96,600.00 96,600.00


- Perlengkapan 1.000 Meter 9,660.00 9,660.00
Jumlah 106,260.00
Upah :
Pekerja Listrik 0.120 h 157,643.00 18,917.16
r
Tukang Listrik 0.120 h 166,729.00 20,007.48
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 42,636.15
Total 148,896.15
Overhead & Profit 10% 0.10 14,889.62
Total Harga Satuan Pekerjaan Total - 163,785.77

2 Dudukan tiang Penangkal petir 1.000 Meter 420,000.00 420,000.00


- Perlengkapan 1.000 Meter 42,000.00 42,000.00
Jumlah 462,000.00
Upah :
Pekerja Listrik 0.550 h 157,643.00 86,703.65
r
Tukang Listrik 0.350 h 166,729.00 58,355.15
r
Kepala tukang Listrik 0.090 h 182,676.00 16,440.84
r
Mandor Listrik 0.035 hr 194,274.00 6,799.59
Jumlah 168,299.23
Total 630,299.23
Overhead & Profit 10% 0.10 63,029.92
Total Harga Satuan Pekerjaan Total - 693,329.15

3 Lightning Strike Counter 1.000 Meter 300,000.00 300,000.00


- Perlengkapan 1.000 Meter 30,000.00 30,000.00
Jumlah 330,000.00
Upah :
Pekerja Listrik 0.550 h 157,643.00 86,703.65
r
Tukang Listrik 0.350 h 166,729.00 58,355.15
r
Kepala tukang Listrik 0.090 h 182,676.00 16,440.84
r
Mandor Listrik 0.035 hr 194,274.00 6,799.59

Page 130 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah 168,299.23
Total 498,299.23
Overhead & Profit 10% 0.10 49,829.92
Total Harga Satuan Pekerjaan Total - 548,129.15

4 Obstruction lamp 1.000 Meter 150,000.00 150,000.00


- Perlengkapan 1.000 Meter 15,000.00 15,000.00
Jumlah 165,000.00
Upah :
Pekerja Listrik 0.550 h 157,643.00 86,703.65
r
Tukang Listrik 0.350 h 166,729.00 58,355.15
r
Kepala tukang Listrik 0.090 h 182,676.00 16,440.84
r
Mandor Listrik 0.035 hr 194,274.00 6,799.59
Jumlah 168,299.23
Total 333,299.23
Overhead & Profit 10% 0.10 33,329.92
Total Harga Satuan Pekerjaan Total - 366,629.15

5 Cable BC 50 mm 1.000 Unit 41,400.00 41,400.00


- Perlengkapan 1.000 Unit 4,140.00 4,140.00
Jumlah 45,540.00
Upah :
Pekerja Listrik 0.055 h 157,643.00 8,670.37
r
Tukang Listrik 0.035 h 166,729.00 5,835.52
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 18,217.39
Total 63,757.39
Overhead & Profit 10% 0.10 6,375.74
Total Harga Satuan Pekerjaan Total - 70,133.13

6 Pipa 2" GIP 1.000 Meter 150,000.00 150,000.00


- Perlengkapan 1.000 Meter 15,000.00 15,000.00
Jumlah 165,000.00
Upah :
Pekerja Listrik 0.055 h 157,643.00 8,670.37
r
Tukang Listrik 0.035 h 166,729.00 5,835.52
r
Kepala tukang Listrik 0.015 h 182,676.00 2,740.14
r
Mandor Listrik 0.005 hr 194,274.00 971.37
Jumlah 18,217.39
Total 183,217.39
Overhead & Profit 10% 0.10 18,321.74
Total Harga Satuan Pekerjaan Total - 201,539.13

7 Spit Tembaga 1.000 Unit 240,000.00 240,000.00


- Perlengkapan 1.000 Unit 24,000.00 24,000.00
Jumlah 264,000.00
Upah :
Pekerja Listrik 0.550 h 157,643.00 86,703.65
r
Tukang Listrik 0.350 h 166,729.00 58,355.15
r
Kepala tukang Listrik 0.090 h 182,676.00 16,440.84
r
Mandor Listrik 0.035 hr 194,274.00 6,799.59
Jumlah 168,299.23
Total 432,299.23
Overhead & Profit 10% 0.10 43,229.92
Total Harga Satuan Pekerjaan Total - 475,529.15

8 Grounding Rod C/W Bak Kontrol 1.000 Unit 540,000.00 540,000.00


- Perlengkapan 1.000 Unit 54,000.00 54,000.00
Jumlah 594,000.00
Upah :
Pekerja Listrik 0.550 h 157,643.00 86,703.65
r
Tukang Listrik 0.350 h 166,729.00 58,355.15
r
Kepala tukang Listrik 0.090 h 182,676.00 16,440.84
r
Mandor Listrik 0.035 hr 194,274.00 6,799.59

Page 131 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah 168,299.23
Total 762,299.23
Overhead & Profit 10% 0.10 76,229.92
Total Harga Satuan Pekerjaan Total - 838,529.15

L PEKERJAAN LIFT
1 Lift pasanger kapasitas 1.000 Kg personil lengkap system 1.00 Unit - -
- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 1.350 h 157,643.00 212,818.05
r
Tukang Listrik 1.050 h 166,729.00 175,065.45
r
Kepala tukang Listrik 0.875 h 182,676.00 159,841.50
r
Mandor Listrik 0.550 hr 194,274.00 106,850.70
Jumlah 654,575.70
Total 654,575.70
Overhead & Profit 10% 0.10 65,457.57
Total Harga Satuan Pekerjaan Total - 720,033.27

M PEKERJAAN SOUND SYSTEM


1 19" Rack 30 RU depth 600mm 1.000 Unit 7,800,000.00 7,800,000.00
- Perlengkapan 1.000 Unit 780,000.00 780,000.00
Jumlah 8,580,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 8,674,178.03
Overhead & Profit 10% 0.10 867,417.80
Total Harga Satuan Pekerjaan Total - 9,541,595.84

2 X-DA4125EN High Efficiency Class D Power amplifier 4x125W, 100V 1.000 Unit 3,840,000.00 3,840,000.00
- Perlengkapan 1.000 Unit 384,000.00 384,000.00
Jumlah 4,224,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 4,318,178.03
Overhead & Profit 10% 0.10 431,817.80
Total Harga Satuan Pekerjaan Total - 4,749,995.84

3 X-MAP04 All in 1 audio source unit (include pre-amplifier) CD/MP3/ 1.000 Unit 150,000.00 150,000.00
- Perlengkapan 1.000 Unit 15,000.00 15,000.00
Jumlah 165,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 259,178.03
Overhead & Profit 10% 0.10 25,917.80
Total Harga Satuan Pekerjaan Total - 285,095.84

4 Junction box panel 1.000 Unit 1,440,000.00 1,440,000.00


- Perlengkapan 1.000 Unit 144,000.00 144,000.00
Jumlah 1,584,000.00
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r

Page 132 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 1,678,178.03
Overhead & Profit 10% 0.10 167,817.80
Total Harga Satuan Pekerjaan Total - 1,845,995.84

4 L-PCM06E Ceilling Loudspeaker 3 / 6 watt 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

5 X-NPMI Configurable Network Paging Console Microphone 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

6 L-PHP30A Horn Loudspeaker 30/15 watt 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

7 X-DCS2000/EN Digital Integrated System Manager 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

8 L-POM40A Wall Loudspeaker 5/10/20 watt 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r

Page 133 of 162


ANALISA ELEKTRIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

9 HN-VC06 Volume Control 6 watt 1.000 Unit - -


- Perlengkapan 1.000 Unit - -
Jumlah -
Upah :
Pekerja Listrik 0.200 h 157,643.00 31,528.60
r
Tukang Listrik 0.300 h 166,729.00 50,018.70
r
Kepala tukang Listrik 0.050 h 182,676.00 9,133.80
r
Mandor Listrik 0.018 hr 194,274.00 3,496.93
Jumlah 94,178.03
Total 94,178.03
Overhead & Profit 10% 0.10 9,417.80
Total Harga Satuan Pekerjaan Total - 103,595.84

10 Instalasi speaker NYYHY 2 x 1.5 mm dalam conduit PVC 20 mm²


- NYY HY 2 x 1.5 MM² 15.00 Meter 13,920.00 208,800.00
- Pipa Conduit PVC 20 mm 15.00 Meter 3,000.00 45,000.00
- Socket Pipa 3.75 Buah 6,600.00 24,750.00
- Tee Dos 2.00 Buah 3,840.00 7,680.00
- Klem Pipa 7.50 Buah 2,400.00 18,000.00
- Fhiser 15.00 Buah 1,800.00 27,000.00
- Las Doop 2.00 Buah 4,200.00 8,400.00
- Isolasi Ban 0.25 Buah 5,400.00 1,350.00
Pekerja Listrik 0.65 hr 157,643.00 102,467.95
Tukang Listrik 0.40 hr 166,729.00 66,691.60
Kepala tukang Listrik 0.25 hr 182,676.00 45,669.00
Mandor Listrik 0.130 hr 194,274.00 25,255.62
Jumlah 581,064.17

11 Instalasi speaker NYYHY 3 x 1.5 mm dalam conduit PVC 20 mm²


- NYY HY 3 x 1.5 MM² 10.00 Meter 11,400.00 114,000.00
- Pipa Conduit PVC 20 mm 10.00 Meter 3,000.00 30,000.00
- Socket Pipa 2.50 Buah 6,600.00 16,500.00
- Tee Dos 2.00 Buah 3,840.00 7,680.00
- Klem Pipa 5.00 Buah 2,400.00 12,000.00
- Fhiser 10.00 Buah 1,800.00 18,000.00
- Las Doop 2.00 Buah 4,200.00 8,400.00
- Isolasi Ban 0.25 Buah 5,400.00 1,350.00
Pekerja Listrik 0.65 hr 157,643.00 102,467.95
Tukang Listrik 0.40 hr 166,729.00 66,691.60
Kepala tukang Listrik 0.25 hr 182,676.00 45,669.00
Mandor Listrik 0.130 hr 194,274.00 25,255.62
Jumlah 448,014.17

Page 134 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

DAFTAR BAHAN MEKANIKAL ELEKTRIKAL

Organisasi / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara : 1.1101201
Program / Program Pengelolahan Persamphan : 1.11.01
Kegiatan / Pembangunan TPS di Kota Administrasi jakarta Utara : 1.11.01.019
(TPS Dipo Rawa Badak Utara)
Kode Rekening / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito samp : 5.2.3.26.20
Tahun Anggaran : 2019

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

1 2 3 4
MEKANIKAL
A PEKERJAAN AIR CONDITION
1 RXQ26AMY14 VRV OUTDOOR 251.000 BTUH unit 4,550,000
2 RXQ36AMY14 VRV OUTDOOR 341.000 BTUH unit 5,850,000
3 RXQ42AMY14 VRV OUTDOOR 399.000 BTUH unit 9,750,000
4 FXAQ 20PVE4 AC VRV type Wall Mounted 7.500 Btu/h + Wired unit 12,350,000
Remote
5 FXAQ 25PVE4 AC VRV type Wall Mounted 9.600 Btu/h + Wired unit 17,550,000
Remote
6 FXAQ 32PVE4 AC VRV type Wall Mounted 12.300 Btu/h + Wired unit 19,500,000
Remote
7 FXAQ 40PVE4 AC VRV type Wall Mounted 15.400 Btu/h + Wired unit 23,400,000
Remote
8 FXAQ 50PVE4 AC VRV type Wall Mounted 19.100 Btu/h + Wired unit 32,500,000
Remote
9 FXAQ 63PVE4 AC VRV type Wall Mounted 24.200 Btu/h + Wired unit 37,700,000
Remote
10 FXFQ 50 AV4 VRV Cassette Round Flow 19.100 Btu/h + Navigation unit 45,500,000
11 FXFQ 80 AV4 VRV Cassette Round Flow 30.700 Btu/h + Navigation unit 58,500,000
12 FXFQ 100 AV4 VRV Cassette Round Flow 38.200 Btu/h + Navigation unit 84,500,000
13 FAN 50 Watt Type ceiling Unit 27,950,000
Standard pipa ASTM B 280
1 Pipa Refrigrant 1/4" m 32,500
Isolasi pipa Refrigrant m 15,600
2 Pipa Refrigrant 3/8" m 45,500
Isolasi pipa Refrigrant m 22,100
3 Pipa Refrigrant 1/2" m 58,500
Isolasi pipa Refrigrant m 28,600
4 Pipa Refrigrant 5/8" m 71,500
Isolasi pipa Refrigrant m 39,000
5 Pipa Refrigrant 3/4" m 84,500
Isolasi pipa Refrigrant m 52,000
6 KHRP26A22T-S REFNET JOINT Unit 94,250
7 KHRP26A33T-S REFNET JOINT Unit 113,100
8 KHRP26A72T-S REFNET JOINT Unit 207,350
9 KHRP26A73T-S REFNET JOINT Unit 301,600
10 KHRP26M73TP9 PIPE SIZE REDUCER Unit 490,100
11 Exhouse Fan 50 CFM ( Ceilling ) Unit 845,000
12 Exhouse Fan 50 CFM (Wall Mounted) Unit 1,235,000
13 Pipa draine 3/4" ( PVC) m' 27,300
14 Isolasi m' 6,500

Page 135 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

B PEKERJAAN AIR BERSIH


1 Pompa Transfer 120 l/mnt, Head 40 m unit 16,250,000
2 Pompa PDAM 150 l/mnt, Head 30 m- 9 m3/jam unit 13,520,000
3 Pompa Booster VSD 2x100 l/mnt, Head 20 m Lengkap Panel Control unit 11,830,000
4 Roof Tank Stainless steel Cap. 3.200 lt unit 8,125,000
5 Booster Pump kapasitas 15 m3/h, 2 x 4 Kw, 3 x 380 V lengkap unit 2,275,000
terkopel,
panel kontrol DOL, Presure tank, presure switch,Vavle ,C.Vale 2,730,000
6
dan Flex.Joint
Pipa PPR PN 10 dia 1/2" M' 54,000
7 Pipa PPR PN 10 dia 3/4" M' 72,000
8 Pipa PPR PN 10 dia 1" M' 114,000
9 Pipa PPR PN 10 dia 1 1/4" M' 132,000
10 Pipa PPR PN 10 dia 11/2" M' 156,000
11 Pipa PPR PN 10 dia 2" M' 192,000
12 Pipa PPR PN 10 dia 2 1/2" M' 252,000
13 Pipa PPR PN 10 dia 3" M' 300,000
14 Water level Control unit 780,000
15 Chek Valve 1" unit 54,000
16 Chek Valve 1 1/2" unit 94,800
17 Chek Valve 2" unit 162,000
18 Ball Valve 2" unit 66,000
19 Ball Valve 1½" unit 42,000
20 Ball Valve 1" unit 24,000
21 Ball Valve ¾" unit 18,000
22 Gate Valve 1" unit 102,000
23 Gate Valve 1 1/4" unit 133,200
24 Gate Valve 1 1/2" unit 174,000
25 Gate Valve 2" unit 210,000
26 Gate Valve 2 1/2" unit 258,000
27 Strainer 1½" unit 162,000
28 Strainer 2 1/2" unit 252,000
29 Pressure Gauge ½" unit 162,000
30 Foot Valve 1" unit 42,000
31 Foot Valve 11/2" unit 78,000
32 Foot Valve 2" unit 108,000
33 FLOW CONTROLL VALVE 1½" unit 150,000
34 Floting Valve 1 " bh 78,000
35 Floting Valve 2 1/2" bh 114,000
36 L. BOW 4" bh 54,000
37 CAP 3/4" bh 78,000
38 CAP 1" bh 102,000
39 Reducer 1 ½" x 1" bh 114,000
40 Elbow 90" ¾" bh 42,000
41 Elbow 90" ½" bh 90,000
42 Elbow 90" 1" bh 174,000
43 Elbow 90" 1 1/4" bh 228,000
44 Elbow 90" 2" bh 294,000

Page 136 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

45 ELBOW FEMALE THREAD ½" bh 30,000


46 REDUCER FEMALE ¾" x ½" bh 78,000
47 TEE ¾" x ½" x ¾" bh 54,000
48 TEE 1" x ¾" x 1" bh 102,000
49 TEE 1" x ½" x 1" bh 40,800
50 TEE 1 1/2" x 1 1/4" x 1 1/2" bh 90,000
51 EQUAL TEE ½" bh 42,000
52 EQUAL TEE 1" bh 132,000
53 EQUAL TEE 1 ½" bh 216,000
54 EQUAL TEE 2" bh 324,000
55 COUPLER 1½" bh 90,000
56 COUPLER 1" bh 82,800
57 COUPLER ¾" bh 69,600
58 COUPLER ½" bh 51,600
59 FLANGE 1½" bh 38,400
60 BLIND FLANGE 1½" bh 138,000
61 FLANGE 2" bh 102,000
62 BLIND FLANGE 2" bh 198,000
63 FLANGE 1½" bh 78,000
64 BLIND FLANGE 1½" bh 108,000
65 FLANGE 2" bh 102,000
66 BLIND FLANGE 2" bh 132,000
C PEKERJAAN STP BIO FILTER
1 STP BST Tank Size Ø 1 x 3,5m set 5,400,000
2 Sparation Chamber lot 414,000
3 Anaerobic Contact Media (PVC + FRP suport) lot 780,000
BIO MEDIA (PVC + FRP suport) lot 558,000
Diffuser (PVC AW Rucika) set 1,032,000
Disinfaction box FPR (fiberglass) set 1,440,000
Chlorine Set (fiberglass) set 1,140,000
Pengikat Tangki (Galvanized) set 1,980,000
Manholes (fiberglass) set 1,440,000
Aerasi Blower 30L/min x unit 4,140,000
4 Instalasi Mekanik dan Elektri bh 1,800,000
5 Pondasi tanki beton bertulang disesuaikan dengan ukuran tanki lot 25,459,200
( P=17xL=6,5xT=0,6)M -
6 Galian dan Uruk Tanah m3 138,000

D PEKERJAAN AIR KOTOR, AIR BEKAS, VENTING


1 Pipa PVC - D dia 1 1/4" m' 25,800
2 Pipa PVC - D dia 11/2" m' 42,000
3 Pipa PVC - D dia 2" m' 50,400
4 Pipa PVC - D dia 4" m' 168,000
5 Pipa PVC - D dia 6" m' 204,000
6 Pipa PVC - AW dia 3" m' 108,000
7 Pipa PVC - AW dia 11/2" m' 76,800

Page 137 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

8 Pipa PVC - AW dia 2" m' 90,000


9 Pipa PVC - AW dia 2 1/2" m' 100,800
10 Pipa PVC - AW dia 4" m' 174,000
11 Pipa PVC - AW dia 6" m' 258,000
12 CLEAN OUT dia 6" m' 252,000
13 CLEAN OUT dia 4" m' 216,000
14 POMPA SUMPIT KAP 200 Lpm, HEAD 20 meter Unit 2,580,000
15 Pipa Conduit PVC HI 20 mm m1 1,800
16 ELBOW 90° 1" Unit 3,720
17 ELBOW 90° 1½" Unit 9,240
18 ELBOW 90° 2" Unit 14,160
19 ELBOW 90° 4" Unit 69,600
20 ELBOW 45° 2" Unit 6,000
21 ELBOW 45° 4" Unit 24,000
22 ELBOW 45° 6" Unit 84,000
23 Y-BRANCH 2" Unit 24,000
24 Y-BRANCH 2" x 4" Unit 48,000
25 Y-BRANCH 4" Unit 66,000
26 REDUCER 1½"X1" Unit 42,000
27 REDUCER 1½"X2" Unit 68,400
28 REDUCER 2" x 1" Unit 108,000
29 REDUCER 2" x 4" Unit 144,000
30 LARGE RADIUS TEE 1" Unit 78,000
31 LARGE RADIUS TEE 1½" Unit 102,000
32 LARGE RADIUS TEE 1" x 2" Unit 108,000
33 LARGE RADIUS TEE 1½" x 2" Unit 150,000
34 LARGE RADIUS TEE 4" Unit 282,000
35 LARGE RADIUS TEE 4" x 6" Unit 295,080
36 LARGE RADIUS TEE 6" Unit 378,000
37 FLOOR DRAIN 4" Unit 270,000
38 FLOOR CLEAN OUT 2" Unit 114,000
39 FLOOR CLEAN OUT 4" Unit 144,000
40 Vent Cap 2" Unit 102,000
41 Kawat Ayam m' 78,000
42 ROOF DRAIN 4" Unit 222,000
F PEKERJAAN INSTALASI FIRE HYDRANT -
5 Pipa BSP Sch 40 medium dia 2" m' 114,000
6 Pipa BSP Sch 40 medium dia 2 1/2" m' 170,400
7 Pipa BSP Sch 40 medium dia 3" m' 234,000
8 Pipa BSP Sch 40 medium dia 4" m' 306,000
ELEKTRIKAL -
A PEKERJAAN LISTRIK -
I PEKERJAAN PANEL -
1 Pilot Lamp + Fuse Buah 180,000
2 Voltmeter Buah 150,000
3 Amperemeter Buah 900,000

Page 138 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

4 Selector Volt 0 - 500V Buah 420,000


5 Selector Switch Buah 300,000
6 CT 400/5A Buah 1,020,000
7 MCCB 4P 350 - 500A 36KA Buah 1,980,000
8 MCCB 3P 70-100A 25KA Buah 1,800,000
10 MCCB 3P 44,1 - 63A 25KA Buah 1,716,000
11 MCCB 3P 28 - 40A 25KA Buah 1,320,000
12 MCCB 3P 20 - 25A 25KA Buah 1,128,000
13 MCCB 3P 17,5 - 25A 25KA Buah 882,000
14 MCCB 3P 60A 18KA Buah 780,000
15 MCCB 3P 20A 10KA Buah 708,000
16 MCCB 3P 50A 25KA Buah 564,000
17 MCCB 3P 35A - 50A 25KA Buah 468,000
18 MCCB 3P 32A - 40A 25KA Buah 384,000
19 MCCB 3P 40A 8KA Buah 1,500,000
20 MCB 3P 25A 18KA Buah 1,140,000
21 MCB 3P 20A 10KA Buah 882,000
22 MCB 3P 6A 10KA Buah 570,000
23 MCB 3P 10A 10KA Buah 672,000
24 MCB 3P 20A 4,5KA Buah 780,000
25 MCCB 3P 20A 10KA Buah 468,000
26 MCB 1P 16A 6KA Buah 900,000
27 MCB 1P 10A 6KA Buah 768,000
28 MCB 1P 20A 4,5KA Buah 642,000
29 MCB 1P 10A 4,5KA Buah 522,000
30 MCB 1P 16A 4,5KA Buah 720,000
31 MCB 1P 6A 4.5KA Buah 510,000
32 BC 16 Buah 300,000
BC 50
33 - CT 400/5A Buah 780,000
34 Interlock Buah 312,000
35 Push button Buah 259,200
36 ATS ls 468,000
37 Surge Arresster 3P + 1N 40 KA Buah 2,100,000
38 Photo Electric Switch Buah 3,000,000
39 Magmetic Contactor Buah 900,000
40 Timer Relay Lengkap switch Auto Manual Buah 2,280,000
41 Exhoust Fan type Ceilling 50 CFM/80 CMH ( wall type) Buah 1,500,000
42 Power Meter Seri PM5350 Buah 14,400,000
II PEKERJAAN KABEL FEEDER -
1 - NYAF 1 x 150 MM² m' 528,000
2 - NYAF 1 x 120 MM² m' 211,200
3 - NYAF 1 x 25 MM² m' 45,600
4 - NYAF 1 x 16 MM² m' 60,000
5 - NYAF 1 x 10 MM² m' 39,600
6 - NYAF 1 x 6 MM² m' 11,400
7 - NYAF 1 x 4 MM² m' 16,320

Page 139 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

8 - NYFGBY 4 x 6 MM² m' 44,400


9 - NYFGBY 4 x 4 MM² m' 34,800
10 - NYFGBY 4 x 25 mm m' 295,000
13 - NYY 4 x 95 MM² m' 732,000
14 - NYY 4 x 70 MM² m' 916,800
15 - NYY 4 x 50 MM² m' 376,800
16 - NYY 4 x 35 MM² m' 277,200
17 - NYY 4 x 25 MM² m' 204,000
18 - NYY 4 x 16 MM² m' 133,200
19 - NYY 4 x 10 MM² m' 117,600
20 - NYY 4 x 6 MM² m' 86,400
21 - NYY 4 x 4 MM² m' 69,600
22 - NYM 3 x 2.5 MM² m' 15,120
23 - NYM 2 x 1.5 MM² m' 13,920
24 - NYM 4 x 4 MM² m' 18,000
25 - NYM HY 4 x 1.5 MM² m' 16,320
26 - NYM HY 3 x 1,5 MM² m' 11,400
27 - NYM HY 3 x 2,5 MM² m' 16,680
28 - NYY HY 2 x 1.5 MM² m' 8,400
35 - Cable Tray 10 x 5 Cm ( Hot Dip Galvanized) m' 90,000
38 - Cable Tray 40 x 10 Cm m' 222,000
42 - Cable Tray Joint T100X100X50 m' 547,200
43 - Cable Tray Joint L400X400X100 m' 78,000
44 - Cable Tray Joint L100X100X50 m' 54,000
45 - Cable Tray Joint Reducer 300x200 m' -
46 - FRC 4 x 4 MM² m' 78,000
III ARMATURE , SAKLAR DAN STOP KONTAK -
1 - RMI (LED TUBE LAMP) 2x16 W Dimension 1200mm bh 420,000
2 Lampu Down Light PLC 18 W bh 150,000
3 Lampu LP HARR HLG 120 W bh 528,000
4 Lampu LB T5 2X18 W bh 384,000

5 -Wall Light 9x9 LED BULB E27 8 Watt bh 258,000


6 - Saklar Tunggal 10 A bh 54,000
7 - Saklar Serie 10 A bh 90,000
8 - Inbow Doos bh 18,000
9 Stop Kontak 1 pass bh 112,800
10 - Stop Kontak Indikator Lamp AC bh 294,000
11 - PJU LED 80 Watt IP66 C/W Pole 9 Meter bh 13,800,000
MATERIAL INSTALASI PENERANGAN DAN STOP KONTAK -
- Pipa Conduit PVC HI 20 mm m' 3,000
- Socket Pipa bh 6,600
- Tee Dos bh 3,840
- Klem Pipa bh 2,400
- Fhiser bh 1,800
- Las Doop m' 4,200

Page 140 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

- Isolasi Ban bh 5,400


12 - Pipa Conduit PVC HI 25 mm m' 30,000
1 2 3 5
B PEKERJAAN PENANGKAL PETIR DAN GROUNDING -
1 - Head Penangkal petir Kurn non radio aktif R 100 M unit 10,200,000
2 - Down Conductor cable N2XSY 70 mm Meter 96,600
3 - Dudukan tiang Penangkal petir unit 420,000
4 - Lightning Strike Counter unit 300,000
5 - Obstruction lamp unit 150,000
6 - Grounding Penangkal Petir -
- Cable BC 50 mm Meter 41,400
- Pipa 11/2" GIP Meter 150,000
- Pipa 2" GIP Meter 150,000
- Pipa 2 1/2" GIP Meter 234,000
- Spit Tembaga Buah 240,000
- Klem tembaga Buah 18,000
- Materia Bantu ls 30,000
- Upah pasang ls 180,000
- Bak kontrol Unit 540,000
C PEKERJAAN TELEPON -
11 - AH-99-PN Single line telephone unit -
12 - Outlet Telephone lantai unit 780,000
19 Instalasi Telephone -
- Kabel ITC 2 x 2 x 0,6 mm Meter 7,800
- Pipa Conduit PVC 20 mm Meter 1,500
- Fitting ( elbow ,male bush, Joint coupling) Buah 3,600
- Saddle Buah 18,000
- Fresher dan Scrup Buah 3,000
- Juntion box Buah 15,000
- Upah pasang Titik 90,000
D PEKERJAAN SOUND SYSTEM -
a BGM -
1 19" Rack 30 RU depth 600mm unit 7,800,000
2 NVR multiplexer 16 Chanel 1 Tera byte unit 1,500,000
3 CPU Komputer Kontrol 2 Video Out put unit 1,440,000
4 Radio Tuner Modulle AM/FM w/Ant. unit 1,620,000
5 X-MAP04 All in 1 audio source unit (include pre-amplifier) CD/MP3/FM/DAB unit 150,000

6 Monitor panel unit 900,000


7 Mixer Pre-amplifiyer w/ module unit 300,000
8 Sirine w/Relay switch Modulle unit 900,000
9 Program Selector Modulle unit 6,588,000
10 Equalizer module unit 3,900,000
11 Power switch panel unit 1,501,080
12 Junction box panel unit 1,440,000
13 Speaker Selector 10 Chanel unit 4,200,000

Page 141 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

14 Power amplifier 120W unit 9,000,000


15 X-DA4125EN High Efficiency Class D Power amplifier 4x125W, 100V/70 unit 3,840,000
16 Blower panel unit 2,520,000
17 Change Over Switch unit 9,000,000
18 X-NPMI Configurable Network Paging Console Microphone unit 3,840,000
19 Emergency Paging Microphone unit 3,840,000
20 Main Distriution Frame unit 2,100,000
21 Power Amplifier 360 watt unit 2,580,000
E PEKERJAAN FIRE ALARM -
1 MCFA 10 Zone Addressable 1 Loop + Battery + Surge Protector Set 230VAC unit 9,000,000

2 Annunciator RLCD-C unit 784,800


3 MI/DCZRM Conventional Zone Interface Module unit 1,440,000
4 - 5601P ROR Heat Detector 135 F unit 540,000
6 -B801RA Detector Base, Suport remote annunciator output with photo smoke unit 300,000
detector

8 - SSM24-6 Alarm Bell 6" unit 780,000


9 -SYS-ST Indicator lamp (STROBE) unit 300,000
12 Terminal BOX FA Unit 150,000
13 M400K/T Break Glass Alarm ( Manual Call Point) unit 420,000
14 Visual Notification Appliance unit 150,000
15 End Of Line ( EOL ) BBS-X Back Box unit 462,000
16 MI/DCMO Output control module unit 252,000
17 Terminal BOX FA unit 146,868
18 BBS-X Back Box 252,000
-
F PEKERJAAN CCTV -
1 HEN16104 NVR 16PoE Port/16 Chanel/H.265/4K unit 4,200,000
2 HED2PER3 IP BALL 2MP H.265 IR TDN 2.8mm PoE IP 66 CCTV Camera unit 6,360,000

2 HBD2PER1 IP BUL 2MP H.265 IR TDN 3.6mm PoE IP66 CCTV Camera unit 7,800,000

2 WD Purple 6 TB unit 294,000


3 Rack cabinet unit 4,320,000
4 Monitor LCD 32" unit 5,400,000
5 SMC-1000I-2U APC Smart UPS 1KVA 2U Rackmountable unit 1,452,000
6 NYMHY 2 x 1,5 mm2 Meter 16,680
7 UTP Cable Cat 6 Meter 16,200
7 Switch Hub 16 Port unit 150,000
7 Switch Hub 8 Port unit 114,000
G PEKERJAAN LAN/INSTALASI DATA -
- Pipa Conduit PVC 20 mm Meter 2,520
- Kabel UTP 2 x 2 x 0,6 mm Meter 3,360
- Pipa Conduit PVC 20 mm Meter 2,520
- Fitting ( elbow ,male bush, Joint coupling) Buah 4,200
- Saddle Buah 2,280
- Fresher dan Scrup Buah 3,000

Page 142 of 162


BAHAN MEKANIKAL DAN ELEKTRIKAL

NO. NAMA / JENIS BAHAN SATUAN HARGA SATUAN BAHAN

- Juntion box Buah 13,200


- Upah pasang Titik 120,000

Page 143 of 162


ANALISA MEKANIKAL

ANALISA HARGA BAHAN DAN UPAH


PEKERJAAN : MEKANIKAL dan PLUMBING

URUSAN PEMERINTAHAN : 1.11 / Lingkup Hidup


Organisasi : 1.1101201 / Suku Dinas Lingkup Hidup Kota Administrasi Jakarta Utara
Program : 1.11.01 / Program Pengelolahan Persamphan
Kegiatan : 1.11.01.019
/ Pembangunan TPS di Kota Administrasi jakarta Utara
(TPS Dipo Rawa Badak Utara)
Kode Rekening : 5.2.3.26.20 / Belanja Modal Pengadaan Kontruksi / Pembangunan Transito sampah
Tahun Anggaran : 2019

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


II PEKERJAAN MEKANIKAL

A PEKERJAAAN AIR CONDITION


1 RXQ26AMY14 VRV OUTDOOR 251.000 BTUH unit 1,00 0,00 4,550,000.00
- #VALUE!
- Perlengkapan unit 1,00
                          0,00 -455000 #VALUE!
Jumlah 5,005,000.00
- Upah Pekerja AC 0.9000 hr 157,643.00 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
Mandor AC hr                                -  
0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 5,374,136.95
Overhead & Profit 10%
10 % 537,413.70
Total Harga Satuan Pekerjaan 5,911,550.65

1 RXQ36AMY14 VRV OUTDOOR 341.000 BTUH unit 1.0000 0,00 -


5,850,000.00 5,850,000.00
- Perlengkapan unit 1,00
                          0,00 -585000 #VALUE!
Jumlah 6,435,000.00
- Upah Pekerja AC hr 0.9000 0,00 157,643.00
- 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
Mandor AC hr                                -  
0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 6,804,136.95
Overhead & Profit 10%
10 % 680,413.70
Total Harga Satuan Pekerjaan 7,484,550.65

1 RXQ42AMY14 VRV OUTDOOR 399.000 BTUH unit 1.0000 0,00 -


9,750,000.00 9,750,000.00
- Perlengkapan unit 1.0000 0,00 - 975000 975,000.00
Jumlah 10,725,000.00
- Upah Pekerja AC hr 0.9000 0,00 157,643.00
- 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
Mandor AC hr                                -  
0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 11,094,136.95
Overhead & Profit 10%
10 % 1,109,413.70
Total Harga Satuan Pekerjaan 12,203,550.65
1 FXAQ 20PVE4 AC VRV type Wall Mounted 7.500 Btu/h + Wired Re unit 1.0000 0,00 -
12,350,000.00 12,350,000.00
- Perlengkapan unit 1.0000 0,00 -
1235000 1,235,000.00
Jumlah 13,585,000.00
- Upah Pekerja AC hr 0.9000 0,00 157,643.00
- 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
hr                                -  
Mandor AC 0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 13,954,136.95
Overhead & Profit 10%
10 % 1,395,413.70
Total Harga Satuan Pekerjaan 15,349,550.65

2 FXAQ 25PVE4 AC VRV type Wall Mounted 9.600 Btu/h + Wired Re unit 1.0000 0,00 -
17,550,000.00 17,550,000.00
- Perlengkapan unit 1.0000 0,00 -
1755000 1,755,000.00
Jumlah 19,305,000.00
- Upah Pekerja AC hr 0.9000 0,00 -
157,643.00 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
hr                                -  
Mandor AC 0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 19,674,136.95
Overhead & Profit 10%
10 % 1,967,413.70
Total Harga Satuan Pekerjaan 21,641,550.65

3 FXAQ 32PVE4 AC VRV type Wall Mounted 12.300 Btu/h + Wired R unit 1.0000 0,00 19,500,000.00
- 19,500,000.00
- Perlengkapan unit 1.0000 0,00 -
1950000 1,950,000.00
Jumlah 21,450,000.00
- Upah Pekerja AC hr 0.9000 0,00 157,643.00
- 141,878.70
Tukang AC 0.7500 hr 166,729.00 125,046.75
Kepala tukang AC 0.4000 hr 182,676.00 73,070.40
hr                                -  
Mandor AC 0.1500 194,274.00 29,141.10
Jumlah -
Jumlah 369,136.95
Total 21,819,136.95
Overhead & Profit 10%
10 % 2,181,913.70

Page 144 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 24,001,050.65

4 FXAQ 40PVE4 AC VRV type Wall Mounted 15.400 Btu/h + Wired R unit 1.0000 0,00 23,400,000.00
- 23,400,000.00
- Perlengkapan unit 1.0000 0,00 -
2340000 2,340,000.00
Jumlah 25,740,000.00
- Upah Pekerja AC hr 1.0000 0,00 157,643.00
- 157,643.00
Tukang AC 0.8000 hr 166,729.00 133,383.20
Kepala tukang AC 0.4500 hr 182,676.00 82,204.20
Mandor AC hr                                -  
0.2000 194,274.00 38,854.80
Jumlah -
Jumlah 412,085.20
Total 26,152,085.20
Overhead & Profit 10%
10 % 2,615,208.52
Total Harga Satuan Pekerjaan 28,767,293.72

5 FXAQ 50PVE4 AC VRV type Wall Mounted 19.100 Btu/h + Wired R unit 1.0000 0,00 -
45,500,000.00 45,500,000.00
- Perlengkapan unit 1.0000 0,00 -
4550000 4,550,000.00
Jumlah 50,050,000.00
- Upah Pekerja AC hr 1.0000 0,00 157,643.00
- 157,643.00
Tukang AC 0.8000 hr 166,729.00 133,383.20
Kepala tukang AC 0.4500 hr 182,676.00 82,204.20
Mandor AC hr                                -  
0.2000 194,274.00 38,854.80
Jumlah -
Jumlah 412,085.20
Total 50,462,085.20
Overhead & Profit 10%
10 % 5,046,208.52
Total Harga Satuan Pekerjaan 55,508,293.72

6 FXAQ 63PVE4 AC VRV type Wall Mounted 24.200 Btu/h + Wired R unit 1.0000 0,00 -
37,700,000.00 37,700,000.00
- Perlengkapan unit 1.0000 0,00 -
3770000 3,770,000.00
Jumlah 41,470,000.00
- Upah Pekerja AC hr 1.1000 0,00 157,643.00
- 173,407.30
Tukang AC 0.9000 hr 166,729.00 150,056.10
Kepala tukang AC 0.5500 hr 182,676.00 100,471.80
hr                                -  
Mandor AC 0.3000 194,274.00 58,282.20
Jumlah -
Jumlah 482,217.40
Total 41,952,217.40
Overhead & Profit 10%
10 % 4,195,221.74
Total Harga Satuan Pekerjaan 46,147,439.14

7 FXFQ 50 AV4 VRV Cassette Round Flow 19.100 Btu/h + Navigatio 1.0000 unit 45,500,000.00 45,500,000.00
- Perlengkapan 1.0000 unit 4550000 4,550,000.00
Jumlah 50,050,000.00
- Upah Pekerja AC 1.2000 hr 157,643.00 189,171.60
Tukang AC 1.0000 hr 166,729.00 166,729.00
Kepala tukang AC 0.6500 hr 182,676.00 118,739.40
Mandor AC 0.4000 hr 194,274.00 77,709.60
Jumlah 552,349.60
Total - 50,602,349.60
Overhead & Profit 10%
10 % 5,060,234.96
Total Harga Satuan Pekerjaan 55,662,584.56

8 FXFQ 80 AV4 VRV Cassette Round Flow 30.700 Btu/h + Navigatio unit 1.0000 0,00 -
58,500,000.00 58,500,000.00
- Perlengkapan unit 1.0000 0,00 -
5850000 5,850,000.00
Jumlah 64,350,000.00
- Upah Pekerja AC hr 1.3500 0,00 157,643.00
- 212,818.05
Tukang AC 1.1500 hr 166,729.00 191,738.35
Kepala tukang AC 0.7500 hr 182,676.00 137,007.00
Mandor AC 0.5500 hr 194,274.00 106,850.70
Jumlah 648,414.10
Total - 64,998,414.10
Overhead & Profit 10%
10 % 6,499,841.41
Total Harga Satuan Pekerjaan 71,498,255.51

9 FXFQ 100 AV4 VRV Cassette Round Flow 38.200 Btu/h+ Navigatio unit 1.0000 0,00 -
84,500,000.00 84,500,000.00
- Perlengkapan unit 1.0000 0,00 -
8450000 8,450,000.00
Jumlah 92,950,000.00
- Upah Pekerja AC hr 1.3500 0,00 157,643.00
- 212,818.05
Tukang AC 1.1500 hr 166,729.00 191,738.35
Kepala tukang AC 0.7500 hr 182,676.00 137,007.00
Mandor AC 0.5500 hr 194,274.00 106,850.70
Jumlah 648,414.10
Total - 93,598,414.10
Overhead & Profit 10%
10 % 9,359,841.41
Total Harga Satuan Pekerjaan 102,958,255.51
9 FAN 50 Watt Type ceiling unit 1.0000 0,00 -
27,950,000.00 27,950,000.00
- Perlengkapan unit 1.0000 0,00 -
2795000 2,795,000.00
Jumlah 30,745,000.00
- Upah Pekerja AC hr 0.8000 0,00 157,643.00
- 126,114.40
Tukang AC 0.7000 hr 166,729.00 116,710.30
Kepala tukang AC 0.4500 hr 182,676.00 82,204.20
Mandor AC 0.3500 hr 194,274.00 67,995.90
Jumlah 393,024.80
Total - 31,138,024.80
Overhead & Profit 10%
10 % 3,113,802.48
Total Harga Satuan Pekerjaan 34,251,827.28

Page 145 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

B STANDART PIPA ASTM B 280


1 Pipa Refrigrant 1/4" 1,00 meter 32,500.00 #VALUE!
Isolasi pipa Refrigrant 1,00 meter 15,600.00 #VALUE!
Perlengkapan unit 1,00 0,00 -
4,810.00 #VALUE!
Jumlah 52,910.00
- Upah Pekerja AC 0.0400 hr 157,643.00 6,305.72
Tukang AC 0.0500 hr 166,729.00 8,336.45
Kepala tukang AC 0.0090 hr 182,676.00 1,644.08
Mandor AC 0.0030 hr 194,274.00 582.82
Jumlah 16,869.08
Total 69,779.08
Overhead & Profit 10%
10 % 6,977.91
Total Harga Satuan Pekerjaan 76,756.98

2 Pipa Refrigrant 3/8" 1.0000 meter 45,500.00 45,500.00


- Isolasi pipa Refrigrant 1.0000 meter 22,100.00 22,100.00
Perlengkapan unit 1,00 0,00 6,760.00
- #VALUE!
Jumlah 74,360.00
- Upah Pekerja AC 0.0400 hr 157,643.00 6,305.72
Tukang AC 0.0500 hr 166,729.00 8,336.45
Kepala tukang AC 0.0090 hr 182,676.00 1,644.08
Mandor AC 0.0030 hr 194,274.00 582.82
Jumlah 16,869.08
Total 91,229.08
Overhead & Profit 10%
10 % 9,122.91
Total Harga Satuan Pekerjaan 100,351.98

3 Pipa Refrigrant 1/4"X3/8" 3/4 - 1 PK 1.0000 meter 58,500.00 58,500.00

4 Pipa Refrigrant 1/2" 1.0000 meter 58,500.00 58,500.00


- Isolasi pipa Refrigrant 1.0000 meter 28,600.00 28,600.00
Perlengkapan unit 1,00 0,00 14,560.00
- #VALUE!
Jumlah 160,160.00
- Upah Pekerja AC 0.0600 hr 157,643.00 9,458.58
Tukang AC 0.0600 hr 166,729.00 10,003.74
Kepala tukang AC 0.0160 hr 182,676.00 2,922.82 -
Mandor AC 0.0040 hr 194,274.00 777.10
Jumlah 23,162.23
Total 183,322.23
Overhead & Profit 10%
10 % 18,332.22
Total Harga Satuan Pekerjaan 201,654.46

5 Pipa Refrigrant 1/4"X1/2" 1,5 PK 1.0000 meter 32,500.00 32,500.00 -

6 Pipa Refrigrant 5/8" 1.0000 meter 71,500.00 71,500.00 -


- Isolasi pipa Refrigrant 1.0000 meter 6,500.00 6,500.00 -
Perlengkapan unit 1,00 0,00 11050
- #VALUE!
Jumlah 121,550.00
- Upah Pekerja AC 0.0900 hr 157,643.00 14,187.87 -
Tukang AC 0.1000 hr 166,729.00 16,672.90 -
Kepala tukang AC 0.0240 hr 182,676.00 4,384.22 -
Mandor AC 0.0050 hr 194,274.00 971.37
Jumlah 36,216.36 -
Total 157,766.36
Overhead & Profit 10%
10 % 15,776.64
Total Harga Satuan Pekerjaan 173,543.00

7 - Pipa Refrigrant 3/4" 1.0000 meter 84,500.00 84,500.00


- Isolasi pipa Refrigrant 1.0000 meter 52,000.00 52,000.00
- Perlengkapan unit 1.0000 0,00 - 27300 27,300.00
Jumlah 163,800.00
- Upah Pekerja AC 0.0900 hr 157,643.00 14,187.87
Tukang AC 0.1000 hr 166,729.00 16,672.90
Kepala tukang AC 0.0240 hr 182,676.00 4,384.22
Mandor AC 0.0050 hr 194,274.00 971.37
Jumlah 36,216.36
Total 200,016.36
Overhead & Profit 10%
10 % 20,001.64
Total Harga Satuan Pekerjaan 220,018.00

8 - Pipa Refrigrant 1/4"X5/8" - 2 -2,5 PK 1.0000 meter 71,500.00 71,500.00 -

9 - Pipa Refrigrant 3/8"X5/8" - 3 - 4 PK 1.0000 meter 84,500.00 84,500.00 -

10 - Pipa Refrigrant 1/2"X3/4" - 5 PK 1.0000 meter 71,500.00 71,500.00 -

11 KHRP26A22T-S REFNET JOINT 1.0000 unit 94,250.00 94,250.00 -


- Perlengkapan unit 1.0000 0,00 -
32,175.00 32,175.00
Jumlah -
- Upah Pekerja AC 0.2200 hr 157,643.00 34,681.46 -
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -

Page 146 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 460,134.46 -

Total 460,134.46
Overhead & Profit 10%
10 % 46,013.45
Total Harga Satuan Pekerjaan 506,147.90

12 KHRP26A33T-S REFNET JOINT unit 1.0000 0,00 -


94,250.00 94,250.00
- Perlengkapan unit 1.0000 0,00 -
14,137.50 14,137.50
Jumlah 108,387.50
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 214,596.96
Overhead & Profit 10%
10 % 21,459.70
Total Harga Satuan Pekerjaan 236,056.65

13 KHRP26A72T-S REFNET JOINT unit 1.0000 0,00 -


113,100.00 113,100.00
- Perlengkapan unit 1.0000 0,00 11,310.00
- 11,310.00
Jumlah 124,410.00
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 230,619.46
Overhead & Profit 10%
10 % 23,061.95
Total Harga Satuan Pekerjaan 253,681.40

14 KHRP26A73T-S REFNET JOINT 1.0000 unit 207,350.00 207,350.00 -


- Perlengkapan unit 1.0000 0,00 -
41,470.00 41,470.00
Jumlah 248,820.00
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 355,029.46
Overhead & Profit 10%
10 % 35,502.95
Total Harga Satuan Pekerjaan 390,532.40

15 KHRP26M73TP9 PIPE SIZE REDUCER 1.0000 unit 301,600.00 301,600.00


- Perlengkapan unit 1.0000 0,00 -
45,240.00 45,240.00
Jumlah 346,840.00
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 - 9
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 453,049.46
Overhead & Profit 10%
10 % 45,304.95
Total Harga Satuan Pekerjaan 498,354.40

11 - Exhouse Fan 50 CFM( Ceilling ) 1.0000 unit 845,000.00 845,000.00


- Perlengkapan unit 1.0000 0,00 126,750.00
- 126,750.00
Jumlah 971,750.00
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 1,077,959.46
Overhead & Profit 10%
10 % 107,795.95
Total Harga Satuan Pekerjaan 1,185,755.40

12 Exhouse Fan 50 CFM (Wall Mounted) 1.0000 unit 1,235,000.00 1,235,000.00


- Perlengkapan unit 1.0000 0,00 -
185,250.00 185,250.00
Jumlah 1,420,250.00
- Upah Pekerja AC hr 0.2200 0,00 157,643.00
- 34,681.46
Tukang AC 0.2500 hr 166,729.00 41,682.25 -
Kepala tukang AC 0.0900 hr 182,676.00 16,440.84 -
Mandor AC 0.0690 hr 194,274.00 13,404.91
Jumlah 106,209.46 -

Total 1,526,459.46
Overhead & Profit 10%
10 % 152,645.95
Total Harga Satuan Pekerjaan 1,679,105.40

13 - Pipa draine 3/4" ( PVC) 1.0000 meter 25,800.00 25,800.00 -


- Isolasi 1.0000 meter 5,400.00 5,400.00 -
- Perlengkapan 1.0000 unit 3,120.00 3,120.00
Jumlah 34,320.00
- Upah Pekerja Ac 0.0100 hr 157,643.00 1,576.43
Tukang AC 0.0100 hr 166,729.00 1,667.29

Page 147 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Kepala tukang AC 0.0010 hr 182,676.00 182.68
Mandor AC - hr 194,274.00 -
Jumlah 3,426.40
Total 37,746.40
Overhead & Profit 10%
10 % 3,774.64
Total Harga Satuan Pekerjaan 41,521.04

14 Instalasi Stop Kontak AC, NYM 3 x 2,5 mm² dalam conduit PVC HI 20 mm² 15.0000 Meter 16,680.00 250,200.00
Pipa Conduit PVC HI 20 mm 15.0000 Meter 3,000.00 45,000.00
Stop Kontak Indikator Lamp AC 1.0000 Buah 294,000.00 294,000.00
Socket Pipa 3.7500 Buah 6,600.00 24,750.00
Tee Dos 2.0000 Buah 3,840.00 7,680.00
Klem Pipa 7.5000 Buah 2,400.00 18,000.00
Fhiser 15.0000 Buah 1,800.00 27,000.00
Las Doop 2.0000 Buah 4,200.00 8,400.00
Isolasi Ban 0.2500 Buah 5,400.00 1,350.00
Pekerja Listrik 0.4500 hr 157,643.00 70,939.35
Tukang Listrik 0.4000 hr 166,729.00 66,691.60
Kepala tukang Listrik 0.2200 hr 182,676.00 40,188.72
Mandor Listrik 0.1300 hr 194,274.00 25,255.62
Jumlah 879,455.29

15 Instalasi AC 3 phase, NYM 4 x 4 mm² dalam conduit PVC HI 25 mm² 15.0000 Meter 18,000.00 270,000.00
Pipa Conduit PVC HI 25 mm 15.0000 Meter 3,000.00 45,000.00
Socket Pipa 3.7500 Buah 294,000.00 1,102,500.00
Tee Dos 2.0000 Buah 6,600.00 13,200.00
Klem Pipa 7.5000 Buah 3,840.00 28,800.00
Fhiser 15.0000 Buah 2,400.00 36,000.00
Las Doop 2.0000 Buah 1,800.00 3,600.00
Isolasi Ban 0.2500 Buah 4,200.00 1,050.00
Pekerja Listrik 0.4500 hr 157,643.00 70,939.35
Tukang Listrik 0.4000 hr 166,729.00 66,691.60
Kepala tukang Listrik 0.2200 hr 182,676.00 40,188.72
Mandor Listrik 0.1300 hr 194,274.00 25,255.62
Jumlah 1,703,225.29

16 Instalasi Kabel Kontrol VRV NYMHy 4 x 1.5 mm² dalam conduit PVC 20 mm² 1.0000 Meter 16,320.00 16,320.00
Pipa Conduit PVC HI 20 mm 1.0000 Meter 3,000.00 3,000.00
Socket Pipa 0.2500 Buah 294,000.00 73,500.00
Tee Dos 0.1000 Buah 6,600.00 660.00
Klem Pipa 0.1500 Buah 3,840.00 576.00
Fhiser 0.1500 Buah 2,400.00 360.00
Las Doop 0.1000 Buah 1,800.00 180.00
Isolasi Ban 0.2500 Buah 4,200.00 1,050.00
Pekerja Listrik 0.0800 hr 157,643.00 12,611.44
Tukang Listrik 0.0500 hr 166,729.00 8,336.45
Kepala tukang Listrik 0.0300 hr 182,676.00 5,480.28
Mandor Listrik 0.0100 hr 194,274.00 1,942.74
Jumlah 124,016.91
F PEKERJAAN AIR BERSIH
1 Pompa Transfer 120 l/mnt, Head 40 m 1.0000 unit 16,250,000.00 16,250,000.00
Perlengkapan 1.0000 unit 1,625,000.00 1,625,000.00
Jumlah 17,875,000.00
Upah Pekerja pipa 0.9000 hr 157,643.00 141,878.70
Tukang pipa 0.9000 hr 166,729.00 150,056.10
Kepala tukang pipa 0.0900 hr 182,676.00 16,440.84
Mandor 0.0900 hr 194,274.00 17,484.66
Jumlah 325,860.30
Total - 18,200,860.30
Overhead & Profit 10%
10 % 1,820,086.03
Total Harga Satuan Pekerjaan 20,020,946.33

2 Pompa PDAM 150 l/mnt, Head 30 m- 9 m3/jam 1.0000 unit 13,520,000.00 13,520,000.00
Perlengkapan 1.0000 unit 2,028,000.00 2,028,000.00
Jumlah 15,548,000.00
Upah Pekerja pipa 0.9000 hr 157,643.00 141,878.70
Tukang pipa 0.9000 hr 166,729.00 150,056.10
Kepala tukang pipa 0.0900 hr 182,676.00 16,440.84
Mandor 0.0900 hr 194,274.00 17,484.66
Jumlah 325,860.30
Total - 15,873,860.30
Overhead & Profit 10%
10 % 1,587,386.03
Total Harga Satuan Pekerjaan 17,461,246.33

3 Pompa Booster VSD 2x100 l/mnt, Head 20 m Lengkap Panel Con 1.0000 unit 11,830,000.00 11,830,000.00
Perlengkapan 1.0000 unit 1,774,500.00 1,774,500.00
Jumlah 13,604,500.00
Upah Pekerja pipa 0.9000 hr 157,643.00 141,878.70
Tukang pipa 0.9000 hr 166,729.00 150,056.10
Kepala tukang pipa 0.0900 hr 182,676.00 16,440.84
Mandor 0.0900 hr 194,274.00 17,484.66
Jumlah 325,860.30
Total - 13,930,360.30
Overhead & Profit 10%
10 % 1,393,036.03

Page 148 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 15,323,396.33

4 Roof Tank Stainless steel Cap. 3.200 lt 1.0000 unit 8,125,000.00 8,125,000.00
Perlengkapan 1.0000 unit 1,218,750.00 1,218,750.00
Jumlah 9,343,750.00
Upah Pekerja pipa 0.9000 hr 157,643.00 141,878.70
Tukang pipa 0.9000 hr 166,729.00 150,056.10
Kepala tukang pipa 0.0900 hr 182,676.00 16,440.84
Mandor 0.0900 hr 194,274.00 17,484.66
Jumlah 325,860.30
Total - 9,669,610.30
Overhead & Profit 10%
10 % 966,961.03
Total Harga Satuan Pekerjaan 10,636,571.33

5 Pipa PPR PN 10 1/2" 1.0000 M' 54,000.00 54,000.00


Perlengkapan 1.0000 unit 8,100.00 8,100.00
Jumlah 62,100.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 68,005.09
Overhead & Profit 10%
10 % 6,800.51
Total Harga Satuan Pekerjaan 74,805.60

6 Pipa PPR PN 10 3/4" 1.0000 M' 72,000.00 72,000.00


Perlengkapan 1.0000 unit 10,800.00 10,800.00
Jumlah 82,800.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 88,705.09
Overhead & Profit 10%
10 % 8,870.51
Total Harga Satuan Pekerjaan 97,575.60

7 Pipa PPR PN 10 dia 1" 1.0000 M' 114,000.00 114,000.00


Perlengkapan 1.0000 unit 17,100.00 17,100.00
Jumlah 131,100.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 137,005.09
Overhead & Profit 10%
10 % 13,700.51
Total Harga Satuan Pekerjaan 150,705.60

8 Pipa PPR PN 10 dia 1 1/4" 1.0000 M' 132,000.00 132,000.00


Perlengkapan 1.0000 unit 19,800.00 19,800.00
Jumlah 151,800.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 157,705.09
Overhead & Profit 10%
10 % 15,770.51
Total Harga Satuan Pekerjaan 173,475.60

9 Pipa PPR PN 10 dia 1 1/2" 1.0000 M' 156,000.00 156,000.00


Perlengkapan 1.0000 unit 23,400.00 23,400.00
Jumlah 179,400.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 185,305.09
Overhead & Profit 10%
10 % 18,530.51
Total Harga Satuan Pekerjaan 203,835.60

10 Pipa PPR PN 10 dia 2" 1.0000 M' 192,000.00 192,000.00


` 1.0000 unit 28,800.00 28,800.00
Jumlah 220,800.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 226,705.09
Overhead & Profit 10%
10 % 22,670.51

Page 149 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 249,375.60

11 Pipa PPR PN 10 dia 2 1/2" 1.0000 M' 252,000.00 252,000.00


Perlengkapan 1.0000 unit 37,800.00 37,800.00
Jumlah 289,800.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 295,705.09
Overhead & Profit 10%
10 % 29,570.51
Total Harga Satuan Pekerjaan 325,275.60

12 Pipa PPR PN 10 dia 3" 1.0000 M' 300,000.00 300,000.00


Perlengkapan 1.0000 unit 45,000.00 45,000.00
Jumlah 345,000.00
Upah Pekerja pipa 0.0150 hr 157,643.00 2,364.65
Tukang pipa 0.0100 hr 166,729.00 1,667.29
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 5,905.09
Total - 350,905.09
Overhead & Profit 10%
10 % 35,090.51
Total Harga Satuan Pekerjaan 385,995.60

1 Water level Control 1.0000 unit 780,000.00 780,000.00


Perlengkapan 1.0000 unit 117,000.00 117,000.00
Jumlah 897,000.00
Upah Pekerja pipa 0.2500 hr 157,643.00 39,410.75
Tukang pipa 0.3100 hr 166,729.00 51,685.99
Kepala tukang pipa 0.0390 hr 182,676.00 7,124.36
Mandor 0.0230 hr 194,274.00 4,468.30
Jumlah 102,689.41
Total - 999,689.41
Overhead & Profit 10%
10 % 99,968.94
Total Harga Satuan Pekerjaan 1,099,658.35

10 Chek Valve 1 1/2" 1.0000 unit 94,800.00 94,800.00


Perlengkapan 1.0000 unit 14,220.00 14,220.00
Jumlah 109,020.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 124,904.75
Overhead & Profit 10%
10 % 12,490.48
Total Harga Satuan Pekerjaan 137,395.23

11 Chek Valve 2" 1.0000 unit 162,000.00 162,000.00


Perlengkapan 1.0000 unit 24,300.00 24,300.00
Jumlah 186,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 202,184.75
Overhead & Profit 10%
10 % 20,218.48
Total Harga Satuan Pekerjaan 222,403.23

12 Ball Valve 3/4" 1.0000 unit 18,000.00 18,000.00


Perlengkapan 1.0000 unit 2,700.00 2,700.00
Jumlah 20,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 36,584.75
Overhead & Profit 10%
10 % 3,658.48
Total Harga Satuan Pekerjaan 40,243.23

13 Ball Valve 1" 1.0000 unit 24,000.00 24,000.00


Perlengkapan 1.0000 unit 3,600.00 3,600.00
Jumlah 27,600.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 43,484.75
Overhead & Profit 10%
10 % 4,348.48

Page 150 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 47,833.23

14 Ball Valve 1 1/2" 1.0000 unit 42,000.00 42,000.00


Perlengkapan 1.0000 unit 6,300.00 6,300.00
Jumlah 48,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 64,184.75
Overhead & Profit 10%
10 % 6,418.48
Total Harga Satuan Pekerjaan 70,603.23

15 Ball Valve 2" 1.0000 unit 66,000.00 66,000.00


Perlengkapan 1.0000 unit 9,900.00 9,900.00
Jumlah 75,900.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 91,784.75
Overhead & Profit 10%
10 % 9,178.48
Total Harga Satuan Pekerjaan 100,963.23

16 Gate Valve 1" 1.0000 unit 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 133,184.75
Overhead & Profit 10%
10 % 13,318.48
Total Harga Satuan Pekerjaan 146,503.23

17 Gate Valve 1 1/4" 1.0000 unit 133,200.00 133,200.00


Perlengkapan 1.0000 unit 19,980.00 19,980.00
Jumlah 153,180.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 169,064.75
Overhead & Profit 10%
10 % 16,906.48
Total Harga Satuan Pekerjaan 185,971.23

18 Gate Valve 1 1/2" flange 1.0000 unit 174,000.00 174,000.00


Perlengkapan 1.0000 unit 26,100.00 26,100.00
Jumlah 200,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75
Total - 215,984.75
Overhead & Profit 10%
10 % 21,598.48
Total Harga Satuan Pekerjaan 237,583.23

19 Gate Valve 2" 1.0000 unit 210,000.00 210,000.00


Perlengkapan 1.0000 unit 31,500.00 31,500.00
Jumlah 241,500.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah
Total - 241,500.00
Overhead & Profit 10%
10 % 24,150.00
Total Harga Satuan Pekerjaan 265,650.00

20 Gate Valve 2 1/2" 1.0000 unit 258,000.00 258,000.00


Perlengkapan 1.0000 unit 38,700.00 38,700.00
Jumlah 296,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah
Total - 296,700.00
Overhead & Profit 10%
10 % 29,670.00

Page 151 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 326,370.00

20 Strainer 1 1/2" 1.0000 unit 162,000.00 162,000.00


Perlengkapan 1.0000 unit 24,300.00 24,300.00
Jumlah 186,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 202,184.75
Overhead & Profit 10%
10 % 20,218.48
Total Harga Satuan Pekerjaan 222,403.23

19 Strainer 2 1/2" 1.0000 unit 252,000.00 252,000.00


Perlengkapan 1.0000 unit 37,800.00 37,800.00
Jumlah 289,800.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 305,684.75
Overhead & Profit 10%
10 % 30,568.48
Total Harga Satuan Pekerjaan 336,253.23

20 Pressure gauge 1/2" 1.0000 unit 162,000.00 162,000.00


Perlengkapan 1.0000 unit 24,300.00 24,300.00
Jumlah 186,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 202,184.75
Overhead & Profit 10%
10 % 20,218.48
Total Harga Satuan Pekerjaan 222,403.23

21 Foot valve 2 " 1.0000 unit 108,000.00 108,000.00


Perlengkapan 1.0000 unit 16,200.00 16,200.00
Jumlah 124,200.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 140,084.75
Overhead & Profit 10%
10 % 14,008.48
Total Harga Satuan Pekerjaan 154,093.23

22 Flow control valve 1 1/2 " 1.0000 unit 78,000.00 78,000.00


Perlengkapan 1.0000 unit 11,700.00 11,700.00
Jumlah 89,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 105,584.75
Overhead & Profit 10%
10 % 10,558.48
Total Harga Satuan Pekerjaan 116,143.23

23 Flow control valve 1 " 1.0000 unit 150,000.00 150,000.00


Perlengkapan 1.0000 unit 22,500.00 22,500.00
Jumlah 172,500.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 188,384.75
Overhead & Profit 10%
10 % 18,838.48
Total Harga Satuan Pekerjaan 207,223.23

24 CAP 3/4" 1.0000 unit 78,000.00 78,000.00


Perlengkapan 1.0000 unit 11,700.00 11,700.00
Jumlah 89,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 105,584.75
Overhead & Profit 10%
10 % 10,558.48
Total Harga Satuan Pekerjaan 116,143.23

25 CAP 1" 1.0000 unit 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45

Page 152 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 133,184.75
Overhead & Profit 10%
10 % 13,318.48
Total Harga Satuan Pekerjaan 146,503.23

26 Reducer 1 1/2" x 1" 1.0000 unit 114,000.00 114,000.00


Perlengkapan 1.0000 unit 17,100.00 17,100.00
Jumlah 131,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 146,984.75
Overhead & Profit 10%
10 % 14,698.48
Total Harga Satuan Pekerjaan 161,683.23

27 Elbow 90" ¾" 1.0000 unit 42,000.00 42,000.00


Perlengkapan 1.0000 unit 6,300.00 6,300.00
Jumlah 48,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 64,184.75
Overhead & Profit 10%
10 % 6,418.48
Total Harga Satuan Pekerjaan 70,603.23

28 Elbow 90" 1/2" 1.0000 unit 90,000.00 90,000.00


Perlengkapan 1.0000 unit 13,500.00 13,500.00
Jumlah 103,500.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 119,384.75
Overhead & Profit 10%
10 % 11,938.48
Total Harga Satuan Pekerjaan 131,323.23

29 Elbow 90" 1" 1.0000 unit 174,000.00 174,000.00


Perlengkapan 1.0000 unit 26,100.00 26,100.00
Jumlah 200,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 215,984.75
Overhead & Profit 10%
10 % 21,598.48
Total Harga Satuan Pekerjaan 237,583.23

30 Elbow 90" 1 1/4" 1.0000 unit 228,000.00 228,000.00


Perlengkapan 1.0000 unit 34,200.00 34,200.00
Jumlah 262,200.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 278,084.75
Overhead & Profit 10%
10 % 27,808.48
Total Harga Satuan Pekerjaan 305,893.23

31 Elbow 90" 2" 1.0000 unit 294,000.00 294,000.00


Perlengkapan 1.0000 unit 44,100.00 44,100.00
Jumlah 338,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 353,984.75
Overhead & Profit 10%
10 % 35,398.48
Total Harga Satuan Pekerjaan 389,383.23

32 Elbow 90" 2" 1.0000 unit 294,000.00 294,000.00


Perlengkapan 1.0000 unit 44,100.00 44,100.00
Jumlah 338,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 353,984.75
Overhead & Profit 10%
10 % 35,398.48
Total Harga Satuan Pekerjaan 389,383.23

33 ELBOW FEMALE THREAD ½" 1.0000 unit 30,000.00 30,000.00

Page 153 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Perlengkapan 1.0000 unit 4,500.00 4,500.00
Jumlah 34,500.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 50,384.75
Overhead & Profit 10%
10 % 5,038.48
Total Harga Satuan Pekerjaan 55,423.23

34 REDUCER FEMALE ¾" x ½" 1.0000 unit 78,000.00 78,000.00


Perlengkapan 1.0000 unit 11,700.00 11,700.00
Jumlah 89,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 105,584.75
Overhead & Profit 10%
10 % 10,558.48
Total Harga Satuan Pekerjaan 116,143.23

35 TEE 1" x ¾" x 1" 1.0000 unit 54,000.00 54,000.00


Perlengkapan 1.0000 unit 8,100.00 8,100.00
Jumlah 62,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 77,984.75
Overhead & Profit 10%
10 % 7,798.48
Total Harga Satuan Pekerjaan 85,783.23

36 TEE 1" x ¾" x 1" 1.0000 unit 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 133,184.75
Overhead & Profit 10%
10 % 13,318.48
Total Harga Satuan Pekerjaan 146,503.23

37 TEE 1" x ½" x 1" 1.0000 unit 40,800.00 40,800.00


Perlengkapan 1.0000 unit 6,120.00 6,120.00
Jumlah 46,920.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 62,804.75
Overhead & Profit 10%
10 % 6,280.48
Total Harga Satuan Pekerjaan 69,085.23

33 EQUAL TEE ½" 1.0000 unit 42,000.00 42,000.00


Perlengkapan 1.0000 unit 6,300.00 6,300.00
Jumlah 48,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 64,184.75
Overhead & Profit 10%
10 % 6,418.48
Total Harga Satuan Pekerjaan 70,603.23

34 EQUAL TEE 1" 1.0000 unit 132,000.00 132,000.00


Perlengkapan 1.0000 unit 19,800.00 19,800.00
Jumlah 151,800.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 167,684.75
Overhead & Profit 10%
10 % 16,768.48
Total Harga Satuan Pekerjaan 184,453.23

34 EQUAL TEE 1 1/2" 1.0000 unit 216,000.00 216,000.00


Perlengkapan 1.0000 unit 32,400.00 32,400.00
Jumlah 248,400.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 264,284.75

Page 154 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Overhead & Profit 10%
10 % 26,428.48
Total Harga Satuan Pekerjaan 290,713.23

34 EQUAL TEE 2" 1.0000 unit 324,000.00 324,000.00


Perlengkapan 1.0000 unit 48,600.00 48,600.00
Jumlah 372,600.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 388,484.75
Overhead & Profit 10%
10 % 38,848.48
Total Harga Satuan Pekerjaan 427,333.23

35 COUPLER 1½" 1.0000 unit 90,000.00 90,000.00


Perlengkapan 1.0000 unit 13,500.00 13,500.00
Jumlah 103,500.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 119,384.75
Overhead & Profit 10%
10 % 11,938.48
Total Harga Satuan Pekerjaan 131,323.23

36 COUPLER 1" 1.0000 unit 82,800.00 82,800.00


Perlengkapan 1.0000 unit 12,420.00 12,420.00
Jumlah 95,220.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 111,104.75
Overhead & Profit 10%
10 % 11,110.48
Total Harga Satuan Pekerjaan 122,215.23

37 COUPLER 3/4" 1.0000 unit 69,600.00 69,600.00


Perlengkapan 1.0000 unit 10,440.00 10,440.00
Jumlah 80,040.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 95,924.75
Overhead & Profit 10%
10 % 9,592.48
Total Harga Satuan Pekerjaan 105,517.23

38 COUPLER 1/2" 1.0000 unit - -


Perlengkapan 1.0000 unit 51,600.00 51,600.00
Jumlah 51,600.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 67,484.75
Overhead & Profit 10%
10 % 6,748.48
Total Harga Satuan Pekerjaan 74,233.23

39 FLANGE 1 1/2" 1.0000 unit 38,400.00 38,400.00


Perlengkapan 1.0000 unit 5,760.00 5,760.00
Jumlah 44,160.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 60,044.75
Overhead & Profit 10%
10 % 6,004.48
Total Harga Satuan Pekerjaan 66,049.23

40 FLANGE 2" 1.0000 unit 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 133,184.75
Overhead & Profit 10%
10 % 13,318.48
Total Harga Satuan Pekerjaan 146,503.23

41 BLIND FLANGE 1 1/2" 1.0000 unit 138,000.00 138,000.00


Perlengkapan 1.0000 unit 20,700.00 20,700.00
Jumlah 158,700.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15

Page 155 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 174,584.75
Overhead & Profit 10%
10 % 17,458.48
Total Harga Satuan Pekerjaan 192,043.23

42 BLIND FLANGE 2" 1.0000 unit 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 133,184.75
Overhead & Profit 10%
10 % 13,318.48
Total Harga Satuan Pekerjaan 146,503.23

43 Pipa 2" GIP 1.0000 unit 114,000.00 114,000.00


Perlengkapan 1.0000 unit 17,100.00 17,100.00
Jumlah 131,100.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 146,984.75
Overhead & Profit 10%
10 % 14,698.48
Total Harga Satuan Pekerjaan 161,683.23

44 Pipa 2 1/2" GIP 1.0000 unit 170,400.00 170,400.00


Perlengkapan 1.0000 unit 25,560.00 25,560.00
Jumlah 195,960.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0500 hr 166,729.00 8,336.45
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 15,884.75 211,844.75
Overhead & Profit 10%
10 % 21,184.48
Total Harga Satuan Pekerjaan 233,029.23

G PEKERJAAN AIR KOTOR, AIR BEKAS, VENTING


1 Pipa PVC - D dia 1 1/4" 1.0000 M' 25,800.00 25,800.00
Perlengkapan 1.0000 unit 3,870.00 3,870.00
Jumlah 29,670.00
Upah Pekerja pipa 0.0360 hr 157,643.00 5,675.15
Tukang pipa 0.0600 hr 166,729.00 10,003.74
Kepala tukang pipa 0.0060 hr 182,676.00 1,096.06
Mandor 0.0020 hr 194,274.00 388.55
Jumlah 17,163.49 46,833.49
Overhead & Profit 10%
10 % 4,683.35
Total Harga Satuan Pekerjaan 51,516.84

2 Pipa PVC - D dia 1 1/2" 1.0000 M' 42,000.00 42,000.00


Perlengkapan 1.0000 unit 6,300.00 6,300.00
Jumlah 48,300.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0090 hr 182,676.00 1,644.08
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 25,745.24 74,045.24
Overhead & Profit 10%
10 % 7,404.52
Total Harga Satuan Pekerjaan 81,449.76

3 Pipa PVC - D dia 2" 1.0000 M' 50,400.00 50,400.00


Perlengkapan 1.0000 unit 7,560.00 7,560.00
Jumlah 57,960.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0090 hr 182,676.00 1,644.08
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 25,745.24 83,705.24
Overhead & Profit 10%
10 % 8,370.52
Total Harga Satuan Pekerjaan 92,075.76

4 Pipa PVC - D dia 4" 1.0000 M' 168,000.00 168,000.00


Perlengkapan 1.0000 unit 25,200.00 25,200.00
Jumlah 193,200.00
Upah Pekerja pipa 0.0810 hr 157,643.00 12,769.08
Tukang pipa 0.1350 hr 166,729.00 22,508.42
Kepala tukang pipa 0.0140 hr 182,676.00 2,557.46
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 38,612.06 231,812.06
Overhead & Profit 10%
10 % 23,181.21
Total Harga Satuan Pekerjaan 254,993.26

Page 156 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

5 Pipa PVC - D dia 6" 1.0000 M' 204,000.00 204,000.00


Perlengkapan 1.0000 unit 30,600.00 30,600.00
Jumlah 234,600.00
Upah Pekerja pipa 0.0810 hr 157,643.00 12,769.08
Tukang pipa 0.1350 hr 166,729.00 22,508.42
Kepala tukang pipa 0.0140 hr 182,676.00 2,557.46
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 38,612.06 273,212.06
Overhead & Profit 10%
10 % 27,321.21
Total Harga Satuan Pekerjaan 300,533.26

5 Pipa PVC - AW dia 3" 1.0000 M' 108,000.00 108,000.00


Perlengkapan 1.0000 unit 16,200.00 16,200.00
Jumlah 124,200.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0900 hr 182,676.00 16,440.84
Mandor 0.0300 hr 194,274.00 5,828.22
Jumlah 45,787.39 169,987.39
Overhead & Profit 10%
10 % 16,998.74
Total Harga Satuan Pekerjaan 186,986.13

5 Pipa PVC - AW dia 1 1/2" 1.0000 M' 76,800.00 76,800.00


Perlengkapan 1.0000 unit 11,520.00 11,520.00
Jumlah 88,320.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0090 hr 182,676.00 1,644.08
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 25,745.24 114,065.24
Overhead & Profit 10%
10 % 11,406.52
Total Harga Satuan Pekerjaan 125,471.76

5 Pipa PVC - AW dia 2" 1.0000 M' 90,000.00 90,000.00


Perlengkapan 1.0000 unit 13,500.00 13,500.00
Jumlah 103,500.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0090 hr 182,676.00 1,644.08
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 25,745.24 129,245.24
Overhead & Profit 10%
10 % 12,924.52
Total Harga Satuan Pekerjaan 142,169.76

5 Pipa PVC - AW dia 4" 1.0000 M' 174,000.00 174,000.00


Perlengkapan 1.0000 unit 26,100.00 26,100.00
Jumlah 200,100.00
Upah Pekerja pipa 0.0540 hr 157,643.00 8,512.72
Tukang pipa 0.0900 hr 166,729.00 15,005.61
Kepala tukang pipa 0.0090 hr 182,676.00 1,644.08
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 25,745.24 225,845.24
Overhead & Profit 10%
10 % 22,584.52
Total Harga Satuan Pekerjaan 248,429.76

5 Pipa PVC - AW dia 6" 1.0000 M' 258,000.00 258,000.00


Perlengkapan 1.0000 unit 38,700.00 38,700.00
Jumlah 296,700.00
Upah Pekerja pipa 0.0810 hr 157,643.00 12,769.08
Tukang pipa 0.1350 hr 166,729.00 22,508.42
Kepala tukang pipa 0.0140 hr 182,676.00 2,557.46
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 38,612.06 335,312.06
Overhead & Profit 10%
10 % 33,531.21
Total Harga Satuan Pekerjaan 368,843.26

5 Pipa PVC - AW dia 2 1/2" 1.0000 M' 100,800.00 100,800.00


Perlengkapan 1.0000 unit 15,120.00 15,120.00
Jumlah 115,920.00
Upah Pekerja pipa 0.0810 hr 157,643.00 12,769.08
Tukang pipa 0.1350 hr 166,729.00 22,508.42
Kepala tukang pipa 0.0140 hr 182,676.00 2,557.46
Mandor 0.0040 hr 194,274.00 777.10
Jumlah 38,612.06 154,532.06
Overhead & Profit 10%
10 % 15,453.21
Total Harga Satuan Pekerjaan 169,985.26

6 CLEAN OUT dia 6 " 1.0000 M' 252,000.00 252,000.00


Perlengkapan 1.0000 unit 37,800.00 37,800.00
Jumlah 289,800.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0700 hr 182,676.00 12,787.32

Page 157 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Mandor 0.0300 hr 194,274.00 5,828.22
Jumlah 25,057.55 314,857.55
Overhead & Profit 10%
10 % 31,485.76
Total Harga Satuan Pekerjaan 346,343.31

6 CLEAN OUT dia 4 " 1.0000 M' 216,000.00 216,000.00


Perlengkapan 1.0000 unit 32,400.00 32,400.00
Jumlah 248,400.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0700 hr 182,676.00 12,787.32
Mandor 0.0300 hr 194,274.00 5,828.22
Jumlah 25,057.55 273,457.55
Overhead & Profit 10%
10 % 27,345.76
Total Harga Satuan Pekerjaan 300,803.31

6 POMPA SUMPIT KAP 200 Lpm, HEAD 20 meter 1.0000 M' 2,580,000.00 2,580,000.00
Perlengkapan 1.0000 unit 387,000.00 387,000.00
Jumlah 2,967,000.00
Upah Pekerja pipa 1.0000 hr 157,643.00 157,643.00
Tukang pipa 0.9000 hr 166,729.00 150,056.10
Kepala tukang pipa 0.3500 hr 182,676.00 63,936.60
Mandor 0.1000 hr 194,274.00 19,427.40
Jumlah 391,063.10 3,358,063.10
Overhead & Profit 10%
10 % 335,806.31
Total Harga Satuan Pekerjaan 3,693,869.41

6 ELBOW 90° 1" 1.0000 M' 3,720.00 3,720.00


Perlengkapan 1.0000 unit 558.00 558.00
Jumlah 4,278.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 12,581.56
Overhead & Profit 10%
10 % 1,258.16
Total Harga Satuan Pekerjaan 13,839.72

7 ELBOW 90° 1½" 1.0000 M' 9,240.00 9,240.00


Perlengkapan 1.0000 unit 1,386.00 1,386.00
Jumlah 10,626.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 18,929.56
Overhead & Profit 10%
10 % 1,892.96
Total Harga Satuan Pekerjaan 20,822.52

8 ELBOW 90° 2" 1.0000 M' 14,160.00 14,160.00


Perlengkapan 1.0000 unit 2,124.00 2,124.00
Jumlah 16,284.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 24,587.56
Overhead & Profit 10%
10 % 2,458.76
Total Harga Satuan Pekerjaan 27,046.32

9 ELBOW 90° 4" 1.0000 M' 69,600.00 69,600.00


Perlengkapan 1.0000 unit 10,440.00 10,440.00
Jumlah 80,040.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 88,343.56
Overhead & Profit 10%
10 % 8,834.36
Total Harga Satuan Pekerjaan 97,177.92

10 ELBOW 45° 2" 1.0000 M' 6,000.00 6,000.00


Perlengkapan 1.0000 unit 900.00 900.00
Jumlah 6,900.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 15,203.56
Overhead & Profit 10%
10 % 1,520.36
Total Harga Satuan Pekerjaan 16,723.92

11 ELBOW 45° 4" 1.0000 M' 24,000.00 24,000.00


Perlengkapan 1.0000 unit 3,600.00 3,600.00

Page 158 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Jumlah 27,600.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 35,903.56
Overhead & Profit 10%
10 % 3,590.36
Total Harga Satuan Pekerjaan 39,493.92

12 ELBOW 45° 6" 1.0000 M' 84,000.00 84,000.00


Perlengkapan 1.0000 unit 12,600.00 12,600.00
Jumlah 96,600.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 104,903.56
Overhead & Profit 10%
10 % 10,490.36
Total Harga Satuan Pekerjaan 115,393.92

13 Y-BRANCH 2" 1.0000 M' 24,000.00 24,000.00


Perlengkapan 1.0000 unit 3,600.00 3,600.00
Jumlah 27,600.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 35,903.56
Overhead & Profit 10%
10 % 3,590.36
Total Harga Satuan Pekerjaan 39,493.92

14 Y-BRANCH 2" x 4" 1.0000 M' 48,000.00 48,000.00


Perlengkapan 1.0000 unit 7,200.00 7,200.00
Jumlah 55,200.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 63,503.56
Overhead & Profit 10%
10 % 6,350.36
Total Harga Satuan Pekerjaan 69,853.92

15 Y-BRANCH 4" 1.0000 M' 66,000.00 66,000.00


Perlengkapan 1.0000 unit 9,900.00 9,900.00
Jumlah 75,900.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 84,203.56
Overhead & Profit 10%
10 % 8,420.36
Total Harga Satuan Pekerjaan 92,623.92

16 REDUCER 1½"X1" 1.0000 M' 42,000.00 42,000.00


Perlengkapan 1.0000 unit 6,300.00 6,300.00
Jumlah 48,300.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 56,603.56
Overhead & Profit 10%
10 % 5,660.36
Total Harga Satuan Pekerjaan 62,263.92

17 REDUCER 1½"X 2 " 1.0000 M' 68,400.00 68,400.00


Perlengkapan 1.0000 unit 10,260.00 10,260.00
Jumlah 78,660.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 86,963.56
Overhead & Profit 10%
10 % 8,696.36
Total Harga Satuan Pekerjaan 95,659.92

18 REDUCER 2" x 1" 1.0000 M' 108,000.00 108,000.00


Perlengkapan 1.0000 unit 16,200.00 16,200.00
Jumlah 124,200.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 132,503.56
Overhead & Profit 10%
10 % 13,250.36

Page 159 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)


Total Harga Satuan Pekerjaan 145,753.92

19 REDUCER 2" x 4" 1.0000 M' 144,000.00 144,000.00


Perlengkapan 1.0000 unit 21,600.00 21,600.00
Jumlah 165,600.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 173,903.56
Overhead & Profit 10%
10 % 17,390.36
Total Harga Satuan Pekerjaan 191,293.92

20 LARGE RADIUS TEE 1" 1.0000 M' 78,000.00 78,000.00


Perlengkapan 1.0000 unit 11,700.00 11,700.00
Jumlah 89,700.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 98,003.56
Overhead & Profit 10%
10 % 9,800.36
Total Harga Satuan Pekerjaan 107,803.92

Page 160 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

21 LARGE RADIUS TEE 1 1/2" 1.0000 M' 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 125,603.56
Overhead & Profit 10%
10 % 12,560.36
Total Harga Satuan Pekerjaan 138,163.92

22 LARGE RADIUS TEE 1" x 2" 1.0000 M' 108,000.00 108,000.00


Perlengkapan 1.0000 unit 16,200.00 16,200.00
Jumlah 124,200.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 132,503.56
Overhead & Profit 10%
10 % 13,250.36
Total Harga Satuan Pekerjaan 145,753.92

23 LARGE RADIUS TEE 1½" x 2" 1.0000 M' 108,000.00 108,000.00


Perlengkapan 1.0000 unit 16,200.00 16,200.00
Jumlah 124,200.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 132,503.56
Overhead & Profit 10%
10 % 13,250.36
Total Harga Satuan Pekerjaan 145,753.92

24 LARGE RADIUS TEE 4" 1.0000 M' 282,000.00 282,000.00


Perlengkapan 1.0000 unit 42,300.00 42,300.00
Jumlah 324,300.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 332,603.56
Overhead & Profit 10%
10 % 33,260.36
Total Harga Satuan Pekerjaan 365,863.92

25 LARGE RADIUS TEE 4" x 6" 1.0000 M' 295,080.00 295,080.00


Perlengkapan 1.0000 unit 44,262.00 44,262.00
Jumlah 339,342.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 347,645.56
Overhead & Profit 10%
10 % 34,764.56
Total Harga Satuan Pekerjaan 382,410.12

Page 161 of 162


ANALISA MEKANIKAL

NO JENIS PEKERJAAN VOL SAT HARGA SATUAN (Rp) JUMLAH (Rp)

26 LARGE RADIUS TEE 6" 1.0000 M' 378,000.00 378,000.00


Perlengkapan 1.0000 unit 56,700.00 56,700.00
Jumlah 434,700.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 443,003.56
Overhead & Profit 10%
10 % 44,300.36
Total Harga Satuan Pekerjaan 487,303.92

26 FLOOR DRAIN 4" 1.0000 M' 270,000.00 270,000.00


Perlengkapan 1.0000 unit 40,500.00 40,500.00
Jumlah 310,500.00
Upah Pekerja pipa 0.0100 hr 157,643.00 1,576.43
Tukang pipa 0.1000 hr 166,729.00 16,672.90
Kepala tukang pipa 0.0100 hr 182,676.00 1,826.76
Mandor 0.0050 hr 194,274.00 971.37
Jumlah 21,047.46 331,547.46
Overhead & Profit 10%
10 % 33,154.75
Total Harga Satuan Pekerjaan 364,702.21

27 FLOOR CLEAN OUT 2" 1.0000 M' 114,000.00 114,000.00


Perlengkapan 1.0000 unit 17,100.00 17,100.00
Jumlah 131,100.00
Upah Pekerja pipa 0.0100 hr 157,643.00 1,576.43
Tukang pipa 0.1000 hr 166,729.00 16,672.90
Kepala tukang pipa 0.0100 hr 182,676.00 1,826.76
Mandor 0.0050 hr 194,274.00 971.37
Jumlah 21,047.46 152,147.46
Overhead & Profit 10%
10 % 15,214.75
Total Harga Satuan Pekerjaan 167,362.21

28 FLOOR CLEAN OUT 4" 1.0000 M' 144,000.00 144,000.00


Perlengkapan 1.0000 unit 21,600.00 21,600.00
Jumlah 165,600.00
Upah Pekerja pipa 0.0100 hr 157,643.00 1,576.43
Tukang pipa 0.1000 hr 166,729.00 16,672.90
Kepala tukang pipa 0.0100 hr 182,676.00 1,826.76
Mandor 0.0050 hr 194,274.00 971.37
Jumlah 21,047.46 186,647.46
Overhead & Profit 10%
10 % 18,664.75
Total Harga Satuan Pekerjaan 205,312.21

28 Vent Cap 2" 1.0000 M' 102,000.00 102,000.00


Perlengkapan 1.0000 unit 15,300.00 15,300.00
Jumlah 117,300.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 125,603.56
Overhead & Profit 10%
10 % 12,560.36
Total Harga Satuan Pekerjaan 138,163.92

29 Kawat Ayam 1.0000 M' 78,000.00 78,000.00


Perlengkapan 1.0000 unit 11,700.00 11,700.00
Jumlah 89,700.00
Upah Pekerja pipa 0.0250 hr 157,643.00 3,941.08
Tukang pipa 0.0150 hr 166,729.00 2,500.94
Kepala tukang pipa 0.0070 hr 182,676.00 1,278.73
Mandor 0.0030 hr 194,274.00 582.82
Jumlah 8,303.56 98,003.56
Overhead & Profit 10%
10 % 9,800.36
Total Harga Satuan Pekerjaan 107,803.92

30 ROOF DRAIN 4" 1.0000 M' 222,000.00 222,000.00


Perlengkapan 1.0000 unit 33,300.00 33,300.00
Jumlah 255,300.00
Upah Pekerja pipa 0.0100 hr 157,643.00 1,576.43
Tukang pipa 0.1000 hr 166,729.00 16,672.90
Kepala tukang pipa 0.0100 hr 182,676.00 1,826.76
Mandor 0.0050 hr 194,274.00 971.37
Jumlah 21,047.46 276,347.46
Overhead & Profit 10%
10 % 27,634.75
Total Harga Satuan Pekerjaan 303,982.21

Page 162 of 162