Professional Documents
Culture Documents
Chris Harris, Rick Harris - Lean Connections - Making Information Flow Efficiently and Effectively-Productivity Press (2008) PDF
Chris Harris, Rick Harris - Lean Connections - Making Information Flow Efficiently and Effectively-Productivity Press (2008) PDF
CONNECTIONS
Making Information Flow
Efficiently and Effectively
CHRIS HARRIS
RICK HARRIS
This book contains information obtained from authentic and highly regarded sources. Reasonable efforts have been made to publish reliable data and
information, but the author and publisher cannot assume responsibility for the validity of all materials or the consequences of their use. The authors and
publishers have attempted to trace the copyright holders of all material reproduced in this publication and apologize to copyright holders if permission
to publish in this form has not been obtained. If any copyright material has not been acknowledged please write and let us know so we may rectify in any
future reprint.
Except as permitted under U.S. Copyright Law, no part of this book may be reprinted, reproduced, transmitted, or utilized in any form by any electronic,
mechanical, or other means, now known or hereafter invented, including photocopying, microfilming, and recording, or in any information storage or
retrieval system, without written permission from the publishers.
For permission to photocopy or use material electronically from this work, please access www.copyright.com (http://www.copyright.com/) or contact
the Copyright Clearance Center, Inc. (CCC), 222 Rosewood Drive, Danvers, MA 01923, 978-750-8400. CCC is a not-for-profit organization that provides
licenses and registration for a variety of users. For organizations that have been granted a photocopy license by the CCC, a separate system of payment
has been arranged.
Trademark Notice: Product or corporate names may be trademarks or registered trademarks, and are used only for identification and explanation with-
out intent to infringe.
TS157.H37 2008
658.5--dc22 2008012562
1 Getting Started................................................................................... 1
The Three Flows of Production......................................................................... 4
Information Flow............................................................................................. 4
Material Flow................................................................................................... 5
People Flow..................................................................................................... 5
Meet RNA Manufacturing................................................................................... 6
Basic Information Flow: The A3........................................................................11
The A3 Illustrated.......................................................................................... 12
Benefits of the A3......................................................................................... 18
Now You Can Begin..........................................................................................19
Key Points..........................................................................................................19
References............................................................................................. 139
Index......................................................................................................141
Chris Harris is one of the new breed of Lean thinkers and a coauthor of the
Shingo Prize Award-winning book Making Materials Flow, published by Jim
Womack and the Lean Enterprise Institute. He has also coauthored a book with
Rick Harris on Human Resources’ role in lean manufacturing entitled Developing
a Lean Workforce, published by Productivity Press. He began his Lean Manufac-
turing training as a team member on the assembly line at Toyota Motor Manu-
facturing Kentucky (TMMK). While at TMMK he was taught by the professionals
the proper use of takt time, standardized work, the utilization of Andon Boards
and the Andon system. Dr. Harris continued his lean training at Toyota Tsusho
America in Georgetown, Kentucky, and gained valuable hands-on experience in
returnable containers, Kanban card systems, supermarkets, milk runs, and lean
pricing. He realized the need to become knowledgeable in the implementation
of lean manufacturing in a unionized environment, receiving this training as a
front line supervisor at Delphi Alternator Division in Anderson, Indiana, a UAW
environment. While in this position he gained a keen understanding of what is
required to implement lean manufacturing in a unionized environment. From
this point Dr. Harris decided to take another avenue and went into corporate
purchasing at a tier-one automotive company. In this position he learned the
importance of Purchasing’s role in lean manufacturing, and its affect of “Global
Purchasing” on the enterprise value stream.
Dr. Harris earned a doctor of business administration degree from Anderson
University. He is vice president of operations for Harris Lean Systems (www.
harrisleansystems.com), and teaches workshops on various topics that assist com-
panies on their Lean journey. He has spoken at the Lean Summit in Poland and is
a regular featured speaker for Jim Womack and the Lean Enterprise Institute.
Rick Harris, president of Harris Lean Systems, has been helping companies to
become lean for the past 14 years. He has had great success helping large and
small companies, union and nonunion, to implement their own lean manufactur-
ing system. HLS, Inc. has been instrumental in assisting companies worldwide
with major financial improvements, (a plant in New York $42 million in 4 years,
a plant in Indiana $32 million in 3 years); he helps to educate executives, plant
ix
managers, and plant staff in the principles of lean manufacturing. Mr. Harris
helps with the actual implementation on the shop floor and the education of the
workforce. He has pioneered the reverse-flow process to achieve an increase in
efficiency of 25%. He has extensive experience in developing new manufacturing
layouts that facilitate one-piece flow, operator flexibility, operator engagement,
first time-through quality, optimum uptime, and reduced capital investment. Mr.
Harris has also coauthored the two Shingo Prize Award-winning books Creating
Continuous Flow and Making Materials Flow published by James Womack and
the Lean Enterprise Institute. He has also coauthored a third book: Developing a
Lean Workforce, published by Productivity Press. He is one of the featured speak-
ers at the Lean Enterprise Institute’s monthly lean conference. Mr. Harris has
been a speaker at the University of Michigan Lean Manufacturing Conference for
the past 7 years, the Lean Enterprise Institute Summit for the past 3 years, the
European Lean Enterprise Institute Summit, the Maynard Forum, the PERA Con-
ference, the Mississippi State Annual Lean Conference the past 2 years, European
AME Conference, the AME Conference in Chicago 2002, and the University of
Kentucky Lean Leadership Forum the past 3 years.
Mr. Harris received his lean training while serving as a manager in assem-
bly at the Toyota plant in Georgetown, Kentucky. During his tenure at TMMK,
he continued his lean learning at the Toyota Tsutsumi Assembly Plant in Toyota
City, Japan. He was a member of the startup team at TMMK, where he gained
extensive knowledge of the Toyota Production System. Prior to his Toyota expe-
rience, he spent 15 years with General Motors, where he began as a produc-
tion operator and progressed through the ranks to become a first line manager
(www.harrisleansystems.com).
xi
The exercises in these sections will get at the heart of what each chapter is
about. Each chapter is based on a certain part of overall information flow in a
production facility, and this question is in place so that when it is answered, the
information flow described in the chapter is clearly defined. Note that there are
lines on which to write under each question, so fill in these lines as you come
across each exercise.
This question is asked because you must understand the customer. Different
forms of information are required for different customers. For example, quality
information is needed by the Quality department, or maintenance information is
needed by the Maintenance department. This section in each chapter identifies
the customer of the information flow being discussed.
This is the final question asked at the beginning of each chapter. Its purpose
is to identify the person or group that holds and is responsible for the informa-
tion. For example, a production associate may be the one who knows when
there is a quality problem or a maintenance problem (such as when a machine
breaks down). The associate holds the responsibility for getting that information
to the customer, such as the Quality or Maintenance departments. Is there a sys-
tem for associates to be able to do that?
By answering these three questions at the beginning of each chapter, you begin
working with the type of information at hand. You know, by answering three
questions, what the information is, who needs it, and who has it. Your charge,
then, is to develop a way to make that information flow from those who have it to
those who need it in an efficient way that fits into your current production system.
Where to Begin
This workbook was written to give you a step-by-step method for implementing
a collection of information-flow tools and linking them together as part of your
overall lean production system. The book starts at the customer (as should any
lean process). It then follows the process back to Purchasing. It would probably
be a good idea to read the book from beginning to end to see how all the infor-
mation-flow tools connect together, and later return to the chapters that explain
the tools you are implementing. However, if you are currently implementing
information-flow tools, just jump in wherever you need to.
Whatever way you choose to go about using this book, we believe it would
be a good idea to complete the exercises in the text. They are set up to get you
thinking about your own processes and to put you on the path toward making
information flow in your facility. Our advice to anyone implementing lean manu-
facturing systems is to start now, keep going, go faster, and never stop learning
as you implement. Best wishes on your lean journey.
Getting Started
This chapter provides background information that will be helpful as you read
this book. It offers an overview of RNA and the three manufacturing flows in a
production facility. It also explains a problem-solving methodology that can be
used in a production facility to make information flow at all levels.
Information explains which products to make and when to make them. It can
also explain a quality problem—where it came from, the reason for the problem,
and the corrective action to make sure that the problem does not happen again.
Information can also be a maintenance problem that needs to be addressed—
how is the Maintenance department notified, how do we know when a repre-
sentative from that department will get there to fix the problem, and how do we
know when the problem is fixed? How does Purchasing know when to order
products? How does management know that processes are being followed? How
does management know if the implementation of lean initiatives is on schedule?
Granted, the above questions and statements are not all-encompassing, but
they can get you started thinking about the different forms of information in
your facility. In short, information can be described as “data needed by someone
to make a decision that is best for the facility.”
Now that you know there is information and that there are people who need it,
you can reasonably ask the next question: “Who has the information?” The infor-
mation can rest in many different places. However, sometimes the information
needed will have to be created; for example, a level production schedule. Because
many organizations do not have a level production schedule, the schedule must be
developed and made to flow to those who need the information.
For a facility to be at its best, information has to flow freely. It cannot be a
source of power or importance in an organization. Often times, we find that infor-
mation is held by a person and let out only on a need-to-know basis. Yet informa-
tion is often needed by more than just people who receive it. In order for a facility
to be at its best, information needs to flow quickly and efficiently to those who
need the information.
Information Flow
Information flow is a significant hurdle that many organizations face. Whether those
companies are implementing lean production or not, organizations have difficulty
making information flow effectively in their facilities. In many production facilities,
especially those that have been in place a long time, information is withheld in
order to give the holder importance, instead of being a way to help the organiza-
tion. Take, for example, a production supervisor. A production supervisor, whose
main job in a mass production facility is to schedule and chase parts, may view his
or her production schedule with a sense of importance. If someone wants to know
what to run next, that person has to talk to the supervisor. Others in the organiza-
tion may feel that if they are the only ones who have certain information, they are
important to the organization. Take, for example, process knowledge. Many organi-
zations control their process knowledge by passing it from generation to generation.
This means that the person who operates the process now will train the person
who will do the process next. This may sound good, but the problem is that they
are the only two people who know how to do the process. When they are gone on
vacation, for example, the facility does not run very well. The method for running
a production process should not be a secret; instead it should be knowledge that is
easy to acquire and improve.
Another information flow hurdle is in the form of metric information that manage-
ment receives. Many times, management does not get necessary information until
it is too late. Good information flow gives management the tools they need to ask
the right questions. For example, receiving only a quarterly report means that three
months go by without new information. Furthermore, the information received may
have little to do with lean implementation or day-to-day operations. Metric informa-
tion flow is important to management because it can provide them the tools they
need to make decisions for the facility. Metric information, as a rule, needs to mea-
sure what you need it to measure, be correct, be timely, and be easily accessible.
Information flow can be described in many ways, but the best way we
have found to assess how a facility’s information flows is to ask questions. For
example:
These are just a few questions that are used to see the current state of infor-
mation flow in a facility. This list of questions is certainly not all encompassing,
but it can get us started thinking about information flow.
Material Flow
Material flow concerns the movement of material from supplier to the facility,
materials moving through the facility, and then to the end customer. Material flow
is closely related to information flow and they can and are often moved with by
same method. Questions that can be asked about material flow are:
Once again, these questions are not all-encompassing, but they can get you
started on the right track.
People Flow
People flow is the third type of flow in production, and it deals with how a
facility effectively moves its people. By answering the following questions, you
can begin to assess the people flow in your facility.
As you can see, RNA has been fairly successful in its lean journey, but as
most successful lean implementations go, RNA sees much more opportunity to
improve. The company plans to focus its new efforts on developing good infor-
mation flow throughout the facility.
The first step RNA made in its implementation was to draw current- and
future-state value stream maps. This gave the company a plan to change. Value
stream maps also act as a good tool to show both information flow and mate-
rial flow and how they interact. However, a future-state value stream map shows
only what the information flow and material flow should look like, not actually
how it is done (see Figure 1.1 and Figure 1.2).
The next step RNA took in its implementation was to develop continuous flow
in its production processes. This gave it stability and consistency in the produc-
tion process. It also allowed it to create and improve good people flow in its
facility (see Figure 1.3).
Although RNA saw big benefits from this training in the involvement and support
for the change to lean, the company was still lacking good information flow on
the production floor.
As a result of its efforts to develop a lean workforce, RNA’s structure on the
production floor has also changed to a team concept based on practices of Toyota.
The production associates are members of a team. A team may consist of four to
eight production associates, depending on the difficulty of the process. There are
four to five teams in a group. The groups are divided by value stream, so there
is likely more than one group per value stream. The leader of the group is the
production supervisor, or is also often called the group leader (salary). There is
also a leader on each team called the team leader (hourly). This person is a pro-
duction associate, but with additional responsibilities. The person responsible for
the entire value stream is the value stream manager. The organizational chart in
Figure 1.4 shows how the production floor is organized.
RNA’s structure is not the only significant change the company has undergone.
Its plant layout has also changed dramatically. Figure 1.5 and Figure 1.6 outline
the differences.
A B Cell 11
Min.2 Min.1
Max 4 Max 3
STOP
STOP
Plant Manager
Lean
Coordinator
Value Stream Manager
Team Leader Team Leader Team Leader Team Leader Team Leader Team Leader
Team Member Team Member Team Member Team Member Team Member Team Member
Team Member Team Member Team Member Team Member Team Member Team Member
Team Member Team Member Team Member Team Member Team Member Team Member
Team Member Team Member Team Member Team Member Team Member Team Member
Entrance
and
office
Receiving area
and
Shipping
Dock
Operations
Office Area
Empty
area due Empty area
to floor due to floor
space space
gained gained in
in creating
creating continuous
continuous flow
flow activities
activities
One other very significant point that deserves mention is that the Produc-
tion Control and Logistics department (PC&L) controls production in the RNA
facility. The PC&L (also called Material Control, the Materials department, and
Production Control in other companies) has the responsibility of scheduling the
facility and procuring all the purchased parts in the facility. This is a major
departure from the way many production facilities have operated in the past,
but it is a necessity in a lean production organization. You may have noticed back
in Figures 1.1 and 1.2 that PC&L is at the top of the value stream map. That is
because in the RNA facility, PC&L is the nerve center or brain of the RNA
Production System (RPS).
There is no doubt that RNA has been successful, but like all good facilities
that are successfully implementing lean systems, the company wants more. RNA
chose information flow as the next big step in its implementation because the
company now sees it as necessary for continued success.
The first step that RNA took to make information flow was to introduce a base
of good information flow in a production facility—the A3 problem-solving format.
Operations
Office Area
The A3 Illustrated
On the next few pages, you will follow RNA from problem to solution using
the A3 format. The first block to be completed is the objective block. What is
expected by solving the problem? What exactly is RNA looking to accomplish?
The theme, objective, targets for RNA is to increase uptime to the expected
95% level while better utilizing manpower efficiency, better utilizing floor space,
and incorporating lean techniques at the marriage press machine. This has to be
done while staying in line with the five-year flow plan of the facility.
It is very important for everyone to keep the goal in mind, so the A3 includes
a theme, objective, targets box (see Figure 1.7). RNA managers found out through
their previous implementations that when people lose sight of the end goal, the
solutions sometimes fix the immediate problems but are not in line with the
long-term goals. RNA wanted to be sure that everyone involved with the solv-
ing of the problem realized what the goal was. As RNA has found time and
time again, information flow is the most difficult of the flows for a manufactur-
ing plant to manage effectively, and the A3 format of problem solving seeks to
address that inefficiency. The objective box, then, is in place to clearly define the
goals of solving the problem.
In the background box, the problem itself is explained. For example, the situa-
tion that RNA is dealing with is as follows: “The automated press that marries the
wheels to the wheel base accounts for an average of eight maintenance hours per
week (downtime), along with the cosmetic quality problem (the pressed wheel
appears to be bent).”
The background box (see Figure 1.8) is also where the problem is grasped and
the degree of the problem is evaluated. RNA evaluated its problem as follows:
The marriage machine is supposed to run at 95% uptime. The majority of the
preventive maintenance items are to be done weekly. PM compliance on this
marriage machine has been 100% for the past year, yet the uptime has continued
at the 65% level. Also, after further review of the big picture, this machine disrupts
our product flow from the standpoint of quality problems and downtime, as
well as the size, floor space, and batch production that this machine requires. It
requires two fulltime operators, one loading and one unloading, who appear to
be a maximum of 50% utilized.
The background box is important because it allows everyone to see the sever-
ity and importance of solving the problem. In this example, there are eight hours
of maintenance each week. If RNA internally charges $100 an hour for its main-
tenance time, these eight hours would equate to more than $800 in maintenance
time per week, which is roughly $3,200 per month and $38,400 per year. This
number does not include the other, more expensive, problems that are caused by
downtime. Those items are the cost of premium shipments, missed shipments,
hourly wages continuing to be paid during downtime, parts to fix the machine,
inventory to cover downtime issues, and so on. It is very expensive for a com-
pany to experience machine downtime. RNA may want to include the actual
dollar figures in this box.
The next box in the A3 problem-solving format is the cause analysis box. In
this box (see Figure 1.9), you discover the point of cause and the root cause of
the problem. In the RNA case, “The point of cause is that the motor running the
machines press had an electrical failure. The root cause of the many failures of
this marriage press is the design. The machines was designed in the early ’70s and
was not designed for quick changeovers. It was designed to run a large volume of
a single part number before being changed over. As we have continued our lean
implementations, we have found ways to quickly change over, but other problems
have arisen, including the downtime issues we are experiencing. In short, the
machine is very old, is very large, and was designed for batch production.”
marriage press machine requires, and appears to have very little downtime. This is
a manual press that will be very efficient and solve the root cause of the problem.
This manual press costs $1,500, so the cost will be absorbed by less than a month
of the current maintenance costs.”
The countermeasure box is critical to the success of using A3s, because it
creates an environment in which, when someone comes to management with
a problem, he or she has thought through the problem, including a potential
solution. Whether this solution is ultimately used is not necessarily the point; the
point is that the person completing the A3 is thinking in a problem-solving way.
Instead of just pointing out a problem, the associate has to say, “Here is the
problem, and here is my plan to solve the problem.”
The next box is the schedule box (see Figure 1.11). You know the problem, the
background of the problem, the severity, the point of cause, root cause, and the
solution, so the next logical step is the implementation plan. Now that you have all
of this information, you need to plan its implementation. “Our schedule is for Mr.
The final box on the A3 problem-solving format is the future actions box (see
Figure 1.12). What actions are you going to take in the future to see whether this
solution was a good one? Can it be further improved? Is there anything additional
that needs to be done? In RNA’s example, the future actions are as follows: “Ms.
Audrey will spend every morning’s startup for the first two weeks after imple-
mentation of the manual press. She will evaluate it on a daily basis. She will
also check the press at 1:30 every day for the first two weeks, along with two
unscheduled periodical checks. There is a 2:30 pm standup meeting at the press
scheduled every afternoon the first week of implementation. The second week,
there is a standing meeting at the press on Monday and Thursday at 2:30 pm.
On the second Friday after implementation, we will provide a report on the
progress, problems, successes, and countermeasures taken.”
RNA has found this box to be very beneficial. It shows that a change will
not be made without a follow-up plan. This is also another lesson that RNA
has learned throughout its lean implementation. A project implemented with-
out sufficient follow-up will likely develop many problems. It is very important
when implementing any initiative that there is a plan in place for follow-up. If
a project is worth doing, it is worth making sure that it is working and that the
issues are being addressed in a quick and efficient manner. Too many times,
RNA managers have seen good projects implemented, only to have them fail
due to a lack of follow-up.
Benefits of the A3
RNA has been able to address many of its concerns by using the A3 problem-
solving format. The A3s have provided everyone involved with the same infor-
mation, talking points, and format to view. They have become standard practice
at the RNA facility. Meetings now focus more on solutions and implementation
plans than on background information. And RNA is now creating problem solv-
ers throughout the facility. RNA has made it a point to quickly spread this format
throughout the entire facility and throughout all of its departments.
The company is now able to see the end goals of a project so that the imple-
mentation method and solution are in line with that goal. RNA has its people now
thinking in the problem-solving mindset, which promises to be very beneficial,
now as well as into the future. They also have schedules, both for implementation
Figure 1.13 A3 Template.
and for follow-up, that can be tracked. With A3, RNA has implemented a tool for
problem solving that is now part of its production system.
Key Points
NNThere are three types of production flow, and they overlap a great deal.
NNAn A3 should be one page, should be in a standard format, and should be
short and to the point.
NNBe sure the A3 focuses on the root cause of the problem.
NNAn A3 must clearly define its objectives.
NNAn A3 should contain schedules for implementation and follow up.
After the basics of the A3, RNA decided that the best place to begin implementing
a comprehensive system of the right information flow would be at the customer.
The majority of its lean implementation began at the customer, because the cus-
tomer defines value. The first step RNA took to implement a system of informa-
tion flow was to develop a way to effectively handle the various orders that it
received from its customers and determine the best way to get those orders (in
the form of production schedules) to the people who needed them.
1. Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of a level production
schedule.
21
The information needed comes from the end customer and takes the form of
an order, one likely generated and provided by the sales department. That order
is then taken by the Production Control department, where it is transferred in
some way to a schedule for the facility. Most facilities know that this needs to
happen, but can have difficulties putting the idea into effect. The key information
in this chapter is the customer order: how it is collected, changed into a schedule,
and then provided to those who need it.
The Grind area supervisor takes the schedule and sees that he or she is sup-
posed to make only 100 A’s on Monday. The area happens to be running very well
that day, and the supervisor does not want to change over because it will cause
inefficiency in the process. Even though the plan is to shutdown and change over,
the supervisor chooses not to because the system is running well and he or she
can see that 500 A’s are needed for the week. The supervisor decides to just run a
week’s worth of Product A on Monday, and thus consumes valuable material and
labor that could have been used to produce the right product.
The problem comes when the downstream process (Paint) is following the
schedule. It runs the scheduled 100 A’s, and then changes over to run 100 B’s
(as the schedule states), only to find out that the previous process (Grind) is not
making B’s. Now there is a real problem in the system. The downstream process
has to change back to A’s to run. At this point, the schedule is more of a “guide-
line” than a schedule, which means that Production Control has lost control. In
cases like this, Production Control will be treated more as “production expediters”
as it tries to keep the plant in parts, even though it does not know what is going
to be run next. This situation is a significant reason that the large inventory levels
stack up in the facility.
The second reason this is too much information is that it forces a facility
schedule for a week at time—or it causes many revised schedules throughout the
week. Some companies in the past would send out a so-called “firm” schedule
for the week. However, on Monday afternoon, they would have to send out a
revised “firm” schedule, also known as a hot sheet. This happened periodically
throughout the week and caused many unplanned changeovers and part short-
ages throughout the facility.
So who is the customer of the production schedule? Is it the direct supplier to
that schedule or the pacemaker process? The pacemaker process is the last point
in the value stream where there can be a schedule and where the product can
flow from that point forward. For example, the pacemaker process in the preced-
ing value stream was Final Assembly. Production Control must send Final Assem-
bly a schedule because Final Assembly is the direct supplier of that schedule.
Looking upstream from Final Assembly to the Paint area, Paint is the direct sup-
plier to Final Assembly. Paint does not need a schedule from Production Control.
Instead, Paint needs a pull signal from Final Assembly, as Final Assembly is the
direct customer of paint. (This concept of moving work-in-process information
is covered in detail in Chapter 3). Paint does not need to know the schedule for
Final Assembly, only what Final Assembly pulls from Paint’s market. The future-
state value stream map in Figure 2.2 illustrates this concept, showing that the
customer of the schedule is only the direct supplier of that schedule.
At this point, if you have been implementing lean manufacturing systems for
some time, the answer to the preceding question may seem obvious. The organi-
zation that is responsible for the information is Production Control. There are two
major reasons that Production Control has to control the schedule.
First, Production Control should be able to see the big picture. We have found
through the years that Production does its best to schedule, but that approach
never works, because Production cannot see the big picture. It is much too
tempting to do what is best for the individual manufacturing areas rather than for
the value stream as a whole.
As companies implement lean manufacturing systems, they begin to ask,
“Why are my production supervisors scheduling the production floor?” The
answer is often “because that is the way it has always been done.” However, in a
lean system, it should be recognized that the production supervisor’s time would
be much better spent supervising and improving the process rather than sched-
uling and chasing parts. This leads to the second major reason that Production
Control should be in charge of this information.
We often ask classes that we teach, “Have you ever been scheduled to make
a part that you did not have the material to make?” In almost every instance,
a giggle comes from the audience because it is such a common practice in
mass-manufacturing facilities to schedule without sufficient thought as to whether
the material needed to make the product is actually on the production floor.
This approach (obviously) disrupts the flow because it can cause unplanned
changeovers, lead to making less product than was needed, or end with mak-
ing a product that was not scheduled at that point in time. Therefore, the second
reason that it is important for Production Control to manage this information is
because, in a lean environment, it should also manage the material and parts.
Production Control should never schedule a product to run that it does not have
the proper material to complete. It is the responsibility of the Production Control
organization to level, balance, and schedule the plant as well as to be sure that
each department has the components to complete the order.
production floor. The rest of this chapter takes us through the process RNA went
through to make the information flow from the customer through Production
Control to the production floor.
A9574 B8363 C8226 D9483 E5847 F9488 G2940 H1122 I3344 J9189
January 1200 800 600 400 200 200 0 200 0 0
The only certainty about forecasts is that they are never right and they always
change, so RNA decided that a better way to understand customer demand was
to look at past history. With the past history, RNA could calculate a takt time for
the value stream. Takt time represents the customer demand rate, or the rate the
customer is buying product, and is calculated by taking the total operating time
per shift and dividing it by customer demand. RNA looked at this history and
decided that 180 was an average daily customer demand for the month of
January. After managers knew the demand, they could calculate the takt time.
the value stream to produce, while still producing only what has been consumed
out of the finished goods market or what has been ordered by the customer. A
level schedule is an important piece of the lean manufacturing puzzle because it
takes pressure off the upstream processes that are used to reacting to what the
downstream processes produce. In a facility where there is a level schedule in
each value stream, product is pulled from upstream processes in a level man-
ner; this is easier to react to than the old batch method that made it very hard for
upstream processes to plan and react.
An example of a level schedule is as follows. The customer orders 2,500 pieces
per week, on average. But, the customer does not take the order in an even
manner. The customer takes the order as it is needed, such as the following:
Monday: 800
Tuesday: 0
Wednesday: 200
Thursday: 900
Friday: 600
If the Production area produced the same way in which the customer orders,
the facility would be inefficient. To run to a level schedule and be more efficient,
the facility would have to hold a buffer stock of 500 pieces and produce 500
pieces a day, operating as outlined in Table 2.2:
The level schedule is also important to the implementation of lean manu-
facturing principles because it is a good way to signal waste in the system. If a
facility puts a level schedule in place, supervisors will quickly see waste or inef-
ficiencies that keep them from producing to that schedule. After a facility can see
the waste and inefficiencies, it can take steps to remove that waste.
One final point is that a level schedule is a key to effectively reducing the
production lead time in a facility. A level schedule forces facilities to produce
quickly and in small batches, thus decreasing lead time, which in turn translates
into less inventory in the system. Thus, a level schedule enables facilities to tie up
less cash in production costs.
RNA broke its finished products into three categories. The first was the high-
est runners, which were run very often and were called runners. This group was
made up of A9574, B8363, C8226, and D9483. The second group included parts
that ran often but with lower volumes; this group was called repeaters. This group
included E5847 and F9488. The third group was called strangers, and included
parts that RNA was contractually obligated to run, but in very low volumes and
not often. This group was composed of parts G2940, H1122, I3344, and J9189.
RNA took these groups and had to make a decision about how often it
wanted to run each part. By breaking the parts into the three groups (runners,
repeaters, and strangers), RNA could make decisions concerning the groups.
For example, RNA decided that it wanted to run the runners twice per shift, the
repeaters once per shift, and the strangers once per week. RNA managers
thought that this would work best for them because they were running their
high-volume parts very often and their medium-volume parts every day. The
parts that were not run very often were run every week, which was a big
improvement over the past, when these parts were run very infrequently in
large lots. (It is important to note that RNA had minima changeover time in final
assembly. Its upstream processes were not so lucky, so the next chapter deals
with how to deal with changeover times in the schedule.)
At this point, RNA was charged with taking the hours in the day and putting
the level schedule in place, but first managers had to consider pitch. The pitch is
the finished goodspack quantity multiplied by the time it takes to produce each
product. RNA’s pitch in this manufacturing area was 25 minutes.
10 pieces in finished good pack × 150 seconds per piece = 1,500 seconds
= 25 minutes for a finished goods pack
Now that they knew the pitch, RNA managers understood how they should
provide the schedule to the production floor. They decided that because the
finished goods pack-out quantity was 10, they should schedule the production
floor in increments of 10. By understanding the pitch, they understood that the
floor could make only two finished pack-out quantities and four pieces of the
next pack-out in 1 hour. With this information (see Figure 2.4), RNA began to
develop a level and balanced schedule for this area.
RNA first had to look at the daily requirements. In the runners group, Prod-
uct A9574 was 60, B8363 was 40, C8226 was 30, and D9483 was 20. The repeat-
ers requirement was 10. RNA managers decided to focus on these two groups
first, because they represented the most significant volume. Now, they looked at
the times of the day and planned accordingly. (From this point forward, the prod-
uct numbers will be represented only by their first letter, as in Figure 2.4.)
Figure 2.4 shows how RNA decided to level the schedule for this area. This
plan accomplishes the managers’ goals of running runners (A,B,C,D) twice a
day and repeaters once per day. Notice in the time slot between 11:30 and 12:30
that there is a plan to run Product H, which is a stranger. RNA managers made a
placeholder for a part from this group. This schedule looks to be good through
the month of January, but if there were a need to run another stranger, RNA
would place that part into the slot that H currently holds.
Note: We concede that this is not an in-depth look into the philosophy of level
scheduling. The purpose of this book is not to show you how to develop a level
schedule, but how to make that schedule flow effectively to and through the pro-
duction floor. There are many other books about how to create a level schedule,
so we let those authors deal with that information. Our focus is on how to get the
schedule from Production Control to the production floor at the right time and in
the right manner to effectively make information flow in the facility.
A9574 B8363 C8226 D9483 E5847 F9488 G2940 H1122 I3344 J9189 Total
January 60 40 30 20 10 10 0 10 0 0 180
February 60 40 30 20 10 10 0 10 0 0 180
March 60 40 30 20 10 10 0 0 0 0 170
April 60 40 30 20 10 10 10 0 0 10 190
May 60 40 30 20 10 10 10 0 0 0 180
June 60 40 30 20 10 10 0 0 10 0 180
July 60 40 30 20 10 10 0 0 0 0 170
August 60 40 30 20 10 10 0 10 0 0 180
September 60 40 30 20 10 10 0 10 0 10 190
October 60 40 30 20 10 10 0 0 0 0 170
November 60 40 30 20 10 10 0 0 10 0 180
December 60 40 30 20 10 10 10 10 0 0 190
what it was scheduled to run. RNA management also knew that it had to order
in finished-good pack-out quantities—it did not make any sense to order in a
quantity that was not a finished-goods pack. RNA’s finished-goods pack-out was
10 pieces. Understanding all of this, RNA management had to determine how to
package and store the information in a production schedule.
RNA managers chose the use of a production kanban card to hold the infor-
mation. In this case, the kanban card is a signal to produce 10 pieces of a part
number (see Figure 2.6).
Although RNA managers had decided to use a kanban, continued to call it a
“schedule,” so as not to get it confused with the kanban cards on the production
floor. In addition, the kanban cards for strangers were a bright pink to signal that
these strangers were on their way. They needed to be a different color because
they were not run every day. RNA management wanted everyone to know that a
rare part was coming through the system so that they could plan for the product.
Now that RNA management had a way to hold the information, they had to
determine how to store the schedule, and they settled on the purchased parts
market. The reason for this choice was that the Production Control department at
RNA is responsible for both the schedule and the parts to make the schedule. All
the purchased parts in the RNA facility are located in the purchased part market.
Managers did not want to store the schedule on the production floor, because the
floor would again have too much information, as it did in the days of the paper
schedule. (Another important reason for keeping the schedule in the purchased
parts market will be discussed in the following section.)
Having decided where to store the information, RNA had to determine what
it would look like. This is a very important point that often is overlooked. Many
facilities know they need a level schedule, can develop a level schedule, but have
difficulty in effectively making the schedule (information) flow. Managers decided
that the best method was to have a board set up just like the level schedule. This
would be a white board with the times at which the production kanban cards
should be run on the left, and places for completed kanban card on the right
(see Figure 2.7).
This board shows what the manufacturing should be producing by the hour. It
is also a tool that can be effectively used in management. In the column on the
right, the kanban cards that are made are returned to the board. A quick look at
Schedule Card
A9574
Quantity:
10
8:00–9:00 7:00–8:00
9:15–10:00 8:00–9:00
10:00–11:00 9:15–10:00
11:30–12:30 10:00–11:00
12:30–1:30 11:30–12:30
1:30–2:30 12:30–1:30
2:30–3:30 1:30–2:30
7:00–8:00 2:30–3:30
(tomorrow)
the board at any time of day lets management know how production is running.
For example, the board in Figure 2.8 indicates that there is a problem in production.
It is 10:30 a.m., but the production kanban for 10:30 a.m. is still on the board:
Production is behind.
Note: Notice that the board in Figure 2.8 begins with the second hour of the day.
This is because what is running the first hour would be provided to the manufac-
turing area the last hour of the day before. This way, when everyone comes in for
the day’s startup, no one is waiting for the schedule, and the startup can begin
on time.
Now that Production Control has the schedule and has it stored in the right
place, managers are faced with physically getting the schedule to the floor.
8:00–9:00 7:00–8:00
9:15–10:00 8:00–9:00
10:00–11:00 9:15–10:00
11:30–12:30
10:00–11:00
12:30–1:30
11:30–12:30
1:30–2:30
12:30–1:30
2:30–3:30
1:30–2:30
7:00–8:00
(tomorrow) 2:30–3:30
One of the major reasons RNA managers believed they could effectively
implement a level schedule is that they have a strong Production Control depart-
ment. This was not always the case; in fact, before the switch to lean production,
RNA considered doing away with the department altogether. RNA now realizes
that the Production Control department is the nerve center of production and a
necessity to lean production.
RNA was able to grow its Production Control department into a solid group
through implementation of a timed material delivery route. A timed material
delivery route is a route that leaves its purchased parts market every hour with
product for the production floor. It is set up to replenish the material that has
been consumed by the production floor.
RNA uses a tugger,* driven by a production control associate, to deliver prod-
uct to multiple production areas in the facility. This associate goes to the produc-
tion floor, delivers product, picks up empty containers, and picks up pull signals
(replenishment kanban cards). The associate then goes to the purchased parts
market, gets the material that corresponds with the pull signals, and returns to
the production area the next hour with product. The cycle then starts again:
The associate delivers the product, picks up empty containers, and picks up
* A tugger is a motorized vehicle that can pull multiple carts filled with material for the production floor.
A9574 A9574
Quantity: Quantity:
10 10
Running Now
A9574
Quantity:
10
Key Points
NNToo much information may be as detrimental having too little information.
NNProduction Control schedules Production.
NNThe schedule revolves around takt time.
NNHaving a level schedule is not enough; you have to effectively move that
information to the production floor.
NNRelease the schedule to Production every hour, or on a cadence that is best
for the organization.
NNDevelop a timed system so that the schedule is taken to Production on a
regular basis.
Production Control
Making Information
Flow Upstream
After a facility creates a level schedule and gets it to the production floor, it has
to develop a method of getting the rest of the facility to plan—and react based
on that schedule. There should be only one schedule from Production Control
for each value stream, as discussed in Chapter 2 and illustrated in the future state
value stream map in Chapter 1. That schedule is placed at the pacemaker pro-
cess, which then begins pulling material from the upstream processes.
Too often, manufacturers are running the wrong products at the wrong time.
We have worked with facilities that have been able to make significant improve-
ment just by making what they need, when they need it—that is, the right product
at the right time. This is different from what many manufacturing firms have done in
the past, which is running what they think they need, when they think they need it.
This concept is not new to lean manufacturing. Virtually every value stream
map shows some form of either information flow or material flow. Good value
stream maps show both. However, we have found that taking the principles that
are shown on the value stream map, such as physically developing and effec-
tively moving information, are more difficult to put into operation than just draw-
ing on a map. This chapter explains a way to make the necessary information
flow to upstream process so that those processes know what product to produce
and when to produce it.
Information Overview
What information is available, who needs it, and who holds and is responsible for
it? This section answers those questions in the context of the development and
execution of internal work in process markets and production boards in upstream
process.
39
The answer to the first part of this question seems to be very simple, but that
is not necessarily the case. The answer cannot, for example, be “Production.”
That answer is too broad. Who really needs the information? The answer is “each
individual manufacturing area in the value stream.” That information needs to
be tailored for each individual area. For example, Process C needs to know what
Final Assy.
Grind Paint
Stamping
C/T 11.4 sec C/T 150 sec
C/T 100 sec
C/T 35 sec
Downtime 0%
Downtime 1% Downtime 25%
Downtime 2%
C/O 10 sec C/O 0 sec
C/O 10 min
C/O 120 sec
Process C needs to run and not anyone else. This information may be tailored by
runtime, changeover time, and lot size. The key is that the information system is
set up with the customer in mind. The customer is the next individual produc-
tion area in the value stream, not just Production as a whole. (See Figure 3.2.)
This information may not be held by anyone yet. This information may have
to be calculated. The responsibility for developing this information lies with the
Production Control department, but it must have a great deal of input from the
Production department. This information must be set up with an understanding
of how Production produces products. For example: If it is easier for Product C
to change over to Product A than it is to change to Product B, the area should
be scheduled to change from Product C to Product A to Product B. An effective
way to accomplish this is to have a work-in-process market. This point will be
illustrated as we follow RNA through its implementation of the internal information-
flow system.
These parts included washers, nuts, bolts, end caps, and so on. These parts were
still delivered on a replenishment basis, based on kanban cards, as before.
Final Assembly received 10 different-color kits that contain a frame, a body,
and two doors. The remaining items in the final assembly cell were purchased
components that included the engine, wheels, wheel shaft, washers, nut, bolt,
grommet, and endcap. Because the parts were set up this way, the purchased
components were replenished every hour as they were consumed, along the
route runner’s normal route.
The 10 different colored doors, frames, and bodies make the part number. For
example, Product A is a red truck, Product B is a blue truck, and Product C is a
white truck. When the route runner looks at the schedule and it says that final
assembly is supposed to make 20 As, it is simple for him to stop at Paint’s market
and get the parts to make the order, which would be 20 kits for Product A: 40
red doors (two doors per truck), 20 red frames, and 20 red bodies.
After the driver does this, he then goes to final assembly, places the sched-
ule on the schedule board, delivers the parts from Paint, and replenishes the
purchased components using the kanban cards that he picked up the previous
Purchased
Parts Market
Downtime 0% Downtime 0%
Figure 3.4 Diagram showing how information flows from Purchased Parts Market through Paint to
Final Assembly.
hour. The driver then picks up the schedule cards that have been made, the kan-
ban cards to be replenished, and any empties that need to be removed. Then the
route runner runs the route again. Figure 3.4 shows this process.
Making sure the necessary material is effectively, efficiently, and consistently
pulled from the Paint market is the key to making information flow upstream in
a lean process.
Product Has Been Pulled from the WIP Market … Now What?
To utilize a WIP market as a base for information flow, Paint has to know what
to put in the market as well as what has been pulled out of the market. To do
The following list provides the information and calculations RNA managers
used to determine whether it is possible to run the parts as they would like.
With this information, RNA began to calculate. It determined that if the company
was going to run the runners every day, it would have to change over four times,
and if it was going to run the repeaters or a stranger, it would need to changeover
A B C D E F G H I J
Daily Demand 60 40 30 20 10 10 0 10 0 0
Total
Products
Made
A B C D E F G H I J
Monday 60 40 30 20 20 10 180
Tuesday 60 40 30 20 20 10 180
Wednesday 60 40 30 20 20 10 180
Thursday 60 40 30 20 20 10 180
Friday 60 40 30 20 20 10 180
The Paint area decided that it was possible to run the runners part numbers
every day and the repeaters once every couple of days, and have the ability to
run a stranger as needed.
RNA can now begin to size its WIP market because its knows it can meet
Final Assembly’s demand and still run the runners every day, the repeaters every
other day, and a stranger as needed.
The beginning size of the WIP market is based on how often a product runs.
For example, all the runners will have to hold a minimum of one day’s worth of
material. The repeaters will have a minimum of two days of inventory, because
they are going to be run every other day. Remember that the Paint department
can change over only five times a day. It has to make 180 pieces every day to
meet customer demand. Therefore, it will run every part every day, except for
Products E and F (those parts are run every other day in a batch size of two
days). If the department tried to run Products E and F every day, it would mean
another changeover. That changeover would mean taking away about 10 min-
utes of production time, which in turn would mean that Paint could not meet
demand, as follows:
TO
Part A B C D E F G H I J
A – 15 8 15 15 15 15 15 15 15
B 15 – 15 5 15 15 15 15 15 15
C 15 10 – 15 15 15 15 15 15 15
D 15 12 12 – 15 15 12 12 12 12
FROM E 10 12 12 15 – 10 15 15 15 15
F 10 12 12 15 10 – 15 15 15 15
G 15 12 12 15 15 15 – 10 10 10
H 15 12 12 15 15 15 10 – 10 10
I 15 12 12 15 15 15 10 10 – 10
J 15 12 12 15 15 15 10 10 10 –
MINUTES
Changeover
1st 2nd 3rd 4th 5th
A C B D H E or F Total changeover time (minutes)
8 10 5 12 15 50
10 Average
This card should never leave the Paint area, and should be in one of only three
places: (1) on the product in the WIP market, (2) in the route runner’s hand, or
(3) on the production pull board.
After the card is pulled, the route runner takes it to the production pull board
and places it in the correct column. At this point, the route runner’s responsibility
is completed in the Paint area.
The production pull board must be very visual, with trigger points in each
column. For example, Product A’s trigger point is when there has been 1 day’s
worth (6 kanban cards) used by final assembly (pulled out of the market). This
is determined through the use of kanban cards. The number of kanban cards in
this information loop is calculated by doubling the EPEI and adding the safety
stock. The EPEI for Product A is one day (6 kanban cards), therefore there should
be 12 kanban cards (2 days) plus 3 kanban cards (1/2 day safety stock) for a total
of 15 kanban cards in the loop. By calculating the loop size this way, when a day
has been pulled out of the market, the producing department has a full day to
produce the product and put it back into the market.
Information Loop Calculation:
2 × EPEI (Every Part Every Interval) + Safety Stock
Part A’s Information Loop Calculation:
2 × 6 (1 day’s worth of kanban cards) + 3 (0.5 day’s worth of kanban cards)
= 12 kanban cards in Information Loop
Figure 3.9 illustrates this point. The Paint area is currently running Product
A. It is just about to finish its run, so the supervisor goes to the production pull
board to see what to run next. When Product C’s trigger point has been reached,
the supervisor knows to run Product C.
Figure 3.10
The cell makes its run of Product a. The supervisor goes to the board again.
This time, he or she looks at Product B. The trigger point has not been hit. There
could be multiple reasons for this—perhaps Final Assembly had a change in sched-
ule or some unplanned downtime. Anything that kept Final Assembly from pulling
parts from Paint’s market would cause Product B not to be at the trigger point.
The RNA supervisor goes to the next column, Product D (see Figure 3.10).
Product D has reached the trigger point, so Product D will be run.
When a product hits the trigger point, the person who gets the cards (nor-
mally the supervisor) gets all the cards up to the trigger point and runs them.
She or he takes them to a simple running-now board in the area (see
Figure 3.11). After all the cards on the
running-now board are complete, the Now Running
supervisor goes to the production pull
board to get the next run.
It is important to note a couple of
points. The first is that the only cards
that are run are those that are pulled
by the supervisor. It is possible that the
board could accumulate more kanban 1 Red Kit
the process. For example, a process is supposed to run only 30 A’s, 30 B’s, and 30
C’s. But, the process runs 40 A’s. Now they are 10 behind on B’s. Now they have
to run 40 B’s. Now they are behind 20 on C’s. Now they run 50 C’s, but they are
now behind on A’s. The safety stock and run plan for an area needs to be fol-
lowed because, otherwise, you get large lot sizes, overtime, overproduction—in
general, the “old way” of manufacturing.
The second point when discussing the production pull board is that there is no
need to panic if a part is not triggered—it all equals out in the end. If you pass
one part without running it, you also pass the time it takes to change over and run
the part. Yes, the changeover sequence may not be optimal, but in the majority of
cases, it will all equal out when you return to the part that was not triggered. It is
important that the production pull board is followed in order, with no backtracking
allowed. To understand backtracking, consider the following example: Product B
was not triggered, and the supervisor ran Product D. Now the supervisor goes back
to the board and sees that Product B and Product H are now triggered. Product H
is the next to run because it follows the planned sequence. A process cannot back-
track and run Product B, or the whole production board will be jeopardized. There
is no need to panic. If the market and board are set up properly, then there will be
no problem, and Product B can be run when it has its turn on the production pull
board.
Lean Connections
There is certainly a lot of information in this chapter. Much of that information is on
the micro level, describing how to set up a WIP market and find the most effective
way to run the area. All this information is important and vital to good informa-
tion flow. However, at this point we would like to go back to the macro level (big
picture) and discuss the process of making information flow at the facility level to
show how the WIP market fits into the whole information-flow system.
The first step is with the route runner in the purchased parts market. The
route runner picks up the next hour’s schedule for Final Assembly. There are other
tasks that the route runner does while in the market, mainly replenishing parts that
have been consumed on the production floor and making them ready to deliver.
The second step is for the route runner to stop at the Paint process and
retrieve the necessary parts to make the order just picked up in the purchased
parts market. The route runner removes the product from the WIP market. He
then removes each kanban card from each kit. He takes the kanban cards and
places them in position on the production pull board.
The third step is that the tugger goes to Final Assembly and delivers the pro-
duction schedule and all the parts that are necessary for the order. He or she also
picks up the information on what has been made the previous hour.
The final step for the tugger is to transport the information of what product
was made to the schedule board in the market. This lets Production Control know
that a product has been made. The route runner then begins the route again.
5/3/08 10:01:03 AM
Making Information Flow Upstream n 55
The whole picture looks like Figure 3.12, where you can see how the informa-
tion flows.
Key Points
NNThe size of WIP market must be correct.
NNKanban cards need to represent (and be attached to) each container or kit.
NNA production pull board acts as a changeover wheel and schedule board,
telling upstream production processes what product to make and when to
make them.
NNA route runner is the person who creates information flow by pulling
product out of the WIP market and placing the kanban cards on the
production pull board.
Purchasing and
Information Flow
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of Purchasing and its
relationship with the production floor.
57
Depending upon how you have developed your lean systems, the person
or people who hold information on whether a purchased component has been
consumed may vary. In facilities that have effectively developed a timed mate-
rial delivery route composed of a PFEP (plan for every part), purchased parts
market, pull signals, and a tugger route, the route runner holds this information.
The reason the route runner holds the information is because he or she is in the
purchased parts market taking parts to the production floor.
The holders of information on a part change can be many individuals. Of
course, if it is a supplier change, Purchasing holds the information, but what
about an engineering change? How about a change made to improve quality? Or
a change made to meet a customer’s needs? Understanding that there are different
organizations that change a part is important when setting up a system that helps
this information flow.
Because there are two different groups that hold two different kinds of infor-
mation, it is reasonable to assume that there are two different parties responsible
for the information. For the information from Production to Purchasing, the asso-
ciate who is pulling parts from the purchased parts market is responsible for that
information. A system needs to be set up so that this can happen with minimal
effort. The second responsible party has to be someone who makes sure all infor-
mation on all the purchased components is correct in the system and that when
there is a change, this change is communicated throughout the organization.
purchased parts for the facility were kept in the purchased parts market. Each
part had a designated space, meaning the part number that was in a space one
day would be there the next day, the next week, and so on.
This is an important point to make because one of the main reasons RNA
developed a purchased parts market was to control the inventory. RNA has
learned that it cannot control inventory in a computer system. Instead, RNA can
only truly control its inventory when it physically controls the inventory. RNA
managers used to think they could control their inventory in a computer system,
but they realized that when they really needed to know how many parts they
had, they had to go to the production floor to count them—so they opted for a
manual system of inventory control. Take, for example, the plant layout in
Figure 4.1, which was drawn before RNA implemented its timed delivery route.
Purchased components were taken directly from Receiving to the production
floor. RNA managers learned that its system may tell them that the parts they are
looking for are in the facility, but it does not tell them exactly where they are in
the facility. This lack of control often lead to RNA’s expediting parts that were
already in the facility. RNA managers came to the conclusion that they could
not control inventory this way and that they needed to implement a purchased
parts market so that they could control inventory. As soon as they completed the
implementation of a purchased parts market, they saw a significant change on
the production floor (see Figure 4.2).
Entrance
Receiving and
and office
Shipping area
Dock
Operations
Office Area
Entrance
and
Receiving office
and area
Shipping
Dock
Operations
Office Area
Supermarket
C
B
A
1 2 3 4
Part number:
Address:
Min:
Max:
The route runner in the RNA facility had become an integral part of the effi-
ciency of the system. In Chapter 2 of this book, the route runner was assigned to
take the schedule and purchased components out to the production area every
hour. In Chapter 3, the route runner was charged with moving work in pro-
cess parts and placing production kanbans on the production board so that the
upstream process knew what they needed to make. Figure 4.4 shows the process
of tying all of this together.
The first step that the route runner takes is to record on the schedule board
what had been made the previous hour. The second step is to pick up the sched-
ule that is to be taken to Production the next hour. The third step that the route
runner performs is to collect all the purchased components there are to pull cards
for. He or she loads the cart with these parts. The fourth step is the actual route,
during which the driver stops at the various areas of the facility and drops off
purchased components, picks up pull signals, and picks up empty containers.
The route runner also takes any WIP parts from the WIP market that need to be
moved, places the kanban card on the production board, and moves the parts to
the next downstream process. The last stop that the route runner makes is at the
pacemaker process, where purchased components and WIP components are deliv-
ered, the schedule is placed, and the schedule that has been made is picked up.
As you can see, the route runner is critical to making information flow
through the production floor. RNA managers wanted to make sure this process
Final Assy.
C/T 150 sec
Downtime 0%
C/O 0 sec
Paint
Downtime 0%
C/O 10 min
was not interrupted, but they also thought the route runner was the best person
to let Purchasing know what had been consumed.
Supermarket
C
B
A
1 2 3 4
Kanban
Holders
This process was very simple for the route runner. There were various card hold-
ers throughout the market. All the route runner was asked to do was to pull the
card and place it in the card holder when he or she opened a box in the purchased
parts market. This was the extent of the route runner’s information flow to purchas-
ing. (See Figure 4.5.)
RNA wanted to make it simple and efficient for the route runner because this
position was so important to the facility. Every shift, someone from the Purchas-
ing department would walk through the purchased parts market and collect the
pull signals, and would then go back to his or her office and order the parts that
needed to be ordered.
This may seem very simple, but that was the point. All the route runner
needed to do was to let Purchasing know what they needed to order, and the
managers accomplished this task through this simple system.
A common question is: “What is the reorder point?”—that is, the point at
which a part should be reordered from the supplier. The answer from a Pro-
duction point of view is that there is no reorder point. This system is based on
replenishment, so when a box is consumed out of the market, it is reordered.
However, many organizations that are implementing lean production find them-
selves in less-than-perfect relationships with their suppliers and have to order
certain quantities on certain days or at certain times.
All that is required, in terms of communication from Production to Purchasing
is that the production floor needs to notify Purchasing that a purchased compo-
nent has been used. This is done easily and efficiently by pulling the kanban card
off the box and placing it in the card holder. It is then Purchasing’s responsibility
to order the part, as its agreements indicate.
Storage Location
Order Frequency
Shipment Size
Supplier
Supplier City
Supplier State
Container Type
Box Weight
1 Part Weight
Total Package
Weight
Length
Width
Height
Usage per
Assembly
Hourly Usage
Standard Pack
Quantity
Packs Used per
Hour
Carrier
Transit Time
# of Pulls in Loop
Supplier
Performance
Material Control Operations Approval:
Material Control Approval:
Industrial Engineering Approval:
Operations Industrial PFEP Manager Approval:
Engineering
the change. By making the person walk to each person on the triangle and get
approval, information had to flow.
After each member of the triangle signed off, the document could then be
taken to the PFEP manager, who would then enter the new information into the
PFEP. In this way, the information on a part change was made to flow from the
person making the change (in this case, Purchasing) to the production floor.
Production Control
Production Industrial
Engineering
Key Points
NNRealize that there is a two-way direction for information flow.
NNDevelop additions to existing systems to accomplish information-flow goals.
NNMake sure that all information flows as part of a system.
NNWork with Purchasing to develop systems from which both Production and
Purchasing can benefit.
Making Quality
Information Flow
Successful lean implementers are often asked a popular question whose answer
may surprise you. The question is, “Now that you have had a great deal of suc-
cess implementing lean manufacturing principles, if you had to do it all again,
what would you do differently?”
The top two answers to this question are almost always the same. First is work-
place organization. People who have had success implementing lean production
systems say that they would really focus on workplace organization from day one.
This is interesting, because much of the literature states that workplace organiza-
tion is a great place to begin a lean initiative. The reason many people do not give
this area a lot of attention at the beginning of the implementation, however, is that
workplace organization does not show up on the books as a line item. There is no
line item that says, “Workplace organization … $5,000 saved.” Most people know
that organizing the workplace is the right thing to do; they just choose to focus
their efforts on other implementation efforts that show up on the books.
The second process that successful lean implementers would do differently
is that they would focus on quality from day one. At the beginning of an imple-
mentation, many people do not concentrate on quality. It is part of the old cul-
ture where statements like, “Just rework the product” or “just keep producing and
sort out the bad ones” were commonplace. In a lean environment, quality is a
big issue because any time there is a quality issue, it disrupts the manufacturing
flow. Any time the manufacturing flow is disrupted, it costs the company money
in the form of downtime, unplanned changeover, missed shipments, and so on.
Good quality is vital to a healthy operation. Understanding that quality is very
important to any facility, especially those firms implementing lean production,
we have to begin to investigate quality.
The purpose of this chapter is not to discuss quality problems or their cause.
The purpose of this chapter is to develop a methodology for making quality
information flow in a manufacturing facility. Everyone’s quality problems are
69
different, but the way to make quality information flow can be quite similar in
lean manufacturing facilities. This chapter outlines that methodology.
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of quality—specifically,
how a system is developed to get real-time quality information to those who can
help quickly correct a quality problem.
There are two different types of quality information flow. The first is the classi-
cal kind of information flow in which you have reports that show the quality level.
This type of information flow can take the form of a percentage in PPM (pieces
per million), FTQ (first time quality), or as other quality information. The one thing
that all these forms of quality information flow have in common is that they are all
historical data. This information tells you only what has happened in the past.
The second type of information flow concerning quality is different. This type
of information on quality is very seldom used outside of firms that are imple-
menting lean production systems. The second type of quality information is
immediate and in real time. This concept is defined throughout this chapter, but
the methods originate from the andon system made popular by Toyota.
Many firms have come to rely on historical data as a way to improve quality.
This chapter does not aim to contradict that process, but to add to it. Historical
quality data is very important to the facility. As you will see throughout the
remainder of this book, historical quality data plays a fairly significant part in the
information flow of a facility.
The information we discuss in this chapter is information on the real-time
quality, or the quality of a process right now. Is the operator having a quality
problem? Is the process receiving bad parts from a previous supplier? Is the
process receiving bad product from a supplier? Is the operator having problems
with the assembly process that could cause poor quality? The answer to these
questions is what we are looking for in this chapter.
The person with real-time quality information in a facility is the person closest
to the quality problem. That person is most often the production associate. The
production associate normally sees the quality problem first and knows why there
is a problem. Sometimes, the production associate can see that there is going to
be a quality problem before there actually is one.
At this point, the question that is often asked during our discussions with
those implementing lean production is, “If they can see the quality problem first
or know that a quality problem is coming, why do they not tell us?” This ques-
tion gets to the root cause of the problem. The answer is another question: “Have
you given production associates a method to notify you immediately when they
have a problem?” The answer to that question in often “no.” How do you develop
a system of information flow so that production associates can let management
know immediately when there is a problem?
Andon
Rope
L10 fixed-Stop
Position
fixed-stop position is the position where the new car starts. The reason that the
line stops only at the LIO fixed-stop position is that if it stopped in the middle
of the process, it would cause a quality problem itself, because associates would
have to determine where they just stopped and start up again. Therefore, when
the rope is pulled, the line does not stop right away; it stops when the product
gets to the end of the station. So, when the rope is pulled, everyone continues to
work until the line stops. When the line stops, everyone, with the exception of
the person who pulled the rope, should be completely finished with their pro-
cesses. When the line resumes, everyone begins work at the beginning of their
processes at the same time. Figure 5.2 illustrates what the system looks like when
the rope is pulled and when the line stops.
Toyota gives its production employees the opportunity to pull the andon and
stop the line. However, this is only the beginning of the system. When the rope
is pulled, a light comes on and a sound comes from the area where the rope was
pulled. It is very important to understand that there is a visual and an audible
indicator when a rope is pulled. The sound is to alert that a rope has been
pulled, and the light indicates which rope has been pulled. Take a look at a pos-
sible andon board in Figure 5.3.
Each letter is a process. When the sound goes off, a person can look at this
board and know which process is having the problem. This is real-time informa-
tion. At the moment there is a problem, there is also a notification. The next step
Pull Signal
Pickup A B C
Quality
Stop
Maintenance
D E
Call
is to determine which person needs to see that the rope has been pulled. That
person is a team leader or production supervisor, depending on the structure
in your facility. It is this person’s responsibility to go immediately to the process
after seeing that the rope has been pulled. The supervisor or team leader then
addresses the problem immediately.
The line does not restart until the rope is pulled again. However, the rope can
be pulled the second time only by the person who responded to the first pull. This
means that there has to be a response to an andon pull before the line can resume.
How Does RNA Make This Concept Work for Its Production System?
RNA managers knew that they needed some way to gather real-time quality infor-
mation. They decided to develop a system modeled after the andon system at Toy-
ota. The first step in their implementation was to give the production associates a
way to let them know when there was a problem. They determined that the rope
method used at Toyota would not work well in their cellular layout. The rope
method is designed more for a traditional assembly line than a manufacturing area
without an assembly line. RNA managers knew that they wanted each machine in
the manufacturing cell to have the capability of notifying management of a qual-
ity problem, so they put a simple light switch on every machine—see Figure 5.4.
(RNA began this implementation utilizing a pilot cell. The company had learned
from implementation lessons in the past and knew that when it was implementing
a new system, it needed to start small to work out the bugs.)
The light switch was bright orange
so that it was easy to see. Each one Andon
was also placed within easy reach of Switch
Pull Signal
Pickup A B C
Quality
Stop
Maintenance
D E
Call
a different chime for each manufacturing area. This way, the supervisor could know
by the sound of the chime which andon board to look at. After the supervisor
looked at the andon board, she or he knew exactly which machine to go to (see
Figure 5.5).
Implementing Andon
RNA management realized it had a
problem at this point in the imple- Machine
mentation. The company had not D
clearly identified each machine in the
manufacturing area. This must be done Andon
Switch
immediately, because the supervisor
had to be able to know which machine
was which when he or she got to the
manufacturing area. (See Figure 5.6).
Now that they had all the hard- Figure 5.6 Visual control of machine.
ware set up, RNA had put a system in
place to make this work. The system it chose to put in place was fairly simple.
When the andon switch was flipped, the team leader of the area had to be at
the machine immediately. It was then necessary to make a determination as to
whether the team leader could remedy the problem or if he or she had to get
support from another area such as Maintenance (discussed in Chapter 6). This
was very simple, and that was what RNA was looking for. Management wanted
production team leaders to be responsible for making the decisions after the
andon was on.
RNA came up with the idea of quality control alarm limits. This was a system,
like the andon system, that could shut down the production area. When the alarm
limit was hit, production had to shut down until the problem was remedied.
For example, the paint area at RNA had a problem from time to time with
runs in the paint. There is a quick fix for this problem, but it sometimes took a
lot of time to figure out that there was a problem. This proved to be very costly
for RNA because a great deal of labor and material had already been invested in
the part after it came out of the paint department.
RNA set a quality control limit on this part at five. This meant that within a
given amount of time (for RNA it was four hours), if the paint department sent five
bad parts to Final Assembly, Final Assembly would shut down until the problem
was fixed at Paint. As you can imagine, this situation not only caused a great deal
of panic in the facility because Final Assembly was not running, but also put
pressure on the paint department to get the problem corrected. (See Figure 5.7.)
Alarm limits are set based upon risk. For example, a part that has a lot of
material and labor already invested in it is much more expensive to the organi-
zation than a part that has very little material and labor. Therefore, the greatest
risk lies with the part that has a lot of labor and material. The alarm limit for this
type of part is normally much smaller, meaning that the system will accept fewer
defective parts before shutting down production, versus a part that is low risk. A
low-risk part may have a quality alarm limit with many pieces, or may not have
an alarm limit at all.
This thought process is different from in the past, when the final assembly
supervisor would have continued to run whatever parts he could get his hands on.
This can cost the company a lot of money in scrap, because (for example) the paint
department just continued to produce product even though a significant percentage
of those parts was bad. Paint just continued to produce because Final Assembly was
using the good parts, and Paint did not want to stop production to fix the quality
problem. But with this new system, Paint has no choice but to fix the problem.
The information that is flowing in this portion of the system is back upstream
to Paint and to management, letting them know they have a serious quality prob-
lem that needs immediate attention.
Alarm
Limit is 5.
Purchased Parts
As RNA went through this implementation process, it began to ask whether it
needed quality alarm limits for purchased parts. RNA was attempting to develop
partnerships with its suppliers. It was starting to make information flow between
Purchasing and Production Control, but were just not there yet.
RNA has no doubt that when it is able to develop partnerships with all its key
suppliers, there will be minimal need to have alarm limits within its system. For
now, however, it is necessary to deal with quality problems from their suppliers.
To do this, the company is not going to have alarm limits, but will have a
zero tolerance policy. If it ever receives a defect from a supplier, RNA will insist
that the suppliers come into the facility and inspect 100% of the product for two
weeks. This may sound extreme, but why should RNA have to inspect parts that
they have purchased from a supplier? The answer is that they should not. RNA
must have good parts from suppliers and until partnerships are developed, steps
must be taken to be sure that the parts from its suppliers are good.
Any quality problem from either internal or external processes disrupts the flow
of manufacturing, and any time the flow in manufacturing is disrupted, it costs the
company money.
Key Points
NNDevelop a way for the production associates to immediately notify manage-
ment when there is a problem.
NNProperly train the production associates on the proper use of the andon
system.
NNProperly train the team leaders and supervisors on the correct way to
respond to andons.
NNProvide a very visual and audible way to see andons (andon board)
NNDevelop alarm limits for high-risk parts.
NNMake sure that you get good quality parts from your supplier.
Making Uptime
Information Flow
After RNA developed a level schedule based on takt time, along with tools to
immediately recognize and fix quality problems, management realized that
something else was missing: information on uptime. RNA had certainly improved
its information flow throughout the facility, but the maintenance organization had
been left out of the loop to this point.
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of the maintenance
department. The sooner Maintenance knows that it needs to fix a problem, the
sooner the technicians can get there to take care of it.
79
Two groups need information about uptime. The first is management. Manage-
ment needs to be able to see uptime information at the value stream level to
evaluate the health of the entire value stream. However, having that information
does not directly help improve the uptime of the facility.
There are many different resources on how facilities increase their uptime,
but the missing link seems often to be the immediate attention needed because
of a maintenance problem. The second group, the maintenance department does
not need historical information on uptime as much as it needs to know the
exact time that the machine went down so it can get the machine back up and
running. A facility implementing a lean production system needs to develop a
system so that Maintenance knows there is a problem and can get the problem
fixed quickly. When a facility is running to takt time, every second of downtime
counts and every minute of downtime costs money.
value-added production associate to have to leave the work area for non-value-
adding activities. Understanding these principles, RNA had to develop a way for
each value-added associate to quickly and directly notify the maintenance organi-
zation without having to leave the area to go look for a maintenance technician.
Maintenance should show up at the area ready to fix the problem. This
includes bringing tools that are commonly used to repair the machine. Before
the implementation of this notification system, it would not have been reasonable
to ask. Now, knowing which machine is down, maintenance technicians can be
prepared when they arrive in the area.
of the ideas that was implemented at RNA was the concept of standard trouble
shooting matrix, a laminated piece of paper on every machine in the RNA facil-
ity. It contains the five most common reasons a machine breaks down and the
countermeasures that are needed to get the machine back up and running. The
trouble-shooting matrix was a list of items to check. So, if a maintenance opera-
tor came to a machine that was down, he or she had a place to start. This list
was developed by past information and performance of the machine. This
also helped to deal with the problems of specialized maintenance technicians,
because now someone who had never worked with a machine at least had a
starting point.
This was not new information at RNA. This information was held in vari-
ous computers and with the individual maintenance technicians throughout the
facility. RNA just needed to take this information and make it flow by putting
it on a visual and using easy-to-understand documentation, as demonstrated in
Figure 6.1.
The next step that the RNA maintenance organization took to make informa-
tion flow at the machine was to add color to the gauges on the machines. In
the philosophy of continuous improvement, RNA saw some immediate improve-
ments that could be done to improve uptime in the area. The first was to begin
to implement visual controls in the area. The most significant quick improvement
was color coordinating all the gauges in the area. Two colors, red and green,
were used. Of course, if the gauge was in the green, everything was okay, and if
the gauge was in the red, action needed to be taken. (See Figure 6.2.)
This was not enough, however. RNA managers asked their production asso-
ciates to check all their gauges at the beginning of the shift startup and to be
sure they were in the acceptable area. They also insisted that, once per day, a
maintenance operator walk through the areas and check the gauges to be sure
that everything was acceptable. If not, action needed to be taken immediately to
make sure that there was not a future problem.
By utilizing the radio communication system, RNA has put an information
flow system in place so that the maintenance technicians can be routed to where
they need to be quickly. It has also taken some steps to make the information
flow at the machine. It has done this through the trouble-shooting matrix and
color-coded gauges.
Trouble-Shooting Matrix
Crimp Machine
Check Fix
1. Check valve on bottom left of machine. Remove obstruction from valve.
2. Check electrical connection. Plug in machine.
3. Make sure water flow is unobstructed. Remove obstruction.
4. Light curtain line up. Correctly line up light curtains.
5. Check lubricant in back of machine. Lubricate per instruction on machine.
0 25 50 75 100
Key Points
NNRecognize the difference between historical uptime data and actionable
uptime information.
NNWhen a machine breaks down, get the information from production associ-
ate to maintenance quickly and efficiently.
NNDevelop a method of communication so that the maintenance organization can
respond in less than two minutes.
NNMake information flow at the machine level so that a maintenance techni-
cian can check for the most common problems first.
After determining the most effective way to move information to and on the
production floor, RNA continued to look for ways to improve and connect its
information flow. Managers turned their focus to the individual processes on the
production floor. The management at RNA had to determine what information
each production associate needed and how to get that information to them.
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of standardized work,
a key to an effective, efficient production environment that consistently provides
excellent quality.
87
RNA determined that the information at the process level was standardized
work. For employees to correctly perform work, they need to be provided with
correct standards to do the work. Standardized work is important to the orga-
nization because it is one of the pillars of a lean production system. By doing
the process the same way every time, the method used can reasonably be used
to improve quality. Quality problems often occur from some type of variability
in the process, such as using a method of assembly different from the one that
is normally used. By being able to count on the production associate to do the
work the same way every time, quality will almost certainly be improved.
A second point to be made in the discussion of standardized work is that
efficiency can be sustained by doing the process the same way every time. If
the standard work is set up to be completed every 55 seconds, it is reasonable
to expect that if the standardized work is done correctly that it should be done
at very close to the 55 seconds. This gives stability to the process, which is a
necessity to continuous improvement. RNA has come to believe in this statement:
“There can be no improvements unless there are standards to improve on.”
Finally, the standardized work links to the production schedule because it
provides management with the time that it takes to do the process. With this
information in hand, production supervisors can properly staff the area. Chapter
8 covers this concept in more detail, but it is important to note here that develop-
ing standards at the process level provides the solid foundation for an efficient
production system.
RNA’s first assumption was that only the hourly operators required standard-
ized work. This assumption seemed to be a safe one, but after further investiga-
tion, the managers determined that others needed the information as well. RNA
came to the conclusion that after only a short period of time, production associ-
ates would be very good at standardized work because they were professionals
and they did the work every day. However, managers and engineers charged
with auditing the process (covered in detail in Chapter 9) for improvement
ideas would also need to see the standardized work. This meant that standard-
ized work was not only for the production associates, but was also important to
managers and engineers because standardized work is the basis for continuous
improvement.
The first concern when answering the previous question is whether standard-
ized work exists. In many organizations beginning their lean journeys, and even
those that have been on the journey for a while, this information does not exist.
It must be developed.
Standardized work is different from conventional work instructions. Standard-
ized work is much more detailed. Both operator and machine times are indicated
at each step in the process, with the steps being listed in the order that they are
to be performed. RNA has found through its implementation process that it is not
the job of the production associate to write his or her own standardized work.
Instead, industrial engineers (IEs, also called manufacturing engineers or produc-
tion engineers) have done a good job of writing the standardized work, as long
as they have a great deal of input from the production associates.
With this thought in mind, RNA determined that the industrial engineers in
the facility would be responsible for the development and dissemination of the
standardized work. Other facilities may not have industrial engineers per se,
but they likely have manufacturing engineers or other types of engineers who
are well equipped to handle the job of developing and writing the standardized
work.
Now that RNA has answered the three questions to get started, they can focus
on the details of developing standardized work—determining the one best method
for putting a product together, and then working on improving that method.
For example, suppose a production associate on first shift is doing the job
one way and the production associate on second shift is doing the job a different
way. Now there is variation in the process. For RNA, as with almost every other
manufacturing facility, variation in the process is a bad thing. It opens the door
for quality problems to occur.
However, just because a facility gets to the point that it has standardized work,
it doesn’t mean it should stop improving the processes. For example, if the pro-
duction associate on first shift is correctly performing standardized work and the
person on second shift has found a “better method,” that better method should
become the new standard. With these ideas in mind, RNA came to the conclusion
that it needed standardized work at every work station, along with a robust system
of auditing and communication to be sure that the standardized work was being
followed and that improvement opportunities were quickly identified and com-
municated to industrial engineers (IEs). It would then be an IE’s task to update the
standardized work.
All this sounded good, but RNA quickly came to the realization that it did not
have the standardized work at the process level and needed to develop it. RNA
charged the IEs to develop the standardized work. Although developing stan-
dardized work is different from the time studies and work instructions they had
created in the past, the management at RNA believed that the IEs could success-
fully transfer their skills into the area of developing standardized work.
After being charged with this important task, the IEs had to determine the
best way to develop standardized work. The production associates on the floor
Industrial Engineering
Production Lean
Coordinator
were prepared to see IEs on the production floor with clipboards and stop
watches because of the training that they received on continuous flow. The
training was part of RNA’s effort to develop a lean workforce. Yet, even though
production associates were prepared for IEs to spend time out to the floor, the
IEs coordinated this effort so that no one was surprised when the IEs came to
each area. Remember: standardized work needs to be developed for each prod-
uct family and IEs need to spend time observing and speaking with production
associates and supervisors.
As with many of their implementation initiatives, RNA created a triangle of
involvement for developing standardized work (see Figure 7.1). This triangle
consisted of IEs (because they were the ones who were responsible for develop-
ing the standard work), Production (which needed to be informed when the IEs
were coming to the floor to develop standardized work), and the lean coordinator
(who gets constant feedback and questions as he or she walks the production
floor, making it good idea for him or her to be informed about—even if not
directly involved in—every facet of the lean implementation).
Developing standardized work is a detailed and time-consuming task. RNA
learned this with its first attempt at developing standardized work. The wheel
assembly process targeted for standardized work (chosen because it was a
simple process with which to start) had seven separate parts that were assembled
so that the wheels would operate properly. It was a good idea to begin a new
implementation initiative on a small scale so that everyone could learn, but in
this case, even the small scale was pretty in depth. The IEs at RNA discovered
that developing standardized work was more detailed and difficult than they had
originally thought.
The first step they took was to get all the information that they could on each
of the five part numbers. This was an easy task because the information was
already gathered in the Plan for Every Part8. After they had the information on
8 The Plan For Every Part is a detailed database containing information on every part in the manufacturing facil-
ity. See Harris, R., et al. (2003).
the parts and had coordinated with Production so that associates knew the IE
was coming into the area, the IE made his or her way to the area.
The IE was positioned so that he or she could watch the hand motions of the
production associate doing wheel assembly. The IE watched as the operator took
the wheel and a washer, placed the washer on one side of the wheel, turned it
over, and placed a washer on the other side of the wheel. The next step was to
take the wheel shaft and place it through the wheel and washers. After that, an
end cap was placed on the shaft to keep the wheel from falling off. The next
step was to place a metal piece down the wheel shaft to hold the washer in place
and keep the wheel from moving too much from side to side. Finally, the tire
was placed on the wheel, and the process was complete. (See Figure 7.2.)
The IE gathered this information and wrote it down. But he or she had learned
from past implementation efforts that input from the production associate was
very valuable. The IE showed the information to the production associate and
asked whether the information was correct. The production associate said that all
the information was correct, but it was not complete. A key step was missing, one
that the production associate knew about, but the IE had not noticed.
This key step was the way that the end cap was put on. It had to be put on
at a 45-degree angle, and then rotated to 90 degrees to ensure that the cap was
firmly in place. The production associates learned this through trial and error.
A few months earlier, the cell was having quality problems, with the end cap
popping off. The problem was traced back to the production associate, who was
putting the end cap straight on. It looked fine, but did not operate properly. The
input from the production associate helped the IE developing the standardized
work understand the importance of communication with the production associ-
ate as well as the key steps in the process.
The IE now needed to time each step in the process. The same methodol-
ogy was used as that which was used to get the work motions at the process.
The IE timed each step in the process and, with input from the production
associate, felt good about the standard steps and times to complete the process.
Realizing that there can be no improvements without standards to improve on,
the IE set the standard for this process, hoping it could quickly be improved.
The IE now had to determine the best way to get the standard work on the
production floor.
60
Totals in seconds: Q H
5/3/08 10:02:18 AM
Information at the Process Level n 97
this way, the charts could be used to help manage the facility through audits and
continuous improvement (see Figure 7.5).
Station Station
A B
Station
D
Station Station
G F
Station Station
A B
Station
D
Station Station
G F
Station Station
A B
Station
D
Station Station
G F
there looking for ways to improve; however at RNA, as in most facilities, the
ideas for improvement originate with production associates most of the time.
Key Points
NNStandardized work at the process level is the basis for process improvement.
NNStandardized work charts should be standard throughout the facility.
NNPlacement of the standardized work charts is important.
NNCombining standardized work at the process level gives Production the
information it needs to make productive and timely manpower decisions.
NNManpower decisions are based on the demand from Production Control,
thus effectively linking Production Control with Production.
The majority of employees at RNA wanted to excel at their jobs and meet expec-
tations. However, in the past, it would have been possible for production associ-
ates to work for years without knowing whether they were meeting expectations.
RNA managers knew that for production associates to efficiently and consistently
meet expectations, they needed more than just standardized work—they needed
to know the expectations. RNA decided to design a way to be sure that the
expectations were correctly and easily presented to the production associates.
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of providing produc-
tion expectations to the production floor in an efficient manner.
101
There are two flows of information at the team level. The first piece of infor-
mation that is critical to developing a stable and efficient production system is the
expectations. Providing expectations is first, because if there are none, expecta-
tions will never be reached.
The second type of information flow deals with information going from the
production area to management. Many times, when people talk about infor-
mation flow, they see it as a one-way street, meaning that someone gives the
expectations to the production associates, and then the flow of information is
complete. If that is true, we are saying that we are not interested in any informa-
tion that the production associates have concerning the process. Facilities imple-
menting lean manufacturing normally come to the realization that the production
associates hold a great deal of information that can be helpful to the improve-
ment (as well as everyday running) of the process. The second flow of informa-
tion, therefore, is information on how the area is running. What problems did the
production associates encounter the last hour? What problems are the produc-
tion associates currently having? Were expectations met last hour? Why were the
expectations not met? How is the quality in the area? Is the area producing what
it should be producing?
The responsibility for setting expectations resides with the production control
department within a lean manufacturing organization. Taking into account that
the production control department must work closely with Production and the
IEs to understand the capabilities of the production floor, the expectations on the
production floor are based on the customer demand rate or takt time.
Expectations are set by the production control department in the form of a
production schedule. Therefore, the production supervisors make staffing deci-
sions based on the area standardized work charts to make the schedule.
The most popular way RNA has found to get the expectations out to the
production floor is through the utilization of a production status board (PSB).
RNA has found that to be the most efficient tool on the production floor to increase
and improve information flow. The PSB is a central place where expectations can
be provided to the production associates.
7:00–8:00
8:00–9:00
Actual Comments
9:15–10:00 output by production
10:00–11:00 associates
Planned
output
11:30–12:00
12:00–1:15
1:30–2:30
2:30–3:30
Total
and the team standardized work charts described in Chapter 7, the expectations
were placed on the PSB (see Figure 8.2).
Supervisor Data
A second area on the PSB provides a way to flow information in the opposite
direction—from production associate to supervisor. At first, the managers did not
understand the significance of flowing information from the production associate
to the supervisor, but after further investigation, they realized that the first people
to notice a problem on the production floor would be the production associates.
RNA had to develop a way for those production associates to easily and quickly
convey those problems to their supervisors so that they could be fixed. The PSB
7:00–8:00 60
8:00–9:00 60
9:15–10:00 45
10:00–11:00 60
11:30–12:00 30
12:00–1:15 75
1:30–2:30 60
2:30–3:30 60
Total 390
7:00–8:00 60 60
8:00–9:00 60 45 Crimp Machine Down
9:15–10:00 45 45
10:00–11:00 60 60
11:30–12:00 30 30
12:00–1:15 75 40 Crimp Machine Down
2:30–3:30 60 60
Total 450 370
was a good tool to make information flow from management to production asso-
ciates as well as to provide a method to make information flow from the produc-
tion associate to the supervisor. The comments section was added to the PSB
(see Figure 8.3) so that the production associates could provide information on
current or possible future problems.
By utilizing this tool, it is evident that the crimp machine is causing substan-
tial problems within the team. The problem, though now identified, still does not
have an owner who has the responsibility of addressing the problem. There must
be someone who periodically checks the PSB to see whether the production
associates have anything that they need taken care of. The board can become
obsolete if no one addresses the information given by the production associates.
The production associates will likely not continue to utilize the board if they do
not think their input is seen as valuable to the organization.
7:00–8:00 60 60 RM
8:00–9:00 60 45 Crimp Machine Down RM AD
9:15–10:00 45 45 RM
10:00–11:00 60 60 RM
11:30–12:00 30 30 RM AD
12:00–1:15 75 40 Crimp Machine Down RM
1:30–2:30 60 30 Crimp Machine Down RM AD
2:30–3:30 60 60 RM
Total 450 370 RM
However, in the past RNA production supervisors were busy and did not
always make it to the manufacturing cell every hour. RNA managers thought it was
so important that the supervisor visit the area every hour to check the progress
(which amounted to checking the PSB) that they made it mandatory for the super-
visor to initial the PSB every hour to indicate that he or she had visited it. They
also made it mandatory to have the supervisor’s manager check the PSB twice a
shift to ensure production was running, and that the supervisor was utilizing the
production status board. (See Figure 8.4.)
Safety Chart
Safety was the first chart because RNA had made big strides in safety at its facility.
RNA’s lost work day rate had gone from 3.4 to 0.44 since beginning the lean
journey. One injury is too many, so managers thought it necessary to put this
document first on the PSB. And it was not enough that they wanted to track
safety, they had to determine how to track safety.
Instead of tracking lost work days, which would have hidden the injuries that
did not lead to lost work time, any safety issue (injury or near-miss), no matter
how minor was charted on the board. Taking this matter one step further, an A3
form had to be completed on the injury. These forms were kept in a binder under
the history side of the PSB for one year.
Quality Chart
Quality was the second chart of the history side of the PSB. Management’s first
thought was to do PPM or parts per million. That sounded good, but did not
really give them the information they wanted. The management was looking for
something that was easier to evaluate with a quick look at the PSB. They chose
to use FTQ or first time quality.
Though this seems relatively straightforward, that is not necessarily the case.
RNA went on to define FTQ as a product that goes through the area from begin-
ning to end without a defect. This did not include reworked parts. So, if a part
went to another area to be reworked or was reworked in the area, that part
counted against the FTQ number.
Uptime Tracking
RNA defined uptime as simply, “the machines were available to run.” This means
that the machine is capable of running, but does not include lost time, material
shortages, returning late from break. All of that information will be collected on
the production side of PSB. This chart’s purpose is to identify the current history
of the uptime in the area. Figure 8.5 shows the history side of the PSB.
There was some disagreement as to how long the history sheets should be
covered and updated. Should the charts be updated daily, weekly, or monthly?
RNA decided that as they were just implementing the PSBs, they wanted to
make sure that they were being used so that they could see the benefits and
work out any problems that they found. Therefore, they decided to update each
chart daily and leave them up for one month. At the end of each month, the
information on the charts was copied into pages in the binder below the history
side of the PSB.
January
Safety
1 5 10 15 20 25 30
Quality
1 5 10 15 20 25 30
Compliance
to Kanban
1 5 10 15 20 25 30
Uptime
1 5 10 15 20 25 30
This binder also holds all the A3 forms completed to address the various prob-
lems that show up on the history side of the PSB. Each problem or abnormality
that shows on any chart on the history side of the PSB should have a completed
A3 form associated with it in the binder.
5/3/08 10:02:40 AM
Information at the Team Level n 113
reused and changed easily. The final production status board was configured like
Figure 8.7, with each of the three sides discussed in the preceding sections.
Key Points
NNIdentify expectations for all employees.
NNDevelop a system so the supervisor checks the PSB every hour.
NNThe PSB is the central tool for information flow at the team (area) level.
NNUse all three sides of the PSB to manage and improve the area.
NNHave a separate PSB for each area or team in the value stream.
Auditing
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of providing manage-
ment with information on how the implementation is going.
1. What Is the Information?
Exercise: What information do you have in your facility that tells you how things
are running? What information do you have in your facility that lets everyone
know that work standards are being followed?
115
A facility has to have information on whether work standards are being fol-
lowed. If a facility does not know whether the standards are being followed, what
good are the standards?
work standards are being followed, they can rest assured that their omission is
not causing variability in the production process that can lead to quality prob-
lems. Equally, if they know that work standards are not being followed, they
can take action to either change the standards or provide support in helping the
associates understand that work standards need to be followed.
This information also lets management know whether what they have
implemented is working. If something is not working the way it was intended,
management needs to make a change. This information will also lead to
improvement opportunities throughout the process.
Management, armed with this information, will be better equipped to effec-
tively manage the facility. It can make informed decisions based on real informa-
tion rather than what it thinks is happening with work standards.
Information about whether work standards are being followed does not cur-
rently exist in a facility that is not consistently conducting audits. The only way
to get that information is to go to the floor and get the information through
audits. The audits can then be posted for everyone to see on the PSB.
Developing an Audit
RNA knew that it needed to develop audits that would be successful. However,
before developing an audit, RNA had to decide what they were going to audit.
Many organizations going down the lean path benefit from using three differ-
ent audits when beginning their auditing process: a workplace organization (6S)
audit; a standardized work audit; and a material route and market audit.
Before you can audit, you have to have something to audit. For example, if an
organization does not have standardized work, it cannot be audited. If a facility
does not have a method of workplace organization, it cannot be audited. Finally,
if there is no material route, there cannot be a material route audit. The point is
that when something is implemented, it must then be audited to ensure that the
implementation is continuing to work. A bad process should not be audited.
RNA currently has all these various attributes of lean production implemented
to some degree, so it can begin to develop its audits. The first audit that is nor-
mally developed is the workplace organization audit because it is not very intru-
sive. Auditing workplace organization in essence is just saying, “Is the work area
clean and organized following the 6S method?” This has proven to be a good
audit to begin to get the associates and supervisors involved in the auditing pro-
cess. It helps get people used to the thought of seeing managers auditing process.
RNA utilizes a strategic plan to train its workforce (Harris and Harris, 2007).
Managers have added a class on auditing so that hourly associates understand
the two purposes of the audit, know who is auditing, and understand where they
can find the audits. This is an important point, because it is not a good idea to
have management on the floor auditing without letting the workforce know what
is going on. This often leads to anxiety, frustration, and even anger.
6S Audit
When RNA began to develop the audit, it had to determine what it wanted to be
audited. Managers were sure that, at the very least, they wanted to audit each of
the S’s in the 6S process. They also considered how long the audit would be. They
wanted to make the audit quick and efficient. RNA made it a point when develop-
ing audits that the audit itself should take 10 minutes or less. They continued to
develop the workplace organization audit with this in mind. Finally, they wanted
the audit to have a score, so that an area could quickly know how it had done.
Figure 9.1 shows the audit form RNA developed for workplace organization.
Date: *If no is checked on any item, the area automatically recieves a 1 for that “S”
Area: **For each No, a corrective action needs to be developed and completed
Auditors: ***Scores are 1-5 for each “S”, Area Score is the total of the 6 “S” scores***
Straighten
Does every item in the area have a place?
Is every place for an item identified?
Are visual controls utilized to identify each place (tape, paint, etc.)?
Is the tape on the floor in good shape?
Shine
Is the area clean?
Are the machines in the area clean?
Is the floor swept?
Standardize
Is the area following the facility standards?
Sustain
Are past audits posted in the area?
Is there evidence that the audits are being used to improve?
Safety
Does the area appear to be free of obvious safety hazards?
Are safety meetings being conducted on a regular basis?
Is there evidence that open safety issues are being addressed?
Area Score
item, but it was important that the associates on the production floor did not feel
as though they were being ambushed. A simple sentence was all that was needed,
like, “Hello, my name is Franklin Hunt and I am here to audit this process.”
RNA managers wanted to be sure that standardized work was being followed,
and they also wanted to know whether there were any improvement ideas. They
also considered how long they wanted the audit to take. The goal was 10 min-
utes. Finally, there was no score needed on this audit, because either the stan-
dardized work was being followed or it was not. If it was not, corrective actions
(in the form of an A3) detailing why the standard was not being followed and
the plan to rectify the situation had to be developed. It could be that the stan-
dard method was improved. That is fine, but the new method would need to
become the new standard. Figure 9.2 shows the standardized work audit form
developed by RNA.
Auditors be sure to introduce yourselves and inform production associates that you are auditing their process.
Process
Date
Work Station
Is the standardized work chart posted?
Is the standardized work up-to-date?
Is standardized work being followed?
Are pull signals being handled properly?
(Associate pulls signal at right time)
Are parts presentation devices organized?
Are parts presentation devices used correctly?
Are production status boards utilized?
Are targets listed?
Are targets up to date?
Evidence that process is being audited regulary?
Comments and Corrective Actions
(Place a X where there is a problem)
Auditing Team
Industrial Engineer
Supervisor Production
Associate
every hour and takes about 57 minutes. Therefore, the audit has to take at least
that long. However, the rest of the audit was the same as the other two. Figure 9.3
is the audit form that RNA developed for the timed material delivery route.
Route
Is copy of route layout on tugger?
Is there an issues log on tugger?
Is route layout document up to date and numbered to know latest data in use?
Are all route stops properly identified?
Are all material drop points properly identified?
Are pull signals, returnables, and dunnage in proper place available for pick-up?
Are route aisles being kept clean to allow quick, safe transport of material?
Does operator (tugger) have standardized work instructions?
Are they being followed?
Is all material in proper presentation device (no material on floor, etc.)?
Is min/max level clearly identified on presentation device and being followed?
Are tugger operator’s break and lunch times coordinated with depts they service?
Are latest route time/manpower utilization analysis available for review?
that it was important to get the hourly associates involved and used to the audit-
ing process. Another reason for having the hourly associate in this auditing
process was because he or she has valuable input and ideas on how to make the
area better. (3) The IE was included because, in the RNA facility, IEs created and
were responsible for standards for workplace organization. They were also in
a good position to pass best practices from one area to another. It was also the
responsibility of the IE to be a gauge for the facility, bringing consistency to the
audits. For example, two identical areas should receive the same score. However,
with an hourly associate and the production supervisor doing the audits, there
could be some bias in the results. It was the responsibility of the IE to provide
consistency.
RNA managers felt good about their auditing team for workplace organization
and decided they would meet every Thursday morning at 9:00 am to audit cell
11. They would spend 10 minutes auditing the area. They would then all sign and
date the audit form. Next, they would take the audit form to the PSB to post it in
place of the previous week’s audit. At this point they would check to see whether
there were any corrective actions from the previous week that had not been taken
care of. If there were, the industrial engineers turned out to be exceptional sup-
port resources to help get these corrective actions complete.
As you can see, the only realistic portion of the day that can be standardized
is often the beginning few hours. Though this does not look like standardized
work based on production standards, it actually is very good standardized work
for upper level managers in a production environment. It allows some quiet time
in the early morning to get caught up from the previous day’s messages, and it
provides specific time for auditing.
Finally, it provides for “sacred time.” Sacred time is a concept that too few
managers use. It is when a manager is out on the floor just watching processes
run and looking for ways to make them run better. There is nothing miraculous
here, but how much time do plant managers and other upper level managers
spend out on the production floor watching how things operate? Plant managers
are normally very surprised at how beneficial they find their sacred time.
everyone goes back to their normal jobs. If they do not go out to the floor and
look to see whether the lean system is still running properly, they can “hope”
that it is. It seems that the reason so many people do not go to the production
floor to check and see whether processes are running properly is that they are
too busy in their current jobs or they are afraid they will have to deal with the
area if the system is not running properly.
This type of implementation causes a lot of harm in a facility using lean
systems. The associates and supervisors get very frustrated. Think about it. A
group of people who have never been to your area come in and tell you how to
run it better, and then they leave, offering no support or explanation. There is
no ownership of this process by anyone. Production does not need to hope that
everything is running properly; it needs to know for sure and that the facility is
operating properly. Auditing is a way to make sure this happens.
We have found that a good way to keep good implementation moving for-
ward is through the use of the previously described auditing methodology. We
are not saying that these three audits are all you need; we are just trying to
provide a good starting point. We actually hope that you will have many more
audits as your implementation progresses. After you learn how to effectively con-
duct, complete, and utilize audits to make information flow, your company, like
RNA, will likely be able to use them to make information flow much better in
your facility.
Key Points
NNDevelop audit forms specifically for what is being audited.
NNDevelop audits with the people who are going to be audited in mind.
NNKeep time as a legitimate concern when conducting and developing audits.
NNDevelop a system to completing the audits.
NNCascading audits are good for information flow.
NNPost the audits so that everyone can see them.
Information Overview
What information is available, who needs it, and who holds and is responsible
for it? This section answers those questions in the context of the glass wall,
which is a tool for managing a facility.
1. What Is the Information?
Exercise: What information is needed in order to know how a facility is doing?
How is the information divided? How do you know whether it is correct?
125
We have started each chapter this way because it is a necessity to know what
the information is before you can make the information flow. In this case, it is
important to identify what information lets people know how the facility is doing
as a whole. A good method that we have seen is to evaluate each value stream.
A facility is divided into the various value streams it has. The lean implementa-
tion is also focused on those value streams. Lean initiatives are normally started
at the value stream level. In lean facilities, there is often a designated value
stream manager for each value stream. This person is charged with making
decisions based on what is best for the value stream.
For these reasons, it seems that the best way to evaluate the current health of
the facility as well as the state of lean implementation in the facility is by value
stream. Therefore, the necessary information is the information on safety, quality,
cost, delivery, uptime, lead time, inventory reduction, floor space, and lean imple-
mentation by value stream.
The seeds for this information have already been planted in the form of the
PSBs. However, the PSB tells only what is happening in that one area, not the
entire value stream. But by taking the information off the various PSBs in the
value stream, the health of the entire value stream can be calculated in terms of
safety, quality, uptime, and compliance to pull, as well as productivity.
The lean implementation is another matter because it often takes place on the
value stream level going across multiple processes. So there needs to be a person
responsible for monitoring all the information in the value stream. That person is
the value stream manager.
implementation and normal production. The glass wall is also separated by value
stream. For example, the RNA facility has four value streams, so its glass wall
needs to have four separate sections, one for each of its value streams. Each sec-
tion needs to look the same. (See Figure 10.2.)
about this, so they developed the next part of the glass wall to address theses
answers. The third part of the glass wall is a detailed plan, along with the sta-
tus of the implementation of each Kaizen burst. This includes the owner of the
implementation, the implementation schedule, progress to that schedule, and the
completion date. Also, any problems that occur during the implementation that
need to be addressed should be included in this area. RNA had now completed
the top part of this section. This section was set up to cover the implementation
of lean production in the value stream (see Figure 10.6).
Safety
The first part of the production side of the board was safety. Even if a facility
is not implementing lean production, safety is important to everyone. RNA had
made great strides in the area of safety through its lean implementation, now
measuring safety by issue (injury or near miss). While in the past the big number
was lost work days, now it is any injury, no matter how small. For every injury in
the plant, an investigation (in the form of an A3) had to be completed so that the
injury would not happen again. This portion of the glass wall was the place to
keep all the injuries and A3s within the value stream.
Quality
The second metric was quality. Quality is a necessity in any system. It does not
matter whether it is manufacturing or a business process, quality is key. RNA
decided that it was going to make quality the second section in this area. It mea-
sures quality in terms of scrap, first-time quality, and parts per million.
NNScrap is considered any part that is not acceptable to the customer and is
calculated in dollars.
NNFirst-time quality is calculated as a percentage of products that go through
the entire production process without a quality problem the first time. Parts
that are reworked are counted against first-time quality.
NNParts per million indicates how many defective parts are produced out of
every million.
Delivery
The next important measurable that RNA wanted to capture on the glass wall was
delivery. One of the most important things a facility can do to secure a good future
is to keep the customer happy. To keep a customer happy, on-time delivery is a must.
RNA made big strides on its on-time delivery and wanted the trend to continue.
RNA calculated delivery a little bit differently from most facilities; it deter-
mined a value stream’s compliance to pull. In essence, if a value stream was
producing what it needed when it needed it, delivery would be no problem. As
long as Production Control was doing a good job of scheduling the value stream,
all the value stream could do was produce what it was asked to produce when it
was asked to produce it. RNA wanted to capture this at the glass wall.
Uptime
Uptime was the next measurable. RNA had done a lot to increase information
flow and improve uptime in the facility, and managers wanted to know whether
uptime was indeed getting better. RNA realized that each percentage of uptime
represented a large dollar figure. RNA calculated that if it could improve uptime
1%, that would translate to more than half a million dollars in savings. Uptime
at the RNA facility was calculated by the percentage of time the machines in the
value stream were available to run.
Inventory
The next measurable was a big deal at RNA, as it is in most manufacturing facili-
ties: inventory. RNA measured inventory by inventory turns by value stream. This
number included both purchased parts and WIP parts. Inventory, more specifi-
cally material, made up over 70% of RNA’s cost of goods sold. RNA knew that it
needed to get control of this significant cost and continually attempt to reduce
inventory levels throughout its value streams, so managers saw it as very impor-
tant to track it on the glass wall.
Floor Space
The final measurable that RNA included on the glass wall was floor space. RNA
had a plan to grow its business by 20% over the next five years. To do this,
managers knew that they were going to need floor space. One of their big ini-
tiatives as a result of lean implementation was to reduce the floor space value
streams used to produce product. RNA had already done a good job reducing
the required floor space, but managers wanted to continue to track it.
The RNA meeting lasted approximately 20 minutes. After the meeting was
over, the plant manager and his staff went to one production area (although no
one in the facility knew which one they were going to). They went to the area
and stood at the production status board to make sure it was being utilized.
They also made sure that everything on the board was up-to-date, specifically
the safety, quality, uptime, and compliance to pull. Next, they went to the pro-
duction or schedule board (what it is called depends on the area) and made sure
that board was being used properly.
Finally, the plant manager and his staff audited workplace organization in the
area along with the production supervisor in the area. They then took their score
for the area and compared it to the posted audit. If they were the same, there
was no problem. If there was a discrepancy or something that needed to be
addressed, the communication could be immediate.
This portion of the day is a vital part of the lean implementation for facilities
going through the lean process. The reason is that it gets upper management out
on the production floor and allows the workforce to see management. By getting
to the production floor on a regular basis, management sends the right message
to the workforce.
We have found that the shop floor is a direct reflection on the leadership of a
facility. In the facilities in which we help people formulate their procedures, we
have found that where management takes the extra effort to spend at least a por-
tion of its day on the production floor, the business tends to be more successful
in its lean implementation, as well as having a better informed workforce.
All together, the morning glass wall meeting is vital to a facility implement-
ing lean production. It is the one event that ties all the information flow together
in a facility. In 20 minutes at the morning glass wall meeting, management can
know how the plant ran the previous day as well as how they are doing in terms
of safety, quality, uptime, and delivery. The managers can also make decisions as
they relate to allocating resources throughout the plant. They can also know how
the lean implementation is progressing. The glass wall lets other supervisors and
support staff know how other areas of the facility are running. Furthermore, the
facility management can get out to the production floor and make sure areas
are running as they were intended. This portion of the morning takes about
45 minutes. So, in less than one hour a day, information can effectively and
efficiently flow through a lean manufacturing facility.
It all starts at the top. If the head manufacturing person on site is dedicated to
making this process work, it works. If he or she does not use the glass wall as
a way to manage the facility, it fails. This is not something that can be delegated
to someone else. It takes the top person on site to facilitate, lead, and utilize the
glass wall on a consistent basis for the glass wall to yield the intended results.
Remember: the number one reason that a lean implementation succeeds, and
the number one reason that a lean implementation fails, is leadership—and that
is you.
Key Points
NNMake your glass wall measure what you want to measure.
NNSet your glass wall up by value stream.
NNA glass wall without a consistent system to use it is will not yield intended
results.
NNA glass wall with a consistent efficient system (such as a morning glass wall
meeting) is an invaluable tool to making information flow on a production
floor.
NNIt takes discipline to make the glass wall work for the long term, but the
benefits will likely far outweigh the negatives.
Harris, R., et. al. (2003). Making Materials Flow. Cambridge, MA: Lean Enterprise
Institute.
Harris, C. and Harris, R. (2007). Developing a Lean Workforce: A Guide for Human
Resources, Plant Managers, and Lean Coordinators. New York: Productivity Press.
Methodology and symbols to develop the value stream maps in this book were taken
from the book Learning to See: Value-Stream Mapping to Create Value and Eliminate
Muda by M. Rother and J. Shook. Brookline, MA: The Lean Enterprise Institute, 1998.
139
141