Hume Pipe Culvert Within Sump No - 2
Hume Pipe Culvert Within Sump No - 2
Updated
Unit Rate Amount.
Rate Amount.
Cum. 129.35 6111.79 129.35 6111.79
77718.02 76039.16
Name of Work: Supplying, & Laying of Hume pipe in Haul road near new patch of Bilpahari under Khottadih OCP
Unit 10.00 m
1 Cost of 600 mm int. dia RCC spun pipe NP-3 ,2.5 m length each. 4 Nos
2 Carriage of 4 nos RCC Spun pipes 600 mm int. dia 2.50m long each. 1 Trip
Total
Analysis of rates for laying of 600 mm internal dia NP-3 RCC spun pipe .
unit 1.00 m.
2 Add escallation @ 5% per annumn from 2009 to 2015 i.e for 6 years.
Total Cost
Rate Amount
5700 22800
5000 5000
1140
28940
4170
33110
3311.00
116 116
34.8
150.80
2.27 : Supplying and filling in plinth with Ajoy River sand under floors including, watering,
ramming consolidating and dressing complete.
Code Description Unit Quantity Rate Amount
Details of cost for 10 cum.
Materials:
6501 Ajoy River sand, I/C CARRIAGE cum 10 260 2600
Labour:
114 Beldars Day .89 233 207.37
115 Coolies Day 1.07 233 249.31
101 Bhishti Day .35 272 95.2
TOTAL 3151.88
Add for water charge @ 1 % 31.52
TOTAL 3183.40
Add for contractor’s profit and over-heads @
15% 477.51
Cost of 10 cum. 3660.91
Cost of 1 cum. 366.09
Say 366.1