Operations Research

Industrial engineering
DYNAMIC
PROGRAMMING

11/04/2017 Operations Research 2


Characteristics of dynamic
programming problem
1. The problem can be divided into
stages, with a policy decision required
at each stage
2. Each stage has a number of states
associated with it
3. The effect of the policy decision at each
stage is to transform the current state
into a state associated with the next
stage (possibly according to a
probability distribution)

11/04/2017 Operations Research 3


Characteristics of dynamic
programming problem
4. The solution procedure is designed to
find an optimal policy for the overall
problem, i.e., a prescription of the
optimal policy decision at each stage
for each of the possible states
5. Given the current state, an optimal
policy for the remaining stages is
independent of the policy adopted in
precious stages (this is the principle of
the optimality for dynamic
programming)
11/04/2017 Operations Research 4
Characteristics of dynamic programming
problem: forward recursive
7. The solution procedure begins by
finding the optimal policy for the first
stage
8. A recursive relationship that identifies
the optimal policy for stage n, given
the optimal policy for stage (n - 1), is
available

11/04/2017 Operations Research 5


Characteristics of dynamic programming
problem: backward recursive
7. The solution procedure begins by
finding the optimal policy for the last
stage
8. A recursive relationship that identifies
the optimal policy for stage n, given
the optimal policy for stage (n + 1), is
available

11/04/2017 Operations Research 6


n
Xn

f S   min cSXn  f
* *
n 1  X n 
 N = number of stages
 n = label for current stage (n = 1, 2,
…, N)
 Sn = current state for stage n
 Xn = decision variable for stage n
 Xn* = optimal value of Xn (given Sn)

11/04/2017 Operations Research 7


f S   min cSXn  f
n
*
Xn
 *
n 1  X n 
 f n Sn , X n  = contribution of stage n,
n + 1, …, N to the objective function if
the system starts in state Sn at stage
n, the immediate decision id Xn, and
optimal decisions are made thereafter

n
*

f Sn   f n Sn , X *
n 

11/04/2017 Operations Research 8


f S   min cSXn  f
n
*
Xn
 *
n 1  X n 
 The recursive relationship will always
be of the form

f S n   max  f n S n , X n 
n
*
Xn

or
f S n   min  f n S n , X n 
n
*
Xn

11/04/2017 Operations Research 9


Characteristics of dynamic
programming problem
8. When we use this recursive
relationship, the solution procedure
moves backward stage by stage –
each time finding the optimal policy
for that stage – until it finds the
optimal policy starting at the initial
stage
Xn fn(Sn, Xn)
Sn X1 X2 X3 fn*(Sn) Xn*
S1
S2
S3
11/04/2017 Operations Research 10
Contoh 1
 Sebuah perusahaan mempunyai
usulan dari ketiga pabriknya untuk
kemungkinan mengembangkan
sarana produksi. Perusahaan tersebut
menyediakan anggaran $5 juta untuk
alokasi pada ketiga pabrik. Setiap
pabrik diminta untuk menyampaikan
usulannya yang memberikan jumlah
biaya (c) dan jumlah pendapatan (R)
untuk setiap usulan.

11/04/2017 Operations Research 27


Contoh 1
Pabrik 1 Pabrik 2 Pabrik 3
Usulan c1 R1 c2 R2 c3 R3
1 0 0 0 0 0 0
2 1 5 2 8 1 3
3 2 6 3 9
4 4 12

11/04/2017 Operations Research 28


Definisi state untuk masing2 tahap :
 Sj = dana yang dialokasikan untuk tahap j
sampai tahap n=3
 Cj = memutuskan untuk memilih proposal
dengan biaya cj pada tahap j (untuk tahap j)
atau memilih proposal xj pada tahap j
 Xj = memutuskan untuk memilih proposal xj
pada tahap j (untuk pabrik j);yang berarti
mengalokasikan sejumlah cj untuk pabrik j
 Rj = perkiraan pendapatan yang akan
diperoleh jika membangun pabrik j dengan
biaya cj sesuai usulan proposal xj
 j = 1,2,3

11/04/2017 Operations Research 29


Contoh 1: stage 1
X1 f1(S1, X1)
S1 0 1 2 f1*(S1) X1*
0 0 0 0
1 0 5 5 1
2 0 5 6 6 2
3 0 5 6 6 2
4 0 5 6 6 2
5 0 5 6 6 2

11/04/2017 Operations Research 30


Contoh 1: Stage 2
X2 f2(S2, X2)
S2 0 2 3 4 f2*(S2) X2*
0 0 0 0
1 5 5 0
2 6 8 8 2
3 6 13 9 13 2
4 6 14 14 12 14 2 atau 3
5 6 14 15 17 17 4

11/04/2017 Operations Research 31


Contoh 1: Stage 3
X3 f3(S3, X3)
S3 0 1 f3*(S3) X3*
5 17 17 17 0 atau 1

 Dana yang tersedia $5 juta dimanfaatkan


semua
 Alokasi dana pabrik 1 – pabrik 2 – pabrik 3
◦ 1–4–0
◦ 1–3–1
◦ 2–2–1
 Total pendapatan = $17 juta
11/04/2017 Operations Research 32
Contoh 1: Rekursif Mundur
f3 (s3 ; c3) = R3 (s3 ; c3)
X3 f3(S3, X3)
S3 0 1 f3*(S3) X3*
0 0 0 0
1 0 3 3 1
2 0 3 3 1
3 0 3 3 1
4 0 3 3 1
5 0 3 3 1

11/04/2017 Operations Research 33


Contoh 1: Rekursif Mundur

f2 = (s2 ; c2) = R2(s2 ; c2) + f3* (s2 – c2)


X2 f2(S2, X2)
S2 0 2 3 4 f2*(S2) X2*
0 0 0 0
1 3 3 0
2 3 8 8 2
3 3 11 9 11 2
4 3 11 12 12 12 3 atau 4
5 3 11 12 15 15 4

11/04/2017 Operations Research 34


Contoh 1: Rekursif Mundur
f2 = (s2 ; c2) = R2(s2 ; c2) + f3* (s2 – c2)
X1 f1(S1, X1)
S1 0 1 2 f1*(S1) X1*
5 15 17 17 17 1 atau 2

 Dana yang tersedia $5 juta dimanfaatkan


semua
 Alokasi dana pabrik 1 – pabrik 2 – pabrik 3
◦ 1–3–1
◦ 1–4–0
◦ 2–2–1
 Total pendapatan = $17 juta
11/04/2017 Operations Research 35
Contoh 2
 Suatu organisasi kesehatan dunia
menyelenggarakan program peningkatan
kepedulian pada kesehatan dan
memberikan pendidikan kesehatan di
beberapa negara terbelakang
 Organisasi tersebut memiliki 5 tim medis
yang siap ditugaskan di 3 negara
 Satu negara paling tidak harus didatangi
1 tim medis
 Performansi diukur dengan penambahan
umur hidup

11/04/2017 Operations Research 36


Contoh 2

Thousands of Additional Person-


Years of Life
Number of Country
Medical Teams 1 2 3
1 45 20 50
2 70 45 70
3 90 75 80
4 105 110 100
5 120 150 130

11/04/2017 Operations Research 37


Contoh 2: Stage 3
X3 f3(S3, X3)
S3 1 2 3 f3*(S3) X3*
1 45 45 1
2 45 70 70 2
3 45 70 90 90 3

11/04/2017 Operations Research 38


Contoh 2: Stage 2
X2 f2(S2, X2)
S2 1 2 3 f2*(S2) X2*
2 65 65 1
3 90 90 90 1 atau 2
4 110 115 120 120 3

11/04/2017 Operations Research 39


Contoh 2: Stage 1
X1 f1(S1, X1)
S1 1 2 3 f1*(S1) X1*
5 170 160 145 170 1

 Alokasi Tim Medis


◦1–3–1
◦ Total additional person-years of life =
170.000

11/04/2017 Operations Research 40


Contoh 2: asumsi suatu negara boleh
tidak dikunjungi tim medis sama sekali
X3 f3(S3, X3)
S3 0 1 2 3 4 5 f3*(S3) X3*
0 0 0 0
1 0 45 45 1
2 0 45 70 70 2
3 0 45 70 90 90 3
4 0 45 70 90 105 105 4
5 0 45 70 90 105 120 120 5

X2 f2(S2, X2)
S2 0 1 2 3 4 5 f2*(S2) X2*
0 0 0 0
1 45 20 45 1
2 70 65 45 70 1
3 90 90 90 75 90 0 atau 1 atau 2
4 105 110 115 120 110 120 3
5 120 125 135 145 155 150 155 4

11/04/2017 Operations Research 41


Contoh 2: asumsi suatu negara boleh
tidak dikunjungi tim medis sama sekali
X1 f1(S1, X1)
S1 0 1 2 3 4 5 f1*(S1) X1*
5 155 170 160 150 145 130 170 1

 Alokasi tim medis


◦1–3–1
◦ Total additional person-years of life =
170.000

11/04/2017 Operations Research 42


Soal 1
 A college student has 7 days remaining before
final examinations begin in her four courses, and
she wants to allocate this study time as
effectively as possible. She needs at least 1 day
on each course, and she likes to concentrate on
just one course each day, so she wants to
allocate 1, 2, 3, or 4 days to each course. Having
recently taken an operations research course,
she decides to use dynamic programming to
make these allocations to maximize the total
grade points to be obtained from four courses.
She estimates that the alternative allocations for
each course would yield the number of grade
points shown in the table. Solve this problem by
dynamic programming.

11/04/2017 Operations Research 43


Soal 1
estimated grade points
number of courses
study days 1 2 3 4
1 3 5 2 6
2 5 5 4 7
3 6 6 7 9
4 7 9 8 9

11/04/2017 Operations Research 44


Soal 2
 Sebuah lembaga penelitian merencanakan
suatu proyek penelitian. Terdapat tiga tim
yang akan menyelesaikan proyek tersebut
dengan pendekatan yang berbeda. Ketiga tim
mempunyai kemungkinan gagal berturut-turut
sebesar 0,4; 0,6; dan 0,8 sehingga
kemungkinan proyek tersebut gagal adalah
sebesar 0,4 x 0,6 x 0,8 = 0,192.
 Untuk mengurangi tingkat kegagalan proyek,
ada dua pakar yang ditugaskan untuk
membantu kerja tim peneliti. Seorang pakar
hanya bisa bergabung di satu tim. Tapi satu
tim boleh dibantu oleh lebih dari satu pakar.

11/04/2017 Operations Research 45


Soal 2
 Data perkiraan tingkat kegagalan tim
apabila dibantu oleh pakar:
Jumlah pakar Tingkat kegagalan
yang bergabung Tim 1 Tim 2 Tim 3
0 0,40 0,60 0,80
1 0,20 0,40 0,50
2 0,15 0,20 0,30

 Tujuan: minimasi tingkat kegagalan

11/04/2017 Operations Research 46


 Xj = memutuskan menambah xj pakar
pada tim j (banyaknya pakar yang
ditambahkan pada tim j)
 P (sj ; xj) = kemungkinan gagal dari
tim j jika menambahkan xj pakar pada
tim j

11/04/2017 Operations Research 47


Soal 2: Stage 1 (n=3)

f3 (s3 ; x3) = p3 (s3 ; x3)


S3 f3(S3) X 3*
0 0,80 0
1 0,50 1
2 0,30 2

11/04/2017 Operations Research 48


Soal 2: Stage 2 (n=2)
X2 f2(S2,X2)=p2(X2) . f3(S2-X2) f2(S2) X2*
S2 0 1 2
0 0,48 0,48 0
1 0,30 0,32 0,30 0
2 0,18 0,20 0,16 0,16 2

0,48 = 0,6 x 0,8

11/04/2017 Operations Research 49


Soal 2: Stage 3 (n=1)
X1 f1(S1,X1)=p1(X1) . f2(S1-X1) f1(S1) X1*
S1 0 1 2
2 0,064 0,060 0,072 0,060 1

0,064 = 0,4 x 0,16

 Alokasi ilmuwan :
◦1–0–1
◦ Probabilitas baru ketiga tim tersebut akan
gagal menjadi 0,060
11/04/2017 Operations Research 50
Soal 3
 Selama satu horizon perencanaan
produksi yang terdiri dari tiga bulan,
permintaan akan produk A adalah dua
unit produk per bulan
 Jika inventory di awal dan akhir horizon
perencanaan harus nol dan tidak
diijinkan terjadi stok kosong pada saat
permintaan datang, maka dalam tiap
bulannya minimal harus tersedia satu
unit produk. Pada bulan pertama harus
diproduksi minimal satu unit produk. Stok
pada bulan ketiga harus nol.

11/04/2017 Operations Research 51


Soal 3
 Untuk memenuhi permintaan selama
tiga bulan tersebut, produk dapat
diproduksi sekaligus dalam satu bulan
tertentu dengan resiko biaya simpan
tinggi atau diproduksi dalam tiap bulan
dengan resiko biaya setup tinggi
 Tujuan: menentukan kebijakan
produksi yang menghasilkan ongkos
total minimum.

11/04/2017 Operations Research 52


Soal 3
 Rincian biaya
Biaya Bulan ke-

1 2 3
Setup cost/run production
14 8 12
Production cost/unit
10 8 10
Holding cost/unit ending in inventory
4 2 6

11/04/2017 Operations Research 53


Soal 4
 Perusahaan X mempunyai data
kebutuhan produksi dari produk A
untuk 3 periode ke depan:

Periode Kebutuhan Produksi

1 3 unit
2 3 unit
3 3 unit
11/04/2017 Operations Research 54
Soal 4
 Setiap kali run produksi dihasilkan 1 unit produk
A. Biaya setup untuk run pertama (1 unit
pertama) adalah $20 dalam setiap periode dan
naik sebesar $2 untuk setiap tambahan 1 unit
yang diproduksi pada periode tersebut.
 Biaya produksi + overhead untuk tiap periode
konstan
 Biaya simpan untuk setiap 1 unit kelebihan
produk adalah $3 per periode
 Kapasitas maksimum gudang adalah 3 unit per
periode
 Inventori awal periode 1 = 0
 Tujuan: menentukan kebijakan produksi yang
menghasilkan ongkos total minimum
11/04/2017 Operations Research 55