NO :......
PEKERJAAN : . . . . . .
Proyek : ONE GALAXY - SURABAYA
Tanggal : . . . . . .
Lokasi/Posisi : 2BR Unit . . . . . . Lantai . . . . . . Tower . . . . . . .
No. Reference Drawing : . . . . . .
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat WALL I II III
I Kitchen / Dinning Room
1 Plumbing
a Zink (CW & HW) 2 ttk
b Mesin Cuci (CW & WW) 2 ttk
2 Elektrikal
a Saklar 3 ttk
b Stop Kontak (SO) 6 ttk
c Thermostat 2 ttk
d Power AC 2 ttk
e Panel / KWH meter 1 ttk
3 Elektronik
a Video Phone 1 ttk
b Gas detector 1 ttk
c Selenoid valve 1 ttk
II Balcony
1 Plumbing
a Floor drain (WW) 1 ttk
2 Elektrikal
a Power outdoor AC 1 ttk
b Lampu 2 ttk
III Maid Room
1 Plumbing
a Water Heater (CW & HW) 2 ttk
b Main Gate Valve Unit 1 ttk
2 Elektrikal
a Saklar 1 ttk
b Stop Kontak (SO) 3 ttk
3 Elektronik
a MATV, Data & Telp
IV Bedroom 1
1 Elektrikal
a Saklar 2 ttk
b Stop Kontak (SO) 5 ttk
c Power AC 1 ttk
d Thermostat 1 ttk
2 Elektronik
a MATV, Data & Telp 2 ttk
V Master Bedroom
1 Elektrikal
a Saklar 2 ttk
b Stop Kontak (SO) 6 ttk
c Power AC 1 ttk
d Thermostat 1 ttk
2 Elektronik
a MATV, Data & Telp 3 ttk
VI Living Room
1 Elektrikal
a Saklar 2 ttk
b Stop Kontak (SO) 3 ttk
c Power AC 1 ttk
2 Elektronik
a MATV, Data & Telp 2 ttk
VII Foyer
1 Elektrikal
a Saklar 1 ttk
VIII Koridor Unit
1 Elektronik
a Door bell 1 ttk
b Indoicator lamp 1 ttk
Catatan : r Tidak Diterima √ Diterima
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 1 PT. SPGN PT. TATAMULIA MKU
Joint Inspection 2 Quality Control inspector Construction Manager
Joint Inspection 3
Joint Inspection 4
Joint Inspection 5 (………………………) (………………...……) (……………………………)
FORM INSPEKSI
NO :......
PEKERJAAN : . . . . . .
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi :2BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Elektrikal
a Lampu 1 ttk
2 MVAC
a Ceilling Fan 1 ttk
II Bathroom
1 Elektrikal
a Lampu 3 ttk
2 MVAC
a Ceilling Fan 2 ttk
III Master Bathroom
1 Elektrikal
a Lampu 5 ttk
2 MVAC
a Ceilling Fan 2 ttk
3 Fire Fighting
a Sprinkler 1 ttk
IV Kitchen / Dinning Room
1 Elektrikal
a Lampu 3 ttk
2 MVAC
a Return Air 1 ttk
b Supply Air 1 ttk
3 Fire Fighting
a Sprinkler 2 ttk
4 Elektronik
a Speaker 1 ttk
b Temperatur Detector 1 ttk
c Smoke Detector 1 ttk
V Balcony
1 MVAC
a Outdoor Unit 1 ttk
b Exoust Louvre 1 ttk
VI Maid Room
1 Elektrikal
a Lampu 1 ttk
2 MVAC
a Ceilling Fan 1 ttk
3 Fire Fighting
a Sprinkler 1 ttk
4 Elektronik
a Smoke Detector 1 ttk
VII Bedroom 1
1 Elektrikal
a Lampu 2 ttk
2 MVAC
a Return Air 1 ttk
b Supply Air 1 ttk
3 Fire Fighting
a Sprinkler 1 ttk
4 Elektronik
a Smoke Detector 1 ttk
VIII Master Bedroom
1 Elektrikal
a Lampu 2 ttk
2 MVAC
a Return Air 1 ttk
b Supply Air 1 ttk
3 Fire Fighting
a Sprinkler 1 ttk
4 Elektronik
a Smoke Detector 1 ttk
IX Living Room
1 Elektrikal
a Lampu 5 ttk
2 MVAC
a Return Air 1 ttk
b Supply Air 1 ttk
3 Fire Fighting
a Sprinkler 1 ttk
4 Elektronik
a Smoke Detector 1 ttk
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat CELLING I II III
X Foyer
1 Elektrikal
a Lampu 2 ttk
2 Fire Fighting
a Sprinkler 2 ttk
3 Elektronik
a Smoke Detector 1 ttk
b Speaker 1 ttk
XI Storage
1 Elektrikal
a Lampu 1 ttk
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :2BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
a Kloset (WC) 1 ttk -
b Kloset (CW jet spray & supply) 2 ttk -
c Wastafel (CW) 1 ttk -
d Wastafel (WW) 1 ttk -
e Shower (CW) 1 ttk -
f FD (WW) 1 ttk -
II Bathroom
1 Plumbing
a Kloset (WC) 1 ttk -
b Kloset CW (jet spray & supply) 2 ttk -
c Wastafel (CW & HW) 2 ttk -
d Wastafel (WW) 1 ttk -
e Shower (CW & HW) 2 ttk -
f FD (WW) 2 ttk -
2 Elektrikal
a Saklar 2 ttk -
b Stop Kontak (SO) 1 ttk -
III Master Bathroom
1 Plumbing
a Kloset (WC) 1 ttk -
c Kloset (CW jet spray & supply) 2 ttk -
d Wastafel (CW & HW) 2 ttk -
e Wastafel (WW) 1 ttk -
f Shower (CW & HW) 2 ttk -
g FD (WW) 2 ttk -
h Bathup (WW) 1 ttk -
i Bathup (CW & HW) 2 ttk -
2 Elektrikal
a Saklar 2 ttk
b Stop Kontak (SO) 1 ttk
IV Kitchen / Dinning Room
1 Plumbing
a Zink (WW) 1 ttk -
V Balcony
1 Plumbing
a FD (WW) 2 ttk -
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal :
......
Lokasi/Posisi :
2BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
II Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
III Master Bathroom
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
IV Kitchen / Dinning Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
6 Gas
V Balcony
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
VI Maid Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
VII Bedroom 1
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
VIII Master Bedroom
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
IX Living Room
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
X Foyer
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XI Storage
1 Elektrikal
2 MVAC
3 Elektronik
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :3BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
Sign Sign
Joint Inspection Date Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
SPGN TATA
Joint Inspection 1 PT. SPGN PT. TATAMULIA MKU
Joint Inspection 2 Quality Control inspector Construction Manager
Joint Inspection 3
Joint Inspection 4
Joint Inspection 5 (………………………) (………………...……) (……………………………)
CV. MKU - One Galaxy-Surabaya
FORM INSPEKSI
NO :......
PEKERJAAN : . . . . . .
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi :3BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
II Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
III Master Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
3 Fire Fighting
a Sprinkler ttk
IV Kitchen / Dinning Room
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Speaker ttk
b Temperatur Detector ttk
c Smoke Detector ttk
V Balcony
1 MVAC
a Outdoor Unit ttk
b Exoust Louvre ttk
VI Maid Room
1 Elektrikal
a Lampu ttk
2 MVAC
a ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
VII Bedroom 1
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
VIII Bedroom 2
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
IX Master Bedroom
1 Elektrikal
a Lampu ttk
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat CELLING I II III
2 MVAC
a Return Air ttk
b Supply Air ttk
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat CELLING I II III
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
X Living Room
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
XI Foyer
1 Elektrikal
a Lampu ttk
2 Fire Fighting
a Sprinkler ttk
3 Elektronik
a Smoke Detector ttk
b Speaker ttk
XII Storage
1 Elektrikal
a Lampu ttk
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :3BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
a Kloset (WC) ttk -
b Kloset (CW jet spray & supply) ttk -
c Wastafel (CW) ttk -
d Wastafel (WW) ttk -
e Shower (CW) ttk -
f FD (WW) ttk -
II Bathroom
1 Plumbing
a Kloset (WC) ttk -
b Kloset CW (jet spray & supply) ttk -
c Wastafel (CW & HW) ttk -
d Wastafel (WW) ttk -
e Shower (CW & HW) ttk -
f FD (WW) ttk -
2 Elektrikal
a Saklar ttk -
b Stop Kontak (SO) ttk -
III Master Bathroom
1 Plumbing
a Kloset (WC) ttk -
c Kloset (CW jet spray & supply) ttk -
d Wastafel (CW & HW) ttk -
e Wastafel (WW) ttk -
f Shower (CW & HW) ttk -
g FD (WW) ttk -
h Bathup (WW) ttk -
i Bathup (CW & HW) ttk -
2 Elektrikal
a Saklar ttk
b Stop Kontak (SO) ttk
IV Kitchen / Dinning Room
1 Plumbing
a Zink (WW) ttk -
V Balcony
1 Plumbing
a FD (WW) ttk -
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :3BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
II Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
III Master Bathroom
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
IV Kitchen / Dinning Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
6 Gas
V Balcony
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
VI Maid Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
VII Bedroom 1
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
VIII Bedroom 2
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
IX Master Bedroom
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
X Living Room
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XI Foyer
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XII Storage
1 Elektrikal
2 MVAC
3 Elektronik
Tanggal : ......
Lokasi/Posisi :4BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :4BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
II Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
III Bathroom I
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
IV Master Bathroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
3 Fire Fighting
a Sprinkler ttk
V Kitchen / Dinning Room
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Speaker ttk
b Temperatur Detector ttk
c Smoke Detector ttk
VI Balcony
1 MVAC
a Outdoor Unit ttk
b Exoust Louvre ttk
VII Maid Room
1 Elektrikal
a Lampu ttk
2 MVAC
a Ceilling Fan ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
VIII Bedroom 1
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
IX Bedroom 2
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat CELLING I II III
4 Elektronik
a Smoke Detector ttk
X Bedroom 3
Unit CEK Diperbaiki
NO ITEM PEKERJAAN KETERANGAN
Qty Sat CELLING I II III
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
XI Master Bedroom
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
XII Living Room
1 Elektrikal
a Lampu ttk
2 MVAC
a Return Air ttk
b Supply Air ttk
3 Fire Fighting
a Sprinkler ttk
4 Elektronik
a Smoke Detector ttk
XIII Foyer
1 Elektrikal
a Lampu ttk
2 Fire Fighting
a Sprinkler ttk
3 Elektronik
a Smoke Detector ttk
b Speaker ttk
XIV Storage
1 Elektrikal
a Lampu ttk
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :4BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
a Kloset (WC) ttk -
b Kloset (CW jet spray & supply) ttk -
c Wastafel (CW) ttk -
d Wastafel (WW) ttk -
e Shower (CW) ttk -
f FD (WW) ttk -
II Bathroom
1 Plumbing
a Kloset (WC) ttk -
b Kloset CW (jet spray & supply) ttk -
c Wastafel (CW & HW) ttk -
d Wastafel (WW) ttk -
e Shower (CW & HW) ttk -
f FD (WW) ttk -
2 Elektrikal
a Saklar ttk -
b Stop Kontak (SO) ttk -
III Bathroom 1
1 Plumbing
a Kloset (WC) ttk -
b Kloset CW (jet spray & supply) ttk -
c Wastafel (CW & HW) ttk -
d Wastafel (WW) ttk -
e Shower (CW & HW) ttk -
f FD (WW) ttk -
2 Elektrikal
a Saklar ttk -
b Stop Kontak (SO) ttk -
IV Master Bathroom
1 Plumbing
a Kloset (WC) ttk -
c Kloset (CW jet spray & supply) ttk -
d Wastafel (CW & HW) ttk -
e Wastafel (WW) ttk -
f Shower (CW & HW) ttk -
g FD (WW) ttk -
h Bathup (WW) ttk -
i Bathup (CW & HW) ttk -
2 Elektrikal
a Saklar ttk
b Stop Kontak (SO) ttk
V Kitchen / Dinning Room
1 Plumbing
a Zink (WW) ttk -
VI Balcony
1 Plumbing
a FD (WW) ttk -
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Tanggal : ......
Lokasi/Posisi :4BR Unit . . . Lantai . . . Tower . . .
No. Reference Drawing : . . . . . .
I Maid Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
II Bathroom
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
III Bathroom 1
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
IV Master Bathroom
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
V Kitchen / Dinning Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
6 Gas
VI Balcony
1 Plumbing
2 Elektrikal
3 MVAC
4 Elektronik
VII Maid Room
1 Plumbing
2 Elektrikal
3 Fire Fighting
4 MVAC
5 Elektronik
VIII Bedroom 1
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
IX Bedroom 2
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
X Bedroom 3
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XI Master Bedroom
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XII Living Room
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XIII Foyer
1 Elektrikal
2 Fire Fighting
3 MVAC
4 Elektronik
XIV Storage
1 Elektrikal
2 MVAC
3 Elektronik
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
DINDING LANTAI
NO TYPE BATHROOM Tinggi (H) From AS Jarak (B) From AS ILUSTRASI GAMBAR
mm mm mm mm
KLOSET
I MAID BATHROOM L R
a Kloset (CW 421 J)
WC - - 500 Center
CW Supply 150 L-110 - -
CW Spray 580 L-100 - -
b Wastafel (LW 7 - CJW) t.850+55mm H
CW Supply 590 R-75 - - H
WW Drain 600 Center - -
c Shower (TX 423 S)
CW Supply 1050 Center - - AS DINDING L
IV MAID ROOM
a Wather Heater
CW Supply 2050 L-75 - - AS DINDING
HW Supply 2050 R-75 - -
LEGEND :
WC = Water Closed Pipe
CW = Clean Water Pipe
HW = Hot Water Pipe
WW = Waste Water Pipe
FD = Floor drain
R = Kanan
L = Kiri
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
1 Shaft C1-19
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø 80 Drain AC 1
2 Shaft C1-20
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
3 Shaft C1-21
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
4 Shaft C1-43
Pipa PVC Ø100 RWP 2
5 Shaft C1-40
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
6 Shaft C1-41
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
7 Shaft C1-42
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø 80 Drain AC 1
8 Pipa C1-54
Pipa PVC Ø100 RWP 2
9 Shaft C1-22
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
10 Shaft C1-23
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø50 Drain AC 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
11 Pipa C1-44
Pipa PVC Ø100 RWP 2
12 Shaft C1-38
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø50 Drain AC 1
13 Shaft C1-39
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
14 Shaft C1-53
Pipa PVC Ø100 RWP 2
15 Shaft C1-37
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø80 Drain AC 1
16 Shaft C1-16
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
17 Shaft C1-52
Pipa PVC Ø100 RWP 2
18 Shaft C1-24
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø80 Drain AC 1
19 Shaft C1-07
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
20 Shaft C1-45
Pipa PVC Ø100 RWP 2
21 Shaft C1-25
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
22 Shaft C1-26
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø80 Drain AC 1
23 Shaft C1-46
Pipa PVC Ø150 RWP 2
24 Shaft C1-36
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
25 Pipa C1-35
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø80 Drain AC 1
26 Shaft C1-51
Pipa PVC Ø150 RWP 2
27 Shaft C1-12
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
28 Shaft C1-34
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
29 Shaft C1-50
Pipa PVC Ø150 RWP 2
30 Shaft C1-10
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
31 Shaft C1-27
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
32 Shaft C1-47
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Pipa PVC Ø150 RWP 2
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
33 Shaft C1-30
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
34 Shaft C1-28
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
35 Shaft C1-29
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
36 Shaft C1-48
Pipa PVC Ø150 RWP 2
37 Shaft C1-32
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
38 Shaft C1-33
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
39 Shaft C1-31
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
40 Shaft C1-49
Pipa PVC Ø150 RWP 2
41 Shaft C1-03
Pipa PVC Ø150 RWP 2
42 Shaft C1-05
Pipa BS Ø100 SPDR 1
Pipa BS Ø150 SP 1
Pipa BS Ø150 SP-HZ 1
Pipa BS Ø150 FH-HZ 1
Pipa Galvanis Ø150 CW Roof Tank 1
Pipa Galvanis Ø150 CW Grafitasi 1
43 Shaft C1-17
Ducting 1400x350 1
Ducting 1400x950 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Ducting 1000x500 1
44 Shaft C1-06
Cable Tray 500x100 1
Cable Ladder 800x100 1
45 Shaft C1-09
Ducting 1400x350 1
Ducting 1400x950 1
46 Shaft C1-14
Ducting 950x550 1
47 Shaft C1-13
Pipa PVC Ø150 RWP 2
Pipa BS Ø150 FH-HZ 1
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 3
Joint Inspection 4
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
1 Shaft C1-19
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø 80 Drain AC 1
2 Shaft C1-20
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
3 Shaft C1-21
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
4 Shaft C1-43
Pipa PVC Ø100 RWP 2
5 Shaft C1-40
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
6 Shaft C1-41
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
7 Shaft C1-42
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø 80 Drain AC 1
8 Pipa C1-54
Pipa PVC Ø100 RWP 2
9 Shaft C1-22
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
10 Shaft C1-23
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø50 Drain AC 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
11 Pipa C1-44
Pipa PVC Ø100 RWP 2
12 Shaft C1-38
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø50 Drain AC 1
13 Shaft C1-39
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
14 Shaft C1-53
Pipa PVC Ø100 RWP 2
15 Shaft C1-37
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø80 Drain AC 1
16 Shaft C1-16
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
17 Shaft C1-52
Pipa PVC Ø100 RWP 2
18 Shaft C1-24
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa PVC Ø80 Drain AC 1
19 Shaft C1-07
Pipa PVC Ø 100 WW 1
Pipa PVC Ø 150 SW 1
Pipa PVC Ø 100 VT 1
Pipa CIP Ø100 KD 1
20 Shaft C1-45
Pipa PVC Ø100 RWP 2
21 Shaft C1-25
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
22 Shaft C1-26
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø80 Drain AC 1
23 Shaft C1-46
Pipa PVC Ø150 RWP 2
24 Shaft C1-36
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
25 Pipa C1-35
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø80 Drain AC 1
26 Shaft C1-51
Pipa PVC Ø150 RWP 2
27 Shaft C1-12
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
28 Shaft C1-34
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
29 Shaft C1-50
Pipa PVC Ø150 RWP 2
30 Shaft C1-10
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
Pipa PVC Ø50 Drain AC 1
31 Shaft C1-27
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
32 Shaft C1-47
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Pipa PVC Ø150 RWP 2
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
33 Shaft C1-30
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
34 Shaft C1-28
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
35 Shaft C1-29
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
36 Shaft C1-48
Pipa PVC Ø150 RWP 2
37 Shaft C1-32
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa CIP Ø100 KD 1
38 Shaft C1-33
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
39 Shaft C1-31
Pipa PVC Ø100 WW 1
Pipa PVC Ø150 SW 1
Pipa PVC Ø100 VT 1
Pipa PVC Ø50 Drain AC 1
40 Shaft C1-49
Pipa PVC Ø150 RWP 2
41 Shaft C1-03
Pipa PVC Ø150 RWP 2
42 Shaft C1-05
Pipa BS Ø100 SPDR 1
Pipa BS Ø150 SP 1
Pipa BS Ø150 SP-HZ 1
Pipa BS Ø150 FH-HZ 1
Pipa Galvanis Ø150 CW Roof Tank 1
Pipa Galvanis Ø150 CW Grafitasi 1
43 Shaft C1-17
Ducting 1400x350 1
Ducting 1400x950 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Ducting 1000x500 1
44 Shaft C1-06
Cable Tray 500x100 1
Cable Ladder 800x100 1
45 Shaft C1-09
Ducting 1400x350 1
Ducting 1400x950 1
46 Shaft C1-14
Ducting 950x550 1
47 Shaft C1-13
Pipa BS Ø150 FH-HZ 1
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 3
Joint Inspection 4
Tanggal : ......
Lokasi/Posisi :Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
1 Shaft C1-19
Pipa PVC Ø 80 Drain AC 1
2 Shaft C1-42
Pipa PVC Ø 80 Drain AC 1
3 Shaft C1-22
Pipa PVC Ø50 Drain AC 1
4 Shaft C1-23
Pipa PVC Ø50 Drain AC 1
5 Shaft C1-38
Pipa PVC Ø50 Drain AC 1
6 Shaft C1-39
Pipa PVC Ø50 Drain AC 1
7 Shaft C1-37
Pipa PVC Ø80 Drain AC 1
8 Shaft C1-24
Pipa PVC Ø80 Drain AC 1
9 Shaft C1-26
Pipa PVC Ø80 Drain AC 1
10 Pipa C1-35
Pipa PVC Ø80 Drain AC 1
11 Shaft C1-12
Pipa PVC Ø50 Drain AC 1
12 Shaft C1-34
Pipa PVC Ø50 Drain AC 1
13 Shaft C1-10
Pipa PVC Ø50 Drain AC 1
14 Shaft C1-27
Pipa PVC Ø50 Drain AC 1
15 Shaft C1-29
Pipa PVC Ø50 Drain AC 1
16 Shaft C1-31
Pipa PVC Ø50 Drain AC 1
17 Shaft C1-05
Pipa BS Ø100 SPDR 1
Pipa BS Ø150 SP 1
Pipa BS Ø150 SP-HZ 1
Pipa BS Ø150 FH-HZ 1
FORM INSPEKSI
NO :......
PEKERJAAN : MEP
Proyek : ONE GALAXY - SURABAYA
Tanggal :
......
Lokasi/Posisi :Lantai . . . Tower . . .
No. Reference Drawing : MEP.COM.001.1
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Pipa Galvanis Ø150 CW Roof Tank 1
Pipa Galvanis Ø150 CW Grafitasi 1
18 Shaft C1-17
Ducting 1400x350 1
Ducting 1400x950 1
Ducting 1000x500 1
18 Shaft C1-06
Cable Tray 500x100 1
Cable Ladder 800x100 1
19 Shaft C1-09
Ducting 1400x350 1
Ducting 1400x950 1
20 Shaft C1-14
Ducting 950x550 1
21 Shaft C1-13
Pipa BS Ø150 FH-HZ 1
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 3
Joint Inspection 4
Tanggal : ......
Lokasi/Posisi : Lantai . . . Tower . . .
No. Reference Drawing :
Cek Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN
Braket I II III
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 3
Joint Inspection 4
Tanggal : .........................
Lokasi/Posisi : Lantai . . . . . . . . . . . . . . . . . . . .
No. Reference Drawing : .........................
Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN STANDAR PEMASANGAN
I II III
I MATERIAL
1 Pipa BS
2 Fitting Screw
3 Fitting Welded
Sesuai spesifikasi & Approval,
4 Support baik dan tidak cacat.
5 Hanger
6 Zinchromate
7 Cat Finish
II PEMASANGAN INSTALASI
Posisi Lurus, diameter, jarak antar
longgar/goyang.
Joint Inspection Date Sign SPGN Sign TATA Sign MKU Dibuat Oleh : DiKetahui Oleh : Disetujui Oleh :
Joint Inspection 3
Joint Inspection 4
Tanggal : .........................
Lokasi/Posisi : Lantai . . . . . . . . . . . . . . . . . . . .
No. Reference Drawing : .........................
Diperbaiki
NO ITEM PEKERJAAN Qty Cek Install KETERANGAN STANDAR PEMASANGAN
I II III
CV. MKU - One Galaxy-Surabaya