Plaster Quantity

Sr. No. Description Quantity Unit

1 Proportion of Mortar 1 6
2 Area of plastering 100 sq.m
3 Thickness of plastering 12 mm
4 Volume of plater 1.2 cu.m.
Adding 50% for voids and 10% for unevenness
5 1.92 cu.m.
∴ Dry Mortar=
Cement 0.2743 cu.m
6
Cement bags 8 numbers
1.646 cu.m
7 Sand
0.58 brass

Cost of Material
Total
Sr. No. Description Quantity Unit Rate Cost

1 Cement 8 numbers 350 2800

2 Sand 1.646 cu.m 1000 1645.71


Total Cost of Materials 4446
Labours Required for Plaster Work
Rate Per Day
Sr. No. Labour Quantity of Labours per 10 cu.m.of work (8 hours)
1 Head Mason 1/2 350
2 Mason 10 325
3 Male Mazdoor 8 300
4 Female Mazdoor 4 275
5 Bhisti 1 300
6 Contingencies Lump Sum
Total Cost of Labours for 100 sq.m. of wok
Total Cost of Labours per sq.m.
Total Cost of Labours for our Work

Estimation of Plaster Work- By Prof. Shaikh


(D.C.E., B.E. Civil, ME Structures)

Unite Constructions & Coaching


Youtube Link: Unite Constructions & Unite Coaching

https://www.youtube.com/channel/UCBAqtp4A_YbEuUE59o7p-9w

Enter Values In these cells only


Total Amount
175
3250
2400
1100
300
250
7475
74.75
Rs.7475