Question 1 Refer to the paragraph below to answer the question


Correct
An industrial engineer has designed two alternative methods of accomplishing a production job. Both methods
Mark 2.00 out of involve the acquisition of the same working place and other capital equipment to be used for this job only.
2.00
Method A calls for a crew consisting of three men each costing P30000 per hour. This method will result in the
production of 10 units per hour of which two will be rejects.
Method B calls for a crew of two men each costing P35.00 per hour and should result in the production of eight
units per hour of which one will be reject.

The cost of the direct material lost in each reject is P20.00. If a certain total number of units is to be produced,
find which method is more economical.
Method A:

Select one:
a. Per unit cost =18.25

b. Per unit cost =16.25 

c. Per unit cost =15.25

d. Per unit cost =19.25

Your answer is correct.

Question 2 Refer to the paragraph below to answer the question


Correct
An industrial engineer has designed two alternative methods of accomplishing a production job. Both methods
Mark 2.00 out of involve the acquisition of the same working place and other capital equipment to be used for this job only.
2.00
Method A calls for a crew consisting of three men each costing P30000 per hour. This method will result in the
production of 10 units per hour of which two will be rejects.

Method B calls for a crew of two men each costing P35.00 per hour and should result in the production of eight
units per hour of which one will be reject.
The cost of the direct material lost in each reject is P20.00. If a certain total number of units is to be produced,
find which method is more economical.
Method B:

Select one:
a. Per unit cost = 12.86 

b. Per unit cost = 14.86

c. Per unit cost = 15.86

d. Per unit cost = 13.86

Your answer is correct.

https://blended.amaesonline.com/abl-trimestral/mod/quiz/review.php?attempt=1272488&cmid=34083 1/3
3/19/2020 Quiz 001: Attempt review

Question 3 Refer to the paragraph for the questions below


Correct
A cement grinding mill “A” with a capacity of 50 tons per hour utilizes forged steel grinding balls costing P12,
Mark 2.00 out of
000 per ton, which have a wear rate of 100 grams per ton cement milled. Another cement mill “B” of the same
2.00
capacity uses high chrome steel grinding balls costing P50, 000 per ton with wear rate of 20 grams per ton
cement milled. Determine the more economical grinding mill, considering other factors to be the same.
For Mill B:

Select one:
a. P65/hour

b. P50/hour 

c. P55/hour

d. P60/hour

Your answer is correct.

Question 4 Refer to the paragraph for the questions below


Correct
A cement grinding mill “A” with a capacity of 50 tons per hour utilizes forged steel grinding balls costing P12,
Mark 2.00 out of 000 per ton, which have a wear rate of 100 grams per ton cement milled. Another cement mill “B” of the same
2.00
capacity uses high chrome steel grinding balls costing P50, 000 per ton with wear rate of 20 grams per ton
cement milled. Determine the more economical grinding mill, considering other factors to be the same.

For Mill A:

Select one:
a. P65/hour

b. P50/hour

c. P60/hour 

d. P55/hour

Your answer is correct.

Question 5 Refer to the paragraph below to answer the question


Correct
An executive receives an annual salary of P600, 000 and his secretary a salary of P180, 000. A certain task can be
Mark 2.00 out of
performed by the executive working alone in four hours. If he delegates the task to his secretary wit will require
2.00
him 30 minutes to explain the work a d another 45 minutes to check the work. Due to the unfamiliarity of the
secretary to do the task, it takes her an additional time of 6 hours after being instructed. Considering salary cost
only, determine the cost of performing the task by each method, if the secretary works 2400 hours a year and the
executive 3000 hours a year.
Cost of performing the task:Secretary working with executive

Select one:
a. P737.50 

b. P837.50

c. P937.50

d. P637.50

Your answer is correct.

◄ Lesson 1: Introduction Jump to... Lesson 2: Present Economy Studies ►


https://blended.amaesonline.com/abl-trimestral/mod/quiz/review.php?attempt=1272488&cmid=34083 2/3
3/19/2020 Quiz 001: Attempt review

https://blended.amaesonline.com/abl-trimestral/mod/quiz/review.php?attempt=1272488&cmid=34083 3/3

You might also like