The cost of the direct material lost in each reject is P20.00. If a certain total number of units is to be produced,
find which method is more economical.
Method A:
Select one:
a. Per unit cost =18.25
Method B calls for a crew of two men each costing P35.00 per hour and should result in the production of eight
units per hour of which one will be reject.
The cost of the direct material lost in each reject is P20.00. If a certain total number of units is to be produced,
find which method is more economical.
Method B:
Select one:
a. Per unit cost = 12.86
https://blended.amaesonline.com/abl-trimestral/mod/quiz/review.php?attempt=1272488&cmid=34083 1/3
3/19/2020 Quiz 001: Attempt review
Select one:
a. P65/hour
b. P50/hour
c. P55/hour
d. P60/hour
For Mill A:
Select one:
a. P65/hour
b. P50/hour
c. P60/hour
d. P55/hour
Select one:
a. P737.50
b. P837.50
c. P937.50
d. P637.50