Project Detailing
Project Detailing
Project Detailing
5 Utility
6 Instrumentation
Load Cell for 04 Nos. 1 Kl SS Batch Tanks, Load Cell Installation & Calibration, Load Cell Weighing system, On-Off Valve,Cabling, Processor, Automation &
Commisioning
7 Electrical
Cabling + Terminations & Load Cell Connection
8 Miscellaneous
Structral work for lifting Existing Batch Tank for Load Cell placing 0.2 lac
Existing Piping Dismantling, Refabrication & fitting for Load Cell installation 0.1 lac
Total Budgatory Cost
Considering 8% contingency
Grand Total
Page 1
Capex
Existing Facalities:-
Addition of Solvents, Stabliziers, Emulsifiers & LC into Formulation Vessels via Mass Flow meter.
Emulsifier excat quantity addition via Mass Flow Meter isn't effective & hence quality suffers.
Presently no weighing systems e.g Load cell provided in Emulsifier/Stabilizer Batch Tanks & Formulation Vessels.
Proposed Facalities:-
Load Cell Installation in 04 Nos. 1 Kl Batch Tank for excat quantity addition of Emulsifier & Stabilizer into vessels.
Automation & PLC Updations for Emulsifier handling system.
Benifits:-
Excat quantity addition of emulsifiers & stabilizers in formulation vessles after Load Cell Installation in Batch Tank.
Page 2
Capex
Page 3
Capex
Page 4
Piping MTO
SS-316/M.S Material Cost 980 780 3700 2500 5800 4500 85 130 105 70 140 90 42 25 1100 3000 3600
Total Material Cost 14700 117000 14800 30000 46400 54000 850 13000 1575 7000 0 9000 0 0 16500 48000 28800
Fitting Cost 224 168 114 85 114 85 74 55 168 126 168 126 85 85 85 114
Total Fitting Cost 3360 25200 456 1020 912 1020 16800 12600 16800 1890 0 0 1360 912
Page 5
Piping MTO
3500 500
250 390
Page 6