Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

TITAN-IKEDA VS PRIMETOWN

In 1992, respondent Primetown Property Group, ISSUE: Whether or not CA erred in giving weight to ITI's report
Inc. Entered into a contract with petitioner Titan- because the project evaluation was commissioned only by
Ikeda Construction and Development Corporation respondent, in disregard of industry practice (without its consent).
for the structural works of its 32-storey Makati
Prime Tower (MPT) WN TITAN INCURRED DELAY.NO

This case involved two contracts entered into by ________________________________________________________


the parties with regard to the project. _

The parties first entered into a contract for a piece A contract is a meeting of the minds between two persons whereby
of work when they executed the supplemental one binds himself, with respect to the other, to give something or to
agreement. Petitioner as contractor bound itself to render some service.
execute the project for respondent, the
owner/developer, in consideration of a price certain Respondent never sent petitioner a written demand asking it to
(P130,000,000). accelerate work on the project and reduce, if not eliminate, slippage
(as stated in their Article XIV.DELAYS AND ABANDONMENT of their
The supplemental agreement was reciprocal in contract)
nature because the obligation of respondent to pay
the entire contract price depended on the If delay had truly been the reason why respondent took over the
obligation of petitioner to complete the project project, it would have sent a written demand as required by the
(and vice versa). construction contract. Moreover, according to the October 12, 1995
letter-agreement, respondent took over the project for the sole
Thereafter, the parties entered into a second reason that such move was part of its (respondent's) long-term plan.
contract. They agreed to extinguish the
supplemental agreement as evidenced by the Respondent, on the other hand, relied on ITI's September 7, 1995
October 12, 1995 letter-agreement which was duly report. The construction contract named GEMM, not ITI, as
acknowledged by their respective representatives. construction manager. Because petitioner did not consent to the
change of the designated construction manager, ITI's September 7,
Despite ongoing negotiations, respondent did not 1995 report could not bind it.
obtain petitioner’s consent in hiring ITI as the
project’s construction manager. Neither did it Issue of delay. Mora or delay is the failure to perform the obligation
inform petitioner of ITI’s September 7, 1995 report. in due time because of dolo (malice) or culpa (negligence). A debtor is
deemed to have violated his obligation to the creditor from the time
On October 12, 1995, petitioner sought to confirm the latter makes a demand. Once the creditor makes a demand, the
respondent's plan to take over the project. Its letter debtor incurs mora or delay.
stated:
Because the parties agreed to extinguish the supplemental
....to take over the construction supervision of the agreement, they were no longer required to fully perform their
balance of the project from [petitioner's] respective obligations. Petitioner was relieved of its obligation to
engineering staff and complete the same by complete the project while respondent was freed of its obligation to
December 31, 1995 as promised by [petitioner's] pay the entire contract price. However, respondent, by executing the
engineer. June 30, 1994 deed of absolute sale, was deemed to have paid
P112,416,716.88. Nevertheless, because petitioner applied part of
This mutual agreement on the take over should not what it received to respondent’s outstanding liabilities, it admitted
be misconstrued in any other way except that the overpayment.
take over is part of the long range plan of
[respondent] that [petitioner], in the spirit of Because petitioner acknowledged that it had been overpaid, it was
cooperation, agreed to hand over the construction obliged to return the excess to respondent. Embodying the principle
supervision to [respondent] as requested. (Prime of solutio indebiti,
Tower na lang daw ang magsupervise from then on
and that Titan Ikeda willingly surrendered that In this instance, respondent paid part of the contract price under the
supervision) assumption that petitioner would complete the project within the
stipulated period. However, after the supplemental agreement was
However records showed that respondent extinguished, petitioner ceased working on the project. Therefore,
Primetower did not merely take over the the compensation petitioner received in excess of the cost of its
supervision of the project but took full control actual accomplishment as of October 12, 1995 was never due. The
thereof. condominium units and parking slots corresponding to the said
excess were mistakenly delivered by respondent and were therefore
not due to petitioner.

Stated simply, respondent erroneously delivered excess units to


petitioner and the latter, pursuant to Article 2154, was obliged to the
return them to respondent.

One who receives payment by mistake in good faith is, as a general


rule, only liable to return the thing delivered. If he benefited
therefrom, he is also liable for the impairment or loss of the thing
delivered and its accessories and accessions.60 If he sold the thing
delivered, he should either deliver the proceeds of the sale or assign
the action to collect to the other party.

Case remanded to identify the ff:

The RTC must first determine the percentage of the project petitioner
actually completed and its proportionate cost. This will be the
amount due to petitioner.

We hold that petitioner did not incur delay

The supplemental agreement was a contract for a stipulated price. In


such contracts, the recovery of additional costs (incurred due to
changes in plans or specifications) is governed by Article 1724 of the
Civil Code.

Article 1724. The contractor who undertakes to build a structure or


any other work for a stipulated price, in conformity with plans and
specifications agreed upon with the landowner, can neither withdraw
from the contract nor demand an increase in the price on account of
higher cost of labor or materials, save when there has been a change
in plans and specifications, provided:

1. such change has been authorized by the proprietor in writing; and


2. the additional price to be paid to the contractor has been
determined in writing by both parties.

Both must concur to recover damages. Petitioner submitted neither


one.Other than bare assertions, petitioner submitted no proof that
the rental pool was in fact able to lease out the units.

Decision of CA set aside.

You might also like