Plain cement concrete 1:3:6 mix with crushed stone

aggregate 40 mm nominal size mechanically mixed, placed


in foundation and compacted by vibration including curing for
14 days.

Mate day 0.640 200.00 128.00 L-12


Mason day 1.000 250.00 250.00 L-11
Mazdoor day 15.000 150.00 2250.00 L-13

40mm Aggregate at site cum 13.800 849.60 11724.48 M-055


Sand at site cum 6.900 562.46 3880.97 M-005
Cement at site tonne 3.300 5912.39 19510.89 M-081
Cost of water KL 18.000 55.00 990.00 M-189

Concrete mixer0.4/ 0.28 cum hour 6.000 240.00 1440.00 P&M-009


Generator set 33 KVA hour 6.000 370.00 2220.00 P&M-079
Water tanker6 KL capacity hour 3.000 472.00 1416.00 P&M-060
4381.03
4819.14
Cost for 15 cum = a+b+c+d+e 53010.51
3534.03

Vibrator is a part of minor T & P which is already included in


overhead charges of the contractor.

Page no - 298
Cement tonne 4.13 5912.39 24418.17 M-081
Coarse sand cum 6.75 562.46 3796.61 M-005
40 mm Aggregate cum 8.10 849.60 6881.76 M-055
20 mm Aggregate cum 4.05 969.60 3926.88 M-053
10 mm Aggregate cum 1.35 1239.60 1673.46 M-051

Mate day 0.86 200.00 172.00 L-12


Mason day 1.50 250.00 375.00 L-11
Mazdoor day 20.00 150.00 3000.00 L-13

Concrete mixer (cap. 0.40/0.28 cum) hour 6.00 240.00 1440.00 P&M-009
Generator 63 KVA hour 6.00 384.00 2304.00 P&M-079

@ 4 per cent on cost of concrete i.e. cost 1919.52


of material, labour and machinery
9981.48
5988.89
Cost for 15 cum = a+b+c+d+e+f 65877.76
4391.85

Page no - 299