GOVERNMENT OF TAMILNADU

RURAL DEVELOPMENT DEPARTMENT

TIRUNELVELI DISTRICT

NAME OF BLOCK : Kadayam

NAME OF PANCHAYAT : Servaikaranpatti

Improvements to VannanKulam MI Tank in


NAME OF WORK :
Servaikaranpatti Panchayat

KUDIMARAMATHU – PARTICIPATORY
NAME OF SCHEME : PROGRAMME FOR REJUVENATION OF MI
TANKS IN RURAL AREAS 2019-20

ESTIMATE AMOUNT : Rs. 500000.00


SPECIFICATION REPORT

Improvements to VannanKulam MI Tank in Servaikaranpatti Panchayat

ESTIMATE AMOUNT (Rs.): 500000.00


INTRODUCTION:
On 20.07.2019, The Hon'ble Chief Minister made an announcement under Rule 110 on the floor of
Legislative Assembly that 5000 MI Tanks and 25,000 Ponds and Ooranies will be improved / modernised
with an allocation of Rs.500 Crores under Kudimaramathu – Participatory Programme For Rejuvenation
of MI Tanks 2019-20.
OBJECTIVES OF WORK

The main objective of the programme is to ensure comprehensive rehabilitation of minor irrigation tanks
which are under the control of Panchayat Union, so as to restore the tanks to their full capacity, increase
ground water recharge, prevent surplus runoff and breaches in the water bodies and also to regulate the
storage of water for drinking and agricultural purpose, thereby ensuring sustainable drinking water
supply and increasing the crop productivity and area of irrigation.

To take up rejuvenation of water bodies by engaging machineries through Panchayat Unions and
Village Panchayats and involving community/Ayacutdars on voluntary basis.

To increase and restore the rural water bodies like Minor Irrigation tanks, Ponds and Qoranies to their
full capacity and to recharge the ground water.

To give the excess excavated clay, silt, savudu and gravel free of cost to the local farmers for agriculture,
public for domestic purposes and to artisans for pottery purposes as envisaged in G.O.No.50, Industries
(MMC1) Department, Dated: 27.4.2017.

To sensitize the Village community/Ayacutdars towards sustained community action for the operation
and maintenance of water bodies in future and further development of the potential of the natural
resources in rural areas.

The loss of precious rain water by flooding to sea will be minimized to a greater extent.

The additional storage of water in the tanks can be utilized for the drinking water ponds in the village
which will solve the drinking water problems of the entire rural areas in additions to the livestocks.
Due to the additional storage of water, the ground water potential of the irrigation tanks will get good
recharge of water and the additional yield of water can be utilized for irrigation as well as for drinking.
Impounding of water in additional will improve the quality of water in the subsequent years.

The scope of work includes selection and prioritisation of MI tanks, preparation of detailed project report
and implementation of the comprehensive rehabilation of the MI tanks.
SCOPE OF WORK

The comprehensive rehabilitation of MI tanks shall consist of assessing the original capacity and
hydraulic standards of the tank and to list out the items of works to be carried out to restore the tank to
its original status. The following components are envisaged as part of the rehabilitation of the MI tanks:

a) Desilting and Deepening of the water spread area using earth moving machinery including removal of
heavy jungle.

b) Strengthening and Consolidation of the bund using the excavated Earth and restore the bund to the
required cross section including provision of protective works, wherever required.

c)Construction of Tank appurtenances like surplus weir, Sluice and Retaining wall etc., complete under
MGNREGS / PUGF.
IMPLEMENTATION METHODOLOGY
The Government vide G.O. Ms No.12, Public Works (W1) Department Dated: 21.01.2017 has permitted
the Public Works department to take up Restoration of Water Bodies with Participatory approach
through implementation of Kudimaramathu. The farmer's organizations or farmers councils or
ayacutdars or user associations. The order also stipulates that 10% of the estimate cost should come as
contribution from the user associations or ayacutdars in the form of either labour or material or cash
contribution.

Since there is no existing farmers association / Ayacutdar association for MI tanks vested with Panchayat
Unions, Ayacutdar association shall be formed on voluntary basis for each Minor Irrigation Tank in rural
areas so as to encourage the Ayacutdars to involve in Kudimaramathu works. Any Ayacutdar
benefiting from the MI tank concerned can be part of the Ayacutdar association. The list of Ayacutdars
will be obtained from Revenue authorities. Wide publicity in the form of Tom Tom / audio
announcements shall be done in the Village Panchayats about the Kudimaramathu Programme. Special
Ayacutdar meeting shall be convened in Village Panchayat area for each MI tank, in order to mobilize the
public and involve them in Kudimaramathu works in the MI tank. In the case of MI Tanks, the desilting
work will be taken up through the concerned Panchayat Union involving the Ayacutdars and local public
on voluntary basis.

The 10% contribution in the form of labour from the farmers/ayacutdars/users association/Public may
be obtained. The labour contribution shall be in the form of labour required for works like sectioning of
bunds, benching of bunds etc,

LOCATION:
This Vannakulam of Servaikaranpatti Village is located in Kadayam Panchayat union in Tirunelveli
District. This tank is located at East of Chekkdiyoor and Purankattanpuliyoor Habitations.

District: Tirunelveli

Taluk: Ambasamudram

Block: Kadayam

Village: Servaikaranpatti

PRESENT CONDITION OF EXISTING FEATURES:

Tank Bund:

This tank having bund of length 955m and this tank bund is found eroded and below standareds for its
entire length and the same has to be strengthened to avoid possible breaches in the bund during the
monsoon. The top, front slopes and rear slopes are lost their original profile.

Sluices:

This tank is having 1Sluice as detailed below:

Location (LS) 437.500m

Sill Level in mts 98.14

Ayacut in Hectares 15.76 Acres

The sluice is fully Damaged condition. Reconstruction may be done.


Surplus weir:

This tank is having 1weir as detailed below:

Location (LS) 258m

Length -

There has no permanent structure for Weir. Hence new costruction may be done.

PROPOSALS:
(a)Tank Bund:

It is proposed to desilt the tank bed and to strengthen the tank bund for improving its capacity. The
quantity of earth required for strengthening of the tank bund to the required standareds has been
arrived by taking levels and level charts. Since the quantum of earth to be desilted will be of very huge
quantity, it is proposed to utilize heavy earth moving machineries and tippers for formation of bund.
Proper compaction of earthwork will be done through watering to OMC (Optimum Moisture Content ) and
compaction of each layer to 95% proctor density through deployement of 8-10 Tonne power roller or
vibratory power roller. The provision of desilting will also include removal of Juliflora jungle and
undersirable vegetation in the tank bund. The tank bund will be strengthened and standardized to the
standards by providing front slope 2 : 1, Rear Slopes 2:1, and top width:3.00m.

In addition to that the following provisions are in this estimate.

Provision for removal of Light Jungle and Juliflora jungle with uprooting in Water spread area

Provision for Labour Welfare Fund @ 1%

Provision for GST @ 5%

Provision for Name Board

Provision for Photographic Charges

Provision for Contingencies

This Estimate is prepared based on the Current Schedule of Rates 2019 -2020

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
CHECK SLIP

1) Name of District : Tirunelveli

2) Name of Block : Kadayam

3) Name of Panchayat : Servaikaranpatti

Improvements to VannanKulam MI Tank in


4) Name of the Work :
Servaikaranpatti Panchayat

5) Estimate Amount : Rs. 1.00 Lakhs

KUDIMARAMATHU – PARTICIPATORY PROGRAMME


6) Name of Scheme : FOR REJUVENATION OF MI TANKS IN RURAL AREAS
2019-20

7) Year of Scheme : 2019-2020

District Collector / Chairman DRDA Tirunelveli


8) Administrative Sanction details :
Proceedings Roc No Dated

9) Technical Sanction No & Date : AEE (RD) Reg DR No. Dated

10) Survey No & Extent Area : Survey No.137 - 04.55.00 Ha

Survey No.130 - 01.04.00 Ha

11) Whether Route map is enclosed : Yes

12) Whether FM sketch is enclosed : Yes

13) Components of works taken up

a) Clearing the light jungle

b) Bund strengthening

c) Tank Deepening

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
HYDRAULIC PARTICULARS OF THE M.I TANK

Improvements to VannanKulam MI Tank in Servaikaranpatti Panchayat

Sl.No Particulars required Details to be furnished

Proposed as
Proposed as
Existing (m) per Drawing
per Memoir (ft)
(m)

1) Full Tank level (FTL) 100.000 - 100.000

1a) Top of Bund (TBL) - - 101.600

2) Maximum water level (MWL) - - 100.600

3) Weir No Permanent Structure

a) Number of weirs 1 - -

b) Their position 258 M - -

c) crest level (FTL) - - -

d) present condition - - -

4) Sluice
a) Number of sluices 1 - -

b) Their position (Chainage) 437.5m - -

Head & Wing


c) Type - -
wall type

d) Sill level 98.14 m - -

e) Present condition Fully Damaged - -

5) Bund Details
a) The length of the bund including surplus weir 955 m - 955 m
b) Top width 2.10m (avg) - 3.00m
c) Downstream slope 2:1 - 2:1
d) Upstream slope 2:1 - 2:1

e) The exact chainage of bund where revetment is


- - -
available

6) Inlet Channel

a) The length and size of Inlet channels available - - -


7) Outlet Channel

a) The length and size of outlet channels available - - -

8) Annual Rainfall

The data of Annual Rainfall should be collected Yes Yes Yes

9) Catchment area

a) The free / Combined catchments based on topo sheet Yes Yes Yes

ASSISTANT EXECUTIVE
ENGINEER(R.D) ASSISTANT ENGINEER (RD)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
MI TANK - MEMOIR

1 Name of the MI Tank : Vannan Kulam


2 Maintained by : Panchayat Union
3 Name of the District : Tirunelveli
4 Name of Taluk : Ambasamudram
5 Name of Block : Kadayam
6 Name of Panchayat : Servaikaranpatti
7 Latitude : 8.8273416 N
8 Longitude : 77.3812117 E
9 Registered Ayacut : 15.76 Acres
10 Catchment area :
Free catchment area :
Combined catchment :
11 Water spread area : 44720 sqm
12 Capacity of tank : 37430.64 cum
13 Number of fillings : 2
14 Water yield from :
Catchment :
Supply channel :

Total :

15 Type of MI Tank : Non System tank

16 Details of Supply Channel :

Length : 300m

Bed width : 3m

Depth of flow : 0.9m

17 Standards of MI Tank :

F.T.L : 100 m

M.W.L : 100.6 m

T.B.L : 101.6 m

18 Bund Details :

Length : 955 m

Width : 2.1 m

Side slope front : 2:1

Side slope rear : 2:1

Retaining wall :
Bathing ghat : Nil

19 Sluice details :

Sluice no : 1

L.S : 437.5m
Sill level : 98.14
Size of vent : 0.1X0.1
Size of Plug : -
Ayacut : 15.76 Acres
20 Details of Surplus Weir : NIL
Weir no :
Chainage :
Length :
Crest level :
21 Name of Upper tank : -
22 Name of Lower down tank : -

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI
PANCHAYAT UNION
SUBDIVISION
CHERANMAHADEVI
KADAYAM
CERTIFICATE

Improvements to VannanKulam MI Tank in


Name of the Work :
Servaikaranpatti Panchayat

1) Certified that this work has not been taken up for the past one year for Deepening / Desilting.

2) Certified that this work has been taken up in Govt/Local Body lands.

3) Certified that this work has not been taken up in any Individual lands.

4) Certified that this work is useful for all village public and not to any individual.

5) Certified that this estimate has been prepared as per PWD schedule of rates Proceedings
No.HDO / Sr. DO-2 / SSR 2019-20 / 19020 / 2018-1, dated 17.06.2019

6) Certified that this estimate is technically scrutinized and countersigned by the concern AE
(RD) / AEE (RD).

7) Certified that the photos enclosed for this work has been actually taken in the proposed site for
this work.

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI SUBDIVISION PANCHAYAT UNION
CHERANMAHADEVI KADAYAM
ABSTRACT
Name of the Work :

Improvements to VannanKulam MI Tank in Servaikaranpatti Panchayat

Sl.
No. Description of Work Qty Unit Rate Per Amount

Clearing Light Jungle without alignment and


uprooting of wild vegetation, bushes, shrubs,
1 saplings and trees of girth upto 300mm for the 5460.00 sqm 3.90 sqm 21294.00
strengthening of the bund and the ground shall be
left in a perfectly clean condition etc., complete.

Clearing Juliflora Jungle with uprooting of wild


vegetation, bushes, shrubs, saplings and trees of
2 girth upto 300mm for the strengthening of the bund 7200.00 sqm 5.90 sqm 42480.00
and the ground shall be left in a perfectly clean
condition etc., complete.

Earth work in all Soils except hard rock requiring


blasting and conveying for formation of bund with
3 lead of 0 to 100m deploying earth moving
machinery and tippers including benching, formation
of bunds, breaking clods, sectioning etc., complete.

Volume of Earth Work in Existing Bund (including


a) 5268.64 cum 71.05 cum 374337.00
Consolidation using Power Roller)

Volume of Earth Work in New Bund (No


b) 252.00 cum 45.55 cum 11479.00
consolidation)

4 Provision for Nameboard arrangements LS LS 4000.00

5 Provision for Photographic charges LS LS 500.00

6 Provision for DPR Preparation LS LS 18000.00

7 Provision for LWF @ 1% LS LS 5000.00

8 Provision for GST @ 5% LS LS 22705.00

9 Contingencies and other unforeseen charges LS LS 205.00

TOTAL 500000.00

ASSISTANT ENGINEER
(RD)
PANCHAYAT UNION
KADAYAM
ASSISTANT EXECUTIVE
ENGINEER(R.D)
CHERANMAHADEVI SUBDIVISION
CHERANMAHADEVI
DETAILED ESTIMATE
Improvements to VannanKulam MI Tank in
Name of the Work :
Servaikaranpatti Panchayat
Sl. Measurements
Description of work No. Contents
No. L B D or H
Clearing Light Jungle without alignment and uprooting of wild vegetation, bushes, shrubs, saplings and trees
1 of girth upto 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean
condition etc., complete.

Water Spread Area 1 X 1 107.00 80.00 - 8560.00

Inlet Channel 1 X 2 60.00 3.00 - 360.00

Outlet Channel 1 X 1 60.00 3.00 - 180.00

Total quantity = 9100.00

Deduct (40% Voids) -3640.00

Net quantity = 5460.00

Clearing Juliflora Jungle with uprooting of wild vegetation, bushes, shrubs, saplings and trees of girth upto
2 300mm for the strengthening of the bund and the ground shall be left in a perfectly clean condition etc.,
complete.

Water Spread Area 1 X 1 120.00 100.00 - 12000.00

Total quantity = 12000.00

Deduct (40% Voids) -4800.00

Net quantity = 7200.00


Earth work in all Soils except hard rock requiring blasting and conveying for formation of bund with lead of 0
3 to 100m deploying earth moving machinery and tippers including benching, formation of bunds, breaking
clods, sectioning etc., complete.
a) Volume of Earth Work in Existing Bund (including Consolidation using Power Roller)
As per Calculation Sheet - Net
1 X 1 5268.64 5268.64
Filling Qty

Total Cutting quantity = 5268.64


b Volume of Earth Work For Dead Storage Trenches (No consolidation)
Sunken Ponds 1 X 3 20.00 8.00 0.30 144.00

Inlet Channel 1 X 2 60.00 3.00 0.20 72.00

Outlet Channel 1 X 1 60.00 3.00 0.20 36.00

Total Cutting quantity = 252.00

4 Provision for Nameboard arrangements LS

5 Provision for Photographic charges LS

6 Provision for DPR Preparation LS


Sl. Measurements
Description of work No. Contents
No. L B D or H

7 Provision for LWF @ 1% LS

8 Provision for GST @ 5% LS

9 Contingencies and other unforeseen charges LS

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI SUBDIVISION PANCHAYAT UNION
CHERANMAHADEVI KADAYAM
DATA SHEET

SL NO DESCRIPTION OF ITEMS RATE PER

Clearing the Heavy jungle [PWD SOR 2019-20, Sl No. 1(1),


1 5.20 sqm
Page-24]

Clearing the Light jungle [PWD SOR 2019-20, Sl No. 2(2),


2 3.90 sqm
Page-24]

Clearing the Scrub jungle [PWD SOR 2019-20, Sl No. 3(3),


3 3.60 sqm
Page-24]

Cleaning the Juliflora jungle with Uprooting [PWD SOR 2019-


4 5.90 sqm
20, Sl No. 7(9 C), Page-24]

Earth work in all Soils except hard rock requiring blasting and
conveying for formation of bund with lead of 0 to 100m
5 deploying earth moving machinery and tippers including 45.55 cum
benching, formation of bunds, breaking clods, sectioning etc.,
complete. PWD SOR 2019-20, Sl No. 86(1), Page-29.

Add to Relevant TNDSS, Rates for New Tank Bunds and


closing breaches for extra watering and consolidation by
6 25.50 cum
Power Roller including Hire charges etc., complete. PWD SOR
2019-20, Sl No. 69(79 B), Page-27.

Benching Old Embankment Slopes 45cm X 45cm etc.,


7 2.80 m
complete. PWD SOR 2019-20, Sl No. 72(80), Page-27.

ASSISTANT EXECUTIVE ASSISTANT ENGINEER


ENGINEER(R.D) (RD)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
CAPACITY CALCULATION

Mean Area
Cumulative
Sl.No Contour Area (Sqm) [A1 + A2 +√(A1 x Depth (m) Capacity (Cum)
Capacity (Cum)
A2)]/3 (Sqm)

1 100.000 36137.914 - - - 0.00

2 99.900 34654.376 35393.55 0.10 3539.35 3539.35

3 99.600 30451.663 32530.39 0.30 9759.12 13298.47

4 99.300 22350.791 26297.04 0.30 7889.11 21187.58

5 99.000 14682.382 18382.81 0.30 5514.84 26702.42

6 98.700 5359.749 9637.70 0.30 2891.31 29593.73

7 98.400 2759.055 3988.10 0.30 1196.43 30790.16

8 98.100 1333.424 2003.52 0.30 601.06 31391.22

9 97.800 151.181 644.53 0.30 193.36 31584.58

Original Capacity 37430.64 Cum

Present Capacity 31584.58 Cum

Balance to be
5846.06 Cum
Desilted

ASSISTANT ENGINEER
ASSISTANT EXECUTIVE (RD)
ENGINEER(R.D) PANCHAYAT UNION
CHERANMAHADEVI KADAYAM
SUBDIVISION
CHERANMAHADEVI
CAPACITY OF TANK

Area of tank = 55900.00 sqm

Water Spread area (excluding


= 44720.00 sqm
Bund ie 80% of tank area) (A)

Height of water Storage(H) = 1.86 m

Original Capacity of tank = 0.45 AH

= 0.45x44720x1.86

= 37430.64 Cum

ASSISTANT EXECUTIVE ASSISTANT


ENGINEER(R.D) ENGINEER (RD)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
Page 17 of 42

Cutting / Filling Area - Calculation


VANNANKULAM
Difference Avg Difference Area
Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 0
1 -4.531 100.834 100.834 0.000 0.000 - - - - -
2 -4.500 100.850 100.840 0.010 0.000 0.005 0.000 0.031 0.000 0.000
3 -3.000 101.600 101.174 0.426 0.000 0.218 0.000 1.500 0.327 0.000
4 -1.500 101.600 101.286 0.314 0.000 0.370 0.000 1.500 0.555 0.000
5 0.000 101.600 101.241 0.359 0.000 0.336 0.000 1.500 0.504 0.000
6 1.500 101.600 100.998 0.602 0.000 0.480 0.000 1.500 0.720 0.000
7 3.000 101.600 100.850 0.750 0.000 0.676 0.000 1.500 1.014 0.000
8 3.079 101.561 100.826 0.735 0.000 0.743 0.000 0.079 0.059 0.000
9 3.427 101.387 100.877 0.510 0.000 0.623 0.000 0.348 0.217 0.000
10 4.500 100.850 100.767 0.083 0.000 0.297 0.000 1.073 0.319 0.000
11 4.682 100.759 100.759 0.000 0.000 0.041 0.000 0.182 0.007 0.000
3.722 0.000

Section: 30
1 -4.697 100.752 100.752 0.000 0.000 - - - - -
2 -4.523 100.839 100.796 0.043 0.000 0.021 0.000 0.174 0.004 0.000
3 -3.023 101.589 100.840 0.749 0.000 0.396 0.000 1.500 0.594 0.000
4 -3.000 101.600 100.841 0.759 0.000 0.754 0.000 0.023 0.017 0.000
5 -1.523 101.600 100.929 0.671 0.000 0.715 0.000 1.477 1.056 0.000
6 0.000 101.600 101.063 0.537 0.000 0.604 0.000 1.523 0.920 0.000
7 1.477 101.600 101.219 0.381 0.000 0.459 0.000 1.477 0.678 0.000
8 2.977 101.600 101.063 0.537 0.000 0.459 0.000 1.500 0.689 0.000
9 3.000 101.600 101.065 0.535 0.000 0.536 0.000 0.023 0.012 0.000
10 3.941 101.130 101.130 0.000 0.000 0.267 0.000 0.941 0.251 0.000
4.221 0.000
Page 18 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 60
1 -7.366 99.417 99.417 0.000 0.000 - - - - -
2 -6.000 100.100 99.417 0.683 0.000 0.341 0.000 1.366 0.466 0.000
3 -4.500 100.850 100.416 0.434 0.000 0.558 0.000 1.500 0.837 0.000
4 -3.000 101.600 100.721 0.879 0.000 0.656 0.000 1.500 0.984 0.000
5 -1.500 101.600 101.026 0.574 0.000 0.726 0.000 1.500 1.089 0.000
6 0.000 101.600 100.998 0.602 0.000 0.588 0.000 1.500 0.882 0.000
7 1.500 101.600 101.026 0.574 0.000 0.588 0.000 1.500 0.882 0.000
8 3.000 101.600 100.998 0.602 0.000 0.588 0.000 1.500 0.882 0.000
9 4.385 100.908 100.908 0.000 0.000 0.301 0.000 1.385 0.417 0.000
6.439 0.000

Section: 90
1 -5.409 100.395 100.395 0.000 0.000 - - - - -
2 -4.500 100.850 100.636 0.214 0.000 0.107 0.000 0.909 0.097 0.000
3 -3.000 101.600 100.934 0.666 0.000 0.440 0.000 1.500 0.660 0.000
4 -1.500 101.600 101.207 0.393 0.000 0.529 0.000 1.500 0.794 0.000
5 0.000 101.600 101.334 0.266 0.000 0.329 0.000 1.500 0.494 0.000
6 1.500 101.600 101.334 0.266 0.000 0.266 0.000 1.500 0.399 0.000
7 3.000 101.600 101.334 0.266 0.000 0.266 0.000 1.500 0.399 0.000
8 3.560 101.320 101.320 0.000 0.000 0.133 0.000 0.560 0.074 0.000
2.917 0.000
Page 19 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 120
1 -4.812 100.694 100.694 0.000 0.000 - - - - -
2 -4.539 100.831 100.735 0.096 0.000 0.048 0.000 0.273 0.013 0.000
3 -3.039 101.581 100.835 0.746 0.000 0.421 0.000 1.500 0.632 0.000
4 -3.000 101.600 100.839 0.761 0.000 0.754 0.000 0.039 0.029 0.000
5 -1.539 101.600 101.008 0.592 0.000 0.676 0.000 1.461 0.988 0.000
6 0.000 101.600 101.155 0.445 0.000 0.518 0.000 1.539 0.797 0.000
7 1.461 101.600 100.959 0.641 0.000 0.543 0.000 1.461 0.793 0.000
8 2.961 101.600 100.757 0.843 0.000 0.742 0.000 1.500 1.113 0.000
9 3.000 101.600 100.752 0.848 0.000 0.845 0.000 0.039 0.033 0.000
10 4.461 100.870 100.555 0.315 0.000 0.581 0.000 1.461 0.849 0.000
11 5.323 100.439 100.439 0.000 0.000 0.157 0.000 0.862 0.135 0.000
5.382 0.000

Section: 150
1 -4.675 100.762 100.762 0.000 0.000 - - - - -
2 -4.510 100.845 100.778 0.067 0.000 0.033 0.000 0.165 0.005 0.000
3 -3.009 101.595 100.884 0.711 0.000 0.389 0.000 1.501 0.584 0.000
4 -3.000 101.600 100.884 0.716 0.000 0.713 0.000 0.009 0.006 0.000
5 -1.509 101.600 100.859 0.741 0.000 0.728 0.000 1.491 1.085 0.000
6 0.000 101.600 100.909 0.691 0.000 0.716 0.000 1.509 1.080 0.000
7 1.491 101.600 100.760 0.840 0.000 0.765 0.000 1.491 1.141 0.000
8 2.991 101.600 100.636 0.964 0.000 0.902 0.000 1.500 1.353 0.000
9 3.000 101.600 100.635 0.965 0.000 0.964 0.000 0.009 0.009 0.000
10 4.491 100.855 100.462 0.393 0.000 0.679 0.000 1.491 1.012 0.000
11 5.991 100.105 99.992 0.113 0.000 0.253 0.000 1.500 0.380 0.000
12 6.217 99.992 99.992 0.000 0.000 0.056 0.000 0.226 0.013 0.000
6.668 0.000
Page 20 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 180
1 -4.443 100.878 100.878 0.000 0.000 - - - - -
2 -3.000 101.600 100.785 0.815 0.000 0.407 0.000 1.443 0.587 0.000
3 -1.500 101.600 100.785 0.815 0.000 0.815 0.000 1.500 1.223 0.000
4 0.000 101.600 100.760 0.840 0.000 0.827 0.000 1.500 1.241 0.000
5 1.500 101.600 100.611 0.989 0.000 0.914 0.000 1.500 1.371 0.000
6 3.000 101.600 100.388 1.212 0.000 1.100 0.000 1.500 1.650 0.000
7 4.500 100.850 100.115 0.735 0.000 0.973 0.000 1.500 1.460 0.000
8 6.000 100.100 99.631 0.469 0.000 0.602 0.000 1.500 0.903 0.000
9 6.938 99.631 99.631 0.000 0.000 0.234 0.000 0.938 0.219 0.000
8.654 0.000

Section: 210
1 -5.083 100.558 100.558 0.000 0.000 - - - - -
2 -4.500 100.850 100.505 0.345 0.000 0.172 0.000 0.583 0.100 0.000
3 -3.000 101.600 100.462 1.138 0.000 0.741 0.000 1.500 1.112 0.000
4 -1.500 101.600 100.537 1.063 0.000 1.100 0.000 1.500 1.650 0.000
5 0.000 101.600 100.477 1.123 0.000 1.093 0.000 1.500 1.640 0.000
6 1.500 101.600 100.422 1.178 0.000 1.151 0.000 1.500 1.727 0.000
7 3.000 101.600 100.231 1.369 0.000 1.274 0.000 1.500 1.911 0.000
8 4.500 100.850 100.203 0.647 0.000 1.008 0.000 1.500 1.512 0.000
9 6.000 100.100 99.602 0.498 0.000 0.572 0.000 1.500 0.858 0.000
10 6.996 99.602 99.602 0.000 0.000 0.249 0.000 0.996 0.248 0.000
10.756 0.000
Page 21 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 240
1 -4.943 100.628 100.628 0.000 0.000 - - - - -
2 -4.500 100.850 100.686 0.164 0.000 0.082 0.000 0.443 0.036 0.000
3 -3.000 101.600 100.661 0.939 0.000 0.551 0.000 1.500 0.827 0.000
4 -1.500 101.600 100.636 0.964 0.000 0.951 0.000 1.500 1.427 0.000
5 0.000 101.600 100.661 0.939 0.000 0.951 0.000 1.500 1.427 0.000
6 1.500 101.600 100.487 1.113 0.000 1.026 0.000 1.500 1.539 0.000
7 3.000 101.600 100.413 1.187 0.000 1.150 0.000 1.500 1.725 0.000
8 4.500 100.850 100.363 0.487 0.000 0.837 0.000 1.500 1.256 0.000
9 5.871 100.165 100.165 0.000 0.000 0.243 0.000 1.371 0.333 0.000
8.570 0.000

Section: 270
1 -6.766 99.717 99.717 0.000 0.000 - - - - -
2 -6.000 100.100 99.717 0.383 0.000 0.191 0.000 0.766 0.146 0.000
3 -4.500 100.850 99.942 0.908 0.000 0.645 0.000 1.500 0.968 0.000
4 -3.000 101.600 100.041 1.559 0.000 1.234 0.000 1.500 1.851 0.000
5 -1.500 101.600 100.066 1.534 0.000 1.547 0.000 1.500 2.321 0.000
6 0.000 101.600 100.090 1.510 0.000 1.522 0.000 1.500 2.283 0.000
7 1.500 101.600 100.115 1.485 0.000 1.498 0.000 1.500 2.247 0.000
8 3.000 101.600 100.190 1.410 0.000 1.448 0.000 1.500 2.172 0.000
9 6.252 99.974 99.974 0.000 0.000 0.705 0.000 3.252 2.293 0.000
14.279 0.000
Page 22 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 300
1 -4.329 100.935 100.935 0.000 0.000 - - - - -
2 -3.000 101.600 101.017 0.583 0.000 0.291 0.000 1.329 0.387 0.000
3 -1.500 101.600 101.142 0.458 0.000 0.520 0.000 1.500 0.780 0.000
4 0.000 101.600 101.067 0.533 0.000 0.496 0.000 1.500 0.744 0.000
5 1.500 101.600 101.117 0.483 0.000 0.508 0.000 1.500 0.762 0.000
6 3.000 101.600 100.942 0.658 0.000 0.570 0.000 1.500 0.855 0.000
7 4.384 100.908 100.908 0.000 0.000 0.329 0.000 1.384 0.455 0.000
3.983 0.000

Section: 330
1 -6.034 100.083 100.083 0.000 0.000 - - - - -
2 -6.000 100.100 100.083 0.017 0.000 0.008 0.000 0.034 0.000 0.000
3 -4.500 100.850 100.588 0.262 0.000 0.139 0.000 1.500 0.209 0.000
4 -3.000 101.600 101.033 0.567 0.000 0.414 0.000 1.500 0.621 0.000
5 -2.143 101.600 101.600 0.000 0.000 0.283 0.000 0.857 0.243 0.000
6 -1.500 101.600 102.025 0.000 0.425 0.000 0.213 0.643 0.000 0.137
7 0.000 101.600 101.901 0.000 0.301 0.000 0.363 1.500 0.000 0.545
8 1.500 101.600 101.777 0.000 0.177 0.000 0.239 1.500 0.000 0.359
9 1.940 101.600 101.600 0.000 0.000 0.000 0.089 0.440 0.000 0.039
10 3.000 101.600 101.173 0.427 0.000 0.213 0.000 1.060 0.226 0.000
11 4.500 100.850 100.825 0.025 0.000 0.226 0.000 1.500 0.339 0.000
12 6.000 100.100 99.860 0.240 0.000 0.132 0.000 1.500 0.198 0.000
13 6.480 99.860 99.860 0.000 0.000 0.120 0.000 0.480 0.058 0.000
1.894 1.080
Page 23 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 360
1 -8.194 99.003 99.003 0.000 0.000 - - - - -
2 -6.000 100.100 99.003 1.097 0.000 0.548 0.000 2.194 1.202 0.000
3 -4.500 100.850 99.656 1.194 0.000 1.146 0.000 1.500 1.719 0.000
4 -3.000 101.600 100.039 1.561 0.000 1.377 0.000 1.500 2.066 0.000
5 -1.500 101.600 100.258 1.342 0.000 1.452 0.000 1.500 2.178 0.000
6 0.000 101.600 100.739 0.861 0.000 1.102 0.000 1.500 1.653 0.000
7 1.500 101.600 101.105 0.495 0.000 0.678 0.000 1.500 1.017 0.000
8 3.000 101.600 101.023 0.577 0.000 0.536 0.000 1.500 0.804 0.000
9 4.500 100.850 100.686 0.164 0.000 0.370 0.000 1.500 0.555 0.000
10 6.000 100.100 100.072 0.028 0.000 0.096 0.000 1.500 0.144 0.000
11 6.056 100.072 100.072 0.000 0.000 0.014 0.000 0.056 0.001 0.000
11.337 0.000

Section: 390
1 -6.464 99.868 99.868 0.000 0.000 - - - - -
2 -6.000 100.100 99.868 0.232 0.000 0.116 0.000 0.464 0.054 0.000
3 -4.500 100.850 100.315 0.535 0.000 0.383 0.000 1.500 0.575 0.000
4 -3.000 101.600 100.613 0.987 0.000 0.761 0.000 1.500 1.142 0.000
5 -1.500 101.600 100.914 0.686 0.000 0.836 0.000 1.500 1.254 0.000
6 0.000 101.600 101.153 0.447 0.000 0.566 0.000 1.500 0.849 0.000
7 1.500 101.600 101.023 0.577 0.000 0.512 0.000 1.500 0.768 0.000
8 3.000 101.600 100.847 0.753 0.000 0.665 0.000 1.500 0.998 0.000
9 4.500 100.850 100.553 0.297 0.000 0.525 0.000 1.500 0.788 0.000
10 6.000 100.100 99.118 0.982 0.000 0.639 0.000 1.500 0.959 0.000
11 7.964 99.118 99.118 0.000 0.000 0.491 0.000 1.964 0.964 0.000
8.351 0.000
Page 24 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 420
1 -3.488 101.356 101.356 0.000 0.000 - - - - -
2 -3.000 101.600 101.416 0.184 0.000 0.092 0.000 0.488 0.045 0.000
3 -1.500 101.600 101.450 0.150 0.000 0.167 0.000 1.500 0.251 0.000
4 0.000 101.600 101.413 0.187 0.000 0.168 0.000 1.500 0.252 0.000
5 1.500 101.600 100.996 0.604 0.000 0.395 0.000 1.500 0.593 0.000
6 3.000 101.600 100.641 0.959 0.000 0.781 0.000 1.500 1.172 0.000
7 4.500 100.850 99.930 0.920 0.000 0.939 0.000 1.500 1.409 0.000
8 6.000 100.100 99.090 1.010 0.000 0.965 0.000 1.500 1.448 0.000
9 8.020 99.090 99.090 0.000 0.000 0.505 0.000 2.020 1.020 0.000
6.190 0.000

Section: 450
1 -3.528 101.336 101.336 0.000 0.000 - - - - -
2 -3.000 101.600 101.702 0.000 0.102 0.000 0.051 0.528 0.000 0.027
3 -1.500 101.600 101.803 0.000 0.203 0.000 0.153 1.500 0.000 0.230
4 0.000 101.600 101.680 0.000 0.080 0.000 0.142 1.500 0.000 0.213
5 0.511 101.600 101.600 0.000 0.000 0.000 0.040 0.511 0.000 0.020
6 1.500 101.600 101.445 0.155 0.000 0.078 0.000 0.989 0.077 0.000
7 3.000 101.600 101.241 0.359 0.000 0.257 0.000 1.500 0.386 0.000
8 4.500 100.850 100.339 0.511 0.000 0.435 0.000 1.500 0.653 0.000
9 6.000 100.100 99.730 0.370 0.000 0.440 0.000 1.500 0.660 0.000
10 6.740 99.730 99.730 0.000 0.000 0.185 0.000 0.740 0.137 0.000
1.913 0.490
Page 25 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 480
1 -7.364 99.418 99.418 0.000 0.000 - - - - -
2 -6.000 100.100 99.418 0.682 0.000 0.341 0.000 1.364 0.465 0.000
3 -4.500 100.850 100.272 0.578 0.000 0.630 0.000 1.500 0.945 0.000
4 -3.000 101.600 101.126 0.474 0.000 0.526 0.000 1.500 0.789 0.000
5 -1.633 101.600 101.600 0.000 0.000 0.237 0.000 1.367 0.324 0.000
6 -1.500 101.600 101.646 0.000 0.046 0.000 0.023 0.133 0.000 0.003
7 0.000 101.600 101.721 0.000 0.121 0.000 0.084 1.500 0.000 0.126
8 1.500 101.600 101.766 0.000 0.166 0.000 0.144 1.500 0.000 0.216
9 2.939 101.600 101.600 0.000 0.000 0.000 0.083 1.439 0.000 0.119
10 3.000 101.600 101.593 0.007 0.000 0.003 0.000 0.061 0.000 0.000
11 3.018 101.591 101.591 0.000 0.000 0.003 0.000 0.018 0.000 0.000
2.523 0.464

Section: 510
1 -8.508 98.846 98.846 0.000 0.000 - - - - -
2 -6.000 100.100 98.846 1.254 0.000 0.627 0.000 2.508 1.573 0.000
3 -4.500 100.850 99.837 1.013 0.000 1.134 0.000 1.500 1.701 0.000
4 -3.000 101.600 100.804 0.796 0.000 0.904 0.000 1.500 1.356 0.000
5 -1.500 101.600 101.351 0.249 0.000 0.522 0.000 1.500 0.783 0.000
6 0.000 101.600 101.425 0.175 0.000 0.212 0.000 1.500 0.318 0.000
7 1.500 101.600 101.409 0.191 0.000 0.183 0.000 1.500 0.275 0.000
8 3.000 101.600 101.446 0.154 0.000 0.172 0.000 1.500 0.258 0.000
9 3.362 101.419 101.419 0.000 0.000 0.077 0.000 0.362 0.028 0.000
6.291 0.000
Page 26 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 540
1 -7.544 99.328 99.328 0.000 0.000 - - - - -
2 -6.000 100.100 99.328 0.772 0.000 0.386 0.000 1.544 0.596 0.000
3 -4.500 100.850 99.793 1.057 0.000 0.914 0.000 1.500 1.371 0.000
4 -3.000 101.600 100.340 1.260 0.000 1.158 0.000 1.500 1.737 0.000
5 -1.500 101.600 100.878 0.722 0.000 0.991 0.000 1.500 1.487 0.000
6 0.000 101.600 101.342 0.258 0.000 0.490 0.000 1.500 0.735 0.000
7 1.500 101.600 101.304 0.296 0.000 0.277 0.000 1.500 0.416 0.000
8 3.000 101.600 101.171 0.429 0.000 0.362 0.000 1.500 0.543 0.000
9 4.384 100.908 100.908 0.000 0.000 0.214 0.000 1.384 0.296 0.000
7.181 0.000

Section: 570
1 -7.538 99.331 99.331 0.000 0.000 - - - - -
2 -6.000 100.100 99.331 0.769 0.000 0.384 0.000 1.538 0.591 0.000
3 -4.500 100.850 99.656 1.194 0.000 0.981 0.000 1.500 1.472 0.000
4 -3.000 101.600 100.039 1.561 0.000 1.377 0.000 1.500 2.066 0.000
5 -1.500 101.600 100.149 1.451 0.000 1.506 0.000 1.500 2.259 0.000
6 0.000 101.600 100.231 1.369 0.000 1.410 0.000 1.500 2.115 0.000
7 3.000 101.600 100.231 1.369 0.000 1.369 0.000 3.000 4.107 0.000
8 5.738 100.231 100.231 0.000 0.000 0.685 0.000 2.738 1.876 0.000
14.486 0.000
Page 27 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 600
1 -4.944 100.628 100.628 0.000 0.000 - - - - -
2 -4.500 100.850 100.560 0.290 0.000 0.145 0.000 0.444 0.064 0.000
3 -3.000 101.600 100.785 0.815 0.000 0.552 0.000 1.500 0.828 0.000
4 -1.500 101.600 100.934 0.666 0.000 0.740 0.000 1.500 1.110 0.000
5 0.000 101.600 100.760 0.840 0.000 0.753 0.000 1.500 1.130 0.000
6 1.500 101.600 100.785 0.815 0.000 0.827 0.000 1.500 1.241 0.000
7 3.000 101.600 100.711 0.889 0.000 0.852 0.000 1.500 1.278 0.000
8 4.778 100.711 100.711 0.000 0.000 0.444 0.000 1.778 0.789 0.000
6.440 0.000

Section: 630
1 -4.986 100.607 100.607 0.000 0.000 - - - - -
2 -4.496 100.852 100.573 0.279 0.000 0.140 0.000 0.490 0.069 0.000
3 -3.000 101.600 100.750 0.850 0.000 0.565 0.000 1.496 0.845 0.000
4 -2.996 101.600 100.750 0.850 0.000 0.850 0.000 0.004 0.003 0.000
5 -1.496 101.600 100.613 0.987 0.000 0.918 0.000 1.500 1.377 0.000
6 0.000 101.600 100.559 1.041 0.000 1.014 0.000 1.496 1.517 0.000
7 1.504 101.600 100.477 1.123 0.000 1.082 0.000 1.504 1.627 0.000
8 3.000 101.600 100.314 1.286 0.000 1.205 0.000 1.496 1.803 0.000
9 3.005 101.598 100.313 1.285 0.000 1.286 0.000 0.005 0.006 0.000
10 4.505 100.848 100.203 0.645 0.000 0.965 0.000 1.500 1.448 0.000
11 6.005 100.098 99.465 0.633 0.000 0.639 0.000 1.500 0.959 0.000
12 7.271 99.465 99.465 0.000 0.000 0.316 0.000 1.266 0.400 0.000
10.054 0.000
Page 28 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 660
1 -5.242 100.479 100.479 0.000 0.000 - - - - -
2 -4.500 100.850 100.613 0.237 0.000 0.118 0.000 0.742 0.088 0.000
3 -3.000 101.600 100.477 1.123 0.000 0.680 0.000 1.500 1.020 0.000
4 -1.500 101.600 100.340 1.260 0.000 1.191 0.000 1.500 1.787 0.000
5 0.000 101.600 100.367 1.233 0.000 1.246 0.000 1.500 1.869 0.000
6 1.500 101.600 100.203 1.397 0.000 1.315 0.000 1.500 1.973 0.000
7 3.000 101.600 100.149 1.451 0.000 1.424 0.000 1.500 2.136 0.000
8 4.500 100.850 99.903 0.947 0.000 1.199 0.000 1.500 1.799 0.000
9 6.000 100.100 99.466 0.634 0.000 0.790 0.000 1.500 1.185 0.000
10 7.268 99.466 99.466 0.000 0.000 0.317 0.000 1.268 0.402 0.000
12.259 0.000

Section: 690
1 -5.858 100.171 100.171 0.000 0.000 - - - - -
2 -4.468 100.866 100.131 0.735 0.000 0.368 0.000 1.390 0.512 0.000
3 -3.000 101.600 100.431 1.169 0.000 0.952 0.000 1.468 1.398 0.000
4 -2.968 101.600 100.438 1.162 0.000 1.166 0.000 0.032 0.037 0.000
5 -1.467 101.600 100.314 1.286 0.000 1.224 0.000 1.501 1.837 0.000
6 0.000 101.600 100.537 1.063 0.000 1.175 0.000 1.467 1.724 0.000
7 1.533 101.600 100.264 1.336 0.000 1.200 0.000 1.533 1.840 0.000
8 3.000 101.600 100.410 1.190 0.000 1.263 0.000 1.467 1.853 0.000
9 3.033 101.584 100.413 1.171 0.000 1.181 0.000 0.033 0.039 0.000
10 4.533 100.834 99.952 0.882 0.000 1.027 0.000 1.500 1.541 0.000
11 6.033 100.084 99.826 0.258 0.000 0.570 0.000 1.500 0.855 0.000
12 6.549 99.826 99.826 0.000 0.000 0.129 0.000 0.516 0.067 0.000
11.699 0.000
Page 29 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 720
1 -5.394 100.403 100.403 0.000 0.000 - - - - -
2 -4.500 100.850 100.372 0.478 0.000 0.239 0.000 0.894 0.214 0.000
3 -3.000 101.600 100.309 1.291 0.000 0.884 0.000 1.500 1.326 0.000
4 -1.500 101.600 100.245 1.355 0.000 1.323 0.000 1.500 1.985 0.000
5 0.000 101.600 100.181 1.419 0.000 1.387 0.000 1.500 2.081 0.000
6 1.500 101.600 100.118 1.482 0.000 1.451 0.000 1.500 2.177 0.000
7 3.000 101.600 100.054 1.546 0.000 1.514 0.000 1.500 2.271 0.000
8 4.500 100.850 99.991 0.859 0.000 1.203 0.000 1.500 1.805 0.000
9 6.000 100.100 99.927 0.173 0.000 0.516 0.000 1.500 0.774 0.000
10 6.346 99.927 99.927 0.000 0.000 0.086 0.000 0.346 0.030 0.000
12.661 0.000

Section: 750
1 -4.948 100.626 100.626 0.000 0.000 - - - - -
2 -4.500 100.850 100.595 0.255 0.000 0.127 0.000 0.448 0.057 0.000
3 -3.000 101.600 100.810 0.790 0.000 0.522 0.000 1.500 0.783 0.000
4 -1.500 101.600 100.983 0.617 0.000 0.703 0.000 1.500 1.055 0.000
5 0.000 101.600 101.058 0.542 0.000 0.579 0.000 1.500 0.869 0.000
6 1.500 101.600 100.909 0.691 0.000 0.616 0.000 1.500 0.924 0.000
7 3.000 101.600 100.735 0.865 0.000 0.778 0.000 1.500 1.167 0.000
8 4.500 100.850 100.214 0.636 0.000 0.750 0.000 1.500 1.125 0.000
9 6.000 100.100 100.015 0.085 0.000 0.360 0.000 1.500 0.540 0.000
10 6.170 100.015 100.015 0.000 0.000 0.042 0.000 0.170 0.007 0.000
6.527 0.000
Page 30 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 780
1 -4.226 100.987 100.987 0.000 0.000 - - - - -
2 -3.022 101.589 101.073 0.516 0.000 0.258 0.000 1.204 0.311 0.000
3 -3.000 101.600 101.071 0.529 0.000 0.523 0.000 0.022 0.012 0.000
4 -1.521 101.600 100.942 0.658 0.000 0.593 0.000 1.479 0.877 0.000
5 0.000 101.600 100.801 0.799 0.000 0.728 0.000 1.521 1.107 0.000
6 1.479 101.600 100.665 0.935 0.000 0.867 0.000 1.479 1.282 0.000
7 2.979 101.600 100.526 1.074 0.000 1.005 0.000 1.500 1.508 0.000
8 3.000 101.600 100.524 1.076 0.000 1.075 0.000 0.021 0.023 0.000
9 4.479 100.861 100.387 0.474 0.000 0.775 0.000 1.479 1.146 0.000
10 5.643 100.279 100.279 0.000 0.000 0.237 0.000 1.164 0.276 0.000
6.540 0.000

Section: 810
1 -4.992 100.604 100.604 0.000 0.000 - - - - -
2 -4.500 100.850 100.573 0.277 0.000 0.139 0.000 0.492 0.068 0.000
3 -3.000 101.600 100.478 1.122 0.000 0.700 0.000 1.500 1.050 0.000
4 -1.500 101.600 100.383 1.217 0.000 1.170 0.000 1.500 1.755 0.000
5 0.000 101.600 100.287 1.313 0.000 1.265 0.000 1.500 1.898 0.000
6 1.500 101.600 100.274 1.326 0.000 1.320 0.000 1.500 1.980 0.000
7 3.000 101.600 100.277 1.323 0.000 1.325 0.000 1.500 1.988 0.000
8 4.500 100.850 100.171 0.679 0.000 1.001 0.000 1.500 1.502 0.000
9 6.000 100.100 100.079 0.021 0.000 0.350 0.000 1.500 0.525 0.000
10 6.042 100.079 100.079 0.000 0.000 0.011 0.000 0.042 0.000 0.000
10.763 0.000
Page 31 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 840
1 -4.003 101.098 101.098 0.000 0.000 - - - - -
2 -3.000 101.600 101.380 0.220 0.000 0.110 0.000 1.003 0.110 0.000
3 -1.978 101.600 101.600 0.000 0.000 0.110 0.000 1.022 0.112 0.000
4 -1.500 101.600 101.703 0.000 0.103 0.000 0.052 0.478 0.000 0.025
5 -1.111 101.600 101.600 0.000 0.000 0.000 0.052 0.389 0.000 0.020
6 0.000 101.600 101.306 0.294 0.000 0.147 0.000 1.111 0.163 0.000
7 1.500 101.600 101.125 0.475 0.000 0.384 0.000 1.500 0.576 0.000
8 3.000 101.600 100.730 0.870 0.000 0.672 0.000 1.500 1.008 0.000
9 4.500 100.850 100.284 0.566 0.000 0.718 0.000 1.500 1.077 0.000
10 5.792 100.204 100.204 0.000 0.000 0.283 0.000 1.292 0.366 0.000
3.412 0.045

Section: 870
1 -5.181 100.509 100.509 0.000 0.000 - - - - -
2 -4.500 100.850 100.512 0.338 0.000 0.169 0.000 0.681 0.115 0.000
3 -3.000 101.600 100.751 0.849 0.000 0.593 0.000 1.500 0.890 0.000
4 -1.500 101.600 100.982 0.618 0.000 0.733 0.000 1.500 1.100 0.000
5 0.000 101.600 101.115 0.485 0.000 0.551 0.000 1.500 0.827 0.000
6 1.500 101.600 101.111 0.489 0.000 0.487 0.000 1.500 0.731 0.000
7 3.000 101.600 100.977 0.623 0.000 0.556 0.000 1.500 0.834 0.000
8 4.500 100.850 100.767 0.083 0.000 0.353 0.000 1.500 0.530 0.000
9 4.731 100.735 100.735 0.000 0.000 0.041 0.000 0.231 0.009 0.000
5.036 0.000
Page 32 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 900
1 -4.118 101.041 101.041 0.000 0.000 - - - - -
2 -3.000 101.600 101.189 0.411 0.000 0.206 0.000 1.118 0.230 0.000
3 -2.966 101.600 101.193 0.407 0.000 0.409 0.000 0.034 0.014 0.000
4 -1.466 101.600 101.068 0.532 0.000 0.469 0.000 1.500 0.704 0.000
5 0.000 101.600 100.946 0.654 0.000 0.593 0.000 1.466 0.869 0.000
6 1.534 101.600 100.947 0.653 0.000 0.653 0.000 1.534 1.002 0.000
7 3.000 101.600 100.965 0.635 0.000 0.644 0.000 1.466 0.944 0.000
8 3.034 101.583 100.965 0.618 0.000 0.626 0.000 0.034 0.021 0.000
9 4.534 100.833 100.448 0.385 0.000 0.502 0.000 1.500 0.753 0.000
10 5.740 100.230 100.230 0.000 0.000 0.193 0.000 1.206 0.233 0.000
4.770 0.000

Section: 930
1 -13.000 96.600 100.493 0.000 3.893 - - - - -
2 -6.000 100.100 100.493 0.000 0.393 0.000 2.143 7.000 0.000 15.001
3 -4.500 100.850 101.158 0.000 0.308 0.000 0.351 1.500 0.000 0.527
4 -3.000 101.600 101.821 0.000 0.221 0.000 0.265 1.500 0.000 0.398
5 -1.500 101.600 101.821 0.000 0.221 0.000 0.221 1.500 0.000 0.332
6 0.000 101.600 101.678 0.000 0.078 0.000 0.150 1.500 0.000 0.225
7 1.500 101.600 101.716 0.000 0.116 0.000 0.097 1.500 0.000 0.146
8 3.000 101.600 101.745 0.000 0.145 0.000 0.131 1.500 0.000 0.197
9 4.500 100.850 101.149 0.000 0.299 0.000 0.222 1.500 0.000 0.333
10 6.000 100.100 100.434 0.000 0.334 0.000 0.317 1.500 0.000 0.476
11 13.000 96.600 100.434 0.000 3.834 0.000 2.084 7.000 0.000 14.588
0.000 32.223
Page 33 of 42

Difference Avg Difference Area


Chainage Location Final Levels Initial Levels Length
Filling Ht Cutting Ht Filling Ht Cutting Ht Filling Area Cutting Area
Section: 954.959
1 -5.837 100.182 100.182 0.000 0.000 - - - - -
2 -4.500 100.850 100.645 0.205 0.000 0.102 0.000 1.337 0.136 0.000
3 -3.000 101.600 101.140 0.460 0.000 0.332 0.000 1.500 0.498 0.000
4 -1.500 101.600 101.092 0.508 0.000 0.484 0.000 1.500 0.726 0.000
5 0.000 101.600 100.998 0.602 0.000 0.555 0.000 1.500 0.833 0.000
6 1.500 101.600 100.908 0.692 0.000 0.647 0.000 1.500 0.971 0.000
7 3.000 101.600 100.877 0.723 0.000 0.707 0.000 1.500 1.061 0.000
8 4.321 100.939 100.939 0.000 0.000 0.362 0.000 1.321 0.478 0.000
4.702 0.000

ASSISTANT EXECUTIVE
ENGINEER(R.D) ASSISTANT
CHERANMAHADEVI ENGINEER(R.D)
SUBDIVISION PANCHAYAT UNION
CHERANMAHADEVI KADAYAM
Cutting / Filling Volume - Calculation

Filling Quantity Cutting Quantity


Sno. Chainage Distance
Filling Area Mean Area Volume Cutting Area Mean Area Volume

1 0.000 - 3.722 - - 0.000 - -


2 30.000 30.000 4.221 3.972 119.160 0.000 0.000 0.000
3 60.000 30.000 6.439 5.330 159.900 0.000 0.000 0.000
4 90.000 30.000 2.917 4.678 140.340 0.000 0.000 0.000
5 120.000 30.000 5.382 4.150 124.500 0.000 0.000 0.000
6 150.000 30.000 6.668 6.025 180.750 0.000 0.000 0.000
7 180.000 30.000 8.654 7.661 229.830 0.000 0.000 0.000
8 210.000 30.000 10.756 9.705 291.150 0.000 0.000 0.000
9 240.000 30.000 8.570 9.663 289.890 0.000 0.000 0.000
10 270.000 30.000 14.279 11.425 342.750 0.000 0.000 0.000
D/F- Weir
12.000 11.425 -137.100 0.000 0.000
258-270
11 300.000 30.000 3.983 9.131 273.930 0.000 0.000 0.000
12 330.000 30.000 1.894 2.939 88.170 1.080 0.540 16.200
13 360.000 30.000 11.337 6.616 198.480 0.000 0.540 16.200
14 390.000 30.000 8.351 9.844 295.320 0.000 0.000 0.000
15 420.000 30.000 6.190 7.271 218.130 0.000 0.000 0.000
16 450.000 30.000 1.913 4.052 121.560 0.490 0.245 7.350
17 480.000 30.000 2.523 2.218 66.540 0.464 0.477 14.310
18 510.000 30.000 6.291 4.407 132.210 0.000 0.232 6.960
19 540.000 30.000 7.181 6.736 202.080 0.000 0.000 0.000
20 570.000 30.000 14.486 10.834 325.020 0.000 0.000 0.000
Filling Quantity Cutting Quantity
Sno. Chainage Distance
Filling Area Mean Area Volume Cutting Area Mean Area Volume

21 600.000 30.000 6.440 10.463 313.890 0.000 0.000 0.000


D/F- Inlet
30.000 10.463 -313.890 0.000 0.000
570-600
22 630.000 30.000 10.054 8.247 247.410 0.000 0.000 0.000
23 660.000 30.000 12.259 11.157 334.710 0.000 0.000 0.000
24 690.000 30.000 11.699 11.979 359.370 0.000 0.000 0.000
25 720.000 30.000 12.661 12.180 365.400 0.000 0.000 0.000
26 750.000 30.000 6.527 9.594 287.820 0.000 0.000 0.000
27 780.000 30.000 6.540 6.534 196.020 0.000 0.000 0.000
28 810.000 30.000 10.763 8.652 259.560 0.000 0.000 0.000
29 840.000 30.000 3.412 7.088 212.640 0.045 0.023 0.690
D/F- Inlet
16.000 7.088 -113.408 0.023 -0.368
824-840
30 870.000 30.000 5.036 4.224 126.720 0.000 0.023 0.690
31 900.000 30.000 4.770 4.903 147.090 0.000 0.000 0.000
32 930.000 30.000 0.000 2.385 71.550 32.223 16.112 483.360
33 954.959 24.959 4.702 2.351 58.679 0.000 16.112 402.139

Total Filling Qty = 6216.171 Total Cutting Qty = 947.531

Net Filling Quantity = 5268.640

ASSISTANT EXECUTIVE
ENGINEER(R.D) ASSISTANT ENGINEER(R.D)
CHERANMAHADEVI PANCHAYAT UNION
SUBDIVISION KADAYAM
CHERANMAHADEVI
FILLING QUANTITY CALCULATION FOR U/S, D/S AND TOP OF BUND

CHAINAGE AREA M.AREA LENGTH QUANTITY Cumm. Qty

BUND - 1 (South)

0.00 11.044 0.000 0.000 0.000 0.000

30.00 7.562 9.303 30.000 279.090 279.090

60.00 2.064 4.813 30.000 144.390 423.480

90.00 0.430 1.247 30.000 37.410 460.890

120.00 0.821 0.626 30.000 18.780 479.670

133.54 1.611 1.216 13.540 16.465 496.135

150.00 0.596 1.104 16.460 18.172 514.307

180.00 0.466 0.531 30.000 15.930 530.237

210.00 3.265 1.866 30.000 55.980 586.217

240.00 1.145 2.205 30.000 66.150 652.367

270.00 1.698 1.422 30.000 42.660 695.027

300.00 9.190 5.444 30.000 163.320 858.347

SUB TOTAL FOR BUND-1 = 858.347

BUND - 2 (East)

0.00 4.633 0.000 0.000 0.000 0.000

30.00 1.847 3.240 30.000 97.200 97.200

60.00 0.760 1.304 30.000 39.120 136.320

90.00 1.355 1.058 30.000 31.740 168.060

120.00 0.000 0.678 30.000 20.340 188.400

150.00 0.000 0.000 30.000 0.000 188.400

180.00 0.000 0.000 30.000 0.000 188.400

210.00 0.000 0.000 30.000 0.000 188.400

240.00 0.056 0.028 30.000 0.840 189.240

257.96 1.907 0.982 17.960 17.637 206.877

SUB TOTAL FOR BUND-2 = 206.877

BUND - 3 (North)
FILLING QUANTITY CALCULATION FOR U/S, D/S AND TOP OF BUND

CHAINAGE AREA M.AREA LENGTH QUANTITY Cumm. Qty

0.00 4.880 0.000 0.000 0.000 0.000

30.00 0.526 2.703 30.000 81.090 81.090

60.00 3.322 1.924 30.000 57.720 138.810

90.00 3.533 3.428 30.000 102.840 241.650

113.26 2.781 3.157 23.260 73.432 315.082

SUB TOTAL FOR BUND-3 = 315.082

BUND - 4 (West)

0.00 7.872 0.000 0.000 0.000 0.000

30.00 7.733 7.803 30.000 234.090 234.090

60.00 6.223 6.978 30.000 209.340 443.430

90.00 5.724 5.974 30.000 179.220 622.650

120.00 8.324 7.024 30.000 210.720 833.370

150.00 10.951 9.638 30.000 289.140 1122.510

180.00 10.907 10.929 30.000 327.870 1450.380

210.00 8.912 9.910 30.000 297.300 1747.680

220.18 6.418 7.665 10.180 78.030 1825.710

SUB TOTAL FOR BUND-4 = 1825.710

GRAND TOTAL = 3206.016


CUTTING QUANTITY CALCULATION FOR U/S, D/S AND TOP OF BUND

CHAINAGE AREA M.AREA LENGTH QUANTITY Cumm. Qty

BUND - 1 (South)

0.00 0.000 0.000 0.000 0.000 0.000

30.00 0.000 0.000 30.000 0.000 0.000

60.00 0.289 0.145 30.000 4.350 4.350

90.00 2.303 1.296 30.000 38.880 43.230

120.00 0.748 1.526 30.000 45.780 89.010

133.54 1.031 0.890 13.540 12.051 101.061

150.00 5.030 3.031 16.460 49.890 150.951

180.00 2.899 3.965 30.000 118.950 269.901

210.00 1.459 2.179 30.000 65.370 335.271

240.00 1.111 1.285 30.000 38.550 373.821

270.00 0.000 0.556 30.000 16.680 390.501

300.00 0.006 0.003 30.000 0.090 390.591

SUB TOTAL FOR BUND-1 = 390.591

BUND - 2 (East)

0.00 0.000 0.000 0.000 0.000 0.000

30.00 0.584 0.292 30.000 8.760 8.760

60.00 0.050 0.317 30.000 9.510 18.270

90.00 1.313 0.682 30.000 20.460 38.730

120.00 5.761 3.537 30.000 106.110 144.840

150.00 5.328 5.545 30.000 166.350 311.190

180.00 11.354 8.341 30.000 250.230 561.420

210.00 9.357 10.356 30.000 310.680 872.100

240.00 1.770 5.564 30.000 166.920 1039.020

257.96 0.000 0.885 17.960 15.895 1054.915

SUB TOTAL FOR BUND-2 = 1054.915

BUND - 3 (North)
CUTTING QUANTITY CALCULATION FOR U/S, D/S AND TOP OF BUND

CHAINAGE AREA M.AREA LENGTH QUANTITY Cumm. Qty

0.00 0.000 0.000 0.000 0.000 0.000

30.00 2.045 1.023 30.000 30.690 30.690

60.00 0.000 1.023 30.000 30.690 61.380

90.00 0.000 0.000 30.000 0.000 61.380

113.26 0.000 0.000 23.260 0.000 61.380

SUB TOTAL FOR BUND-3 = 61.380

BUND - 4 (West)

0.00 0.000 0.000 0.000 0.000 0.000

30.00 0.000 0.000 30.000 0.000 0.000

60.00 0.000 0.000 30.000 0.000 0.000

90.00 0.000 0.000 30.000 0.000 0.000

120.00 0.000 0.000 30.000 0.000 0.000

150.00 0.000 0.000 30.000 0.000 0.000

180.00 0.000 0.000 30.000 0.000 0.000

210.00 0.000 0.000 30.000 0.000 0.000

220.18 0.000 0.000 10.180 0.000 0.000

SUB TOTAL FOR BUND-4 = 0.000

GRAND TOTAL = 1506.886


Volume Report Between OGL and FORMATION
VANNANKULAM
Sl. Section Previous Cutting Volume Filling Volume
No. From Section Difference Width Area Average Volume Area Average Volume
Sq. Mtrs Sq. Mtrs Cubic Meters Sq. Mtrs Sq. Mtrs Cubic Meters

1 0.000 - 0.000 8.180 0.000 - - 3.724 - -

2 30.000 0.000 30.000 7.569 0.000 0.000 0.000 4.222 3.973 119.190

3 60.000 30.000 30.000 8.690 0.000 0.000 0.000 6.442 5.332 159.960

4 90.000 60.000 30.000 8.969 0.000 0.000 0.000 2.917 4.680 140.400

5 120.000 90.000 30.000 8.526 0.000 0.000 0.000 5.385 4.151 124.530

6 150.000 120.000 30.000 10.844 0.000 0.000 0.000 6.670 6.028 180.840

7 180.000 150.000 30.000 11.386 0.000 0.000 0.000 8.658 7.664 229.920

8 210.000 180.000 30.000 12.079 0.000 0.000 0.000 10.759 9.709 291.270

9 240.000 210.000 30.000 10.814 0.000 0.000 0.000 8.571 9.665 289.950

10 270.000 240.000 30.000 13.097 0.000 0.000 0.000 14.278 11.425 342.750

D/f- Weir 258-270 12.000 0.000 0.000 11.425 -137.100

11 300.000 270.000 30.000 7.956 0.000 0.000 0.000 3.984 9.131 273.930

12 330.000 300.000 30.000 11.494 1.080 0.540 16.200 1.896 2.940 88.200

13 360.000 330.000 30.000 14.250 0.000 0.540 16.200 11.338 6.617 198.510

14 390.000 360.000 30.000 19.464 0.000 0.000 0.000 8.353 9.846 295.380

15 420.000 390.000 30.000 11.508 0.000 0.000 0.000 6.191 7.272 218.160

16 450.000 420.000 30.000 10.268 0.488 0.244 7.320 1.914 4.053 121.590

17 480.000 450.000 30.000 10.382 0.462 0.475 14.250 2.523 2.219 66.570

18 510.000 480.000 30.000 11.870 0.000 0.231 6.930 6.294 4.409 132.270

19 540.000 510.000 30.000 11.928 0.000 0.000 0.000 7.185 6.740 202.200

20 570.000 540.000 30.000 13.164 0.000 0.000 0.000 14.484 10.835 325.050

21 600.000 570.000 30.000 9.722 0.000 0.000 0.000 6.443 10.464 313.920

22 630.000 600.000 30.000 12.257 0.000 0.000 0.000 10.053 8.248 247.440

23 660.000 630.000 30.000 12.510 0.000 0.000 0.000 12.261 11.157 334.710

24 690.000 660.000 30.000 12.407 0.000 0.000 0.000 11.699 11.980 359.400

25 720.000 690.000 30.000 11.740 0.000 0.000 0.000 12.662 12.181 365.430

26 750.000 720.000 30.000 11.118 0.000 0.000 0.000 6.531 9.597 287.910
Volume Report Between OGL and FORMATION
VANNANKULAM
Sl. Section Previous Cutting Volume Filling Volume
No. From Section Difference Width Area Average Volume Area Average Volume
Sq. Mtrs Sq. Mtrs Cubic Meters Sq. Mtrs Sq. Mtrs Cubic Meters

27 780.000 750.000 30.000 9.869 0.000 0.000 0.000 6.542 6.537 196.110

28 810.000 780.000 30.000 11.034 0.000 0.000 0.000 10.762 8.652 259.560

29 840.000 810.000 30.000 11.091 0.045 0.023 0.690 3.414 7.088 212.640

D/f- inlet 824-840 16.000 0.023 -0.368 7.088 -113.408

30 870.000 840.000 30.000 9.912 0.000 0.023 0.690 5.037 4.226 126.780

31 900.000 870.000 30.000 9.858 0.000 0.000 0.000 4.768 4.903 147.090

32 930.000 900.000 30.000 26.000 32.218 16.109 483.270 0.000 2.384 71.520

33 954.959 930.000 24.959 10.158 0.000 16.109 402.065 4.705 2.353 58.729

Total 1476.155 Total 6698.496

ASSISTANT ENGINEER
(RD)
ASSISTANT EXECUTIVE ENGINEER(R.D) PANCHAYAT UNION
CHERANMAHADEVI SUBDIVISION KADAYAM
CHERANMAHADEVI