Notes:
SUBSCRIBE UPDATES. IT'S FREE!
1. This is a generic checklist for Typical o shore platform with all facilities. For projects containing only
typical Wellhead facilities Platforms / Riser Platforms / Electrical facilities platforms etc.., this check list can
be ltered out for relevant items or topics not required can be stroked-o . Your email:
Enter email address...

Subscribe
2. The Checker shall complete and maintain this Check list for rst and IFC issues. For intermediate issues,
Revision Checklist shall be used unless there are major scope change.

3. The originator of the Drawing can use this checklist for self checking, but need not ll it. Popular Recent Comments

SL NO. DESCRIPTION Piping Layout Drawings Abbreviations and


Legends
GENERAL  July 12, 2017

1 All P&IDs are available with index and document numbers as per index sheet Nozzle Orientation Drawing
2 Legend P&ID cover information about all the line services, abbreviations, symbols,  July 12, 2017
Piping/Instrumentation/Equipment (like sample stations, level instruments) which are used in
Centrifugal Pump Piping Design Layout
P&ID are matching.
 July 12, 2017
3 Missing / Incomplete information like Line numbers, Tag numbers, Flow directions, Instrument
details, Equipment details, Trim details, Continuation P&ID etc. Tank farm: Types, Design Considerations,
Plot Plan Arrangement, Dyke Enclosure-
4 Whenever the pipe class (spec) changes, the line shall be allotted a di erent unique line Part 1
number.  July 12, 2017

5 All line numbers mentioned with spec, rating, and insulation requirement.
7 Excel Functions You Must
6 Notes are complete, clear. Impact on piping/ layouts reviewed and commented if required Know to Work Smarter
 July 12, 2017
7 Highlight any tag numbers, line numbers are repeating.

8 P&ID holds are reviewed for impact in Piping/ Layout

9 New line number provided whenever there is spec change, branches

10 Check Spec Breaks, Pressure ratings, Insulating Gasket requirement.

11 Check number of equipment, type of equipment, design conditions of equipment, equipment


Piping-engineering
11,905 likes
sizes are matching with mechanical/process data sheets

12 Compare with Process ow diagram(PFD)

13 Piping Specialties are identi ed and numbered Like Page Share

14 Check instrumentation requirements impacting Piping/Layout (Upstream -Downstream


straight run requirements, Level requirements) Be the first of your friends to like this

15 Tracing / Heating requirements for Pipes and Equipment

16 P&ID are reviewed with Piping Material Speci cations (PMS) requirements. Or reach me on aj@piping-
17 Check all instruments with tags and tag numbering are as per legend engineering.com
18 Check the type of instrument used is matching with instrumentation hook up

19 Scope breaks identi ed (like Company/Vendor/Instrumentation/ existing /new project scope/


by others) Google+
20 Scope breaks and Spec breaks between piping and pipeline

21 Check all equipment numbers, names, sequence, type of equipment and any maintenance
requirement speci c to process is mentioned in P&ID

22 Check all instruments are placed on equipment as per vendor requisition 

23 Check Separate Line numbers should be given not only wherever there is a change of pipe
class but also where the design conditions of the line change.

24 Check center line elevation is given for horizontal vessels, pump nozzles, Manways, instrument
nozzle heights etc.

25 Check revisions are cleared marked and consistent

26 Check Gravity ow, Slope, Free draining/ No Pockets requirements

27 Check Drain funnel requirement (Number of open drain funnels)

28 Check Removable break-up spool requirement

29 Check the insulation type and insulation thickness requirement for Pipes and Equipment

30 Review process vent and drain requirement

31 Check valve types used (special attention for requirement of Full bore Ball Valves,
Wafer/Lug/Lug/Swing Check valve)

32 Check type of valve required in line and valve position and condition etc.

33 Check the line size and rating where temperature gauges located

34 Check Reducer provision for control valves, PSVs, Equipment Nozzles

35 Review Branch locations, Sequences, Line connections based on layouts

36 check PSV size, line rating, stand by provision and any bypass requirement is provided

37 Check Strainers details(type, orientation)

38 Check possibility of Tie ins at suggested locations based on existing material, pipe thickness,
ange rating, site conditions.

39 Check manual valves with mechanical interlock & speci ed

40 check provisions and locations for chemical injection(CI, Wax, PPD, Biocide)

41 Check tundish requirement (with SP numbers) near Process vessels

42 Check for bunding requirement for Process vessels (when process vessels is not mounted on
skid) & utility tanks

43 Check sampling station details at legend sheet

44 Check straight run requirement for example pumps, ow elements, vessel, compressors etc.

45 Check diaphragm type instruments are used in dirty services

46 Check the requirement of metal seated Ball valves, Target tees and sand probes in well uid
services containing sand.

47 Check notes, details for purging, ushing, rodding, cleaning requirements.

48 Preferred Slope of the Main Rack headers could be 1:300 or 1:500.

49 Preferred slope values on branch lines could be around 1:200 or 1:333.

50 Line slope values mentioned on P&ID for long headers should be veri ed (by studying
structural arrangement) before implementation.

51 Process to show all pump vents & drains on the P&IDs as per Pump vendor drawings.

52 Spec break shall be only at the ange joints even if it is indicated otherwise in the P&IDs &
there are no dissimilar metal welded at spec breaks

53 Drip pans requirement pig traps & SP number allocation of them

54 If dissimilar materials cannot be avoided then use a design that will prevent galvanic
corrosion, that is could be insulation assembly (inert Ring Joints and bolts).

55 all Instrument /Piping- CS/SS scope breaks shall be provided with insulating kit

56 Check Strainer requirement downstream of Rupture Disc (Fragment type)

57 Upstream & Downstream straight length requirement for special uid measurement devices.
Such as Venturi Tubes, Flow Nozzles, Electro Magnetic Flow meters, Ultrasonic Doppler ow
meter, Mass ow meter etc.

58 Slopes for launchers/ receivers Identi ed correctly

59 See feasibility to convert welded tie-ins to anged as per Site conditions

60 Compare Tie-in numbers and locations in construction and demolition P&ID

61 Review demolition scope in Demolition P&IDS (in project scope or by others)