1. Purpose:
This procedure is established to provide for taking corrective actions and preventive
actions for nonconforming situations to avoid recurrence and to prevent occurrence of
the same.
2. Scope:
3.Responsibility:
Project Manager/MR
QA/QC Manager/HSE Manager
Department Heads
4. Procedure:
The Management Representative/HSE Officer discusses the same with the relevant
personnel, decide on the best approach and ensure that the root cause of the problem
is identified.
Once the root cause is identified, actions are taken to eliminate the root cause to ensure
there is no recurrence of the situation.
Upon satisfactory completion of the corrective action, the form is closed out. Corrective
actions are analyzed and discussed during Management Review Meetings.
ALCAT CONTRACTING INTEGRATED MANAGEMENT Doc No PR 006
COMPANY W.L.L. (ALCAT)
SYSTEM PROCEDURE Rev No 01
CORRECTIVE AND Rev Date 01st Jan. 14
PREVENTIVE ACTIONS Page 2 of 3
Prepared by Management Representative Approved by General Manager
Corrective actions are analyzed and discussed during Management Review Meetings
when their effectiveness is also reviewed.
The relevant Department Heads and the Management Representative shall carry out
preventive action as per following steps to eliminate the cause of potential
nonconformities in order to prevent their occurrence.
Review of critical processes, which affect the product quality, all nonconformity
reports during the past month and audit reports of past audits.
QUALITY & HSE related issues identified.
Identify the potential cause of nonconformity.
Identify the similar areas/products.
Prepare preventive action plan to eliminate the cause in similar areas/products.
Verification for preventive action implementation.
Effectiveness of preventive action.
The Management Representative shall study the complaints and necessary corrective
action and preventive action shall be taken in consultation with the Section Heads and
staff as appropriate. Details of actions taken in the complaint shall be registered in the
customer compliant register (F 019) and in the NC status register. Corrective and
ALCAT CONTRACTING INTEGRATED MANAGEMENT Doc No PR 006
COMPANY W.L.L. (ALCAT)
SYSTEM PROCEDURE Rev No 01
CORRECTIVE AND Rev Date 01st Jan. 14
PREVENTIVE ACTIONS Page 3 of 3
Prepared by Management Representative Approved by General Manager
An identified date for action shall be adhered and submitted to the initiator with defined
root cause of the deficiency and proposed correction action.