Doc. No.

: HSE/FRM-22
Rev.: 00
JOB SAFETY ANALYSIS Date: Dec 02, 08
Page: 1 of 3

Project: Gul Ahmed Wind power Project#: 1161 Area: GAWPP-


SITE General Comments: Proper PPE, TBT should be conducted before start the job,
Access control authority would be DEL Site Manager/Site Engineer
Date: 02-02-2016 Supervisor: Muhammad Ali (Mech. Engineer)

Job Description: Lifting & Rigging Activity (Loading/Unloading of the Equipment)


Equipment & Severity
Item Detail of Activity Risk Involved Preventive Measure Responsible Person
Tools used Rating
TRANSPORTATION
 UNEVEN ROAD  CRANE SHOULD BE CHECKED, BEFORE RIGGING 2
1 OF THE MATERIALS
& CRANE TO JOB  CRANE  UNSAFE CONDITIONS TRANSPORTATION TO JOB SITE ON DAILY BASIS. SUPERVISOR 2
SITE.  TRAILER
 PROPER ACCESS (BRIDGES) SHOULD BE USED.
 FLAT BED  CRANE COLLAPSE DURING 3
MATERIAL LOADING /  FLAGMAN WILL BE ASSIGNED WITH THE CRANE & 3
 MULTI AXEL  LIFTING AREA AUTHORIZES
2 UNLOADING HEAVY EQUIPMENT. 2
TRAILER  PERSONAL INJUREY
 MATERIAL MUST BE CHECKED BEFORE LOADING / 3
 LIFTING GEARS  PROPERTY DAMAGE
UNLOADING.
 MATERIAL MUST BE PROPERLY SECURED WITH
(SLINGS,
SETTING UP CRANE  CRANE FAILURE DUE TO SLING & SHACKLES BEFORE LIFTING UP.
FOR LIFTING. SHACKLES,
3 HYDROLIC SYSTEM  CRANE WILL BE SET UP AT LEVEL SURFACE WITH E & P I/C 2
WEB-BELT,
 CAUSE OF SERIOUS OUTRIGGER PADS.
TAG LINE,
 OUTRIGGERS WILL BE FULLY EXTENDED CRANE.
CHAIN BLOCK,
 CRANE MUST BE 3RD PARTY CERTIFIED.
LEVER HOST, FORK HSE INSPECTOR
4 LIFTING WITH CRANE  FIRE DUE TO LOOSE WIRING  ALL LIFTS WILL BE UNDER THE RATED CAPACITY OF 2
LIFTER, PICK WAY
CRANE I.E. LOAD CHART.
TRUCK & ETC).
 CERTIFIED CRANE OPERATOR AND RIGGERS (3RD
INSPECTION OF  FALL OF OBJECT
5 CRANE PARTY CERTIFIED) WILL CARRY OUT THE LIFTING RIGGING ENGINEER 3
& RIGGING GEARS
ACTIVITY.

6 DEMOBILIZATION  ALL LIFTING TACKLES WILL HAVE 3RD PARTY RIGGING 2


CRANES SUPERVISOR
 PERSONNEL INJURY  CERTIFICATIONS & HEALTHY (GOOD CONDITION).
EQUIPMENT’S,
TOOLS AND  SLIPPING  RIGGING PLAN & STUDY REQUIRED FOR HEAVY
WORKER.

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
© Copyrights Ordinance 2002, All Rights Reserved
LIFTING.

 ONLY SINGLE PERSON MUST BE GIVEN SIGNAL TO


CRANE OPERATOR.
 EMPLOYEES SHOULD BE TRAINED ON SAFE
RIGGING TECHNIQUES.

 TRIPPING  TOOLBOX TALK MUST BE CONDUCTED BEFORE


 ELECTRIC SHOCK EACH LIFT.
 DUE TO POWER LINE  LIFTING AREA SHOULD BE BARRICADED WITH
WARNING.
 ALL LOADS WILL BE CONTROLLED BY TAG LINES, IF
LENGTH IS LONG THAN DOUBLE TAG LINE USED.
 LIFTING CREW WILL WORK WITH COMPLETE PPES.
 AREA MUST BE CHECKED & FREE FROM
ELECTRICAL WIRES BEFORE ASSEMBLING TO THE
CRANE.
 TOOL & JOINTS ETC. SHOULD BE LIFT BY ROPE &
BASKET RIGGING
 SCAFFOLDING SHOULD BE ERECTED UNDER SUPERVISOR
 MATERIAL CAN FALL
SKILLED SUPERVISION. 2
7 SCAFFOLDING  PERSONAL FALL
WORK AT HEIGHT
CHARRY PICKLES  FULL BODY HARNESS MUST BE WORN WHILE WORK 3
 IMPROPER SCAFFOLDING
AT HEIGHT 6 FEET & ABOVE. 3
ERECTION
 SCAFFOLDING MUST BE ERRECTED WITH SCAFFOLDING
STANDARD & INSPECTED BY SCAFFOLDING INSPECTOR
INSPECTOR.
 WORK WOULD BE NEVER ALLOWED IN LESS OR
 MANUAL HANDLING 2
LIGHTS & STANDS IMPROPERLY DISPRESSED ILLUMINATION/LIGHTS. RIGGING
8
WORK AT NIGHT (FLOOD LIGHTS  SLIP, TRIP & FALL 2
WHITE)  ALL WORK AT NIGHT ARRANGEMENT MUST BE SUPERVISOR
 POOR ILLUMINATION 2
DONE BEFORE START OF WORK AT NIGHT.

 WASTE MATERIAL SHOULD BE STACKED PROPERLY


WASTE DRUMS  ENVIRONMENT HAZARD RIGGING 1
9 HOUSEKEEPING & DUMPED IN DESIGNATED PLACES.
SHOPPER BAGS  SLIP, TRIP & FALL SUPERVISOR 2
 WASTE MATERIAL SHOULD BE BARRICADED.

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
© Copyrights Ordinance 2002, All Rights Reserved
Severity Rating: (1) First Aid / Minor Property Damage (2) Recordable Accident / Property Damage
(3) Lost Time Accident / Major Property Loss (4) Catastrophic Accident

Are you aware of, and do you have the correct PPE? What are the risks? How do controlled risks?

_______________________________ __________________________
AREA ENGINEER / SUPERVISOR HSE REPRESENTATIVE

This document is the intellectual property of Descon Engineering Limited. Any unauthorized use, including modification and reproduction of the content is strictly prohibited.
© Copyrights Ordinance 2002, All Rights Reserved