Date Tasks
Completed
13/01/20 Create website for Unit 13
Write a proposal which includes:
- Rationale
- Project Concept
- Evaluation
Wardrobe sheet
Write up feedback
26/03/20 Make sure the following is completed,
uploaded and signed off:
- Crew confirmation emails
- Crew list (With locations and times
needed)
- Contingency crew organised
- Actor confirmation emails
- Actor schedule (Where and when needed
and what clothes need to wear/take)
- Location permission confirmed
- Up to date, fully completed production
schedule
- Times, dates, crew needed, actors
needed, locations, props needed,
equipment needed
- Reshoot times and dates
- Contingency plan times and date
27/03/20 Complete any unfinished work (Catch-up
day)
28/03/20 AT WORK 10am – 7pm
29/03/20 Complete any unfinished work (Catch-up
day)
30/03/20 Film – Behind the scene footage/photos
31/03/20 Film
01/04/20 Film
02/04/20 Film
03/04/20 Complete any unfinished work (Catch-up
day)
04/04/20 AT WORK 10am – 7pm
05/04/20 Complete any unfinished work (Catch-up
day)
06/04/20 Film
07/04/20 Film
08/04/20 Film
09/04/20 Film
10/04/20 Film
11/04/20 AT WORK 10am – 7pm
Production Schedule V4
12/04/20 Film
13/04/20 Film
14/04/20 Film
15/04/20 Film
16/04/20 Film
17/04/20 Film
18/04/20 AT WORK 10am – 7pm
19/04/20 Film
0/04/20 Edit – Show progression of editing – first
draft all the way to final render
21/04/20 Edit
22/04/20 Edit
23/04/20 Edit
24/04/20 Complete any unfinished work (Catch-up
day)
25/04/20 AT WORK 10am – 7pm
26/04/20 Complete any unfinished work (Catch-up
day)
27/04/20 Edit – proof of feedback and what I have
done due to it
28/04/20 Edit
29/04/20 Edit
30/04/20 Edit
01/05/20 Complete any unfinished work (Catch-up
day)
02/05/20 AT WORK 10am – 7pm
03/05/20 Complete any unfinished work (Catch-up
day)
04/05/20 Reshoot
05/05/20 Reshoot
06/05/20 Edit – screenshots of editing process with
evaluation of it
07/05/20 Final Render
Weekly Blog
08/05/20 FINAL EDIT SUBMISSON
09/05/20 AT WORK 10am – 7pm
10/05/20 Complete any unfinished work (Catch-up
day)
11/05/20 Evaluation
- Test shoots
- Drafts
- Script
- Behind the scenes
12/05/20 Present final render to variety of people:
Production Schedule V4
- Peers
- Surveys
- Focus Groups
13/05/20 Present feedback in professional way
14/05/20 From feedback how will I progress?