Professional Documents
Culture Documents
Cofmow Itp
Cofmow Itp
Cofmow Itp
CONTRACTORES NAME AND ADDRESS:- ITEM DESCRIPTION QAP NO:- FQP-CIVIL- UK-01 Project:-Uttrakhand Projects
CIVIL WORKS ( SITE ACTIVITY) QAP Date :- 02.11.2019 Rev No. 01 Client: Uttrakhand Govt.
SR.NO. COMPONENTS TEST/CHECKS QUANTUM CHECKS ACCEPTANCE CRETERIA RECORD REFRENCE DOCUMENTS INSPECTION REMARKS
A INSPECTION OF INCOMING MATERIALS IR CLASS
CEMENT Review of MTC for Physical & once per batch Tech SPC/IS Manufactures Test Tech SPC/IS P
1 Chemical Analysis Certificate
Sieve Analysis For Each Vehicle before Unload
Flakiness & Elongation Monthly
Specific Gravity Monthly
2 COARSE & FINE AGGREGATE Bulk Density Seasonal/Monthly IS-383, IS-2386 LAB TEST REPORT Tech SPC/IS P
Crushing & Impact Value Monthly
Silt & Clay Content For Each Vehicle before Unload
Moisture Content As per Requirement
VISUAL INSPECTION Each Lot
3 BRICKS Dimension, Water Absorption, IS-1077, IS-2180 LAB TEST REPORT SPECS/DRGS. P
Compressive Strength & Each Lot
Effolorence
Chemical & Physical Analysis Review of MTC
Manufactures Test Tech SPC/IS As per grade
4 REINFORCEMENT P
Handling & Storage 100% Certificate mentionedby Designer
Rolling Margin Each Lot IS-1786/As Per Approved Make
B INSPECTION AT PROCESS
Mix Ratio. W/C Ratio, Slump 1 Set ( 6 Cubes) per 50 CU.M/ 1 Set ( 6 Cubes)
IS-456,IS-516,IS-1199, IS-3025 Slump Register to be P
per Foundation, Slump Test shall be done on
Each Miller & IS-7861 Maintained SPECS/DRGS.
5 CONCRETE
For Each grade Intially once & IS-10262/IS-
Mix Design there after for Every Change of 456/Tech.Spec./Initial Cube Tech.Spec
Source Test Results before Use Design Mix Report P
BACK FILLING OMC & MDD Once per Source
6 Field Dry Density/ Compaction One Test Per Layer Foundation SPECS/DRGS. P
SOIL Test Filling IS-2720, Is -10379, Min 90 % General Engg
SAND Max & Min Dry Density Once per Source Compaction Practice
2 EARTHWORK
2.1 EXCAVATION Physical Dimension & Level 100% Project Specification
2.2 BACKFILLING Material Test - Soil As per Project Specifications Project Specification
(1) Gradation Analysis 1 set for existing embankment
(2) Atterberg’s limits - liquid limit & plastic limit 1 set per source of borrow material
(3) Optimum Moisture Content (OMC), Maximum Dry
Density (MDD)
(2) All Physical & Chemical test 3rd Party Lab once in 3 months Project Specification
(3) Physical Tests at site lab for each batch received at site
A) Consistency
B) Initial & Final Setting time IS:12330/8112/12269/455/1489
C) Soundness
D) Fineness
E) Compressive Strength
Field Test
(1) Alignment, Level, Height, width & slope Every bed Within tolerances in spec
5 BLOCKWORK
5.1 Material Check Material (Block)
INSPECTION
REFERENCE
RECORD DOCUMENTS
HYT IRCLASS COFMOW
Checklist P W R/W
Field Test Report
P W R/W
MTC Register R R R
P W R/W
Project Specification P W W
MTC IS 9103 R R R
Checklist P W R/W
Checklist P W R/W
P W R/W
MTC
IS 2185 Part 3-1985 , IS –
6441 (PART – I AND V)
P W R/W
P W R/W
Third Party Test Report
P W R/W
W R/W
MTC IS 2250 : 1981 P W R/W
Mortar cube Register IS 2250:1981 P W R/W
P W R/W
P W R/W
Technical Spec / As per
Check list P W R/W
Method Statement
P W R/W
P W R/W
P W R/W
P W R/W
Checklist P W R/W
P W R/W
P W R/W
P W R/W
Drawing / Technical Spec /
Method Statement P W R/W
P W R/W
P W R/W
P W R/W
P W R/W
P W R/W