Bill No. 6.

1 - General Items
Ite Quanti
m Description ty Unit Rate Amount
RM RM
1.0 Preliminaries

Allow for the provision of -


a Lump
) Performance Bond amounting to 5% of Sum 3,000.00 3,000.00
Contract Sum
b Lump
) All Insurance in accordance to Preamble Sum 5,000.00 5,000.00
to Bill of Quantity
1.1 Lump
Contractor's Superintendence Sum
Provide all necessary superintendence 15,000.00 15,000.0
during the execution of the works including 0
appointment of a site agent
1.2 Lump
Setting out and survey works Sum
Allow for the services of Licensed Surveyor, 5,000.00 5,000.00
approved by the S.O. for setting out of the
works and other survey works in accordance
with the Specification

1.3 Lump -
Office Accomodation for Superintending Sum
Office and his staff
Provide and maintain a site office for the
S.O.'s supervision staff inclusive of furniture
and fitting and all in accordance with
drawings and specification.

1.4 Lump
Contractor's Office and Accommodation Sum
Provide and maintain Contractor's office, store, 5,000.00 5,000.00
workshop, workmen's accommodation necessary
fencing and their removal or reinstatement on
completion of the Works

1.5 Services
a Allow for the provision or water, lighting Lump
) power for the works and for S.O.'s and Sum 1,500.00 1,500.00
Contractor's offices and accommodation of
the contractor's staff

b Lump -
) Allow for the provision of water, lighting and Sum
power for office accommodation for
Superintending Officer and his staff
c Lump
) Allow for the provision of First Aid Box, Helmet, Sum
Boots and all necessary services, guards, 500.00 500.00
watching and pay all charges as required.
1.6 Telephone for S.O.'s Staff Lump
Allow for the installation of a handphone Sum 1,000.00 1,000.00
system for the exclusive use of S.O.'s
representative and payment for all monthly
charges including the bills for the telephone
calls
1.7 Sign Boards Lump
Supply, erect and maintain sign boards in Sum 1,500.00 1,500.00
accordance with the Specification and
drawing

37,500.0
Total Carried Forward 0

General Items

Item Description Quantity Unit Rate Amount


RM RM

Brought Forward : 37,500.00


1.8 Lump
Progress Photographs Sum
Provide colour progress photographs to be 1,000.00 1,000.00
taken when directed by the S.O. Each set
shall consist of eight colour prints of postcard
size. 6 sets of the photograph shall be
submitted at forthnightly interval.

1.9 Temporary Works Lump


Allow for the provision and maintenance of all Sum 5,000.00 5,000.00
temporary works including temporary drains,
access road for both contractors and other
contractors, temporary diversion and all others
as specified by S.O.'s or as shown in the
drawing.
1.10
Plants
Lump
Allow for mobilisation and demobilisation
Sum 15,000.00 15,000.00
of all plants

1.11
Working Hours for S.O.'s Supervisory's Staff
Lump
Allow for the compliance of working hours for
Sum 1,000.00 1,000.00
Superintending Officer's site representatives
1.12
Clearing up site
Lump
Allow for clearing up site during progress and on
Sum 5,000.00 5,000.00
completion of works

1.13 Lump
As-Built Drawings Sum
Allow for the preparation of as built drawings 1,500.00 1,500.00
with Engineer and Licensed Surveyor
endorsement and all attendance of the
Superintending Officer to verify the accuracy of
the drawings.

The as-built drawings shall be prepared


using Autocad or compatible computer
software. 3 sets of paper prints and one set
of diskette containing the file shall be
submitted to the Engineer.

1.14 Traffic Control Lump


Sum 3,000.00 3,000.00
Allow for the provision and maintenance of
temporary road diversion, all traffic or warning sign,
signals, barricades, road barriers and blinking
lamps as compliance with requirement of JKR and
other relevant authorities in connection with the
works
1.15
Co-ordination
Lump
Allow for co-ordination with other contractors
Sum 2,000.00 3,000.00
working on the site

1.16 Compliance to Specification and Conditions of Lump


Contract Sum 500.00 500.00
Allow for the compliance of Specification and
conditions of Contract which are not specifically
mentioned in the Bill

Total Carried To Summary 72,500.00

Bill No. 6.2 Major Drainage Works & Internal Drainage System
Ite Quantit
m Description y Unit Rate Amount
RM RM
Precast Drain
2.1 Excavate and construct precast drain (brickwall to be
paid separately) including lean concrete, mesh fabric,
Grade 20 concrete bedding with X-distance as shown
on drawing , jointing and stepping where required .

(a) 300mm half round drain 2,491 lin. m. 80.00 199,280.00


(b) 450mm half round drain R.O lin. m. 120.00
Brickwork
2.2 Construct cement sand brickwall to sides of half
round drain inclusive of R.C. Struts, crusher run,
weep holes complete with geotextile wrapping to
the thickness as shown on the drawings, cement
mortar rendering and backfilling complete as shown
on the drawing.

(a) 225mm thick 3,186 sq.m. 47.00 149,742.00


(b) 345mm thick 390 sq.m. 65.00 25,350.00
(c) 450mm thick 55 sq.m. 85.00 4,675.00

Pipe Culvert
2.3 Supply and construct precast pipe culvert Class "Y"
to road crossing including spigot, socket, rubber
ring and all necessary joint. Rate to include
excavation, lean concrete, Grade 20 concrete
bedding and surround, mesh fabric reinforcement,

(a) 750 mm dia. (with concrete surround) 34 lin.m 260.00 8,840.00


(b) 900 mm dia. (with concrete surround) R.O lin.m 320.00
(c) 1050 mm dia. (with concrete surround) R.O lin.m 395.00

Culvert Sump For Pipe Culvert


2.4 Excavate, supply and construct cement sand brick sump
at inlet and outlet of culvert to the thickness as shown in
drawings. Rate to include lean concrete, Grade 20
concrete bedding, mesh fabric reinforcement, cement
rendering, R.C strut, stainless steel steps and M.S

(a) Internal size 1050mm x 900mm, depth


not exceeding 1.5m 5 no. 850.00 4,250.00
(b) Internal size 1050mm x 900mm, depth exceeding
1.5m, not exceeding 2.0m 1 no. 1,100.00 1,100.00
(c) Internal size 1200mm x 900mm, depth exceeding
1.5m, not exceeding 2.0m R.O no. 1,350.00
(d) Internal size 1200mm x 900mm, depth exceeding
2m, not exceeding 2.5m R.O no. 1,600.00
(e) Internal size 1350mm x 900mm, depth exceeding R.O no. 1,850.00
2m, not exceeding 2.5m
House Entrance Slab

Total carried to summary 393,237.00


Bill No. 6.3 Road Work

Item Description Quantity Unit Rate Amount


RM RM
Preparation of Pavement Formation
3.1
Excavate and shape the road subgrade to the correct
alignment, levels and gradients as shown on the
drawings, including boxing out and consolidating by a
10 ton smooth-wheeled roller ; part return of
excavated material to shoulder and medium including
fill-in, ram and compact to the required formation level
and gradient; removal of excess excavated material to
filling ground designated by S.O. including filling in,
ram and compaction.

Sub-Base
2,700 sq.m. 2.50 45,900
3.2
Supply, spread and compact sand to the 50mm
compacted thickness.

Road-Base

3.3 Supply, spread and compact approved crushed


rock road base to the compacted thickness as
shown in the drawings

2,700 sq.m. 11.20 189,000

Asphaltic Concrete Surfacing


3.4
Supply and apply emulsified bituminous prime coat to
surface of crushed rock road base
2,700 sq.m. 0.70 10,710.70
3.5
Supply and apply bituminous tack coat to binder
course surface prior to laying of wearing course
2,700 sq.m. 0.70 10,443.30
3.6
Supply , lay and compact asphaltic concrete
surfacing to the compacted thickness as shown in
the drawing

(a) wearing course - 50 mm thick


2,700 sq.m. 23.00 186,487.50
2,700 sq.m. 27.00 218,700
(b) binder course - 60 mm thick

Pavement Marking and Road Sign

3.7
Supply and install "BERHENTI" sign and 300mm wide
stop lines pavement marking with Thermoplastic paint
at all junction to JKR standard.
11 no. 450.00 4,950.00

Total Carried Forward

Bill No. 6.3 Road Work (Con't)

Item Description Quantity Unit Rate Amount


RM RM
Brought Forward : 671,781.70
3.9 To supply and install all road signage complete at all the
road junction governed under area as
shown on the drawings to JKR satisfaction.
2 450.00 900.00
3.10 To mark the pavement of the junction, accerelation and
deceleration lane at all the road junction governed under
Phase 1 as shown in the drawings or as directed by S.O.
and to JKR satisfaction.

(a) 100mm wide broken centre lines no.


1,759 lin.m 2.50 4,397.50
(b) 150mm wide pavement edge lines 3,449 lin.m 3.50 12,071.50

(d) Straight through direction arrow 5 no. 80.00 400.00

(e) Left and right turn direction arrow R.O no. 100.00
(g) Straight through, left and right turn direction arrow 1 no. 120.00 120.00

(f) Left or right turn direction arrow R.O no. 90.00

Kerb
3.11 550 lin.m 25.00 27,500
Excavate, supply and construct precast kerb Type
M1 including 1:3:6 concrete base and haunching,
reinforcement and formwork, where required and
painting complete.

3.13

178 lin.m. 38.00 6,764.00


200 lin.m. 105.00 21,000.00

Replacement of Unsuitable Material

3.15 Excavate and remove from site unsuitable material below R.O m3 30.00
road formation level up to 600 mm deep and replace with
compacted suitable material from contractor own source

Total Carried To Summary 860,700.00


Bill No. 6.4 Sewerage Reticulation

Item Description Quantity Unit Rate Amount


RM RM

Trench Excavation
4.1 (i) Trench excavation of sewer pipe for depth exceeding 1.5 m 12,026.00
but not exceeding 2.0 m including part backfill on completion,
compaction, removal of surplus, shoring and/or sheet pile
where necessary:(a) 225mm dia V.C. pipe
(b) 300mm dia V.C. pipe 20.00 15,485.60
601 lin.m 20.00 2,104.00
R.O
(ii) -ditto- exceeding 2.0m but not exceeding 3.0m lin.m
(a) 225mm dia V.C. pipe
(b) 300mm dia V.C. pipe 596 26.00 12,325.50
lin.m 20.00 2,256.00
105
(iii) -ditto- exceeding 3.0m but not exceeding 4.0m lin.m
(a) 225mm dia V.C. pipe
(b) 300mm dia V.C. pipe 224 55.00
113 lin.m 20.00 4,220.00
(iv) -ditto- exceeding 3.0m but not exceeding 4.0m lin.m
(a) 225mm dia D.I.(Ductile Iron). Pipe(b) 300mm dia V.C.
pipe R.O 80.00
211 lin.m 20.00
lin.m
Extra over item 4.1 for trench excavation in mettalled road. lin.m
4.2 Rate to include cutting of mettalled pavement with R.O 75.00
diamond cutter, reinstatement of mettalled road with
50mm thick sand blanket, 300mm thick crusher run, 50mm
thick binder course and 60mm thick wearing coarse.

4.3 R.O Lump


Ditto ~ for trench excavation under existing road side drains. Sum
Rate to include reinstatement of road side drain. 2,000.00

4.4 R.O Lump


Ditto ~ for trench excavation under existing main drains. Sum
Rate to include reinstatement of pudu cut main drain. 1,000.00

Pipe Laying

Notes : -
All sewer with diameter less than 450mm shall be
vitrified clay pipe (VCP) with flexible joint and comply
with M.S 881 Part 1 1991, M.S. 1061;1986.
Foundation base of sewer must be compacted with
crushed run.

All sewer with diameter 450mm and above shall be


centrifugal spun reinforced concrete pipe (RCP) of
class Z. All RCP shall be internally line with 12mm
thick high alumina cement mortar. All pipe joints with
flexible rubble rings joints.

4.5
Supply and lay sewer pipes complete including
jointing, concrete/granular bedding, haunching all as
specified
(a) 225mm dia V.C. pipe (Class A bedding)
1,421 lin.m 105.00 149,205.00
(b) 300mm dia V.C. pipe (Class A bedding) 429 lin.m 100.00 42,900.00
4.6

Connection to Existing Mainhole


Allow for connection of VCP pipe to existing manhole.
Rate to include reinstatement and make good of Lump
existing manhole. Sum 1,000.00 1,000.00

Carried Forward 241,522.10

Quanti
Item Description ty Unit Rate Amount
RM RM
Brought Forward :
241,522.1
Precast Concrete Manhole 0
4.7 Excavate, supply and construct precast
concrete manholes complete including lean
concrete, Grade 20 cast in-situ concrete ring
base, building in pipes, benching, precast r.c.
chamber, Grade 20 mass concrete surround,
formwork, stainless steel steps, precast r.c.
cover slab complete as detailed and shoring
and/or sheet pile where necessary during
construction.
(manhole cover and frames to be paid separately)
(i
) Manhole type 1 with chamber diameter 1200mm
(for sewer pipe 225mm & 300mm)
2,000.
(a) below ground level to invert level not exceeding 2.0m 14 no 00 28,000.00
(b) ditto exceeding 2.0m but not exceeding 3.0m 11 no 2,800. 30,800.00
00
(c) ditto exceeding 3.0m but not exceeding 4.0m 5 no 3,300. 16,500.00
00
(d) ditto exceeding 4.0m but not exceeding 5.0m 4 no 3,301. 13,204.00
00
4.8
Supply and fix the following for manhole
backdrop including excavation:

(a) D.I. Tee 225mm x 225mm dia including N/A no 150.00


M.S. cover plate

(c) 90 degree medium D.I. Bend 225mm dia.


N/A no 20.00
(e) D.I. Straights 225mm dia N/A lin.m 60.00
(g) concrete grade 15 mix including formwork N/A cu.m 70.00
4.9 Supply and fix Heavy Duty ductile iron manhole 34 no 440.00 14,960.00
covers and frames as specified

344,986.1
Carried Forward 0

Quantit
Item Description y Unit Rate Amount
RM RM
Brought Forward :
344,986.10
Testing of Sewer Line

Lump 2,000.0
4.6 (a) Carry out test for straightness and obstruction on all 1 Sum 0 2,000.00
sewer lines as specified in Clause 4.3(a) of Section 5 of
Specification
Lump 2,000.0
(b) Carry out water testing on all sewer lines as specified in 1 Sum 0 2,000.00
Clause 4.3(b) of Section 5 of Specification

(c) Carry out air testing on all sewer lines as specified in


Clause 4.3(c) of Section 5 of Specification
N/A
(d
Carry out C.C.T.V. Test and submission of test report for
)
sewer lines as directed by S.O. representative or IWK/JPP

(i) 225mm dia. V.C. pipe lin.m


278 25.00 6,937.50
4.7 cu.m
Excavate beyond foundation level as directed by the
S.O. and backfill with selected material (Provisional)
Rate
Service Connection only

4.8 (a
) Excavate, supply and lay 150mm dia. V.C.
service pipe in class A bedding, 225mm dia. x 150mm
dia. v.c. 'Y' junction including concrete thrust block,
150mm dia. x 45 degree v.c. short bend, end cap at
location as directed by S.O. (Provisional) complete as
shown on the drawings
91 no 450.00 40,950.00
(b Rate no 50.00
) Supply and install Marker complete as shown on the Only
drawings
(c Rate no
) To excavate, supply and construct last manhole within Only
housing lot at the depth of 1.35m as shown on the
drawings

d 1 L.s
To supply and install end cap and install marker to D.I
)
pipe for future connection to last manhole of P.S.No.4 165.00

IWK Inspection
4.9 Allow for liasing with IWK/JPP for interim 1 Lump 4,000.00
inspection during construction and final Sum
4,000.0
inspection for handing over
0

Total Carried To Summary 400,873.60


Bill No. 6.5 Water Reticulation
Quantit
Item Description y Unit Rate Amount
RM RM

TRENCH EXCAVATION

Excavate in all material below completed platform


level Trench excavation shall be measured once
only to the full depth of the trench.
5.1 Excavation trench not exceeding 1.5 m deep for
water mains. Rate to include
backfilling,compaction, dewatering, timbering and
removal of surplus excavated material for : (a)
150mm dia. pipe
2,005 lin.m 8.00 16,040.00
(b) 200mm dia. pipe R.O lin.m 10.00

(c) 300mm dia. pipe R.O lin.m 15.00 7,120.00


(d) 450mm dia. pipe 356 lin.m 20.00

-ditto- exceeding 1.5m


5.2 (a) 150mm dia pipe R.O lin.m 15.00
(b) 200mm dia. pipe R.O lin.m 20.00

5.3 (c) 300mm dia. pipe R.O lin.m 30.00 150.00


(d) 450mm dia. pipe R.O lin.m 40.00
15.00
Remove unsuitable materials beyond nominal 10 cu.m
limits of trench excavations as orded by the
S.O. and backfill with selected materials; rate
to include disposal material to spoil pit as
directed (provisional)

5.4 109 cu.m 35.00 3,815.00


Supply, fill, spread and compact approved
sand in pipe trenches and at road crossing.
Rate to include transportation of sand.

5.5 Import selected earth from borrow site, rate to 10 cu.m 15.00 150.00
include excavation, backfilling, ramming and
compaction (provisional)

PIPE LAYING
Notes:

( All spigot and socket ended pipes and


a specials shall be suitable for internally &
) externally welded slip joints

( All steel pipe shall be concrete lined internally


b and bitumen coated externally. All exposed
) steel pipes and specials shall be externally
painted.
( The rate for joining pipe, special or fitting shall
c be deemed to include the supply and
) installation of all joint coupling or mechanical
coupling and jointing material complete

( All flanges shall be suitable for a rating of 16


d bars unless specified otherwise
)

Total Carried To Forward 27,275.00

Water Reticulation
Item Description Quantity Unit Rate Amount
RM RM

Brought Forward 27,275.00


(e) The thickness of steel shells and concrete lining
shall be as stated in the specifications

(f) Plain ended pipes shall be suitable for mechanical


coupling or internally and externally welded collar
joints

(g) all pipe diameters mentioned refer to nominal


diameter.

P/E means plain ended


B/F means both end flanged
F/PE means one flanged end and one plain ended
5.6 Supply, lay and join spigot and socket ended
standard or sized steel water pipe; Rate to
include loading, transport, handle, repair lining
and coating where required, cutting, internally &
externally welding and protection to welded joints
and painting as specified.

(a) 150mm dia. pipe


2,005 lin.m 88.00 176,440.00
(b) 200mm dia. pipe R.O lin.m 126.00

(b) 300mm dia. pipe R.O lin.m 200.00 106,800.00


(d) 450mm dia. pipe 356 lin.m 300.00

Culvert Crossing

5.7
Supply, lay and join steel pipe and special for
crossing over culvert or sump rate to include
1 No. flanged off-take tee for air valve
connection, welding, jointing 4 nos. steel
gusseted bends and 75mm x 6mm thk. M.S.
steel strap as shown on drawing -

(a) 150mm dia. pipe

STEEL SPECIALS

Supply and fix steel specials P/E. Rate to include VA


Dresser joint or mechanical coupling and jointing
material complete
7 no 2,800.00 19,600.00
150mm dia. P/E bend
5.8 (a) up to 30 degree
11 no 210.00 2,310.00
(b) more than 60 degree 7 no 220.00 1,540.00

5.9 Tee barrel plain ended and with flanged branch


(a) 150mm x 150mm dia
12 no 240.00 2,880.00
5.10 Hydrant tee, barrel plain ended with flanged
concentric branch (a) 150mm x 100mm dia

TAPERS
11 no 210.00 2,310.00
5.11 Supply and fix cross P/E

(a) 200mm x 150mm 2 no 450.00 900.00


(b) 300mm x 200 mm R.O no 900.00

Total Carried Forward 340,055.00

Water Reticulation

Item Description Quantity Unit Rate Amount


RM RM

Brought Forward : END 340,055.00


CAPS
5.12 Supply and fix end caps
(a) 150mm dia 1 no 220.00 220.00
(b) 200mm dia R.O no 253.00

(c) 300mm dia R.O no 710.00 850.00


(d) 450mm dia 1 no 850.00

Short piece
5.13 short piece x 600mm long P/E for sluice valve connection
(a) 150mm dia.
8 no. 52.80 422.40
(b) 200mm dia. Rate Only no. 77.00

(c) 300mm dia. Rate Only no. 132.00


(d) 450mm dia 2 no 250.00 500.00

5.14 600mm long flanged and plain ended short piece


for sluice valve connection (a) 150mm dia.

8 no. 660.00 5,280.00


(b) 200mm dia. Rate Only no. 1,210.00

(c) 300mm dia. Rate Only no. 1,870.00


(d) 450mm dia 2 no 2,000.00 4,000.00
Flanged Adaptor
5.15 Supply and fix flanged adaptor for sluice valve connection

(a) 150mm dia.


8 no. 300.00 2,400.00
(b) 200mm dia. Rate Only no. 500.00

(c) 300mm dia. Rate Only no. 800.00 1,800.00


(d) 450mm dia 2 no 900.00
Valves
Supply and fix cast iron fittings and specials for air
valve, sluive valve and Hydrant. Rate to include
mechanical coupling and jointing material

5.16 Air Valves


a) 50mm dia. double orifice air valve complete
with isolating stopcock 7 no 650.00 4,550.00

Sluice Valves

5.17 a) 150mm dia. double flanged sluice valves


suitable for a working pressure of 16 bars 8 no 700.00 5,600.00
b) 200mm dia. ditto - Rate Only no 960.00

c) 300mm dia. ditto (d) Rate Only no 2,000.00 7,000.00


450mm dia 2 no 3,500.00

Double oulet pillar hydrant


5.18 (a) 100mm dia. x 300mm B/F ductile iron
lengthening piece
11 no 110.00 1,210.00
(b) 100mm dia. x 500mm B/F ductile iron
lengthening piece
11 no 132.00 1,452.00
(c) 100mm dia. x 1000mm B/F ductile iron
lengthening piece
11 no 187.00 2,057.00
(d) 100mm dia. sluice valve, P.N. 16 rating, B/F 11 no 412.50 4,537.50

(e) 100mm dia. Ductile iron duckfoot bend 11 no 9.00 99.00

(f) Ductile iron double outlet pillar and painted as


directed by the S.O., rate to include concrete base

11 no 305.00 3,355.00

Total Carried Forward 385,387.90


Water Reticulation

Item Description Quantity Unit Rate Amount


RM RM

Brought Forward : Scour 385,387.90


valve
5.19 Scour valve including 100 mm dia. sluice
valve, ductile iron lengthening piece, flanged
spigot, gibault coupling and short length of
100mm dia. uPVC Pipe class D to drain
complete as shown on drawing. Rate to
include reinstatement of drains to its original
state ( excluding tee)

3 no 1,200.00 3,600.00
5.20 Washout 3 no. 1,200.00 3,600.00
Washout at dead end including 100mm
dia. sluice valve, brick chamber and short
length of uPVC pipe class D to drain
complete as shown on Drawing. Rate to
include reinstatement of drains to its
original state

P.C Markers and Chambers

5.21 Supply and fix precast concrete marker,


including painting as directed for (a)
sluice valve 10 no 75.00 750.00
(b) air valve 7 no 75.00 525.00

5.22 (c) scour valve/ washout 3 no 75.00 225.00


(e) pipe 5 no 75.00 375.00

Supply and construct precast concrete chamber


as detailed on drawing; rate to include
excavation, sand bedding, complete with
covers requirement
(a) hydrant valve no 300.00 3,300.00
11
(b) sluice valve 10 no 300.00 3,000.00

(c) air valve 7 no 300.00 2,100.00

5.23
Supply and construct brickwork chamber as
detailed on drawing; rate to include
excavation, sand bedding , complete with
covers to JBA requirement (a) scour valve

Thrust and Anchor Blocks


3 no 650.00 1,950.00
5.24 Supply and construct thrust, diaphram and
anchor blocks. Rate to include excavation
backfilling, compaction, concrete mix as
specified, formwork, steel reinforcement and all
as shown on the drawings.

10 cu.m 260.00 2,600.00

Total Carried Forward 407,412.90

Water Reticulation

Item Description Quantity Unit Rate Amount


RM RM
Brought Forward : 407,412.90

Miscellaneous

5.25
Allow for pressure and leakage test including
supply of water and instruments.
Lump Sum 3,500.00 0.00
5.26
Allow for disinfection and flushing of pipe
including supply for chemicals, sampling
Lump Sum 2,000.00 0.00
and chemical analysis Service
Connection

5.27
Excavate and provide 25mm dia service
connection at the following M.S pipe rate
to include malleable D.I. Clamp saddle,
ferrul, tapping complete
(a) 150mm dia
91 no 120.00 10,920.00
5.28

Excavate, supply and lay 25mm dia S.S. pipe from


tapping point up to the meter position rate to
include bends, laying through drain and all
reinstatement back to its original conditions,
Supplying and laying sand or quarry dush to
S.Steel service connection pipe at road crossing
and all as shown on the drawings.

382 lin.m 55.00 21,021.00


5.29 Supply and fix (all fitting shall be of Stainless Steel)

(a) 15mm dia ball cock


91 no 9.00 819.00
(b) 25mm x 15mm Elbow 91 no 17.00 1,547.00

(c) 20mm Nipple 91 no 7.50 682.50

(d) 20mm Integrated Lockable Valve (ILV) 91 no 40.00 3,640.00

(e) 25mm x 20mm Bush 91 no 5.30 482.30

(f) 25mm x 20mm Reducer 91 no 18.00 1,638.00

(g) 15mm Nipple 91 no 6.00 546.00

Zone Meter (District Metering)

5.3 Supply and install a zone meter complete with by Rate Only no 15,000.00
pass and all necessary fitting, bends, felxible
coupling,flange adapter, valves and bulk meter
(provisional)

Sampling Box

5.31 Supply and install a PUAS approved sampling box. Location Rate Only no 5,000.00
to be reconfirmed by PUAS.

Total Carried to Summary 448,708.70


SUMMARY OF TENDER

Contract For Construction And Completion of Road & Drainage Works, Sewer
Reticulation, Water Reticulation And Ancillary Work For Bungalow and Semi-D
lots at Phase 3 For Cadangan Pembangunan Perumahan Di Atas Lot, Kampung
Gesir Tengah, Daerah Kuala Kubu Bharu Selangor Darul Ehsan

Bill No Description
Amount
RM

1 General Items 72,500.00

2 Major Drainage Works & Internal Drainage System 410,407.00

3 Road Work 723,496.20

4 Sewerage Reticulation 400,873.60

5 Water Reticulation 448,708.70

Sub-Total Amount 2,055,985.50

Add Levy as required by The Construction Industry Development


Board = Sub-Total Amount x ( 0.125%/99.875% )
2,573.20

Total carried forward to Form of Tender 2,058,558.70