Professional Documents
Culture Documents
23 10th - JCC-WR - Minutes - 07 - 10 - 15
23 10th - JCC-WR - Minutes - 07 - 10 - 15
Minutes of 10th Joint Co-ordination Committee meeting of IPPs granted LTA in WR held on 07.10.2015 at
POWERGRID, Gurgaon
1. The 10th Joint Co-ordination Committee meeting of IPPs in WR was held at POWERGRID Office, Gurgaon on 7th Oct, 2015.
The list of participants of the meeting is enclosed at Annexure-I.
2. DGM (CTU Planning), POWERGRID stated that Minutes of the 9th meeting of the Joint Co-ordination Committee of IPPs
granted LTA in WR held on 25.05.2015 were issued vide letter ref. no. C/CTU/W/OA/9JCC dated 24.06.2015 and Special Joint
Co-ordination Committee meeting of IPPs granted LTA in WR, SR & ER held on 07.07.2015 were issued vide ref. no.
C/CTU/JCC/Special dated 24.07.2015. As no observations/comments were received on the minutes, accordingly the minutes of
9th Joint Co-ordination Committee and Special Joint Co-ordination Committee of IPPs in WR, as circulated were confirmed.
3. DGM (CTU Planning) mentioned that LTOA/LTA to most of the applicants was granted on the basis of target regions. It is
therefore high time that the firm beneficiaries should be finalized at the earliest as the common transmission system required is
completed / very close to completion. However till firm beneficiaries are finalized the end links cannot be planned which may
lead to constraints in supply of power. Upon completion of the corridor, the LTA/LTOA customers shall be liable to pay the
applicable transmission charges and requisite payment security needs to be established by the LTA/LTOA customers, as per
the CERC Regulations.
4. It was also stressed that generation developers should ensure completion of their dedicated lines to match with the
commissioning of transmission network in order to prevent bottling up of power. POWERGRID stated that interim arrangements
through LILO of existing lines were provided only as a contingency measure and the IPPs need to focus on implementing the
final dedicated transmission system. Constraints are liable to be faced in evacuation of power from the generation projects
connected through LILO arrangements, provided as an interim arrangement. Therefore, all the IPPs should expedite the
construction of their dedicated line as well as the terminating bays at the Pooling Station.
5. Agenda for the 10th JCC meeting was taken-up and the outcome of the same is placed below
Page 1 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum Beneficiaries beneficiary (9 JCC / Special (10 JCC) Connectivity line &
(MW) WR NR JCC) Status
CHATTISGARH IPP
Rajasthan: LILO of one ckt of ACB RERC order reserved for adoption
U-1: U-1:
Maruti Clean Coal 200 MW TPS - WR PS(Bilaspur) of tariff for the PPA with
1 171 126 45 Commissioned, Commissioned,
(1X300) CSPTCL : 14 400kV D/c line is Rajasthan. Representative agreed
COD in Jun’15 COD in Jul’15
MW Commissioned for opening of LC by Oct’ 15
Dheeru gen - WR PS No representative was available to
2 Dheeru Power Gen 450 367.5 82.5 NIL Uncertain Not Attended
(Bilaspur) 400kV D/c line update the status.
Chhattisgarh State Plant & Corridor wise PPA details
3 Power Trading Co. 432 260 172 NIL Not Attended were to be informed. A final letter
Ltd* may be issued by CTU
MADHYA PRADESH IPP
Jaiprakash Power MP-465.3 U-1& 2 : Jaiprakash - Satna
4 Ventures Ltd. 1240.8 853.5 387.3 MW Commissioned in Not Attended 400kV D/c (High LTA of 465.3 MW under operation.
(2X660) (Operational) Sep’ 14 & Feb’ 15 Capacity) is ready
Aryan MP - Developer informed in past JCC
Aryan MP Power
Vindhyachal Pooling that project has been abandoned
5 generation Pvt. Ltd 1122.0 841.5 280.5 NIL Abandoned Not Attended
station 400kV D/c (High and petition for cancellation of
(2X600)
Capacity) LTA is filed in CERC.
Bina TPS - Suitable
Location (along Bina
Jaiprakash Power Ventures has
Bina Power Supply (PG) - Bina (MPPTCL)
acquired the company and filed
6 Company Ltd 265.35 132.68 132.67 NIL Commissioned Commissioned 400kV D/c line) - 400kV
petition in CERC for
(2X250) D/c (High Capacity)
relinquishment of LTA granted.
line: Termination of one
ckt to Bina (PG) & other
Page 2 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum Beneficiaries beneficiary (9 JCC / Special (10 JCC) Connectivity line &
(MW) WR NR JCC) Status
ckt to Bina (MPPTCL)-
Commissioned
Total 3681.15 2581.1 432.17
HIGH CAPACITY TRANSMISSION CORRIDOR – V
(Transmission System Associated with Chhattisgarh IPPs)
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC ) Connectivity line &
(MW)
WR NR ER JCC) Status
RAIGARH (KOTRA) COMPLEX
400kV RKM- Raigarh
RKM Powergen Ltd U-1/2: Jun/Jul’ 15 U-1/2: Oct/Nov’15 PS (Near Kotra) D/c Start-up power is drawing
1 819 419 200 200 NIL
(4X360) U-3/4: Aug/Sep’ 15 U-3/4: Mar/May’16 (Quad) line – through LILO arrangement
expected by Dec’ 15
400kV Athena - Representative informed
Athena
UP: 300 MW U-1: Dec’ 15 U-1: Dec’ 15 Raigarh PS (Near that 92% works of the
2 Chhattisgarh 683 342 341
(LOI) U-2: Mar’ 16 U-2: Mar’ 16 Kotra) D/c (Quad) line generation plant are
Power Ltd. (2X600)
– expected by Dec’ 15 completed.
400kV SKS - Raigarh
U-1/2: Feb’16/ PS (Near Kotra) D/c
SKS Power Gen. (LOI )
3 683 319 364 Dec’15 Not Attended line (Triple/Quad) -
(Ch) Ltd. (4X300) 100- RERC
U-3/4: Jan/Mar’ 18 Commissioned in
Feb’ 15
400kV Korba (W)-
Korba West Power U-1: COD in Raigarh PS (near
4 240 140 100 CSPTCL: 5% U-1: Mar'14 (COD)
Co. Ltd. (1X600) Mar'14 Kotra) D/c line –
expected by Nov’15
CSPTCL: 424 Representative stated
400kV Visa Power-
MW cancellation of coal block
Raigarh PS (Near
West Bengal: allocation as a force
Visa Power Ltd. U-1: Mar/Jun' 17 U-1: Sep’17 Kotra) D/c (Triple)
5 678 478 200 200 MW with majeure condition. CTU
(1X600+1X660) U-2: Sep' 19 U-2: Mar’19 line - expected by
option to informed issue may be
Jun’16
increase to treated in line with the in
510 MW APTEL/CERC orders in
Page 3 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC ) Connectivity line &
(MW)
WR NR ER JCC) Status
similar cases..
It was informed to the
generation developer that
liability towards payment of
transmission charges starts
as and when the identified
transmission system gets
commissioned.
Tamil Nadu: U-1: Feb’ 14 DB Power – Raigarh
208 MW U-2: PS (near Kotra)
DB Power Ltd. Tamil Nadu - 208 MW LTA
6 705 530 175 Rajasthan- Synchronized in Not Attended 400kV D/c
(2X600) to SR operational.
410 (matter in Mar’ 15, COD yet (Triple/Quad) line -
RERC) to be achieved commissioned
RAIGARH (TAMNAR) COMPLEX
U-1/2: Mar’14 U-1/2: Mar’14 JPL – Raigarh PS
Tamil Nadu :
(COD) (COD) (near Tamnar) 2xD/c
400 MW
Jindal Power Ltd. U-3: Jan’15 (COD) U-3: Jan’15 (COD) 400kV (Quad) – 3
7 1400 700 700 Kerala: 190 &
(4X600) U-4: synchronized U-4: synchronized ckts commissioned,
142.5 MW th
in Mar’ 15, COD yet in Mar’ 15, COD 4 circuit expected by
to be declared expected in Mar’16 Oct’15
225MW from Dongamahua
Jindal Power Ltd. CPP (4x135MW) + 175MW
8 400 400 NIL Commissioned Commissioned
(400 MW) from existing Tamnar TPS
(4x250MW)
TRN approached CERC
through
TRN - Raigarh PS
IA:17/2015 in Petition No.
(near Tamnar) 400kV
TRN Energy Pvt. UP : 390 MW U-1: Jan’ 16 U-1: Jan’ 16 92/2015 which was held to
9 393 243 150 D/c line –
Ltd (2X300) U-2: Jun’ 16 U-2: Jun’ 16 be infructuous. CERC
Commissioned in
referred the Matter to
Jul’15
Committee for
relinquishment charges
JANJGIR-CHAMPA COMPLEX
KSK Mahanadi Tamil Nadu: U-1/2: U-1/2: 400kV KSK – Generation developer was
10 2340 2340
Power Co. Ltd. 500 MW Aug'13/Aug'14 Aug'13/Aug'14 Champa Pooling suggested to expedite the
Page 4 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC ) Connectivity line &
(MW)
WR NR ER JCC) Status
(6X600) UP: 1000 MW (COD) (COD); Station 2xD/c (Quad) implementation of the
st
Gujarat : U-3/4: Jan/Apr' 16 U-3/4: Sep’16/ – 1 D/c line dedicated transmission lines
1010MW U-5/6: Jul/Oct' 16 Mar’17; expected by Dec’15;
nd
U-5/6: Sep/Dec’17 2 line by Mar’ 16
Tamil Nadu : U-1/2:
Balco –
200 MW Commissioned, Representative not attended
Bharat Aluminium U-1/2: Dharamjaygarh /
Kerala : 95 COD yet to be JCC, however forwarded the
11 Co. Ltd. (BALCO- 200 100 100 Commissioned, Korba PS 400kV D/c
MW achieved status of progress. 100 MW
4X300) U-3/4: Oct' 15 (Triple/Quad) line –
Chhattisgarh: U-3/4: Jun/Aug' to Tamil Nadu Operational.
expected by Oct’ 15
55 MW 15
Representative informed
that implementation
resumed after resolving land
issues, 81% of U-1 & 60% of
LANCO – Champa U-2 works completed.
Lanco Amarkantak
U-1: Aug’ 16 U-1: Aug’16 PS 400kV D/c (Quad) It was informed to the
12 Power Pvt. Ltd. 858 858 NIL
U-2: Dec’ 16 U-2: Dec’16 line - expected by representative that liability
(2X660)
Apr’16 towards payment of
transmission charges shall
start as and when identified
transmission system gets
commissioned.
Representative not attended
CSPTCL : 25 U-1: U-1: Vandana Vidhyut –
Vandana Vidyut JCC. Status sent vide letter
MW Commissioned; Apr’14 (COD) ; Dharamjaygarh PS
13 Ltd. (2X135 + 265 165 100 dated 08.10.15.
Telangana : U-2:Sep’15 U-2:Mar’16 400kV D/c line :
1X270)
120 MW U-3:Apr’18 U-3:Apr’19 Mar’17
RAIGARH COMPLEX
Page 5 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC ) Connectivity line &
(MW)
WR NR ER JCC) Status
Ltd* with time schedule by
CSPTCL
Total 16288 10907 5181 200
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC) Connectivity line
(MW)
WR NR ER SR JCC) & Status
PPA with Haryana is
under dispute; It was
informed by Lanco
Pathadi TPS - WR representative that they
PS (near Sipat) will open LC on behalf of
PTC(Lanco-II) Commissioned in
1 300 0 300 0 0 NIL Commissioned 400kV D/c (Quad) PTC for operation of
(1X300) Sep’14
line - LTA/ Further the LANCO
commissioned representative consented
to be present in the next
hearing in the PTC
matter (166/MP/2015).
Representative agreed
Mahan TPS – WR that they shall revert
Mahan (Essar U-1: Apr’ 13 (COD) U-1: Apr’ 13 (COD)
2 1200 1200 0 0 0 MP: 150 MW PS 400kV D/c line - back on opening of LC;
power Ltd.(2X600) U-2: Jun’ 15 U-2: Dec’ 15
expected by Mar’16 Copy of PPA to be
forwarded
KPCL - Champa Developer informed that
Karnataka Power
PS 400kV D/c project is uncertain as
3 Corporation Ltd 763 0 0 0 763 NIL Uncertain Uncertain
(Quad) line fuel linkage yet to be
(2X800)
made by GoI.
Page 6 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC) Connectivity line
(MW)
WR NR ER SR JCC) & Status
MB TPS - Jabalpur 392 MW operational;
MB Power
UP-192 MW U-1: May’ 15 (COD) U-1: May’ 15 (COD) PS 400kV D/c Representative
4 (Madhya Pradesh) 392 200 192 0 0
(Operational) U-2 : Aug’ 15 U-2: Dec’15 (Triple) line – requested for return of
Limited (2X600)
Commissioned CBG as per Regulations.
Consistently not
attending the JCC
Pipavav TPS –
meetings, accordingly it
Pipavav Energy Pirana 400kV D/c
5 1200 550 290 360 0 NIL Not Attended Not Attended may be put-up to WR
Private Ltd (triple) line
constituents meeting for
Conn/LTA applications
for discussion & decision
Developer informed that
Uncertain
Salaya TPS - as the project is based
(No certain date
Bachau 400kV D/c on imported coal, it has
given despite
Essar Power (Triple) line - become unviable for
6 250 0 0 0 250 NIL Uncertain repetitive
Gujarat Ltd. advanced stage of which they are
requests) –
completion discussing with lenders &
3 years from
GUVNL. MoEF clearance
MoEF Clearance
is not available.
TEL(DGEN) TPS-
Navsari 400kV D/c Not generating power
Torrent Energy U-1/2/3: Dec’ 14
7 800 400 400 0 0 NIL Not Attended (Triple/Quad) line – due to non-availability of
Ltd. (COD)
commissioned - Gas
Jul’13
Reduction of quantum
LILO of one ckt of from 300 to 270 MW
Dhariwal Bhadravati - Parli (120-WR; 150-NR);
Tamil Nadu: Commissioned in
8 Infrastructure Ltd. 300 150 150 0 0 Commissioned 400kV line at LTA applied for SR for
100 MW Aug’14
Dhariwal TPS - 100MW and the same
Commissioned quantum need to be
relinquished from WR;
Representative not
Kakrapar NPP - attended JCC, status of
9 NPCIL (Kakrapar) 1400 1400 0 0 0 NIL Not attended Not attended
Navsari 400kV D/c progress not submitted
th
since 8 JCC.
Page 7 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Sl. LTOA / LTA LTOA Target Beneficiaries Firm Comm. schedule Comm. schedule Dedicated / Remarks
th th
No. Applicant Quantum beneficiary (9 JCC / Special (10 JCC) Connectivity line
(MW)
WR NR ER SR JCC) & Status
Interconnection at
Commissioned in
NTPC 495.7 400kV Bus of
10 495.78 0 0 0 NIL Oct’15 Aug’15,
(Vindhyachal -V) 8 Vindhyachal TPS-
COD by Oct’15
IV switchyard
Lara - Raigarh PS
1586. U1: Apr’17; U1: Apr’17;
11 NTPC (Lara-I) 1586.51 0 0 0 NIL (Kotra) 400 kV D/c
51 U2: Oct’17 U2: Oct’17
line
Consistently not
attending the JCC
meetings, accordingly it
Heavy Water
12 17 17 0 0 0 NIL Uncertain Uncertain may be put-up to WR
Board
constituents meeting for
Conn/LTA applications
for discussion & decision
It was inquired from
representative about the
total quantum of LTA
Jhabua TPS - sought including Kerala &
Kerala: Jabalpur PS 400kV MPPMCL vis-à-vis the
13 Jhabua Power Ltd 210 210 0 0 0 U-1: Sep’ 15 U-1: Dec’15
204.25 MW D/c (Triple) line - total capacity of Unit-I.
Commissioned For this it was agreed by
the representative that
they shall send the
clarifications.
MPPMCL to give letter
Jhabua TPS -
MP Power for consent of payment of
Jabalpur Pool
14 Management 246 246 0 0 0 NIL Dec’15 Dec’15 relinquishment charges
400kV D/c (Triple)
Company Ltd. for reduction of LTA on
line: Commissioned
account of auxiliary.
6974.
1382
Total 9729.09 09 0 1013
Page 8 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Transfer of power from generation projects near Bilaspur complex in Chhattisgarh & MP projects
Page 9 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Establishment of Pooling Stations at Raigarh (Near Kotra) and Raipur for IPP Generation Projects in Chhattisgarh Part-1
Establishment of Pooling Stations at Champa and Raigarh (Near Tamnar) for IPP Generation Projects in Chhattisgarh Part-2
Page 10 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Integration of Pooling Stations in Chhattisgarh with Central part of WR for IPP Generation Projects in Chhattisgarh Part-3
Transmission System strengthening in Western part of WR for IPP Generation Projects in Chhattisgarh Part-4
Page 11 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Page 12 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
System strengthening in Wardha-Aurangabad corridor for IPP Projects in projects in Chhattisgarh Part-7
Page 13 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
[TBCB award placed to succesful bidder Sterlite in Mar ’12 with commissioning schedule of 39 months(June ’15)]
Page 14 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Page 15 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Annexure-I
List of Participants in the 10th Joint Co-ordination Committee meeting of IPPs granted LTA in WR held on 07.10.2015
Page 16 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Page 17 of 18
Minutes of 10th JCC Meeting of IPPs granted LTA in WR
Page 18 of 18