Gouting Procedure 0005 (PI-SD-GRP-BBL4-0005)
Gouting Procedure 0005 (PI-SD-GRP-BBL4-0005)
SUB CONTRACTOR
PT. FERROSTAAL INDONESIA
MECHANICAL / ELECTRICAL INSTALLATION
DOC NO : PI-SD-GRP-BBL4-0005
TITLE
GROUTING PROCEDURE
A APPROVED
STATUS
B APPROVED WITH COMMENTS
C NOT APPROVED
D RE-SUBMIT
ACTION
E FINAL
NOTES :
PI-SD-GRP-BBL4-0005
GROUTING PROCEDURE
22 Jan 2011
PLTU 4 BANGKA Rev 0
BELITUNG 2 X 16.5 MW
PT. POESER INDONESIA – SDMECO (J.O)
Page 2 of 6
PT. FERROSTAAL INDONESIA
Revisio Sectio
Description
n n
Table of Contents
1. INTRODUCTION 4
1.1 Definition and Acronyms....................................................................................................4
2. REFERENCES 4
2.1 Specification.........................................................................................................................4
2.2 Code and Standard.............................................................................................................4
3. MATERIAL 4
4. FOUNDATION PREPARATION 4
5. GROUTING 5
6. CURRING AND FINISHING 6
7. INSPECTION 6
PI-SD-GRP-BBL4-0005
GROUTING PROCEDURE
22 Jan 2011
PLTU 4 BANGKA Rev 0
BELITUNG 2 X 16.5 MW
PT. POESER INDONESIA – SDMECO (J.O)
Page 4 of 6
PT. FERROSTAAL INDONESIA
1. INTRODUCTION
1.1 Scope
This procedure covers basic requirement for grouting and make sure all
grouting work for equipment erection work are follow the technical
specification, project standard, product manufacturer recommendation.
2. REFERENCES
2.1 Specification
This document shall use for the related documents as mention below:
Main Contractor Specification
3. MATERIAL
2.1 Grout material
2.2 Material Portland cement mortar grout as follow civil work or Main Contractor
Specification
4. FOUNDATION PREPARATION
4.1. Padding Plate
PI-SD-GRP-BBL4-0005
GROUTING PROCEDURE
22 Jan 2011
PLTU 4 BANGKA Rev 0
BELITUNG 2 X 16.5 MW
PT. POESER INDONESIA – SDMECO (J.O)
Page 5 of 6
PT. FERROSTAAL INDONESIA
Padding plates of different thickness and size shall be used to level the
equipments. Non shrink grout material will be used set the padding plates as
per drawing.
4.2 All loose concrete defective areas on foundation surface shall be removing by
chipping, or by other means. Foundation surface must be roughened to
minimum depth of 3 mm.
4.3 Foundation surface and equipment base plates must be free of all oil,
greases, paint, rust, loose mill scale and dirt.
4.4 For premixed grout the foundation shall be well saturated with water for
approximately 24 hours prior to grouting or as specified by the grout
manufacturer.
4.5 Water shall be kept out of anchor bolt sleeves prior to grout.
5. GROUTING
5.1 Prior to grouting of the equipment base, the following work has to complete:
5.1.1 Tightening of bolt
5.1.2 Foundation to be cleaned
5.1.3 Wedges are tack weld
5.1.4 Install formwork to be leak proof
5.1.5 Foundation
5.2 Mixing, placing and curing of the grouting material shall be in accordance with
the manufacturer specification intended material to be used will be Sitka
Grout 215 for the grouting of foundation. Sitka Epoxy 42 for the grouting
anchor specialist at Anchor Box. Mix Portland cement and gravel will be
according to with mix design of concrete.
5.3 Prior to grout equipment base, formwork has to be install around the
foundation by using ½” thickness plywood material.
5.4 Pouring of grout material on to foundation should be done at one pouring
point and should let the grout follow by gravity force to prevent any air pocket
occurred below the best of equipment.
5.5 For equipment with common base two type of grout to used.
5.6 Grout temperature during placing shall not exceed 32°C, useless otherwise
indicated.
PI-SD-GRP-BBL4-0005
GROUTING PROCEDURE
22 Jan 2011
PLTU 4 BANGKA Rev 0
BELITUNG 2 X 16.5 MW
PT. POESER INDONESIA – SDMECO (J.O)
Page 6 of 6
PT. FERROSTAAL INDONESIA
7. INSPECTION
All grouting work shall be visually inspected in accordance with requirement the
inspection report shall be repair