Professional Documents
Culture Documents
RMP Horizontal and Vertical Clearance For Wires
RMP Horizontal and Vertical Clearance For Wires
RMP Horizontal and Vertical Clearance For Wires
Disclaimers
Disclaimer for Rocky Mountain Power and Pacific Power employees: this standard provides a reference to the
National Electric Safety Code and has been expanded to cover common voltages used by Rocky Mountain
Power and Pacific Power. As an estimator or designer you are responsible for verifying that this standard is cur-
rent and that additional clearance requirements including but not limited to elevation adders, state and local
rules or regulations are applied appropriately or in concert with this standard.
Disclaimer for Contractors: this standard is developed for internal company use only and is provided as a ref-
erence document. Contractors are responsible for understanding and adhering to all federal, state and local
rules and regulations which may supersede this standard.
Purpose
This standard provides minimum clearances of wires, conductors, cables and equipment from buildings,
bridges, swimming pools, and other installations as required by the National Electrical Safety Code (NESC)
Rule 234. These minimum clearances must be maintained on all lines operated by Rocky Mountain Power and
Pacific Power in the states of Utah, Wyoming, Idaho, Oregon, and Washington. These clearances do not apply
in the state of California where General Order No. 95 is the governing regulation.
Scope
This standard contains extrapolated tables for company use from Rule 234 of the 2017 edition of the
NESC. This standard also contains tables that were not provided by the code, but were derived from applic-
able sections of the NESC Rule 234 (2017). Since the NESC (2017) provides clearance values for voltages
up to 22 kV or 50 kV line to ground, highlighted sections of the tables were developed to include clearance val-
ues for higher voltages used by the company. These values incorporate elevation adder and/or voltage
adder for all applicable line voltages and were calculated based on the NESC Rule 234G1 and 234G2
(2017).
NOTE 1: text in this font, that follows "NESC Rule" headings in this document is taken directly from NESC C2-
2017 (National Electrical Safety Code® (NESC®) (Accredited Standards Committee C2-2017). All rights
reserved. Figure titles, table headings, and footnotes indicate figure or table content that has been taken dir-
ectly from NESC C2-2017.
NOTE 2: it is the user’s responsibility to ensure that the calculated clearances are compliant with the most cur-
rent edition of the NESC.
Additional Clearances
1. Construction Tolerance – line construction has many aspects that have inherent variability, which
include but are not limited to mapping inaccuracies, structure setting depth variations, and conductor sag
variations. For transmission line construction it is strongly recommended that a construction tolerance of
three (3) feet be added to the clearances listed in this standard to ensure that the NESC minimum clear-
ances are met under the worst loading conditions.
2. Elevation Adder – for voltages exceeding 50 kV line to ground and at elevations exceeding 3300 feet
above sea level, the additional clearance calculated from the NESC Rule 234G1 (2017) must be
increased by 3% for each 1000 feet in excess of 3300 feet above mean sea level. The tables in this stand-
ard list calculated values for elevations up to 12300 feet in increments of 3000 feet.
3. Local Governance – some state, city, or county authorities may require greater minimum clearances than
the NESC minimum clearances within their jurisdiction. It is the responsibility of the user to ensure com-
pliance with all pertinent ordinances for overhead line construction in the local area.
A. Application
In each of Rules 234B, 234C, and 234D, horizontal clearance requirements are specified for two conditions: (1) the con-
ductor without wind displacement (at rest), and (2) the conductor with wind displacement. In each case, the clearance
requirements for both conditions shall be satisfied.
1. Vertical and horizontal clearances (no wind displacement)
The vertical and horizontal clearances specified in Rules 234B, 234C, 234D, 234E, 234F, and 234I apply under
whichever conditions of the following conductor temperature and loading conditions produces the closest approach.
Rules 234A1a, 234A1b, and 234A1c apply above and alongside subject installations; Rule 234A1d applies below and
alongside subject installations.
a. 50 °C (120 °F), no wind displacement, final sag.
b. The maximum conductor temperature for which the line is designed to operate, if greater than 50 °C (120 °F),
no wind displacement, final sag.
c. 0 °C (32 °F), no wind displacement, final sag, with radial thickness of ice, if any, specified in NESC Table
230-1 for the zone concerned.
d. The minimum conductor temperature for which the line is designed, no wind displacement, initial sag.
EXCEPTION: Vertical or lateral conductors or cables attached directly to the surface of a supporting structure
in accordance with other rules are not subject to the provisions of this rule.
NOTE: The phase and neutral conductors of a supply line are normally considered separately when determining
the sag of each due to temperature rise.
NESC Rule 234B (2017) Clearances of Wires, Conductors, and Cables from Other
Supporting Structures
Wires, conductors, or cables of one line passing near a lighting support, traffic signal support, a supporting
structure of a second line, or intermediate poles in skip-span construction, without being attached thereto, shall
have clearance from any part of such structure not less than the following:
Horizontal Clearances
Table 1—Horizontal Clearance of Conductors from Other Supporting Structures NO WIND‡
Note: Table cell revisions are in the company's green table revision style and also italicized to help them stand out.
Horizontal clearance required without wind (ft.)
Conductor or cable Elevation: Elevation: Elevation: Elevation:
Sea level to 3300 ft. 3301 to 6300 ft. 6301 to 9300 ft. 9301 to 12300 ft.
Up to 22 kV phase-to-ground (ft.)† 5.0 5.0 5.0 5.0
22 kV to 70 kV phase-to-ground
6.6 6.8 6.9 7.1
115 kV phase-to-phase (ft.)
70 kV to 84 kV phase-to-ground
7.1 7.3 7.5 7.7
138 kV phase-to-phase (ft.)
84 kV to 98 kV phase-to-ground
7.6 7.9 8.1 8.4
161 kV phase-to-phase (ft.)
98 kV to 140 kV phase-to-ground
9.0 9.4 9.8 10.1
230 kV phase-to-phase (ft.)
140 kV to 210 kV phase-to-ground
11.3 11.9 12.5 13.1
345 kV phase-to-phase (ft.)
210 kV to 318 kV phase-to-ground
14.9 15.8 16.7 17.6
500 kV phase-to-phase (ft.)
† EXCEPTION: For effectively grounded guys and messengers, insulated communication conductors and cables, neutrals
meeting Rule 230E1, and cables of 300 V or less to ground meeting the requirements of Rule 230C1, 230C2, or 230C3, the
horizontal clearance may be reduced to 900 mm (3 ft.).
‡ The NESC (2017) does not provide a table for horizontal clearances (without wind) of wires, conductors, or cables from
other supporting structures. The base value of 5.0 ft. was obtained from the NESC Rule 234B1a (2017), and the voltage
and elevation adders were calculated from the NESC Rule 234G1 and 234G2 (2017). The calculated values were rounded
up to the nearest tenth of a foot.
Vertical Clearances
Table 4—Horizontal Clearances WITH WIND of Wires, Conductors, Cables, and Rigid Live
Parts from Buildings, Signs, Billboards, Chimneys, Radio and Television Antennas, Tanks,
Flagpoles and Flags, Banners, and Other Installations Except Bridges†
Note: Table cell revisions are in the company's green table revision style and also italicized to help them stand out.
Horizontal clearance required when displaced by wind
Elevation: Elevation: Elevation:
Conductor or cable
(m.) (ft.) 3301 to 6300 ft. 6301 to 9300 ft. 9301 to 12300 ft.
(ft.) (ft.) (ft.)
Open supply conductors, 0 to 750 V① 1.1 3.5 3.5 3.5 3.5
230C2 cable, above 750 V 1.1 3.5 3.5 3.5 3.5
230C3 cable, above 750 V 1.1 3.5 3.5 3.5 3.5
Open supply conductors, over
1.4 4.5 4.5 4.5 4.5
750 V to 22 kV
22 kV to 27 kV phase-to-ground
-- 4.7 4.7 4.7 4.7
46 kV phase-to-phase (ft.)
27 kV to 42 kV phase-to-ground
-- 5.2 5.2 5.2 5.2
69 kV phase-to-phase (ft.)
42 kV to 70 kV phase-to-ground
-- 6.1 6.3 6.4 6.6
115 kV phase-to-phase (ft.)
70 kV to 84 kV phase-to-ground
-- 6.6 6.8 7.0 7.2
138 kV phase-to-phase
84 kV to 98 kV phase-to-ground
-- 7.1 7.4 7.6 7.9
161 kV phase-to-phase (ft.)
98 kV to 140 kV phase-to-ground
-- 8.5 8.9 9.3 9.6
230 kV phase-to-phase (ft.)
140 kV to 210 kV phase-to-ground
-- 10.8 11.4 12.0 12.6
345 kV phase-to-phase (ft.)
210 kV to 318 kV phase-to-ground
-- 14.4 15.3 16.2 17.1
500 kV phase-to-phase (ft.)
EXCEPTION 2: Where the voltage between conductors meeting Rule 230D does not exceed 300 V, or where the
voltage of cables meeting Rule 230C2 or 230C3 does not exceed 750 V, or where the cable meets Rule 230C1,
and the roof or balcony is not readily accessible, the clearance over the roof or balcony, including the drip loop
shall be not less than either of the following:
Table 5—(Expanded NESC Table 234-1) Clearance of wires, conductors, cables, and unguarded rigid live parts adjacent but not attached to buildings
and other installations except bridges
(Voltages are phase-to-ground for effectively grounded circuits and those other circuits where all ground faults are cleared by promptly de-energizing the faulted section, both initially and following subsequent breaker operations. See the defin-
itions section for voltages of other systems. Clearances are with NO WIND displacement except where stated in the footnotes below. See Rules 234A, 234C1a, 234C2, and 234H4.) Table revisions are in green and italicized.
Insulated Unguarded rigid
communication live parts, 0 to Open Supply Conductors
conductors and 750 V; Elevation Range: Sea Level to 3300 ft.†
cables; messengers; noninsulated Unguarded
overhead shield/ communication rigid live parts,
surge-protection conductors; Supply over 750 V to
wires; effectively Supply ungrounded cables over 22 kV; ungroun-
98 kV to 140 kV phase-to-ground
27 kV to 42 kV phase-to-ground
22 kV to 27 kV phase-to-ground
70 kV to 84 kV phase-to-ground
84 kV to 98 kV phase-to-ground
42 kV to 70 kV phase to-ground
Open supply
ungrounded por- to 750 V 0 to 750 V; and ing Rule portions of
98 kV to 140 kV phase-to-ground
27 kV to 42 kV phase-to-ground
22 kV to 27 kV phase-to-ground
70 kV to 84 kV phase-to-ground
84 kV to 98 kV phase-to-ground
42 kV to 70 kV phase to-ground
grounded guys; 750 V cases, 0 to 750 ing Rule guys ply con-
† Unhighlighted columns courtesy of IEEE, (National Electrical Safety Code® (NESC®) (Accredited Standards Committee C2-2017). All rights reserved. The highlighted columns are not in the NESC Table 234-1 (2017). They were
added to indicate minimum clearance requirements for voltages above 22 kV line to ground, and the values were calculated based on the NESC Rule 234G1 (2017). Values are rounded up to the nearest tenth of a foot. Revisions
are in green and italicized.
98 kV to 140 kV phase-to-ground
98 kV to 140 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
345 kV phase-to-phase (Ft.)
1. Buildings
a. Horizontal
(1) To walls, projections, and
7.5② ⑩ 9.3 9.8 10.4 11.9 14.4 18.3 9.4 10.0 10.6 12.3 15.0 19.2 9.6 10.2 10.9 12.6 15.6 20.1
guarded windows
(2) To unguarded windows⑧ 7.5⑩ 9.3 9.8 10.4 11.9 14.4 18.3 9.4 10.0 10.6 12.3 15.0 19.2 9.6 10.2 10.9 12.6 15.6 20.1
(3) To balconies and areas readily
7.5⑩ 9.3 9.8 10.4 11.9 14.4 18.3 9.4 10.0 10.6 12.3 15.0 19.2 9.6 10.2 10.9 12.6 15.6 20.1
accessible to pedestrians③
b. Vertical⑭
(1) Over or under roofs or pro-
jections not readily accessible to 12.5 14.3 14.8 15.4 16.9 19.4 23.3 14.4 15.0 15.6 17.3 20.0 24.2 14.6 15.2 15.9 17.6 20.6 25.1
pedestrians③
(2) Over or under balconies,
porches, decks, and roofs readily 13.5 15.3 15.8 16.4 17.9 20.4 24.3 15.4 16.0 16.6 18.3 21.0 25.2 15.6 16.2 16.9 18.6 21.6 26.1
accessible to pedestrians③
(3) Over roofs, ramps, decks, and
loading docks accessible to
13.5 15.3 15.8 16.4 17.9 20.4 24.3 15.4 16.0 16.6 18.3 21.0 25.2 15.6 16.2 16.9 18.6 21.6 26.1
vehicles but not subject to truck
traffic ⑥
† Unhighlighted columns courtesy of IEEE, (National Electrical Safety Code® (NESC®) (Accredited Standards Committee C2-2017). All rights reserved. The highlighted columns are not in the NESC Table 234-1 (2017). This
table was created to indicate minimum clearance requirements for voltages above 50 kV line to ground and at elevations exceeding 3300 feet above sea level. The values were calculated based on the NESC Rule 234G1 and
234G2 (2017) and rounded up to the nearest tenth of a foot. Revisions are in green and italicized.
98 kV to 140 kV phase-to-ground
98 kV to 140 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
345 kV phase-to-phase (Ft.)
TC 151 Clearances of Wires, Conductors, Cables, and Equipment from Buildings, Bridges, and Other Installations
1 8 Ap r 1 7
1 8 Ap r1 7
NOTE: The following notes appear courtesy IEEE, (National Electrical Safety Code® (NESC®) (Accredited
Standards Committee C2-2017). All rights reserved.
NOTE: The clearance values shown in this table are computed by adding the applicable Mechanical and Electrical (M
& E) value of Table A-1 to the applicable Reference Component of Table A-2b of Appendix A.
① Not used in this edition.
② Where available space will not permit this value, the clearance may be reduced by 2 ft. provided the wires, con-
ductors, or cables, including splices and taps, and unguarded rigid live parts have a covering that provides sufficient
dielectric strength to limit the likelihood of a short circuit in case of momentary contact with a structure or building.
③ A roof, balcony, or similar structure is considered readily accessible to pedestrians if it can be casually accessed
through a doorway, window, ramp, stairway, or permanently mounted ladder by a person, on foot, who neither exerts
extraordinary physical effort nor employs tools or devices to gain entry. A permanently mounted ladder is not con-
sidered a means of access if its bottom rung is 8 ft. or more from the ground or other permanently installed access-
ible surface or is otherwise equipped with barriers to inhibit climbing by unauthorized persons.
④ The required clearances shall be to the closest approach of motorized signs or moving portions of installations
covered by Rule 234C.
⑤ The portion(s) of span guys between guy insulators and the portion(s) of anchor guys above guy insulators that
are not effectively grounded shall have clearances based on the highest voltage to which they may be exposed due to a
slack conductor or guy.
⑥ For the purpose of this rule, trucks are defined as any vehicle exceeding 8 ft. in height.
⑦ This clearance may be reduced to 3 in for the effectively grounded portions of guys.
⑧ Windows not designed to open may have the clearances permitted for walls and projections.
⑨ The clearance at rest shall be not less than the value shown in this table. Also, when the conductor or cable is dis-
placed by wind, the clearance shall be not less than 3.5 ft.; see Rule 234C1b.
⑩ The clearance at rest shall be not less than the value shown in this table. Also, when the conductor or cable is dis-
placed by wind, the clearance shall be not less than 4.5 ft.; see Rule 234C1b.
⑪ The portion of anchor guys below the lowest insulator meeting Rules 279A1 and 215C5 may have the same clear-
ance as effectively grounded guys.
⑫ This footnote not used in this edition.
⑬ This footnote not used in this edition.
⑭ For clearances above railings, walls, or parapets around balconies, decks, or roofs, use the clearances required for
row 1b(1). For such clearances where an outside stairway exists to provide access to such balconies, decks, or roofs,
use the clearances required for row 2b(2).
⑮ Does not include neutral conductors meeting Rule 230E1.
⑯ These clearance values also apply to guy insulators.
⑰ It is presumed that a flag or banner is fully extended but that there is no deflection or displacement of the flagpole
or other supporting structure due to wind and that the conductors, cables, or rigid live parts are not displaced by the
wind. The specified clearance is measured to the point of maximum displacement of the banner or flag towards the
overhead utility facility.
⑱ When designing a line to accommodate oversized vehicles, these clearance values shall be increased by the dif-
ference between the known height of the oversized vehicle and 14 ft.
Table 7—Horizontal Clearance WITH WIND of Wires, Conductors, Cables, and Unguarded
Rigid Live Parts from Bridges†
Horizontal clearance required when displaced by wind
Elevation: Elevation: Elevation:
Conductor or cable
(m) (ft.) 3301 to 6300 ft. 6301 to 9300 ft. 9301 to 12300 ft.
(ft.) (ft.) (ft.)
Open supply conductors, 0 to 750 V① 1.1 3.5 3.5 3.5 3.5
230C2 cable, above 750 V 1.1 3.5 3.5 3.5 3.5
230C3 cable, above 750 V 1.1 3.5 3.5 3.5 3.5
Open supply conductors,
1.4 4.5 4.5 4.5 4.5
over 750 V to 22 kV
22 kV to 27 kV phase-to-ground
-- 4.7 4.7 4.7 4.7
46 kV phase-to-phase (ft.)
27 kV to 42 kV phase-to-ground
-- 5.2 5.2 5.2 5.2
69 kV phase-to-phase (ft.)
42 kV to 70 kV phase-to-ground
-- 6.1 6.3 6.4 6.6
115 kV phase-to-phase (ft.)
70 kV to 84 kV phase-to-ground
-- 6.6 6.8 7.0 7.2
138 kV phase-to-phase
84 kV to 98 kV phase-to-ground
-- 7.1 7.4 7.6 7.9
161 kV phase-to-phase (ft.)
98 kV to 140 kV phase-to-ground
-- 8.5 8.9 9.3 9.6
230 kV phase-to-phase (ft.)
140 kV to 210 kV phase-to-ground
-- 10.8 11.4 12.0 12.6
345 kV phase-to-phase (ft.)
210 kV to 318 kV phase-to-ground
-- 14.4 15.3 16.2 17.1
500 kV phase-to-phase (ft.)
Table 8—(Expanded NESC Table 234-2) Clearance of wires, conductors, cables, and unguarded rigid live parts from bridges
(Voltages are phase-to-ground for effectively grounded circuits and those other circuits where all ground faults are cleared by promptly de-energizing the faulted section, both initially and following subsequent breaker operations.
See the definitions section for voltages of other systems. Clearances are with NO WIND displacement except where stated in the footnotes below. See Rules 234A, 234D1a, and 234H4.) Table revisions are in green and italicized.
98 kV to 140 kV phase-to-ground
27 kV to 42 kV phase-to-ground
22 kV to 27 kV phase-to-ground
70 kV to 84 kV phase-to-ground
84 kV to 98 kV phase-to-ground
42 kV to 70 kV phase to-ground
of 0 to 750 V meeting over 750 V meeting supply ungrounded equipment
(1) Attached ③ ⑤ 3.0 3.5⑧ 5.5⑨ 5.0 5.7 6.2 7.1 7.6 8.0 9.4 11.8 15.4
(2) Not attached ④ ⑤ 4.0 4.5⑧ 6.5⑨ 6.0 6.7 7.2 8.1 8.6 9.0 10.4 12.8 16.4
† Unhighlighted columns courtesy of IEEE, (National Electrical Safety Code® (NESC®) (Accredited Standards Committee C2-2017). All rights reserved. The highlighted columns are not in the
NESC Table 234-2 (2017). They were added to indicate minimum clearance requirements for voltages above 22 kV line to ground, and the values were calculated based on the NESC Rule 234G1
(2017). Values are rounded up to the nearest tenth of a foot.
98 kV to 140 kV phase-to-ground
98 kV to 140 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
345 kV phase-to-phase (Ft.)
† Unhighlighted columns courtesy of IEEE, (National Electrical Safety Code® (NESC® ) (Accredited Standards Committee C2-2017). All rights reserved. The highlighted columns are not in the
NESC Table 234-2 (2017). This table was created to indicate minimum clearance requirements for voltages above 50 kV line to ground and at elevations exceeding 3300 feet above sea level. The
values were calculated based on the NESC Rule 234G1 and 234G2 (2017) and rounded up to the nearest tenth of a foot.
TC 151 Clearances of Wires, Conductors, Cables, and Equipment from Buildings, Bridges, and Other Installations
1 8 Ap r 1 7
1 8 Ap r1 7
NOTE: The following notes appear courtesy IEEE, (National Electrical Safety Code® (NESC®) (Accredited
Standards Committee C2-2017). All rights reserved.
① Where over traveled ways on or near bridges, the clearances of Rule 232 apply also.
② Bridge seats of steel bridges carried on masonry, brick, or concrete abutments that require frequent access for inspec-
tion shall be considered as readily accessible portions.
③ Clearance from supply conductors to supporting arms and brackets attached to bridges shall be the same as specified
in Table 235-6 (Rule 235E1) if the supporting arms and brackets are owned, operated, or maintained by the same utility.
④ The portion(s) of span guys between guy insulators and the portion(s) of anchor guys above guy insulators that are
not effectively grounded shall have clearances based on the highest voltage to which they may be exposed due to a slack
conductor or guy.
⑤ Where conductors passing under bridges are adequately guarded against contact by unauthorized persons and can be
de-energized and grounded per Rule 444D for maintenance of the bridge, clearances of the conductors from the bridge,
at any point, may have the clearances specified in Table 235-6 for clearance from surfaces of support arms plus one-
half the final sag at 15 °C (60 °F), no wind of the conductor at that point.
⑥ Where the bridge has moving parts, such as a lift. bridge, the required clearances shall be maintained throughout the
full range of movement of the bridge or any attachment thereto.
⑦ Where permitted by the bridge owner, supply cables may be run in rigid conduit attached directly to the bridge. Refer
to Part 3 for installation rules.
⑧ The clearance at rest shall be not less than the value shown in this table. Also, when the conductor or cable is dis-
placed by wind, the clearance shall be not less than 3.5 ft.; see Rule 234D1b.
⑨ The clearance at rest shall be not less than the value shown in this table. Also, when the conductor or cable is dis-
placed by wind, the clearance shall be not less than 4.5 ft.; see Rule 234D1b.
⑩ Does not include neutral conductors meeting Rule 230E1.
⑪ These clearance values also apply to guy insulators.
Table 10—(Expanded NESC Table 234-3) Clearance of wires, conductors, cables, or unguarded
rigid live parts over or near swimming pools
(Voltages are phase-to-ground for effectively grounded circuits and those other circuits where all ground faults are cleared by promptly de-energizing the faulted section, both initially and following subsequent breaker operations.
See the definitions section for voltages of other systems. Clearances are with NO WIND displacement. Table revisions are in green and italicized.
See Rules 234A, 234E1, 234E2, and 234H4.)
Open Supply Conductors
Insulated com- Unguarded rigid live Elevation Range: Sea Level to 3300 ft.†
munication conductors parts,
and cables; mes- 0 to 750 V; Supply
Unguarded rigid
sengers; overhead noninsulated com- cables over
live parts over
98 kV to 140 kV phase-to-ground
27 kV to 42 kV phase-to-ground
22 kV to 27 kV phase-to-ground
70 kV to 84 kV phase-to-ground
84 kV to 98 kV phase-to-ground
750 V to 22 kV;
42 kV to 70 kV phase to-ground
Open sup-
tection wires; groun- ductors; supply cables meeting
† Unhighlighted columns courtesy of IEEE, (National Electrical Safety Code® (NESC® ) (Accredited Standards Committee C2-2017). All rights reserved. The highlighted columns are not in the
NESC Table 234-3 (2017). They were added to indicate minimum clearance requirements for voltages above 22 kV line to ground, and the values were calculated based on the NESC Rule 234G1
(2017). Values are rounded up to the nearest tenth of a foot.
98 kV to 140 kV phase-to-ground
98 kV to 140 kV phase-to-ground
Open supply
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
345 kV phase-to-phase (Ft.)
TC 151 Clearances of Wires, Conductors, Cables, and Equipment from Buildings, Bridges, and Other Installations
1 8 Ap r 1 7
1 8 Ap r1 7
b. Any side of a grain bin is considered to be a nonloading side if it is so designated, or if it is so closely abutting
another structure or obstruction, or so close to a public road or other right-of-way that a portable auger, con-
veyor, or elevator is not reasonably anticipated to be used over that side or portion to fill the grain bin.
c. Where an agreement excludes the use of portable augers, conveyors, or elevators from a designated portion of a
grain bin, such portion is considered to be a nonloading side.
Figure 4 (NESC 234-4a)—Clearance envelope for grain bins filled by permanently installed
augers, conveyors, or elevators
Legend
P = probe clearance 5.5 m. (18 ft.) required by Rule 234F1a
H = horizontal clearance 4.6 m. (15 ft.) required by Rule 234F1b
T = transition clearance
V1 = vertical clearance above a building required by Rule 234C (Table 234-1)
V2 = vertical clearance required by Rule 232B (Table 232-1 or 232-2)
Figure 5 (NESC 234-4b)—Clearance envelope for grain bins filled by portable augers,
conveyors, or elevators
Table 12—Clearances of wires, conductors, cables, and rigid live parts from grain bins†
Open Supply Conductors Elevation Range: Sea Level to 3300 ft.
84 kV to 98 kV phase-to-ground
42 kV to 70 kV phase to-ground
70 kV to 84 kV phase-to-ground
NESC Rule 234F1a (2017) 18.0 18.2 18.7 19.6 20.1 20.6 22.0 24.3 27.9
NESC Rule 234F1b (2017) 15.0 15.2 15.7 16.6 17.1 17.6 22.0 21.3 24.9
† The NESC (2017) does not provide this table. This table was created to indicate minimum clearance requirements for voltages above 22 kV line to ground. The base values were taken from the
NESC Rule 234F1 (2017), and calculated values were derived based on the NESC Rule 234G1 (2017) and rounded up to the nearest tenth of a foot.
‡ Does not apply to a neutral conductor meeting Rule 230E1.
98 kV to 140 kV phase-to-ground
98 kV to 140 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
50 kV to 70 kV phase-to-ground
84 kV to 98 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
70 kV to 84 kV phase-to-ground
345 kV phase-to-phase (Ft.)
† The NESC (2017) does not provide this table. This table was created to indicate minimum clearance requirements for voltages above 50 kV line to ground and at elevations exceeding 3300 feet
above sea level. The base values were taken from the NESC Rule 234F1 (2017), and calculated values were derived based on the NESC Rule 234G1 and 234G2 (2017) and rounded up to the
nearest tenth of a foot.
‡ Does not apply to a neutral conductor meeting Rule 230E1.
TC 151 Clearances of Wires, Conductors, Cables, and Equipment from Buildings, Bridges, and Other Installations
1 8 Ap r 1 7
1 8 Ap r1 7
The horizontal and vertical clearances of unguarded rigid live parts such as potheads, transformer bushings, surge
arresters, and short lengths of supply conductors connected thereto, which are not subject to variation in sag, shall
be not less than those required by Rule 234C or 234D, as applicable.
2. Clearance to equipment cases
Equipment shall be mounted so that clearances are not less than that given by Rules 234J2a, 234J2b, and 234J2c.
a. Effectively grounded equipment cases may be located on or adjacent to buildings, bridges, or other structures
provided that clearances for unguarded rigid live parts of such equipment, as specified in Rule 234J1, are
maintained.
b. Equipment cases that are not effectively grounded shall be located so that the clearances of Rule 234C or
234D, as applicable, are maintained.
c. Equipment cases shall be located so as not to serve as a means of approach to unguarded rigid live parts by
unqualified persons.
NOTE: Rule 234J is not subject to the loading conditions of Rule 234A.
Deviation from this standard requires prior approval. Contact the standards engineering manager for approval processes and forms.
Printed versions of this standard may be out of date. Please consult the online standards for the most recent version. This standard shall be used and duplicated
only in support of PacifiCorp projects. ©2017 by PacifiCorp.