Rebar Takeoff For 6 Months
Rebar Takeoff For 6 Months
ESTIMATED KG. AS PER BID PLAN(PER FLOOR) RCR AS PER BID PLAN TOTAL ESTIMATED KGS. FOR 6 MONTHS DURATION
FOUNDATION 1169.21 99920.6866 85.46 99920.6866
COLUMNS 399.28 259224.5544 649.23 3110694.6528
SHEARWALLS 94.86 24248.1132 255.62 290977.3584
BEAMS AND GIRDERS 188.0925 55428.978825 294.69 665147.7459
SLAB 106.81 9648.1473 90.33 115777.7676
TOTAL: 4282518.2113
NOTE: This computation was based on the bid plans from DADEC and assuming that the schedule will be 2 floors every month.