INTERNAL DAILY REPORT

PROJECT : REBUILDING THE BRIDGE OF THE MAYORAL OFFICE NOMOR : . . . . . . . . / FN / III / 2020

WORK PACKAGE : STRUCTURAL HARI : Senin

FOUNDATION BRIDGE TANGGAL : 23-Mar-20

CONTRACTOR : CV. FITRAH NUR LOKASI : MAYOR BRIDGE

CLIENT b : PT. UPC SIDRAP BAYU ENERGI

NO. WORKING ITEM WORK STATUS REMARKS/COMMENTS

1 Pek, Persiapan = Pemasangan Dinding Pagar Pengaman.

NO. WORK PLAN FOR TOMORROW WORK STATUS REMARKS / COMMENTS

1 Pek, Persiapan = Pemasangan dinding Pagar pengaman dan Rambu Lalu lintas

A. MAN POWER B. TOOLS/ EQUIMENT C. MATERIAL DELIVERED

Job role Number Item Qty Unit Condition Item Qty Unit Purpose

Supervisor 1 Gergagji 2 Pcs baik Balok Kayu 52 btg


Logistic 1 Palu 2 Pcs baik Seng 50 lbr
Pelaksana 1 meter 2 Pcs baik Paku 5 kg
Tukang 4

D. WORKING HOUR E. CLIMATIC F. PROBLEM / DELAYS

08.00 - 12.00 cerah


12.00 - 13.00 cerah
13.00 - 17.00 cerah

G. PHOTOGRAPHS - attached

H. PIC of UPC & Contractor;

Contractor Reps. UPC Repr.

MUKHLIS MUSTAMIN ( . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . . .)
Supervisor