Professional Documents
Culture Documents
Hutama-Rsea VS Citra MMTC
Hutama-Rsea VS Citra MMTC
CITRA METRO
MANILA TOLLWAYS CORPORATION, Respondent
FACTS:
During the construction of the Skyway Project, petitioner Hutama wrote respondent
Citra on several occasions requesting payment of the formers interim billings,
pursuant to the provisions of the EPCC. Respondent Citra only partially paid the
interim billings, thus, prompting petitioner Hutama to demand the payment of the
outstanding balance. Respondent Citra however still failed to do so.
On December 15, 1999, the Skyway Project was opened for public use, and toll fees
were accordingly collected. After informing respondent Citra that the construction of
the Skyway Project was already complete, petitioner Hutama reiterated its demand
that respondent Citra pay the outstanding balance on the interim billings, as well as
the Early Completion Bonus agreed upon in the EPCC. Respondent Citra refused to
comply with petitioners demands.
On May 24, 2004, petitioner, through counsel, sent a letter to respondent Citra
demanding payment of the following: a) the outstanding balance on the interim
billings; b) the amount of petitioners final billing; c) early completion bonus; and d)
interest charges on the delayed payment.
Petitioner Hutama filed a Request for Arbitration, seeking to enforce its money
claims against respondent.
Respondent Citra averred that the CIAC had no jurisdiction over the case as the
filing by petitioner was premature because a condition precedent, i.e., prior referral
by the parties of their dispute to the Dispute Adjudication Board (DAB), required by
Clause 20.4 of the EPCC, had not been satisfied or complied with.
The CIAC ruled that it had jurisdiction over the case, and that the determination of
whether petitioner had complied with Clause 20.4 of the EPCC was a factual issue
that may be resolved during the trial. Respondent Citra filed a Motion for
Reconsideration of the CIAC Order but was denied by the same.
Respondent Citra filed a special civil action for certiorari and prohibition. CA ruled in
favor of respondent Citra and annulled the Order of the CIAC, and enjoined the said
Commission from proceeding with the case until the dispute between petitioner and
respondent had been referred to and decided by the DAB. Petitioner Hutama filed a
Motion for Reconsideration. Denied.
Petitioner filed the instant petition for review before the Supreme Court raising the
issue of whether CIAC has jurisdiction over the case.
ISSUE:
HELD:
Prior referral to DAB as provided for in Clause 20.4 of EPCC is not a condition
precedent before CIAC can assume jurisdiction over the dispute in the case.
The CIAC shall have jurisdiction over a dispute involving a construction contract if:
Even in the absence of such a clause in the construction contract, the parties still
agree to submit their dispute to arbitration.
The bare fact that the parties herein incorporated an arbitration clause in the EPCC
is sufficient to vest the CIAC with jurisdiction over any construction controversy or
claim between the parties. The arbitration clause in the construction contract ipso
facto vested the CIAC with jurisdiction.