Estimate For Boq.
Estimate For Boq.
FUEL OF DUMPTRUCK :
EQUIPMENTS
RATE (PESO) UNITS FUEL RATE UNITS CU.M. / HR. SQ.M. / HR. FUEL RATE x DUMPING DISTANCE x NO. OF TRIPS * NO. OF DAYS * NO. OF TRUCKS
ROAD GRADER 1700 PER HR. 15 PER HR. 50.25 335
ROAD ROLLER 1600 PER HR. 10 PER HR. 50.25 335 Sample 1555.2
CHAINSAW 180 PER HR. 2 PER HR.
PLATE COMPACTOR 150 PER HR. 1 PER HR. 35 233.33 SPECIAL CASES
BACKHOE 2200 PER HR. 18 PER HR. 30 200 Item 100 - Clearing and Grubbing
BULLDOZER 3540 PER HR. 25 PER HR. 50 333.33
DUMPTRUCK 800 PER HR. 0.9 PER KM SQ.M. / Day
BATCHING PLANT 50 PER DAY Bulldozer 3000
TRANSIT MIXER 700 PER HR. 7 PER HR. Backhoe 3000
PAYLOADER 1800 PER HR. 18 PER HR. 90 600
WATERTRUCK W/ PUMP 750 PER HR. 0.9 PER HR. SPL - 2 Project Billboard (4' x 8') 2.00 each
ELF TRUCK 600 PER HR. 0.9 PER HR. sizes Coco Lumber 18.00 pcs
ELECTRIC GEN SET 200 PER HR. 3 PER HR. 2 x 2 x 10 60.00 bd.ft
ONE BAGGER MIXER 180 PER HR. 1 PER HR. 2.4 2 x 3 x 10 90.00 bd.ft
VIBRATOR 180 PER HR. 3 PER HR. 2x3x8 72.00 bd.ft
KNEADING MACHINE 180 PER HR. 3 PER HR. Tarpaulin 4' x 8' 64.00 sq.ft.
JACK HAMMER 350 PER HR. PER HR. CWN # 2 Depends 2.00 box
MANUAL BAR CUTTER 500 PER HR. PER HR. 4 TONS/HR CWN # 4 Use always 2.00 box
907.185 KG/HR PLY WOOD (4' x 8') 2.00 sheet
CU.M/TRIP
Estimate of Gabion
a
c
h h b
a
b
Computation for proposed Gabion Table
a (m) b (m)
Area =
Proposed Gabion 1.00 20.00
= 0.5 * (1 + 20) * 5 Gabion (1mx2mx1m) 1.00 2.00
= 52.50 sq.m.
Volume = 52.50 cu.m.
No. of 1 m x 2 m x 1 m Gabion
Gabion Volume
no. of Gabion = 52.50 / 2
Volume = 1 m x 2 m x 1 m = 26.25 pcs
= 2.00 cu.m. 27 pcs
Costing:
Boulder Volume
Amount
45,900.00
42,000.00
87,900.00
P 1,674.29
Project Safety And Health
Labor No. of personnel Rate /hr
First Aider 450.00
Project Billboard
Labor No. of personnel Rate/hr
Carpenter 1 340.00
Laborer 2 340.00
Traffic Management
Labor No. of personnel Rate/hr
Flagmen 2.00 340.00
Carpenter 1.00 340.00
Laborer 1.00 340.00
Price Capacity
Item No. : 100
Labor : Foreman & Laborer
Price Capacity
Item No. : 102
Labor : Foreman & Laborer
Price Capacity
Item No. : 102(3)a
Labor : Foreman & Laborer
Price Capacity
Item No. : 103 (3)
Labor : Foreman & Laborer
Equipment: Backhoe(18ltr/hr)
Dump Truck (1ltr/hr) 800.00 rate/hr
Price Capacity
Item No. : 103 (6)
Labor : Foreman & Laborer
Equipment: Backhoe(18ltr/hr)
Dump Truck (1ltr/hr) 800.00 rate/hr 1.00 ltrs/hr
Materials : Diesel 35.00 rate/ltr
Oil 110.00 rate/ltr
Foundation Fill 5,200.00 T/L
rvey Instrument (Rental) 1 set = 100,000
BOX CULVERT ESTIMATE
2pcs each bar no. in the box culvert per section except no. 6
WINGWALL:
Splicing:
Desired Length
=
comerical length # of Splice
Assume cover 40 mm
CLEAR t BAR 1 BAR 2 BAR 3
SPAN HEIGHT SPACING SPACING SPACING
mm DIA. DIA. DIA.
(s) (h) (mm) (mm) (mm)
2400 280 16 260 16 260 16 260
3000
2750 280 16 260 16 260 16 260
HEIGHT 2.4
WIDTH 3 LENGTH 12.1
NO. OF LENGTH PCS OF
Bar no. SPACING Total Length (m) Bar no.
PCS (mm) BAR 6
1 260 92 4860 38 447.1 1
2 260 92 3280 26 301.8 2
3 260 92 3880 30 357 3
4 260 92 6360 50 585.1 4
5 200 120 1800 14 216 5
TOTAL 158 BAR 6 Length
Length of Bar 6 12.1 m
Total Length of Bar 6 1911.8 m
4 1 92 92 m
no. of splice no. of splice
6 2 158 168 m
Summary:
DATAS NEEDED
WINGWALL COMPUTATION: h+t
2.68
HEIGHT 2.8
WIDTH 3 LENGTH 12.8
NO. OF LENGTH PCS OF
SPACING Total Length (m)
PCS (mm) BAR 6
260 98 5210 40 510.6
260 98 3630 28 355.7
260 98 3880 30 380.2
260 98 6535 52 640.4
200 128 1800 14 230.4
TOTAL 164
Length of Bar 6 12.8 m
Total Length of Bar 6 2099.2 m
Summary:
DATAS NEEDED
L
4.41
(TWO VERTICAL BARS PER SECTION)
Size of Pipe Concrete 317 Kg. / Sq. cm. (4500 lb/sq. in)
ID ID W A B C E P
Grout
vol 5.726 cu.m. total
cement 28.63 bags total
sand 2.29 cu.m. total
b/sq. in) Grouted Riprap and Stone Masonry
Minimum
Reinforcement 10 cu.m.
Sq.cm./m. of pipe
1 Line Each
= 25.74 bags
4.23
2 Line Each Sand = 0.2 x 10
4.66
2 Line Each
= 2 cu.m.
6.56
Boulders = 1.2 x 10
= 12
capacity
15 for 910 and below dia.
12 for 1220 and above dia.
Labor
Thermoplastic Detailed Estimate
Factors:
No. of
Area = Length x Strip x Thickness
= 4310 x 1 x 0.15
= 646.5 sq.m. (Center Line)
= 4310 x 2 x 0.1
= 862 sq.m. (Edge Line)
Summary:
Additional of 5% as wastage
Dimension of Holes
Concrete Post No. of Holes : 3
Dimension of Concrete Post Length : 0.2
Width : 0.1 m Thickness : 0.15 m
Length : 0.85 m Spacing : 3m Volume of =
holes: =
Volume of Post
V = 0.1 x 0.85 x 0.15
= 0.01275 m³
No. of CHB =
`
No. of Post =
n = 419.5 ÷ 3 =
= 139.8333 ≈ 139 x 2 no. of side ≈
278 pcs
Total Volume of Fill
Total Volume Post = 278 x 0.01275
= 3.545 m³
Canal Slab Stiffener
Base : 1.1 m Height : 0.15 m Length : 0.8
Width : 0.15
Volume of Slab = 1.1 x 0.15 x 419.5
= 69.218 m³ Volume of Stiffener =
=
Given: Height : 1.00 m no. of side : 2 side
no. of Stiffener =
Assume: Thickness of Plaster = 0.01 m =
≈
Volume of Plaster = 1 x 419.5 x 0.01 x 2
= 8.390 m³ Total Volume of Stifffener
Summary:
Total
(Total Surface Area of Area of
Area - Conc. ÷ CHB
Post.
419.5 x 0.85 x 2 - 278 x (.1 x .85) ÷ 0.4 x 0.2
8619
8619 pcs
= 8619 x 0.006
= 51.714 m³
Page 1
Stiffener
m Thickness : 0.1 m
m Spacing : 4m
419.5 ÷ 4
104.875
104 pcs
= 104 x 0.012
= 1.248 m³
Page 2
CALCULATION OF GUARD RAIL POST
LENGTH OF GUARD RAIL : m
VOLUME OF CONCRETE
Volume of Concrete = L x W x H
=
RAIL POST