Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 25

FOR DUMPTRUCK COMPUTATION

NOTE: PAYLOADER = DUMPTRUCK


HAULING TIME AND MOTION NO. OF TRIPS PER DAY :
QUANTITY = 699.60 cu.m = 8 HR/DAY X 60 MIN/HR
HAULING DISTANCE = 24 KM 101.14286 MIN
= 4.00 TRIPS/DAY
DUMPTRUCK CYCLE TIME NO. OF DT NEEDED :
LOADING TIME = 8 MIN x = 101.142857142857 MIN
TURNING TIME = 2 MIN 8 MIN
TOTAL = 10 MIN = 12.6428571428571 UNIT/S
SAY = 12 UNIT/S 3 unit/s
TRAVEL TIME, LOADED @ 30 KPH VOLUME HAULED PER DAY
= HAULING DIST ÷ 30 KPH = 4.00 TRIPS/DAY X 3 UNIT/S X 10
= 48 MIN = 120.00 CU.M
UNLOADING AND TURNING TIME = 2 MIN
TRAVEL TIME, EMPTY @ 35 KPH NO. OF DAYS TO COMPLETE HAULING
= HAULING DIST ÷ 35 KPH = QUANTITY (in cu.m) ÷ VOLUME HAULED PER DAY
= 41.1428571428572 MIN = 699.60 ÷ 120.00
TOTAL CYLCYE TIME = 101.142857142857 MIN = 5.83
SAY = 6.00 DAYS
= 47 HOURS

FUEL OF DUMPTRUCK :
EQUIPMENTS
RATE (PESO) UNITS FUEL RATE UNITS CU.M. / HR. SQ.M. / HR. FUEL RATE x DUMPING DISTANCE x NO. OF TRIPS * NO. OF DAYS * NO. OF TRUCKS
ROAD GRADER 1700 PER HR. 15 PER HR. 50.25 335
ROAD ROLLER 1600 PER HR. 10 PER HR. 50.25 335 Sample 1555.2
CHAINSAW 180 PER HR. 2 PER HR.
PLATE COMPACTOR 150 PER HR. 1 PER HR. 35 233.33 SPECIAL CASES
BACKHOE 2200 PER HR. 18 PER HR. 30 200 Item 100 - Clearing and Grubbing
BULLDOZER 3540 PER HR. 25 PER HR. 50 333.33
DUMPTRUCK 800 PER HR. 0.9 PER KM SQ.M. / Day
BATCHING PLANT 50 PER DAY Bulldozer 3000
TRANSIT MIXER 700 PER HR. 7 PER HR. Backhoe 3000
PAYLOADER 1800 PER HR. 18 PER HR. 90 600
WATERTRUCK W/ PUMP 750 PER HR. 0.9 PER HR. SPL - 2 Project Billboard (4' x 8') 2.00 each
ELF TRUCK 600 PER HR. 0.9 PER HR. sizes Coco Lumber 18.00 pcs
ELECTRIC GEN SET 200 PER HR. 3 PER HR. 2 x 2 x 10 60.00 bd.ft
ONE BAGGER MIXER 180 PER HR. 1 PER HR. 2.4 2 x 3 x 10 90.00 bd.ft
VIBRATOR 180 PER HR. 3 PER HR. 2x3x8 72.00 bd.ft
KNEADING MACHINE 180 PER HR. 3 PER HR. Tarpaulin 4' x 8' 64.00 sq.ft.
JACK HAMMER 350 PER HR. PER HR. CWN # 2 Depends 2.00 box
MANUAL BAR CUTTER 500 PER HR. PER HR. 4 TONS/HR CWN # 4 Use always 2.00 box
907.185 KG/HR PLY WOOD (4' x 8') 2.00 sheet
CU.M/TRIP
Estimate of Gabion
a

c
h h b
a

b
Computation for proposed Gabion Table
a (m) b (m)
Area =
Proposed Gabion 1.00 20.00
= 0.5 * (1 + 20) * 5 Gabion (1mx2mx1m) 1.00 2.00
= 52.50 sq.m.
Volume = 52.50 cu.m.
No. of 1 m x 2 m x 1 m Gabion
Gabion Volume
no. of Gabion = 52.50 / 2
Volume = 1 m x 2 m x 1 m = 26.25 pcs
= 2.00 cu.m. 27 pcs

Costing:

Description Price Description Quantity Unit Price


1m x 2m x 1m Gabion 1,700.00 Gabion 27.00 1,700.00
Boulders 800.00 Boulders 52.50 800.00
Total Amount

Unit Cost = Total Amount / Total Qu

Unit Cost = P 1,674.29


h (m) L (km)
5.00 1.00
1.00 -

Boulder Volume

Volume = Volume of Gabion


= 52.50 cu.m.

Amount
45,900.00
42,000.00
87,900.00

= Total Amount / Total Quantity

P 1,674.29
Project Safety And Health
Labor No. of personnel Rate /hr
First Aider 450.00

Materials Unit Cost Unit


First Aid Kit / Medicine 1,000.00 mo
Safety Shoes 1,000.00 pairs
Rubber Boots 400.00 pcs
Safety Helmet 315.00 pcs
Rain Coat 350.00 pcs
Hand Gloves 55.00 pairs
Dust Mask 35.00 pcs

Project Billboard
Labor No. of personnel Rate/hr
Carpenter 1 340.00
Laborer 2 340.00

Materials Unit Cost Unit


Tarpauline Printing 800.00 Each
Plywood - 5mm Ordinary 525.00 Sheet
2 x 2 x 8 - Coco Lumber 15.00 Bd.Ft.
2 x 3 x 10 - Coco Lumber 15.00 Bd.Ft.
CWN #2 1/2 70.00 Kg
CWN #4 70.00 Kg
CWN #1 100.00 Kg

Traffic Management
Labor No. of personnel Rate/hr
Flagmen 2.00 340.00
Carpenter 1.00 340.00
Laborer 1.00 340.00

Materials Unit Cost Unit


Tarpuline Printing For Road Signs 160.00 Each
Plywood - 5mm Ordinary 300.00 Sheet
2 x 2 x 8 - Coco Lumber 15.00 Bd.Ft.
2 x 3 x 10 - Coco Lumber 15.00 Bd.Ft.
CWN #2 1/2 70.00 Kg
CWN #4 70.00 Kg
CWN #1 100.00 Kg
Bamboo 50.00 Pcs
Paint (Black) 500.00 Gal
Paint (Yellow) 500.00 Gal
Construction Survey ang Staking
Labor No. of personnel Rate/hr Equipment
Surveyor 700.00 Survey Instrument (Rental)
Instrument Man 340.00
Survey Aide 340.00

Materials Unit Cost qty


Field Book 100.00 5.00
Scientific Calculator 1,500.00 1.00
Mechanical Pencil 200.00 1.00
Sign Pen 30.00 12.00
Bamboo 50.00 30.00
Permanent Marker 60.00 3.00
Ink Refill 100.00 1.00
Twine 80.00 5.00
CWN #4 70.00 15.00

Price Capacity
Item No. : 100
Labor : Foreman & Laborer

Equipment: Backhoe (18ltr/hr) 2,200.00 rate/hr 3,000.00 sq.m. / day

Materials : Diesel 35.00 rate/ltr


Oil 100.00 rate/ltr

Price Capacity
Item No. : 102
Labor : Foreman & Laborer

Equipment: Bulldozer ( 25 ltr/hr ) 3,540.00 rate/hr 50.00 cu.m.


Backhoe (16 ltr / hr ) 2,200.00 rate/hr 30.00 cu.m.
Dump Truck ( 1 ltr/hr ) 800.00 rate/hr
Payloader ( 18 ltr/hr ) 1,800.00 rate/hr

Materials : Diesel 35.00 rate/ltr


Oil 110.00 rate/ltr

Price Capacity
Item No. : 102(3)a
Labor : Foreman & Laborer

Equipment: Bulldozer ( 25 ltr/hr ) 3,540.00 rate/hr


Backhoe (16 ltr / hr ) 2,200.00 rate/hr
Dump Truck ( 1 ltr/hr ) 800.00 rate/hr
Payloader ( 18 ltr/hr ) 1,800.00 rate/hr

Materials : Diesel 35.00 rate/ltr


Oil 110.00 rate/ltr

Price Capacity
Item No. : 103 (3)
Labor : Foreman & Laborer
Equipment: Backhoe(18ltr/hr)
Dump Truck (1ltr/hr) 800.00 rate/hr

Materials : Diesel 35.00 rate/ltr


Oil 110.00 rate/ltr
Foundation Fill 5,200.00 T/L

Price Capacity
Item No. : 103 (6)
Labor : Foreman & Laborer
Equipment: Backhoe(18ltr/hr)
Dump Truck (1ltr/hr) 800.00 rate/hr 1.00 ltrs/hr
Materials : Diesel 35.00 rate/ltr
Oil 110.00 rate/ltr
Foundation Fill 5,200.00 T/L
rvey Instrument (Rental) 1 set = 100,000
BOX CULVERT ESTIMATE

2pcs each bar no. in the box culvert per section except no. 6

WINGWALL:
Splicing:

Desired Length
=
comerical length # of Splice

Desired Length - ( Comercial Length - 40 (bar diameter) ) (# of Splice)


ERT ESTIMATE

Assume cover 40 mm
CLEAR t BAR 1 BAR 2 BAR 3
SPAN HEIGHT SPACING SPACING SPACING
mm DIA. DIA. DIA.
(s) (h) (mm) (mm) (mm)
2400 280 16 260 16 260 16 260
3000
2750 280 16 260 16 260 16 260

HEIGHT 2.4
WIDTH 3 LENGTH 12.1
NO. OF LENGTH PCS OF
Bar no. SPACING Total Length (m) Bar no.
PCS (mm) BAR 6
1 260 92 4860 38 447.1 1
2 260 92 3280 26 301.8 2
3 260 92 3880 30 357 3
4 260 92 6360 50 585.1 4
5 200 120 1800 14 216 5
TOTAL 158 BAR 6 Length
Length of Bar 6 12.1 m
Total Length of Bar 6 1911.8 m

SPLICING: Commercial Length 6 m SPLICING:


BAR NO. # of Splice # of pcs Splice Length

4 1 92 92 m
no. of splice no. of splice
6 2 158 168 m

Summary:

16 mm dia. RSB Total Length 1691.092 m


12 mm dia. RSB Total Length 2128.2 m

DATAS NEEDED
WINGWALL COMPUTATION: h+t
2.68

# OF VERTICAL BARS # OF HORIZONTAL


BARS
38 19
FOR ESTIMATE PURPOSE (HORIZONTAL * L) & (VERTICAL * (h+t) + .4)

# OF HORIZONTAL BARS * LENGTH =19 X 4.41 = 83.79


# OF VERTICAL BARS * ((h+t) +.4) =38*(2.68+.4) = 117.04 (TWO VERTICAL BARS PER
200.83

er) ) (# of Splice) = Splice Length Total


BAR 4 BAR 5 BAR 6
SPACING SPACING SPACING
DIA. DIA. DIA.
(mm) (mm) (mm)
16 260 12 200 12 250
16 260 12 200 12 250

HEIGHT 2.8
WIDTH 3 LENGTH 12.8
NO. OF LENGTH PCS OF
SPACING Total Length (m)
PCS (mm) BAR 6
260 98 5210 40 510.6
260 98 3630 28 355.7
260 98 3880 30 380.2
260 98 6535 52 640.4
200 128 1800 14 230.4
TOTAL 164
Length of Bar 6 12.8 m
Total Length of Bar 6 2099.2 m

SPLICING: Commercial Length 6 m


Splice
BAR NO. # of Splice # of pcs Length
4 1 98 116 m
no. of splice
6 2 164 289 m

Summary:

16 mm dia. RSB Total Length 1887.016 m


12 mm dia. RSB Total Length 2330.2 m

DATAS NEEDED
L
4.41
(TWO VERTICAL BARS PER SECTION)
Size of Pipe Concrete 317 Kg. / Sq. cm. (4500 lb/sq. in)

Wall Thickness Tongue ( Groove Depth


in mm
( mm ) mm ) ( mm ) ( mm )

ID ID W A B C E P

24" 610 64 660 680 667 686 44

36" 910 86 988 1007 1994 1013 64

48" 1220 108 1315 1334 1321 1340 64

60" 1520 127

Pipe Culvert 52 ln.m.


diameter Thickness backhoe
0.910 0.086
Fabrication
vol 0.2226 cu.m. per pipe
cement 128.00 bags total
sand 6.56 cu.m. total
gravel 8.91 cu.m. total

Grout
vol 5.726 cu.m. total
cement 28.63 bags total
sand 2.29 cu.m. total
b/sq. in) Grouted Riprap and Stone Masonry
Minimum
Reinforcement 10 cu.m.
Sq.cm./m. of pipe

Circular Reinforcement cement = 2.574 x 10

1 Line Each
= 25.74 bags
4.23
2 Line Each Sand = 0.2 x 10
4.66
2 Line Each
= 2 cu.m.
6.56
Boulders = 1.2 x 10
= 12
capacity
15 for 910 and below dia.
12 for 1220 and above dia.

Labor
Thermoplastic Detailed Estimate
Factors:

Description Quantity Unit

Thermoplastic Paint (TP) 0.25 bag/ sq.m.


Glass Bead 0.2 pc. / TP
Primer (Tack Coat) 0.167 ltr./ sq.m.
LPG (50 kg) 0.02 tank/sq.m.
LPG (12 kg) 0.02 tank/sq.m.
Calsumine 0.2 kg. / km

Length of Road = 4,310.00 m

No. of
Area = Length x Strip x Thickness
= 4310 x 1 x 0.15
= 646.5 sq.m. (Center Line)

= 4310 x 2 x 0.1
= 862 sq.m. (Edge Line)

Area Total = 1508.5 sq.m.

Thermoplastic Paint (TP) 1508.5 x 0.25 = 378 bags


Glass Bead 378 x 0.2 = 76 pcs
Primer (Tack Coat) 1508.5 x 0.166667 = 252 ltrs
LPG (50 kg) 1508.5 x 0.02 = 31 tanks
LPG (12 kg) 1508.5 x 0.02 = 31 tanks
Calsumine 4.31 x 0.2 = 1 kg

Summary:
Additional of 5% as wastage

Thermoplastic Paint (TP) 397 bags


Glass Bead 80 pcs
Primer (Tack Coat) 265 ltrs
LPG (50 kg) 33 tanks email:
LPG (12 kg) 33 tanks
Calsumine 2 kg
arvinayoso@yahoo.com
CALCULATION OF LINED CANAL
Length of Lined Canal = 419.5 m

CONCRETE HOLLOW BLOCK ( 6" x 8" x 1


Dimension of Concrete Hollow Block
Width : 0.2
Length : 0.4

Dimension of Holes
Concrete Post No. of Holes : 3
Dimension of Concrete Post Length : 0.2
Width : 0.1 m Thickness : 0.15 m
Length : 0.85 m Spacing : 3m Volume of =
holes: =
Volume of Post
V = 0.1 x 0.85 x 0.15
= 0.01275 m³
No. of CHB =
`
No. of Post =
n = 419.5 ÷ 3 =
= 139.8333 ≈ 139 x 2 no. of side ≈
278 pcs
Total Volume of Fill
Total Volume Post = 278 x 0.01275
= 3.545 m³
Canal Slab Stiffener
Base : 1.1 m Height : 0.15 m Length : 0.8
Width : 0.15
Volume of Slab = 1.1 x 0.15 x 419.5
= 69.218 m³ Volume of Stiffener =
=
Given: Height : 1.00 m no. of side : 2 side
no. of Stiffener =
Assume: Thickness of Plaster = 0.01 m =

Volume of Plaster = 1 x 419.5 x 0.01 x 2
= 8.390 m³ Total Volume of Stifffener

Summary:

Volume of Concrete Post = 3.545 m³


Volume of Concrete Fill = 51.714 m³
Volume of Slab = 69.22 m³
Volume of Plaster = 8.39 m³
Volume of Stiffener = 1.248 m³
134.114 m³
CONCRETE HOLLOW BLOCK ( 6" x 8" x 16" )
of Concrete Hollow Block
m Thickness : 0.15 m
m

cores Width : 0.1 m


m Thickness : 0.1 m

3 x 0.2 x 0.1 x 0.1


0.006 m³

Total
(Total Surface Area of Area of
Area - Conc. ÷ CHB
Post.
419.5 x 0.85 x 2 - 278 x (.1 x .85) ÷ 0.4 x 0.2
8619
8619 pcs

= 8619 x 0.006
= 51.714 m³

Page 1
Stiffener
m Thickness : 0.1 m
m Spacing : 4m

0.8 x 0.15 x 0.1


0.012

419.5 ÷ 4
104.875
104 pcs

= 104 x 0.012
= 1.248 m³

Page 2
CALCULATION OF GUARD RAIL POST
LENGTH OF GUARD RAIL : m

Dimension of Guard Rail Post


Length : 1.7 m Thickness 0.2 m
Width : 0.2 m Spacing : 3.65 m

VOLUME OF CONCRETE

Volume of Concrete = L x W x H
=
RAIL POST

You might also like