Professional Documents
Culture Documents
ABB Johannesburg Microgrids - Case Study v9 LoRes PDF
ABB Johannesburg Microgrids - Case Study v9 LoRes PDF
C A S E S T U DY
—
Left: ABB’s
— The power reliability challenge
Longmeadow facility
in Johannesburg,
Seamless islanding for South Africa has the highest electricity demand in
Africa, with up to 41 percent of its generated power
South Africa
total continuity of supply consumed by the industrial sector. Although energy
—
Right: ABB PowerStore demand has stayed relatively flat in recent years,
Battery Energy In 2016, ABB installed an integrated solar PV–
energy costs have steadily increased, in particular
Storage System diesel-battery microgrid at its Longmeadow
peak demand charges. These have been used as an
facility in Johannesburg, South Africa. This
incentive for businesses to reduce consumption at
integrates multiple energy sources and battery-
particular times of the day where utilities struggle
based stabilization technology within a smart
to meet high power demand. Ageing distribution
control system that facilitates the seamless
grid infrastructure, power quality issues such as
transition between grid-connected and islanded
voltage dips and an eventual resumption of load
modes without any disruption to the connected
shedding events are additional challenges.
loads. The facility is now able to operate as its own
‘power island’, supplying reliable power 24/7 and
However, the country’s businesses and production
ensuring that business continues as normal
facilities need uninterrupted and reliable power
despite any planned or unplanned disturbances or
supply to maintain continuous operation. Many
outages of the main power grid. While continuity
therefore rely on diesel generators to provide a
of supply is the critical factor, the ABB system also
back-up power supply. This situation is not
optimizes the site’s use of solar power to reduce
uncommon in many other parts of Africa and other
its reliance on increasingly expensive and polluting
regions of the world, such as South America or
diesel fuel.
South East Asia, where increasing demand for
electricity is also outpacing generation and
distribution capacity.
Typical back up solution Microgrid solution
PowerStore
PV Battery
Diesel
Grid Diesel generators Grid generators
G G G G G G —
The back-up solution
before (left) and after
implementing the
microgrid (right)
Factory Factory
Microgrids to the rescue On average, the facility had to be isolated from the
Microgrids are increasingly being deployed to grid up to 10 times a month. As a result, its total
ensure local continuity of supply, reduce reliance energy cost in 2015, including utility fees and diesel
on fossil fuels and defer large-scale grid fuel, was US$630,000.
investments in areas that have a weak connection
to the main electricity grid. To address this challenge, ABB has transformed
the existing generator backup system into an
Such grid-connected microgrids are growing in innovative microgrid solution. Now, only two
popularity to help address rising power demands, 600 kVA diesel generators are required, with the
take advantage of the falling cost of renewable support of a 1 MVA/ 380 kWh PowerStore™ Battery
sources – in particular solar photovoltaic (PV) based on lithium-ion (Li-ion) technology and a
technology and batteries - and improve supply Microgrid Plus Control System as well as a 750 kWp
resilience and autonomy especially for critical rooftop solar PV (photovoltaic) system.
applications.
This world-leading solution offers fully grid-
ABB facility shows the way connected and off-grid functionality designed
ABB’s 96,000-square-meter Johannesburg facility to maximize the use of renewable energy and
houses the company’s national headquarters, as ensure uninterrupted power supply. The seamless
well as manufacturing facilities, with around 1,000 transition to islanded operation keeps the facility
employees. It is supplied with power by a medium running smoothly during both planned or
voltage grid connection to the local utility with unplanned power outages.
electrical loads adding up to a total of 1000 kW.
1000
T3: Diesel generator 2 picks up
800
the rest of the load, PowerStore
power output reduces to zero
600
200
-200
-400
-600
-800
—
Seamless transition from grid
-1000
connection to islanding mode
with PowerStore (Red trace),
solar PV (Yellow trace) and the
Time T1 T2 T3 T4
two generators (Light Blue and
Brown traces) – the Green trace
PowerStore (kW) Load (kW) PV (kW) Gen1 (kW) Gen2 (kW) Grid (kW) shows the power from the grid
—
Substantial savings
ABB estimates that without the new microgrid This environmentally-friendly solution
solution annual diesel fuel consumption at the contributes to a substantial reduction of carbon
facility would be approximately 52,000 liters. emissions (by an estimated 1,000 tons per year)
Instead, this has been cut to about 38,000 liters – as well as significantly reducing the operational
a 27 percent saving. In addition, the generators are cost of the industrial complex.
now running for only 106 hours annually, compared
to 433 hours without the microgrid – a 75 per cent Leon Viljoen, ABB’s country management director
reduction in running time. This has led to a for South Africa said:
reduction in annual diesel fuel costs from
US$62,000 million to US$44,000, following the “ Securing access to reliable, high quality power
installation of the microgrid – a 30 percent saving. is a business-critical issue for all the country’s
industrial operations. Since switching over to
the new microgrid in June 2016 we now have
Without the microgrid grid full confidence that it is always ‘business as
energy costs would have been normal’ for this site, no matter what is
happening on the local grid. As well as securing
US$610,000 in 2016. our supply, the microgrid brings a very
significant added benefit in enabling us
With the microgrid they are to make the best possible use of renewable
energy while delivering substantial
US$460,000, which equates operational savings.”
to a 25 percent saving.
— —
ABB India Contact Center We reserve the right to make technical We reserve all rights in this document
Tel 1800 420 0707 changes or modify the contents of this and in the subject matter and illustrations
Toll free number within India document without prior notice. With contained therein. Any reproduction,
+91 80 67 143 000 regard to purchase orders, the agreed disclosure to third parties or utilization
International number particulars shall prevail. ABB AG does not of its contents – in whole or in parts
Email contact.center@in.abb.com accept any responsibility whatsoever for – is forbidden without prior written
potential errors or possible lack of consent of ABB AG. Copyright© 2017 ABB
information in this document. All rights reserved
abb.com/microgrids