Professional Documents
Culture Documents
BOQ
BOQ
BOQ
Sketsa Perhitungan
1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat
Tinggi Galian = 1.05 m
Lebar Galian = 1.00 m
Panjang Galian = 1.00 m
Jumlah = 9.00 Bh
Volume = 9.45 m3
2. Pekerjaan Struktur
a. Foot Plat
- Beton
Lebar Atas = 0.30 m
Lebar Bawah = 0.20 m
Tinggi = 0.35 m
Panjang = 1.00 m
Volume = 0.18 m3
Lebar = 0.30
Tinggi = 0.30
Volume = 0.09 m3
Lebar = 0.30 m
Tinggi = 0.70 m
Volume = 0.06 m3
- Bakisting = 7.56 m2
b. Sloof 30 x 40 cm
Panjang = 27.00 m
Lebar = 0.30 m
Tinggi = 0.40 m
Volume Beton = 3.24 m3
Bakisting = 21.60 m2
c. Kolom 15 x 15 cm
Tinggi = 3.50 m
Lebar = 0.15 m
Panjang = 0.15 m
Jumlah Kolom = 9.00 bh
Volume Beton = 0.71 m3
Bakisting = 18.90 m2
Sketsa Perhitungan
d. Ring Balk 15 x 20 cm
Panjang = 27.00 m
Lebar = 0.20 m
Tinggi = 0.15 m
Volume Beton = 0.81 m3
Bakisting = 10.80 m2
3. Pekerjaan Dinding
Panjang = 27.00 m
Tinggi Dinding = 3.50 m
Luas Dinding = 94.50 m2
Pengurangan Dinding
Pintu 1
Tinggi = 2.30 m
Lebar = 1.70 m
Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m
Pintu 1
Tinggi = 1.55 m
Lebar = 1.15 m
Rooster 1
Tinggi = 1.20 m
Lebar = 0.80 m
Rooster 2
Tinggi = 0.60 m
Lebar = 1.60 m
Luasan = 14.48 m2
Plesteran = 160.04 m2
Acian = 160.04 m2
Pengecetan = 160.04 m2
Sketsa Perhitungan
4. Pekerjaan Atap
Kayu 6/12 Kuda-Kuda 1
Panjang Kayu = 19.25 m
Volume Kayu = 0.14 m3
Beugel u = 2.00 Bh
Plat Strip = 4.00 bh
Bout 15 cm = 5.00 bh
Bout 30 cm = 4.00 bh
Panjang = 41.35 m
6. Pekerjaan Plafon
Panjang = 7.45 m
Lebar = 6.45 m
Luas Plafon = 48.05 m2
Pengecetan Plafon = 48.05 m2
List Plafond = 69.00 m'
7. Pekerjaan Teras
Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m
Luas = 2.07 m2
Volume Kayu = 0.03 m3
Jendela 1
Tinggi = 1.55 m
Lebar = 1.15 m
Luasan = 1.78 m2
Volume Kayu = 0.03 m3
Panjang = 2.00 m
Lebar = 1.50 m
Tebal = 0.20 m
Volume = 0.60 m3
Uraian Volume Rumah Genset
1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat M3 9.45
b. Urugan Tanah Kembali m3 7.18
2. Pekerjaan Struktur
a. Foot Plat
- Beton m3 2.95
- Penulangan Ø12 - 150 mm Kg 422.73
- Bakisting M2 7.56
b. Sloof 30 x 40 cm
- Beton m3 3.24
- Bakisting M2 21.60
- Penulangan Polos Kg 347.54
c. Kolom 15 x 15 cm
- Beton m3 0.71
- Bakisting M2 18.90
- Penulangan Polos Kg 194.32
d. Ring Balk 15 x 20 cm
- Beton m3 0.81
- Bakisting M2 10.80
- Penulangan Polos Kg 146.17
e. Plat Lantai T = 0.2 m
- Beton m3 6.00
- Bakisting M2
- Penulangan Polos Kg 611.97
3. Pekerjaan Dinding
- Dinding Batako M2 80.02
- Dinding Rooster M2 1.92
- Plesteran M2 160.04
- Acian M2 160.04
- Pengecatan M2 160.04
4. Pekerjaan Atap
- Kuda-Kuda Kayu 6/12 cm M3 0.26
- Gording Kayu 5/12 cm M3 0.45
Beugel u Bh 2.00
Plat Strip Bh 4.00
Bout 15 cm Bh 5.00
Bout 30 cm Bh 4.00
- Seng Gelombang BJLS. 0.30 M2 73.31
5. Pekerjaan List Plank 3 x 20 M2 41.35
6. Pekerjaan Plafon M2 48.05
7. Pekerjaan Teras
- Volume Galian Tanah M3 2.93
- Volume Urugan Pasir M3 0.33
- Volume Anstamping M3 0.98
- Urugan Tanah M3 0.78
- Pasangan Batu M3 1.17
- Volume Rabat Lantai K-125 M3 0.80
- Volume Rabat K-175 M3 0.53
- Volume Sloof M3 0.39
- Penulangan Sloof 15 x 20 Kg 70.52
8. Pekerjaan Pintu dan Jendela
- Kayu Jendela dan Pintu M3 0.09
- Daun Jendela M2 1.78
- Daun Pintu M2 5.98
- Engsel Pintu Bh 12.00
- Engsel Jendela Bh 4.00
- Kait Angin Bh 2.00
- Kunci Tanam Bh 2.00
9. Beton Dudukan Genset M3 0.60
BACK UP VOLUME PEKERJAAN
PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM
LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)
TAHUN ANGGARAN : 2019
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
MT
1.10
0.80
MT
0.45
0.60
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
GALIAN TYPE 3 (a.18-P.22a)
Jalan Lingkungan /Lapen
Galian Tanah 906.00 0.70 0.85 539.07
Bahu Jalan
Urugan Tanah Kembali Timbunan Pasir
906.00 0.70 0.45 285.39
Urugan Pasir Galian/Timbunan tanah kembali
906.00 0.70 0.40 0.04 253.64
MT
0.30
Pipa GIP Ø 50 mm
Transmisi dari Res. 500 m3
0.55 Pipa GIP Ø 200 mm
Transmisi dari IPA
0.70
1.10
1.10
0.80
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
3 GALIAN PIPA PIPA DENGAN PEMBONGKARAN TROTOAR & SALURAN
Pembongkaran Trotoar Existing Jalan negara/Hotmix
520.00 0.95 494.00 M2
Pemasangan Kembaali Paving Trotoar Trotoar/Pas. Paving
dibongakar & dipasang kembali
520.00 0.95 494.00 M2
Beton Penutup Saluran
dibongakar & dipasang kembali
Saluran Existing
GALIAN TYPE 1 (Pa.19-a.2, Pa.33-Pa.37)
Pembongkaran Dasar Saluran Existing 445.00 0.80 0.30 106.80
Pemasangan Kembali Dasar saluran Existing Rabat Beton
0.80 445.00 0.80 0.30 106.80
Galian Tanah 445.00 0.80 0.30 106.80
Bongkaran Pas. Batu
Urugan Pasir Pas. Batu kembali
0.30
445.00 0.80 0.30 0.03 106.77
Pipa GIP Ø 200 mm
0.30
(Transmisi)
0.80
1.20
Rabat Beton
0.30
Pembongkaran Dasar Saluran Existing Pip a GIP Ø 200 mm
(Transmisi)
0.15
129.30 M3
Pemasangan Kembali Dasar saluran Existing 1.00 129.30 M3
Galian Tanah 118.05 M3
Urugan Pasir 117.99 M3
0.05
Bongkaran Pas. Batu
0.30
Pas. Batu kembali
0.60
1.10
1.50
0.80
6 Crossing Jalan
Jalan Hotmix
Galian Tanah Pengaspalan kembali
8.00 0.80 0.60 3.84 M3
Jalan Negara /Hotmix
Urugan Pasir Beton Mutu K.175 8.00 0.80 0.20 0.03 1.25 M3
Urugan Tanah Kembali Sirtu
8.00 0.80 0.20 1.28 M3
Galian/Timbunan Tanah Kembali
Urugan Sirtu Jalan ke Bandara 8.00 0.80 0.10 0.64 M3
Hotmix
Beton K-175 8.00 0.80 0.10 0.64 M3
Lapisan Aspal 8.00 0.80 0.03 0.19 M3
1.10
0.80
Jalan Lapen
Galian Tanah 42.00 0.60 0.85 21.42 M3
Urugan Pasir Rabat Beton 42.00 0.60 0.40 0.03 10.05 M3
Timbunan Pasir
Jalan Lingkungan /Lapen
Urugan Tanah Kembali Galian/Timbunan tanah kembali 42.00 0.60 0.35 8.82 M3
Rabat Beton Muka Jalan
42.00 0.60 0.10 2.52 M3
0.45
0.60
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
2 RENCANA PIPA DISTRIBUSI GIP 200 MM
A Rencana Reservoar 500 m3 - Reservoar Existing 100 M3 (CP. 5 - P. 1b)
Pipa GIP dia. 50mm 1 lubang dengan pipa GIP 100 85.00
Pipa GIP dia. 50mm dalam 1 lubang Timbunan Pasir 25.00
Total Pipa GIP 50 mm 110.00 M'
Galian
Knee GIP Ø 50mm - 90° Timbunan tanah kembali 1.00 Bh
Water Moer GIP Ø 50mm 2.00 Bh
MT
Socket GIP Ø 50mm 15.00 Bh
0.30
Galian Tanah 25.00 0.26 0.50 3.25 M3
Urugan Tanah Kembali 25.00 0.26 0.30 1.95 M3
Pipa GIP Ø 50 mm
Urugan Pasir 0.20 25.00 0.26 0.20 0.00 1.30 M3
0.26
0.55
Galian
Timbunan tanah kembali
MT
0.45
0.40
Timbunan Pasir
0.45
Jalan Hotmix
0.40
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 1 (Patok b.6)
Pembuatan Bak Kontrol
Galian Tanah 0.15
B
1.30 1.30 0.85 1.44
Pengurang 100x100x50 mm
Tee All Flange
1.30 0.40 0.75 0.39
Pip a PVC Ø 3" (Exis ting)
Pesi Pengangkat
Renc. Pip a GIP Ø 100 MM
1.00
A
Total 1.05 M3
Urugan sirtu A Gate Valv e Ø 50 mm
1.00 1.00 0.10 0.10 M3
Lantai Kerja Rabat Beton K-175 0.15
1.00 1.00 0.05 0.05 M3
Pas. Bata 1PC : 4PS 0.15
1.00
0.15
0.30 4.60 0.85 3.91 M2
Beton Tumbuk K-100 Bibir Bak Kontrol 0.20
4.60 0.15 0.20 0.14
Pengurang 0.60
4.60 0.07 0.08 0.03
Saluran Existing
Total 0.11 M3
0.20
Pembesian B 7.58 Kg
Bekisting 4.60 0.08 0.35 M2
Plesteran 4.14 M2
Acian 4.14 M2
Bongkaran Saluran 1.60 0.60 0.30 0.29 M3
Pasangan Kembali Saluran 1PC : 4PS Penutup Beton Bertu la ng (Pra Cetak)
0.29 M3
1 PC : 3 Ps : 5 Kr
0.08
0.08 1.15
Beton Tumbuk
1 PC : 3 Ps : 5 Kr Paving Block
Timbunan Pasir
0.05 0.07
2.00 Bh
Pipa PVC Ø 3" (Existing)
Gate Valve All Flange Ø 100mm (Distribusi)
0.05
0.10
Gatevalve Ø 100 mm
0.30
0.15
Rabat Beton K.175 0.40
Bend 90°
Timbunan Sirtu Pipa GIP Ø 100 mm
1.10
POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 2 (Patok P.72)
Pembuatan Bak Kontrol
Galian Tanah B 1.30 1.30 0.85 1.44
1.30 0.40 0.75
0.15
Pengurang 0.39
100x100x50 mm Cro sing Jalan Hotmix
Tee All Flange
A
Renc. Pipa GIP Ø 100 MM
Total 1.05 M3
Urugan sirtu 1.00 1.00 0.10 0.10 M3
1.00
Bekisting 0.35 M2
B
Plesteran 4.14 M2
DENAH BAK KONTROL (BK. 2)
Acian Skala 1:20
4.14 M2
Bongkaran Saluran 1.80 0.60 1.00 1.08 M3
Pasangan Kembali Saluran 1PC : 4PS 1.08 M3
1.00 Bh
Renc. Pip a GIP Ø 100 mm
Gate Valve All Flange Ø 100mm (Distrib usi)
Gate Valve Ø 50 mm
0.85
1 PC : 4 Ps
Bend 90°
Pip a GIP Ø 50 mm
1.80
POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 3 (Patok P.79)
Pembuatan Bak Kontrol B
Pasangan Kembali Saluran 1PC : 4PS DENAH BAK KONTROL (BK. 2) 0.32 M3
Skala 1:20
0.55
0.35
0.15
Bend 90°
0.15 1.00 0.15 Pip a GIP Ø 50 mm
0.60
1.50
POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
Pipa GIP dia. 75mm (P.69-P.72)
Pipa GIP dia. 75mm Type 1 150.00
Pipa GIP dia. 75mm Type 2 175.00
Total Pipa GIP 75 mm 325.00 M'
Bend All Flange GIP Ø 75mm - 45° 3.00 Bh
Loose Flange GIP 75 mm 3.00 Bh
Paking Karet dia. 75mm 3.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 24.00 Bh
Water Moer GIP Ø 100mm 2.00 Bh
Socket GIP Ø 75mm 49.00 Bh
0.45
Pipa GIP Ø 75 mm
0.30
0.35
Pipa GIP Ø 75 mm
0.225
BK 4 (Patok CP.6)
Pembuatan Bak Kontrol
Galian Tanah 1.30 1.30 0.85 1.44
Pengurang 1.30 0.40 0.75 0.39
0.15
Total 1.05 M3
Urugan sirtu 1.00 1.00 0.10 0.10 M3
75x75x50 mm
Lantai Kerja Rabat Beton K-175 Tee All Flange 1.00 1.00 0.05 0.05 M3
Renc. Pipa GIP Ø 100 MM
Pesi Pengangkat
Pas. Bata 1PC : 4PS Dop Ø 75 mm
4.60 0.85 3.91 M2
Beton Tumbuk K-100 Bibir Bak Kontrol 1.00 4.60 0.15 0.20 0.14
Pengurang 4.60 0.07 0.08 0.03
Total 0.11 M3
Gate Valve Ø 50 mm
Tutup Bak Kontrol
Beton K-175 1.15 1.15 0.08 0.10 M3
0.15
Pembesian 1.20 8.00 0.40 7.58 Kg
Dop Ø 50 mm
Bekisting 4.60 0.08 0.35 M2
0.15 1.00 0.15
Plesteran 4.14 M2
Patok Tanda Titi Taping
Acian 0.30 Pipa PVC Ø 3" di isi beton 4.14 M2
0.30
0.15
Dop Ø 50 mm
BERAT SATU
NO KETERANGAN 0.30 SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
0.08 1.15
0.08 1.00 Bh
Beton Tumbuk
0.05 0.07 TP
0.15
POTONGAN B - B
Skala 1:20
0.15
Total 0.11 M3
Tutup Bak Kontrol
Beton K-175 1.15 1.15 0.08 0.10 M3
Patok Tanda Titi Taping
Pipa PVC Ø 3" di isi beton
0.15 1.00 0.15
Beton Tumbuk
1 PC : 3 Ps : 5 Kr I Patok Tanda Titi Taping
Pipa PVC Ø 3"
0.05 0.07 TP
0.15
POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 6 (Patok CP.7)
Pembuatan Bak Kontrol
Galian Tanah 1.30 1.30 0.85 1.44
Pengurang 1.30 0.40 0.75 0.39
0.15
Total 1.05 M3
Urugan sirtu 75x75x50 mm
1.00 1.00 0.10 0.10 M3
Tee All Flange
Lantai Kerja Rabat Beton K-175 Pesi Pengangkat Renc. Pipa GIP Ø 100 MM 1.00 1.00 0.05 0.05 M3
Pas. Bata 1PC : 4PS 4.60 0.85 3.91 M2
1.00
Beton Tumbuk K-100 Bibir Bak Kontrol 4.60 0.15 0.20 0.14
Pengurang Gate Valve Ø 50 mm
4.60 0.07 0.08 0.03
Total 0.11 M3
Tutup Bak Kontrol 0.15
I Beton Tumbuk
1 PC : 3 Ps : 5 Kr
Pipa PVC Ø 3"
TP 0.07 0.05
Patok Tanda Titi Taping
0.15
POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
3 PEMBANGUNAN RESERVOIR KAPASITAS 500 M3
a Galian Tanah 1.00 1.00 1.15 22.00 25.30
30.00 12.65 2.40 455.40
3.30 2.58 0.20 1.70
+145.38
Talu d Penahan Camp. 1PC : 5PS
130.71 0.80 0.55 57.51
2.75 539.92
Pengurang 0.80 0.80 0.55 22.00 7.74
Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm
Total 532.17 M3
Pipa Outlet GIP Ø 100 mm ke CP.6 (Pel. Ipi)
c Pondasi Footplate
m
m
PipaOutlet GIPØ100m
PipaOutlet GIPØ50m
Beton K-225 2.75 0.90 0.90 0.30 22.00 5.35
0.30 0.30 0.80 4.00
Talud Penahan Camp. 1PC : 5PS
0.29
+147.75
Pipa Outlet GIP Ø 100 mm ke CP7 (Ds Tanjung) Pipa Inlet GIP Ø 200 mm
Dari IPA Wolowona (PDAM Kab. Ende)
0.30 0.30 1.20 18.00 1.94
Pipa Outlet GIP Ø 50 mm
ke Desa Rukun Lima (Reser 200 m3)
Pembesian
Telapak Memanjang 2.00 6.00 0.40 104.28
Telapak Melintang 2.00 6.00 0.40 104.28
Tiang 1 1.20 8.00 0.40 15.17
Tiang 2 1.50 8.00 0.40 85.32
Sengkang Tiang 1 1.00 8.00 0.40 12.64
Sengkang Tiang 2 1.00 12.00 0.40 85.32
Total 407.01 Kg
0 .25
0 .15 2 .45
Plat Atap ( T = 1 5 cm)
Pipa Over flow
GIP Ø100 mm
0.2 0 0.20 0.20 0. 20 0.2 5
0 .2 5 3 .90 3 .80 3.8 0 3.80 3.90
Bekisting
0.5 0
0. 25
0.4 5
Total 53.52 M3
2.85
2.50
Ø 8 - 150
Ø 10 - 150
Ø 10 - 150
Ø 12 - 150
Ø 8 - 150 5.70 0.25 2.85 2.00 8.12
0.25 4 Ø 10
Total 72.13 M3
4 Ø 10
0.25
Water Stop
L Water Stop
K
Ø 10 - 150 Ø 10 - 150 Ø 10 - 150
Pembesian 2.85
Ø 10 - 150
Water Stop
Ø 10 - 150
Water Stop
Ø 10 - 150
Water Stop
0.30
Ø 10 - 150 Ø 10 - 150
Pembesian Water Stop Water Stop
Utama
Ø 12 - 150 Ø 12 - 150
3.15 8.00 1.04 471.74
Sengkang
0.30 0.30
1.00 31.50 0.40 223.97
Total 695.71 Kg
DETAIL I DETAIL J
j Balok Reservoir SKALA 1 : 20 SKALA 1 : 20
Pembesian Ø 12 - 150
Ø 12 - 150 0.15
Utama 133.75 4.00 0.62 330.10
4 Ø 10
Sengkang Water Sto p
1.00 891.67 0.40 352.21
Water Stop Ø 10 - 150
Ø 10 - 150 Total 682.30 Kg
Ø 10 - 150
k Plat Atap Reservoir Ø 10 - 150
DETAIL K 56.24
SKALA 1 : 20
Pengurang 0.70 0.70 0.25 7.00 0.86
Total 55.38 M3
8Ø 12
Ø 8-100
Pembesian
8Ø 12
Memanjang 10.80 136.67 0.62 1821.38
8D13 0,30 3.03 23.67 0.62 88.49
Melintang 20.80 70.00 0.62 1796.70
0,30
KL. 30x30
3.85 18.20 0.62 86.47
Skala 1:20
Total 3793.04 Kg
Foot plat
Skala 1:25
Bekisting 20.50 10.50 215.25
3.55 2.73 9.69
Total 224.94 M2
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
l Pasangan Batako Ruang Kontrol Pas 1PC : 5PS 8.20 3.75 30.75
Pengurang 0.90 2.00 1.80
Total 28.95 M2
1.98 0.73 4.13 4.00 4.00 4.00 4.13
n Pengecatan 3.25
55.44 2.85 158.00
0.60 2.85 22.00 37.62
57.90
Total 253.52 M2
Pas. Pondasi Batu Kali 5.13
1Pc : 5Ps
3.50
Kolom 30x30
o Pekerjaan Talud
Galian Tanah Footplate 1.00x1.00 48.40 0.70 0.60 20.33
DENAH RENCANA PONDASI
SKALA 1 : 100 43.20 1.30 0.45 25.27
Total 45.60 M3
Ø10 - 150
Ø10 - 150
Ø10 - 150
Ø10 - 150
Ø10 - 150
p Urugan Pasir Lantai Sekitar Reservoar Ø 10 - 150 5.80 2.40 0.10 1.39
Ø 10 - 150
3.22
5.80 2.50 0.10 1.45
20.50 1.75 0.10 3.59
Total 21.54 M3
q Rabat Beton Mutu K-125 Lantai Sekitar Reservoir 5.80 2.40 0.05 0.70
5.20 2.60 0.05 0.68
3.40 3.00 0.05 0.51
6.00 3.80 0.05 1.14
26.50 2.73 0.05 3.62
9.20 3.50 0.05 1.61
5.80 2.50 0.05 0.73
20.50 1.75 0.05 1.79
Total 10.77 M3
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
r Aksesoris
Flange Socket Ø 200mm 5.00 Bh
Flange Socket Ø 100mm 35.00 Bh
Flange Socket Ø 75mm 12.00 Bh
Bend All Flange Ø 200mm - 90° 3.00 Bh
Bend All Flange Ø 100mm - 90° 6.00 Bh
Bend All Flange Ø 50mm - 90° 0.05 5.00 Bh
A
Gate Valve All Flange Ø 100mm Engsel 0.50 4.00 Bh
Gate Valve All Flange Ø 75mm 2.00 Bh
Gate Valve All Flange Ø 50mm 2.00 Bh
Handel Besi Ø10mm
Giboult Joint Ø 100mm 4.00 Bh
Palt Baja 70x70
JUMLAH 1952.97
dipasang kembali
0.15 0.95 0.15
Pa. 26 - Pa. 27 50
Pa. 27 - Pa. 30 150
Pa. 37 - Pa. 41 243
2 Bongkaran Trotoar 1.10
0.80
JUMLAH 2214.8
0.80
JUMLAH 520
Jalan negara/Hotmix
Pa. 63 - Pa. 70 306 L = 0.60, T = 0.70
Pa. 70 - a. 8 223 L = 0.80, T = 0.60
0.75
Rabat Beton
0.80
JUMLAH 529
NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN
Pengaspalan kembali
1.10
0.80
JUMLAH 41
5 Crossing Jalan
Pa.2 - Pa.3 6 Lapen
Pa.5 - Pa.6 6 Lapen
Pa.8 - Pa.9 6 Lapen
Rabat Beton
Timbunan Pasir
Jalan Lingkungan /Lapen
Pa.9 - Pa.10 8 Lapen
Galian/Timbunan tanah kembali
Pa.15 - Pa.16 6 Lapen
Muka Jalan
Pa.25 - Pa.26 10 Lapen
0.45
0.60
JUMLAH 42
a. 8 - Cp. 4 341
Timbunan Pasir
MT
0.10
1.50
0.80
JUMLAH 341
REKAPITULASI
ENGINEER ESTIMATE
PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM
LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)
TAHUN : 2019
JUMLAH
No URAIAN PEKERJAAN SATUAN VOLUME HARGA
(RP.)
1 2 3 4 5
PEKERJAAN BANGUNAN
IV BAK RESERVOIR(200 M3) UNIT 1.00 Rp 588,202,384.89
4 Pengadaan dan Pemasangan Pipa GIP Ø 40 mm Ke Kampung Adat M' 498.00 Rp 68,885,054.00
PEKERJAAN
VII PENYELESAIAN
Jumlah Rp 8,263,738,458.48
PPn 10 % Rp 826,373,845.85
Jumlah Total Rp 9,090,112,304.33
Dibulatkan Rp 9,090,112,000.00
Terbilang :
Sembilan Milyar Sembilan Puluh Juta SeRatus Dua Belas Ribu Rupiah
Konsultan Perencana
CV. SAHWANA
STAFANUS L. TAPOBALI, ST
Team Leader
BILL OF QUANTITY
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6
I PEKERJAAN PERSIAPAN
- Pembersihan Lokasi Ls 1.00 Rp 3,500,000.00 Rp 3,500,000.00
- Pengukuran Dan Pematokan Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
- Pemasangan Papan nama Ls 1.00 Rp 750,000.00 Rp 750,000.00
Jumlah Harga Pekerjaan Rp 11,750,000.00
III RENCANA PIPA TRANSMISI GIP 150 MM
1 Pengadaan dan Pemasangan Pipa GIP Ø 150 mm
a Pengadaan Pipa dan Aksesoies
- Socket Ø 150mm Bh 603.15 Rp 174,010.53 Rp 104,954,451.27
- Water Moor Ø 150mm Bh 67.02 Rp 417,000.00 Rp 27,945,950.00
- Bend All Flange Ø 150mm - 90° Bh 3.00 Rp 862,500.00 Rp 2,587,500.00
- Bend All Flange Ø 150mm - 45° Bh 5.00 Rp 862,500.00 Rp 4,312,500.00
- Bend All Flange Ø 150mm - 22.5° Bh 3.00 Rp 737,500.00 Rp 2,212,500.00
- Flange Ø 150mm Bh 28.00 Rp 902,000.00 Rp 25,256,000.00
- Paking Karet Ø 150mm Bh 28.00 Rp 17,825.00 Rp 499,100.00
- Baut Moer 5/8 x 3 Metal + Ring Bh 312.00 Rp 8,625.00 Rp 2,691,000.00
Sub Jumlah Rp 170,459,001.27
b Kontruksi Pemasangan pipa GIP Ø 150 mm
- Pengadaan & Pemasangan Pipa GIP Ø 150 mm M' 4,021.00 Rp 660,304.00 Rp 2,655,082,384.00
- Ujicoba pengaliran M' 4,021.00 Rp 1,854.00 Rp 7,454,934.00
Sub Jumlah Rp 2,662,537,318.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA TRANSMISI GIP DIAMETER 150 MM Rp 2,832,996,319.27
2 Pekerjaan Crossing Jalan
i Pekerjaan Crossing Jalan Hotmix
- Galian Tanah M3 3.84 Rp 54,625 Rp 209,760.00
- Urugan Pasir M3 1.25 Rp 536,608.00 Rp 670,760.00
- Urugan Tanah Kembali M3 1.28 Rp 19,550.00 Rp 25,024.00
- Urugan Sirtu M3 0.64 Rp 381,110.00 Rp 243,910.40
- Beton K-175 M3 0.64 Rp 1,963,845.00 Rp 1,256,860.80
- Lapisan Aspal M3 0.19 Rp 1,500,000.00 Rp 285,000.00
TOTAL PEKERJAAN CROSSING JALAN HOTMIX Rp 2,691,315.20
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
IV PEKERJAAN BANGUNAN BAK RESERVOIR(200 M3)
Pekerjaan Persiapan
- Pembersihan Lokasi Ls 1.00 500,000.00 500,000.00
- Pengadaan Air Kerja Ls 1.00 500,000.00 500,000.00
Sub Jumlah 1 1,000,000.00
Pekerjaan tanah
- Galian Tanah Cadas M3 143.17 110,055.00 15,756,794.46
- Urugan Sirtu M3 13.12 381,110.00 5,001,687.64
- Timbunan Tanah Kembali M3 47.72 19,550.00 933,004.20
Sub Jumlah 2 21,691,486.30
Pekerjaan Struktur
- Pekerjaan Pasangan Batu Kali 1pc : 4ps M3 23.52 1,394,664.00 32,802,497.28
- Pekerjaan Pasangan Batu Kosong M3 9.80 831,327.00 8,147,004.60
- Beton Tumbuk mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 M3 6.56 1,773,797.00 11,639,655.91
- Lantai Beton Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 32.81 2,072,760.00 68,007,255.60
- Beton Dinding Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 51.22 2,072,760.00 106,170,912.72
- Plat Penutup Beton Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M2 17.72 2,072,760.00 36,722,052.54
- Pembesian Lantai kg 6,035.85 16,729.00 100,973,734.65
- Pembesian Dinding kg 3,818.01 16,729.00 63,871,506.02
- Pembesian Plat Beton Penutp kg 2,874.81 16,729.00 48,092,716.56
- Acian M2 695.49 32,188.00 22,386,271.18
- Pengecatan Bak M2 269.01 34,249.00 9,213,152.25
Sub Jumlah 3 508,026,759.31
Pekerjaan Pelengkap Accessories
- Flange socket/Flange Drat GIP. Dia 100 mm Buah 46.00 718,658.00 33,058,268.00
- Flange socket/Flange Drat GIP. Dia 50 mm Buah 1.00 805,000.00 805,000.00
- Tee All Flange GIP 150 x 150 x 150 mm Buah 1.00 450,000.00 450,000.00
- Tee All Flange GIP 100 x 100 x 100 mm Buah 3.00 128,800.00 386,400.00
- Gate Valve All Flange GIP Dia.100 mm Buah 7.00 25,000.00 175,000.00
- Gate Valve All Flange GIP Dia.50mm Buah 1.00 25,000.00 25,000.00
- Bend All Flange 90° GIP. Dia 100 mm Buah 11.00 500.00 5,500.00
- Bend All Flange 90° GIP. Dia 50 mm Buah 12.00 16,730.94 200,771.28
- Dop GIP Dia. 100 mm Buah 2.00 68,700.00 137,400.00
- Paking Karet dia 150 mm Buah 1.00 29,000.00 29,000.00
- Paking Karet dia 100 mm Buah 53.00 25,000.00 1,325,000.00
- Paking Karet dia 50 mm Buah 2.00 9,500.00 19,000.00
- Mur Baut 5/8 Buah 440.00 8,625.00 3,795,000.00
- Giboult Joint GIP Dia. 150 mm Buah 1.00 179,000.00 179,000.00
- Giboult Joint GIP Dia. 100 mm Buah 4.00 107,000.00 428,000.00
- Giboult Joint GIP Dia. 50 mm Buah 1.00 59,000.00 59,000.00
- Watermeter Dia 100mm Buah 1.00 3,270,000.00 3,270,000.00
- Watermeter Dia 50mm Buah 1.00 2,154,000.00 2,154,000.00
- Reducher Dia. 150 -100 mm Buah 2.00 420,200.00 840,400.00
- Reducher Dia. 100 - 50 mm Buah 1.00 325,000.00 325,000.00
- Pipa Udara Buah 8.00 287,500.00 2,300,000.00
- Tangga Besi Buah 4.00 575,000.00 2,300,000.00
- Engsel Pasang 8.00 39,675.00 317,400.00
- Gembok Buah 4.00 50,000.00 200,000.00
- Tutup Manhole dari plat baja Buah 4.00 862,500.00 3,450,000.00
- Pintu Teralis Buah 1.00 1,250,000.00 1,250,000.00
Sub Jumlah 4 57,484,139.28
Total Pekerjaan Bangunan Bak Reservoir 200 m3 Rp 588,202,384.89
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
V RENCANA PIPA DISTRIBUSI
1 Pengadaan dan Pemasangan Pipa GIP Ø 100 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 100mm - 90° Bh 2.00 Rp 119,000.00 Rp 238,000.00
- Water Moer GIP Ø 100mm Bh 170.00 Rp 193,000.00 Rp 32,810,000.00
- Socket GIP Ø 100mm Bh 1,511.00 Rp 80,212.25 Rp 121,200,717.13
Sub Jumlah Rp 154,248,717.13
b Kontruksi Pemasangan pipa GIP Ø 100 mm
- Pengadaan & Pemasangan Pipa GIP Ø 100 mm M' 10,090.00 Rp 329,813.00 Rp 3,327,813,170.00
- Ujicoba pengaliran M' 10,090.00 Rp 1,509.00 Rp 15,225,810.00
Sub Jumlah Rp 3,343,038,980.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 100 MM Rp 3,497,287,697.13
2 Pengadaan dan Pemasangan Pipa GIP Ø 50 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 50mm - 90° Bh 3.00 Rp 35,000.00 Rp 105,000.00
- Knee GIP Ø 50mm - 45° Bh 6.00 Rp 33,000.00 Rp 198,000.00
- Water Moer GIP Ø 50mm Bh 66.47 Rp 49,500.00 Rp 3,290,100.00
- Socket GIP Ø 50mm Bh 600.00 Rp 59,667.66 Rp 35,800,596.56
Sub Jumlah Rp 39,393,696.56
b Kontruksi Pemasangan pipa GIP Ø 50 mm
- Pengadaan & Pemasangan Pipa GIP Ø 50 mm M' 3,988.00 Rp 246,638.00 Rp 983,592,344.00
- Ujicoba pengaliran M' 3,988.00 Rp 1,302.00 Rp 5,192,376.00
Sub Jumlah Rp 988,784,720.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 50 MM Rp 1,028,178,416.56
3 Pengadaan dan Pemasangan Pipa GIP Ø 25 mm
A Jalur Pipa Distribusi Pipa GIP Ø 25 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 25mm - 90° Bh 2.00 Rp 21,500.00 Rp 43,000.00
- Knee GIP Ø 25mm - 45° Bh 2.00 Rp 21,000.00 Rp 42,000.00
- Water Moer GIP Ø 25mm Bh 17.00 Rp 29,000.00 Rp 493,000.00
- Socket GIP Ø 25mm Bh 153.00 Rp 22,500.00 Rp 3,442,500.00
Sub Jumlah Rp 4,020,500.00
b Kontruksi Pemasangan pipa GIP Ø 25 mm
- Pengadaan & Pemasangan Pipa GIP Ø 25 mm M' 1,020.00 Rp 128,184.00 Rp 130,747,680.00
- Ujicoba pengaliran M' 1,020.00 Rp 1,302.00 Rp 1,328,040.00
Sub Jumlah Rp 132,075,720.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 25 MM Rp 136,096,220.00
4 Pengadaan dan Pemasangan Pipa GIP Ø 40 mm Ke Kampung Adat
A Jalur Pipa Distribusi Pipa GIP Ø 40 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 40mm - 90° Bh 2.00 Rp 28,000.00 Rp 56,000.00
- Knee GIP Ø 40mm - 45° Bh 5.00 Rp 27,000.00 Rp 135,000.00
- Water Moer GIP Ø 40mm Bh 8.00 Rp 39,000.00 Rp 312,000.00
- Socket GIP Ø 40mm Bh 75.00 Rp 25,500.00 Rp 1,912,500.00
Sub Jumlah Rp 2,415,500.00
b Kontruksi Pemasangan pipa GIP Ø 40 mm
- Pengadaan & Pemasangan Pipa GIP Ø 40 mm M' 498.00 Rp 132,102.00 Rp 65,786,796.00
- Ujicoba pengaliran M' 498.00 Rp 1,371.00 Rp 682,758.00
Sub Jumlah Rp 66,469,554.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 40 MM KE KAMPUNG ADAT Rp 68,885,054.00
VI PEKERJAAN HIDRAN UMUM
i Pembuatan Pondasi Hidran Umum
- Galian tanah M³ 4.78 110,055.00 526,503.12
- Beton Tumbuk 1pc : 3 ps : 5 kr M³ 0.92 1,716,270.00 1,573,476.34
- Pekerjaan Aanstamping Batu Kali M³ 1.03 831,327.00 857,929.46
- Pasangan Batu Kali 1pc : 4 ps M2 3.06 1,394,664.00 4,267,671.84
- Urugan Pasir M³ 0.82 536,608.00 440,286.86
- Urugan Tanah Kembali M³ 0.59 19,550.00 11,557.96
- Plesteran 1 pc : 3 ps M2 8.39 66,424.00 556,984.69
- Acian M2 7.83 32,188.00 251,880.53
- Pengecatan Ls 1.00 1,500,000.00 1,500,000.00
Sub Jumlah 1 8,486,290.80
ii Asesories Hidran Umum
- Tee All Socket 20 x 20 x 20 Buah 1.00 12,100.00 12,100.00
- Bend 90 dia. 25mm Buah 4.00 21,500.00 86,000.00
- Bend 90 dia. 20mm Buah 2.00 19,500.00 39,000.00
- Stop Kran Inlet dia. 25mm Buah 1.00 39,000.00 39,000.00
- Tap Kran dia. 20mm Buah 2.00 49,414.22 98,828.44
- Double Neeple dia. 25mm Buah 2.00 11,509.00 23,018.00
- Double Neeple dia. 20mm Buah 3.00 9,009.00 27,027.00
- Water Moer dia. 25mm Buah 1.00 29,000.00 29,000.00
- Water Moer dia. 20mm Buah 3.00 26,000.00 78,000.00
- Kran Pelampung dia. 25mm Buah 1.00 69,000.00 69,000.00
- Packing Karet dia. 20mm Buah 2.00 5,095.65 10,191.30
- Tangki Hidran Umum Fiber Kapsitas 2m3 Buah 1.00 4,500,000.00 4,500,000.00
Sub Jumlah 2 5,011,164.74
TOTAL PEKERJAAN HIDRAN UMUM Rp 13,497,455.54
JUMLAH 3 UNIT Rp 40,492,366.63
VII PEKERJAAN PENYELESAIAN
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
- Pembersihan kembali lokasi Ls 1.00 Rp 2,000,000.00 Rp 2,000,000.00
- Pelaporan dan Dokumentasi Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
- Asbuilt Drawing Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
TOTAL PEKERJAAN PENYELESAIAN Rp 14,500,000.00
UPAH TENAGA KERJA DAN HARGA SATUAN BAHAN
Upah Tenaga
No. Tenaga Kerja Satuan
Kerja (Rp./Hr)
1 Pekerja Org/Hari 61,000.00
2 Mandor Org/Hari 70,000.00
3 Kepala Tukang Org/Hari 75,000.00
4 Tukang Kayu Org/Hari 70,000.00
5 Tukang Batu Org/Hari 70,000.00
6 Tukang Besi Org/Hari 70,000.00
7 Tukang Las Org/Hari 70,000.00
8 Tukang Pipa Org/Hari 70,000.00
9 Tukang Cat Org/Hari 70,000.00
10 Operator Org/Hari 70,000.00
11 Pembantu Operator Org/Hari 61,000.00
12 Driver Org/Hari 70,000.00
13 Pembantu Driver Org/Hari 61,000.00
14 Mekanik Org/Hari 61,000.00
15 Helper (Pembantu) Org/Hari 59,500.00
16 Welder (Tukang Las) Org/Hari 70,000.00
No. Material Satuan Harga ( Rp )
1 2 3 4
BAHAN LOKAL
1 SemenPortland Kg 2,258.49
2 SemenPortland Zak 82,300.00
3 Semen Putih Kg 2,125.00
4 Pasir Filter M3 401,013.61
5 Pasir Urug M3 373,013.61
6 Pasir Pasang M3 401,013.61
7 Pasir Beton M3 401,013.61
8 Pasir Beton Kg 286.44
9 Sirtu M3 262,000.00
10 Batu Kali/Gunung/Karang M3 401,013.61
11 Koral Beton M3 571,000.00
12 Batu Gravel 5-10 cm M3 423,013.61
13 Batu Gravel 5-10 cm Kg 313.34
14 Batu Gravel 3-5 cm M3 812,718.64
15 Batu Gravel 3-5 cm Kg 602.01
16 Kerikil Gravel 2-3 cm M3 803,013.61
17 Kerikil Gravel 2-3 cm Kg 594.82
18 Kerikil Gravel 1-2 cm M3 596,439.37
19 Kerikil Gravel 1-2 cm Kg 441.81
20 Kerikil Gravel 0.5-1 cm M3 871,013.61
21 Kerikil Gravel 0.5-1 cm Kg 645.20
22 Bata Merah Buah 2,000.00
23 Batu Batako Buah 5,000.00
24 Batu Roster Buah 11,000.00
25 Kayu Klass III M3 3,163,000.00
26 Papan Bekisting 3/30 M3 2,531,000.00
27 Kayu Klas II Balok M3 4,428,000.00
28 Paku Biasa Kg 17,250.00
29 Sekrup Bh 7,500.00
30 Besi Beton Kg 12,625.00
31 Kawat Beton Kg 19,550.00
32 Kawat Lat Kg 184,000.00
33 Kawat Bronjong Kg 27,500.00
34 Cat Manie Kg 40,000.00
35 Cat Tembok (waterproof) Kg 63,250.00
36 Plamir Tembok Kg 7,000.00
37 Kuwas Buah 20,000.00
38 Amplas Lembar 7,500.00
39 Cat Kayu/Besi Kg 69,000.00
40 Cat Dasar Kg 63,250.00
41 Cat Tembok Kg 63,250.00
42 Plamir Kayu Kg 51,750.00
43 Plitur Liter 41,000.00
44 Plitur Kayu Liter 50,000.00
45 Minyak Cat (Tinner) Kg 31,625.00
46 Minyak Bekesting Kg 20,125.00
47 Sealant Tube 33,350.00
48 Lem Kayu (Webber) Liter 28,750.00
49 Lem Kayu (Webber) Kg 57,500.00
50 Paku Seng Kg 23,000.00
51 Paku 2-3 Kg 10,000.00
52 Paku 5-7 Kg 15,000.00
53 Paku 10 Kg 17,000.00
54 Paku 12 Kg 20,000.00
55 Lisplang Lembar 45,000.00
56 Besi Siku 40.40.4 M' 18,400.00
57 Besi Siku 50.50.5 M' 34,500.00
58 Besi Siku 30.30.3 M' 46,920.00
59 Plat Baja 1.9 mm Kg 69,662.92
60 Besi Profil Kg 32,666.67
61 Besi Beton Kg 23,000.00
62 Besi Strip M2 161,000.00
63 Besi Tralis M¹ 14,375.00
64 Kawan Beton Kg 19,550.00
65 Kawat Las Btg 2,300.00
66 Kawat Bronjong Kg 27,500.00
67 Kawat Harmonika M² 28,750.00
68 Kawat Duri Rol 287,500.00
69 Kawat Duri M' 3,500.00
70 Triplek 4 mm Lembar 74,300.00
71 Plywood/Multipek 9 mm Lembar 143,750.00
72 Teakwood 4 mm Lembar 97,750.00
73 Beugel U Buah 25,000.00
74 Jendela Nako M² 138,000.00
75 Besi Strip M² 161,000.00
76 Kunci Tanam Buah 86,250.00
77 Engsel Pintu Buah 28,750.00
78 Spring Knip Buah 12,000.00
79 Espanyolet Buah 45,000.00
80 Kait Angin Buah 17,250.00
81 Engsel Kupu-Kupu Buah 23,000.00
82 Grendel Buah 17,250.00
83 Kaca Tebal 3 mm M² 143,750.00
84 Kaca Tebal 5 mm M² 94,300.00
85 Plastik Kasa M¹ 23,000.00
86 Waterstop Lebar 20 cm M' 51,750.00
87 Angker Moer Baut Ø 16 mm - 25 cm Buah 5,750.00
88 Baja Honeycom WF.375.125.6.9, termasuk pabrikasi Kg 39,502.50
89 Baja WF.250.125.6.9 Kg 10,925.00
90 Baja Wide Flange (WF) 300.150.6,5.9 Kg 10,000.00
91 Baja Wide Flange (WF) 350.175.7.11 Kg 10,000.00
92 Baja Wide Flange (WF) 400.200.8.13 Kg 10,000.00
93 Baja Wide Flange (WF) 500.200.10.16 Kg 10,000.00
94 Baja Wide Flange (WF) 600.200.11.17 Kg 10,000.00
95 Baja Wide Flange (WF) 800.300.14.26 Kg 15,000.00
96 Pengaku dan Brancing L.50.50.05 Kg 10,752.50
97 Pengaku Kanal C.80.50.5 Kg 10,752.50
98 Plat-Plat 12.10.8.6 Kg 10,752.50
99 Plat RIB Buah 10,000.00
100 Besi Plat Pengaku Samping 300.232.08 Buah 300,000.00
101 Plat Tumpu Baja WF Tebal 12mm (30x40cm) Buah 450,000.00
102 Clamp Pipa Plat Strip 80.05 Buah 128,800.00
103 Baut Moer HTB Sambungan WF Ø 16 mm Buah 22,137.50
104 Baut Moer Pengaku dan Brancing Ø 16 mm Buah 18,112.50
105 Baut Moer Clamp Pipa Ø 19 mm Buah 14,950.00
106 Angker Moer Baut Ø 25 mm - 30 mm Buah 97,175.00
107 Pagar Landak Besi Beton dan Plat Strip Buah 560,625.00
108 Sambungan WF Set 563,500.00
109 Angker Moer Baut Ø 25 mm - 30 cm Buah 97,175.00
110 Baut Mur 19 mm + Ring Buah 12,000.00
111 Balok Kayu Bayam Buah 75,000.00
112 Angker rod 16 mm, panjang 60 cm Buah 21,500.00
113 Sling baja dia. 16mm M' 18,500.00
114 Sling baja dia. 12 mm M' 15,000.00
115 span skrup 16mm Buah 29,000.00
116 Kausen Buah 5,000.00
117 Klem sling Buah 20,000.00
118 Baut-moer 16 Buah 3,433.00
119 Baut-moer 12 Buah 1,900.00
120 Plat GIP 200.120.6 mm Buah 15,000.00
121 Plat GIP 120.80.6 mm Buah 20,000.00
122 Plat GIP 350.120.6 mm Buah 25,000.00
123 Clamp Support Pipa Ø 200 mm Buah 161,000.00
124 Clamp Support Pipa Ø 150 mm Buah 138,000.00
125 Clamp Support Pipa Ø 100 mm Buah 92,000.00
126 Clamp Support Pipa Ø 75mm Buah 74,750.00
127 Clamp Support Pipa Ø 50mm Buah 56,000.00
128 Ijuk Kg 10,000.00
129 Tutup Bak Kontrol Buah 862,500.00
130 Engsel Besi Buah 39,675.00
131 Gembok Buah 50,000.00
132 Pipa Udara Buah 287,500.00
133 Tangga Kontrol Buah 575,000.00
134 Pipa Selubung Buah 78,750.00
135 Pagar BRC dia. 6mm Lembar 184,012.50
136 Pintu Pagar BRC Lebar 1M¹ Buah 1,200,000.00
137 Pintu Teralis Buah 1,250,000.00
138 Jelusi Buah 750,000.00
139 Kawat saringan Buah 30,000.00
140 Katup Saringan Buah 102,000.00
141 Paving Block M² 125,000.00
142 Keramik 20 x 20 Buah 6,900.00
143 Keramik 30 x 30 Buah 8,818.18
144 Air Bersih M3 30,000.00
145 Air Bersih Ltr 30.00
146 Minyak Bensin Ltr 7,475.00
147 Minyak Solar Ltr 6,325.00
148 Minyak Pelumas Ltr 40,250.00
No. Material Satuan Harga ( Rp )
1 2 3 4
BAHAN NON LOKAL
A PIPA GALVANIZED IRON PIPE (GIP) ACESSORIES
1 Pipa Galvanized Steel Pipe {GPS) Ø 200 mm M¹ 528,853.27
2 Pipa Galvanized Steel Pipe {GPS) Ø 150 mm M¹ 522,031.59
3 Pipa Galvanized Steel Pipe {GPS) Ø 100 mm M¹ 240,636.76
4 Pipa Galvanized Steel Pipe {GPS) Ø 75 mm M¹ 166,024.20
5 Pipa Galvanized Steel Pipe {GPS) Ø 50 mm M¹ 179,002.98
6 Pipa Galvanized Steel Pipe {GPS) Ø 40 mm M¹ 102,000.00
7 Pipa Galvanized Steel Pipe {GPS) Ø 25 mm M¹ 76,000.00
8 Pipa Galvanized Steel Pipe {GPS) Ø 20 mm M¹ 56,000.00
9 Pipa Galvanized Steel Pipe {GPS) Ø 15 mm M¹ 48,500.00
10 Socket GIP. Ø 150 mm Buah 174,010.53
11 Socket GIP. Ø 100 mm Buah 80,212.25
12 Socket GIP. Ø 75 mm Buah 55,341.40
13 Socket GIP. Ø 50 mm Buah 59,667.66
14 Socket GIP. Ø 40 mm Buah 25,500.00
15 Socket GIP. Ø 25 mm Buah 22,500.00
16 Double Nipple GIP. Ø 150 mm Buah 124,600.00
17 Double Nipple GIP. Ø 100 mm Buah 63,152.25
18 Double Nipple GIP. Ø 75 mm Buah 39,666.38
19 Double Nipple GIP. Ø 50 mm Buah 25,990.00
20 Double Nipple GIP. Ø 40 mm Buah 21,300.00
21 Double Nipple GIP. Ø 25 mm Buah 14,030.00
22 Water Moor GIP. dia 150 mm Buah 417,000.00
23 Water Moor GIP. dia 100 mm Buah 193,000.00
24 Water Moor GIP. dia 75 mm Buah 109,000.00
25 Water Moor GIP. dia 50 mm Buah 49,500.00
26 Water Moor GIP. dia 40 mm Buah 39,000.00
27 Water Moor GIP. dia 25 mm Buah 29,000.00
28 Bend All Flange CI. Ø 150 mm - 90 Buah 675,000.00
29 Bend All Flange CI. Ø 150 mm - 45 Buah 675,000.00
30 Bend All Flange CI. Ø 100 mm - 90 Buah 477,000.00
31 Bend All Flange CI. Ø 100 mm - 45 Buah 477,000.00
32 Bend All Flange CI. Ø 75 mm - 90 Buah 405,000.00
33 Bend All Flange CI. Ø 75 mm - 45 Buah 405,000.00
34 Bend All Flange CI. Ø 50 mm - 90 Buah 339,000.00
35 Bend Ø 150 mm - 90˚ Socket Buah 456,200.00
36 Bend Ø 150 mm - 45˚ Socket Buah 410,000.00
37 Bend Ø 100 mm - 90˚ Socket Buah 119,000.00
38 Bend Ø 100 mm - 45˚ Socket Buah 135,000.00
39 Bend Ø 75 mm - 90˚ Socket Buah 77,000.00
40 Bend Ø 75 mm - 45˚ Socket Buah 67,000.00
41 Bend Ø 50 mm - 90˚ Socket Buah 35,000.00
42 Bend Ø 50 mm - 45˚ Socket Buah 33,000.00
43 Bend Ø 150 mm - 22.5˚ Socket Buah 409,000.00
44 Bend Ø 100 mm - 22.5˚ Socket Buah 132,000.00
45 Bend Ø 75 mm - 22.5˚ Socket Buah 67,000.00
44 Bend Ø 50 mm - 22.5˚ Socket Buah 33,000.00
45 Bend Steel (Las) Ø 150 mm - 90˚ Buah 487,788.00
46 Bend Steel (Las) Ø 150 mm - 45˚ Buah 487,788.00
47 Bend Steel (Las) Ø 150 mm - 22,50˚ Buah 487,788.00
48 Bend Steel (Las) Ø 150 mm - 11,25˚ Buah 487,788.00
49 Water Meter All Flange Ø 150 mm Buah 4,470,000.00
50 Water Meter All Flange Ø 100 mm Buah 3,270,000.00
51 Water Meter All Flange Ø 75 mm Buah 2,550,000.00
52 Water Meter All Flange Ø 50 mm Buah 2,154,000.00
53 Gilbout Joint Joint CI. Ø 150 mm Buah 179,000.00
54 Gilbout Joint Joint CI. Ø 100 mm Buah 107,000.00
55 Gilbout Joint Joint CI. Ø 75 mm Buah 79,000.00
56 Gilbout Joint Joint CI. Ø 50 mm Buah 59,000.00
57 Flange Flaxible Joint Ø 150 mm Buah 780,600.00
58 Flange Flaxible Joint Ø 100 mm Buah 674,000.00
59 Flange Flaxible Joint Ø 75 mm Buah 525,600.00
60 Water Moor Ø 150 mm Buah 417,000.00
61 Water Moore Ø 100 mm Buah 193,000.00
ANALISA PEKERJAAN
HARGA SATUAN PEKERJAAN PERSIAPAN
A.2.2.1.13. Pembongkaran 1 m3 beton bertulang
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.3334 61,000 81,337.40
Mandor L.04.01 OH 0.6660 70,000 46,620.00
JUMLAH TENAGA KERJA 127,957.40
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 127,957.40
E Overhead & Profit 15% 15% 19,193.61
F Harga Satuan Pekerjaan (D+E) - 147,151.00
A TENAGA - -
Pekerja L.01.01 OH 0.7500 61,000 45,750.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 47,500.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 47,500.00
E Overhead & Profit 15% 15% 7,125.00
F Harga Satuan Pekerjaan (D+E) - 54,625.00
A TENAGA - -
Pekerja L.01.01 OH 1.0000 61,000 61,000.00
Mandor L.04.01 OH 0.0320 70,000 2,240.00
JUMLAH TENAGA KERJA 63,240.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 63,240.00
E Overhead & Profit 15% 15% 9,486.00
F Harga Satuan Pekerjaan (D+E) - 72,726.00
A TENAGA - -
Pekerja L.01.01 OH 0.2500 61,000 15,250.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 17,000.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 17,000.00
E Overhead & Profit 15% 15% 2,550.00
F Harga Satuan Pekerjaan (D+E) - 19,550.00
A TENAGA - -
Pekerja L.01.01 OH 0.2500 61,000 15,250.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 17,000.00
B BAHAN - -
Sirtu m3 1.2000 262,000 314,400.00
JUMLAH HARGA BAHAN 314,400.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 331,400.00
E Overhead & Profit 15% 15% 49,710.00
F Harga Satuan Pekerjaan (D+E) - 381,110.00
HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 202.0000 2,258 456,214.25
Pasir Pasang m3 0.4850 401,014 194,491.60
JUMLAH HARGA BAHAN 1,131,922.18
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,286,797.18
E Overhead & Profit 15% 15% 193,019.58
F Harga Satuan Pekerjaan (D+E) - 1,479,816.00
A TENAGA
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 163.0000 2,258 368,133.28
Pasir Pasang m3 0.5200 401,014 208,527.07
JUMLAH HARGA BAHAN 1,057,876.68
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,212,751.68
E Overhead & Profit 15% 15% 181,912.75
F Harga Satuan Pekerjaan (D+E) - 1,394,664.00
A TENAGA
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 136.0000 2,258 307,154.15
Pasir Pasang m3 0.5440 401,014 218,151.40
JUMLAH HARGA BAHAN 1,006,521.88
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,161,396.88
E Overhead & Profit 15% 15% 174,209.53
F Harga Satuan Pekerjaan (D+E) - 1,335,606.00
A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 276.0000 2,258 623,342.24
Pasir Beton kg 828.0000 286 237,170.90
Kerikil (Maks 30 mm) kg 1012.0000 602 609,237.97
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,476,201.12
C PERALATAN - -
D Jumlah (A+B+C) - 1,604,011.12
E Overhead & Profit 15% 15% 240,601.67
F Harga Satuan Pekerjaan (D+E) - 1,844,612.00
A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.2000 61,000 73,200.00
Tukang Batu L.02.03 OH 0.2000 70,000 14,000.00
Kepala Tukang L.03.01 OH 0.0200 75,000 1,500.00
Mandor L.04.01 OH 0.0600 70,000 4,200.00
JUMLAH TENAGA KERJA 92,900.00
B BAHAN
Semen portland kg 230.0000 2,258 519,451.87
Pasir Beton kg 893.0000 286 255,789.39
Kerikil (Maks 30 mm) kg 1027.0000 602 618,268.18
Air Liter 200.0000 30 6,000.00
JUMLAH HARGA BAHAN 1,399,509.44
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,492,409.44
E Overhead & Profit 15% 15% 223,861.42
F Harga Satuan Pekerjaan (D+E) - 1,716,270.00
A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (12 ±2) cm, w/c = 0,66
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 326.0000 2,258 736,266.56
Pasir Beton kg 760.0000 286 217,693.10
Kerikil (Maks 30 mm) kg 1029.0000 602 619,472.20
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,579,881.87
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,707,691.87
E Overhead & Profit 15% 15% 256,153.78
F Harga Satuan Pekerjaan (D+E) - 1,963,845.00
A.4.1.1.6 Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 352.0000 2,258 794,987.21
Pasir Beton kg 731.0000 286 209,386.39
Kerikil (Maks 30 mm) kg 1031.0000 602 620,676.23
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,631,499.83
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,759,309.83
E Overhead & Profit 15% 15% 263,896.47
F Harga Satuan Pekerjaan (D+E) - 2,023,206.00
A.4.1.1.7. Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 371.0000 2,258 837,898.45
Pasir Beton kg 698.0000 286 199,933.93
Kerikil (Maks 30 mm) kg 1047.0000 602 630,308.45
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,674,590.83
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,802,400.83
E Overhead & Profit 15% 15% 270,360.12
F Harga Satuan Pekerjaan (D+E) - 2,072,760.00
A TENAGA
Pekerja L.01.01 OH 0.0700 61,000 4,270.00
Tukang Besi L.02.05 OH 0.0700 70,000 4,900.00
Kepala Tukang L.03.01 OH 0.0070 75,000 525.00
Mandor L.04.01 OH 0.0040 70,000 280.00
JUMLAH TENAGA KERJA 9,975.00
B BAHAN
Besi beton (polos/ulir) kg 10.5000 12,625 132,562.50
Kawat beton kg 0.1500 19,550 2,932.50
JUMLAH HARGA BAHAN 135,495.00
C PERALATAN - -
D Jumlah (A+B+C) - 145,470.00
E Overhead & Profit 15% 15% 21,820.50
F Harga Satuan Pekerjaan (D+E) - 167,290.00
A TENAGA
Pekerja L.01.01 OH 0.5200 61,000 31,720.00
Tukang Kayu L.02.04 OH 0.2600 70,000 18,200.00
Kepala Tukang L.03.01 OH 0.0260 75,000 1,950.00
Mandor L.04.01 OH 0.0260 70,000 1,820.00
JUMLAH TENAGA KERJA 53,690.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 10 cm kg 0.3000 15,000 4,500.00
Minyak bekisting Liter 0.1000 20,125 2,012.50
JUMLAH HARGA BAHAN 133,032.50
C PERALATAN - -
D Jumlah (A+B+C) - 186,722.50
E Overhead & Profit 15% 15% 28,008.38
F Harga Satuan Pekerjaan (D+E) - 214,730.00
A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0150 4,428,000 66,420.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 2.0000 6,900 13,800.00
JUMLAH HARGA BAHAN 267,077.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 335,222.50
E Overhead & Profit 15% 15% 50,283.38
F Harga Satuan Pekerjaan (D+E) - 385,505.00
A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0180 4,428,000 79,704.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 2.0000 6,900 13,800.00
JUMLAH HARGA BAHAN 280,361.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 348,506.50
E Overhead & Profit 15% 15% 52,275.98
F Harga Satuan Pekerjaan (D+E) - 400,782.00
A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0150 4,428,000 66,420.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 6.0000 6,900 41,400.00
JUMLAH HARGA BAHAN 294,677.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 362,822.50
E Overhead & Profit 15% 15% 54,423.38
F Harga Satuan Pekerjaan (D+E) - 417,245.00
A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0300 3,163,000 94,890.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0200 4,428,000 88,560.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 3.0000 6,900 20,700.00
Penjaga jarak bekisting / spacer Buah 4.0000 500 2,000.00
JUMLAH HARGA BAHAN 266,487.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 334,632.50
E Overhead & Profit 15% 15% 50,194.88
F Harga Satuan Pekerjaan (D+E) - 384,827.00
PEKERJAAN :
LOKASI :
TAHUN :
1 Pipa GIP Ø 50 mm M' 14,078.00 15.00 30.00 45.00 7.00 6.00 4.00 1.21 0.40 0.50 13.93 1,000,000.00 5.03 30.18 3,000.00 99.40 2,346.33 1,385.00 10,060.00 61,000.00 1.21 53.17 10,113.17 1,685.53
2 Pipa GIP Ø 75 mm M' #NAME? 15.00 30.00 45.00 7.00 6.00 4.00 2.01 0.67 0.77 9.10 1,000,000.00 8.37 50.22 3,000.00 59.74 #NAME? 543.35 16,740.00 61,000.00 2.01 225.52 16,965.52 2,827.59
3 Pipa GIP Ø 100 mm M' #NAME? 15.00 30.00 45.00 7.00 6.00 4.00 2.93 0.98 1.08 6.51 1,000,000.00 12.20 73.20 3,000.00 40.98 #NAME? 266.62 24,400.00 61,000.00 2.93 669.89 25,069.89 4,178.32
4 Pipa GIP Ø 200 mm M' 4,021.00 15.00 30.00 45.00 7.00 6.00 4.00 4.61 1.54 1.64 4.28 1,000,000.00 19.20 115.20 3,000.00 26.04 670.17 111.43 38,400.00 61,000.00 4.61 2,522.66 40,922.66 6,820.44
ANALISA MATERIAL ON SITE
Volume Panjang Pipa Panjang Total Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Total Biaya kirim
Container/Truck (Roll / Btg) / Container/Truck dr Jkt ke Sby dr Jkt ke Sby dr Pelbh Sby dr Pelbh Sby dr Labuan Bajo dr Labuan Bajo ke loksai
No. Diameter
(Roll / Btg) (M') (M') (Rp./Truck) (Rp./M') ke Labuan Bajo ke Labuan Bajo ke Lokasi ke Lokasi Sementara
(Rp./ Container) (Rp./ M') (Rp./ Truck') (Rp./ M') (Rp.M')
1 Pipa PE. Ǿ 63 mm (2") 10.00 Roll 100.00 1,000.00 3,500,000.00 3,500.00 9,000,000.00 9,000.00 1,500,000.00 1,500.00 14,000.00
2 Pipa PE. Ǿ 110 mm (4") 166.67 Btg 6.00 1,000.00 3,500,000.00 3,500.00 9,000,000.00 9,000.00 1,500,000.00 1,500.00 14,000.00
3 Pipa HDPE. Ǿ 250 mm (10") 664.67 Btg 6.00 3,988.00 3,500,000.00 877.63 9,000,000.00 2,256.77 1,500,000.00 376.13 3,510.53
ANALISA MATERIAL ON SITE
1 HARGA SEMEN PER KG DI LOKASI PEKERJAAN
A 1 Kg Harga Semen dan Biaya Angkut sd lokasi yang dapat di akses kendaraan
- Jarak angkut PP = 60.00 Km K 245
- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 246
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 247
- Kecepatan truck rata-rata per jam = 35.00 Km K 248
- Kapasitas angkut truk = 3,000.00 Kg K 249
- Waktu per trip + fixed time = 2.71 Jam K 250
- Jumlah jam efektif per hari = 7.00 Jam K 251
- Jumlah trip per Hari = 2.58 Trip K 252
- Berat per zak semen = 50.00 Kg K 253
- Kapasitas angkut per trip per truck = 60.00 Zak K 254
- Sewa truck per trip = 1,000,000.00 Rp. K 255
- Produksi per hari = 154.74 Zak K 256
- Ongkos angkut ke lokasi per zak = 6,462.59 Rp. K 257
- Harga upah pekerja = 61,000.00 Rp. K 258
- Jumlah pekerja bongkar muatan = 4.00 Orang K 259
- Biaya bongkar muat per zak = 1,576.87 Rp. K 260
- Harga Semen per zak = 82,300.00 Rp. K 261
- Ongkos Angkut ke Lokasi per zak = 6,462.59 Rp. K 262
- Ongkos Bongkar Muat per zak = 1,576.87 Rp. K 263
- Jumlah Harga Semen per zak di lokasi ( q + r + s ) = 90,339.46 Rp. K 264