BACK UP VOLUME RUMAH GENSET

Sketsa Perhitungan

1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat
Tinggi Galian = 1.05 m
Lebar Galian = 1.00 m
Panjang Galian = 1.00 m
Jumlah = 9.00 Bh
Volume = 9.45 m3

b. Urugan Tanah Kembali


Tinggi Urugan = 0.85 m Urugan Pondasi Foot Plat
Panjang = 1.00 m
Lebar = 0.35 m
Volume urugan = 2.68 m3

Tinggi Urugan = 0.15 m Urugan Tanah Timbunan Lantai


Panjang = 6.00 m
Lebar = 5.00 m
Volume Urugan = 4.50 m3

2. Pekerjaan Struktur
a. Foot Plat
- Beton
Lebar Atas = 0.30 m
Lebar Bawah = 0.20 m
Tinggi = 0.35 m
Panjang = 1.00 m
Volume = 0.18 m3

Lebar = 0.30
Tinggi = 0.30
Volume = 0.09 m3

Lebar = 0.30 m
Tinggi = 0.70 m
Volume = 0.06 m3

Total Volume Beton = 2.95 m3


- Penulangan Ø12 - 150 mm
Panjang Tul. = 2.50 m
Jumlah = 7.67 Btng
Panjang Total = 19.17 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Arah x = 17.06 Kg

Panjang Tul. = 1.30 m


Jumlah = 12.00 Btng
Panjang Total = 15.60 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Arah y = 13.88 Kg

Total Berat Tul. 1 = 278.48 Kg


Sketsa Perhitungan

- Penulangan 2 (8- Ø12, Ø8-150)


Panjang Tul. = 1.65 m
Jumlah = 8.00 Btng
Panjang Total = 13.20 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 11.75 Kg

Panjang Tul. = 1.10 m


Jumlah = 8.33 Btng
Panjang 1 Seng. = 1.30 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 4.28 Kg

Total Berat Tul. 2 = 144.24 Kg

Berat Total Tul. = 422.73 Kg

- Bakisting = 7.56 m2

b. Sloof 30 x 40 cm
Panjang = 27.00 m
Lebar = 0.30 m
Tinggi = 0.40 m
Volume Beton = 3.24 m3

Bakisting = 21.60 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 27.00 m
Jumlah = 10.00 Btng
Panjang Total = 270.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 240.30 Kg

Panjang Tul. = 27.00 m


Jumlah = 181.00 Btng
Panjang 1 Seng. = 1.50 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 107.24 Kg

Berat Total = 347.54 Kg

c. Kolom 15 x 15 cm
Tinggi = 3.50 m
Lebar = 0.15 m
Panjang = 0.15 m
Jumlah Kolom = 9.00 bh
Volume Beton = 0.71 m3

Bakisting = 18.90 m2
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 3.50 m
Jumlah = 4.00 Btng
Panjang Total = 14.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 12.46 Kg

Panjang Tul. = 3.50 m


Jumlah = 24.33 Btng
Panjang 1 Seng. = 0.95 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 9.13 Kg

Berat Total = 194.32 Kg

d. Ring Balk 15 x 20 cm
Panjang = 27.00 m
Lebar = 0.20 m
Tinggi = 0.15 m
Volume Beton = 0.81 m3

Bakisting = 10.80 m2

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 27.00 m
Jumlah = 4.00 Btng
Panjang Total = 108.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 96.12 Kg

Panjang Tul. = 27.00 m


Jumlah = 181.00 Btng
Panjang 1 Seng. = 0.70 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 50.05 Kg

Total Tulangan = 146.17 Kg

e. Plat Lantai T = 0.2 m


Panjang = 6.00 m
Lebar = 5.00 m
Tebal = 0.20 m
Volume Beton = 6.00 m3

- Penulangan Ø12 -150 mm


Panjang = 6.00 m
Lebar = 5.00 m
Panjang Tul. Atas 1 = 1.30 m
Panjang Tul. Atas 2 = 0.90 m
Berat Tulangan Ø12 = 0.89 Kg/m
Sketsa Perhitungan

- Tulangan Atas Arah Memanjang


Panjang = 4.88 m
Jumlah Tulangan = 34.33 Btng

- Tulangan Bawah Arah Memanjang


Panjang = 6.00 m
Total Panjang Tul. = 373.55 m
Berat Tulangan = 332.46 Kg

- Tulangan Atas Arah Melintang


Panjang = 2.66 m
Jumlah Tulangan = 41.00 Btng

- Tulangan Bawah Arah Memanjang


Panjang = 5.00 m
Total Panjang Tul. = 314.06 m
Berat Tulangan = 279.51 Kg

Total Berat Tulangan = 611.97 Kg

3. Pekerjaan Dinding
Panjang = 27.00 m
Tinggi Dinding = 3.50 m
Luas Dinding = 94.50 m2

Pengurangan Dinding
Pintu 1
Tinggi = 2.30 m
Lebar = 1.70 m

Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m

Pintu 1
Tinggi = 1.55 m
Lebar = 1.15 m

Rooster 1
Tinggi = 1.20 m
Lebar = 0.80 m

Rooster 2
Tinggi = 0.60 m
Lebar = 1.60 m

Luasan = 14.48 m2

Luas Tembok = 80.02 m2

Plesteran = 160.04 m2
Acian = 160.04 m2
Pengecetan = 160.04 m2
Sketsa Perhitungan

4. Pekerjaan Atap
Kayu 6/12 Kuda-Kuda 1
Panjang Kayu = 19.25 m
Volume Kayu = 0.14 m3

Kayu 6/12 Kuda-Kuda 2


Panjang Kayu = 2.77 m
Volume Kayu = 0.12 m3

Total Kayu Atap = 0.26 M3

Kayu Gording 5/10 Kuda-Kuda 1


Panjang Gording = 7.45 m
Jumlah Gording = 6.00 Btng
Volume Kayu = 0.45 m3

Beugel u = 2.00 Bh
Plat Strip = 4.00 bh
Bout 15 cm = 5.00 bh
Bout 30 cm = 4.00 bh

- Penutup Atap Seng


Panjang = 7.45 m
Lebar 1 = 4.00 m
Lebar 2 = 1.84 m
Luas = 73.31 m2
Seng Bubungan = 7.45 m

5. Pekerjaan List Plank 3 x 20

Panjang = 41.35 m

6. Pekerjaan Plafon
Panjang = 7.45 m
Lebar = 6.45 m
Luas Plafon = 48.05 m2
Pengecetan Plafon = 48.05 m2
List Plafond = 69.00 m'

7. Pekerjaan Teras

Panjang = 5.00 m Lebar Rabat Lantai K-125 = 1.35 m


Lebar = 1.50 m Labar Rabat Lantai K-125 = 0.25 m
Tebal Urugan = 0.05 m Lebar Lantai Rabat K-175 = 2.10 m
Tebal Anstamping = 0.15 m Tebal Rabat K-125 = 0.10 m
Lebar Anstamping = 0.50 m Tebal Rabat K-175 = 0.05 m
Lebar Pondasi = 0.30 m Tinggi Sloof = 0.20 m
Tinggi Pondasi = 0.30 m Lebar Sloof = 0.15 m
Tinggi Galian = 0.45 m

- Volume Galian Tanah = 2.93 m3 - Volume Rabat Lantai K-125 = 0.80 m3


- Volume Urugan Pasir = 0.33 m3 - Volume Rabat K-175 = 0.53 m3
- Volume Anstamping = 0.98 m3 - Volume Sloof = 0.39 m3
- Urugan Tanah = 0.78 m3
- Pasangan Batu = 1.17 m3
Sketsa Perhitungan

- Penulangan 10- Ø12, Ø8 -150 mm


Panjang Tul. = 13.00 m
Jumlah = 4.00 Btng
Panjang Total = 52.00 m
Berat Tulangan Ø12 = 0.89 Kg/m
Berat Tul. Pokok = 46.28 Kg

Panjang Tul. = 13.00 m


Jumlah = 87.67 Btng
Panjang 1 Seng. = 0.70 m
Berat Tulangan Ø8 = 0.40 Kg/m
Berat Tul. Sengkang = 24.24 Kg

Total Tulangan = 70.52 Kg

8. Pekerjaan Pintu dan Jendela


Pintu 1
Tinggi = 2.30 m
Lebar = 1.70 m
Luas = 3.91 m2
Volume Kayu = 0.03 m3

Pintu 2
Tinggi = 2.30 m
Lebar = 0.90 m
Luas = 2.07 m2
Volume Kayu = 0.03 m3

Jendela 1
Tinggi = 1.55 m
Lebar = 1.15 m
Luasan = 1.78 m2
Volume Kayu = 0.03 m3

Total Volume Jendela dan Pintu


= 0.09 m3

9. Beton Dudukan Genset

Panjang = 2.00 m
Lebar = 1.50 m
Tebal = 0.20 m
Volume = 0.60 m3
Uraian Volume Rumah Genset

Jenis Pekerjaan Satuan Volume

1. Galian Tanah
a. Galian Tanah Untuk Pondasi Foot Plat M3 9.45
b. Urugan Tanah Kembali m3 7.18
2. Pekerjaan Struktur
a. Foot Plat
- Beton m3 2.95
- Penulangan Ø12 - 150 mm Kg 422.73
- Bakisting M2 7.56
b. Sloof 30 x 40 cm
- Beton m3 3.24
- Bakisting M2 21.60
- Penulangan Polos Kg 347.54
c. Kolom 15 x 15 cm
- Beton m3 0.71
- Bakisting M2 18.90
- Penulangan Polos Kg 194.32
d. Ring Balk 15 x 20 cm
- Beton m3 0.81
- Bakisting M2 10.80
- Penulangan Polos Kg 146.17
e. Plat Lantai T = 0.2 m
- Beton m3 6.00
- Bakisting M2
- Penulangan Polos Kg 611.97
3. Pekerjaan Dinding
- Dinding Batako M2 80.02
- Dinding Rooster M2 1.92
- Plesteran M2 160.04
- Acian M2 160.04
- Pengecatan M2 160.04
4. Pekerjaan Atap
- Kuda-Kuda Kayu 6/12 cm M3 0.26
- Gording Kayu 5/12 cm M3 0.45
Beugel u Bh 2.00
Plat Strip Bh 4.00
Bout 15 cm Bh 5.00
Bout 30 cm Bh 4.00
- Seng Gelombang BJLS. 0.30 M2 73.31
5. Pekerjaan List Plank 3 x 20 M2 41.35
6. Pekerjaan Plafon M2 48.05
7. Pekerjaan Teras
- Volume Galian Tanah M3 2.93
- Volume Urugan Pasir M3 0.33
- Volume Anstamping M3 0.98
- Urugan Tanah M3 0.78
- Pasangan Batu M3 1.17
- Volume Rabat Lantai K-125 M3 0.80
- Volume Rabat K-175 M3 0.53
- Volume Sloof M3 0.39
- Penulangan Sloof 15 x 20 Kg 70.52
8. Pekerjaan Pintu dan Jendela
- Kayu Jendela dan Pintu M3 0.09
- Daun Jendela M2 1.78
- Daun Pintu M2 5.98
- Engsel Pintu Bh 12.00
- Engsel Jendela Bh 4.00
- Kait Angin Bh 2.00
- Kunci Tanam Bh 2.00
9. Beton Dudukan Genset M3 0.60
BACK UP VOLUME PEKERJAAN
PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM
LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)
TAHUN ANGGARAN : 2019

BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN

1 RENCANA PIPA TRANSMISI GIP 200 MM


PATOK CP.0 - CP. 5

Pipa GIP dia. 200mm 5544.80 M


Bend All Flange Ø 200mm - 90° 3.00 Bh
Bend All Flange Ø 200mm - 45° 5.00 Bh
Bend All Flange Ø 200mm - 22.5° 3.00 Bh
Flange Ø 200mm 28.00 Bh
Paking Karet Ø 200mm 28.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 312.00 Bh

1 GALIAN PIPA PIPA BIASA


GALIAN TYPE 1 (CP.0-Pa.5, Pa. 25, Pa.30-Pa.33)
Galian Tanah 425.00 0.80 1.50 510.00
Urugan Tanah Kembali Timbunan Pasir 425.00 0.80 1.10 374.00
Galian/Tim bunan tanah kembali
Urugan Pasir 425.00 0.80 0.40 0.03 135.97
Trotoar/Pas. Paving
Bahu Jalan

Jalan Negara /Hotmix

MT

1.10

Pipa GIP Ø 200 mm


0.40

0.80

GALIAN TYPE 2 (CP.4-a.18)


Galian Tanah 436.00 0.60 0.85 222.36
Urugan Tanah Kembali Bahu Jalan
436.00 0.60 0.45 117.72
Timbunan Pasir
Urugan Pasir Galian/Timbunan tanah kembali
Jalan Lingkungan /Lapen
436.00 0.60 0.40 0.03 104.61

MT

0.45

Pipa GIP Ø 200 mm


0.40

0.60
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
GALIAN TYPE 3 (a.18-P.22a)
Jalan Lingkungan /Lapen
Galian Tanah 906.00 0.70 0.85 539.07
Bahu Jalan
Urugan Tanah Kembali Timbunan Pasir
906.00 0.70 0.45 285.39
Urugan Pasir Galian/Timbunan tanah kembali
906.00 0.70 0.40 0.04 253.64

MT

0.30
Pipa GIP Ø 50 mm
Transmisi dari Res. 500 m3
0.55 Pipa GIP Ø 200 mm
Transmisi dari IPA

0.70

GALIAN TYPE 4 (2 PIPA DALAM 1 LUBANG) (P.22a-CP.5)


Galian Tanah 185.97 1.10 0.85 173.88
Urugan Tanah Kembali 185.97 1.10 0.30 61.37
Timbunan Pasir
Urugan Pasir 185.97 1.10 0.55 0.04 112.47
Galian/Timbunan tanah kembali Pipa GIP Ø 50 mm
Transmisi dari Res. 500 m3
TOTAL GALIAN PIPA BIASA MT
Ke Res. 200 m3

Galian Tanah 1445.31 M3


0.30
Pipa GIP Ø 100 mm
Urugan Tanah Kembali 838.48 M3
Distribusi dari Res. 500 m3
Urugan Pasir 606.69 M3
0.55
Pipa GIP Ø 200 mm
Transmisi dari IPA

1.10

2 GALIAN PIPA PIPA DENGAN PEMBONGKARAN TROTOAR


Pembongkaran Trotoar Existing 2214.80 0.95 2104.06 M2
Pemasangan Kembaali Paving Trotoar 2214.80 0.95 2104.06 M2
Jalan Negara /Hotmix
Galian Tanah Timbunan Pasir 2214.80 0.80 1.50 2657.76 M3
Urugan Tanah Kembali Galian/Timbunan tanah kembali 2214.80 0.80 1.10 1949.02 M3
Urugan Pasir Bongkaran Trotoar/Paving 2214.80 0.80 0.40 0.03 708.70 M3
dipasang kembali
0.15 0.95 0.15

1.10

Pipa GIP Ø 200 mm


0.40
(Transmisi)

0.80
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
3 GALIAN PIPA PIPA DENGAN PEMBONGKARAN TROTOAR & SALURAN
Pembongkaran Trotoar Existing Jalan negara/Hotmix
520.00 0.95 494.00 M2
Pemasangan Kembaali Paving Trotoar Trotoar/Pas. Paving
dibongakar & dipasang kembali
520.00 0.95 494.00 M2
Beton Penutup Saluran
dibongakar & dipasang kembali
Saluran Existing
GALIAN TYPE 1 (Pa.19-a.2, Pa.33-Pa.37)
Pembongkaran Dasar Saluran Existing 445.00 0.80 0.30 106.80
Pemasangan Kembali Dasar saluran Existing Rabat Beton
0.80 445.00 0.80 0.30 106.80
Galian Tanah 445.00 0.80 0.30 106.80
Bongkaran Pas. Batu
Urugan Pasir Pas. Batu kembali
0.30
445.00 0.80 0.30 0.03 106.77
Pipa GIP Ø 200 mm
0.30
(Transmisi)

0.80

GALIAN TYPE 2 (Pa.25-Pa.26, Pa.42-Pa.43)


Pembongkaran Dasar Saluran Existing 75.00 1.00 0.30 22.50
Pemasangan Kembali Dasar saluran Existing Jalan negara/Hotmix 75.00 1.00 0.30 22.50
Trotoar/Pas. Paving

Galian Tanah dibongakar & dipasang kembali


Beton Penutup Saluran
75.00 1.00 0.15 11.25
dibongakar & dipasang kembali
Urugan Pasir Saluran Existing 75.00 1.00 0.15 0.03 11.22

1.20
Rabat Beton

Bongkaran Pas. Batu


GALIAN PIPA PIPA DENGAN PEMBONGKARAN TROTOAR & SALURAN Pas. Batu kembali

0.30
Pembongkaran Dasar Saluran Existing Pip a GIP Ø 200 mm
(Transmisi)
0.15
129.30 M3
Pemasangan Kembali Dasar saluran Existing 1.00 129.30 M3
Galian Tanah 118.05 M3
Urugan Pasir 117.99 M3

4 GALIAN PIPA PIPA DENGAN PEMBONGKARAN SALUAN


GALIAN TYPE 1 (Pa.63-Pa.70)
Pembongkaran Dasar Saluran Existing Jalan negara/Hotmix
306.00 0.60 0.30 55.08
Pemasangan Kembali Dasar saluran Existing 306.00 0.60 0.30 55.08
Galian Tanah 306.00 0.60 0.40 73.44
Urugan Pasir 306.00 0.60 0.30 0.03 55.05
0.65
Rabat Beton

0.05
Bongkaran Pas. Batu
0.30
Pas. Batu kembali

Pipa GIP Ø 200 mm


0.40
(Transmisi)

0.60

GALIAN TYPE 2 (Pa.70-a.8)


Pembongkaran Dasar Saluran Existing 223.00 0.80 0.30 53.52
Pemasangan Kembali Dasar saluran Existing 223.00 0.80 0.30 53.52
Galian Tanah
0.75
223.00 0.80 0.30 53.52
Urugan Pasir Rabat Beton 223.00 0.80 0.30 0.03 53.49

Bongkaran Pas. Batu 0.05

Pas. Batu kembali 0.30


GALIAN PIPA PIPA DENGAN PEMBONGKARAN SALURAN
Pipa GIP Ø 200 mm
Pembongkaran Dasar Saluran Existing 0.30 108.60 M3
(Transmisi)
Pemasangan Kembali Dasar saluran Existing 108.60 M3
0.80
Galian Tanah 126.96 M3
Urugan Pasir 108.54 M3
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
5 GALIAN PIPA PIPA DENGAN PEMBONGKARAN RABAT BETON
Pembongkaran Rabat Beton 341.00 0.80 0.10 27.28 M3
Pemasangan Kembali Rabat Beton 341.00 0.80 0.10 27.28 M3
Galian Tanah Timbunan Pasir 341.00 0.80 1.50 409.20 M3
Urugan Tanah Kembali Galian/Timbunan tanah kembali
Bahu Jalan Rabat Beton 341.00 0.80 1.10 300.08 M3
Trotoar/Pas. Paving
Urugan Pasir 1.50 Jalan Negara /Hotmix 341.00 0.80 0.40 0.03 109.09 M3
MT
0.10

1.10

1.50

Pipa GIP Ø 200 mm


0.40

0.80

6 Crossing Jalan
Jalan Hotmix
Galian Tanah Pengaspalan kembali
8.00 0.80 0.60 3.84 M3
Jalan Negara /Hotmix
Urugan Pasir Beton Mutu K.175 8.00 0.80 0.20 0.03 1.25 M3
Urugan Tanah Kembali Sirtu
8.00 0.80 0.20 1.28 M3
Galian/Timbunan Tanah Kembali
Urugan Sirtu Jalan ke Bandara 8.00 0.80 0.10 0.64 M3
Hotmix
Beton K-175 8.00 0.80 0.10 0.64 M3
Lapisan Aspal 8.00 0.80 0.03 0.19 M3
1.10

Pipa GIP Ø 200 mm


0.40
(Transmisi)

0.80

Jalan Lapen
Galian Tanah 42.00 0.60 0.85 21.42 M3
Urugan Pasir Rabat Beton 42.00 0.60 0.40 0.03 10.05 M3
Timbunan Pasir
Jalan Lingkungan /Lapen
Urugan Tanah Kembali Galian/Timbunan tanah kembali 42.00 0.60 0.35 8.82 M3
Rabat Beton Muka Jalan
42.00 0.60 0.10 2.52 M3
0.45

Pipa GIP Ø 200 mm


0.40

0.60
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
2 RENCANA PIPA DISTRIBUSI GIP 200 MM
A Rencana Reservoar 500 m3 - Reservoar Existing 100 M3 (CP. 5 - P. 1b)
Pipa GIP dia. 50mm 1 lubang dengan pipa GIP 100 85.00
Pipa GIP dia. 50mm dalam 1 lubang Timbunan Pasir 25.00
Total Pipa GIP 50 mm 110.00 M'
Galian
Knee GIP Ø 50mm - 90° Timbunan tanah kembali 1.00 Bh
Water Moer GIP Ø 50mm 2.00 Bh
MT
Socket GIP Ø 50mm 15.00 Bh

0.30
Galian Tanah 25.00 0.26 0.50 3.25 M3
Urugan Tanah Kembali 25.00 0.26 0.30 1.95 M3
Pipa GIP Ø 50 mm
Urugan Pasir 0.20 25.00 0.26 0.20 0.00 1.30 M3

0.26

B Rencana Reservoar 500 m3 - Reservoar Existing 200 M3 (CP. 5 - a18.1)


Pipa GIP dia. 50mm 1 lubang dengan pipa GIP 100 & pipa GIP 200 261.97
Pipa GIP dia. 50mm 1 lubang dengan pipa GIP 100 Timbunan Pasir 830.00
Pipa GIP dia. 50mm dalam 1 lubang 25.00
Galian
Total Pipa GIP 50 mm Timbunan tanah kembali 1116.97 M'
Knee GIP Ø 50mm - 90° 2.00 Bh
MT
Water Moer GIP Ø 50mm 6.00 Bh
Socket GIP Ø 50mm 178.00 Bh
0.30

Galian Tanah 25.00 0.26 0.50 3.25 M3


Pipa GIP Ø 50 mm
Urugan Tanah Kembali 0.20 25.00 0.26 0.30 1.95 M3
Urugan Pasir 25.00 0.26 0.20 0.00 1.30 M3
0.26

C Rencana Reservoar 500 m3 - Arah Pelabuhan Ipi (CP. 5 - CP. 6)


Pipa GIP dia. 100mm 1 lubang dengan pipa GIP 50 85.00
Pipa GIP dia. 1000mm bongkar trotoar 512.00
Pipa GIP dia. 1000mm di tanah biasa 832.40
Total Pipa GIP 100 mm 1429.40 M'
Bend All Flange GIP Ø 100mm - 90° 9.00 Bh
Bend All Flange GIP Ø 100mm - 45° 4.00 Bh
Loose Flange GIP 100 mm 13.00 Bh
Paking Karet dia. 100mm 13.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 104.00 Bh
Water Moer GIP Ø 100mm 6.00 Bh
Socket GIP Ø 100mm 218.00 Bh
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
GALIAN TYPE 1 (CP.5-P.1a) 1 lubang dengan pipa 50mm
Galian Tanah 85.00 0.55 0.75 35.06 M3
Timbunan Pasir
Urugan Tanah Kembali 85.00 0.55 0.25 11.69 M3
Galian
Urugan Pasir Timbunan tanah kembali 85.00 0.55 0.50 0.01 23.37 M3
MT
0.25
Pipa GIP Ø 50 mm
0.50 Pipa GIP Ø 100 mm

0.55

GALIAN TYPE 2 (P.1a-b.6)


Galian Tanah Jalan Lingkungan /Lapen
832.40 0.40 0.75 249.72 M3
Urugan Tanah Kembali 832.40 0.40 0.45 149.83 M3
Bahu Jalan
Urugan Pasir 832.40 0.40 0.30 0.01 99.88 M3
Timbunan Pasir

Galian
Timbunan tanah kembali

MT

0.45

Pipa GIP Ø 100 mm


0.30

0.40

GALIAN TYPE 3 (b.6-P.79) Bongkar Trotoar


Pembongkaran Trotoar Existing 512.00 0.50 256.00 M2
Pemasangan Kembaali Paving Trotoar 512.00 0.50 256.00 M2

Timbunan Pasir

Galian Tanah Galian/Timbunan tanah kembali 512.00 0.40 0.75 153.60 M3


Saluran Existing
Urugan Tanah Kembali Bongkaran Trotoar/Paving
512.00 0.40 0.45 92.16 M3
dipasang kembali
0.15 1.00 0.15
Urugan Pasir 512.00 0.40 0.30 0.01 61.43 M3

0.45

Pipa GIP Ø 100 mm


0.30

Jalan Hotmix
0.40
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 1 (Patok b.6)
Pembuatan Bak Kontrol
Galian Tanah 0.15
B
1.30 1.30 0.85 1.44
Pengurang 100x100x50 mm
Tee All Flange
1.30 0.40 0.75 0.39
Pip a PVC Ø 3" (Exis ting)
Pesi Pengangkat
Renc. Pip a GIP Ø 100 MM

1.00
A
Total 1.05 M3
Urugan sirtu A Gate Valv e Ø 50 mm
1.00 1.00 0.10 0.10 M3
Lantai Kerja Rabat Beton K-175 0.15
1.00 1.00 0.05 0.05 M3
Pas. Bata 1PC : 4PS 0.15
1.00
0.15
0.30 4.60 0.85 3.91 M2
Beton Tumbuk K-100 Bibir Bak Kontrol 0.20
4.60 0.15 0.20 0.14
Pengurang 0.60
4.60 0.07 0.08 0.03
Saluran Existing

Total 0.11 M3
0.20

Tutup Bak Kontrol


0.30

Beton K-175 0.60


1.15 1.15 0.08 0.10 M3
Renc. Pip a GIP Ø 50 mm

1.20 8.00 0.40


6 m (Persiapan Taping SR)

Pembesian B 7.58 Kg
Bekisting 4.60 0.08 0.35 M2
Plesteran 4.14 M2
Acian 4.14 M2
Bongkaran Saluran 1.60 0.60 0.30 0.29 M3
Pasangan Kembali Saluran 1PC : 4PS Penutup Beton Bertu la ng (Pra Cetak)
0.29 M3
1 PC : 3 Ps : 5 Kr
0.08
0.08 1.15
Beton Tumbuk
1 PC : 3 Ps : 5 Kr Paving Block
Timbunan Pasir

0.05 0.07

Giboult Joint Ø 100 mm Galian/T imbunan Tanah

Gate Valv e Ø 50 mm Timbunan Pasir


Flange Ø 100 mm

Aksesories Bak Kontrol


Pas. Batu Bata
Renc. Pipa GIP Ø 100 mm
1 PC : 4 Ps
0.85 (Distribusi)

Tee All Flange Ø 100x100x100mm 1.00 Bh


Tee 100 x 100 x 100

2.00 Bh
Pipa PVC Ø 3" (Existing)
Gate Valve All Flange Ø 100mm (Distribusi)
0.05
0.10

Giboul Join Ø 100mm Rabat Beton K.175


Timbunan Sirtu
2.00 Bh
4.00 Bh
0.15 1.00 0.15
Bend All Flange Ø 1000mm - 90°
POTONGAN A - A
Paking Karet Ø 100mm Skala 1:20 16.00 Bh
Loose Flange Ø 100mm Penutup Beton Bertula ng (Pra Cetak)
1 PC : 3 Ps : 5 Kr
16.00 Bh
Beton Tumbuk

Baut Moer 5/8 x 3 Metal + Ring 1 PC : 3 Ps : 5 Kr


Kanstin
dibongkar dan dipasang kembali
0.30 0.60 0.30 128.00 Bh
Saluran Pasangan Batu
Dibongkar dan dipasang kemabali sepanjang 60 cm
Jalan Hotmix
0.05 0.07 Galia n/Timbunan Tanah
Timbunan Pasir

Gatevalve Ø 100 mm

Pas. Batu Bata Pip a Renc. GIP Ø 100 mm


1 PC : 4 Ps Pip a Distribusi dari Renc. Reservoar 500 m
0.85

0.30

0.15
Rabat Beton K.175 0.40
Bend 90°
Timbunan Sirtu Pipa GIP Ø 100 mm

0.15 1.00 0.15

1.10

POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 2 (Patok P.72)
Pembuatan Bak Kontrol
Galian Tanah B 1.30 1.30 0.85 1.44
1.30 0.40 0.75
0.15

Pengurang 0.39
100x100x50 mm Cro sing Jalan Hotmix
Tee All Flange

A
Renc. Pipa GIP Ø 100 MM
Total 1.05 M3
Urugan sirtu 1.00 1.00 0.10 0.10 M3
1.00

Lantai Kerja Rabat Beton K-175 A


1.00 1.00 0.05 0.05 M3
Gate Valve Ø 50 mm

Pas. Bata 1PC : 4PS


0.15
4.60 0.85 3.91 M2
0.30

4.60 0.15 0.20


0.15 1.00 0.15
Beton Tumbuk K-100 Bibir Bak Kontrol 0.14
0.20

Pengurang 4.60 0.07 0.08 0.03


0.80
Total 0.11 M3
Tutup Bak Kontrol Saluran Existing

Beton K-175 0.20 1.15 1.15 0.08 0.10 M3


Pembesian 0.30
1.20 8.00 0.40 7.58 Kg
4.60 0.08
0.60

Bekisting 0.35 M2
B

Plesteran 4.14 M2
DENAH BAK KONTROL (BK. 2)
Acian Skala 1:20
4.14 M2
Bongkaran Saluran 1.80 0.60 1.00 1.08 M3
Pasangan Kembali Saluran 1PC : 4PS 1.08 M3

Penutup Beton Bertu lang (Pra Cetak)


1 PC : 3 Ps : 5 Kr
0.08
1.15 0.08
Beton Tumbuk
1 PC : 3 Ps : 5 Kr

Aksesories Bak Kontrol Paving Block


0.07 0.05

Tee All Flange Ø 100x100x50mm Gib oult Joint Ø 100 mm


1.00 Bh
Fla nge Ø 100 mm Pas. Batu Bata

1.00 Bh
Renc. Pip a GIP Ø 100 mm
Gate Valve All Flange Ø 100mm (Distrib usi)
Gate Valve Ø 50 mm
0.85
1 PC : 4 Ps

Gate Valve All Flange Ø 50mm 1.00 Bh


Renc. Pipa GIP Ø 50 mm
Renc. Pipa GIP Ø 100 mm
Giboul Join Ø 100mm (Persiapan Taping SR)
(Distrib usi) 1.00 Bh
0.15

Giboul Join Ø 50mm 0.15 1.00 0.15


1.00 Bh
Bend All Flange Ø 50mm - 90° POTONGAN A - A 4.00 Bh
Penutup Beton Bertu lang (Pra Cetak) Skala 1:20
1 PC : 3 Ps : 5 Kr I
Dop Ø 50mm Beto n Tumbuk
Pip a PVC Ø 3" 1.00 Bh
1 PC : 3 Ps : 5 Kr
TP
Paking Karet Ø 100mm Paving Block
2.00 Bh
0.05 0.07

Paking Karet Ø 50mm 11.00 Bh


Loose Flange Ø 100mm Pas. Batu Bata
1 PC : 4 Ps
2.00 Bh
0.85 Flange Ø 100 mm

Loose Flange Ø 50mm 11.00 Bh


Baut Moer 5/8 x 3 Metal + Ring 82.00 Bh
0.90

Pipa GIP Ø 50mm 0.15 0.70 4.00 M'


0.15 1.00 0.15

Bend 90°
Pip a GIP Ø 50 mm

1.80

POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 3 (Patok P.79)
Pembuatan Bak Kontrol B

Galian Tanah 0.15


1.30 1.30 0.85 1.44
Pengurang 100x100x50 mm
Tee All Flange 1.30 0.40 0.75 0.39
PesiPengangkat
Ren c. Pipa GIP Ø100 MM
A
1.00
Total 1.05 M3
Urugan sirtu 1.00 1.00 0.10 0.10 M3
A Gate Valv e Ø 50 mm

Lantai Kerja Rabat Beton K-175 1.00 1.00 0.05 0.05 M3


4.60 0.85
0.15
Pas. Bata 1PC : 4PS 3.91 M2
4.60 0.15 0.20
0.30
Beton Tumbuk K-100 Bibir Bak Kontrol 0.15 1.0 0 0.15
0.14
4.60 0.07 0.08
0.20
Pengurang 0.03
Total 0.11 M3
Tutup Bak Kontrol 0.80

Salu ran Existin g


Beton K-175 1.15 1.15 0.08 0.10 M3
Pembesian 0.20
1.20 8.00 0.40 7.58 Kg
Bekisting 0.30 4.60 0.08 0.35 M2
Plesteran 0.60
Ren c. Pipa GIP Ø50 mm
6 m (Persiapan Taping SR)
4.14 M2
B
Acian Patok Tanda Titi Taping
Pip a PVC Ø3 " di is i beton
4.14 M2
Bongkaran Saluran
0.30
1.80 0.60 0.30 0.32 M3
0.30

Pasangan Kembali Saluran 1PC : 4PS DENAH BAK KONTROL (BK. 2) 0.32 M3
Skala 1:20

Aksesories Bak Kontrol Penutup Beto n Bertula ng (Pra Cetak)


1 PC : 3 Ps : 5 Kr
0.08
Tee All Flange Ø 100x100x50mm Beto n Tumbuk
1 PC : 3 Ps : 5 Kr
0.08 1.15
1.00 Bh
Gate Valve All Flange Ø 100mm 0.05 0.07 Paving Block 1.00 Bh
Gate Valve All Flange Ø 50mm 1.00 Bh
Giboult Joint Ø 100 mm

Giboul Join Ø 100mm Pas. Batu Bata


1 PC : 4 Ps
Flange Ø 100 mm
Gate Valv e Ø 50 mm
Renc. Pip a GIP Ø 100 mm 1.00 Bh
0.85 (Distribusi)

Giboul Join Ø 50mm 1.00 Bh


Bend All Flange Ø 50mm - 90° Renc. Pipa GIP Ø 100 mm Renc. Pipa GIP Ø 50 mm 4.00 Bh
(Persiapan Taping SR)
(Distribusi)

Dop Ø 50mm 0.15 1.00 Bh


Paking Karet Ø 100mm 0.15 1.00 0.15 2.00 Bh
POTONGAN A - A
Paking Karet Ø 50mm Skala 1:20 11.00 Bh
2.00 Bh
Penutup Beto n Bertu la ng (Pra Cetak)
Loose Flange Ø 100mm 1 PC : 3 Ps : 5 Kr
I Patok Tanda Tit i Tapin g
Pip a PVC Ø 3"
Beto n Tumbuk 0.30 0.80 0.30
Loose Flange Ø 50mm 1 PC : 3 Ps : 5 Kr
TP 11.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 0.05 0.07
82.00 Bh
Pipa GIP Ø 50mm 3.00 M'
Pas. Batu Bata
1 PC : 4 Ps
0.85 Flange Ø 100 mm

0.55
0.35

0.15

Bend 90°
0.15 1.00 0.15 Pip a GIP Ø 50 mm

0.60

1.50

POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
Pipa GIP dia. 75mm (P.69-P.72)
Pipa GIP dia. 75mm Type 1 150.00
Pipa GIP dia. 75mm Type 2 175.00
Total Pipa GIP 75 mm 325.00 M'
Bend All Flange GIP Ø 75mm - 45° 3.00 Bh
Loose Flange GIP 75 mm 3.00 Bh
Paking Karet dia. 75mm 3.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 24.00 Bh
Water Moer GIP Ø 100mm 2.00 Bh
Socket GIP Ø 75mm 49.00 Bh

GALIAN TYPE 1 (P.79-P.82)


Galian Tanah 150.00 0.40 0.75 45.00 M3
Urugan Tanah Kembali
Timbunan Pasir
150.00 0.40 0.45 27.00 M3
Urugan Pasir Galian/Timbunan tanah kembali
150.00 0.40 0.30 0.00 18.00 M3

0.45

Pipa GIP Ø 75 mm
0.30

Jalan Hotmix 0.40

GALIAN TYPE 2 (P.82-CP.6)


Galian Tanah 175.00 0.33 0.58 32.70 M3
Urugan Tanah Kembali 175.00 0.33 0.35 19.91 M3
Timbunan Pasir
Urugan Pasir 175.00 0.33 0.23 0.00 12.79 M3
Galian/Timbunan tanah kembali

0.35

Pipa GIP Ø 75 mm
0.225

Jalan Hotmix 0.325

BK 4 (Patok CP.6)
Pembuatan Bak Kontrol
Galian Tanah 1.30 1.30 0.85 1.44
Pengurang 1.30 0.40 0.75 0.39
0.15
Total 1.05 M3
Urugan sirtu 1.00 1.00 0.10 0.10 M3
75x75x50 mm
Lantai Kerja Rabat Beton K-175 Tee All Flange 1.00 1.00 0.05 0.05 M3
Renc. Pipa GIP Ø 100 MM
Pesi Pengangkat
Pas. Bata 1PC : 4PS Dop Ø 75 mm
4.60 0.85 3.91 M2
Beton Tumbuk K-100 Bibir Bak Kontrol 1.00 4.60 0.15 0.20 0.14
Pengurang 4.60 0.07 0.08 0.03
Total 0.11 M3
Gate Valve Ø 50 mm
Tutup Bak Kontrol
Beton K-175 1.15 1.15 0.08 0.10 M3
0.15
Pembesian 1.20 8.00 0.40 7.58 Kg
Dop Ø 50 mm
Bekisting 4.60 0.08 0.35 M2
0.15 1.00 0.15
Plesteran 4.14 M2
Patok Tanda Titi Taping
Acian 0.30 Pipa PVC Ø 3" di isi beton 4.14 M2

0.30
0.15
Dop Ø 50 mm

0.15 1.00 0.15


Patok Tanda Titi Taping
0.30 Pipa PVC Ø 3" di isi beton

BERAT SATU
NO KETERANGAN 0.30 SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN

Aksesories Bak Kontrol


Penutup Beton Bertulang (PraCetak)

Tee All Flange Ø 75x75x50mm 1 PC : 3 Ps : 5 Kr

0.08 1.15
0.08 1.00 Bh
Beton Tumbuk

Gate Valve All Flange Ø 50mm


1 PC : 3 Ps : 5 Kr
1.00 Bh
0.05
Giboul Join Ø 75mm Muka Tanah
0.07
Muka Tanah
1.00 Bh
Giboul Join Ø 50mm Giboult Jo int Ø 75 mm 1.00 Bh
Pas. Batu Bata Flange Ø 75 mm

Dop Ø 75mm 1.00 Bh


1 PC : 4 Ps Gate Valve Ø 50 mm
0.85

Dop Ø 50mm 1.00 Bh


Renc. Pipa GIP Ø 50 mm

Paking Karet Ø 75mm


Renc. Pipa GIP Ø 100 mm
(D istribusi)
(P ers iapan Taping SR)
2.00 Bh
0.15
Paking Karet Ø 50mm 3.00 Bh
0.15 1.00 0.15

Loose Flange Ø 75mm 2.00 Bh


POTONGAN A - A
Loose Flange Ø 50mm Skala 1:20 3.00 Bh
Penutup Beto n Bertulang (Pra Cetak)

Baut Moer 5/8 x 3 Metal + Ring 1 PC : 3 Ps : 5 Kr


34.00 Bh
Beton Tumbuk
I
1.00 M'
1 PC : 3 Ps : 5 Kr
Pipa GIP Ø 50mm
Patok Tanda Titi Taping
Pipa PVC Ø 3"

0.05 0.07 TP

Pas. Batu Bata


1 PC : 4 Ps
0.85 Flange Ø 75 mm

0.15

0.15 1.00 0.15

POTONGAN B - B
Skala 1:20

D Rencana Reservoar 500 m3 - Arah Wali Sanga (CP. 5 - CP. 7)


Pipa GIP dia. 100mm Type 1 185.97
Pipa GIP dia. 100mm Type 2 2264.00
Total Pipa GIP 100 mm Jalan Lingkungan /Lapen 2449.97 M'
Bend All Flange GIP Ø 100mm - 90° Bahu Jalan 7.00 Bh
Bend All Flange GIP Ø 100mm - 22,5° 2.00 Bh
Loose Flange GIP 100 mm Timbunan Pasir 9.00 Bh
Paking Karet dia. 100mm Galian 9.00 Bh
Timbunan tanah kembali
Baut Moer 5/8 x 3 Metal + Ring 72.00 Bh
MT
Water Moer GIP Ø 100mm 12.00 Bh
Socket GIP Ø 100mm 0.45 385.00 Bh

GALIAN TYPE 2 (CP.5-CP.7) Pipa GIP Ø 100 mm


0.30
Galian Tanah 2264.00 0.40 0.75 679.20 M3
Urugan Tanah Kembali 0.40 2264.00 0.40 0.45 407.52 M3
Urugan Pasir 2264.00 0.40 0.30 0.01 271.67 M3
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 5 (Patok c.1, P.34, P.38, P.48, P.56, P.63)
Pembuatan Bak Kontrol
Galian Tanah 1.30 1.30 0.85 1.44
0.15
Pengurang 1.30 0.40 0.75 0.39
75x75x50 mm Total 1.05 M3
Tee All Flange

Urugan sirtu Pesi Pengangkat


Renc. Pipa GIP Ø 100 MM 1.00 1.00 0.10 0.10 M3
Lantai Kerja Rabat Beton K-175 1.00 1.00 0.05 0.05 M3
1.00
Pas. Bata 1PC : 4PS 4.60 0.85 3.91 M2
Beton Tumbuk K-100 Bibir Bak Kontrol 4.60 0.15 0.20 0.14
Gate Valve Ø 50 mm

Pengurang 4.60 0.07 0.08 0.03

0.15
Total 0.11 M3
Tutup Bak Kontrol
Beton K-175 1.15 1.15 0.08 0.10 M3
Patok Tanda Titi Taping
Pipa PVC Ø 3" di isi beton
0.15 1.00 0.15

Pembesian 0.30 1.20 8.00 0.40 7.58 Kg


Bekisting 4.60 0.08 0.35 M2
0.30
Plesteran 4.14 M2
Acian 4.14 M2

Aksesories Bak Kontrol


Tee All Flange Ø 75x75x50mm Penutup Beton Bertulang (Pra Cetak)
1 PC : 3 Ps : 5 Kr 1.00 Bh
0.08
0.08 1.15
Gate Valve All Flange Ø 50mm Beton Tumbuk 1.00 Bh
1 PC : 3 Ps : 5 Kr

Giboul Join Ø 75mm 1.00 Bh


0.05 0.07
Giboul Join Ø 50mm Muka Tanah Muka Tanah
1.00 Bh
Dop Ø 50mm Giboult Joint Ø 75 mm
1.00 Bh
Paking Karet Ø 75mm Pas. Batu Bata
1 PC : 4 Ps
Flange Ø 75 mm
Gate Valve Ø 50 mm
2.00 Bh
0.85
Paking Karet Ø 50mm 3.00 Bh
Loose Flange Ø 75mm 2.00 Bh
Renc. Pip a GIP Ø 50 mm
Renc. Pipa GIP Ø 100 mm
Loose Flange Ø 50mm (Distribusi)
(Persiapan Taping SR) 3.00 Bh
0.15
Baut Moer 5/8 x 3 Metal + Ring 34.00 Bh
Pipa GIP Ø 50mm 0.15 1.00 0.15 1.00 M'
POTONGAN A - A
Skala 1:20
Penutup Beton Bertu lang (Pra Cetak)
1 PC : 3 Ps : 5 Kr

Beton Tumbuk
1 PC : 3 Ps : 5 Kr I Patok Tanda Titi Taping
Pipa PVC Ø 3"

0.05 0.07 TP

Pas. Batu Bata


1 PC : 4 Ps
0.85 Flange Ø 100 mm

0.15

0.15 1.00 0.15

POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BK 6 (Patok CP.7)
Pembuatan Bak Kontrol
Galian Tanah 1.30 1.30 0.85 1.44
Pengurang 1.30 0.40 0.75 0.39
0.15
Total 1.05 M3
Urugan sirtu 75x75x50 mm
1.00 1.00 0.10 0.10 M3
Tee All Flange
Lantai Kerja Rabat Beton K-175 Pesi Pengangkat Renc. Pipa GIP Ø 100 MM 1.00 1.00 0.05 0.05 M3
Pas. Bata 1PC : 4PS 4.60 0.85 3.91 M2
1.00
Beton Tumbuk K-100 Bibir Bak Kontrol 4.60 0.15 0.20 0.14
Pengurang Gate Valve Ø 50 mm
4.60 0.07 0.08 0.03
Total 0.11 M3
Tutup Bak Kontrol 0.15

Beton K-175 Patok Tanda Titi Taping


1.15 1.15 0.08 0.10 M3
Pipa PVC Ø 3" di isi beton
0.15 1.00 0.15
Pembesian 1.20 8.00 0.40 7.58 Kg
0.30
Bekisting 4.60 0.08 0.35 M2
0.30
Plesteran 4.14 M2
Acian 4.14 M2

Aksesories Bak Kontrol


Penutup Beton Bert ulang (Pra Cetak)
Tee All Flange Ø 75x75x50mm 0.08
1 PC : 3 Ps : 5 Kr
1.00 Bh
1.15 0.08
Gate Valve All Flange Ø 50mm Beton Tumbuk
1 PC : 3 Ps : 5 Kr 1.00 Bh
Giboul Join Ø 75mm 1.00 Bh
0.07 0.05

Giboul Join Ø 50mm Muka Tanah Muka Tanah 1.00 Bh


Dop Ø 75mm Giboult Joint Ø 75 mm 1.00 Bh
Flange Ø 75 mm Pas. Batu Bata
Dop Ø 50mm Gate Valve Ø 50 mm
0.85
1 PC : 4 Ps 1.00 Bh
Paking Karet Ø 75mm 2.00 Bh
Paking Karet Ø 50mm 3.00 Bh
Renc. Pip a GIP Ø 50 mm
Renc. Pipa GIP Ø 100 mm
Loose Flange Ø 75mm (Persiapan Taping SR)
(Distribusi) 2.00 Bh
0.15
Loose Flange Ø 50mm 3.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 0.15 1.00 0.15
34.00 Bh
POTONGAN A - A
Pipa GIP Ø 50mm Skala 1:20 1.00 M'
Penutup Beton Bertula ng (Pra Cetak)
1 PC : 3 Ps : 5 Kr

I Beton Tumbuk
1 PC : 3 Ps : 5 Kr
Pipa PVC Ø 3"

TP 0.07 0.05
Patok Tanda Titi Taping

Pas. Batu Bata


1 PC : 4 Ps
Flange Ø 100 mm 0.85

0.15

0.15 1.00 0.15

POTONGAN B - B
Skala 1:20
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
3 PEMBANGUNAN RESERVOIR KAPASITAS 500 M3
a Galian Tanah 1.00 1.00 1.15 22.00 25.30
30.00 12.65 2.40 455.40
3.30 2.58 0.20 1.70
+145.38
Talu d Penahan Camp. 1PC : 5PS
130.71 0.80 0.55 57.51
2.75 539.92
Pengurang 0.80 0.80 0.55 22.00 7.74
Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm
Total 532.17 M3
Pipa Outlet GIP Ø 100 mm ke CP.6 (Pel. Ipi)

Pipa Outlet GIP Ø 50 mm


ke Dusun Rukun Lima Atas (Reser 100 m3) 10.50 16.00

b Urugan Tanah Kembali Pip a Penguras GIP Ø 100 mm


Elevasi Reser
+146.41 177.39 M3
5
Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm Pipa Udara Ø50mm

c Pondasi Footplate

m
m

PipaOutlet GIPØ100m
PipaOutlet GIPØ50m
Beton K-225 2.75 0.90 0.90 0.30 22.00 5.35
0.30 0.30 0.80 4.00
Talud Penahan Camp. 1PC : 5PS

0.29
+147.75
Pipa Outlet GIP Ø 100 mm ke CP7 (Ds Tanjung) Pipa Inlet GIP Ø 200 mm
Dari IPA Wolowona (PDAM Kab. Ende)
0.30 0.30 1.20 18.00 1.94
Pipa Outlet GIP Ø 50 mm
ke Desa Rukun Lima (Reser 200 m3)

6.00 20.50 3.50


Total 7.58 M3
30.00
SITEPLAN
SKALA 1 : 150

Pembesian
Telapak Memanjang 2.00 6.00 0.40 104.28
Telapak Melintang 2.00 6.00 0.40 104.28
Tiang 1 1.20 8.00 0.40 15.17
Tiang 2 1.50 8.00 0.40 85.32
Sengkang Tiang 1 1.00 8.00 0.40 12.64
Sengkang Tiang 2 1.00 12.00 0.40 85.32
Total 407.01 Kg
0 .25
0 .15 2 .45
Plat Atap ( T = 1 5 cm)
Pipa Over flow
GIP Ø100 mm
0.2 0 0.20 0.20 0. 20 0.2 5
0 .2 5 3 .90 3 .80 3.8 0 3.80 3.90

Bekisting
0.5 0
0. 25
0.4 5

Pas. Dinding Bataco


1Pc : 5Ps
3 .2 5

Telapak 3.60 0.30 22.00 23.76


2. 85
2.5 0
Beton Bertulang (t = 20 cm) B eton Ber tulang (t = 25 cm)
Pipa Outlet GIP Ø 100 mm 1pc:2ps3:kr
1.50 0 .50

Tiang 0.30 0.80 4.00 3.84


0. 40 0. 30
0.20
Pas. Pondasi Batu Kali
0.05 0. 45
0 .4 5 0. 35
0.20 0. 20

Pond asi Footplate


Pipa Pengu ras GIP Ø 100 mm
2.58 4.1 3 4 .00
Lantai Kerja 1Pc : 3Ps : 5Kr (T = 5 cm)
4.00 Sirtu (T = 10 cm)
Pas . Batu Kosong ( T = 30 cm)
4.00 4.13
0 .80
1. 00
0.30 1.20 4.00 25.92
POTONGAN A - A
SKALA 1 : 100

Total 53.52 M3

d Pasangan Pondasi Batu Kali 122.25 0.35 0.80 34.23


8.20 0.33 0.50 1.33
Total 35.56 M3

e Urugan Sirtu 4.45 3.45 0.10 1.54


4.73 3.73 0.10 4.00 7.06
4.73 3.60 0.10 6.00
0.25 4.90 0.20 4.90 0.25
10.22
0.25
0.45
Total 18.81 M3
Pipa Inlet GIP Ø 200 mm

2.85
2.50

f Lantai Kerja 4.45 3.45 0.05 0.77


0.30
0.05
0.10
4.73 3.73 0.05 4.00 3.53
4.73 3.60 0.05 6.00 5.11
Lantai Kerja 1Pc : 3Ps : 5Kr (T = 5 cm) Total 9.40 M3
Sirtu (T = 10 cm)
Pas. Batu Kosong ( T = 30 cm)
5.13 5.13 2.88

g Lantai Dasar Reservoar POTONGAN B - B


SKALA 1 : 100

Berton K-225 20.62 10.55 0.30 65.26 M3

Pembesian Memanjang 21.22 70.33 0.89 2650.63


Pembesian Melintang 11.15 137.47 0.89 2722.17
Total 5372.80 Kg

Bekisting 62.34 0.30 18.70 M2


BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
h Dinding Reservoir
Beton K-225 55.44 0.25 2.85 39.50
8.60 0.25 2.85 4.00 24.51
0.25 4.90 0.20 4.90 0.25

Ø 8 - 150
Ø 10 - 150
Ø 10 - 150
Ø 12 - 150
Ø 8 - 150 5.70 0.25 2.85 2.00 8.12
0.25 4 Ø 10

Total 72.13 M3
4 Ø 10
0.25
Water Stop
L Water Stop
K
Ø 10 - 150 Ø 10 - 150 Ø 10 - 150

Pembesian 2.85
Ø 10 - 150

Water Stop
Ø 10 - 150

Water Stop
Ø 10 - 150

Water Stop

Melintang Dinding 55.74 19.00 0.62 1306.88


Water Stop Water Stop

Memanjang Dinding 3.15 369.60 0.62 1436.67


Ø 12 - 150 Water Stop Ø 12 - 150

0.30

Melintang Sekat I J 8.90 19.00 0.62 208.67


DETAIL PENULANGAN
SKALA 1 : 50
6.00 19.00 0.62 140.68
Memanjang Sekat 3.15 57.33 0.62 222.86
3.15 38.00 0.62 147.71
Total 3463.47 Kg

Bekisting 55.44 2.85 316.01


8.60 2.85 4.00 196.08
5.70 2.85 2.00 64.98
Total 577.07 M2
0.20 0.25

i Kolom Reservoir Ø 10 - 150 Ø 10 - 150


Water Stop
Beton K225 0.30 0.30 3.15 18.00 5.10 M3

Ø 10 - 150 Ø 10 - 150
Pembesian Water Stop Water Stop

Utama
Ø 12 - 150 Ø 12 - 150
3.15 8.00 1.04 471.74
Sengkang
0.30 0.30
1.00 31.50 0.40 223.97
Total 695.71 Kg

Bekisting Ø 12 - 150 0.60 2.85 14.00 23.94 M2

DETAIL I DETAIL J
j Balok Reservoir SKALA 1 : 20 SKALA 1 : 20

Beton K225 133.75 0.25 0.10 3.34 M3


Ø 10 - 150 Ø 8 - 150
Ø 8 - 150

Pembesian Ø 12 - 150
Ø 12 - 150 0.15
Utama 133.75 4.00 0.62 330.10
4 Ø 10
Sengkang Water Sto p
1.00 891.67 0.40 352.21
Water Stop Ø 10 - 150
Ø 10 - 150 Total 682.30 Kg

Ø 10 - 150
k Plat Atap Reservoir Ø 10 - 150

Beton K-225 0.25 20.50 10.50 0.25 53.81


DETAIL L 3.55 2.73 0.25 2.42
SKALA 1 : 20

DETAIL K 56.24
SKALA 1 : 20
Pengurang 0.70 0.70 0.25 7.00 0.86
Total 55.38 M3
8Ø 12
Ø 8-100
Pembesian
8Ø 12
Memanjang 10.80 136.67 0.62 1821.38
8D13 0,30 3.03 23.67 0.62 88.49
Melintang 20.80 70.00 0.62 1796.70
0,30
KL. 30x30
3.85 18.20 0.62 86.47
Skala 1:20
Total 3793.04 Kg
Foot plat
Skala 1:25
Bekisting 20.50 10.50 215.25
3.55 2.73 9.69
Total 224.94 M2
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
l Pasangan Batako Ruang Kontrol Pas 1PC : 5PS 8.20 3.75 30.75
Pengurang 0.90 2.00 1.80
Total 28.95 M2
1.98 0.73 4.13 4.00 4.00 4.00 4.13

m Plesteran & Acian 55.44 2.85 316.01


0.60 2.85 22.00 37.62
3.50
57.90
5.13
Total 411.53 M2

n Pengecatan 3.25
55.44 2.85 158.00
0.60 2.85 22.00 37.62
57.90
Total 253.52 M2
Pas. Pondasi Batu Kali 5.13
1Pc : 5Ps

3.50

Kolom 30x30

o Pekerjaan Talud
Galian Tanah Footplate 1.00x1.00 48.40 0.70 0.60 20.33
DENAH RENCANA PONDASI
SKALA 1 : 100 43.20 1.30 0.45 25.27
Total 45.60 M3

Urugan Tanah Kembali 15.20 M3

Pasangan Batu Talud 48.40 0.50 0.50 12.10


48.40 0.40 1.00 19.36
43.20 0.50 0.60 12.96
43.20 0.40 1.10 19.01
Ø 10 - 150

Ø 10 - 150 Total 63.43 M3


Ø 10 - 150

Pasangan Batu Saluran 47.20 1.60 0.20 15.10 M3


Ø10 - 150

Ø10 - 150

Ø10 - 150

Ø10 - 150

Ø10 - 150

Ø10 - 150
p Urugan Pasir Lantai Sekitar Reservoar Ø 10 - 150 5.80 2.40 0.10 1.39
Ø 10 - 150

5.20 2.60 0.10 1.35


3.40 3.00 0.10 1.02
6.00 3.80 0.10 2.28

DENAH PENULANGAN PLAT ATAP


26.50 2.73 0.10 7.23
9.20 3.50 0.10
SKALA 1 : 100

3.22
5.80 2.50 0.10 1.45
20.50 1.75 0.10 3.59
Total 21.54 M3

q Rabat Beton Mutu K-125 Lantai Sekitar Reservoir 5.80 2.40 0.05 0.70
5.20 2.60 0.05 0.68
3.40 3.00 0.05 0.51
6.00 3.80 0.05 1.14
26.50 2.73 0.05 3.62
9.20 3.50 0.05 1.61
5.80 2.50 0.05 0.73
20.50 1.75 0.05 1.79
Total 10.77 M3
BERAT SATU
NO KETERANGAN SKETSA PANJANG LEBAR TINGGI TEBAL JUMLAH RATA2 LUAS VOLUME
JENIS AN
r Aksesoris
Flange Socket Ø 200mm 5.00 Bh
Flange Socket Ø 100mm 35.00 Bh
Flange Socket Ø 75mm 12.00 Bh
Bend All Flange Ø 200mm - 90° 3.00 Bh
Bend All Flange Ø 100mm - 90° 6.00 Bh
Bend All Flange Ø 50mm - 90° 0.05 5.00 Bh
A
Gate Valve All Flange Ø 100mm Engsel 0.50 4.00 Bh
Gate Valve All Flange Ø 75mm 2.00 Bh
Gate Valve All Flange Ø 50mm 2.00 Bh
Handel Besi Ø10mm
Giboult Joint Ø 100mm 4.00 Bh
Palt Baja 70x70

Giboult Joint Ø 75mm 2.00 1.05


2.00 Bh
Giboult Joint Ø 50mm 6.00 Bh
Tee All Flange Ø 100mm DENAH TUTUP 2.00 Bh
SKALA 1 : 25
Paking Karet Ø 200 mm 6.00 Bh
Paking Karet Ø 100 mm Handel Besi Ø10mm
0.50
21.00 Bh
Paking Karet Ø 75 mm 10.00 Bh
Palt Baja 70x70
Paking Karet Ø 50 mm Gembok
Engsel 0.80 12.00 Bh
Besi Siku 50x50x5 0.05 0.05
Dop GIP Ø 75 mm 2.00 Bh
Baut Moer 5/8 x 3 Metal + Ring 312.00 Bh
DETAIL PINTU RESERVOAR
Tutup Bak Kontrol SKALA 1 : 20 7.00 Bh
Engsel Besi 17.00 Bh
POTONGAN A
Gembok SKALA 1 : 25 8.00 Bh
Pintu Teralis 1.00 Bh
NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

CP.0 - Pa. 5 250


Pa. 25 - 25
MT
Pa. 30 - Pa. 33 150
CP. 4 - a. 18 436 L = 0.60, T = 0.85
1 Galian Tanah 1.10

a. 18 - P. 22a 906 L = 0.70, T = 0.85


0.40
Pipa GIP Ø 200 mm
P. 22a - CP. 5 185.97 L = 1.10, T = 0.85
0.80

JUMLAH 1952.97

NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

Jalan Negara /Hotmix Pa. 5 - Pa. 19 750


Timbunan Pasir

Galian/Timbunan tanah kembali a. 2 - Pa. 25 58.8


Bongkaran Trotoar/P aving

dipasang kembali
0.15 0.95 0.15
Pa. 26 - Pa. 27 50
Pa. 27 - Pa. 30 150
Pa. 37 - Pa. 41 243
2 Bongkaran Trotoar 1.10

Pa. 43 - Pa. 63 963


Pipa GIP Ø 200 mm
0.40
(Transmisi)

0.80

JUMLAH 2214.8

NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

Pa. 19 - a. 2 245 L = 0.80, T = 0.60


Jalan negara/Hotmix

Trotoar/Pas. Paving Pa. 25 - Pa. 26 25 L = 1.00, T = 0.50


dibongakar & dipasang kembali
Beton Penutup Saluran
dibongakar & dipasang kembali
Pa. 33 - Pa. 37 200 L = 0.80, T = 0.60
Saluran Existing
Pa. 42 - Pa. 43 50 L = 1.00, T = 0.50

3 Bongkaran Trotoar & Saluran


0.80
Rabat Beton

Bongkaran Pas. Batu


0.30
Pas. Batu kembali
Pipa GIP Ø 200 mm
0.30
(Transmisi)

0.80

JUMLAH 520

NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

Jalan negara/Hotmix
Pa. 63 - Pa. 70 306 L = 0.60, T = 0.70
Pa. 70 - a. 8 223 L = 0.80, T = 0.60

0.75
Rabat Beton

4 Bongkaran Saluran 0.05


Bongkaran Pas. Batu

Pas. Batu kembali 0.30

Pipa GIP Ø 200 mm


0.30
(Transmisi)

0.80

JUMLAH 529
NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

Pengaspalan kembali

Beton Mutu K.175


Jalan Negara /Hotmix Pa. 41 - Pa.42 35 Hotmix
Sirtu a.10 - CP.4 6 Hotmix
Galian/Timbunan Tanah Kembali
Jalan ke Bandara
Hotmix

1.10

Pipa GIP Ø 200 mm


0.40
(Transmisi)

0.80

JUMLAH 41
5 Crossing Jalan
Pa.2 - Pa.3 6 Lapen
Pa.5 - Pa.6 6 Lapen
Pa.8 - Pa.9 6 Lapen
Rabat Beton
Timbunan Pasir
Jalan Lingkungan /Lapen
Pa.9 - Pa.10 8 Lapen
Galian/Timbunan tanah kembali
Pa.15 - Pa.16 6 Lapen
Muka Jalan
Pa.25 - Pa.26 10 Lapen
0.45

Pipa GIP Ø 200 mm


0.40

0.60

JUMLAH 42

NO JENIS GALIAN SKETSA PATOK PANJANG KETERANGAN

a. 8 - Cp. 4 341

Timbunan Pasir

Galian/Timbunan tanah kembali


Bahu Jalan Rabat Beton
Trotoar/Pas. Paving
1.50 Jalan Negara /Hotmix

MT
0.10

6 Bongkaran Rabat Bahu Jalan


1.10

1.50

Pipa GIP Ø 200 mm


0.40

0.80

JUMLAH 341
REKAPITULASI
ENGINEER ESTIMATE
PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM
LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)
TAHUN : 2019

JUMLAH
No URAIAN PEKERJAAN SATUAN VOLUME HARGA
(RP.)
1 2 3 4 5

I PEKERJAAN PERSIAPAN Rp 11,750,000.00

II PEKERJAAN PEMBANGUNAN BRONCAPTERING UNIT 1.00 Rp 45,350,000.00

III RENCANA PIPA TRANSMISI GIP 150 MM

1 Pengadaan dan Pemasangan Pipa GIP Ø 150 mm M' 4,021.00 Rp 2,832,996,319.27

PEKERJAAN BANGUNAN
IV BAK RESERVOIR(200 M3) UNIT 1.00 Rp 588,202,384.89

V RENCANA PIPA DISTRIBUSI

1 Pengadaan dan Pemasangan Pipa GIP Ø 100 mm M' 10,090.00 Rp 3,497,287,697.13

2 Pengadaan dan Pemasangan Pipa GIP Ø 50 mm M' 3,988.00 Rp 1,028,178,416.56

3 Pengadaan dan Pemasangan Pipa GIP Ø 25 mm M' 1,020.00 Rp 136,096,220.00

4 Pengadaan dan Pemasangan Pipa GIP Ø 40 mm Ke Kampung Adat M' 498.00 Rp 68,885,054.00

VI PEKERJAAN HIDRAN UMUM UNIT 3.00 Rp 40,492,366.63

PEKERJAAN
VII PENYELESAIAN

Pembersihan kembali lokasi Ls 1.00 Rp 2,000,000.00

Pelaporan dan Dokumentasi Ls 1.00 Rp 7,500,000.00

Asbuilt Drawing Ls 1.00 Rp 5,000,000.00

Jumlah Rp 8,263,738,458.48
PPn 10 % Rp 826,373,845.85
Jumlah Total Rp 9,090,112,304.33
Dibulatkan Rp 9,090,112,000.00
Terbilang :
Sembilan Milyar Sembilan Puluh Juta SeRatus Dua Belas Ribu Rupiah

Konsultan Perencana
CV. SAHWANA

STAFANUS L. TAPOBALI, ST
Team Leader
BILL OF QUANTITY

PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM


LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)

TAHUN ANGGARAN : 2019

HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
1 2 3 4 5 6

I PEKERJAAN PERSIAPAN
- Pembersihan Lokasi Ls 1.00 Rp 3,500,000.00 Rp 3,500,000.00
- Pengukuran Dan Pematokan Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
- Pemasangan Papan nama Ls 1.00 Rp 750,000.00 Rp 750,000.00
Jumlah Harga Pekerjaan Rp 11,750,000.00
III RENCANA PIPA TRANSMISI GIP 150 MM
1 Pengadaan dan Pemasangan Pipa GIP Ø 150 mm
a Pengadaan Pipa dan Aksesoies
- Socket Ø 150mm Bh 603.15 Rp 174,010.53 Rp 104,954,451.27
- Water Moor Ø 150mm Bh 67.02 Rp 417,000.00 Rp 27,945,950.00
- Bend All Flange Ø 150mm - 90° Bh 3.00 Rp 862,500.00 Rp 2,587,500.00
- Bend All Flange Ø 150mm - 45° Bh 5.00 Rp 862,500.00 Rp 4,312,500.00
- Bend All Flange Ø 150mm - 22.5° Bh 3.00 Rp 737,500.00 Rp 2,212,500.00
- Flange Ø 150mm Bh 28.00 Rp 902,000.00 Rp 25,256,000.00
- Paking Karet Ø 150mm Bh 28.00 Rp 17,825.00 Rp 499,100.00
- Baut Moer 5/8 x 3 Metal + Ring Bh 312.00 Rp 8,625.00 Rp 2,691,000.00
Sub Jumlah Rp 170,459,001.27
b Kontruksi Pemasangan pipa GIP Ø 150 mm
- Pengadaan & Pemasangan Pipa GIP Ø 150 mm M' 4,021.00 Rp 660,304.00 Rp 2,655,082,384.00
- Ujicoba pengaliran M' 4,021.00 Rp 1,854.00 Rp 7,454,934.00
Sub Jumlah Rp 2,662,537,318.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA TRANSMISI GIP DIAMETER 150 MM Rp 2,832,996,319.27
2 Pekerjaan Crossing Jalan
i Pekerjaan Crossing Jalan Hotmix
- Galian Tanah M3 3.84 Rp 54,625 Rp 209,760.00
- Urugan Pasir M3 1.25 Rp 536,608.00 Rp 670,760.00
- Urugan Tanah Kembali M3 1.28 Rp 19,550.00 Rp 25,024.00
- Urugan Sirtu M3 0.64 Rp 381,110.00 Rp 243,910.40
- Beton K-175 M3 0.64 Rp 1,963,845.00 Rp 1,256,860.80
- Lapisan Aspal M3 0.19 Rp 1,500,000.00 Rp 285,000.00
TOTAL PEKERJAAN CROSSING JALAN HOTMIX Rp 2,691,315.20
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
IV PEKERJAAN BANGUNAN BAK RESERVOIR(200 M3)
Pekerjaan Persiapan
- Pembersihan Lokasi Ls 1.00 500,000.00 500,000.00
- Pengadaan Air Kerja Ls 1.00 500,000.00 500,000.00
Sub Jumlah 1 1,000,000.00
Pekerjaan tanah
- Galian Tanah Cadas M3 143.17 110,055.00 15,756,794.46
- Urugan Sirtu M3 13.12 381,110.00 5,001,687.64
- Timbunan Tanah Kembali M3 47.72 19,550.00 933,004.20
Sub Jumlah 2 21,691,486.30
Pekerjaan Struktur
- Pekerjaan Pasangan Batu Kali 1pc : 4ps M3 23.52 1,394,664.00 32,802,497.28
- Pekerjaan Pasangan Batu Kosong M3 9.80 831,327.00 8,147,004.60
- Beton Tumbuk mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87 M3 6.56 1,773,797.00 11,639,655.91
- Lantai Beton Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 32.81 2,072,760.00 68,007,255.60
- Beton Dinding Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M3 51.22 2,072,760.00 106,170,912.72
- Plat Penutup Beton Mutu F'c =19.3 Mpa (K225) , Slump (12±2) cm, W/C =0.58 M2 17.72 2,072,760.00 36,722,052.54
- Pembesian Lantai kg 6,035.85 16,729.00 100,973,734.65
- Pembesian Dinding kg 3,818.01 16,729.00 63,871,506.02
- Pembesian Plat Beton Penutp kg 2,874.81 16,729.00 48,092,716.56
- Acian M2 695.49 32,188.00 22,386,271.18
- Pengecatan Bak M2 269.01 34,249.00 9,213,152.25
Sub Jumlah 3 508,026,759.31
Pekerjaan Pelengkap Accessories
- Flange socket/Flange Drat GIP. Dia 100 mm Buah 46.00 718,658.00 33,058,268.00
- Flange socket/Flange Drat GIP. Dia 50 mm Buah 1.00 805,000.00 805,000.00
- Tee All Flange GIP 150 x 150 x 150 mm Buah 1.00 450,000.00 450,000.00
- Tee All Flange GIP 100 x 100 x 100 mm Buah 3.00 128,800.00 386,400.00
- Gate Valve All Flange GIP Dia.100 mm Buah 7.00 25,000.00 175,000.00
- Gate Valve All Flange GIP Dia.50mm Buah 1.00 25,000.00 25,000.00
- Bend All Flange 90° GIP. Dia 100 mm Buah 11.00 500.00 5,500.00
- Bend All Flange 90° GIP. Dia 50 mm Buah 12.00 16,730.94 200,771.28
- Dop GIP Dia. 100 mm Buah 2.00 68,700.00 137,400.00
- Paking Karet dia 150 mm Buah 1.00 29,000.00 29,000.00
- Paking Karet dia 100 mm Buah 53.00 25,000.00 1,325,000.00
- Paking Karet dia 50 mm Buah 2.00 9,500.00 19,000.00
- Mur Baut 5/8 Buah 440.00 8,625.00 3,795,000.00
- Giboult Joint GIP Dia. 150 mm Buah 1.00 179,000.00 179,000.00
- Giboult Joint GIP Dia. 100 mm Buah 4.00 107,000.00 428,000.00
- Giboult Joint GIP Dia. 50 mm Buah 1.00 59,000.00 59,000.00
- Watermeter Dia 100mm Buah 1.00 3,270,000.00 3,270,000.00
- Watermeter Dia 50mm Buah 1.00 2,154,000.00 2,154,000.00
- Reducher Dia. 150 -100 mm Buah 2.00 420,200.00 840,400.00
- Reducher Dia. 100 - 50 mm Buah 1.00 325,000.00 325,000.00
- Pipa Udara Buah 8.00 287,500.00 2,300,000.00
- Tangga Besi Buah 4.00 575,000.00 2,300,000.00
- Engsel Pasang 8.00 39,675.00 317,400.00
- Gembok Buah 4.00 50,000.00 200,000.00
- Tutup Manhole dari plat baja Buah 4.00 862,500.00 3,450,000.00
- Pintu Teralis Buah 1.00 1,250,000.00 1,250,000.00
Sub Jumlah 4 57,484,139.28
Total Pekerjaan Bangunan Bak Reservoir 200 m3 Rp 588,202,384.89
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
V RENCANA PIPA DISTRIBUSI
1 Pengadaan dan Pemasangan Pipa GIP Ø 100 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 100mm - 90° Bh 2.00 Rp 119,000.00 Rp 238,000.00
- Water Moer GIP Ø 100mm Bh 170.00 Rp 193,000.00 Rp 32,810,000.00
- Socket GIP Ø 100mm Bh 1,511.00 Rp 80,212.25 Rp 121,200,717.13
Sub Jumlah Rp 154,248,717.13
b Kontruksi Pemasangan pipa GIP Ø 100 mm
- Pengadaan & Pemasangan Pipa GIP Ø 100 mm M' 10,090.00 Rp 329,813.00 Rp 3,327,813,170.00
- Ujicoba pengaliran M' 10,090.00 Rp 1,509.00 Rp 15,225,810.00
Sub Jumlah Rp 3,343,038,980.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 100 MM Rp 3,497,287,697.13
2 Pengadaan dan Pemasangan Pipa GIP Ø 50 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 50mm - 90° Bh 3.00 Rp 35,000.00 Rp 105,000.00
- Knee GIP Ø 50mm - 45° Bh 6.00 Rp 33,000.00 Rp 198,000.00
- Water Moer GIP Ø 50mm Bh 66.47 Rp 49,500.00 Rp 3,290,100.00
- Socket GIP Ø 50mm Bh 600.00 Rp 59,667.66 Rp 35,800,596.56
Sub Jumlah Rp 39,393,696.56
b Kontruksi Pemasangan pipa GIP Ø 50 mm
- Pengadaan & Pemasangan Pipa GIP Ø 50 mm M' 3,988.00 Rp 246,638.00 Rp 983,592,344.00
- Ujicoba pengaliran M' 3,988.00 Rp 1,302.00 Rp 5,192,376.00
Sub Jumlah Rp 988,784,720.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 50 MM Rp 1,028,178,416.56
3 Pengadaan dan Pemasangan Pipa GIP Ø 25 mm
A Jalur Pipa Distribusi Pipa GIP Ø 25 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 25mm - 90° Bh 2.00 Rp 21,500.00 Rp 43,000.00
- Knee GIP Ø 25mm - 45° Bh 2.00 Rp 21,000.00 Rp 42,000.00
- Water Moer GIP Ø 25mm Bh 17.00 Rp 29,000.00 Rp 493,000.00
- Socket GIP Ø 25mm Bh 153.00 Rp 22,500.00 Rp 3,442,500.00
Sub Jumlah Rp 4,020,500.00
b Kontruksi Pemasangan pipa GIP Ø 25 mm
- Pengadaan & Pemasangan Pipa GIP Ø 25 mm M' 1,020.00 Rp 128,184.00 Rp 130,747,680.00
- Ujicoba pengaliran M' 1,020.00 Rp 1,302.00 Rp 1,328,040.00
Sub Jumlah Rp 132,075,720.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 25 MM Rp 136,096,220.00
4 Pengadaan dan Pemasangan Pipa GIP Ø 40 mm Ke Kampung Adat
A Jalur Pipa Distribusi Pipa GIP Ø 40 mm
a Pengadaan Pipa dan Aksesoies
- Knee GIP Ø 40mm - 90° Bh 2.00 Rp 28,000.00 Rp 56,000.00
- Knee GIP Ø 40mm - 45° Bh 5.00 Rp 27,000.00 Rp 135,000.00
- Water Moer GIP Ø 40mm Bh 8.00 Rp 39,000.00 Rp 312,000.00
- Socket GIP Ø 40mm Bh 75.00 Rp 25,500.00 Rp 1,912,500.00
Sub Jumlah Rp 2,415,500.00
b Kontruksi Pemasangan pipa GIP Ø 40 mm
- Pengadaan & Pemasangan Pipa GIP Ø 40 mm M' 498.00 Rp 132,102.00 Rp 65,786,796.00
- Ujicoba pengaliran M' 498.00 Rp 1,371.00 Rp 682,758.00
Sub Jumlah Rp 66,469,554.00
TOTAL PEKERJAAN PEMBANGUNAN PIPA DISTRIBUSI GIP DIAMETER 40 MM KE KAMPUNG ADAT Rp 68,885,054.00
VI PEKERJAAN HIDRAN UMUM
i Pembuatan Pondasi Hidran Umum
- Galian tanah M³ 4.78 110,055.00 526,503.12
- Beton Tumbuk 1pc : 3 ps : 5 kr M³ 0.92 1,716,270.00 1,573,476.34
- Pekerjaan Aanstamping Batu Kali M³ 1.03 831,327.00 857,929.46
- Pasangan Batu Kali 1pc : 4 ps M2 3.06 1,394,664.00 4,267,671.84
- Urugan Pasir M³ 0.82 536,608.00 440,286.86
- Urugan Tanah Kembali M³ 0.59 19,550.00 11,557.96
- Plesteran 1 pc : 3 ps M2 8.39 66,424.00 556,984.69
- Acian M2 7.83 32,188.00 251,880.53
- Pengecatan Ls 1.00 1,500,000.00 1,500,000.00
Sub Jumlah 1 8,486,290.80
ii Asesories Hidran Umum
- Tee All Socket 20 x 20 x 20 Buah 1.00 12,100.00 12,100.00
- Bend 90 dia. 25mm Buah 4.00 21,500.00 86,000.00
- Bend 90 dia. 20mm Buah 2.00 19,500.00 39,000.00
- Stop Kran Inlet dia. 25mm Buah 1.00 39,000.00 39,000.00
- Tap Kran dia. 20mm Buah 2.00 49,414.22 98,828.44
- Double Neeple dia. 25mm Buah 2.00 11,509.00 23,018.00
- Double Neeple dia. 20mm Buah 3.00 9,009.00 27,027.00
- Water Moer dia. 25mm Buah 1.00 29,000.00 29,000.00
- Water Moer dia. 20mm Buah 3.00 26,000.00 78,000.00
- Kran Pelampung dia. 25mm Buah 1.00 69,000.00 69,000.00
- Packing Karet dia. 20mm Buah 2.00 5,095.65 10,191.30
- Tangki Hidran Umum Fiber Kapsitas 2m3 Buah 1.00 4,500,000.00 4,500,000.00
Sub Jumlah 2 5,011,164.74
TOTAL PEKERJAAN HIDRAN UMUM Rp 13,497,455.54
JUMLAH 3 UNIT Rp 40,492,366.63
VII PEKERJAAN PENYELESAIAN
HARGA JUMLAH
NO URAIAN PEKERJAAN SATUAN VOLUME SATUAN HARGA
(Rp.) (Rp.)
- Pembersihan kembali lokasi Ls 1.00 Rp 2,000,000.00 Rp 2,000,000.00
- Pelaporan dan Dokumentasi Ls 1.00 Rp 7,500,000.00 Rp 7,500,000.00
- Asbuilt Drawing Ls 1.00 Rp 5,000,000.00 Rp 5,000,000.00
TOTAL PEKERJAAN PENYELESAIAN Rp 14,500,000.00
UPAH TENAGA KERJA DAN HARGA SATUAN BAHAN

PEKERJAAN : PERECANAAN TEKNIS/DED PEMBANGUNAN DAN PENYEDIAAN SPAM


LOKASI : KABUPATEN SUMBA TIMUR (PURU KAMBERA)
TAHUN ANGGARAN : 2019

Upah Tenaga
No. Tenaga Kerja Satuan
Kerja (Rp./Hr)
1 Pekerja Org/Hari 61,000.00
2 Mandor Org/Hari 70,000.00
3 Kepala Tukang Org/Hari 75,000.00
4 Tukang Kayu Org/Hari 70,000.00
5 Tukang Batu Org/Hari 70,000.00
6 Tukang Besi Org/Hari 70,000.00
7 Tukang Las Org/Hari 70,000.00
8 Tukang Pipa Org/Hari 70,000.00
9 Tukang Cat Org/Hari 70,000.00
10 Operator Org/Hari 70,000.00
11 Pembantu Operator Org/Hari 61,000.00
12 Driver Org/Hari 70,000.00
13 Pembantu Driver Org/Hari 61,000.00
14 Mekanik Org/Hari 61,000.00
15 Helper (Pembantu) Org/Hari 59,500.00
16 Welder (Tukang Las) Org/Hari 70,000.00
No. Material Satuan Harga ( Rp )
1 2 3 4
BAHAN LOKAL
1 SemenPortland Kg 2,258.49
2 SemenPortland Zak 82,300.00
3 Semen Putih Kg 2,125.00
4 Pasir Filter M3 401,013.61
5 Pasir Urug M3 373,013.61
6 Pasir Pasang M3 401,013.61
7 Pasir Beton M3 401,013.61
8 Pasir Beton Kg 286.44
9 Sirtu M3 262,000.00
10 Batu Kali/Gunung/Karang M3 401,013.61
11 Koral Beton M3 571,000.00
12 Batu Gravel 5-10 cm M3 423,013.61
13 Batu Gravel 5-10 cm Kg 313.34
14 Batu Gravel 3-5 cm M3 812,718.64
15 Batu Gravel 3-5 cm Kg 602.01
16 Kerikil Gravel 2-3 cm M3 803,013.61
17 Kerikil Gravel 2-3 cm Kg 594.82
18 Kerikil Gravel 1-2 cm M3 596,439.37
19 Kerikil Gravel 1-2 cm Kg 441.81
20 Kerikil Gravel 0.5-1 cm M3 871,013.61
21 Kerikil Gravel 0.5-1 cm Kg 645.20
22 Bata Merah Buah 2,000.00
23 Batu Batako Buah 5,000.00
24 Batu Roster Buah 11,000.00
25 Kayu Klass III M3 3,163,000.00
26 Papan Bekisting 3/30 M3 2,531,000.00
27 Kayu Klas II Balok M3 4,428,000.00
28 Paku Biasa Kg 17,250.00
29 Sekrup Bh 7,500.00
30 Besi Beton Kg 12,625.00
31 Kawat Beton Kg 19,550.00
32 Kawat Lat Kg 184,000.00
33 Kawat Bronjong Kg 27,500.00
34 Cat Manie Kg 40,000.00
35 Cat Tembok (waterproof) Kg 63,250.00
36 Plamir Tembok Kg 7,000.00
37 Kuwas Buah 20,000.00
38 Amplas Lembar 7,500.00
39 Cat Kayu/Besi Kg 69,000.00
40 Cat Dasar Kg 63,250.00
41 Cat Tembok Kg 63,250.00
42 Plamir Kayu Kg 51,750.00
43 Plitur Liter 41,000.00
44 Plitur Kayu Liter 50,000.00
45 Minyak Cat (Tinner) Kg 31,625.00
46 Minyak Bekesting Kg 20,125.00
47 Sealant Tube 33,350.00
48 Lem Kayu (Webber) Liter 28,750.00
49 Lem Kayu (Webber) Kg 57,500.00
50 Paku Seng Kg 23,000.00
51 Paku 2-3 Kg 10,000.00
52 Paku 5-7 Kg 15,000.00
53 Paku 10 Kg 17,000.00
54 Paku 12 Kg 20,000.00
55 Lisplang Lembar 45,000.00
56 Besi Siku 40.40.4 M' 18,400.00
57 Besi Siku 50.50.5 M' 34,500.00
58 Besi Siku 30.30.3 M' 46,920.00
59 Plat Baja 1.9 mm Kg 69,662.92
60 Besi Profil Kg 32,666.67
61 Besi Beton Kg 23,000.00
62 Besi Strip M2 161,000.00
63 Besi Tralis M¹ 14,375.00
64 Kawan Beton Kg 19,550.00
65 Kawat Las Btg 2,300.00
66 Kawat Bronjong Kg 27,500.00
67 Kawat Harmonika M² 28,750.00
68 Kawat Duri Rol 287,500.00
69 Kawat Duri M' 3,500.00
70 Triplek 4 mm Lembar 74,300.00
71 Plywood/Multipek 9 mm Lembar 143,750.00
72 Teakwood 4 mm Lembar 97,750.00
73 Beugel U Buah 25,000.00
74 Jendela Nako M² 138,000.00
75 Besi Strip M² 161,000.00
76 Kunci Tanam Buah 86,250.00
77 Engsel Pintu Buah 28,750.00
78 Spring Knip Buah 12,000.00
79 Espanyolet Buah 45,000.00
80 Kait Angin Buah 17,250.00
81 Engsel Kupu-Kupu Buah 23,000.00
82 Grendel Buah 17,250.00
83 Kaca Tebal 3 mm M² 143,750.00
84 Kaca Tebal 5 mm M² 94,300.00
85 Plastik Kasa M¹ 23,000.00
86 Waterstop Lebar 20 cm M' 51,750.00
87 Angker Moer Baut Ø 16 mm - 25 cm Buah 5,750.00
88 Baja Honeycom WF.375.125.6.9, termasuk pabrikasi Kg 39,502.50
89 Baja WF.250.125.6.9 Kg 10,925.00
90 Baja Wide Flange (WF) 300.150.6,5.9 Kg 10,000.00
91 Baja Wide Flange (WF) 350.175.7.11 Kg 10,000.00
92 Baja Wide Flange (WF) 400.200.8.13 Kg 10,000.00
93 Baja Wide Flange (WF) 500.200.10.16 Kg 10,000.00
94 Baja Wide Flange (WF) 600.200.11.17 Kg 10,000.00
95 Baja Wide Flange (WF) 800.300.14.26 Kg 15,000.00
96 Pengaku dan Brancing L.50.50.05 Kg 10,752.50
97 Pengaku Kanal C.80.50.5 Kg 10,752.50
98 Plat-Plat 12.10.8.6 Kg 10,752.50
99 Plat RIB Buah 10,000.00
100 Besi Plat Pengaku Samping 300.232.08 Buah 300,000.00
101 Plat Tumpu Baja WF Tebal 12mm (30x40cm) Buah 450,000.00
102 Clamp Pipa Plat Strip 80.05 Buah 128,800.00
103 Baut Moer HTB Sambungan WF Ø 16 mm Buah 22,137.50
104 Baut Moer Pengaku dan Brancing Ø 16 mm Buah 18,112.50
105 Baut Moer Clamp Pipa Ø 19 mm Buah 14,950.00
106 Angker Moer Baut Ø 25 mm - 30 mm Buah 97,175.00
107 Pagar Landak Besi Beton dan Plat Strip Buah 560,625.00
108 Sambungan WF Set 563,500.00
109 Angker Moer Baut Ø 25 mm - 30 cm Buah 97,175.00
110 Baut Mur 19 mm + Ring Buah 12,000.00
111 Balok Kayu Bayam Buah 75,000.00
112 Angker rod 16 mm, panjang 60 cm Buah 21,500.00
113 Sling baja dia. 16mm M' 18,500.00
114 Sling baja dia. 12 mm M' 15,000.00
115 span skrup 16mm Buah 29,000.00
116 Kausen Buah 5,000.00
117 Klem sling Buah 20,000.00
118 Baut-moer 16 Buah 3,433.00
119 Baut-moer 12 Buah 1,900.00
120 Plat GIP 200.120.6 mm Buah 15,000.00
121 Plat GIP 120.80.6 mm Buah 20,000.00
122 Plat GIP 350.120.6 mm Buah 25,000.00
123 Clamp Support Pipa Ø 200 mm Buah 161,000.00
124 Clamp Support Pipa Ø 150 mm Buah 138,000.00
125 Clamp Support Pipa Ø 100 mm Buah 92,000.00
126 Clamp Support Pipa Ø 75mm Buah 74,750.00
127 Clamp Support Pipa Ø 50mm Buah 56,000.00
128 Ijuk Kg 10,000.00
129 Tutup Bak Kontrol Buah 862,500.00
130 Engsel Besi Buah 39,675.00
131 Gembok Buah 50,000.00
132 Pipa Udara Buah 287,500.00
133 Tangga Kontrol Buah 575,000.00
134 Pipa Selubung Buah 78,750.00
135 Pagar BRC dia. 6mm Lembar 184,012.50
136 Pintu Pagar BRC Lebar 1M¹ Buah 1,200,000.00
137 Pintu Teralis Buah 1,250,000.00
138 Jelusi Buah 750,000.00
139 Kawat saringan Buah 30,000.00
140 Katup Saringan Buah 102,000.00
141 Paving Block M² 125,000.00
142 Keramik 20 x 20 Buah 6,900.00
143 Keramik 30 x 30 Buah 8,818.18
144 Air Bersih M3 30,000.00
145 Air Bersih Ltr 30.00
146 Minyak Bensin Ltr 7,475.00
147 Minyak Solar Ltr 6,325.00
148 Minyak Pelumas Ltr 40,250.00
No. Material Satuan Harga ( Rp )
1 2 3 4
BAHAN NON LOKAL
A PIPA GALVANIZED IRON PIPE (GIP) ACESSORIES
1 Pipa Galvanized Steel Pipe {GPS) Ø 200 mm M¹ 528,853.27
2 Pipa Galvanized Steel Pipe {GPS) Ø 150 mm M¹ 522,031.59
3 Pipa Galvanized Steel Pipe {GPS) Ø 100 mm M¹ 240,636.76
4 Pipa Galvanized Steel Pipe {GPS) Ø 75 mm M¹ 166,024.20
5 Pipa Galvanized Steel Pipe {GPS) Ø 50 mm M¹ 179,002.98
6 Pipa Galvanized Steel Pipe {GPS) Ø 40 mm M¹ 102,000.00
7 Pipa Galvanized Steel Pipe {GPS) Ø 25 mm M¹ 76,000.00
8 Pipa Galvanized Steel Pipe {GPS) Ø 20 mm M¹ 56,000.00
9 Pipa Galvanized Steel Pipe {GPS) Ø 15 mm M¹ 48,500.00
10 Socket GIP. Ø 150 mm Buah 174,010.53
11 Socket GIP. Ø 100 mm Buah 80,212.25
12 Socket GIP. Ø 75 mm Buah 55,341.40
13 Socket GIP. Ø 50 mm Buah 59,667.66
14 Socket GIP. Ø 40 mm Buah 25,500.00
15 Socket GIP. Ø 25 mm Buah 22,500.00
16 Double Nipple GIP. Ø 150 mm Buah 124,600.00
17 Double Nipple GIP. Ø 100 mm Buah 63,152.25
18 Double Nipple GIP. Ø 75 mm Buah 39,666.38
19 Double Nipple GIP. Ø 50 mm Buah 25,990.00
20 Double Nipple GIP. Ø 40 mm Buah 21,300.00
21 Double Nipple GIP. Ø 25 mm Buah 14,030.00
22 Water Moor GIP. dia 150 mm Buah 417,000.00
23 Water Moor GIP. dia 100 mm Buah 193,000.00
24 Water Moor GIP. dia 75 mm Buah 109,000.00
25 Water Moor GIP. dia 50 mm Buah 49,500.00
26 Water Moor GIP. dia 40 mm Buah 39,000.00
27 Water Moor GIP. dia 25 mm Buah 29,000.00
28 Bend All Flange CI. Ø 150 mm - 90 Buah 675,000.00
29 Bend All Flange CI. Ø 150 mm - 45 Buah 675,000.00
30 Bend All Flange CI. Ø 100 mm - 90 Buah 477,000.00
31 Bend All Flange CI. Ø 100 mm - 45 Buah 477,000.00
32 Bend All Flange CI. Ø 75 mm - 90 Buah 405,000.00
33 Bend All Flange CI. Ø 75 mm - 45 Buah 405,000.00
34 Bend All Flange CI. Ø 50 mm - 90 Buah 339,000.00
35 Bend Ø 150 mm - 90˚ Socket Buah 456,200.00
36 Bend Ø 150 mm - 45˚ Socket Buah 410,000.00
37 Bend Ø 100 mm - 90˚ Socket Buah 119,000.00
38 Bend Ø 100 mm - 45˚ Socket Buah 135,000.00
39 Bend Ø 75 mm - 90˚ Socket Buah 77,000.00
40 Bend Ø 75 mm - 45˚ Socket Buah 67,000.00
41 Bend Ø 50 mm - 90˚ Socket Buah 35,000.00
42 Bend Ø 50 mm - 45˚ Socket Buah 33,000.00
43 Bend Ø 150 mm - 22.5˚ Socket Buah 409,000.00
44 Bend Ø 100 mm - 22.5˚ Socket Buah 132,000.00
45 Bend Ø 75 mm - 22.5˚ Socket Buah 67,000.00
44 Bend Ø 50 mm - 22.5˚ Socket Buah 33,000.00
45 Bend Steel (Las) Ø 150 mm - 90˚ Buah 487,788.00
46 Bend Steel (Las) Ø 150 mm - 45˚ Buah 487,788.00
47 Bend Steel (Las) Ø 150 mm - 22,50˚ Buah 487,788.00
48 Bend Steel (Las) Ø 150 mm - 11,25˚ Buah 487,788.00
49 Water Meter All Flange Ø 150 mm Buah 4,470,000.00
50 Water Meter All Flange Ø 100 mm Buah 3,270,000.00
51 Water Meter All Flange Ø 75 mm Buah 2,550,000.00
52 Water Meter All Flange Ø 50 mm Buah 2,154,000.00
53 Gilbout Joint Joint CI. Ø 150 mm Buah 179,000.00
54 Gilbout Joint Joint CI. Ø 100 mm Buah 107,000.00
55 Gilbout Joint Joint CI. Ø 75 mm Buah 79,000.00
56 Gilbout Joint Joint CI. Ø 50 mm Buah 59,000.00
57 Flange Flaxible Joint Ø 150 mm Buah 780,600.00
58 Flange Flaxible Joint Ø 100 mm Buah 674,000.00
59 Flange Flaxible Joint Ø 75 mm Buah 525,600.00
60 Water Moor Ø 150 mm Buah 417,000.00
61 Water Moore Ø 100 mm Buah 193,000.00
ANALISA PEKERJAAN
HARGA SATUAN PEKERJAAN PERSIAPAN
A.2.2.1.13. Pembongkaran 1 m3 beton bertulang
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.3334 61,000 81,337.40
Mandor L.04.01 OH 0.6660 70,000 46,620.00
JUMLAH TENAGA KERJA 127,957.40
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 127,957.40
E Overhead & Profit 15% 15% 19,193.61
F Harga Satuan Pekerjaan (D+E) - 147,151.00

HARGA SATUAN PEKERJAAN TANAH


A.2.3.1.1. Penggalian 1 m3 tanah biasa sedalam 1 m
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.7500 61,000 45,750.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 47,500.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 47,500.00
E Overhead & Profit 15% 15% 7,125.00
F Harga Satuan Pekerjaan (D+E) - 54,625.00

A.2.3.1.2. Penggalian 1 m3 tanah biasa sedalam 2 m


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.9000 61,000 54,900.00
Mandor L.04.01 OH 0.0450 70,000 3,150.00
JUMLAH TENAGA KERJA 58,050.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 58,050.00
E Overhead & Profit 15% 15% 8,707.50
F Harga Satuan Pekerjaan (D+E) - 66,757.00

A.2.3.1.3. Menggali 1 m3 tanah biasa sedalam 3 m


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 1.0500 61,000 64,050.00
Mandor L.04.01 OH 0.0670 70,000 4,690.00
JUMLAH TENAGA KERJA 68,740.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 68,740.00
E Overhead & Profit 15% 15% 10,311.00
F Harga Satuan Pekerjaan (D+E) - 79,051.00
A.2.3.1.4. Menggali 1 m3 tanah keras sedalam 1 m
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 1.0000 61,000 61,000.00
Mandor L.04.01 OH 0.0320 70,000 2,240.00
JUMLAH TENAGA KERJA 63,240.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 63,240.00
E Overhead & Profit 15% 15% 9,486.00
F Harga Satuan Pekerjaan (D+E) - 72,726.00

A.2.3.1.5. Menggali 1 m3 tanah cadas sedalam 1 m


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Mandor L.04.01 OH 0.0600 70,000 4,200.00
JUMLAH TENAGA KERJA 95,700.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 95,700.00
E Overhead & Profit 15% 15% 14,355.00
F Harga Satuan Pekerjaan (D+E) - 110,055.00

A.2.3.1.9. Pengurugan kembali 1 m3 galian tanah Tanah Biasa Sedalam 1 M


Pengurugan kembali 1 m3 galian dihitung dari 1/3 kali dari koefisien pekerjaan galian
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.2500 61,000 15,250.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 17,000.00
B BAHAN - -
JUMLAH HARGA BAHAN -
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 17,000.00
E Overhead & Profit 15% 15% 2,550.00
F Harga Satuan Pekerjaan (D+E) - 19,550.00

A.2.3.1.11. Pengurugan 1 m3 dengan pasir urug


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 0.3000 61,000 18,300.00
Mandor L.04.01 OH 0.0100 70,000 700.00
JUMLAH TENAGA KERJA 19,000.00
B BAHAN - -
Pasir urug M3 1.2000 373,014 447,616.33
JUMLAH HARGA BAHAN 447,616.33
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 466,616.33
E Overhead & Profit 15% 15% 69,992.45
F Harga Satuan Pekerjaan (D+E) - 536,608.00

A.2.3.1.14. Pengurugan 1 m3 sirtu padat


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA - -
Pekerja L.01.01 OH 0.2500 61,000 15,250.00
Mandor L.04.01 OH 0.0250 70,000 1,750.00
JUMLAH TENAGA KERJA 17,000.00
B BAHAN - -
Sirtu m3 1.2000 262,000 314,400.00
JUMLAH HARGA BAHAN 314,400.00
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 331,400.00
E Overhead & Profit 15% 15% 49,710.00
F Harga Satuan Pekerjaan (D+E) - 381,110.00
HARGA SATUAN PEKERJAAN PONDASI
A.3.2.1.1. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 3PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA - -
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 202.0000 2,258 456,214.25
Pasir Pasang m3 0.4850 401,014 194,491.60
JUMLAH HARGA BAHAN 1,131,922.18
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,286,797.18
E Overhead & Profit 15% 15% 193,019.58
F Harga Satuan Pekerjaan (D+E) - 1,479,816.00

A.3.2.1.2. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 4PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 163.0000 2,258 368,133.28
Pasir Pasang m3 0.5200 401,014 208,527.07
JUMLAH HARGA BAHAN 1,057,876.68
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,212,751.68
E Overhead & Profit 15% 15% 181,912.75
F Harga Satuan Pekerjaan (D+E) - 1,394,664.00

A.3.2.1.3. Pemasangan 1 m3 pondasi batu belah campuran 1SP : 5PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.5000 61,000 91,500.00
Tukang Batu L.02.03 OH 0.7500 70,000 52,500.00
Kepala Tukang L.03.01 OH 0.0750 75,000 5,625.00
Mandor L.04.01 OH 0.0750 70,000 5,250.00
JUMLAH TENAGA KERJA 154,875.00
B BAHAN - -
Batu belah m3 1.2000 401,014 481,216.33
Semen portland Kg 136.0000 2,258 307,154.15
Pasir Pasang m3 0.5440 401,014 218,151.40
JUMLAH HARGA BAHAN 1,006,521.88
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,161,396.88
E Overhead & Profit 15% 15% 174,209.53
F Harga Satuan Pekerjaan (D+E) - 1,335,606.00

A.3.2.1.9. Pemasangan 1 m3 batu kosong (anstamping)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.7800 61,000 47,580.00
Tukang Batu L.02.03 OH 0.3900 70,000 27,300.00
Kepala Tukang L.03.01 OH 0.0390 75,000 2,925.00
Mandor L.04.01 OH 0.0390 70,000 2,730.00
JUMLAH TENAGA KERJA 80,535.00
B BAHAN
Batu belah m3 1.2000 401,014 481,216.33
Pasir urug m3 0.4320 373,014 161,141.88
JUMLAH HARGA BAHAN 642,358.20
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 722,893.20
E Overhead & Profit 15% 15% 108,433.98
F Harga Satuan Pekerjaan (D+E) - 831,327.00
HARGA SATUAN PEKERJAAN BETON
A.4.1.1.1 Membuat 1 m3 beton mutu f’c = 7,4 MPa (K 100)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 247.0000 2,258 557,846.14
Pasir Beton kg 869.0000 286 248,914.87
Kerikil (Maks 30 mm) kg 999.0000 602 601,411.79
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,414,622.80
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,542,432.80
E Overhead & Profit 15% 15% 231,364.92
F Harga Satuan Pekerjaan (D+E) - 1,773,797.00

A.4.1.1.2 Membuat 1 m3 beton mutu f’= 9,8 MPa (K 125)


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 276.0000 2,258 623,342.24
Pasir Beton kg 828.0000 286 237,170.90
Kerikil (Maks 30 mm) kg 1012.0000 602 609,237.97
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,476,201.12
C PERALATAN - -
D Jumlah (A+B+C) - 1,604,011.12
E Overhead & Profit 15% 15% 240,601.67
F Harga Satuan Pekerjaan (D+E) - 1,844,612.00

A.4.1.1.4 Membuat 1 m3 lantai kerja beton mutu f’c = 7,4 MPa (K 100), slump (3-6) cm, w/c = 0,87
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.2000 61,000 73,200.00
Tukang Batu L.02.03 OH 0.2000 70,000 14,000.00
Kepala Tukang L.03.01 OH 0.0200 75,000 1,500.00
Mandor L.04.01 OH 0.0600 70,000 4,200.00
JUMLAH TENAGA KERJA 92,900.00
B BAHAN
Semen portland kg 230.0000 2,258 519,451.87
Pasir Beton kg 893.0000 286 255,789.39
Kerikil (Maks 30 mm) kg 1027.0000 602 618,268.18
Air Liter 200.0000 30 6,000.00
JUMLAH HARGA BAHAN 1,399,509.44
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,492,409.44
E Overhead & Profit 15% 15% 223,861.42
F Harga Satuan Pekerjaan (D+E) - 1,716,270.00
A.4.1.1.5. Membuat 1 m3 beton mutu f’ = 14,5 MPa (K 175), slump (12 ±2) cm, w/c = 0,66
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 326.0000 2,258 736,266.56
Pasir Beton kg 760.0000 286 217,693.10
Kerikil (Maks 30 mm) kg 1029.0000 602 619,472.20
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,579,881.87
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,707,691.87
E Overhead & Profit 15% 15% 256,153.78
F Harga Satuan Pekerjaan (D+E) - 1,963,845.00

A.4.1.1.6 Membuat 1 m3 beton mutu f’= 16,9 MPa (K 200), slump (120 ± 20) mm, w/c = 0,61
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 352.0000 2,258 794,987.21
Pasir Beton kg 731.0000 286 209,386.39
Kerikil (Maks 30 mm) kg 1031.0000 602 620,676.23
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,631,499.83
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,759,309.83
E Overhead & Profit 15% 15% 263,896.47
F Harga Satuan Pekerjaan (D+E) - 2,023,206.00

A.4.1.1.7. Membuat 1 m3 beton mutu f’ = 19,3 MPa (K 225), slump (120 ± 20) mm, w/c = 0,58
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 1.6500 61,000 100,650.00
Tukang Batu L.02.03 OH 0.2750 70,000 19,250.00
Kepala Tukang L.03.01 OH 0.0280 75,000 2,100.00
Mandor L.04.01 OH 0.0830 70,000 5,810.00
JUMLAH TENAGA KERJA 127,810.00
B BAHAN
Semen portland kg 371.0000 2,258 837,898.45
Pasir Beton kg 698.0000 286 199,933.93
Kerikil (Maks 30 mm) kg 1047.0000 602 630,308.45
Air Liter 215.0000 30 6,450.00
JUMLAH HARGA BAHAN 1,674,590.83
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 1,802,400.83
E Overhead & Profit 15% 15% 270,360.12
F Harga Satuan Pekerjaan (D+E) - 2,072,760.00

A.4.1.1.15 Pemasangan 1 m’ PVC Waterstop lebar 200 mm


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.0700 61,000 4,270.00
Tukang Pipa L.02.13 OH 0.0350 70,000 2,450.00
Kepala Tukang L.03.01 OH 0.0040 75,000 300.00
Mandor L.04.01 OH 0.0070 70,000 490.00
JUMLAH TENAGA KERJA 7,510.00
B BAHAN
Waterstop lebar 200 mm m 1.0500 51,750 54,337.50
JUMLAH HARGA BAHAN 54,337.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 61,847.50
E Overhead & Profit 15% 15% 9,277.13
F Harga Satuan Pekerjaan (D+E) - 71,124.00
A.4.1.1.17 Pembesian 10 kg dengan besi polos atau besi ulir
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.0700 61,000 4,270.00
Tukang Besi L.02.05 OH 0.0700 70,000 4,900.00
Kepala Tukang L.03.01 OH 0.0070 75,000 525.00
Mandor L.04.01 OH 0.0040 70,000 280.00
JUMLAH TENAGA KERJA 9,975.00
B BAHAN
Besi beton (polos/ulir) kg 10.5000 12,625 132,562.50
Kawat beton kg 0.1500 19,550 2,932.50
JUMLAH HARGA BAHAN 135,495.00
C PERALATAN - -
D Jumlah (A+B+C) - 145,470.00
E Overhead & Profit 15% 15% 21,820.50
F Harga Satuan Pekerjaan (D+E) - 167,290.00

A.4.1.1.20 (K3) Pemasangan 1 m2 bekisting untuk pondasi


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.5200 61,000 31,720.00
Tukang Kayu L.02.04 OH 0.2600 70,000 18,200.00
Kepala Tukang L.03.01 OH 0.0260 75,000 1,950.00
Mandor L.04.01 OH 0.0260 70,000 1,820.00
JUMLAH TENAGA KERJA 53,690.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 10 cm kg 0.3000 15,000 4,500.00
Minyak bekisting Liter 0.1000 20,125 2,012.50
JUMLAH HARGA BAHAN 133,032.50
C PERALATAN - -
D Jumlah (A+B+C) - 186,722.50
E Overhead & Profit 15% 15% 28,008.38
F Harga Satuan Pekerjaan (D+E) - 214,730.00
A.4.1.1.22 (K3) Pemasangan 1 m2 bekisting untuk kolom
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0150 4,428,000 66,420.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 2.0000 6,900 13,800.00
JUMLAH HARGA BAHAN 267,077.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 335,222.50
E Overhead & Profit 15% 15% 50,283.38
F Harga Satuan Pekerjaan (D+E) - 385,505.00

A.4.1.1.23 (K3) Pemasangan 1 m2 bekisting untuk balok


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0180 4,428,000 79,704.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 2.0000 6,900 13,800.00
JUMLAH HARGA BAHAN 280,361.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 348,506.50
E Overhead & Profit 15% 15% 52,275.98
F Harga Satuan Pekerjaan (D+E) - 400,782.00

A.4.1.1.24 (K3) Pemasangan 1 m2 bekisting untuk lantai


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0400 3,163,000 126,520.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0150 4,428,000 66,420.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 6.0000 6,900 41,400.00
JUMLAH HARGA BAHAN 294,677.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 362,822.50
E Overhead & Profit 15% 15% 54,423.38
F Harga Satuan Pekerjaan (D+E) - 417,245.00
A.4.1.1.25 (K3) Pemasangan 1 m2 bekisting untuk dinding
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)

A TENAGA
Pekerja L.01.01 OH 0.6600 61,000 40,260.00
Tukang Kayu L.02.04 OH 0.3300 70,000 23,100.00
Kepala Tukang L.03.01 OH 0.0330 75,000 2,475.00
Mandor L.04.01 OH 0.0330 70,000 2,310.00
JUMLAH TENAGA KERJA 68,145.00
B BAHAN
Kayu kelas III m3 0.0300 3,163,000 94,890.00
Paku 5 - 12 cm kg 0.4000 15,000 6,000.00
Minyak bekisting Liter 0.2000 20,125 4,025.00
Balok kayu kelas II m3 0.0200 4,428,000 88,560.00
Plywood 9 mm Lbr 0.3500 143,750 50,312.50
Dolken kayu Ø 8-10/400 cm Batang 3.0000 6,900 20,700.00
Penjaga jarak bekisting / spacer Buah 4.0000 500 2,000.00
JUMLAH HARGA BAHAN 266,487.50
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 334,632.50
E Overhead & Profit 15% 15% 50,194.88
F Harga Satuan Pekerjaan (D+E) - 384,827.00

HARGA SATUAN PEKERJAAN PASANGAN DINDING


A.4.4.1.1. Pemasangan 1m2 dinding Batako tebal 1 batu campuran 1 SP : 4 PP
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 61,000 18,300.00
Tukang Batu L.02.03 OH 0.1000 70,000 7,000.00
Kepala Tukang L.03.01 OH 0.0100 75,000 750.00
Mandor L.04.01 OH 0.0150 70,000 1,050.00
JUMLAH TENAGA KERJA 27,100.00
B BAHAN
Bata merah Bh 11.0000 5,000 55,000.00
Semen portland Kg 26.5500 2,258 59,962.81
Pasir Pasang m3 0.0430 401,014 17,243.59
JUMLAH HARGA BAHAN 132,206.40
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 159,306.40
E Overhead & Profit 15% 15% 23,895.96
F Harga Satuan Pekerjaan (D+E) - 183,202.00

A.4.4.1.1. Pemasangan 1m2 dinding Batako tebal 1 batu campuran 1 SP : 5 PP


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 61,000 18,300.00
Tukang Batu L.02.03 OH 0.1000 70,000 7,000.00
Kepala Tukang L.03.01 OH 0.0100 75,000 750.00
Mandor L.04.01 OH 0.0150 70,000 1,050.00
JUMLAH TENAGA KERJA 27,100.00
B BAHAN
Bata merah Bh 11.0000 5,000 55,000.00
Semen portland Kg 22.2000 2,258 50,138.40
Pasir Pasang m3 0.0430 401,014 17,243.59
JUMLAH HARGA BAHAN 122,381.98
C PERALATAN - -
JUMLAH HARGA ALAT -
D Jumlah (A+B+C) - 149,481.98
E Overhead & Profit 15% 15% 22,422.30
F Harga Satuan Pekerjaan (D+E) - 171,904.00

HARGA SATUAN PEKERJAAN PLESTERAN


A.4.4.2.1. Pemasangan 1 m2 plesteran 1SP : 1PP tebal 15 mm.
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.3000 61,000 18,300.00
Tukang Batu L.02.03 OH 0.1500 70,000 10,500.00
Kepala Tukang L.03.01 OH 0.0150 75,000 1,125.00
Mandor L.04.01 OH 0.0150 70,000 1,050.00
JUMLAH TENAGA KERJA 30,975.00
B BAHAN
Semen portland Kg 15.5040 2,258 35,015.57
Pasir Pasang m3 0.0160 401,014 6,416.22
JUMLAH HARGA BAHAN 41,431.79
Bongkaran 1 M3 Pasangan Batu (Manual)
No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 1.8000 61,000 109,800.00
Mandor L.04.01 OH 0.1800 70,000 12,600.00
JUMLAH TENAGA KERJA 122,400.00
B BAHAN - -
JUMLAH HARGA BAHAN
C PERALATAN - -
Palu/ Godam (Baja Keras) E. 30 Bh 0.0060 200,000 1,200.00
Pahat Beton (Baja Keras) E. 29 Bh 0.0090 50,000 450.00
Linggis (Baja Keras) E.29 Bh 0.0200 110,000 2,200.00
JUMLAH HARGA ALAT 3,850.00
D Jumlah (A+B+C) - 126,250.00
E Overhead & Profit 15% 15% 18,937.50
F Harga Satuan Pekerjaan (D+E) - 145,187.00

1 M³ Membongkar Cor Beton Tmbuk 1pc : 3ps : 5kr


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1650 61,000 10,065.00
Mandor L.04.01 OH 0.0800 70,000 5,600.00
JUMLAH TENAGA KERJA 15,665.00
B BAHAN - -
JUMLAH HARGA BAHAN
C PERALATAN - -
Linggis (Baja Keras) E.29 Bh 1.0000 100,000 100,000.00
JUMLAH HARGA ALAT 100,000.00
D Jumlah (A+B+C) - 115,665.00
E Overhead & Profit 15% 15% 17,349.75
F Harga Satuan Pekerjaan (D+E) - 133,014.00

1 M2 Membongkar Paving Block Existing


No Uraian Kode Satuan Koefisien Harga Satuan (Rp.) Jumlah Harga (Rp.)
A TENAGA
Pekerja L.01.01 OH 0.1600 61,000 9,760.00
Tukang Batu L.02.04 OH 0.0500 70,000 3,500.00
Kepala Tukang Batu L.03.01 OH 0.0050 75,000 375.00
Mandor L.04.01 OH 0.0075 70,000 525.00
JUMLAH TENAGA KERJA 14,160.00
B BAHAN - -
JUMLAH HARGA BAHAN
C PERALATAN -
JUMLAH HARGA ALAT
D Jumlah (A+B+C) - 14,160.00
E Overhead & Profit 15% 15% 2,124.00
F Harga Satuan Pekerjaan (D+E) - 16,284.00
PIPA 200 MM

ANALISA MATERIAL ON SITE

A. BIAYA ANGKUT PIPA DIA. 8" (200 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 30.00 km = 60.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 60.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 5.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 5 mnt + 5 mnt ) x 4 orng x 2 / 60 mnt = 1.3 jam
- waktu per trip = 60.00 km / ((30 + 60 ) / 2 ) km/jam + 1.3 jam = 2.7 jam
- Jumlah trip per hari = 7 jam / 2.7 jam = 2.63 truk
- Biaya Transport Truck per trip = = Rp. 500,000.00 /trip
- Berat pipa per batang = 26.39 kg x 6.00 m = 158.32 kg/m
- Kapasitas angkut per truk / trip = = 35.00 Batang
- Jumlah pipa yang dibutuhkan = 4,021.00 m / 6.00 m = 670.17 Batang
- Produksi per hari = 2.63 truk x 35.00 btng = 91.88 Batang
- Ongkos angkut = 19.1 trip x Rp 500,000.00 / 91.88 btng = Rp. 39,076.77 /Batang
- Ongkos naik turun (4 Orang) = 4 x 17,500.00 orng/hari/ 91.88 btng = Rp. 1,142.86 /Batang
- Total Harga per Batang = 39,076.77 /btng + 1,142.86 /btng = Rp. 40,219.63 /Batang
- Total Harga per m = 40,219.63 /btng / 6.00 /m per btng = Rp. 6,703.27 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.20 km = 0.40 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 0.6 jam (PP) =
- lama berjalan PP = = 0.50 jam
- lama istirahat PP = = 0.10 jam
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Kapasitas angkut per batang = 7 / (0.5 + 0.1) x 4 orng = 46.7 Batang
- Ongkos angkut = ( 2 org x 18.000 orng/hari x 1.6 jam ) / 9 btng = Rp. 900.00 /Batang
- Total Harga per m = 900.00 /btng / 6.00 /m per btng = Rp. 150.00 / m (b)

C. HARGA SATUAN PIPA dia 8" DI LOKASI PEKERJAAN


Harga pipa dia 8" (200 mm) Rp 528,853.27

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Lokasi Pipa dia 8" (200 mm) m1 1 522,000.00 Rp 522,000.00

2. Biaya Angkut ( Trasportasi truk ) a m1 1 6,703.27 Rp 6,703.27

3. ongkos Angkut trip m1 1 150.00 Rp 150.00


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 528,853.27


PIPA 150 MM
ANALISA MATERIAL ON SITE

A. BIAYA ANGKUT PIPA DIA. 6" (150 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 30.00 km = 60.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 45.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 4.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 6 mnt + 4 mnt ) x 4 orng x 2 / 60 mnt = 1.2 jam
- waktu per trip = 60.00 km / 37.50 km/jam + 1.2 jam = 2.8 jam
- Jumlah trip per hari = 7 jam / 2.8 jam = 2.50 truk
- Biaya Transport Truck per hari = = Rp. 1,000,000.00 /hari
- Berat pipa per batang = 19.20 kg x 6.00 m = 115.20 kg/m
- Kapasitas angkut per truk / trip = = 26.04 Batang
- Jumlah pipa yang dibutuhkan = 12,122.00 m / 6.00 m = 2,020.33 Batang
- Produksi per hari = 2.50 truk x 26.04 btng = 65.10 Batang
- Ongkos angkut = 77.6 trip x Rp 1,000,000.00 / 65.10 btng = Rp. 425,586.10 /Batang
- Ongkos naik turun (4 Orang) = 4 x 34,000.00 oh / 65.10 btng = Rp. 3,133.44 /Batang
- Total Harga per Batang = 425,586.10 /btng + 3,133.44 /btng = Rp. 428,719.54 /Batang
- Total Harga per m = 428,719.54 /btng / 6.00 /m per btng = Rp. 71,453.26 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.70 km = 1.40 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 1,3 jam (PP) =
- lama berjalan PP = = 1.15 jam
- lama istirahat PP = = 0.15 jam
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Kapasitas angkut per hari = 7 / (1.15 + 0.15 ) x 4.0 orng = 21.5 Btng/hr
- Ongkos angkut = (1.15 jam +0.15 jam)/ 4 * 34000) * 1 Km = Rp. 15,470.00 /Batang
- Total Harga per m = 15,470.00 /btng / 6.00 /m per btng = Rp. 2,578.33 / m (b)

C. HARGA SATUAN PIPA dia 6" DI LOKASI PEKERJAAN


Harga pipa dia 6" (150 mm) Rp 522,031.59

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Harga pipa dia 6" (150 mm) m1 1 448,000.00 Rp 448,000.00

2. Biaya Angkut ( Trasportasi truk ) a m1 1 71,453.26 Rp 71,453.26

3. ongkos Angkut trip m1 1 2,578.33 Rp 2,578.33


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 522,031.59


PIPA 100 MM
ANALISA MATERIAL ON SITE

A. BIAYA ANGKUT PIPA DIA. 4" (100 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 30.00 km = 60.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 45.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 4.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 5 mnt + 4 mnt ) x 4 orng x 2 / 60 mnt = 1.2 jam
- waktu per trip = 60.00 km / 37.50 km/jam + 1.2 jam = 2.8 jam
- Jumlah trip per hari = 7 jam / 2.8 jam = 2.50 truk
- Biaya Transport Truck per hari = = Rp. 1,000,000.00 /hari
- Berat pipa per batang = 12.20 kg x 6.00 m = 73.20 kg/m
- Kapasitas angkut per truk / trip = = 35.00 Batang
- Jumlah pipa yang dibutuhkan = 10,090.00 m / 6.00 m = 1,681.67 Batang
- Produksi per hari = 2.50 truk x 35.00 btng = 87.50 Batang
- Ongkos angkut = 48.0 trip x Rp 1,000,000.00 / 87.50 btng = Rp. 196,112.73 /Batang
- Ongkos naik turun (4 Orang) = 4 x 61,000.00 oh / 87.50 btng = Rp. 4,182.86 /Batang
- Total Harga per Batang = 196,112.73 /btng + 4,182.86 /btng = Rp. 200,295.59 /Batang
- Total Harga per m = 200,295.59 /btng / 6.00 /m per btng = Rp. 33,382.60 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.20 km = 0.40 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 0.25 jam (PP) =
- lama berjalan PP = = 0.20 jam
- lama istirahat PP = = 0.05 jam
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Kapasitas angkut per hari = 7 / (0.20 + 0.05 ) x 4 orng = 112.0 Btng/hr
- Ongkos angkut = (0.75 jam +0.15 jam)/ 4 * 61000) * 1.4 Km = Rp. 1,525.00 /Batang
- Total Harga per m = 1,525.00 /btng / 6.00 /m per btng = Rp. 254.17 / m (b)

C. HARGA SATUAN PIPA dia 4" DI LOKASI PEKERJAAN


Harga pipa dia 4" (100 mm) Rp 240,636.76

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Harga pipa dia 4" (100 mm) m1 1 207,000.00 Rp 207,000.00

2. Biaya Angkut ( Trasportasi truk ) a m1 1 33,382.60 Rp 33,382.60

3. ongkos Angkut trip m1 1 254.17 Rp 254.17


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 240,636.76


PIPA 75 MM
ANALISA MATERIAL ON SITE

A. BIAYA ANGKUT PIPA DIA. 3" (75 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 30.00 km = 60.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 45.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 4.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 4 mnt + 5 mnt ) x 4 orng x 2 / 60 mnt = 1.2 jam
- waktu per trip = 60.00 km / (25+35)/2 km/jam + 1.2 jam = 2.8 jam
- Jumlah trip per hari = 7 jam / 2.8 jam = 2.50 truk
- Biaya Transport Truck per hari = = Rp. 750,000.00 /hari
- Berat pipa per batang = 8.37 kg x 6.00 m = 50.22 kg/m
- Kapasitas angkut per truk / trip = = 35.00 Batang
- Jumlah pipa yang dibutuhkan = 30.00 m / 6.00 m = 5.00 Batang
- Produksi per hari = 2.50 truk x 35.00 btng = 87.50 Batang
- Ongkos angkut = 0.1 trip x Rp 750,000.0 / 87.50 btng = Rp. 437.32 /Batang
- Ongkos naik turun (4 Orang) = 4 x 61,000.00 orng/hari/ 87.50 btng = Rp. 4,182.86 /Batang
- Total Harga per Batang = 437.32 /btng + 4,182.86 /btng = Rp. 4,620.17 /Batang
- Total Harga per m = 4,620.17 /btng / 6.00 /m per btng = Rp. 770.03 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.20 km = 0.40 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 0.25 jam (PP) =
- lama berjalan PP = = 0.20 jam
- lama istirahat PP = = 0.05 jam
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Kapasitas angkut per hari = 7 / (0.2 + 0.05 ) x 4 orng = 112.0 Btng/hr
- Ongkos angkut = ( 2 org x 61500 orng/hari x 1.3 jam ) / 9 btng = Rp. 1,525.00 /Batang
- Total Harga per m = 1,525.00 /btng / 6.00 /m per btng = Rp. 254.17 / m (b)

C. HARGA SATUAN PIPA dia 3" DI LOKASI PEKERJAAN


Harga pipa dia 3" (75 mm) Rp 166,024.20

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Harga pipa dia 3" (75 mm) m1 1 165,000.00 Rp 165,000.00

2. Biaya Angkut ( Trasportasi truk ) a m1 1 770.03 Rp 770.03

3. ongkos Angkut trip m1 1 254.17 Rp 254.17


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 166,024.20


PIPA 50 MM
ANALISA MATERIAL ON SITE

A. BIAYA ANGKUT PIPA DIA. 2" (50 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 30.00 km = 60.00 km.
- Kecepatan rata-rata dengan muatan = = 35.00 km / jam
- Kecepatan rata-rata tanpa muatan = = 40.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 5.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 4.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 5 mnt + 4 mnt ) x 4 orng x 2 / 60 mnt = 1.2 jam
- waktu per trip = 60.00 km / ((35+40)/2) km/jam + 1.2 jam = 2.8 jam
- Jumlah trip per hari = 7 jam / 2.8 jam = 2.50 truk
- Biaya Transport Truck per hari = = Rp. 750,000.00 /hari
- Berat pipa per batang = 5.10 kg x 6.00 m = 30.60 kg/m
- Kapasitas angkut per truk / trip = = 30.00 Batang
- Jumlah pipa yang dibutuhkan = 14,078.00 m / 6.00 m = 2,346.33 Batang
- Produksi per hari = 2.50 truk x 30.00 btng = 75.00 Batang
- Ongkos angkut = 78.2 trip x Rp 750,000.00 / 75.00 btng = Rp. 279,325.40 /Batang
- Ongkos naik turun (4 Orang) = 4 x 61,000.00 orng/hari/ 75.00 btng = Rp. 4,880.00 /Batang
- Total Harga per Batang = 279,325.40 /btng + 4,880.00 /btng = Rp. 284,205.40 /Batang
- Total Harga per m = 284,205.40 /btng / 6.00 /m per btng = Rp. 47,367.57 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.25 km = 0.50 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 0.25 jam (PP) =
- lama berjalan PP = = 0.20 jam
- lama istirahat PP = = 0.05 jam
- Jumlah Pekerja yang dibutuhkan = 2.00 orang
- Kapasitas angkut per batang = 7 / 0.25 x 3 Tim = 56.0 Batang
- Ongkos angkut = 2.00 x 61,000.00 / 56.00 = Rp. 3,812.50 /Batang
- Total Harga per m = 3,812.50 /btng / 6.00 /m per btng = Rp. 635.42 / m (b)

C. HARGA SATUAN PIPA dia 2" DI LOKASI PEKERJAAN


Harga pipa dia 2" (50 mm) Rp 179,002.98

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Lokasi Pipa dia 2.5" di pelabuhan Rote m1 1 131,000.00 Rp 131,000.00

2. Biaya Angkut ( Trasportasi truk ) a m1 1 47,367.57 Rp 47,367.57

3. ongkos Angkut trip m1 1 635.42 Rp 635.42


(dengan Tenaga Manusia) b

Total harga onsite / m1 Rp 179,002.98


ANALISA HARGA PIPA DILOKASI SEMENTARA

PEKERJAAN :
LOKASI :
TAHUN :

Standar : SNI.0039 - 87 / BS.1387 - 85, MEDIUM CLASS

Pengiriman Port To Door Pengangkutan dari Pelabuhan Harga Pipa di Lokasi


Harga Pabrik di Surabaya Asuransi 2 % Keuntungan 10 %
No. Jenis dan Ukuran ke Pelabuhan Sumba Kupang ke Lokasi Sementara Sementara
Harga/Batng Harga/Meter Harga/Batng Harga/Meter Harga/Batng Harga/Meter Harga/Batng Harga/Meter Harga/Batng Harga/Meter Harga/Batng Harga/Meter
Harga Pabrik B
1 Pipa GIP Ø 50 mm 716,280.00 119,380.00 15,300.00 2,550.00 10,113.17 1,685.53 1,432.56 238.76 71,628.00 11,938.00 814,753.73 135,792.29
2 Pipa GIP Ø 75 mm 1,189,122.00 198,187.00 25,410.00 4,235.00 16,965.52 2,827.59 2,378.24 396.37 118,912.20 19,818.70 1,352,787.97 225,464.66
3 Pipa GIP Ø 100 mm 1,735,938.00 289,323.00 57,600.00 9,600.00 25,069.89 4,178.32 3,471.88 578.65 173,593.80 28,932.30 1,995,673.57 332,612.26
4 Pipa GIP Ø 200 mm 2,832,397.00 472,066.17 58,800.00 9,800.00 40,922.66 6,820.44 5,664.79 944.13 283,239.70 47,206.62 3,221,024.15 536,837.36
ANALISA BIAYA ANGKUTAN
PEKERJAAN : 0
LOKASI : 0
TAHUN : 0 `

Jarak Jumlah Jumlah


Kecepatan Kecepatan Waktu Lamanya Kapasitas Jumlah Ongkos
Angkut dr Waktu Waktu Muat Pekerja yg Berat Berat Pipa Pipa Ongkos Ongkos Ongkos
Panjang Rata-rata Rata-rata Bongkar dr Waktu Waktu per Jumlah Trip Sewa Truck per Kapasitas Angkut per Produksi Upah Pekerja Bongkar
Jenis dan Pelabuhan Kerja ke Truck Dibutuhkan Pipa per per yang Angkut per Angkut per Angkut per
No Sat. Pipa Muat per Tanpa Muat Truck per Bongkar Trip per Hari Trip Truck Truck / per Hari Pekerja Bongkar Muat per
Diameter pipa ke Lokasi Efektif per Batang (Berat Pipa Meter Batang akan Batang Batang Meter
Jam per Jam Batang Muat Trip Muat Batang
(PP) per Btg /25 ) diangkut
( M' ) (Km) (Km) (Km) ( Jam ) ( Menit ) ( Menit ) ( Org ) ( Jam ) ( Jam ) ( Truck ) ( Rp ) ( Kg ) ( Kg ) ( Kg ) ( Btg ) ( Btg ) ( Btg ) ( RP. ) ( RP. ) ( Org ) (Rp) (Rp) (Rp)
12 = 13 = 25 =
17 = 19 = 20 = 21 = 22 = 26 =
1 2 3 4 5 6 7 8 9 10 11 = (17 / 25 ) (9+10)x(11x (5/(6+7)/2 14 = (8/13) 15 16 18 23 24 = 11 (23x24)/ 27 = (26/6)
(6x16) (18/17) (4/6) (14x19) (14x15)/21 (22+25)
2)/60 )+12 21

1 Pipa GIP Ø 50 mm M' 14,078.00 15.00 30.00 45.00 7.00 6.00 4.00 1.21 0.40 0.50 13.93 1,000,000.00 5.03 30.18 3,000.00 99.40 2,346.33 1,385.00 10,060.00 61,000.00 1.21 53.17 10,113.17 1,685.53
2 Pipa GIP Ø 75 mm M' #NAME? 15.00 30.00 45.00 7.00 6.00 4.00 2.01 0.67 0.77 9.10 1,000,000.00 8.37 50.22 3,000.00 59.74 #NAME? 543.35 16,740.00 61,000.00 2.01 225.52 16,965.52 2,827.59
3 Pipa GIP Ø 100 mm M' #NAME? 15.00 30.00 45.00 7.00 6.00 4.00 2.93 0.98 1.08 6.51 1,000,000.00 12.20 73.20 3,000.00 40.98 #NAME? 266.62 24,400.00 61,000.00 2.93 669.89 25,069.89 4,178.32
4 Pipa GIP Ø 200 mm M' 4,021.00 15.00 30.00 45.00 7.00 6.00 4.00 4.61 1.54 1.64 4.28 1,000,000.00 19.20 115.20 3,000.00 26.04 670.17 111.43 38,400.00 61,000.00 4.61 2,522.66 40,922.66 6,820.44
ANALISA MATERIAL ON SITE

PIPA HDPE DIA. 250 MM

A. BIAYA ANGKUT PIPA DIA. 10" (250 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 15.00 km = 30.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 60.00 km / jam
- Waktu kerja effektif = = 8.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 6.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 6 mnt + 5 mnt ) x 4 orng x 2 / 60 mnt = 1.5 jam
- waktu per trip = 30.00 km / ((30 + 60 ) / 2 ) km/jam + 1.5 jam = 2.1 jam
- Jumlah trip per hari = 8 jam / 2.1 jam = 3.75 truk
- Biaya Transport Truck per trip = = Rp. 500,000.00 /trip
- Berat pipa per batang = 11.14 kg x 6.00 m = 66.84 kg/m
- Kapasitas angkut per truk / trip = = 25.00 Batang
- Jumlah pipa yang dibutuhkan = 3,988.00 m / 6.00 m = 664.67 Batang
- Produksi per hari = 3.75 truk x 25.00 btng = 93.75 Batang
- Ongkos angkut = 26.6 trip x Rp 500,000.00 / 93.75 btng = Rp. 66,466.67 /Batang
- Ongkos naik turun (4 Orang) = 4 x 15,000.00 orng/hari / 93.75 btng = Rp. 960.00 /Batang
- Total Harga per Batang = 66,466.67 /btng + 960.00 /btng = Rp. 67,426.67 /Batang
- Total Harga per m = 67,426.67 /btng / 6.00 /m per btng = Rp. 11,237.78 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 1.60 km = 3.20 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 30 menit (PP) =
- lama berjalan PP = = 0.40 jam
- lama istirahat PP = = 0.10 jam
- Jumlah Pekerja yang dibutuhkan = 2.00 orang
- Kapasitas angkut per batang = 7 / (1.45 + 0.15 ) x 4 orng = 9.0 Batang
- Ongkos angkut = ( 4 org x 18.000 'orng/hari x 1.6 jam ) / 9 btng = Rp. 1,666.67 /Batang
- Total Harga per m = 1,666.67 /btng / 6.00 /m per btng = Rp. 277.78 / m (b)

C. HARGA SATUAN PIPA dia 10" DI LOKASI PEKERJAAN


Harga pipa dia 10" (250 mm) Rp 805,877.09

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Lokasi Pipa HDPE dia 250 mm di pelabuhan Waingapu m1 1 794,361.53 Rp 794,361.53

2. Biaya Angkut ( Trasportasi truk ) a m1 1 11,237.78 Rp 11,237.78

3. ongkos Angkut trip m1 1 277.78 Rp 277.78


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 805,877.09


PIPA HDPE DIA. 110 MM

A. BIAYA ANGKUT PIPA DIA. 4" (110 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 7.50 km = 15.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan = 50.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 6.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 6 mnt + 5 mnt ) x 4 orng x 2 / 60 mnt = 1.5 jam
- waktu per trip = 15.00 km / ((30 + 60 ) / 2 ) km/jam + 1.5 jam = 1.8 jam
- Jumlah trip per hari = 7 jam / 1.8 jam = 3.80 truk
- Biaya Transport Truck per trip = = Rp. 750,000.00 /trip
- Berat pipa per batang = 2.20 kg x 6.00 m = 13.20 kg/batang
- Kapasitas angkut per truk / trip = = 35.00 batang
- Jumlah pipa yang dibutuhkan = 1,000.00 m / 6.00 m = 166.67 batang
- Produksi per hari = 3.80 truk x 35.00 batang = 133.03 batang
- Ongkos angkut = 4.8 trip x Rp 750,000.00 / 133.03 batang = Rp. 14,577.26 /batang
- Ongkos naik turun (4 Orang) = 4 x 15,000.00 orng/hari / 133.03 batang = Rp. 676.53 /batang
- Total Harga per Batang = 14,577.26 /btg + 676.53 /batang = Rp. 15,253.79 /batang
- Total Harga per m = 15,253.79 /btg / 6.00 /m per batang = Rp. 2,542.30 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.03 km = 0.05 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 20 menit (PP) =
- lama berjalan PP = = 0.20 jam
- lama istirahat PP = = 0.10 jam
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Kapasitas angkut per batang = 7 / 0.30 x 4 orang = 93.3 batang
- Ongkos angkut = 4.00 x 15,000.00 / 93.33 = Rp. 56.25 /Batang
- Total Harga per m = 56.25 /btg / 6.00 /m per batang = Rp. 9.38 / m (b)

C. HARGA SATUAN PIPA dia 4" DI LOKASI PEKERJAAN


Harga pipa dia 4" (110 mm) Rp 166,669.97

NO URAIAN SATUAN VOLUME HARGA SATUAN JUMLAH HARGA

1. Harga Pipa HDPE Dia. 110mm di basecamp m1 1 164,118.30 Rp 164,118.30

2. Biaya Angkut ( Trasportasi truk ) a m1 1 2,542.30 Rp 2,542.30

3. ongkos Angkut trip m1 1 9.38 Rp 9.38


(dengan Tenaga Manusia) b

Total harga onsite m1 Rp 166,669.97

PIPA HDPE DIA. 63 MM

A. BIAYA ANGKUT PIPA DIA. 2" (63 mm)


Analisa Angkutan :
- Jarak angkut PP = 2 x L = 2 x 10.00 km = 20.00 km.
- Kecepatan rata-rata dengan muatan = = 30.00 km / jam
- Kecepatan rata-rata tanpa muatan 45.00 km / jam
- Waktu kerja effektif = = 7.00 jam
- Waktu Yang Dibutuhkan Untuk Menaikkan Pipa Kedalam truk/Batang = 6.00 menit
- Waktu Yang Dibutuhkan Untuk Menurunkan & Mengatur Pipa dari Truk/Batang = 5.00 menit
- Jumlah Pekerja yang dibutuhkan = 4.00 orang
- Lamanya waktu Muat / Bongkar = ( 6 mnt + 5 mnt ) x 4 orng x 2 / 60 mnt = 1.5 jam
- waktu per trip = 20.00 km / ((30 + 60 ) / 2 ) km/jam + 1.5 jam = 2.0 jam
- Jumlah trip per hari = 7 jam / 2.0 jam = 3.50 truk
- Biaya Transport Truck per trip = = Rp. 1,000,000.00 /trip
- Berat pipa per batang = 0.73 kg x 100.00 m = 73.00 kg/roll
- Kapasitas angkut per truk / trip = = 12.00 roll
- Jumlah pipa yang dibutuhkan = 1,000.00 m / 100.00 m = 10.00 roll
- Produksi per hari = 3.50 truk x 12.00 roll = 42.00 roll
- Ongkos angkut = 0.8 trip x Rp 1,000,000.00 / 42.00 roll = Rp. 9,920.63 /roll
- Ongkos naik turun (4 Orang) = 4 x 61,000.00 orng/hari / 42.00 roll = Rp. 8,714.29 /roll
- Total Harga per Batang = 9,920.63 /roll + 8,714.29 /roll = Rp. 18,634.92 /roll
- Total Harga per m = 18,634.92 /roll / 100.00 /m per roll = Rp. 186.35 /m (a)

B. Pemindahan Pipa ke lokasi Site (Dengan Tenaga Manusia)


- Jarak angkut PP = 2 x L = 2 pp x 0.60 km = 1.20 km.
- Jam kerja effektif = = 7.00 jam
- Waktu yang ditempuh asumsi 20 menit (PP) =
- lama berjalan PP = = 0.20 jam
ANALISA HARGA PIPA DILOKASI SEMENTARA
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

STANDARD SNI 06 - 4829 - 2005 / IS0 4427.96, S 8 - SDR - 17 (PN 10)

Price List 2018 Pengiriman Harga Pipa


No. Jenis dan Ukuran dari produsen Dor To Door dr Pabrik Asuransi 0,03 % Keuntungan 10 % di Lokasi
pipa ke Lokasi di NTT
(Rp./M') (Rp./M') (Rp./M') (Rp./M') (Rp./M')

1 Pipa PE. Ǿ 63 mm (2") 45,350.00 14,000.00 136.05 4,535.00 64,021.05


3 Pipa PE. Ǿ 110 mm (4") 136,100.00 14,000.00 408.30 13,610.00 164,118.30
6 Pipa HDPE. Ǿ 250 mm (10") 717,000.00 3,510.53 2,151.00 71,700.00 794,361.53
ANALISA RENCANA ANGGARAN BIAYA ANGKUTAN
#REF! #REF!
#REF! #REF!
#REF! #REF!
#REF! #REF!

Volume Panjang Pipa Panjang Total Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Biaya Kirim Total Biaya kirim
Container/Truck (Roll / Btg) / Container/Truck dr Jkt ke Sby dr Jkt ke Sby dr Pelbh Sby dr Pelbh Sby dr Labuan Bajo dr Labuan Bajo ke loksai
No. Diameter
(Roll / Btg) (M') (M') (Rp./Truck) (Rp./M') ke Labuan Bajo ke Labuan Bajo ke Lokasi ke Lokasi Sementara
(Rp./ Container) (Rp./ M') (Rp./ Truck') (Rp./ M') (Rp.M')

1 2 3 4 5 = (4 x 3) 6 7 = (6/5) 8 9 = (8/5) 10 11 = (10/5) 12 = (7+9+11)

1 Pipa PE. Ǿ 63 mm (2") 10.00 Roll 100.00 1,000.00 3,500,000.00 3,500.00 9,000,000.00 9,000.00 1,500,000.00 1,500.00 14,000.00
2 Pipa PE. Ǿ 110 mm (4") 166.67 Btg 6.00 1,000.00 3,500,000.00 3,500.00 9,000,000.00 9,000.00 1,500,000.00 1,500.00 14,000.00
3 Pipa HDPE. Ǿ 250 mm (10") 664.67 Btg 6.00 3,988.00 3,500,000.00 877.63 9,000,000.00 2,256.77 1,500,000.00 376.13 3,510.53
ANALISA MATERIAL ON SITE
1 HARGA SEMEN PER KG DI LOKASI PEKERJAAN

A 1 Kg Harga Semen dan Biaya Angkut sd lokasi yang dapat di akses kendaraan
- Jarak angkut PP = 60.00 Km K 245
- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 246
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 247
- Kecepatan truck rata-rata per jam = 35.00 Km K 248
- Kapasitas angkut truk = 3,000.00 Kg K 249
- Waktu per trip + fixed time = 2.71 Jam K 250
- Jumlah jam efektif per hari = 7.00 Jam K 251
- Jumlah trip per Hari = 2.58 Trip K 252
- Berat per zak semen = 50.00 Kg K 253
- Kapasitas angkut per trip per truck = 60.00 Zak K 254
- Sewa truck per trip = 1,000,000.00 Rp. K 255
- Produksi per hari = 154.74 Zak K 256
- Ongkos angkut ke lokasi per zak = 6,462.59 Rp. K 257
- Harga upah pekerja = 61,000.00 Rp. K 258
- Jumlah pekerja bongkar muatan = 4.00 Orang K 259
- Biaya bongkar muat per zak = 1,576.87 Rp. K 260
- Harga Semen per zak = 82,300.00 Rp. K 261
- Ongkos Angkut ke Lokasi per zak = 6,462.59 Rp. K 262
- Ongkos Bongkar Muat per zak = 1,576.87 Rp. K 263
- Jumlah Harga Semen per zak di lokasi ( q + r + s ) = 90,339.46 Rp. K 264

Jumlah Harga semen per kg = 2,258.49 Rp.

ANALISA MATERIAL ON SITE


2 HARGA BATU KALI PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K7


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K8
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K9
- Kecepatan truck rata-rata per jam = 35.00 Km K 10
- Kapasitas angkut per truk per trip = 3.00 M3 K 11
- Waktu per trip + fixed time = 1.86 Jam K 12
- Jumlah jam efektif per hari = 7.00 Jam K 13
- Jumlah trip per Hari = 3.77 Trip K 14
- Sewa truck per trip = 1,000,000.00 Rp. K 15
- Produksi per hari = 11.31 M3 K 16
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 17
- Harga upah pekerja = 61,000.00 Rp. K 18
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 19
- Biaya bongkar muat per M3 = 21,578.23 Rp. K 20

Harga Batu Kali per M3 = 291,000.00 Rp. K 21


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp. K 22
Ongkos Bongkar Muat per M3 = 21,578.23 Rp. K 23

Jumlah Harga per M3 di lokasi (p + q + r) = 401,013.61 Rp. K 24


ANALISA MATERIAL ON SITE
3 HARGA BATU KARANG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 61,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 21,578.23 Rp.

Harga Batu Karang per M3 = 291,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 21,578.23 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 401,013.61 Rp.

ANALISA MATERIAL ON SITE


4 HARGA KORAL BETON PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K 30


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 31
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 32
- Kecepatan truck rata-rata per jam = 35.00 Km K 33
- Kapasitas angkut per truk per trip = 3.00 M3 K 34
- Waktu per trip + fixed time = 1.86 Jam K 35
- Jumlah jam efektif per hari = 7.00 Jam K 36
- Jumlah trip per Hari = 3.77 Trip K 37
- Sewa truck per trip = 1,000,000.00 Rp. K 38
- Produksi per hari = 11.31 M3 K 39
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 40
- Harga upah pekerja = 61,000.00 Rp. K 41
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 42
- Biaya bongkar muat per M3 = 21,578.23 Rp. K 43

Harga Koral Beton per M3 = 231,000.00 Rp. K 44


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp. K 45
Ongkos Bongkar Muat per M3 = 21,578.23 Rp. K 46

Jumlah Harga per M3 di lokasi (p + q + r) = 341,013.61 Rp. K 47


ANALISA MATERIAL ON SITE
5 HARGA PASIR URUG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K 174


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 175
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 176
- Kecepatan truck rata-rata per jam = 35.00 Km K 177
- Kapasitas angkut per truk per trip = 3.00 M3 K 178
- Waktu per trip + fixed time = 1.86 Jam K 179
- Jumlah jam efektif per hari = 7.00 Jam K 180
- Jumlah trip per Hari = 3.77 Trip K 181
- Sewa truck per trip = 1,000,000.00 Rp. K 182
- Produksi per hari = 11.31 M3 K 183
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 184
- Harga upah pekerja = 61,000.00 Rp. K 185
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 186
- Biaya bongkar muat per M3 = 21,578.23 Rp. K 187

Harga Pasir Urug per M3 = 263,000.00 Rp. K 188


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp. K 189
Ongkos Bongkar Muat per M3 = 21,578.23 Rp. K 190

Jumlah Harga per M3 di lokasi (p + q + r) = 373,013.61 Rp. K 191

ANALISA MATERIAL ON SITE


6 HARGA PASIR PASANG PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K 197


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 198
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 199
- Kecepatan truck rata-rata per jam = 35.00 Km K 200
- Kapasitas angkut per truk per trip = 3.00 M3 K 201
- Waktu per trip + fixed time = 1.86 Jam K 202
- Jumlah jam efektif per hari = 7.00 Jam K 203
- Jumlah trip per Hari = 3.77 Trip K 204
- Sewa truck per trip = 1,000,000.00 Rp. K 205
- Produksi per hari = 11.31 M3 K 206
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 207
- Harga upah pekerja = 61,000.00 Rp. K 208
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 209
- Biaya bongkar muat per M3 = 21,578.23 Rp. K 210

- Harga Pasir Pasang per M3 = 291,000.00 Rp. K 211


- Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp. K 212
- Ongkos Bongkar Muat per M3 = 21,578.23 Rp. K 213

Jumlah Harga per M3 di lokasi (p + q + r) = 401,013.61 Rp. K 214


ANALISA MATERIAL DILOKASI SEMENTARA
7 HARGA PASIR BETON PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K 197


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 198
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 199
- Kecepatan truck rata-rata per jam = 35.00 Km K 200
- Kapasitas angkut per truk per trip = 3.00 M3 K 201
- Waktu per trip + fixed time = 1.86 Jam K 202
- Jumlah jam efektif per hari = 7.00 Jam K 203
- Jumlah trip per Hari = 3.77 Trip K 204
- Sewa truck per trip = 1,000,000.00 Rp. K 205
- Produksi per hari = 11.31 M3 K 206
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 207
- Harga upah pekerja = 61,000.00 Rp. K 208
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 209
- Biaya bongkar muat per M3 = 21,578.23 Rp. K 210

- Harga Pasir Beton per M3 = 291,000.00 Rp. K 211


- Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp. K 212
- Ongkos Bongkar Muat per M3 = 21,578.23 Rp. K 213

Jumlah Harga per M3 di lokasi (p + q + r) = 401,013.61 Rp. K 214

ANALISA MATERIAL DILOKASI SEMENTARA


8 HARGA PASIR FILTER PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 61,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 21,578.23 Rp.

- Harga Pasir Filter per M3 = 291,000.00 Rp.


- Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
- Ongkos Bongkar Muat per M3 = 21,578.23 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 401,013.61 Rp.


ANALISA MATERIAL ON SITE
9 HARGA BATU GRAVEL Ø 5 - 10 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 61,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 21,578.23 Rp.

Harga Batu Gravel per M3 = 313,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 21,578.23 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 423,013.61 Rp.

ANALISA MATERIAL ON SITE


10 HARGA BATU PECAH 2-3 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 61,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 21,578.23 Rp.

Harga Batu Pecah per M3 = 693,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 21,578.23 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 803,013.61 Rp.


ANALISA MATERIAL ON SITE
11 HARGA BATU PECAH 0,5-1 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 61,000.00 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 21,578.23 Rp.

Harga Kerikil Gravel cm per M3 = 761,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 21,578.23 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 871,013.61 Rp.

ANALISA MATERIAL ON SITE


12 HARGA BATU PECAH Ø 3 - 5 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km K 245


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km K 246
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km K 247
- Kecepatan truck rata-rata per jam = 35.00 Km K 248
- Kapasitas angkut per truk per trip = 3.00 M3 K 249
- Waktu per trip + fixed time = 1.86 Jam K 250
- Jumlah jam efektif per hari = 7.00 Jam K 251
- Jumlah trip per Hari = 3.77 Trip K 252
- Sewa truck per trip = 1,000,000.00 Rp. K 253
- Produksi per hari = 11.31 M3 K 254
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp. K 255
- Harga upah pekerja = 88,435.37 Rp. K 256
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang K 257
- Biaya bongkar muat per M3 = 31,283.26 Rp. K 258
K 259
Harga Batu Pecah per M3 = 693,000.00 Rp. K 260
Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 31,283.26 Rp. K 261
K 262
Jumlah Harga per M3 di lokasi (p + q + r) = 812,718.64 Rp. K 263
ANALISA MATERIAL ON SITE K 264

13 HARGA BATU PECAH Ø 1 - 2 CM PER M3 SD LOKASI PEKERJAAN

- Jarak angkut pulang pergi = 30.00 Km


- Kecepatan truck rata-rata dengan muatan per jam = 25.00 Km
- Kecepatan truck rata-rata tanpa muatan per jam = 45.00 Km
- Kecepatan truck rata-rata per jam = 35.00 Km
- Kapasitas angkut per truk per trip = 3.00 M3
- Waktu per trip + fixed time = 1.86 Jam
- Jumlah jam efektif per hari = 7.00 Jam
- Jumlah trip per Hari = 3.77 Trip
- Sewa truck per trip = 1,000,000.00 Rp.
- Produksi per hari = 11.31 M3
- Ongkos angkut ke lokasi per M3 = 88,435.37 Rp.
- Harga upah pekerja = 11.31 Rp.
- Jumlah tenaga bongkar muatan per M3 = 4.00 Orang
- Biaya bongkar muat per M3 = 4.00 Rp.

Harga Batu Gravel per M3 = 508,000.00 Rp.


Ongkos Angkut ke Lokasi per M3 = 88,435.37 Rp.
Ongkos Bongkar Muat per M3 = 4.00 Rp.

Jumlah Harga per M3 di lokasi (p + q + r) = 596,439.37 Rp.