ADDENDUM
ADDENDUM
ADDENDUM
PROYEK : Pemasangan 15 (Lima belas) Unit ATG untuk Instalasi Bandaran 13 Unit, Depot Kediri 1 Unit, Depot Tenau Kupang 1 Unit
A.I. NO : 7F5.001
JUMLAH HARGA
VOLUME HARGA SATUAN
NO. URAIAN-PEKERJAAN UNIT Kontrak Terpasang Tambah / Kurang
MATERIAL JASA MATERIAL JASA MATERIAL JASA MATERIAL JASA
Kontrak Terpasang +/-
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
I Pekerjaan Persiapan
1 Mobilisasi dan Demobilisasi tenaga kerja, peralatan kerja, material Ls 1 1 - - 9,000,000 - 9,000,000 - 9,000,000 - -
2 Gambar kerja (Installation wiring connection) Ls 1 1 - - 4,000,000 - 4,000,000 - 4,000,000 - -
Accuracy Level : ± 1 mm
Accuracy Density : ± 0.005 g/cc
Reapeatability : ≤ 1 mm
Sensitivity : ± 0.25 mm
Display : LCD 2 lines, 16 Alphanumeric Characters per line
Function : Measuring of Level, Interface, Water, Density
c/w (for Servo Tank Gauging) : - Density Displacer, SS 316, Weight 260 gr, volume,
shape Max. pressure 20 barg, diameter 90 mm.
Accuracy Level : ≤ 1 mm
Accuracy Density : ± 0.005 g/cc
Reapeatability : ≤ 1 mm
Sensitivity : ± 0.25 mm
Display : LCD 2 lines, 16 Alphanumeric Characters per line
Function : Measuring of Level, Interface, Water, Density
c/w (for Radar Tank Gauging) : Water bottom sensor for level interface
measurement PT for continuous density
measurement local indicator, Manufacture std
protocol)
6 Inventory System Including : Total Observed volume, Gross Observed volume, set 1 1 - 20,000,000 - 20,000,000 - 20,000,000 - - -
Gross Standard volume, Net standart colume, Total
Mass & Vapour Mass, Flow Rate, Density, Mass,
Flow, Gauge Alarm (Low, Low, Low, High, High, High)
All Measured Data From Interface.
7 Field Power and Control Switch : Explosion Proof Set 14 14 - 2,000,000 - 28,000,000 - 28,000,000 - - -
8 PC c/w Monitor 21" LCD & Printer Laser : Spec sesuai RKS Set 1 1 - 12,000,000 - 12,000,000 - 12,000,000 - - -
Jet
9 UPS : Kapasitas 1,5 KVA c/w Assesories Needed Unit 1 1 - 2,000,000 - 2,000,000 - 2,000,000 - - -
III Pekerjaan Pemasangan
1 Kabel individual shielded steel wire for signal 1.3 mm m 1,900 4,301 2,401 20,000 1,000 38,000,000 1,900,000 86,010,000 4,300,500 48,010,000 2,400,500
2 Power cable NYFGBY 3 x 2.5 mm2 m 1,900 3,727 1,827 22,500 1,000 42,750,000 1,900,000 83,846,250 3,726,500 41,096,250 1,826,500
3 Stanchion for TSI, switch, round box bh 14 14 - 1,600,000 16,000 22,400,000 224,000 22,400,000 224,000 - -
4 Adaptor for ATG (modifikasi mainhole) bh 14 14 - 2,000,000 1,000,000 28,000,000 14,000,000 28,000,000 14,000,000 - -
5 Adaptor for MIT (modifikasi mainhole) bh 14 14 - 900,000 200,000 12,600,000 2,800,000 12,600,000 2,800,000 - -
6 Unistraat lg 30 30 - 250,000 2,750 7,500,000 82,500 7,500,000 82,500 - -
7 Unistraat clamp 3/4" bh 115 115 - 17,500 1,000 2,012,500 115,000 2,012,500 115,000 - -
8 Conduit 3/4" m 508 508 - 20,000 1,000 10,160,000 508,000 10,160,000 508,000 - -
JUMLAH HARGA
VOLUME HARGA SATUAN
NO. URAIAN-PEKERJAAN UNIT Kontrak Terpasang Tambah / Kurang
MATERIAL JASA MATERIAL JASA MATERIAL JASA MATERIAL JASA
Kontrak Terpasang +/-
( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. ) ( Rp. )
9 Conduit 1/2" m 508 508 - 15,000 1,000 7,620,000 508,000 7,620,000 508,000 - -
10 Flexible Conduit 3/4" lg 60 60 - 53,000 2,000 3,180,000 120,000 3,180,000 120,000 - -
11 Flexible Conduit 1/2" lg 15 15 - 46,000 2,000 690,000 30,000 690,000 30,000 - -
12 Junction box (round box) explotion proof + dudukannya bh 3 3 - 1,500,000 500,000 4,500,000 1,500,000 4,500,000 1,500,000 - -
13 Junction box dudukannya (di control room) bh 1 1 - 1,000,000 500,000 1,000,000 500,000 1,000,000 500,000 - -
14 Accessories : electrical accessories. Bolt & nuf, U bolt, conduit support & etc. Ls 1 1 - 2,500,000 500,000 2,500,000 500,000 2,500,000 500,000 - -
15 Tee (explotion proof) bh 30 30 - 225,000 10,000 6,750,000 300,000 6,750,000 300,000 - -
16 Gasket Ls 1 1 - 18,000,000 3,000,000 18,000,000 3,000,000 18,000,000 3,000,000 - -
17 Galian tanah keras untuk jalur kabel m3 250 250 - - 22,500 - 5,625,000 - 5,625,000 - -
18 Proteksi pasir urug 15 cm m3 75 75 - 95,000 2,250 7,125,000 168,750 7,125,000 168,750 - -
19 Bata merah sebagai pelindung kabel + Handling bh 4,000 4,000 - 750 - 3,000,000 - 3,000,000 - - -
20 Urug kembali dan merapikan m3 175 175 - - 13,000 - 2,275,000 - 2,275,000 - -
21 Grounding cable complit : set 14 14 - 500,000 100,000 7,000,000 1,400,000 7,000,000 1,400,000 - -
- Kabel BC 50 mm2 (15 m)
- Conduit 3/4" (10 m)
- Clem 3/4" (3 buah)
- Scoon cable (1 buah)
22 Bongkaran Bandwall untuk jalur kabel Ls 1 1 - - 2,000,000 - 2,000,000 - 2,000,000 - -
23 Perbaikan pasangan batu kali bandwall Ls 1 1 - 3,750,000 1,250,000 3,750,000 1,250,000 3,750,000 1,250,000 - -
24 Set 6 6 - 7,500,000 2,000,000 45,000,000 12,000,000 45,000,000 12,000,000 - -
Pembuatan stilling wel dari pipa API 5 L Grade B Ø 10" tebal 6.4 mm yang dilobangi Ø 3/4"
dengan jarak 50mm horizontal dan jarak 200mm vertikal c/w dudukan tank gauging (u/ T6, T7, - -
T9, T11, T12, T64)
25 Tank Cleaning (u/ T6, T7, T9, T11, T12, T64) Tanki 6 6 - 900,000 4,500,000 5,400,000 27,000,000 5,400,000 27,000,000 - -
26 Pemasangan Arrester di Ruang Control Room:
a) Arrester Power Stop Kontak CNS 3 D - D bh 1 1 - 3,000,000 500,000 3,000,000 500,000 3,000,000 500,000 - -
b) Arrester Computer CNS - D bh 1 1 - 3,000,000 500,000 3,000,000 500,000 3,000,000 500,000 - -
c) Box Arrester bh 1 1 - 2,000,000 300,000 2,000,000 300,000 2,000,000 300,000 - -
27 Pengurusan surat rekomendasi dari Dirjen MIGAS dan Surat Ijin Alat Ukur dari DIMET Ls 1 1 - - 7,000,000 - 7,000,000 - 7,000,000 - -
(termsauk pengiriman masing-2 1 (satu) unit ATG Servo & Radar ke DIMET Bandung)
SUPARWATI ISRIYANTO