Table of Contents
Document Number Rev. Document Title Page
Number
A307-000-WB-MR- A ENQUIRY DOCUMENT 2
3314-1243-RFQ
A307-000-WB-MR- A VALVES-BALL (AS/INCONEL/D UPLEX) 85
3314
6-81-0001 2 Standard specification for Positive Material Identification (PMI) at 89
Supplier's Works
6-81-0004 5 ITP for valves 97
6-78-0001 0 Specification for Quality Mgt. System Requirements from Bidders 104
6-78-0003 0 Specification for Documentation Requirement from Suppliers 113
6-44-0052 6 Technical notes for valves. 125
6-79-0015 1 Specification for duplex stainless steel and super duplex stainless 145
steel
6-79-0016 1 Specification for welding of duplex stainless steel and super 157
duplex stainless steel
A307-6-44-0006- 0 SPECS FOR MR OR PACKAGE INPUT 168
3314
A307-000-16-43- A ADDITIONAL TECHNICAL REQUIREMENTS FOR VALVES- 187
ATR-3314 BALL (CAT-II)
A307-000-16-43- 0 VENDOR DATA REQUIREMENTS FOR VALVES-BALL (CAT-II) 191
VDR-3314
A307-0IV-16-43-SP- 0 JOB SPECIFICATION 193
3001
A307-000-16-43-SP- 0 SPECIAL REQUIREMENTS FOR IBR1 195
0001
Page 1 of 196
EI Bhawan Annexe, Bhikaiji Cama Place, RK Puram, New Delhi – 110 066, INDIA
Phone No : 0091-11-26762121 ; Fax No : 0091-11-26191714, 26167664
REQUEST FOR QUOTATION (RFQ)
RFQ No. : SM/A307-000-WB-MR-3314/1243 Date: 18–FEB-2014
Gentlemen,
Bids are requested on behalf of our Client M/s Bharat Petroleum Corporation Limited on e-procurement
system for the subject item in total compliance to technical specifications, scope, terms & conditions of enquiry
documents / attachments.
1. Bidder should submit their bids strictly as per the requirements outlined hereunder and as specified in
the material requisition.
2. The bidders are required to submit soft copies of their bids electronically on the CPP Portal only (URL:
http://eprocure.gov.in/cppp) using valid Digital Signature Certificate, on or before the bid submission
date and time. Bidders are required to register themselves at http://eprocure.gov.in/cppp).
Bidders to refer attached E-TENDERING METHODOLOGY (ANNEXURE-I) for detailed instructions
on registration and online bid submission.
Special Notes for e-tendering:
a) NIC Portal mandates that the bidders are to be registered on the portal before any enquiry can be
issued to them. In order to expedite issue of enquiries, the enquiry is being issued through EIL Tender
Portal and also being published on Central Public Procurement Portal. The enquiry shall be issued to
the bidders on the NIC e-Procurement Portal as soon as their registration is completed in the NIC Portal
(https://eprocure.gov.in/eprocure/app ).
b) All those vendors who have still not registered on the NIC Portal are required to register on the same
(immediately after issue of enquiry on EIL portal but not later than ten days before the bid due date) for
facilitating issue of enquiry to them on the NIC Portal failing which it will not be possible for them to
upload their bids. Pursuant to registration, the vendors are also required to login in EIL tender portal and
update NIC’s registration details and inform the undersigned regarding the same for the subject enquiry.
In any case, the enquiry shall be issued on NIC portal to NIC registered vendors about one week before
the bid due date. Therefore, all those bidders who have not complied with the above registration
requirements will not be issued this enquiry on NIC portal and will not be eligible to bid. Request for
extension in due date of submission of bids due to non registration or delayed registration in NIC portal
shall not be entertained.
Page 1 of 6
Page 2 of 196
c) The bid has to be necessarily submitted on the NIC Portal and only those bidders who are issued the
enquiry through NIC Portal will be eligible to submit their bids. In case a bidder does not register on the
NIC Portal and as a consequence, cannot be issued the enquiry through NIC Portal, it shall be deemed
that he is not interested in bidding against this enquiry and no further correspondence will be
entertained.
d) In future, EIL shall be issuing all enquiries through NIC Portal alone and bidders who do not register with
NIC Portal may not be able to submit their bids. Therefore, it is in the interest of the bidders that they
register on the NIC Portal at the earliest.
e) The vendor registration on NIC Portal is a very user friendly process. However, in case of any doubt,
the vendor may contact the 24*7 CPP Portal Helpdesk at contact no. 1800 233 7315.
3. Bidders in their own interest are requested to register on CPP Portal and upload/submit their bid well in
time. Bidder will be responsible for any delay due to other issues.
4. Bidders are required to upload the complete bid comprising of Part-I:- Unpriced Bid along with all
supporting documents & Part-II :- Priced Bid on the CPP Portal (http://eprocure.gov.in/cppp) only.- Refer
E-Tendering Methodology (ANNEXURE-I) enclosed with RFQ documents.
5. Upon the successful and timely submission of bids, the portal will give a successful bid submission
message & a bid summary will be displayed with the bid no. and the date & time of submission of the bid
with all other relevant details. The bid summary has to be printed and kept as an acknowledgment of the
submission of bid. This acknowledgment may be used as an entry pass for attending the un-priced bid
opening, if bidders so desire.
6. Technical specification should be strictly as per the Material Requisition attached. It may be noted that
the Bid shal be evaluated as received and technical queries may not be issued.
7. Commercial requirements are specified in the Special Instructions to Bidders, General Purchase
Conditions, Agreed Terms & Conditions (ATC) questionnaire and all other RFQ documents. The pre-
filled Agreed Terms & Conditions Questionnaire should be returned duly signed and stamped along with
copy of your un-priced bid.
8. The order, if placed, will be issued by our above-mentioned client.
9. If not bidding, please inform vide E-mail with attached regret letter within the due date & time, with
reasons(s) of not participating in the RFQ. In case there is no response, names of such bidder may not
be considered for issuance of future enquiries.
10. Direct bids only, without the intermediary of an Indian Agent will be considered from Foreign Bidder.
11. Delivery Period:-
FOR INDIAN BIDDERS: Within 6 Months on FOT Despatch Point Basis from the date of Fax of
Acceptance. Date of LR/GR shall be considered the date of delivery.
FOR FOREIGN BIDDERS: Within 5 Months on FOB International Sea Port of Exit Basis from the Date
of Fax of Acceptance. Date of clean bill of lading shall be considered the date of delivery.
12. Payment Terms shall be as per following:-
For Indian bidders: The payment to Indian bidders shall be made in accordance with S. No. 1.2 & 1.7
Under Section A of Special Instruction to Bidders (SIB).
For Foreign Bidders: The payment to foreign bidders shall be made in accordance with S. No. 2.1
Under Section A of Special Instruction to Bidders (SIB).
13. The offer should be valid for 04 (FOUR) months from final bid due date.
14. Only E-Bids uploaded in the e-tendering portal (http://eprocure.gov.in/cppp) shall be acceptable.
Physical bids and Bids/ Offer through Email or fax/ Telex/Telegraphic or Bids received in open
Page 2 of 6
Page 3 of 196
condition or Bids in any other mode shall not be accepted.
15. The bidder shall bear all costs associated with the preparation and submission of its bid, and the
Purchaser/Consultant shall in no case be responsible or liable for these costs regardless of the
conduct or outcome of the bidding process.
16. Canvassing in any form by the Bidder or by any other agency on their behalf may lead to
disqualification of their bid.
17. The E-bids received online shall be opened at EIL office on due date and time as specified above.
Bidder can view online the name of the other bidders who have submitted their e-bids after opening is
performed by EIL.
18. All technically and commercially acceptable bidders will be advised of venue, date and time of priced
bid opening. Bids shall be opened online, hence bidders may review opening status at their places.
Interested bidder may sent their representatives (duly authorised by a competent person and having
the Letter of Authority as per proforma enclosed), of such technically and commercially acceptable
bidders. Time and Date of opening of Price Bids shall be notified to the qualified and acceptable
bidders at a later date.
19. As Purchaser intends to contract directly with suppliers of the goods for which bids are invited, the
bids should be prepared by the suppliers and submitted directly. Purchaser reserves the right to reject
offers made by intermediaries.
20. Addendum / corrigendum to the RFQ documents if issued must be signed and submitted along with
the bid.
21. Bidders to note that price changes against Technical / commercial clarifications, in line with terms &
conditions of enquiry documents are not allowed. In case any bidder gives revised prices / price
implications against such clarifications, their bid shall be liable for rejection.
22. EIL reserves the right to use in-house information for assessment of bidder’s capability for
consideration of bid.
23. In case any bidder is found to be involved in cartel formation, his bid will not be considered for
evaluation / placement of order. Such bidder will also be debarred from bidding in future.
24. The bidder who is providing the technology from the company which is recently acquired / taken over
by them or purchasing the technology by other companies, shall be provide proper documentary
evidence. In the absence of the same their offer shall be liable for rejection.
25. Bidders are requested to quote as per their capability as registered in EIL, as on the date of issue of
RFQ.
26. Owner reserves its right to allow Public Sector Enterprises (Central/State), Micro & Small Enterprises
(MSEs) and MSEs owned by Scheduled Caste (SC)/ Scheduled tribe (ST) entrepreneurs, purchase
preference as admissible/applicable from time to time under the existing Govt. policy. Bidder to
submit documentary evidence for the same duly certified by Statutory Auditor of the bidder or a
practicing Charted Account (not being an employee or a Director or not having any interest in the
Bidder’s company / firm) where audited accounts are not mandatory as per law.). In this regard, item
wise quantity may be splitted and the quoted price shall remain valid.
27. The Net Worth of the bidder should be positive as per the immediate preceding year's audited
financial results. However, Central Public Sector Enterprises (CPSEs) are exempted from this
requirement. If the bidder is not meeting the above criteria their bid shall not be evaluated further.
Bidders are therefore requested to furnish the Audited Financial Statement for the immediate
preceding year including Profit & Loss Account.
Bidders are required to submit the complete audited financial report for the preceding
financial year including balance sheet, profit and loss statements along with all relevant
annexures required to assess the positive net worth of the bidder in that financial year. Failure
to submit the same may render your bid liable for rejection.
28. Purchaser reserve the right to make any changes in the terms and conditions of purchase and to
reject any or all the bids.
Page 3 of 6
Page 4 of 196
Contact Persons for this RFQ are:
Mr Subhendu Mondal, AGM(C&P),
Phone No. +91-(0)11-2676-3883 & email: subhendu.mondal@eil.co.in
Mr Anindya Sinha, Manager (C&P),
Phone No. +91-(0)11-2676-3886 & email: anindya.sinha@eil.co.in
Mr. Naveen Baswal, Engineer (C&P),
Phone No. +91-(0)11-2676-3880 & email: naveen.baswal@eil.co.in
(SUBHENDU MONDAL)
ASST. GEN. MANAGER(C&P)
ENGINEERS INDIA LIMITED
LIST OF ENCLOSURES
DOCUMENT
A) Request For Quotation (RFQ)
B) Proforma of Letter of Authority for Attending Un-priced / Priced Bid Opening
C) Price Schedule Format (For Indian Bidders)
D) Price Schedule Format (For Foreign Bidders)
E) Commercial document:
i) Agreed Terms & Conditions (For Indian Bidders)
ii) Agreed Terms & Conditions (For Foreign Bidders)
iii) Special Instruction to Bidders (SIB)
iv) General Purchase Conditions (Indian)
v) General Purchase Conditions (Imported)
vi) Special Packaging Requirements ( For Foreign Bidders)
vii) Tax Residency Certificate
viii) Proforma of Bank Guarantee (Performance)
ix) Integrity Pact
x) E-tendering Methodology (Annexure-I).
xi) Instructions for Foreign bidders for DSC
F) Technical document MR No. A307-000-WB-MR-3314 Rev. A
Page 4 of 6
Page 5 of 196
Proforma of Letter of Authority
for Attending Unpriced / Priced Bid Opening
No. Date:
Dear Sir,
We confirm that we shall be bound by all and whatsoever our representative(s) shall commit.
Yours faithfully,
Signature _________________________
Name & Designation ________________
For & on behalf of __________________
Note:
This Letter of Authority should be on the letterhead of the bidder and should be signed by a
person competent and having the Power of Attorney to bind the bidder.
Page 5 of 6
Page 6 of 196
PREAMBLE TO PRICE SCHEDULE FORMAT
INDIGENOUS BIDDERS:
1) Bidder must quote the price in enclosed Price Schedule Formats for Indian Bidders only. The Price
Schedule Formats shall not be changed and/or retyped and upload the same in CPPP portal.
2) Bidders must indicate Freight Charges (inclusive of service tax) upto project site in the Price Schedule
Formats (for Indian Bidders) in terms of percentage.
FOREIGN BIDDERS:
1) Bidder must quote the price in enclosed Price Schedule Formats (Foreign Bidders) only. The Price
Schedule Formats shall not be changed and/or retyped and upload the same in CPPP portal.
2) Bidder shall quote in USD / Euro / INR only. Bids of such Bidder(s) who quote in any other Currency may
not be considered for further evaluation.
3) Bidders must indicate Ocean Freight Charges upto Port of Entry Kochi (India) in the Price Schedule
Formats (for Foreign Bidders) in terms of percentage of quoted FOB International Port of Exit Prices.
1) Bidder’s quoted prices are inclusive of all testing charges as per requirement of Material Requisition.
3) In case of discrepancy between unit Price & total Price, unit Price shall govern.
4) Bidder must submit signed and stamped Un-Priced copy of Price Schedule indicated Quoted or Not
Quoted against each item with their Unpriced offer.
5) Bidder must quote the price in enclosed Price Schedule formats only. The formats shall not be changed
and/or retyped.
Page 6 of 6
Page 7 of 196
PRICE SCHEDULE (INDIAN BIDDERS) Rev.0
Name Of Vendor:
INDICATE FREIGHT CHARGES (INCLUSIVE OF SERVICE TAX) UPTO PROJECT SITE IN TERMS OF
………...…..%
PERCENTAGE OF FOT DESPATCH POINT PRICE :
Page 8 of 196
PRICE SCHEDULE (FOREIGN BIDDERS) Rev.0
RFQ NO. : SM/A307-000-WB-MR-3314/1243
Name Of Vendor:
INDICATE OCEAN FREIGHT CHARGES UPTO KOCHI PORT, KERALA (INDIA) IN TERMS OF
……….……..%
PERCENTAGE OF QUOTED F.O.B. UNIT PRICE :
Page 9 of 196
A307_ATC (I) Page 1 of 8
2. DULY SIGNED & STAMPED COPIES OF THIS “QUESTIONNAIRE”, WITH ALL THE
CLAUSES DULY CONFIRMED/ PRECISELY REPLIED TO BY THE SUPPLIER, SHALL BE
ENCLOSED.
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
1. Price Basis:
i) Quoted supply prices are on FOT - Despatch Point basis Confirmed
inclusive of Packing & Forwarding.
ii) Specify Despatch Point
-----------------------
iii) Freight Charges:
a) Confirmed , Quoted in Price
a) Confirm firm transportation charges inclusive of Service Tax Schedule
and Ed Cess, upto project site, has been quoted separately
by you in Price Schedule.
b) Confirmed
b) No Variation on any account (including Statutory Variation) on
Service Tax on Transportation Charges shall be paid by the
owner.
iv) Insurance:
Page 10 of 196
A307_ATC (I) Page 2 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
b. Present Rate of Excise Duty & Edu. Cess payable extra on ………..%
finished goods (including Spares)
c. Any variations in Excise Duty & Edu. Cess at the time of Confirmed
supplies for any reasons including variation due to Turnover
shall be borne by the Seller. Only Statutory Variations within
the Contractual Delivery / completion period shall be borne by
Purchaser.
d. If Excise Duty & Edu. Cess is not applicable at present due to Confirmed
any reason, the same shall be borne by Seller if it becomes
applicable later.
e. Confirm Excise Duty & Edu. Cess will not be applicable on Confirmed
transportation charges.
Page 11 of 196
A307_ATC (I) Page 3 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
7. Site Work:
For Site Work, if in the scope of the Bidder as per MR, please
confirm the following:
Confirm that quoted site work prices are exclusive of Service
a. Tax & Edu. Cess but inclusive of VAT on Works Contract and Confirmed
all other applicable taxes & duties.
b. Percentage of Service Tax & Edu. Cess as applicable extra -------------------%
on Site Work.
c. Supplier shall submit the Assessment/ Liability
Certificate from Sales Tax authorities indicating the VAT
on Works Contract payable for enabling Owner to
deduct the same from Supplier Invoices & make Confirmed
payment to the tax authorities. TDS Certificate towards
VAT on Works Contract shall be provided by Owner.
Statutory variation on VAT on Works Contract shall not
be payable by Owner.
d. Statutory Variation on Service Tax & Edu. Cess on Site work
shall be paid by the Owner against documentary evidence
Confirmed
within Contractual completion period.
Page 12 of 196
A307_ATC (I) Page 4 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
a. Charges for Supervision / Training, if in the scope of the Confirmed, Quoted in Price
Bidder as per MR have been indicated by bidder separately in Schedule
the Price Schedule.
e. Bidders shall also provide additional BG of an amount equal Noted & Confirmed
to the per diem charges for the number of days considered for
evaluation, over and above 10% PBG to cover compensation
for delay in mobilizing the erection/ commissioning personnel.
This BG will be released to the bidder upon the erection/
commissioning personnel reporting at site. This BG shall be
furnished along with payment milestone for submission of
final documentation as per MR and shall be initially valid up to
six months which shall be extended based on the request by
Owner.
Page 13 of 196
A307_ATC (I) Page 5 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
13.1 PART ORDER:
a. Confirm acceptance of Part Order clause as per GPC Confirmed (If Applicable as per MR)
(Indigenous). And bidder also confirm acceptance to part
quantity orders of any items (having quantities 5 Nos. & more)
to facilitate purchase preference to MSME bidders as per
Govt. guide lines.
13.2 MSME BIDDERS:
YES/ NO
a Confirm whether the bidder is a MSME bidder or not. (Please tick whichever is applicable)
b In case bidder is a MSME bidder, they must submit
documentary evidence for the same duly certified by
Statutory Auditor of the bidder or a practicing Charted
_________________
Account (not being an employee or a Director or not
having any interest in the Bidder’s company/ firm) where
audited accounts are not mandatory as per law.
c In case bidder does not submit duly authenticated
documentary evidence as required above, bidder shall Confirmed
not be considered eligible for availing MSME benefits.
d Any charges quoted extra as lumpsum (like IBR,
Testing, freight, etc.) shall be applicable prorata on
Confirmed
value basis in the event of part order / part quantities/
split order.
14. Repeat Order:
Confirm Acceptance of Repeat Order clause as per RFQ Confirmed
Covering Letter / SIB / GPC.
Page 14 of 196
A307_ATC (I) Page 6 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
Confirmed
iii) Inclusive of all statutory certification charges PESO/CCOE
etc. (if applicable) as required in the Material Requisition
Confirmed
c. Is your shop approved by IBR/CCE authority, if yes, indicate
validity.
i. IBR IBR Approved
ii. CCE
It is the responsibility of supplier to get the entire imported
materials and the built in imported contents inspected by TPIA Confirmed
(i.e. Lloyds/BV/DNV/TUV/CEIL) in the country of origin and
the quoted prices are inclusive of charges towards the same.
19. Import Content:
If your offer is based on certain imported raw materials (Applicable / Not Applicable)
required for equipments/ materials offered, please specify the (Please tick whichever is applicable)
following :
b. Indicate rate of Import Duties considered and included in the Refer Annexure to Price Schedule
quoted prices.
c. Indicate brief description/ specification with itemised CIF Refer Annexure to Price Schedule
value and country of origin of imported material.
d. Indicate classification with tariff no. under which Vendor Refer Annexure to Price Schedule
intends to import.
Page 15 of 196
A307_ATC (I) Page 7 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
l. The CIF Value(s) indicated by the vendor shall be deemed to Confirmed
be the maximum value(s) for the purpose of payment of
variation in custom duty and/or other statutory variations, if
any, thereon.
22. Whether any of the Directors of Bidder is a relative of any Confirmed No relation
Director of Owner/EIL or the Bidder is a firm in which any
Director of Owner/EIL or his relative is a Partner or the Bidder
is a private company in which any director of Owner/EIL is a
member or Director.
23. Please confirm you have not been banned or delisted by any Not Banned
Government or Quasi Government agencies or PSUs. If you
have been banned, then this fact must be clearly stated. This
does not necessarily mean cause for disqualification.
However if this declaration is not furnished the bid shall be
rejected as non-responsive.
24. Please confirm your offer contains the following:
Page 16 of 196
A307_ATC (I) Page 8 of 8
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
contradiction between the confirmations given above and
terms & conditions mentioned elsewhere in the offer, the
confirmation given/confirmed herein above shall prevail.
28. Confirm that Net worth of the Bidder’s company is Confirmed & Submitted
positive as per the immediate preceding year’s audited
financial results & Immediate preceding year’s audited
annual financial results has been submitted along with un-
priced bid.
Page 17 of 196
A307_ATC (F) Page 1 of 7
2. DULY SIGNED & STAMPED COPIES OF THIS “QUESTIONNAIRE”, WITH ALL THE CLAUSES
DULY CONFIRMED/ PRECISELY REPLIED TO BY THE SUPPLIER, SHALL BE ENCLOSED.
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
1. a) Confirm that the offer contains firm prices on Confirmed
F.O.B. International Seaport of Exit Basis
b) Indicate International Seaport of Exit -----------------------------
c) Indicate the HSN Code of the Items __________________
d) Details of any Free Trade Agreement (FTA) /
Comprehensive Economic Partnership
Agreement (CEPA) / Treaty between Bidders
country Govt. & Indian Government for availing
custom duty exemption / concession. If bidder will
not specifically mention the same, it is to be Applicable / Not Applicable
considered that there is no specific Agreement /
Treaty between Govt. of Bidders & Purchasers
County.
e) Confirm quoted prices are inclusive of stowage
charges. Confirmed
Page 18 of 196
A307_ATC (F) Page 2 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
g) In case you have not indicated the ocean freight
charges separately in the price schedule please
quote the same in terms of Percentage of the ------------ %
quoted FOB Price.
h) In case ocean freight charges are repeated
anywhere in the bid/Price Schedule/ATC, then Confirmed
higher shall be considered for evaluation & lower
for ordering. (In case of CFR)
2. Insurance:
a) For Supply Only
Price quoted must exclude Marine insurance
charges from FOB International Port of Exit, as Confirmed
same shall be arranged by the Owner. However
all marine insurance charges for inland transit
upto FOB International Port of Exit must be
included by you in your prices.
b) For Supply + Site Work
Comprehensive Insurance (Transit/Marine-cum-
Confirmed
storage-cum-erection till handing over of
equipment) has been taken care by the Seller &
charges of the same have been included in the
quoted prices.
3. Owner reserves the option to place order either on
FOB or CFR basis (applicable only as per Confirmed
requirement mentioned in RFQ documents).
4. Delivery / Completion Period:
a) Delivery / Completion period shall be as Confirmed
mentioned in the RFQ covering letter.
b) Confirm delivery period shall be reckoned from Confirmed
the date of Fax of Acceptance.
c) Confirm date of clean Bill of Lading shall be
considered as date of delivery. (In case order is Confirmed
placed on FOB port of Exit basis or on CFR
basis)
Page 19 of 196
A307_ATC (F) Page 3 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
7. Site Work:
For Site Work, if in the scope of the Bidder as per
MR, please confirm the following:
Page 20 of 196
A307_ATC (F) Page 4 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
Page 21 of 196
A307_ATC (F) Page 5 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
16. Indicate shipping weight (net and gross) and volume
of the consignment.
---------------------------
17. Performance Bank Guarantee:
a. Confirm goods to be supplied by you shall be
guaranteed for performance as per the General Confirmed
Purchase Conditions (Imports) & Special Instructions
to Bidders (SIB) and submission of the Bank
Guarantee 15% of Order Total Value (10% towards
Performance and 5% towards Price Reduction
Schedule for delay in Delivery) shall be valid till full
guarantee period plus 3 (Three) Months.
Page 22 of 196
A307_ATC (F) Page 6 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
22. Price Reduction on delay in delivery/completion:
a) Confirm acceptance of price reduction schedule Confirmed
for delay in deliveries/completion of work/services
specified in General Purchase Conditions (GPC)
enclosed with the RFQ Document. Liquidated
damages or penalty are not acceptable.
Page 23 of 196
A307_ATC (F) Page 7 of 7
SL.
DESCRIPTION SUPPLIER’S CONFIRMATION
NO.
VENDOR’S NAME:
Page 24 of 196
BPCL-KR
Job: A307
Page 25 of 196
BPCL-KR
Job: A307
INDEX
SECTION – A (TERMS OF PAYMENT)
1.0 Payment Terms For Indian Bidders
2.0 Payment Terms For Foreign Bidders
3.0 Ocean Freight
SECTION – B: EVALUATION CRITERIA FOR COMPARISION OF BIDS
4.0 Where only Indian Bids are under comparison
5.0 Where only Foreign Bids are under comparison
6.0 Where Indian as well as Foreign Bids are under comparison
7.0 General Notes
8.0 Special Notes on Taxes/Duties and CENVAT benefits
9.0 Price Reduction Schedule Towards Delay In Delivery
10.0 Guarantee / Warranty Period
SECTION-C: (COMMERCIAL LOADING OF OFFERS IN CASE OF DEVIATIONS)
11.0 Basis of Loading
12.0 Payment Terms
13.0 Performance Bank Guarantee (PBG)
14.0 Delayed Deliveries
15.0 Price Variation
16.0 Freight charges
17.0 Indian taxes/ duties
18.0 Utilities
19.0 Delivery/Completion Period
20.0 Foreign Exchange Rate Variation/Custom Duty Variation For Indian Bidders (On
Built-In Import Content)
21.0 VAT on Works Contracts/ Service Tax/ Splitting Of Orders
22.0 Entry Tax
23.0 Rejection Criteria
24.0 Suo-Moto Changes In Prices
25.0 Price Implication Not Permitted
26.0 Integrity Pact
SECTION-D: SPECIAL CONDITIONS.
27.0 Delivery Schedule/ Completion Period
28.0 Despatch Instructions for Indigenous Supplies
29.0 Additional Taxes & Duties (Applicable For Indian Bidder)
30.0 Recovery Of Custom Duty, Excise Duty And Sales Tax
31.0 Governing Law
32.0 Purchaser’s Rights And Remedies
33.0 Deduction At Source
34.0 Statutory Approval
35.0 Lien
36.0 Limitation Of Liability
SECTION-E: GENERAL INSTRUCTIONS
37.0 General
38.0 Fraudulent Practices
39.0 One Bid Per Bidder
40.0 Language Of Bid
41.0 Earnest Money Deposit:
42.0 Modification And Withdrawal Of Bids
43.0 Examination Of Bids And Determination Of Responsiveness
44.0 Owner’s Right To Accept Any Bid And To Reject Any Bid
45.0 Notification Of Award
46.0 Waiver Or Transfer Of The Agreement
47.0 T&C For Foreign Suppliers (To Whom RFQ Issued) Operated Through Their Indian
Office / Subsidiaries
48.0 Tax Residency Certificate (TRC) Format For Foreign Bidder
49.0 Requirement of Employment Visa For Foreign Nationals
Page 26 of 196
BPCL-KR
Job: A307
1.1 Where the Material Requisition is only for supply of materials and there is no Supplier Data
Requirement specified in MR e.g. Bulk Piping Items, etc.
1.1.1 100% Payment within 30 days after receipt and acceptance of materials at site and on submission of
Performance Bank Guarantee for 10% of Total Order Value, valid till the full guarantee period plus
Three months claim period.
1.2 Where the Material Requisition calls for Supplier Drawings/Technical Documentation.
1.2.1 90% Payment within 30 days of receipt and acceptance of materials at Site and on submission of
dispatch documents.
1.2.2 10% Payment after receipt of final technical documentation as per PR against EIL’s certification and
on submission of Performance Bank Guarantee for 10% of Total Order Value, valid till full guarantee
period plus Three months claim period.
1.3 Where Supply of materials and Erection or Site Work are in the scope of Supplier and
Package Items.
1.3.1 Supply
1.3.1.1 5% Payment on approval of all drawings atleast in CODE-2 by EIL against submission of Bank
Guarantee of equivalent amount valid till complete execution of Order plus Three months claim
period.
1.3.1.2 15% Payment after receipt of identified raw materials at Supplier’s Works and against certification by
EIL and submission of Bank Guarantee of equivalent amount valid till complete execution of Order
plus Three months claim period.
1.3.1.3 60% Payment after receipt of equipment/materials at BPCL’s Site. Billing Schedule to be furnished
by the Supplier in case pro-rata payments are required.
1.3.1.4 10% payment after completion of Site Work and submission of final Technical documents as
specified in the Purchase Requisition against EIL’s Certification and submission of Performance
Bank Guarantee for 10% of Total Order Value (Supply plus Site Work), valid till full guarantee period
plus three months claim period.
In case of delay in start of the site work beyond 6 months, the above 10% Payment shall be released
against submission of Bank Guarantee of equivalent amount valid initially for 1 year and subject to
extension upto completion of the site work. However, in the event of delay in the site work, the
Supplier is not relieved of his responsibility to carry out the same.
1.3.1.5 10% payment within 30 days of handing over the successfully commissioned equipment. Wherever
commissioning is not in the Supplier’s scope, the payment will be released after completion of Site
Work as per PR and handing over of equipment.
Page 27 of 196
BPCL-KR
Job: A307
1.4.2 15% after receipt of identified raw materials at Supplier’s Works and against certification by EIL and
submission of Bank Guarantee of equivalent amount valid till complete execution of Order plus
Three months claim period.
1.4.3 60% Payment through NEFT against receipt of materials at BPCL’s Site. Billing Schedule to be
furnished by the Supplier in case pro-rata payments are required.
1.4.4 10% Payment after receipt of final documents as required in Purchase Requisition against EIL’s
certification and on submission of Performance Bank Guarantee for 10% of Total Order Value, valid
till full guarantee period plus Three months claim period.
1.4.5 Balance 10% Payment within 30 days of receipt of equipment at Site.
1.6 Payment for PGTR / Per Diem Charges for Supervision of Erection, Testing &
Commissioning
1.6.1 100% Payment of Invoice Amount shall be paid on completion of supervision services / PGTR
against submission of Invoice along with Time Sheet duly certified by EIL/BPCL Site-In-Charge.
Payment shall be made after deducting Income Tax at applicable rate. Service Tax, if any, shall be
paid on submission of Service Tax Invoice.
1.6.2 Where erection/commissioning supervision, commissioning assistance is required from the vendor,
penalty for non mobilization/delay in mobilization as per order shall also be specified in the
specifications. The penalty shall generally be 1.5 times the per diem rate for each day of delay of
reporting to site and shall be in addition to price reduction for delayed delivery.
1.6.3 Wherever supervision is in the scope of MR, bidders shall provide additional BG of an amount equal
to the per diem charges for the number of days considered for evaluation over and above 10%
PBG to cover compensation for delay in mobilising the erection/ commissioning personnel. This BG
will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG
shall be furnished along with payment milestone for submission of final documentation as per PR
and shall be valid up to six months which shall be extended based on the request by BPCL. (In case
where commissioning, Performance Guarantee Test, etc. are required and the 10% is under hold,
this condition shall not be applicable).
1.7 Transportation charges
1.7.1 100% Payment within 4 weeks after receipt of materials at site.
1.8 General
1.8.1 Excise Duty, Service Tax & VAT on Supplies shall be released only on receipt of Cenvatable/
Vatable copy of corresponding Invoice enabling availing of Input Credit by BPCL.
1.8.2 No initial advance payment along with Order shall be made by the Owner against Supplies as well
as Services (i.e. Transportation, Erection, Site Work, etc.). If a Supplier insists on the same, their
Offer shall be rejected.
1.8.3 Bank Guarantee(s) shall be issued through Scheduled Commercial Bank in India/ Indian Branch of
Foreign Bank, directly to BPCL as per the Pro-forma enclosed with RFQ documents and Supplier
shall also enclose copy of the same along with Invoice.
Page 28 of 196
BPCL-KR
Job: A307
1.8.4 All payments shall be released either through Electronic Clearing System (ECS) / Electronic Fund
Transfer (EFT)/ Real Time Gross Settlement (RTGS) or through internet, within 30 days of receipt of
Invoice and all requisite documents, complete in all respects.
1.8.5 Billing schedule shall be submitted to EIL & BPCL by the Supplier for approval within 30 days from
the date of Purchase Order wherever specified therein. No payment against pro-rata dispatch shall
be made without approval of Billing Schedule.
1.8.6 Major Raw Material: Shall be as specified below:
i. Columns and Vessels: Plates and Forgings
ii. Heat Exchangers: Plates, Forgings and Tubes
iii. Pumps/Compressors: Castings and Drivers
iv. Any other item(s) as may be defined in MR/PR.
2.2 Where the Material Requisition calls for Supply of material and Erection or Site Work in the
scope of Supplier and Package Items
For Supply Portion
2.2.1 90% Payment of FOB Supply value through an Irrevocable Letter of Credit against submission of
Shipping Documents. The Letter of Credit shall be established only on receipt of acceptance of Fax
of Acceptance/Purchase Order along with submission of Bank Guarantee of 15% of Order Value
(10% towards Performance Bank Guarantee valid till full Guarantee period plus Three months claim
period & separate 5% Bank Guarantee towards Price Reduction Schedule due to delay in delivery
valid till contractual delivery date (CDD) + Five and half Months).
2.2.2 10% Payment of FOB Supply value through direct wire transfer through banking channels on
completion of Erection or Site Work or Commissioning/Performance Guarantee Test Run (PGTR) at
site, as applicable as per Purchase Order/Purchase Requisition (PR) against submission of final
documents or Certificate of Completion of Work by BPCL Site.
For PGTR cases only
The above amount (10%) shall be released against successful demonstration of Performance
Guarantee Test Run & submission of Invoices duly certified by Site-In-charge or 6 months from
receipt of material at site (against BG of equivalent amount valid for 1 year), whichever is earlier.
However in the event of delay in conducting the PGTR, the bidder is not relieved of his responsibility
to carry out the same. No additional payment shall be made for visit of supplier to site for
demonstrating the PGTR, if the same is included in the scope of supplier.
Page 29 of 196
BPCL-KR
Job: A307
period plus Three months claim period & separate 5% Bank Guarantee towards Price Reduction
Schedule due to delay in delivery valid till contractual delivery date (CDD) + Five and half Months).
2.5.3 Wherever supervision is in the scope of MR, bidders shall provide additional BG of an amount equal
to the per diem charges for the number of days considered for evaluation over and above 10%
PBG to cover compensation for delay in mobilising the erection/ commissioning personnel. This BG
will be released to the bidder upon the erection/ commissioning personnel reporting at site. This BG
shall be furnish along with dispatch documents which shall be initially valid up to six months whixh
shall be extended based on the request by BPCL.
2.6 General
2.6.1 No initial advance payment along with Order shall be made by the Owner against Supplies as well
as Services (i.e. Transportation, Erection, Site Work, etc.). If a Supplier insists on the same, their
Offer shall be rejected.
2.6.2 All Bank Guarantee(s) shall be issued through any Indian Scheduled Bank or branch of an
International Bank situated in India and registered with Reserve Bank of India as scheduled foreign
Bank as per Pro-forma provided in RFQ documents. All Bank Guarantees will be directly to BPCL by
the Bank.
2.6.3 All bank charges and stamp duties payable outside India in connection with payments shall be borne
by the Supplier. All bank charges and stamp duties payable in India shall be borne by BPCL except
L/C Amendment charges for delays in delivery. Confirmation charges for Confirmed L/C shall be
borne by Supplier.
2.6.4 Billing schedule shall be submitted to EIL & BPCL by the Supplier for approval within 30 days from
the date of Purchase Order wherever specified therein. No part shipment shall be made without
approval of billing schedule.
2.6.5 Subject to Technical Acceptability, For supplies sourced within India (if any) by Foreign
Bidder & directly dispatched to Site shall have following provisions: (Refer Annexure-A)
Page 30 of 196
BPCL-KR
Job: A307
Freight Charges/ CFR prices should be valid for additional 4 months from the date of Order. The
bidder is required to furnish the shipping details within 45 days from the date of order. In case the
bidder is not able to prove the shipping details within 45 days then 4 months shall be considered
from the date of receipt of shipping details of consignment for converting FOB to CFR.
3.4 Above clause no. 3.1 to 3.3 is not applicable for Turn-Key jobs where ocean freight along with
Marine cum transit cum erection insurance in bidders scope.
If a Bidder does not quote Ocean freight charges, his offer shall be loaded with maximum freight
charges as quoted by the other bidders.
Comparison shall be done on equivalent Indian Rupees considering RBI Reference rate of Foreign
Exchange published on the day of Opening of Priced Bids.
Normally, deviations in Payment terms, Firm prices & Performance Bank Guarantee are not
acceptable. However, wherever Bidder insists, the loading shall be done as applicable to Indigenous
cases on FOB price.
Page 31 of 196
BPCL-KR
Job: A307
Foreign Bidders:
Bids shall be evaluated on the basis of landed cost at Site including the charges of inspection by
Third Party Inspection Agency, all duties, taxes and ocean freight charges as under less Cenvatable
CVD/SAD, Cenvatable Service Tax, VAT on Supplies, VAT on Works Contract, whichever is
applicable.
Wherever supervision and site works are involved, in that cases service tax plus Ed. Cess shall be
loaded with as applicable rates
7.0 GENERAL NOTES:
i. Cost of Mandatory (Insurance) Spares, if identified in the Material Requisition, Commissioning
spares and Special Tools & Tackles will be included for price evaluation of bids, but costs of Spares
for Two Years Normal Operation & Maintenance shall be excluded.
ii. Cost of loading towards Technical Parameters (Utilities, etc.) wherever applicable shall be carried
out.
iii. BPCL shall claim CENVAT benefits on Excise Duty, CVD/SAD, Service Tax as well as the Cess
applicable and accordingly Excise Duty/ CVD/ SAD/ Cess/ Service Tax shall be considered and
necessary credit shall be given for evaluation and comparison of bids.
Wherever Site Work, AMC, Training, Supervision, etc. are required as per MR/RFQ, the same shall
be considered for evaluation.
iv. Bidders shall indicate the Customs Duty at Merit Rate in their Offer.
v. The Bidder must ascertain and confirm along with supporting documents in the bid, if any Custom
duty exemption / waiver is applicable to the products being supplied by bidder under any multi-lateral
/ bi-lateral trade agreement between India and Bidder’s country.
The bidder shall liable to provide all documentation to ensure availment of the exemption / waiver. In
case the bidder defaults on this due to any reason whatsoever, they shall be liable to bear the
incremental Custom Duty applicable, if any.
Any Custom Duty applicability on account of any change in the bi-lateral / multi-lateral agreement
shall be in bidder’s account.
Page 32 of 196
BPCL-KR
Job: A307
Documentation to be furnished for availing any exemption / waiver of Custom Duty shall be
specifically listed in Letter of Credit also as the pre-requisite for release of payment against shipping
documents and this documentation shall necessarily from a part of shipping documents.
vi. BPCL shall issue Concessional Form ‘C’ for Central SalesTax, for all applicable cases.
vii. Comparison shall be done on equivalent Indian Rupees considering RBI Reference Rate of Foreign
Exchange published on the day of opening of the Price Bids.
viii. Third Party Inspection charges for foreign bidder must be included in quoted prices or anything
specifically mentioned in RFQ documents..
ix. Excise Duty, Central Sales Tax, VAT on Supplies & Service Tax shall not be included in the quoted
prices and shall be payable extra at actual. BPCL shall claim eligible credit on CENVAT/Service
Tax/VAT quoted by the Bidder and therefore eligible portion of CENVAT/Service Tax/VAT shall be
considered for price comparison. Bidder shall be required to furnish proper invoices issued in
accordance with relevant rules for enabling BPCL to avail CENVAT benefits. Further, the amount of
Excise Duty, Service Tax & VAT shall only be payable against submission of CENVATABLE/
VATABLE Invoices, subject to maximum amount quoted in the Offer and in case of non-submission,
will not be paid.
x. Bidders quoted transportation charges shall be inclusive of service tax plus education cess
thereupon applicable on transportation.
xi. Transit Insurance/ Marine Insurance shall be excluded from Supplier’s scope for the items where
only supply is involved, and in such cases, the same shall be arranged by the Owner. For purchases
involving Site Work, the Comprehensive Insurance (Transit/Marine cum Storage, Erection, till
handing over of equipment) shall be in the scope of Supplier.
xii. Owner reserves its right to allow Public Sector Enterprises (Central/State), Micro & Small
Enterprises (MSEs) and MSEs owned by Scheduled Caste (SC)/ Scheduled tribe (ST)
entrepreneurs, purchase preference as admissible/applicable from time to time under the existing
Govt. policy. Bidder to submit documentary evidence for the same duly certified by Statutory Auditor
of the bidder or a practicing Charted Account (not being an employee or a Director or not having any
interest in the Bidder’s company / firm) where audited accounts are not mandatory as per law.). In
this regard, item wise quantity may be splitted and the quoted price shall remain valid.
xiii. If various item rates are present in the RFQ and if there is correction/wrong entry or a difference
between the values entered in figures and in words, the following procedure shall be adopted for
evaluation.
i. When there is a difference between the rate in figures and in words for an item, the rate
which corresponds to the amount worked out by the Bidder for the item based on the
notional quantity specified, shall be taken as correct.
ii. When the rate quoted by the Bidder in figures and words tallies but the amount is incorrect,
the rate quoted by the Bidder shall be taken as correct.
iii. When it is not possible to ascertain the correct rate as detailed above, the rate quoted for
the item in words shall be adopted as the quoted rate.
iv. If the total amount written against an item does not correspond to the rate written in figures
and if the rate in words is missing, then the higher of the rates, i.e. higher of the rate worked
out by dividing the amount by the notional quantity and the rate quoted shall be considered
for evaluation In the event that such a bid is determined as the lowest bid, the lower of the
rates shall be considered for award of works.
Page 33 of 196
BPCL-KR
Job: A307
bids. Credit shall be taken during evaluation for 20% of Kerala VAT rate, 96% of Service Tax
rate and full amount for other Cenvatable taxes and duties.
(iv) Excise Duty, Central Sales Tax, Kerala VAT & Service Tax shall not be included in the
quoted prices and shall be payable extra at actuals. Further, the amount of Excise Duty,
Service Tax, Central Sales Tax, KVAT shall only be payable against submission of
supporting documents/Cenvatable/Vatable invoices subject to maximum amount quoted in
the offer and in case of non-submission, will not be paid.
(v) Non Cenvatable Excise Duty, if any is to be included in quoted prices & no variation on any
account (including statutory variation) shall be paid by Owner.
(vi) All New taxes/duties/cess/levies notified after the last date of submission of bid (final bid due
date) but within contractual delivery/ completion period, shall be to Owner’s account.
(vii) The bidder shall be required to furnish details of any special dispensation regarding
concessional/ exempted taxes/ duties.
“Price Reduction schedule for (Supply + Site work) shall be @ 0.5% of value of total order value
(TOV) of per week of delay or part thereof subject to maximum of 5% total order value (TOV)”.
Price Reduction Schedule (Supply + Site work) towards delay in delivery for foreign bidder shall be
applicable as per clause no. 17 of GPC Import of RFQ subject to following modification:
“Imports, for any delay in delivery of equipments / materials or part thereof beyond the delivery
date stipulated, the vendor shall be liable to pay, compensation at 0. 5% of the total FOB Value of
order per week of delay or part thereof subject to maximum of 5% of the total FOB Value of
order”.
iii. Wherever the supply period and site work are indicated as two separate periods and
notice of site readiness is required for site work, intervening period, if any shall be
excluded, while calculating the price schedule for delay.”
b) In case item involving supply and site work excluding comprehensive Insurance
policy:-
Performance Guarantee shall be as per clause 30 of GPC (For Indigenous materials &
equipments).
Page 34 of 196
BPCL-KR
Job: A307
b. In case item involving supply and site work Excluding comprehensive Insurance
policy:-
Performance Guarantee shall be as per clause 26 of GPC (For Foreign materials & equipments).
In cases like turnkey jobs, to derive the delivery period of supply items, the total period of turnkey
jobs shall be split into delivery period of supplies & site work period in the ratio of 70:30 for loading of
differential payment terms for the supply periods as defined above.
ii. Foreign suppliers shall not be permitted to offer differential payment terms as against the terms
specified in the RFQ/ GPC and in case they insist, their offer shall be rejected.
iii. Advance along with FOA/ PO will not be allowed. If a supplier insists for advance payment along
with FOA/PO, his offer shall be rejected.
Page 35 of 196
BPCL-KR
Job: A307
In case a Supplier does not accept the delayed delivery clause and/or takes any deviation (indicates
Penalty clause/Liquidated damages in place of Price Reduction Clause) or takes exception to the
percentage rate mentioned in GPC, the offer of such supplier(s) shall be loaded as under:
0.5% UDOV to 5%TOV : No loading
0.5% UDOV to 5% UDOV : 5%
0.5% UDOV to less than 5% TOV : Differential between the offered %age and 5%
Any other deviation/Liquidated : 5%
Damages/ penalty or non acceptance
of price reduction schedule
ii. For Supply + Site Work: [considering 0.5% total order value (TOV) ~ 5% total order value
(TOV)]
0.5% TOV to 5%TOV : No loading
0.5% UDOV to 5%TOV : 5% loading
0.5% TOV to less than 5% TOV : Differential between the Offered % and 5%
Any other deviation/Liquidated : 5%
Damages/ penalty or non acceptance
of price reduction schedule
15.0 PRICE VARIATION:
Suppliers must quote firm & fixed prices unless price variation is specified in the RFQ. Where price
variation is permitted as per RFQ, the loading thereto shall be as follows:
c) No ceiling on the formula specified (This 1.5 times the maximum ceiling specified by
loading other Suppliers. In case all other Suppliers
shall be done only after putting efforts with have quoted firm prices then @ 1.25% for
Supplier to indicate ceiling and obtaining every month of quoted delivery period to be
BPCL’s approval) taken as ceiling.
d) No formula and no ceiling specified by Offer may be rejected.
Supplier
(This shall be resorted to only after putting
efforts with Supplier and obtaining BPCL’s
approval)
19.0 UTILITIES:
Cost loading in respect of utilities etc. will be considered as mentioned in RFQ documents.
20.0 FOREIGN EXCHANGE RATE VARIATION/CUSTOM DUTY VARIATION FOR INDIAN BIDDERS
(ON BUILT-IN IMPORT CONTENT) :
i. Prices shall remain firm and fixed without any escalation except for statutory variation in customs
duty rate.
The prices shall be firm and fixed on account of FE variation also.
Page 36 of 196
BPCL-KR
Job: A307
ii. Indigenous bidders shall be required to quote their prices including customs duty (Merit rate)
towards their built in import content. CIF content in Indian Rupees shall also be furnished by
Bidders along with the merit rate of customs duty considered.
iii. The statutory variation in customs duty shall be subject to the following
guidelines and the supplier shall confirm the following in their bid:
(a) Maximum CIF value of import content shall be furnished in the bid.
(b) The material to be imported covering the above CIF value to be indicated in the bid.
(c) Any increase in price due to increase in customs duty rate beyond two-third of the quoted
delivery period will be to supplier’s account. However, any decrease in price due to
decrease in customs duty rate at the time of actual clearance of imported materials shall
be passed on to BPCL.
(d) Variation in price due to customs duty rate will be dealt with separately after receipt of
materials at site against documentary evidence.
Page 37 of 196
BPCL-KR
Job: A307
(i.) Any Suo-moto reduction in price offered by a supplier within the bid validity by way of discount or
revised prices subsequent to the bid due date and which is not as a result of any change in scope of
supply or terms and conditions, shall not be taken into account for evaluation. However, such
reduction in price shall be taken into account for ordering if such supplier happens to be the
recommended supplier as per the originally quoted prices.
(ii.) However, in the event of any suo-moto price increase sought by a supplier subsequent to the bid
due date and which is not as a result of any change in scope of supply or terms and conditions, the
bid of such a supplier shall be rejected for the items in which such suo-moto increase is made.
(iii.) Any wrong interpretation of taxes & duties or any taxes & duties not specified in the offer shall be
borne by Bidder.
25.0 PRICE IMPLICATION NOT PERMITTED:
Price implications on account of technical clarifications shall not be permitted as long as
BPCL/EIL do not change the specifications/ scope spelt out in the RFQ.
Page 38 of 196
BPCL-KR
Job: A307
29.0 NEW / ADDITIONAL TAXES & DUTIES (Applicable for Indian Bidder):
i. Within the contractual delivery period, if any new taxes and/or duties come into force the same will
be reimbursed to bidder against documentary evidence. However any new or additional taxes/
duties imposed after contractual delivery shall be to borne by seller.
ii. All necessary taxes & duties registration, if required for carrying out the site activities shall be done
by the bidder and cost towards the same shall be included in quoted prices.
iii. The statutory variations on Customs duty (rate) considered on above CIF value of built – in import
content, within contractual delivery period shall be to Employer’s account against submission of the
documentary evidence. However, any increase in the rate of Customs duty beyond the contractual
completion period shall be to bidder’s account. In case of wrong classification, no variation
including statutory variation of Customs Duty will be payable extra. Any decrease in the rate of
Customs duty shall be passed on to the Employer.
iv. The statutory variations on Excise rate and amount of Excise Duty, CST with concessional form &
VAT without concessional form, which will be payable on the finished goods and Cenvatable
Service Tax, as applicable, within the contractual delivery period shall be to Employer’s account
against submission of the documentary evidence. Any increase in the rate of these taxes and
duties beyond the contractual completion period shall be to bidder’s account. However, any
decrease in the rate of taxes & duties shall be passed on to the Employer.
v. Works Contract Tax & service tax on transportation, if applicable, shall be included in the quoted
prices and no variation including statutory variations shall be payable by BPCL.
Approval from any authority (i.e. Inspector of Boiler, Electrical Inspector, and Municipal Corporation
of Greater Kochi (MCGK) etc.) required as per statutory rules and regulations of Central/ State
Government shall be the responsibility of Contractor agency.
The application on behalf of the OWNER for submission to relevant authorities along with copies of
required certificate complete in all respects shall be prepared and submitted by the Contractor
agency well ahead of time so that the actual construction/ commissioning of the work is not delayed
for want of the approval/ inspection by concerned authorities. The Contractor agency shall arrange
the inspection of the works by the authorities and necessary coordination and liaison work in this
respect shall be the responsibility of the Contractor agency. Reimbursement by the OWNER of the
A307_SIB Rev.6 dt. 14.04.2014 Page 15 of 20
Page 39 of 196
BPCL-KR
Job: A307
statutory fees payable by Contractor agency (as per advance approval of OWNER) may be provided
for, subject to submission of receipt.
The Contractor agency shall carry out any change/ addition required to meet the requirements of the
statutory authorities, within the quoted rates. The inspection and acceptance of the work by statutory
authorities shall be the responsibility of the Contractor agency.
List of all documents, drawings, forms, affidavits etc required for the approvals shall be submitted by
the contractor agency.
35.0 LIEN:
Supplier shall ensure that the Scope of Supply supplied under the Agreement shall be free from any
claims of title/liens from any third party. In the event of such claims by any party, Supplier shall at
his own cost defend, indemnify and hold harmless Purchaser or its authorised representative from
such disputes of title/liens, costs, consequences etc.
37.0 GENERAL: Bidders shall submit their Bids in following manner & containing the listed inputs, duly
filled-in, stamped & signed by authorized signatory of Bidder holding Power of Attorney, as a
minimum requirement:
a) PART-I: UNPRICED OFFER
A. All technical specifications as per requirement of MR.
B. Agreed Terms & Conditions duly filled in.
C. Terms & Conditions for Supervision of Erection/Testing/Commissioning, if applicable
D. Terms & Conditions for Site Work, if applicable
E. Copy of Registration with EIL, if applicable
F. Copy of MOU/ MOM, if any, signed with EIL and referred in offer.
G. Integrity Pact, duly filled-in, stamped & signed on each page (if applicable).
H. Complete Audited Financial Report of latest preceding Financial year.
I. Deviation sheet, if any.
J. Price Schedule with prices blanked out but “Quoted/ Not quoted” to be mentioned & its
relevant enclosures, duly filled-in, stamped & signed on each page.
b) PART-II: PRICED OFFER
A. Price Schedule with prices filled in.
B. Statement that all specifications and terms & conditions are as per un-priced part of offer.
Note:
Bidding currency shall be Indian Rupees for supplies dispatched from India & and USD/EURO for
supplies dispatched from foreign.
Page 40 of 196
BPCL-KR
Job: A307
b) In case, the information/ document furnished by the Bidder/ Contractor forming basis of
evaluation of his bid is found to be false/ forged after the award of the contract, Owner shall
have full right to terminate the contract and get the remaining job executed at the risk & cost of
such Bidder/ Contractor without any prejudice to other rights available to Owner under the
contract such as forfeiture of CPBG/ Security Deposit, withholding of payment etc.
c) In case, this issue of submission of false documents comes to the notice after execution of
work, Owner shall have full right to forfeit any amount due to the Bidder/ Contractor along with
forfeiture of CPBG/ Security Deposit furnished by the bidder/ contractor.
d) Further, such bidder/ contractor shall be put on Blacklist/ Holiday/ Negative List of OWNER/EIL
debarring them from future business with Owner & EIL for a time period, as per the prevailing
policy of OWNER & EIL.
b) In the event of submission of any document/ certificate by the Bidder in a language other than
English, the English translation of the same duly authenticated by Chamber of Commerce of
Bidder’s country shall be submitted by the Bidder. Metric measurement system shall be
applied.
41.0 EARNEST MONEY DEPOSIT:
Bidder shall furnish, as part of its Bid, EMD for an amount as indicated in the NIT/ IFB. If the
Bidder is unable to submit Bid Document Fee & EMD in original within the due date & time, then
bidder shall submit the original Bid Document Fee & EMD within 7 days from the date of unpriced
bid opening, provided copy of the same have been uploaded on E-Tendering Website. In case
the bidder fails to submit the same in original within 7 days, then their bid shall be rejected,
irrespective of their status/ ranking in tender and notwithstanding the fact that a copy of Bid
Document Fee & EMD was earlier uploaded by the bidder. OWNER shall not pay any interest on
EMD furnished.
The EMD shall be in favour of BPCL and shall be acceptable in the form of Crossed Demand Draft
or Bank Guarantee in the prescribed pro-forma.
The Bank Guarantees/DD for EMD shall be issued by any Scheduled Commercial Bank (other than
co-operative Bank) in India or any Indian Branch of Foreign Bank and same shall be as per the
format given in this bidding document. Swift Message or Cash or Cheque in lieu EMD shall not be
acceptable.
The bank guarantee for submission of EMD shall be valid as period mentioned in EMD / Bid
Security format or elsewhere mentioned in Bid Document / RFQ.
EMD/ Bid securities of unsuccessful bidders will be returned upon award of Contract. However,
EMD of the successful Bidder will be returned upon the Bidder's acceptance of PO/ signing the
Contract and furnishing the PBG.
The EMD may be forfeited:
If a Bidder withdraws its bid during the period of Bid Validity or does any breach of
tendering terms and conditions, or
In case of a successful Bidder, if the Bidder fails, within the specified period:
i. To submit the order acceptance.
ii. To furnish the PBG.
Page 41 of 196
BPCL-KR
Job: A307
Page 42 of 196
BPCL-KR
Job: A307
I. The parent company shall issue an authorization from the authorized signatory like CEO, CFO, CS
to confirm their authorization to the subsidiary to manufacture & supply the equipments.
II. The parent company shall furnish a back-up guarantee duly signed by above signatory for the
performance of the equipment.
III. The order shall be placed on Indian subsidiary and the payment shall be released to Indian
subsidiary.
IV. Indian subsidiary shall be a manufacturing company in the same product & not a liaison /
representative office.
V. Bidder to submit bipartite agreement between parent & subsidiary to ensure experience &
compliance to contract.
VI. All critical components / parts to be supplied by parent company only which is enlisted with EIL.
Page 43 of 196
BPCL-KR
Job: A307
ANNEXURE-A
INTEGRATED REFINERY EXPANSION PROJECT (IREP) OF
M/s BPCL KOCHI REFINERY, KOCHI, KERALA (INDIA)
(Job No. A307)
TERMS & CONDITIONS FOR INDIAN SOURCED COMPONENTS / SERVICES BY FOREIGN
BIDDER
Foreign bidder may source components / sub-supplies and services from India, if allowed as per Material
Requisition. Such sub-supplies / services shall be subject to following Commercial Terms & Conditions:
1. PRICING:
1.1 The Foreign bidder shall quote firm price for items being sourced from India in Indian rupees on FOT
Site basis inclusive of packing, forwarding, transportation, all applicable taxes, duties & levies payable
upto site.
1.2 Materials if ordered against this Bidding Document are required to be dispatched on door delivery basis
through a reliable bank approved Road Transport Company unless the transport company is named by
the Owner.
2. AWARD OF ORDER:
Client will place single order for Main Supplies/ Services including Indian source supplies/ Services
with single point responsibility taken care by foreign (principal) bidder. However obligation of
Performance Bank Guarantee & Price Reduction Schedule for complete package shall always be in
scope of foreign (principal) Bidder.
3. DELIVERY:
The delivery period for items being sourced from India, shall be on FOT site basis within the delivery
period specified for foreign bidder as per Terms of Bidding document.
5. OVERALL RESPONSIBILTY:
Overall responsibility towards the contractual obligations like delivery, bid security, order execution,
performance guarantee etc. including supplies being sourced from India shall be only with the
foreign (principal) bidder.
7. INSPECTION
i. Inspection of Item being sourced from India shall be by EIL/Owner.
ii. Any change in sourcing from indigenous supplies to imported supplies and vice-versa after bid
submission is not permitted.
iii. Considering EIL Inspection charges, during evaluation prices of Indigenous source item shall be
loaded by @1.25% of FOT Despatch Point Price price.
8. PAYMENT TERMS:
8.1 Indian Sourced supplies:
100% payment along with taxes and duties will be paid against receipt & acceptance of Indian sourced
goods/material at project site and on presentation of invoice suitable for availing Cenvat.
8.2 Payment of Indian source supplies/Services shall be released directly to Indian counterpart against
Invoices raised by Indian counterpart duly endorsed by Foreign principal for payment.
8.3 The payments shall be made after Adjustment of Price Reduction Schedule.
9. In case of any deviation to above requirement, loading shall be applicable as mentioned for Indian
Bidder.
Page 44 of 196
Page 45 of 196
Page 46 of 196
Page 47 of 196
Page 48 of 196
Page 49 of 196
Page 50 of 196
Page 51 of 196
Page 52 of 196
Sham
PatroleUI"
INDEX
1. NON-WAIVER
ADDRESSES
ARBITRATION
TECHNICAL
VENDOR'S
DELAYED
DELAYS
OILS
SPARE
PACKING
SHIPPING
RESPECT
CANCELLATION
PART
RECOVERY
MODIFICATIONS
INSPECTION-CHECKING-
PRICE
CONFIRMATION
COMPLETE
PATENTS
EXPEDITING
NO ASSIGNMENT
&ORDER/REPEAT
TRANSITLUBRICANTS
PARTS
DUE
AND
DELIVERY
DEFINITIONS
TERMS
SHIPMENT
SERVICES
WEIGHTS
SALES
IMPORT
PERFORMANCE
REFERENCE FOR
DRAWINGS
AGREEMENT
OF
INFORMATION
TO
MARKING
ROYALTIES
CONDITIONS
OF
LICENCE
REJECTION,RISK
AND
OF
AND DELIVERY
SUMS
PAYMENT
FOR OF
FORCE
ORDER
VENDOR'SDUE
ORDER
AND
INSURANCE
MEASURES
SHIPMENTMAJEURE
TESTING
GUARANTEE
REMOVAL DATES
DOCUMENTATION
OFPERSONNEL
NOTICES
REJECTED 19.
34.
33.
30.
31.
32. DATA REQUIREMENT
GOODS AND REPLACEMENT 25.
28.
20.
24.
27.
26.
21.
23.
29.
22.
-1-
Page 53 of 196 •
1. DEFINITIONS: 7.1 All tests mechanical and others and particularly
The following expressions used in the purchase order those required by relevant codes will be performed
shall have meaning indicated against each of these; at the Vendor's expenses and in accordance with
inspector's instructions. The vendor will also bear
The OWNER means BHARAT PETROLEUM
the expenses.
CORPORATION LIMITED a company incorporated in
India having its registered office at Mumbai. India and 7.2 Concerning preparation and rendering of tests
shall include its successors and assigns. required by Boiler Inspector~te or such other
"GoodslMaterials" : Goods and/or materials shall mean statutory testing agencies or by L10yds register of
shipping as may be required.
any of the articles, materials, machinery, equipment,
supplies drawings, data and other property and all 7.3 Before shipping or despatch, the equipment and/
services Including but not limited to assigning, delivery, or materials will have to be checked and stamped
Installation, Inspection. testing and commissioning by Inspectors who are authorised also to forbid
specified or required to complete the order. the use and despatch of any equipment and/or
materials which during tests and inspection fail to
·Vendor" : Vendor shall mean the person, firm or
comply with the specification. codes and testing
corporation to whom this purchase order is issued, and
requirements.
include its successors and assigns.
7.4 The Vendor will have to-
"Inspectors" : Inspectors deputed by Owner.
2. REFERENCE FOR DOCUMENTATION: Inform Owner at least fifteen days in advance of
the exact place date and time of rendering the
Purchase order Number must appear on all equipment or materials for required Inspection.
correspondence, drawings, invoices, shipping notes,
Provide free access to inspectors during normal
packing and on any documents or papers connected
working hours to Vendors or his /lts sub-Vendor's
with the order.
work and place at their disposal all useful means
3. IMPORT LICENCE: of performing, checking, marklhg testing,
Relevant particulars of the import licence if any shall be inspection and final stamping.
duly indicated in the invoice and shipping documents Even if the inspection and tests are fully carried
as well as on the packages or consignments. out Vendor is not absolved to any degree of his
4. CONFIRMATION OF ORDER: responsibilities to ensure that all equipments and
The vendor shall acknowledge the receipt of the materials supplied comply strictly with
Purchase order within ten days following the mailing of requirements as per agreement both during
this order and shall thereby confirm his acceptance of requirements as per agreements both during
this Purchase Order in its entirety without exceptions. construction, at the time of delivery, inspection on
This acknowledgment will be on both purchase order arrival at site and after Its erection or start-up and
and General Purchase Conditions. Vendor shall also guarantee period as stipulated In clause 26 hereof.
submit along with order acceptance a Bank Guarantee 7.5The Vendor's responsibility will not be lessened to
as per clause 26 hereunder. any degree due to any comments made by Owner/
6. SALES CONDITIONS: Owner's representatives and inspectors on the
Vendor's drawings or specifications or by
With Vendor acceptance of provisions of this Purchase
inspectors witnessing any chemical or physical
Order he waives and considers as cancelled any of his
tests. In any case the equipment must be in strict
general sales conditions. accordance with the Purchase Order and or its
6. COMPLETE AGREEMENT: attachments failing which the Owner shall have the
The terms and conditions of this Purchase Order right to reject the goods and hold the Vendor liable
constitute the entire agreement between the parties for non-performance of contract.
thereto. Changes will be binding only if the amendments 8. EXPEDITING:
are made in writing and signed by an authorised
Owner/Owner's representatives have been assigned to
representative of the Owner and the Vendor.
expedite both manufacture and shipment of equipment
7. INSPECTION-CHECKING-TERMS: and materials covered by the Purchase Order. The
The equipment, materials and workmanship covered by Owner/Owner's representatives shall have free access
the Purchase Order is subject to inspection and testing to Vendor's shop and/or sub supplier's shop at any time
at any time prior to shipment and/or despatch and to and they shall provide all necessary assistance and
final Inspection within a reasonable time after arrival at Information to help them perform their job.
site. Inspectors shall have the right to carry out the 9. WEIGHTS AND MEASUREMENTS:
Inspections and testing which will Include the raw
The shipping documents, invoices, packing lists and all
materials at manufacturer's shop, at fabricator's shop other relevant documents shall contain the same units
and at the time of actual despatch before and after
of weight and measurements as given in the Owner's
completion of packing. Purchase Order.
-2-
Page 54 of 196 •
10. OILS & LUBRICANTS: CARE GLASS FRAGilE, DON'T ROLL. THIS END UP.
The first filling of oils and lubricants for every equipment THIS END DOWN.· to be indicated by arrow.
shall be included In the price. The vendor shall also A distinct colour splash in say red-black around each
recommend for quality and quantity of oils and lubricants package crate/bundle shall be given for identification.
required for one year's continuous operation. Ail pipes and sheets shall be marked with strips bearing
11. SPARE PARTS: progressive No.
The vendor must furnish itemised and priced list of spare In case of bundles, the shipping marks shall be
parts required for two years operation of the equipment. embossed on metal or similar tag and wired securely
The vendor shall provide the necessary cross sectional on each end.
drawing to Identify the spare parts numbers and their For bulk uniform material when packed in several cases,
location as well as inter-changeability chart. progressive serial numbers shall be indicated on each
12. PACKING AND MARKING: cases. All nozzles, holes and opening and also all
delicate surfaces shall be carefully protected against
All equipment/materials shall be suitably packed in
damage and bad weather. Flange faces of all nozzles
weather proof, seaworthy packing for ocean transport
shall be protected by blanks. All manufactured surfaces
under tropical conditions and for rail or road or other
shall be painted with rust proof paint.
appropriate transport in India. The packing shall be
strong and efficient enough to ensure safe preservance All threaded fittings shall be packed in cases.
upto the final point of destination. The vendor shall be held liable for all damages or
Equipment / Materials shall be protected by suitable breakages to the goods due to defective or Insufficient
coat of paint and all bright parts protected from rust by packing as well as for corrosion due to insufficient
application of rust preventive as may be necessary. All greasing/ protection.
machined surface shall be suitably protected. On three sides of the packages, the following marks
All fragile and all exposed parts will be packed with care shall appear clearly visible in indeliable paint and on
and the packages shall bear the words -HANDLE WITH Vendor's care and expense.
To:
Chief Manager (Projects)
Bharat Petroleum Corporation Ltd.
Koehl Refinery, Ambalamugal
Kochi - 682 302
Item:
Equipment:
NetWeight: Kgs.
Dimensions:
-3-
Page 55 of 196 •
l!!RI§.;. MarKIngshall be bold-minimum letter height 5cm. charges, if any, surcharge, discount, etc. cleal
for every order and every shipment, packages must be and separately and the net total freight payab
marked with serial progressive numbering. All packages shown at the bottom.
will bear warning signs on the outside denoting the All documents vlz. bill of lading/airway bi,
center of gravity and sling marks. Packages that require Invoices/packing list, freight memos, country 4
special handing and transport should have their centres origin certificates, test certificate, drawings an
of gravity and points at which they may be gripped catalogues should be in English language.
clearly indicated and marked -Attention Special Load
In addition to the bill of lading which should b
Handle with Care" In English Language. Any other
obtained In 3 stamped original plus as many copiei
direction for handling shall be clearly indicated on the
as required, Invoices packing lists, freight memos
package.
(If the freight particulars are not shown In the billl
Top heavy containers will be so marked either Top of lading), country of origin certificate, test
Heavy or Heavy Ends. When packing material is clean composition certificate, shall be made out agains',
and light coloured, a dark black stencil paint shall be each shipment in as many number of copies as
acceptable. However, where packaging material is shown below. The bill of lading, invoice and
soiled or dark, a coat of flat zinc white paint shall be packing list specifically must show uniformly, the
applied and allowed to dry before applying the specific marks and numbers, contents case wise country
markings. of origin, consignees name, port of destination and
In case of large equipments like vessels, heat all other particulars as indicated under clause 12.
exchangers, etc. documents contained in the envelope The invoice must show the unit rates and net total
shall be fastened Inside a shell connection with an EO.B. prices. Items packed separately should also
identifying arrow sign -documents" applied with Indelible be Invoiced and the value shown accordingly.
paint. Packing list must show apart from other particulars
13. SHIPMENT AND SHIPMENT NOTICES: actual contents in each case, net and gross
weights and dimensions, and the total number of
The Vendor shall make shipment only after prior
packages. All documents should be duly signed
approval of Inspector whenever specifically mentioned.
by the Vendor's authorised representatives.
As soon as any shipment is made, the Foreign Supplier
shall send advance information by way of Fax message Shipping arrangements shall be made by
to Chief Manager (Projects), Bharat Petroleum Chartering Wing Ministry of Surface Transport,
Corporation Ltd., Koehl Refinery, Ambalamugal, Kochi- New Delhi through their respective forwarding
682 302 giving particulars of the shipment, vessel's agents, M/s. Schenker & Co., P.O. Box 110313
name, port of shipment, bill of lading number and date, 02043 Hamburg West Germany, Ph. 49 (040)
total FOB and freight value with confirmation copies by 361350, Fax (040) 36135216 Gr.2/a, Telex
post to the owner, Bharat Petroleum Corporation 217004-33 Sh.d, for shipping consignments from
Limited, Koehl Refinery, Ambalamugal, Kochi -682 302 UK / continent port; M/s. OPT Overseas Project
In case of air shipment a copy each of airway bill & Transport Inc. 46 sellers Street, kearny, N.J.
Invoice shall be sent by fax to BPCL as soon as 07032, Tel (201) 998-7771, Telex 673-3586, Fax
shipment is made. (201 )998-7833. In respect of consignments form
US/CANADA, MEXICO & SOUTH AMERICA and
14 SHIPPING:
the Embassy of India in Japan, Tokyo in respect
14.1 SEA SHIPMENT: of consignments from Japaneses ports. Supplier
All shipment of materials shall be made by first shall furnish to the respective agents the full details
class direct vessels, through the chartering wing, of consignments such as outside dimensions,
Ministry of Surface Transport Govt, of India, New weights (both gross and net) No. of packages,
Delhi as per procedure detailed hereunder. The technical descriptions and drawings, name ofthe
Foreign supplier shall arrange with Vessels Supplier, ports of loading, etc. 6 weeks notice shall
Owners or Forwarding Agents for proper storage be given by the supplier to enable the concerned
of the entire Cargo intended for the project in a agency to arrange shipping space.
specific manner so as to facilitate and to avoid The bill of lading Shall Indicate the following:
any over carriage at the port of discharge. All
Shipper: Government of India
shipment shall be under deck unless carriage on
deck is unavoidable. Consignee:
Bharat Petroleum Corporation Ltd.-
The bills of lading should be made out in favour of
Koehi Refinery,
Bharat Petroleum Corporation Ltd.,
Ambalamugal,
All columns in the body of the bill of lading namely Kochl - 682 302.
marks and nos. material description, weight
In case of supplies from USA, Export licences, if
particulars, etc. should be uniform in all the
any required from the American Authorities shall
shipping documents. The freight particulars should
be obtained by the U.S. suppliers. If need be
mention the basis of freight tonnage, heavy lift
-4-
•
Page 56 of 196
assistance for obtaining such export licences their delivery. By time delivery, is meant the date on the
would be available from India supply Mission at Bill of lading/Air way Bill at FOB port of despatch.
Washington. 17. DELAYED DELIVERY:
14.2 AIRSHIPMENT:
The time and date of delivery of materials/equipment
In case of Airshipment, the material shall be as stipulated in the Purchase Order shall be deemed
shipped through freight consolidator (approved by to be the essence of the agreement. For any delay in
us). The airway bill shall be made out in favour of delivery of equipment materials or part thereof beyond
BHARAT PETROLEUM CORPORATION LTD, the delivery date stipulated, the vendor shall be liable
Kochi Refinery, Ambalamugal, Kochi - 682 302 to pay compensation at O. 5% per week or part thereof
Tel: 91-484-2722061-69, Fax: 91-484- 2721094/ the FOB Port of embarkation value of the non-delivered
2720855/56. items of equipment subject to maximum of 5% of the
14.3 TRANSMISSION OF SHIPPING DOCUMENTS: total FOB value. The Owner reserves the right of
cancelling the Purchase Order for any delay exceeding
Foreign supplier shall obtain the shipping
the period of maximum compensation and the vendor
documents in eleven complete sets including three
shall be liable to all consequences thereof. If the delay
original stamped copies of the Bill of lading/Airway
in delivery is due to Force Majeure, the owner shall be
Bill as quickly as possible is made, and airmail as
free to act in terms under clause 18 of this text.
shown below so that they are received at least
three weeks before the Vessels' arrival in case of 18. DELAYS DUE TO FORCE MAJEURE:
sea shipment and immediately on air freighting in In the event of causes of Force Majeure occuring within,
case of air-shipment. Foreign supplier shall be fully the contractual date of delivery the Owner on receipt of
responsible for any delay and/or demurrage in application from the Vendor may extend the contractual
clearance of the consignment at the port due to date of delivery without imposition of penalty. Only those
delay in transmittal of the shipping documents. causes which depend on natural calamities, civil wars
If in terms of latter of otherwise, the complete and national strikes which have a duration of more than
original set of documents are required to be sent seven consecutive calendar days are considered the
to BPCL through Bank the distribution indicated causes of force majeure. The decision of Owner shall
below will confine to copies of documents only be final and binding on Vendor.
minus originals. The Vendor must advise the Owner by a Registered
Documents letter duly certified by a local chamber of statutory
BPCL, Kochi Refinery
authorities, the beginning and the end of the delay
Bill of lading/ 4 (including 1 immediately, but in no case later than within 10 days of
Airway Bill original) the beginning and end of such cause of Force Majeure
Invoice 4 condition as defined above.
Packing List 4 19. REJECTION, REMOVAL OF REJECTED GOODS
Freight Memo 4 AND REPLACEMENT:
Country of Origin-
Certificate 4 In case the testing and inspection at any stage of
4 inspection reveal that the equipment, materials and
Drawing
1 workmanship do not comply with the specification and
Catalogue
Invoice ofthird 4 requirements, the same shall be removed by the Vendor
at his/its own expense and risk within the time allowed
Party/Lloyd for
by the Owner. The Owner shall be at liberty to dispose
Inspection charges,
of such rejected goods in such a manner as he may
wherever applicable.
think appropriate. In the event the Vendor fails to remove
15. TRANSIT RISK INSURANCE:
the rejected goods within the period as aforesaid, all
Insurance against all marine and transit risk on FOB to expenses incurred by the Owner for such disposal shall
warehouse basis shall be covered under the owner's be to the account of the Vendor. The freight paid by the
marine policy. However, the Vendor shall ensure the in Owner, if any, on the inward joumey of the rejected
effecting shipments clear bills of lading/airway bills are materials shall be reimbursed by the vendor to the
obtained and the carriers responsibility is fully retained Owner before the rejected materials are removed by
the carriers so that the consignee's interests are fully the Vendor. The Vendor will have to proceed with the
secured and are in no way jeopardized. replacement of that equipment without claiming any
16. RESPECT FOR DELIVERY DATES: extra payment if so required by the Owner. The time
taken for replacement in such event will not be added
Time of delivery mentioned in the Purchase Order shall
to the contractual delivery period.
be the essence of the agreement and no variation shall
be permitted except with prior authorisation in writing 20. PRICE:
from the Owner. Goods should be delivered securely Unless otherwise agreed to in the terms of the Purchase
packed and in good order and condition at the place Order, the price shall be :
and within the time specified in the Purchase Order for
-5-
Page 57 of 196 •
Firm and not subject to escalation for any reason equipment and/or materials or which can, in any way.
whatsoever even though It might be necessary for the 26. PERFORMANCE GUARANTEE:
order execution to take longer than the delivery period
The Vendor shall guarantee that any and all materials
specified in the order. used in execution of the Purchase Order shall in strict
21. TERMS OF PAYMENT: compliance with characteristics, requirements and
Payment will be made by the Owner against submission specifications and that the same shall be free from any
of despatch documents by Cash Against Documents/ defects. Checking of the Vendor's drawings by the
Letter of Credit. Owner/Owner's representatives and their approval and
22. RECOVERY OF SUMS DUE: permission to ship or despatch the equipment and
materials granted by Inspectors shall not relieve the
Whenever any claim against the Vendor for payment
Vendor from any part of hlsllts responsibilities for proper
of a sum of money arises out of or under the contract,
fulfillment of the requirements. The Vendor will
the Owner shall be entitled to recover such sums from
guarantee that all materials and equlpments shall be
any sum them due or when at any time thereafter may
repaired or replaced as the case may be at site, at its
become due from the Vendor under this or any other
contract with the Owner and should this sum be not own expense, in case the same have been found to be
defective in respect of material, workmanship or smooth
sufficient to cover the recoverable amount, the vendor
and rated operation within a period of twelve months
shall pay to the Owner on demand the balance after the same have been Commissioned or 18 months
remaining due.
from despatch whichever is earlier.
23. MODIFICATIONS:
The guarantee period for the part that may be altered,
The Owner shall have the right to make technical repaired or replaced shall be 12 months from the date
changes or modifications in the technical documents/ on which the same is commissioned.
specifications. Any major changes or modifications shall
Acceptance by the Owner or Its inspectors of any
be at the cost, if any, of the Owner. As soon as possible
equipment and materials or its replacement will not
after receipt of the written request for changes the
relieve the Vendor of its responsibility of supplying the
vendor shall furnish in writing to the owner an estimate
equipment/materials strictly according to the guarantee
of cost for such major changes and modifications and
agreed by the Vendor. The Vendor shall furnish a Bank
its effect on the FOB delivery date. On receipt of
Guarantee along with the order acceptance for the
Owner's written authorisation, the Vendor shall promptly
amount equivalent to 10% of the F.O.B. value of
proceed with the changes/modifications.
equipment/ materials to support Vendor's performance
24. CANCELLATION: (as per proforma hereunder). This Bank Guarantee shall
The owner reserves the right to cancel this Purchase remain in force for the entire period covered by the
Order or any part thereof and shall be entitled to rescind performance guarantee. It will be the responsibility of
the contract wholly or in part In a written notice to the the Vendor to keep the Bank Guarantee fully
Vendor if: subscribed. Any shortfall in the value of the Bank
The Vendor fails to comply with the terms of this Guarantee as a result of encashment by the owner
Purchase Order. either in full or in part in terms of the performance
Guarantee shall be made good by the Vendor within
The Vendor fails to deliver the goods on time and/or one week thereof.
replace the rejected goods promptly:
27. NON-WAIVER:
The Vendor makes a general assignment for the benefit
of creditors; and Failure of the Owner/Owner's representatives to insist
upon any of the terms or conditions incorporated in the
A receiver is appointed for any of the property owned
Purchase Order or failure or delay to exercise any rights
by the Vendor.
or remedies specified herein or by law or failure to
Upon receipt of the said cancellation notice, the Vendor properly notify Vendor in the event of breach, or the
shall discontinue all work on the Purchase Order and acceptance of payment of any goods hereunder or
matters connected with it. approval of design shall not release the Vendor and
The owner in that event will be entitled to procure the shall not be deemed waiver of any right of the Owner
requirement in the open market and recover excess or Owner's representatives to Insist upon the strict
payment over the Vendor reserving to Itself the right to performance thereof or any of his or their rights or
forfeit the security deposit, if any, placed by the Vendor remedies as to any such goods regardless of when
against the contract. goods are shipped, received or accepted nor shall any
25. PATENTS AND ROYALTIES: purported modification or revision ofthe order by Owner/
Owner's representative act as waiver of the terms
On acceptance of this order, the Vendor will be deemed hereof.
to have entirely indemnified the Owner's representatives
from any legal action or claims regarding compensation 28. NO ASSIGNMENT:
for breach of patent rights which the Vendor deems The purchase Order shall not be assigned to any other
necessary to comply for manufacturing the orclefed agency by the Vendor without obtaining prIor-written
-6-
Page 58 of 196 •
consent of the Owner. maintenance of the equipment if required by the Owner.
29. VENDOR'S DRAWINGS AND DATA REQUIREMENT: The terms and conditions for the services of the
Vendor's personnel shall be indicated in the quotation
The Vendor shall submit drawings data and itself.
documentation in accordance with but not limited to
32. ARBITRATION:
what is specified in the bid document and lor In Vendor's
drawings and data form attached to the Purchase Order Any dispute or difference between the Vendor on one
and as called for in clause 8, vlz, 'Expediting' above. hand and the Owner on the other. of any kind
The types, quantities and time limits of submitting this whatsoever at any time or times, arising out of or in
must be respected in its entirety failing which the connection with or incidental to the Purchase Order
purchase Order shall not be deemed to have been including any dispute or difference regarding the
executed for all purposes including settlement of interpretation of the terms and conditions or any clause
payment since the said submission is an integral part thereof shall be referred to arbitration under the Rules
of purchase Order execution. of International Chamber of Commerce in Paris. The
30. TECHNICAL INFORMATION: venue of such arbitration shall be in India. The Indian
law shall apply.
Drawings, specifications & details shall be the property
of the Owner and shall be returned by the Vendor on 33. PART ORDER I REPEAT ORDER:
demand. The Vendor shall not make use of drawings Vendor shall agree to accept part order at owner's
and specifications for any purpose at any time save option without any limitations whatsoever and also
and except for the purposes of the Owner. The Vendor accept repeat order during a period of six months after
shall not disclose the technical Information furnished placement of purchase order at the same unit prices
or gained by the Vendor to any person, firm or body or terms and conditions.
corporate authority and shall make all endeavours to 34. ADDRESS:
ensure that the technical Information is kept
Bharat Petroleum Corporation Ltd.
CONFIDENTIAL. The technical information imparted
and supplied to the Vendor by the Owner shall at all Kochi Refinery
times remain the absolute property ofthe Owner. Ambalamugal
31. SERVICES OF VENDOR'S PERSONNEL: Kochi - 682 302
Upon two weeks advance notice, the Vendor shall INDIA
depute the necessary personnel to India for supervision Tel: 91-484-2722061-69
of erection and start up of the equipment and train a Fax: 91-484-2721094/2720855/56
few of the Owner's personnel for the operation and
-7-
Page 59 of 196 •
PROFORMA OF BANK GUARANTEE
( Performance )
(Ref. clause 26)
To
Bharat Petroleum Corporation Limited
Koehl Refinery, Ambalamugal, Kerala- 682302
Dear Sir,
In consideration of the Bharat Petroleum Corporation Limited (hereinafter called 8the Company8 which expression shall
include its suceessorsand assigns) having awarded to MIs. (Name) (address)
..................................................•....................................................................................................................... (hereinafter
referred to as ~he Supplier- which expression wherever the subject or context so permits Include Its successors and assigns) a
supply contract In terms Interalia, of the Company's Purchase Order No dated and the
General Purchase Conditions of the company and upon the condition of supplier's fumishing security for the Performance of the
supplier's obligation and/or discharge of the supplier's liability under and/or In connection with the said supply contract up to a
sum of (in figure) (in words) .
................ ) contract value.
we, (Name) (constitution) ; (hereinafter called
8the Bank8 which expression shall include its successors and assigns) hereby jointly and severally undertake the guarantee to
pay to the Company In (Currency) forthwith on demand in writing and without protest or demur of any and all moneys anywise
payable by the Supplier to the Company under in respect of or in connection with the said supply contract inclusive of all the
Company's losses and damages and costs, (Inclusive between attorney and client), charges and expenses and other moneys
anywise payable In respect to the above as specified in any notice of demand made by the Company to the Bank with reference
to this Guarantee up to aggregate limit of Rs (Rupees .
.. ... . ... .. . .. .... .. . ... .. ... ... ... ... .... ..only)
AND the Bank hereby agrees with company that:
This Guarantee / Undertaking shall be a continuing / undertaking and shall remain valid and irrevocable for all claims of the
Company and liabilities of the Supplier arising up to and until midnight of .
This date shall be 6 months from the last date of guarantee period
This Guarantee / Undertaking shall be in addition to any other guarantee or security whatsoever that the company may now or at
any time anywise have in relation to the Supplier's obligationslliabilities under and/or connection with the said supply contract,
and the Company shall have full authority to take recourse to or reinforce this security in preference to the other securlty(ies) at
its sole discretion, and failure on the part of the Company in enforcing or requiring enforcement of any other security shall have
the effect of releasing the Bank from its liability hereunder.
The company shall be at liberty without reference to the bank and without affecting the full liability of the Bank hereunder to take
any other security in respect of the Supplier's obligations and/or liabilities under or In connection with the said supply contract
and to vary the terms vis a vis the supplier of the said supply contract or to grant time and/or Indulgence to the supplier or to
reduce or to Increase or otherwise vary the prices of the total contract value or and/or the remedies of the company under any
other security (Ies) now or hereafter held by the company and no such dealing(s), varlation(s), reduction(s), Increase(s) or the
indulgence(s) or arrangement(s) with the supplier or release or forbearance whatsoever shall have the effect of releasing the
Bank from its full liability to the Company hereunder or of prejudicing rights of the Company, against the Bank.
The Guarantee / Undertaking shall not be determined or affected by the liquidation or winding up, dissolution or change of
constitution or insolvency of the supplier but shall in all respects and for all purposes be binding and operative until payment of all
moneys payable to the Company in terms hereof.
The Bank hereby waives all rights at any time inconsistent with the terms of its Guarantee / Undertaking and the obligations of the
Bank in terms hereof shall not be anywise affected or suspended by reason of any dispute or disputes having been raised by the
supplier (whether or not pending before any Arbitrator, office, Tribunal or Court) or any denial of liability by the supplier or any
other of communication whatsoever by the supplier stopping or preventing or purporting to stop or prevent any payment by the
Bank to the Company in terms hereof.
The amount stated in any notice of demand addressed by the Company to the Guarantor as liable to be paid to the Company by
the supplier or as suffered or incurred by the Company on account of any losses or damages of costs, charges and or expenses
shall as between the Bank and the company be conclusive of the amount so liable to be paid to the Company or suffered or
incurred by the Company, as the case may be and payable by the Guarantor to Company in terms hereof.
Yours faithfully,
-8-
Page 60 of 196 •
Job No. : A307
BPCL-KR - IREP
All raw/solid wood packaging material used for packaging shall be appropriately treated and marked as
per ISPM-15 (International Standards of Phyto-sanitary measures 15) OR shall be accompanied by a
Phytosanitary Certificate with the treatment endorsed.
The treatment of raw/solid wood packaging material prior to export shall include either Methyl Bromide
(MB) @ 48 g/m3 for 16 hrs at 21º C and above or any equivalent thereof or heat treatment (HT) at 56º
C for 30 min (core temperature of wood) or Kiln Drying (KD) or Chemical Pressure Impregnation (CPI)
or any other treatments provided that these meet the HT specifications of the ISPM-15.
However, the above conditions shall not be applicable to wood packaging material wholly made of
processed wood products such as ply wood, particle board, oriental strand board of veneer that have
been created using glue, heat and pressure or combination thereof. The above conditions shall also
not be applicable to wood packaging material such as veneer peeler cores, wood wool & shavings and
thin wood pieces (less than 6mm thickness) unless they are found to be harboring any pests.
SPR-Foreign Page 1 of 1
Page 61 of 196
Tax Residency Certificate (TRC) Format for Foreign Bidder
Note:-
1. Tax Residency Certificate (TRC) containing above details is compulsory for claiming tax
relief under Double Taxation Avoidance Agreement (DTAA) in respect of foreign
remittances.
2. TRC containing the details as above shall be verified by the Govt of the country or the
specified territory of which the contractor/ Licensor (ie, assessee) claims to be a resident
for the purpose of tax.
3. Bidder must submit TRC containing the details as above along with invoice for the
purpose of effecting payment. Please be noted that non furnishing of TRC will delay
the payment to non – residents.
Page 62 of 196
PROFORMA OF BANK GUARANTEE
( Performance )
(Ref. clause 26)
To
Bharat Petroleum Corporation Limited
Kochi Refinery, Ambalamugal, Kerala- 682 302
Dear Sir,
In consideration of the Bharat Petroleum Corporation Limited (hereinafter called “the
Company” which expression shall
include its successors and assigns) having awarded to M/s.
(Name)…................................... ………………………………..(address)
…………………………………............ ................................................. ...................
................................................... (hereinafter
referred to as “The Supplier” which expression wherever the subject or context so
permits include its successors and assigns) a supply contract in terms interalia, of the
Company’s Purchase Order No………………………dated……………………… and the
General Purchase Conditions of the company and upon the condition of supplier’s
furnishing security for the Performance of the supplier’s obligation and/or discharge of
the supplier’s liability under and/or in connection with the said supply contract up to a
sum of (in figure)…………........................…. (in words)
..........................................................................................
........................................................................
……………..............................................………) contract value.
We,
(Name)………...........................……………………(constitution)………………....................
.......….. (hereinafter called “the Bank” which expression shall include its successors and
assigns) hereby jointly and severally undertake the guarantee to pay to the Company in
(Currency) forthwith on demand in writing and without protest or demur of any and all
moneys anywise payable by the Supplier to the Company under in respect of or in
connection with the said supply contract inclusive of all the Company’s losses and
damages and costs, (inclusive between attorney and client), charges and expenses and
other moneys anywise payable in respect to the above as specified in any notice of
demand made by the Company to the Bank with reference to this Guarantee up to
aggregate limit of Rs………………………...... (Rupees ….....
...................................................................
……………………………………..only)
This Guarantee / Undertaking shall be a continuing / undertaking and shall remain valid
and irrevocable for all claims of the Company and liabilities of the Supplier arising up to
and until midnight of……………………………..
This date shall be 6 months from the last date of guarantee period
Page 63 of 196
Company in enforcing or requiring enforcement of any other security shall have the
effect of releasing the Bank from its liability hereunder.
The company shall be at liberty without reference to the bank and without affecting the
full liability of the Bank hereunder to take any other security in respect of the Supplier’s
obligations and/or liabilities under or in connection with the said supply contract and to
vary the terms vis a vis the supplier of the said supply contract or to grant time and/or
indulgence to the supplier or to reduce or to increase or otherwise vary the prices of the
total contract value or and/or the remedies of the company under any other security (ies)
now or hereafter held by the company and no such dealing(s), variation(s), reduction(s),
increase(s) or the indulgence(s) or arrangement(s) with the supplier or release or
forbearance whatsoever shall have the effect of releasing the Bank from its full liability to
the Company hereunder or of prejudicing rights of the Company, against the Bank.
The Bank hereby waives all rights at any time inconsistent with the terms of its
Guarantee / Undertaking and the obligations of the Bank in terms hereof shall not be
anywise affected or suspended by reason of any dispute or disputes having been raised
by the supplier (whether or not pending before any Arbitrator, office, Tribunal or Court) or
any denial of liability by the supplier or any other of communication whatsoever by the
supplier stopping or preventing or purporting to stop or prevent any payment by the Bank
to the Company in terms hereof.
The amount stated in any notice of demand addressed by the Company to the
Guarantor as liable to be paid to the Company by the supplier or as suffered or incurred
by the Company on account of any losses or damages of costs, charges and or
expenses shall as between the Bank and the company be conclusive of the amount so
liable to be paid to the Company or suffered or incurred by the Company, as the case
may be and payable by the Guarantor to Company in terms hereof.
Yours faithfully,
Page 64 of 196
Page 65 of 196
Page 66 of 196
Page 67 of 196
Page 68 of 196
Page 69 of 196
Page 70 of 196
Annexure – 1
E-TENDERING METHODOLOGY
https://eprocure.gov.in/eprocure/app .
REGISTRATION
1) Bidders are required to enroll on the e-Procurement module of the Central Public
Procurement Portal (URL: https://eprocure.gov.in/eprocure/app) by clicking on the link “Click
here to Enroll” on the CPP Portal is free of charge.
2) As part of the enrolment process, the bidders will be required to choose a unique username
and assign a password for their accounts.
3) Bidders are advised to register their valid email address and mobile numbers as part of the
registration process and submit in EIL tender portal for updation of records
(http://tenders.eil.co.in) . These details would be used for any communication from the CPP
Portal.
4) Upon enrolment, the bidders will be required to register their valid Digital Signature
Certificate (DSC) (Class II or Class III Certificates with signing key usage) issued by any
Certifying Authority recognized by CCA India (e.g. Sify / TCS / nCode / eMudhra etc.), with
their profile.
5) Foreign Bidders have to refer “DSC details for foreign Bidders” for Digital signature
Certificates requirements which comes under Download Tab at
https://eprocure.gov.in/eprocure/app and the remaining part is same as above and below.
6) Only one valid DSC should be registered by a bidder. Please note that the bidders are
responsible to ensure that they do not lend their DSC‟s to others which may lead to misuse.
7) Bidder then logs in to the site through the secured log-in by entering their user ID / password
and the password of the DSC / e-Token.
1) There are various search options built in the CPP Portal, to facilitate bidders to search active
tenders by several parameters. These parameters could include Tender ID, organization
name, location, date, value, etc. There is also an option of advanced search for tenders,
wherein the bidders may combine a number of search parameters such as organization
name, form of contract, location, date, other keywords etc. to search for a tender published
on the CPP Portal.
2) Once the bidders have selected the tenders they are interested in, the same can be moved
to the respective „My Tenders‟ folder. This would enable the CPP Portal to intimate the
bidders through SMS / e-mail in case there is any corrigendum issued to the tender
document.
Page 71 of 196
3) The bidder should make a note of the unique Tender ID assigned to each tender, in case
they want to obtain any clarification / help from the Helpdesk.
PREPARATION OF BIDS
1) Bidder should take into account any corrigendum published on the tender document before
submitting their bids.
2) Please go through the tender advertisement and the tender document carefully to
understand the documents required to be submitted as part of the bid. Please note the
number of covers in which the bid documents have to be submitted, the number of
documents - including the names and content of each of the document that need to be
submitted. Any deviations from these may lead to rejection of the bid.
3) Bidder, in advance, should get ready the bid documents to be submitted as indicated in the
tender document and generally, they can be in PDF / XLS / RAR / DWF formats. Bid
documents may be scanned with 100 dpi with black and white option. However, Price
Schedule / SOR shall be strictly in RAR format without altering any contents of the
formats uploaded by EIL in their Bidding Document.
4) To avoid the time and effort required in uploading the same set of standard documents which
are required to be submitted as a part of every bid, a provision of uploading such standard
documents (e.g. PAN card copy, annual reports, auditor certificates etc.) has been provided
to the bidders. Bidders can use “My Space” area available to them to upload such
documents. These documents may be directly submitted from the “My Space” area while
submitting a bid, and need not be uploaded again and again. This will lead to a reduction in
the time required for bid submission process.
SUBMISSION OF BIDS
1) Bidder should log into the site well in advance for bid submission so that he/she upload the
bid in time i.e. on or before the bid submission time. Bidder will be responsible for any delay
due to other issues.
2) The bidder has to digitally sign and upload the required bid documents one by one as
indicated in the tender document.
3) Bidder has to select the payment option as “offline” to pay the tender fee / EMD as
applicable and enter details of the instrument.
4) Bidder should prepare the EMD as per the instructions specified in the tender document. The
original should be posted/couriered/given in person to the Tender Processing Section, with
in 7 calendar days of the date of Unpriced bid opening. The details of the DD/any other
accepted instrument, physically sent, should tally with the details available in the scanned
copy and the data entered during bid submission time. Otherwise the uploaded bid will be
rejected.
5) A Price Bid format has been provided with the tender document to be filled by all the bidders.
Bidders are requested to note that they should necessarily submit their financial bids in the
format provided and no other format is acceptable. Bidders are required to download the
Price Bid file, open it and complete the cells with their respective financial quotes and other
details (such as name of the bidder). No other cells should be changed. Once the details
have been completed, the bidder should save it and submit it online, without changing the
filename. If the Price Bid file is found to be modified by the bidder, the bid will be rejected.
Page 72 of 196
6) The server time (which is displayed on the bidders‟ dashboard) will be considered as the
standard time for referencing the deadlines for submission of the bids by the bidders,
opening of bids etc. The bidders should follow this time during bid submission.
7) All the documents being submitted by the bidders would be encrypted using PKI encryption
techniques to ensure the secrecy of the data. The data entered cannot be viewed by
unauthorized persons until the time of bid opening. The confidentiality of the bids is
maintained using the secured Socket Layer 128 bit encryption technology. Data storage
encryption of sensitive fields is done.
8) The uploaded tender documents become readable only after the tender opening by the
authorized bid openers.
9) Upon the successful and timely submission of bids, the portal will give a successful bid
submission message & a bid summary will be displayed with the bid no. and the date & time
of submission of the bid with all other relevant details.
10) The bid summary has to be printed and kept as an acknowledgement of the submission of
the bid. This acknowledgement may be used as an entry pass for any bid opening meetings.
RETENDER
1) Please note that if Tender has been retendered, than it is mandatory for the bidder to
submit their offer again on CPP Portal.
ASSISTANCE TO BIDDERS
1) Any queries relating to the tender document and the terms and conditions contained therein
should be addressed to the Tender Inviting Authority for a tender or the relevant contact
person indicated in the tender.
2) Any queries relating to the process of online bid submission or queries relating to CPP Portal
in general may be directed to the 24x7 CPP Portal Helpdesk. The contact number for the
helpdesk is 1800 233 7315.
Page 73 of 196
Government eProcurement System
This document gives the procedure to be followed by bidders who are resident of countries other
than India for participating in Online Tendering Activity.
As per the IT ACT 2000, all bidders who participate in the online bidding process in this site
should possess a valid Digital Signature issued by any of the Digital Signature Certificate (DSC)
vendors approved by CCA, India (https://cca.gov.in). The following document gives the procedure
that is generally followed by various vendors.
Generally, the documents that are required to be submitted by Foreign Nationals are as follows:
1. Identity Proof (ID Proof) of the person in whose name DSC has to be issued (E.g.
Passport copy)
2. Bank account statement in country of residence, duly attested by Indian Embassy / High
Commission / Consulate / Apostille in the country where the applicant is currently
located. (At least 6 months of Bank transactions) with the proof indicating the account is
owned by the Individual.
3. Copy of the Trade license attested by any one of the authorities as specified in Point 2
above.
4. As the Individual is representing the company, an Authorization on company’s letter head
as given in the form
5. Copy of the Authorization letter or invitation letter from department for the
participation in the tender by any one of the tender inviting authority.
As of now, it is learnt that GNFC, TCS, eMudhra issue DSCs with the above procedure. The
copy of the nCodes, TCS and eMudhra Format is enclosed as Annexure; the Copies of other
vendors will be made available on receipt of information from these vendors.
Note: The Information given by the vendors is attached for facilitating the Foreign Nationals to
procure DSCs from the Indian CA authorized vendors for information purpose only as shared by
the respective CA's.
Please find below the details of various vendors and procedure for obtaining DSC:
GNFC
Tata Consultancy Services
eMudhra
Material to be delivered at (job site) BPCL, KOCHI, KERALA within the delivery period specified in the "Request For
Quotation" (RFQ).
Notes :
1. This page is a record of all the Revisions of this Requisition.
2. The nature of the Revision is briefly stated in the "Details" column below, the Requisition in its entirety shall be
considered for contractual purposes.
4. When revised pages only are issued, the revised pages shall form part of the original Requisition. The original
requisition alongwith the revised pages shall be considered in its entirety for contractual purposes.
5. Vendors are required to quote strictly as per technical specifications / notes stipulated in the material requisition. The
offers with deviations are likely to be summarily rejected.
This is a system generated approved document and does not require signature
EIL - 588 A - 216 x 279
REVISION
SR. NO DOCUMENT TITLE DOCUMENT NO.
NO. DATE
1 ADDITIONAL TECHNICAL A307-000-16-43-3314 A 22/01/2014
REQUIREMENTS
2 TECHNICAL NOTES FOR VALVES 6-44-0052 6 04/08/2010
3 INSPECTION AND TEST PLAN FOR 6-81-0004 5 17/06/2013
VALVES
except in the limited way and private use permitted by written consent given by the lender to the borrower for the intended use. EIL-1641-515 Rev.0 A4-210x297
I
151fRiseA ENGINEERS FOR POSITIVE MATERIAL
si at efaleg INI NA LIMITED
/A “nul na. Lnden.,), IDENTIFICATION (PMI) AT
6 - 81 - 0001 Rev. 2
SUPPLIER'S WORKS Page I of 8
covingii 4
c 1T
STANDARD SPECIFICATION
FOR
POSITIVE MATERIAL
IDENTIFICATION
(PMI)
AT SUPPLIER'S WORKS
40D ., 15,
2 20.10.11 REVISED AND RE-ISSUED AKC DM
Page 89 of 196
STANDARD SPECIFICATION STANDARD SPECIFICATION No.
151Mae? - le.' ENGINEERS FOR POSITIVE MATERIAL
imegver INDIA LIMITED
yin eRaWanJelwill Govl of India Undertakno IDENTIFICATION (PM I) AT
6-81-0001 Rev. 2
SUPPLIER'S WORKS Page 2 of 8
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 REFERENCE DOCUMENTS 4
3.0 DEFINITIONS 4
4.0 PMI EXAMINATION 5
5.0 ACCEPTABLE METHODS FOR PMI 5
6.0 EXTENT OF PMI EXAMINATION 6
7.0 RECORDING AND DOCUMENTATION 7
8.0 MARKING 7
1.0 SCOPE
1.1 This specification applies to the requirements for Positive Material Identification (PMI) to be
performed at the Supplier's works on Metallic Materials procured either directly by the
Owner/EIL/ LSTK contractor or indirectly through the sub-Suppliers.
1.2 Any post order deviation from this specification must be approved by Owner/EIL in the
Deviation/ Waiver Permit format (No. 5-0000-0180-F1) enclosed with Material Requisition.
1.3 This specification covers the procedures and methodology to be adopted to assure that the
chemical composition of the material is consistent with the material specifications as specified
in purchase documents using 'Alloy Analyzer' at the time of final inspection before dispatch.
1.4 The scope of this specification shall include but shall not be limited to Positive Material
Identification (PMI) to be performed on Materials listed below:
1.5 All grades of material supplies including Stainless Steels shall be liable for PMI test at site. In
case of any defective materials being found at site, the Supplier shall be responsible to effect
replacement of such defective materials at project site without any delays to the satisfaction of
EIL site RCM (Resident Construction Manager).
2.1 API Recommended Practice 578 (First Edition, May 1999) - Material Verification Program for
New and Existing Alloy Piping Systems.
3.0 DEFINITIONS
3.1 Supplier: Any Supplier or Manufacturer on whom an order is placed for the supply of referred
items. This definition shall also include any sub-Supplier or manufacturer on whom a sub-order
is placed by the Supplier.
Page 92 of 196
STANDARD SPECIFICATION STANDARD SPECIFICATION No.
SaIRCIELM—; ENGINEERS FOR POSITIVE MATERIAL
Par taiReZ VW INDIA LIMITED 6-81-0001 Rev. 2
IDENTIFICATION (PM I) AT
SUPPLIER'S WORKS Page 5 of 8
3.2 Inspection Lot: A group of items offered for inspection covered under same size, Heat and
Heat treatment lot.
3.3 Alloy Material: Any metallic material (including welding filler materials) that contains
alloying elements such as chromium, nickel, molybdenum or vanadium, which are intentionally
added to enhance mechanical or physical properties and/or corrosion resistance.
4.1 The Supplier shall submit a procedure of PMI to comply with the requirements of this
Specification Approval of PMI Procedure shall be obtained from Owner/EIL/TPIA prior to
commencing manufacture/ inspection of product.
4.2 PMI examination of materials is independent of any certification, markings or colour coding
that may exist and is aimed at verifying that the alloy used are as per specified grades.
4.3 The Supplier shall identify all incoming alloy materials and maintain full traceability of all alloy
materials, including all off-cuts. Transfer of identification marks shall be undertaken prior to
cutting to ensure maintenance of identification on off-cuts.
4.4 The Supplier shall ensure that all alloy materials are segregated and stored in separately
identified locations to prevent the mix up of materials of different alloy specifications or alloy
material with carbon steel. Non ferro-magnetic materials shall be segregated at all times from
ferro-magnetic materials.
5.1 The method used for PMI examination shall provide a quantitative determination of the alloying
elements like chromium, nickel, molybdenum or vanadium in Alloy Steel items.
5.2 Instruments or methods used for PMI examination shall be able to provide quantitative,
recordable, elemental composition results for positive identification of alloying elements
present.
5.3 The acceptable instruments for alloy analyzer shall be either "Portable X-Ray fluorescence" or
"Optical Emission" type each capable of verifying the percentage of alloy elements within
specified range.
5.4 Chemical spot testing, magnets, alloy sorters and other methods using eddy current or
triboelectric testing methods are not acceptable for PMI examination.
5.5 The PMI instrument used shall have the sensitivity to detect the alloying elements in the
specified range.
5.6 All PMI instruments shall have been serviced within a 6 month period of the time of use to
verify the suitability of batteries, sources etc., and the data of the last service shall be stated on
the PMI Report Form (Sample enclosed).
5.7 Each analyzer must be calibrated according to the manufacturer's specification at the beginning
and end of each shift. Instrument must be checked against known standard for each alloy type
to be inspected during the shift.
Page 93 of 196
STANDARD SPECIFICATION STANDARD SPECIFICATION No.
ISillaZreq e ENGINEERS FOR POSITIVE MATERIAL
s'Ig7e2eg W
INDIA UMITED
Govt a Inaa Undenakingi IDENTIFICATION (PMI) AT
6-81-0001 Rev. 2
SUPPLIER'S WORKS Page 6 of 8
5.8 Certified samples, with full traceability, of a known alloy materials shall be available for use as
a random spot check on the instrument calibration.
5.9 The surfaces to be examined shall be prepared by light grinding or abrasive paper and solvent
cleaner. Evidence of Arc burn resulting from examination shall be removed by light grinding or
abrasive paper. No permanent marks, which are injurious to the usage of product in service, are
acceptable.
5.10 Alloy Steel ring type joint Gaskets shall be inspected by using portable X-Ray fluorescence
instrument.
5.11 Testing shall be done as per the procedures outlined by the manufactures of alloy analyzer
being used. Modification of these procedures if any must be approved by Owner/EIL.
5.12 The persons performing PMI shall demonstrate their capabilities to the satisfaction of
Owner/EIL/TPIA visiting engineer. If the Supplier has qualified operator on their rolls, he may
perform the examination. Otherwise PMI examination shall be sub-contracted to an independent
testing agency approved by EIL.
5.13 Whenever material is identified as not meeting requirements by the visiting engineer a rejection
note shall be issued.
Following sampling plans shall be applicable for PMI examination of various items.
Note:
For Welded Pipes and Fittings, PMI shall be performed on Base Metal as well as
weldments.
Whenever any sample drawn to PMI test on the basis of percentage selection in B & C
above, fails to meet specification requirements, 100% of items of lot shall be tested for
PMI.
Page 94 of 196
STANDARD SPECIFICATION STANDARD SPECIFICATION No.
i.311-aelti . ENGINEERS FOR POSITIVE MATERIAL
ogrir EiRtegi INDIA LIMITED
IA Go' at India Undertaking) IDENTIFICATION (PMI) AT
6-81-0001 Rev. 2
SUPPLIER'S WORKS Page 7 of 8
The results of PMI examination shall be recorded in a Report Format as enclosed with this
specification.
8.0 MARKING
8.1 All alloy materials tested by PMI shall be identified using either of the following methods by
indicating "PMI OK"
Material Specification/Grade
Element Cr Mo Ni V
Specified Range
Actual observations
Instrument Type / ID
fktorr a -crteTur
INSPECTION AND TEST PLAN
FOR
VALVES
Page 97 of 196
STANDARD SPECIFICATION NO.
INSPECTION AND TEST PLAN
ei ENGINEERS
fg-zrr iffaeg INDIA LIMITED FOR 6-81-0004 Rev. 5
eieM1,751,275141 IA Govt of India Undertaking)
VALVES Page 2 of 7
Abbreviations:
Members:
Page 98 of 196
STANDARD SPECIFICATION NO.
INSPECTION AND TEST PLAN
k31 eJ ENGINEERS
fg- zrr la154tg INDIA LIMITED FOR 6-81-0004 Rev. 5
(A Govt of India Undertaking)
VALVES Page 3 of 7
1.0 SCOPE
This Inspection and Test Plan covers the minimum testing requirements of Valves.
SCOPE OF INSPECTION
SL QUANTUM OF
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO CHECK SUPPLIER EIL/TPIA
SUPPLIER
1.0 Procedure
Hydrostatic Test,
Heat Treatment, NDT, Procedure
1.1 Helium Leak Test Documented Procedures 100% - H R
Documents
And
Other Procedures
Fire safe, H
As per PR / Purchase Acceptance
1.3 Pre-Qualification Tests Cryogenic & Other - H
Specification Report (If new)
Test as applicable
Page 99 of 196
STANDARD SPECIFICATION NO.
INSPECTION AND TEST PLAN
k31 elei la ENGINEERS
6-81-0004 Rev. 5
5V--ar faireg INDIA LIMITED FOR
17177R FRIVU ‘7,1.3,195 +1) IA Govt India Undertaking)
Al
VALVES Page 4 of 7
SCOPE OF INSPECTION
SL QUANTUM OF
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO CHECK SUPPLIER EIL/TPIA
SUPPLIER
Chemical ,Mechanical ,
Castings & Forgings Heat Treatment, Test R R
2.1. 100% H
(Body, Bonnet, Disc, Stem, Body ring) NDT,IGC & Other Certificates
Properties as applicable
Test
2.4 Bars for Trim material Chemical Analysis Each Heat Certificates& H R -
Lab Report
Test
Gaskets, Gear units, Fasteners, Gland, Physical / Chemical Certificates& H R -
2.5 100%
Packings, etc. Properties Lab Report
Test
Performance , Certificates ,
2.6 Actuators as applicable Statutory Certificates as 100% H H R
Inspection
nspection
report
SCOPE OF INSPECTION
SL QUANTUM OF
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO CHECK SUPPLIER EIL/TPIA
SUPPLIER
Inspection
3.2 Machining of components Visual / Dimension 100% - H -
Reports
RW
4.2 Visual / Dimension Surface & Dimension 100% Test Report - H
(Note 1)
Check
SCOPE OF INSPECTION
SL QUANTUM OF
STAGE/ ACTIVITY CHARACTERISTICS RECORD SUB
NO CHECK SUPPLIER EIL/TPIA
SUPPLIER
Stamping of Valves H
Stamping Of Accepted Inspection
4.6 Final Stamping which are witnessed - H
Valves rt
Report (Note-1)
by EIL/TPIA.
5.0 Painting
Inspection -
5.1 Painting and Color coding as applicable Visual / DFT Check 100% - H
Report
Legend: H- Hold (Do not proceed without approval), P-Perform, RW - Random Witness (As specified or 10% ( min.1 no. of each size and type of Bulk item)), R-
Review, W-Witness (Give due notice, work may proceed after scheduled date).
1 4 €€ 141 1 4 I I KOR
-1 -
SPECIFICATION
FOR
DUPLEX STAINLESS STEEL AND
SUPER DUPLEX STAINLESS STEEL
414 44 #6daAr_
07.10.11 REVISED & REISSUED AS STANDARD
1 SPECIFICATION SKM SG PPL DM
0 28.12.04 ISSUED AS STANDARD SPECIFICATION SG VRK KKM SKG
Standards Standards
Prepared Checked Committee Bureau
Rev. Date Purpose Convenor Chairman
No by by
Approved by
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 CODES AND STANDARDS 4
3.0 STEEL MANUFACTURE 5
4.0 HEAT TREATMENT 5
5.0 APPLICABLE REQUIREMENTS FOR DSS AND SDSS 5
6.0 PRE-QUALIFICATION CRITERIA FOR MILL / MANUFACTURER 8
7.0 CORROSION TESTS FOR PRE-QUALIFICATION 9
8.0 REQUIREMENTS FOR PRODUCTION TESTING 11
9.0 QUALITY SURVEILLANCE AND INSPECTION 12
10.0 DOCUMENTS TO BE SUBMITTED 12
1.0 SCOPE
1.1 This specification covers the specific requirements for manufacture, inspection, testing and
supply of duplex stainless steels conforming to UNS No.(s) S 31803, S 32205 or equivalent
and super duplex stainless steel conforming to UNS No.(s) S 32760, S 32750, S 39274, S
32550, J 93380 or equivalent. DSS and SDSS material shall be considered acceptable when
they meet the pre-qualification criteria mentioned in this specification.
1.2 This specification shall be read together with the corresponding product specifications
mentioned in the relevant piping material specifications or the equipment data sheets/design
drawings intended to be used in sour and/or chloride containing environments, as applicable.
1.3 In case of conflict between this specification and the referred material codes/standard
specifications, the requirement of this specification shall govern.
The manufacture, inspection, testing, marking and supply of the item covered by this
specification shall follow the latest editions of the following codes and standard specifications:
ASTM A 182 Forged or rolled alloy steel pipe, flanges, forged fittings and valves and
parts for high temperature service
ASTM A 240 Heat resisting chromium and chromium - nickel stainless steel plate, sheet
and strip for pressure vessels
ASTM A 276 Stainless steel bars and shapes
ASTM A 351 Casting - austenitic, austenitic-ferritic (duplex) for pressure containing
parts
ASTM A 370 Standard methods and definitions for mechanical testing of steel
ASTM A 743 Castings - iron-chromium-nickel-base corrosion resistant, for general
application
ASTM A 744 Casting - iron-chromium-nickel-base corrosion resistant, for severe
application
ASTM A 789 Seamless and welded ferritic/austenitic stainless steel tubing for general
service
ASTM A 790 Seamless and welded ferritic- austenitic stainless steel pipe
ASTM A 799 Steel castings-stainless instrument calibration for estimating ferrite
content
ASTM A 815 Wrought ferritic, ferritic-austenitic and martensitic stainless steel pipe
fittings
ASTM A 923 Standard test methods for detecting detrimental intermetallic phase in
wrought duplex austenitic/ferritic stainless steels
ASTM A 928 Specification for ferritic/austenitic (duplex) stainless steel pipe electric
fusion welded with addition of filler metal
ASTM E 18 Rockwell hardness testing of metallic materials
ASTM E 562 Determining volume fraction by systematic manual point count
ASTM G 36 Performing stress corrosion cracking tests in a boiling magnesium
chloride
ASTM G 48 Standard test methods for pitting and crevice corrosion resistance of
stainless steels and related alloys by use of ferric chloride solution
ASME B 16.34 Valves- flanged, threaded, and welding end
ASME Sec.V Non-destructive examination
MSS-SP-55 Manufacturers Standardization Society of the Valve and Fitting Industry
Standard — Quality Standard for Steel Castings for valves, flanges, and
fittings and other components (visual method)
NACE MR0175/ Petroleum and natural gas industries-Materials for use in H2S-containing
ISO 15156 environments in oil and gas production:
Part 1: General principles for selection of cracking-resistant materials
Part 3: Cracking-resistant CRAs (corrosion-resistant alloys) and other alloys
NACE MR0103 Material resistant to Sulfide Stress Cracking in corrosive petroleum
refining environments
NACE TM0177 Laboratory testing of metals for resistance to sulfide stress cracking and
stress corrosion cracking in H2 S environments
SNT-TC-1A Personnel qualification and certification of nondestructive testing
personnel, American Society for Nondestructive Testing (ASNT)
3.1 The steel shall be manufactured / produced by the following or as specified in the applicable
material specification:
3.1.1 The steel shall be made by one of the following primary steel making processes:
3.1.2 The steel shall be subjected to tertiary steel refining treatments such as vacuum oxygen
decarburization (VOD)/ argon oxygen decarburization (ACID), and vacuum arc degassing
(VAD) to minimize dissolved gas contents, inclusions content and to meet the chemical
composition with close tolerances.
All the finished product forms shall be solution annealed by holding it at 1020-1100°C
followed by a fast cooling procedure. The duration of homogenizing treatment is dependent on
the product forms and thickness, but shall be not less than 20 minutes per 25 mm of thickness.
For product thickness is less than or equal to 10 mm, forced air cooling shall be carried out
while for thickness greater than 10 mm, water quenching shall be carried out. All hot
working/forging operations shall be carried out within a temperature range of 1020-1100°C.
No hot working/forging operations shall take place at temperature less than 1020°C.
All the finished product forms shall be supplied in solution annealed condition. The product
shall be homogenized at 1050-1120°C followed by a fast cooling procedure. The duration of
homogenizing treatment is dependent on the product forms and thickness, but shall be not less
than 20 minutes per 25 mm of thickness. For product thickness is less than or equal to 10 mm,
forced air cooling shall be carried out while for thickness greater than 10 mm, water
quenching shall be carried out. All hot working/forging operations shall be carried out within
a temperature range of 1050-1120°C. No hot working/forging operations shall take place at
temperature less than 1050°C.
Chemical composition of DSS and SDSS shall be as per Clause Nos. 5.1.1 and 5.1.2
respectively.
5.1.1 DSS
Element Wt%
5.1.2 SDSS
Element Wt%
5.1.3 If any other elements are proposed to be added, such proposals shall be submitted to Company
for specific written approval. Copper (Cu) and Tungsten (W) additions exceeding the limits as
specified above shall be acceptable, provided the weldability and freedom from undesirable
metallurgical constituents are ensured.
The pitting resistance equivalent number of the duplex stainless steel materials shall be greater
than 35, when calculated as mentioned in Clause No.5.2.1.
The pitting resistance equivalent number of the super duplex stainless steel materials shall be
greater than 40, when calculated as mentioned in Clause No. 5.2.1.
5.3 Microstructure
5.3.1 DSS
The duplex stainless steel shall have approximately equal proportions of austenite and ferrite
phases and the ferrite content shall be in the range of 40-55% in the austenite-ferrite matrix.
5.3.2 SDSS
For super duplex stainless steel, the ferrite content shall be in the range of 35-55% in the
austenite-ferrite matrix.
5.3.3 Ferrite content measurement for DSS and SDSS material shall be carried out for each heat by
metallography method in accordance with ASTM E 562.
5.3.4 For DSS and SDSS products, either in the as-supplied condition, solution annealed condition,
or in the as welded condition, the microstructure shall not reveal the presence of any carbide
or any intermetallic phases to the extent that are detrimental to the toughness and corrosion
resistance of the material. The detection of the detrimental intermetallic phases in the wrought
products shall be carried out in accordance with ASTM A 923. The intermetallic phases shall
not be more than 1%.
S4 Mechanical Properties
The material in the solution-annealed condition shall conform to the mechanical properties
such as ultimate tensile strength, 0.2% & 1% offset yield strength, % elongation, hardness
applicable for the respective UNS No. of the material. The tensile test shall be carried out as
per ASTM A 370.
The hardness test method shall be in accordance with ASTM E 18. If any other methods
including portable hardness tester are to be deployed for checking production welds, then the
correlation between the qualification method and the production method shall be established
and the calibration graph shall be generated for use at the field/shop.
Wrought materials
at 20°C 120 J (Average)/ 90 J (Minimum)
at -30°C 100 J (Average)/ 75 J (Minimum)
Cast materials
at 20°C 75 J (Average)/ 55 J (Minimum)
at -30°C 60 J (Average)/ 40 J (Minimum)
6.1 The DSS and SDSS material components shall be procured from a pre-qualified supplier. The
supplier shall be qualified for specific TINS No. for which the mill was pre-qualified. Any
change in UNS No. shall require a fresh pre-qualification.
6.1.1 Pre-Qualification Criteria for Vendors with Prior Experience Track Record
Vendors/manufacturers who have proven track record of supplying DSS and SDSS materials
for sour service and chloride containing environments in chemical process industries (CPI) to
any of the reputed operating companies/Engineering Consultants or Process Licensors such as
UOP, IFP, EXXON, BP, CHEVRON, IOCL, HPCL, BPCL, and EIL shall be considered as
`pre-qualified vendors/manufacturers', on production of the relevant Purchase Orders and test
certificates, certified by a witnessing third party inspection agency such as DNV, Lloyds, BV,
ABS, TUV, SGS, CEIL, and EIL for the conformance of the materials to the respective
materials specification of the mentioned operators / engineering consultants. For pre-qualified
vendors, Clause No.6.1.2 is not applicable.
A vendor who has no track record of supplying DSS and SDSS materials for sour service and
chloride containing environments in chemical process industries (CPI) to any of the reputed
engineering consultants/operators, as mentioned above in Clause No.6.1.1, shall be considered
as a new vendor. The chemical, the mechanical and all the corrosion tests shall be carried out
as mentioned in Clause Nos. 5.0, 7.0 for pre-qualification by any one of the reputed third party
inspection agencies like Lloyds, BV, CEIL, DNV, TUV, and EIL.
6.2 The corrosion tests for DSS and SDSS in accordance with the Clause No. 7.0 shall be
conducted for the pre-qualification of the manufacturers/mills.
6.3 All the tests reports including the corrosion tests shall be based upon the tests conducted on
the product specimen drawn from a single heat, and shall bear the same heat number.
6.4 In case the manufacture(s) had already conducted all the corrosion above tests on a product of
the same material in the past, and has an approved quality assurance system in place, and the
test results are certified by a witnessing a third party inspection agency approved by the
Company, the test results shall be furnished by the bidder, along with his bid, for Company's
review.
The manufacturer(s) shall be qualified based on the satisfactory review of the submitted test
results. The Company's decision in this regard shall be final and binding on the bidder.
While selecting and procuring the duplex stainless steel and super duplex stainless steel
materials for a specific project, care shall be taken to use the same UNS No. for the entire
system. Bidder shall note that, subsequent to qualification, a change in combination of
mill/manufacturer and UNS No. shall call for a fresh qualification exercise to be conducted.
6.5.1 Visual
All castings for valves, flanges, fittings and other components of DSS and SDSS shall be
visually examined in accordance with the quality levels mentioned in MSS-SP-55. The
procedure for visual examination and the acceptance criteria shall be as per MSS-SP-55.
6.5.2 Radiography
Radiography examination shall be performed on all DSS and SDSS valve castings (in
accordance with ASME B16.34 with the acceptance criteria mentioned therein) and flanges,
fittings and other components of DSS and SDSS in accordance with Article 2 of ASME
Section V. The operator's certification to SNT-TC-1A or equivalent is required.
Wet fluorescent penetrant examination shall be performed on the exterior and accessible
interior surfaces of all DSS and SDSS valve castings (in accordance with ASME B16.34 with
the acceptance criteria mentioned therein) and flanges, fittings and other components of DSS
and SDSS in accordance with Article 6 of ASME Section V. The operator's certification to
SNT-TC-1A or equivalent is required.
7.1 Sulphide Stress Cracking (SSC) test as per Clause No. 7.2, Chloride Stress Cracking (CSC)
test as per Clause No. 7.3, Pitting Corrosion test as per Clause No. 7.4, Crevice Corrosion test
as per Clause No.7.5, are mandatory when DSS and SDSS steel materials are intended to be
used for sour service and chloride containing environments.
If DSS and SDSS materials are intended to be used for chloride containing environments only,
the SSC test as per Clause No.7.2 shall be waived off. The remaining corrosion tests specified
in this section shall be carried out for DSS and SDSS materials meant for use in the chloride
containing environments.
The corrosion tests applicable for DSS and SDSS materials shall be as furnished in the
following paragraphs:
SSC test on duplex stainless steel shall be carried out by using the following test solutions and
test conditions:
The CSC tests shall be conducted on representative specimens of DSS and SDSS, in
accordance with the testing procedure mentioned in ASTM G-36, in aerated, boiling
40% calcium chloride (CaCl 2) solution at 100°C with the pH of the solution
maintained around 6.5.
Acceptance criteria: stress to cause rupture in 500 hours shall exceed 0.85 times the
actual ultimate tensile strength values of duplex stainless steel and super duplex
stainless steel material individually.
7.4.1 DSS
The pitting corrosion test shall be conducted on the representative DSS specimen, in
accordance with ASTM G-48 method A, using 6% ferric chloride (FeCI 3 .6 H 2 0) solution
by weight at 30°C, as well as at 50°C, for duration of 24 hours.
Acceptance criteria: no pitting shall occur on the surface of the test sample at 30°C. For
the testing at 50°C, the weight loss shall be reported to company for review.
7.4.2 SDSS
The pitting corrosion test shall be conducted on the representative SDSS specimen, in
accordance with ASTM G-48 method A, using 6% ferric chloride (FeCI 3 .6 1420) solution
by weight at 40°C, as well as at 50°C, for duration of 24 hours.
Acceptance criteria: no pitting shall occur on the surface of the test sample at 40°C. For
the testing at 50°C, the weight loss shall be reported to company for review.
7.5.1 DSS
The crevice corrosion test shall be performed on the representative DSS specimen, in
accordance with ASTM G-48 method B, using 6% ferric chloride (FeCI3 .6 H 2 0) solution
by weight, at 25°C for duration of 24 hours.
Acceptance criteria: no crevice shall form on the surface of the test sample at 25°C.
7.5.2 SDSS
a) The crevice corrosion test shall be performed on the representative SDSS specimen, in
accordance with ASTM G-48 method B, using 6% ferric chloride (FeCI3.6 F120) solution
by weight, at 30°C for duration of 24 hours.
b) Acceptance criteria: no crevice shall form on the surface of the test sample at 30°C.
Separate test blanks shall be required for each process of manufacture of the finished products.
Each test sample shall receive the same working / heat treatment as the finished products it
represents.
If the test specimen cannot be taken from a finished product, then a representative test
specimen shall be taken from the same heat, heat treated in the same batch, and be subjected to
the same extent of working as the most worked section of the finished product. In case the
finished product is of welded type, then the test piece shall be so chosen as to include the
parent metal, the weld metal and the heat affected zone.
The product analysis and the mechanical properties evaluation shall be conducted strictly as
per requirements of the relevant material product specifications. Micro-structural examination,
ferrite measurement and hardness testing on the finished product, shall be carried out for one
sample per heat per method of manufacturer.
The test results shall be submitted to the Company as a part of the product documentation.
On placement of order, a vendor who has met the pre-qualification criteria, shall carry out the
following production tests, to meet the acceptance criteria mentioned in the respective clauses.
All the following tests shall be witnessed and certified by a reputed the third party Inspection
Agency duly approved by the Company, on the first heat:
The routine testing of product of each heat shall be carried out on a regular basis, in house.
The chemical composition, the pitting resistance equivalent number, the mechanical
properties, the micro-structural examination and for casting, the visual examination, the
radiography and the wet fluorescent penetrant examinations shall conform to the requirements
specified in the respective Clauses of this specification.
The supplier shall perform all the tests and inspection procedures mentioned above to ensure
that the materials conform to the requirements of this specification. Company, or the
representative duly approved by the Company, shall have unhindered access to the material
being manufactured for inspection and/or witnessing the selection of test samples, the
preparation of test specimens, and the performance of tests. The company or its representative
shall have the right to indicate the pieces from which the specimens are to be drawn for
various tests. In case of any reasonable doubts regarding the quality of the product, Company
shall have the option to ask for the re-qualification of the mill at the vendor's/contractor's cost.
Inspection by the Company or its authorized representative shall not relieve the supplier of his
responsibility for ensuring the compliance of the materials supplied to this specification.
The vendors/suppliers shall submit the following records of the tests and inspection conducted
on the materials, as per the applicable Clauses mentioned in this specification, to the company
in quadruplicate:
3 14.-3G41
07.10.11 REVISED & REISSUED AS STANDARD
1 SPECIFICATION PC SG PPL DM
0 28.12.04 ISSUED AS STANDARD SPECIFICATION SG VRK KKM SKG
Standards Standards
Prepared Checked Committee Bureau
Rev. Date Purpose Convenor Chairman
No by by
Approved by
STEEL Page 2 of 11
Abbreviations:
CONTENTS
1.0 SCOPE 4
2.0 CODES AND STANDARDS 4
3.0 WELDING PROCESSES 4
4.0 WELDING CONSUMABLES 5
5.0 APPLICABLE REQUIREMENTS FOR DSS AND SDSS WELDING CONSUMABLES 5
6.0 CLEANING 6
7.0 QUALIFICATION CRITERIA 6
8.0 CORROSION TESTS FOR QUALIFICATION 9
9.0 FABRICATION 11
10.0 QUALITY SURVEILLANCE AND INSPECTION 11
11.0 DOCUMENTS TO BE SUBMITTED 11
1.0 SCOPE
1.1 This specification covers the requirements for the welding processes, the quality of the
welding consumables, the welding consumable qualification, the welding procedure
qualification, the welder qualification and the quality assurance testing during fabrication of
DSS and SDSS components. DSS and SDSS welding consumables shall be considered
acceptable when they meet the qualification criteria mentioned in this specification. This
specification shall be applicable for both shop fabricated and field/site fabricated components.
1.2 This specification shall be read together with the corresponding product specifications,
mentioned in the relevant piping material specifications, and/or the equipment data
sheets/design drawings, intended to be used in sour and/or chloride containing environments,
as applicable.
1.3 In case of conflict between this specification and the referred material codes/standard
specifications, the requirement of this specification shall govern.
The manufacture, inspection, testing, marking and supply of the item covered by this
specification shall follow the latest editions of the following codes and standard specifications:
ASTM A 370 Standard methods and definitions for mechanical testing of steel
ASTM A 923 Standard test methods for detecting detrimental intermetallic phase in
wrought duplex austenitic/ferritic stainless steels
ASTM E 18 Rockwell hardness testing of metallic materials
ASTM E 562 Determining volume fraction by systematic manual point count
ASTM G 36 Performing stress corrosion cracking tests in a boiling magnesium
chloride
ASTM G 48 Standard test methods for pitting and crevice corrosion resistance of
stainless steels and related alloys by use of ferric chloride solution
ASME Section II- Material specifications — Welding rods, Electrodes and Filler metals
Part C
ASME Section V Non-destructive examination
ASME Sec.VIII- Rules for construction of pressure vessels
Division 1
ASME Section IX Welding and Brazing qualifications
NACE MR0175/ Petroleum and natural gas industries-Materials for use in
ISO 15156- H2S-containing environments in oil and gas production:
Part 1: General principles for selection of cracking-resistant materials
Part 3: Cracking-resistant CRAs (corrosion-resistant alloys) and other alloys
NACE MR0103 Material resistant to Sulfide Stress Cracking in corrosive petroleum
refining environments
NACE TM0177 Laboratory testing of metals for resistance to sulfide stress cracking and
stress corrosion cracking in H2S environments
SNT-TC-1A Personnel qualification and certification of nondestructive testing
personnel, American Society for Nondestructive Testing (ASNT)
Shielded metal arc welding (SMAW), Gas tungsten arc welding (GTAW), Gas metal arc
welding (GMAW), Submerged arc welding (SAW) and Plasma arc welding (PAW) processes
are suitable for duplex and super duplex stainless steel. All necessary operational precautions
such as cleanliness, protective inert gas shielding applicable for DSS and SDSS shall be
adopted while employing these welding processes.
The welding consumables for welding duplex stainless steels of UNS No.(s) S 31803, S 32205
or equivalent and for welding super duplex stainless steel of UNS No.(s) S 32760,S 32750,S
39274, S 32550, J 93380 or equivalent shall conform to the recommendations made by the
DSS and SDSS base metal manufacturers. The welding consumables shall be used only after
conducting the requisite consumable qualifications tests as given in Clause No. 7.0.
The chemical composition of the DSS and SDSS welding consumables shall be adjusted with
respect to austenite formers such as nickel and ferrite formers such as molybdenum, in order
to obtain the requisite ferrite-austenite balance and the corrosion resistance properties in the
as-welded condition of the weldment. The specific chemical composition of as-welded deposit
shall be as recommended by the DSS and SDSS base metal manufacturers.
The pitting resistance equivalent number of the DSS welding consumables shall be greater
than 35, when calculated as mentioned in Clause No.5.2.1.
The pitting resistance equivalent number of the SDSS welding consumables shall be greater
than 40, when calculated as mentioned in Clause No. 5.2.1.
5.3 Microstructure
The ferrite content of the weld metal estimated through metallography examination should be
between 30 to 55% to obtain weld joints with the best ductility and corrosion resistance
properties. The welding consumables composition and the welding heat input should be so
selected as to give the ferrite content of the weld metal between 30 and 55%. Ferrite content
measurement shall be carried out by the metallography method in accordance with ASTM E
562.
5.4.1 DSS
Tensile Strength 680-880 N/mm2
Yield Strength (0.2% Offset) 450 N/mm2 (Min.)
Elongation 25% (Min)
5.4.2 SDSS
Tensile Strength 800-1050 N/mm2
Yield Strength (0.2% Offset) 550 N/mm2
Yield Strength (1% Offset) 650 N/mm2
Elongation 25% minimum
6.0 CLEANING
6.1 Cleaning of weld joints before and after the welding shall follow the good engineering
practices applicable for stainless steels. All accessible weld surfaces shall be cleaned after
welding by using pickling paste or pickling agent recommended by the welding consumable
suppliers, for a minimum period of 20 minutes, followed by water washing. This process shall
remove all oxide, tarnish, heat tint and surface contamination.
In the case of tube-to-tube sheet joints of the exchanger, extra care shall be taken to
completely remove the traces of the pickling paste or agent to maintain weld quality.
Wherever completely removal of pickling paste or agent cannot be ensured, such as air cooler
with plug type headers, pickling shall not be carried out.
Where access for cleanings not practicable, such as pipe butt welds, reliance must be placed
on good purging practice to minimize contamination of the backing gas by air. The purge gas
must contain below 10-ppm oxygen or moisture to achieve maximum corrosion resistance of
welds.
6.2 The area where DSS and SDSS fabrications are carried out shall be separated from carbon and
low-alloy steel fabrication area.
Each classification of the DSS and SDSS welding consumables, used for welding procedure
qualification, welder qualification as well as for production welds, shall be procured from
qualified welding consumable manufacturers.
7.1.1 Qualification Criteria for Vendors/Manufacturers with Prior Experience Track Record
Vendors/manufacturers who have proven track record of supplying DSS and SDSS welding
consumables for sour service and chloride containing environments in chemical process
industries (CPI) to any of the reputed operating companies/Engineering Consultants or
Process Licensors such as UOP, IFP, EXXON, BP, CHEVRON, IOCL, HPCL, BPCL, and
EIL shall be considered as qualified vendors/manufacturers', on production of the relevant
purchase orders and test certificates, certified by a witnessing third party inspection agency
such as DNV, Lloyds, BV, ABS, TUV, SGS, CELL, and EIL for the conformance of the
materials to the respective materials specification of the mentioned operators/engineering
consultants. For qualified vendors / manufacturers, Clause No.7.1.2 is not applicable.
A vendor/manufacturer who has no track record of supplying DSS and SDSS welding
consumables for sour service and chloride containing environments in chemical process
industries (CPI) to any of the reputed engineering consultants/operators, as mentioned above
in Clause No.7.1.1, shall be considered as a new vendor/manufacturer. The chemical, the
mechanical and all the corrosion tests shall be carried out as mentioned in Clause Nos. 5.0, 8.0
for qualification by any one of the reputed third party inspection agencies like Lloyds, BV,
CEIL, DNV, TUV, and EIL.
Sulphide Stress Cracking (SSC) test as per Clause No. 8.1, Chloride Stress Cracking (CSC)
test as per Clause No. 8.2, Pitting Corrosion test as per Clause No. 8.3 and Crevice Corrosion
test as per Clause No.8.4, are mandatory for DSS and SDSS welding consumables.
In case the vendors/manufacture(s) had already conducted all the corrosion tests in the past,
and has an approved quality assurance system in place, and the test results are certified by a
witnessing a third party inspection agency such as DNV, Lloyds, BV, ABS, TUV, SGS, CEIL,
and EIL, the test results shall be furnished by the bidder, along with his bid, for Company's
review.
The vendors/manufacturers shall be qualified based on the satisfactory review of the submitted
test results. The Company's decision in this regard shall be final and binding on the bidder.
7.2.1 General
7.2.1.1 Each particular welding procedure shall be specially qualified. Previous test reports shall not
be recognized as a qualification record for the work to be performed on a new job.
7.2.1.2 Welding consumable qualification tests and welding procedure qualification tests shall be
conducted before the start of fabrication, by employing an approved welding procedure in
presence of the Company third party inspection agency such as DNV, Lloyds, BV, ABS,
TUV, SGS, CEIL, and EIL.
7.2.1.3 All the mills supplying the raw material/pipes etc. shall be required to pass the tests required
for the procedure qualification testing. Approved procedure shall be common to all the mills.
7.2.1.4 In case a combination of different UNS No. has to be used, due to unavoidable reasons, each
combination shall be specifically subjected to welding procedure qualification testing
including all the corrosion tests.
Procedure qualification tests shall be performed on welded test pieces that include the parent
metal, heat affected zone and the weld metal.
The chemical composition analyzed shall conform to the claimed composition mentioned in
the technical brochures of the welding consumable manufacturers approved by the Company
prior to qualification.
The ferrite content measurement of test pieces shall be carried out by both of the following
method:
Metallography examination
Magna-gage method/Ferrite Scope
The procedure of ferrite measurement and the calibration of measuring instruments shall bear
the approval of the Company before being employed. Ferrite content measurement shall be
carried out by the metallography method in accordance with ASTM E 562. Acceptance level
shall be as per Clause No.5.3.
The weld metal of DSS and SDSS shall be checked by the method in accordance with ASTM
A 923, for the presence of intermetallic phases that are detrimental to the weld metal. The
intermetallic phases shall not be more than 1%.
These tests shall include tensile testing, impact testing and bend testing, in accordance with
ASTM A 370. Bend tests shall be performed with a plunger diameter equal to 4 times the
thickness. The acceptance values for tensile and impact testing shall be as per Clause Nos.
5.4.1 and 5.4.2. In case of bend testing, the specimen shall not reveal any crack or fissure.
Each qualification test shall include a cross-sectional hardness survey. The test method shall
be in accordance with ASTM E 18. The distance between indentations shall be a maximum of
1.0 mm. The hardness values shall not exceed RC 28 for DSS and RC 32 for SDSS.
If any other methods including portable hardness tester are to be deployed for checking
production welds, then the correlation between the qualification method and the production
method shall be established and the calibration graph shall be generated for use at the
field/shop. The acceptance criteria shall be as per Rockwell 'C' scale.
Sulphide Stress Cracking (SSC) test as per Clause No. 8.1, Chloride Stress Cracking (CSC)
test as per Clause No. 8.2, Pitting Corrosion test as per Clause No. 8.3, Crevice Corrosion test
as per Clause No.8.4, are mandatory when DSS and SDSS weldments are intended to be used
for sour service and chloride containing environments.
If DSS and SDSS weldments are intended to be used only for chloride containing
environments, the SSC test as per Clause No.8.1 shall be waived off. The remaining corrosion
tests specified in this section shall be carried out for DSS and SDSS weldments meant for use
in the chloride containing environments.
7.2.3.5 Radiography
All welds shall be 100% radiographed. The radiography procedure shall be followed as per
ASME Section V. Acceptance standard shall be as per ASME. Section-VIII, Division-1, UW-
51. The operator's certification to SNT-TC-1A or equivalent is required.
All fillet and groove welds other than those to be examined by radiography shall be tested by
fluorescent penetrant test or by fluorescent magnetic particle test. No defect indication shall
be accepted. The procedures for penetrant tests and magnetic particle tests shall be followed as
per ASME Section V. The operator's certification to SNT-TC-IA or equivalent shall be
ensured.
For DSS and SDSS, no post weld heat treatment is envisaged or recommended. In case,
autogenous welding is adopted or if the process licensor or the client recommends a PWHT,
then the only PWHT shall be solution annealing. The solution annealing heat treatment
procedures shall be established for ensuring retention of the properties of the welded joints for
DSS and SDSS materials. The heat treatment procedures shall be approved by the Company's
representative before their implementation.
Welders shall be qualified at the fabrication yard/barge employing the qualified welding
procedure. The qualification test pieces of each welder shall be subjected to microstructure
examination, mechanical tests, cross sectional hardness survey, radiography examination,
fluorescent penetrant and fluorescent magnetic particle tests, and with the same test procedure
and acceptance criteria as mentioned above in Clause Nos. 7.2.3.1, 7.2.3.2, 7.2.3.3, 7.2.3.5,
7.2.3.6 respectively.
DSS
SSC test on duplex stainless steel shall be carried out by using the following test solutions and
test conditions:
SDSS
The Sulphide Stress Corrosion Cracking tests on super duplex stainless steel shall be carried
out by using the following solutions and test conditions:
The CSC tests shall be conducted on representative specimens of DSS and SDSS, in
accordance with the testing procedure mentioned in ASTM G-36, in aerated, boiling 40%
calcium chloride (CaCl 2 ) solution at 100° C with the pH of the solution maintained
around 6.5.
Acceptance criteria: Stress to cause rupture in 500 hours shall exceed 0.85 times the
actual ultimate tensile strength values of duplex stainless steel and super duplex stainless
steel material individually.
DSS
The pitting corrosion test shall be conducted on the representative DSS specimen, in
accordance with ASTM G-48 method A, using 6% ferric chloride (FeCI 3 .6 H20) solution
by weight at 30°C, as well as at 50°C, for duration of 24 hours.
Acceptance criteria: No pitting shall occur on the surface of the test sample at 30°C. For
the testing at 50°C, the weight loss shall be reported to company for review.
SDSS
The pitting corrosion test shall be conducted on the representative SDSS specimen, in
accordance with ASTM G-48 method A, using 6% ferric chloride (FeCI 3 .6 I-1 2 0) solution
by weight at 40°C, as well as at 50°C, for duration of 24 hours.
Acceptance criteria: No pitting shall occur on the surface of the test sample at 40°C. For
the testing at 50°C, the weight loss shall be reported to company for review.
8.4 Crevice Corrosion Test
DSS
The crevice corrosion test shall be performed on the representative DSS specimen, in
accordance with ASTM G-48 method B, using 6% ferric chloride (FeCI 3 .6 H 2 0) solution
by weight, at 25°C for duration of 24 hours.
Acceptance criteria: No crevice shall form on the surface of the test sample at 25°C.
SDSS
The crevice corrosion test shall be performed on the representative SDSS specimen, in
accordance with ASTM G-48 method B, using 6% ferric chloride (FeCI 3 .6 H 2 0) solution
by weight, at 30°C for duration of 24 hours.
Acceptance criteria: No crevice shall form on the surface of the test sample at 30°C.
9.0 FABRICATION
9.1 No fabrication shall start until the Company approves the results of the welding consumable
qualification, the welding procedure qualification tests and the welder qualification tests as per
the approved procedure.
9.3 The weld joints not conforming to the specification requirements with respect to the results of
above tests, shall be cut out to make fresh joints. The reasons for such a breakdown in quality
assurance system shall be investigated and the report shall be submitted to the Company for
review.
The vendors/suppliers shall perform all the tests and inspection procedures mentioned above
to ensure that the welding consumables, the procedure and the fabrication conform to the
requirements of this specification. Company, or the representative duly approved by the
Company, shall have unhindered access for inspection and/or witnessing the selection of test
samples, the preparation of test specimens, and the performance of tests. The company or its
representative shall have the right to indicate the pieces from which the specimens are to be
drawn for various tests. In case of any reasonable doubts regarding the quality of the product,
Company shall have the option to ask for a re-qualification, at the vendor's/contractor's cost.
Inspection by the Company or its authorized representative shall not relieve the supplier of his
responsibility for ensuring the compliance of the materials supplied to this specification.
The vendors/suppliers shall submit the following records of the tests and inspection conducted
on the materials, as per the applicable Clauses mentioned in this specification, to the company
in quadruplicate:
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ OF MANUFACTURER
ISO 10497) / BS EN ISO 10497 / API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 19/12/2013
Page 168 of 196 540AF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 2 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ OF MANUFACTURER
ISO 10497) / BS EN ISO 10497 / API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 30/12/2013
Page 169 of 196 540AG
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 3 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ OF MANUFACTURER
ISO 10497) / BS EN ISO 10497 /API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
9 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
10 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
11 ONE VALVE PER SIZE SHALL BE HELIUM VACUUM TESTED AS PER ASME V, SUBSECTION-A, ARTICLE 10
(HOOD METHOD) APPENDIX IX TO CHECK SUITABILITY FOR VACUUM SERVICE.
12 VENDOR SHALL CERTIFY SUITABILITY OF VALVES FOR 10MM OF HgA VACUUM SERVICE AT INTENDED
TEMPERATURE.
13 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 19/12/2013
Page 170 of 196 540AH
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 4 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API 6D VALVES,MIN BODY WALL &
THICKNESS SHALL BE PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO OF MANUFACTURER
10497) / BS EN ISO 10497/API RP 6FA.
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
11 NACE REQUIREMENTS SHALL BE AS PER MR0103.
12 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
13 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
14 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 19/12/2013
Page 171 of 196 540AU
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 5 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497/API RP 6FA. OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
9 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
10 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
11 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 19/12/2013
Page 172 of 196 540BF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 6 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ OF MANUFACTURER
ISO 10497) / BS EN ISO 10497 / API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
13 VALVES SHALL MEET THE SPECIAL REQUIREMENT FOR ITEMS OF UOP2 IN MR AS PER DOC. NO. A307-00H-16-
43-SP-1001 AND FOR HYDROGEN SERVICE AS SPECIFIED IN 'TECHNICAL NOTES FOR VALVES'.
DATE 30/12/2013
Page 173 of 196 540BH
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 7 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497/API RP 6FA. OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
9 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
10 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
11 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
12 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 0.5" TO 0.75" -
SCH 80S & 1" TO 1.5"- SCH 40S
DATE 19/12/2013
Page 174 of 196 541AV
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 8 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497/API RP 6FA. OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
11 VALVES SHALL MEET THE NACE REQUIREMENTS AS PER MR0103 AND FOR HYDROGEN SERVICE AS
SPECIFIED IN 'TECHNICAL NOTES FOR VALVES'.
12 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
13 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 0.5" TO 0.75" -
SCH 80S & 1" TO 1.5"- SCH 40S
14 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
15 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 21/12/2013
Page 175 of 196 541BL
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 9 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497 / API RP 6FA OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
13 VALVES SHALL MEET THE SPECIAL REQUIREMENT FOR ITEMS OF SHL1 IN MR AS PER DOC. NO. A307-0IV-16-
43-SP-3001 AND FOR HYDROGEN SERVICE AS SPECIFIED IN 'TECHNICAL NOTES FOR VALVES'.
14 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 0.5" TO 1.5" -
SCH 160
DATE 30/12/2013
Page 176 of 196 541GH
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 10 of 19
OTHERS
SPECIAL SERVICE IBR1 (IBR + API RP VERY HIGH PRESSURE (VHP) STEAM; MAX.
CONDITIONS 934A) TEMP 538 DEG. C.
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497 / API RP 6FA OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D & IBR
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
13 VALVES SHALL MEET THE SPECIAL REQUIREMENTS FOR ITEMS OF IBR1 IN MR AS PER DOC. NO. A307-000-16-
43-SP-0001.
14 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 0.5" TO 1.5" -
SCH XXS
15 ALL VALVES SHALL BE SUPPLIED WITH IBR CERTIFICATE IN FORM-III C.
16 ALL VALVES SHALL BE PAINTED RED ON BODY-COVER JOINT.
17 VALVES TO COMPLY WITH DESIGN REQUIREMENTS OF IBR ALSO.
DATE 30/12/2013
Page 177 of 196 542EF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 11 of 19
OTHERS
SPECIAL SERVICE IBR1 (IBR + API RP VERY HIGH PRESSURE (VHP) STEAM; MAX.
CONDITIONS 934A) TEMP 538 DEG. C.
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497 / API RP 6FA OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D & IBR
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
13 VALVES SHALL MEET THE SPECIAL REQUIREMENTS FOR ITEMS OF IBR1 IN MR AS PER DOC. NO. A307-000-16-
43-SP-0001.
14 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 0.5" TO 1.5" -
SCH XXS
15 ALL VALVES SHALL BE SUPPLIED WITH IBR CERTIFICATE IN FORM-III C.
16 ALL VALVES SHALL BE PAINTED RED ON BODY-COVER JOINT.
17 VALVES TO COMPLY WITH DESIGN REQUIREMENTS OF IBR ALSO.
DATE 30/12/2013
Page 178 of 196 542EG
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 12 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ OF MANUFACTURER
ISO 10497) / BS EN ISO 10497 /API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
7 FOR TRUNNION MOUNTED BALL, BODY SEAT SHALL BE SPRING LOADED.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
9 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
DATE 19/12/2013
Page 179 of 196 544AF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 13 of 19
NOTES
10 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
11 10% VALVE CASTINGS SHALL UNDERGO RADIOGRAPHIC EXAMINATION.
DATE 19/12/2013
Page 180 of 196 544AF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 14 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497/API RP 6FA. OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
7 FOR TRUNNION MOUNTED BALL,BODY SEAT SHALL BE SPRING LOADED.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
12 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
13 10% VALVE CASTINGS SHALL UNDERGO RADIOGRAPHIC EXAMINATION
DATE 19/12/2013
Page 181 of 196 544BF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 15 of 19
NOTES
14 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
DATE 19/12/2013
Page 182 of 196 544BF
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 16 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 VALVES CAN ALSO BE SUPPLIED IN ACCORDANCE WITH API-6D. FOR API-6D VALVES, MIN BODY WALL &
THICKNESS SHALL BE AS PER ASME B16.34. SEAL
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO OF MANUFACTURER
10497) / BS EN ISO 10497 / API RP 6FA
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
7 FOR TRUNNION MOUNTED BALL, BODY SEAT SHALL BE SPRING LOADED.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 100% VALVE CASTINGS SHALL UNDERGO RADIOGRAPHIC EXAMINATION.
DATE 30/12/2013
Page 183 of 196 545AG
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 17 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497/API RP 6FA. OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
7 FOR TRUNNION MOUNTED BALL, BODY SEAT SHALL BE SPRING LOADED.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 100 % VALVE CASTINGS SHALL UNDERGO RADIOGRAPHIC EXAMINATION.
11 VALVES SHALL MEET THE NACE REQUIREMENTS AS PER MR0103 AND FOR HYDROGEN SERVICE AS
SPECIFIED IN 'TECHNICAL NOTES FOR VALVES'.
12 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
SHEET REV. NO. 0
DATE 21/12/2013
Page 184 of 196 546BL
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 18 of 19
NOTES
13 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
14 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 2" TO 6" - SCH
40S & 8"- SCH 80S
15 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
DATE 21/12/2013
Page 185 of 196 546BL
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
JOB SPECIFICATION NO.
VALVE MATERIAL
SPECIFICATION A307-6-44-0006 Rev. 0
Page 19 of 19
OTHERS
NOTES
1 THIS VALVE SPEC SHEET SHALL BE READ IN CONJUNCTION WITH TECHNICAL NOTES FOR VALVES.
2 ONLY IN THE CASE OF CATEGORY - II MRs,BIDDER SHALL CLEARLY WRITE ALL/ ANY DEVIATION AGAINST
EACH PART/ MATERIAL OF VALVE IN THE SPACE PROVIDED FOR AND WHEREVER BIDDER AGREES WITH
EIL'S SPEC BIDDER SHALL INDICATE "AGREED".
3 NO CUTTING/ OVERWRITING BY BIDDER ON EIL'S SPEC IS ALLOWED.
SIGNATURE
4 MINIMUM BODY WALL THICKNESS SHALL BE AS PER ASME B16.34. &
5 ALL VALVES SHALL BE FIRE SAFE DESIGN.FIRE SAFE TEST SHALL BE AS PER (API 607 IV EDITION/ (API 607/ ISO SEAL
10497) / BS EN ISO 10497 / API RP 6FA OF MANUFACTURER
6 TESTING SHALL BE AS PER BS EN 12266-1/API 6D.
7 FOR TRUNNION MOUNTED BALL, BODY SEAT SHALL BE SPRING LOADED.
8 ALL VALVES SHALL BE BIDIRECTIONAL.
10 BIDDER'S STAMPING ON THE VALVE SPECIFICATION SHEET SHALL BE CONSTRUED TO MEAN BIDDER'S
ACCEPTANCE OF SUITABILITY OF VALVE AND VALVE SHEETS FOR SERVICE AND 'SPECIAL SERVICE
CONDITIONS' MENTIONED IN THE VALVE SPECIFICATION SHEETS.
11 STEM SEAL/BODY SEAL MATERIALS SHALL BE PROVIDED WITH CORROSION INHIBITOR.
12 THE DIMENSION OF HAND WHEEL / T-TYPE LEVER SHALL BE WITHIN THE END TO END DIMENSION OF THE
BALL VALVE
13 VALVES SHALL MEET THE SPECIAL REQUIREMENT FOR ITEMS OF SHL1 IN MR AS PER DOC. NO. A307-0IV-16-
43-SP-3001 AND FOR HYDROGEN SERVICE AS SPECIFIED IN 'TECHNICAL NOTES FOR VALVES'.
14 VALVE ENDS SHALL MATCH THICKNESSES OF CONNECTING PIPES WHICH ARE AS FOLLOWS : 2" TO 3" - SCH
160, 4"-SCH XXS & 6" TO 8"- SCH 120
15 100 % VALVE CASTINGS SHALL UNDERGO RADIOGRAPHIC EXAMINATION.
DATE 30/12/2013
Page 186 of 196 547GH
Template No. 5-0000-0001-T2 Rev. 1 Copyright EIL-All rights reserved
DOCUMENT No.
ADDITIONAL TECHNICAL A307-000-16-43-ATR 3314
REQUIREMENTS Rev A
Page 1 of 4
Format No.
PageEIL187
1641-1924
of 196 Rev. 1 Copyright EIL – All rights reserved
DOCUMENT No.
ADDITIONAL TECHNICAL A307-000-16-43-ATR-3314
REQUIREMENTS Rev A
Page 2 of 4
1. Bidder to note that bid evaluation may be carried out without any post bid
correspondence.
2. Bidder shall furnish quotations only for those items (as per Vendor’s enlistment
with EIL) which he can supply as per MR specifications including fulfillment of
Qualification criterion as per MR.
3. If the bid does not include complete scope and technical/performance data,
proven track record (PTR) etc, required to be submitted with the bid, the offer
shall be liable for rejection.
4. The submission of prices by the Bidder shall be construed as compliance with all
technical specifications for the corresponding item(s).
8. For items specified under “NAC4” (i.e. NACE + H2), shall meet the requirements
of NACE and H2 service as specified in the Technical Notes for Valves,
6-44-0052.
9. For items specified under “IBR1” (i.e. IBR + API RP 934A), shall meet the
requirements as per the Doc. No. A307-000-16-43-SP-0001.
10. For items specified under “SHL1” (i.e. H2 + API RP 934C), shall meet the
requirements as per the Doc. No. A307-0IV-16-43-SP-3001.
11. For all MR items, Bidder shall furnish Proven Track Record (PTR) as given
below and shall meet the following requirements:
Format No.
PageEIL188
1641-1924
of 196 Rev. 1 Copyright EIL – All rights reserved
DOCUMENT No.
ADDITIONAL TECHNICAL A307-000-16-43-ATR-3314
REQUIREMENTS Rev A
Page 3 of 4
b) For Trunnion mounted Fire Safe Alloy Steel Ball valves (for MR.Sr.Nos.19
and 21):
i) The bidder shall be enlisted in EIL under Trunnion Fire Safe Ball
valves.
ii) The bidder shall have manufactured & supplied Forged/Cast Alloy
Steel (1.25%Cr/ 2.25%Cr/ 5%Cr/ 9%Cr) Fire Safe Trunnion Ball valves
in the last 7 years to be reckoned from the bid due date. Bidder shall
submit copy of the Purchase Order/Purchase Requisition / Inspection
Release Note for the same.
iii) PTR of submitted rating shall qualify items of same rating and below
(e.g. PTR of 300 rating shall qualify items in 300 rating and 150 rating)
iv) PTR of submitted size shall qualify items of same size and below (e.g.
PTR of 6” size shall qualify items sizes 6” and below).
b) For Trunnion mounted Fire Safe DSS Ball valves. (for MR.Sr. Nos. 20 and
21):
v) The bidder shall be enlisted in EIL under Trunnion mounted Fire Safe
Ball valves.
vi) The bidder bidder shall have manufactured & supplied Forged/Cast
Duplex SS (ASTM A182GR.F60/F51(DUAL)/ASTM A995 GR.4A UNS
J92205) Fire Safe Trunnion mounted Ball valves in the last 7 years to
Format No.
PageEIL189
1641-1924
of 196 Rev. 1 Copyright EIL – All rights reserved
DOCUMENT No.
ADDITIONAL TECHNICAL A307-000-16-43-ATR-3314
REQUIREMENTS Rev A
Page 4 of 4
be reckoned from the bid due date. Bidder shall submit copy of the
Purchase Order/Purchase requisition / Inspection release Note for the
same
vii) PTR of submitted rating shall qualify items of same rating and below
(e.g. PTR of 300 rating shall qualify items in 300 rating and 150 rating)
viii) PTR of submitted size shall qualify items of same size and below (e.g.
PTR of 6” size shall qualify items sizes 6” and below).
c) In addition to above, all corrosion tests and other tests reports, duly
witnessed by Third Party Inspector (TPI) as per EIL specifications 6-79-
0015 & 6-79-0016 shall be submitted along with PTR.
a) The bidder shall be enlisted in EIL under Floating Fire Safe Ball valves.
b) The bidder shall have manufactured & supplied Forged Inconel 625
(ASTM B564 UNS NO6625 (INCONEL 625)) Fire Safe Floating Ball
valves in the last 7 years to be reckoned from the bid due date. Bidder
shall submit copy of the Purchase Order/Purchase requisition / Inspection
release Note for the same.
c) PTR of submitted rating shall qualify items of same rating and below (e.g.
PTR of 1500 rating shall qualify items in 1500 rating and below rating)
d) PTR of submitted size shall qualify items of same size and below (e.g.
PTR of 1.5” size shall qualify items sizes 1.5” and below).
12. In case of any conflict amongst various documents enclosed with the MR, the
most stringent requirement shall govern and Owner/EIL decision in this regards
shall be final.
Format No.
PageEIL190
1641-1924
of 196 Rev. 1 Copyright EIL – All rights reserved
Document No.
VENDOR DATA REQUIREMENTS A307-000-16-43-VDR-3314
FOR Rev. 0
VALVES-BALL (CAT-II) Page 1 of 2
The following drawings/documents marked " " shall be furnished by the bidder.
VDR
POST ORDER
S. WITH WITH
N DESCRIPTION FOR FOR DATA REMARKS
BID
O. REVIEW RECORD BOOK
(FINAL)
1. Document Control Index
2. Detailed Dimensional Drawings For SW & BW end
metal seated ball
valves & as per ATR
3. PROVEN TRACK RECORD (PTR) AS PER
ATR ATTACHED WITH MR
Notes :
1. "TICK" denotes applicability.
2. Post order, drawing / document review shall commence only after approval of Document Control Index (DCI).
3. All post order documents shall be submitted / approved through EIL eDMS portal.
4. Final documentation shall be submitted in hard copy (Six prints) and soft ( two CDs/DVDs ) in addition to
submission through EIL eDMS.
5. Refer - 6-78-0001: Specification for quality management system from Bidders.
6. Refer - 6-78-0003: Specification for documentation requirement from Suppliers.
7. All drawings & documents shall be submitted in A4 or A3 paper sizes. Documents in higher paper size shall
be submitted in exceptional circumstances or as indicated in the MR/Tender.
8. Post order- The schedule of drawing / data submission shall be mutually agreed between EIL & the bidder /
contractor / supplier during finalization of Document Control Index (DCI).
9. Bill of Material shall form part of the respective drawing.
10. # Drawing reqired only for items of Manufacturers standard
UNIT : VGOHDT
PROJECT : IREP, BPCL-KR
1.1 These requirements are applicable for 1 1/4 Cr-1/2 Mo piping material.
1.4 All fabrication requirements as per API RP 934-C for welding consumables,
welding procedure and qualification, heat treatment, testing including NDE
etc.,as applicable, shall also be complied at shop as well as at field.
2 GENERAL INSTRUCTIONS:
1.1 These requirements are applicable for 2 1/4 Cr-1 Mo piping material.
1.3 In addition to the requirement of API RP 934-A, requirements of IBR as per EIL
Specification /standard shall also be applicable and complied.
1.4 All fabrication requirements as per API RP 934-A for welding consumables,
welding procedure and qualification, heat treatment, testing including NDE
etc.,as applicable, shall also be complied at shop as well as at field.
1.5 These requirements are applicable for piping classes G2E & G22E.
2 GENERAL INSTRUCTIONS: