METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

1.0 Introduction

The Heating Ventilation Cooling Air-conditioning System (HVAC) equipment selected for the
Alfaisal University is of the Chilled Water system.
The Chilled water system shall be made up of the various associated components namely:-

1. Water Cooled Type Liquid Chiller

2. Cooling Towers

3. Primary and Secondary Centrifugal End-suction Chilled water pumps

4. Condenser water Centrifugal End-suction pumps

5. Chilled water type Air-handling units

6. Chilled water type Fan Coil units

7. Pre-insulated Black steel Chilled water pipes

8. Galvanized Condenser water pipes

9. Associated water valves

10.Insulated Galvanized iron ductwork system

11.Electrical Motor Control Centres including interconnection power and control wiring

12.Host of other associated necessary services

1
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

2.0 Equipment Selection

The Water-cooled Liquid Chillers selected for the HVAC System will be made up of five (5)
units with a cooling refrigerant capacity of 900 Tons each, total refrigerant tonnage is 4500.
Tag Name: Selection 1 S.S 380’) as provided by “Carrier” Evergreen Chiller Performance
Outputs.

Technical data: ( as extracted from ‘ARABIAN AIR CONDITIONINGN CO.

Chiller
Chiller Model………………………..19XR-7071477DKH62
Starter / VFD………………………...Starter – Unit Mounted, Solid State
Refrigerant Type……………………..R-134a

Cooler
Size…………………………………..70
Waterbox Type………………………Nozzle-in-Head, 1034 kPa
Passes………………………………...2
Tubing………………………………..Turbo-EDE (TBE), .635mm, Copper
Fluid Type……………………………Fresh Water
Fouling Factor (sqm-K)/kW………….0.01761

Compressor
Size…………………………………...477

Flow Controls
Float Valve Size……………………...15
Flasc Orifice………………………….68

Weight
Total Rigging Weight………………...13,561 kg
Total Operating weight……………….15,556 kg
Refrigerant Weight…………………… 907 kg

Condenser
Size……………………………………71
Waterbox Type……………………….. Nozzle-in-Head, 1034 kpa
Passes………………………………….2
Tubing…………………………………Spike Fin III (SPK3),.635mm, Copper
Fluid Type……………………………..Fresh Water
Fouling Factor (sqm-K)/kW…………...0.04403

Motor
Size…………………………………….DKH
Line Voltage/Hertz…………………….380-3-60

2
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

3.0 Tag Name:( Selection 1 S.S 380*) as provided by “Carrier”


Evergreen Chiller Performance Outputs
Technical data
Chiller Model……………………..19XR-7071477DKH62

Output Type Full Load


Percent Load 100.00
Chiller Capacity 900 Tons *
Chiller Input kW 608 kW
Chiller Input Power 0.675 kW/Ton
Cooler
Entering Temp. 12.0C
Leaving Temp 6.0C
Flow Rate 125.0 L/s
Pressure Drop 62.1 kPa
Condenser
Leaving Temp 34.8C
Entering Temp 30.0C
Flow Rate 188.0 L/s
Pressure Drop 74.8 kPa
Motor
Motor Input Power 606 kW
Motor RLA 1010
Motor OLTA 1091
Motor LRDA 5678
Motor Inrush Amps 2555
Chiller RLA 1013
Max Fuse/CB Amps 2000
Min Circuit Ampacity 1266

Certified in accordance with the ARI Water-Chilling Packages


using the Vapor Compression Cycle Certification Program, which is
based on ARI Standard 550/590-2003

3
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

4.0 Equipment Capacity

Equipment selected for the Alfaisal University HVAC System consist of five (5) ‘Carrier’
Centrifugal water-cooled type Liquid Chillers model 19XR 7071477DKH62S

Components of ‘Carrier Centrifugal water-cooled Liquid Chiller


( As extracted from ‘Carrier Literature form 17/19XR-2PD )

1. Single stage ‘Hermetic Type’ centrifugal compressor complete with motorized variable guide
vanes, internal transmission gears, Cast iron impellers, bearings and integral lubrication system
with auxiliary pump.

2. Compressor squirrel cage induction motor type refrigerant cooled.

3. Cooler and Condenser section – fabricated with 0.025” thick H.P. copper tubes /steel shell
and tube sheets / steel water boxes.

4. Metering valve to maintain proper liquid level of refrigerant in the Heat exchanger.

5. A Microprocessor Control Centre.

Equipment Physical Dimensions and weight.

The physical dimensions of each Liquid Chiller of the ‘19XR’ model are as follows:-
Length – 4.400m x Width – 2.124m x Height – 2.245m
Rigging Weight – 13,561 kg

4
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

5.0 Location of HVAC Water-cooled Liquid Chillers

The water-cooled Centrifugal Liquid Chillers will be located on 200 high concrete plinths at the
Ground floor area of the Utility Building (Grid 1-6/A-D)

5
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

6.0 Logistic

Transportation of Equipment to site shall be via five (5) Heavy duty Trailers. Schedule delivery
should be by 9 Sept 06.

Unloading shall be at selected area i.e. open space beside the Utility Block and ‘Future Ice
Storage’ at Grid 3-4/D.
(refer to attached A4 sketch – Utility Ground Floor Proposed Chiller Temporary Storage)

Unloading of the Chillers will be via a 25Tons Mobile Crane.

6
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

7.0 Installation Period :-(refer to attached ‘Milestone Microsoft Project


Schedule)

(a) Preliminaries

Preparation of Preliminaries shall be from 2 Sept 06 to 7 Sept 06.- consist of the following:-

(i) Installation of Scaffolding

(ii) Placement of Flat Steel Plate platform on scaffolding structure

(iii) Placement /arrangement of I-Beams

(b) Chiller Equipment Installation

Physical installation of five (5) units shall be from 9 Sept 06 till 20 Sept 06

7
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

8.0 Installation Procedures

To carry out the exercise, we proposed to provide seven (7) skilled personnel.
Procedures – four (4) stages are proposed:-

(a) Chiller Equipment units on arrival shall be hoisted to the temporary storage area
(refer to A4 sketch plan view of location – Proposed Chilled Temporary Storage)

8
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

8.0 Installation Procedures (continue)

(b) The next procedure is to route the Chiller into its location i.e. by hoisting Chiller onto the
entrance of loading dock of the Utility Block. Loading area consist of a 10mm thick Flat
steel platform.
This platform shall be supported by steel scaffolding. Placed on the flat steel platform will be
dimensionally arranged steel I-Beams of 250 x 250 x 10mm thick.
(refer A4 sketch of the temporary loading dock - ‘Load Skates Position’ / section A-A)

SECTION A-A

LOAD SKATE POSITION

9
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

8.0 Installation Procedures (continue)

(c) A array of ‘Rail’ system using 250 x 250 x 10mm thick I-Beams shall form the route to
five (5) nos. ‘Chiller’ concrete plinths.

10
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

8.0 Installation Procedures (continue)

(d) To ‘transport’ the Chillers to destination, four (4) Heavy Duty Load Skates’ of nominal
tonnage of 10Tons each will be strategically placed on the I-Beam.

These Chiller units shall then be mechanically ‘rolled’ to and placed on the concrete plinths.
(refer to A4 sketch plans – ‘Load Skates Position’ and section A-A and Steps 1 – 3 –
Proposed Chiller Installation Routing for CH10/1)

11
METHOD STATEMENT

Installation of ‘Carrier’ Centrifugal Water Cooled Liquid Chiller

8.0 Installation Procedures (continue)

(e) Once the Chillers are positioned, four (4) spring isolators will be installed on the four (4)
ends of the Chiller steel foundation frame.

To install these spring isolators, we propose to use15Tons Hydraulic Pumps.

End of Method Statement.