OFFICE NOTE

Sub :- Constructing remaining work of Kaniel and Torna minors and their sub
minors (earthwork, C.C. lining, C.C. conduit and structures) in the
command area of Mahemdavad branch canal

- Proposal for approval of extension of time limit without benefit of


the price escalation
- Agency :- M/s. K. C. Suthar, Modasa
Ref :- S. E., N. P. Canal Circle No. 5, Gandhinagar’s letter No. NPCC-5/ AS(C)/
TC/1997 dtd. 24.08.2012

A proposal for approval of extension of time limit from 29.09.2011 to 15.01.2012 (109
days) without benefit of the price escalation for the work under captioned subject has been
submitted by the S.E., N.P. Canal Circle No.5, Gandhinagar vide his letter under reference. The
tender for the said work was approved in favour of M/s. K. C. Suthar, Modasa by the S.E., N.P. Canal
Circle No.5, Gandhinagar vide his letter No. NPCC-5/ AS(C)/TC/4416 dated 29.11.2010. The details of
work and tender is as under.

1 Name of work Constructing remaining work of Kaniel and Torna


minors and their sub minors (earthwork, C.C. lining,
C.C. conduit and structures) in the command area of
Mahemdavad branch canal

2 Estimated cost put to tender Rs. 55.77 lacs


3 Amount of accepted tender Rs. 49.38 lacs ( 11.46 % below)
4 Name of agency M/s. K. C. Suthar, Modasa
5 Agreement No. B- 2/2 of 2010-11
6 Date of work order 29.12.2010
7 Stipulated date of completion of 28.09.2011 ( 9 months)
work
8 Status of work Work is completed on 15.01.2012
9 Extension of time limit granted, if No
any
10 Amount of work carried out in Rs.23.60 lacs
stipulated time limit
11 Extension of time limit demanded by Upto 15.01.2012
the agency
12 Extension of time limit From 29 .09.2011 to 15.01.2012 (109 days) without
recommended benefit of the price escalation
13 Price escalation payable on account As there is no provision of price escalation in the
of extension of time limit tender, price escalation will not be paid

2.0 Agency could not complete the work within the stipulated time limit i.e. upto 28.09.2011.
Agency has applied for extension of time limit upto 15.01.2012 vide his letter dated 25.08.2011
stating the reasons for delay in completion of work. The reasons putforth by the agency for
extension of time limit are evaluated by the SE/EE and reasons considered for extension of time limit
are as under.

Sr. Reason Work is delayed for the period Extension of time limit
No. recommended on
account of each reason
1 Farmers opposed to give 44 days 44 days
possession of acquired land in ( 16.02.2011 to 31. 03.2011)
ch. 200 m to 350 m and ch. 800
to 1200 m for want of award
payment
2 Additional structures for 65 days 65 days
crossing sub minor canals as ( 28.06.2011 to 31.08.2011 )
per representation from
farmers and representatives of
local bodies and according to
site condition, were provided
3 Non availability of required 40 days (20.02.2011 0 days
borrow area within prescribed to 31.03.2011 ) Overlaps with
lead and late permission from reason at Sr. No. 1
the Panchayat
Total 109 days

As the work has been completed on 15.01.2012 and the reasons for delay in completion of work are
not attributed to the agency, it is recommended to approve the extension of time limit from
29.09.2011 to 15.01.2012 i.e. 109 days without benefit of price escalation by the EE/SE. As there is
no provision of price escalation in the tender, there will not be any financial implication on account
of price escalation due to extension of time limit.
3.0 In accordance with the powers delegated vide Nigam’s circular No. CPC/ TLE/2011/646 dated
27.07.2011 to sanction the extension of time limit, where price adjustment is not involved, the Chief
Engineer is empowered to sanction the extension of time limit for the tenders amounting upto Rs. 3
crores subject to prior approval of the MD for extension beyond 4 (four) months.