Professional Documents
Culture Documents
60 CON NSH MS C 0040 - Rev.H
60 CON NSH MS C 0040 - Rev.H
KINGDOM OF SAUDI ARABIA DOCUMENT TRANSMITTAL Date : 05-Oct-19 To. :UK EUI
SONG : Construction Manager SSA Project No. : $C6122 Samsung Saudi Arabia Co., Ltd. |
Transmittal No.: | NSH-SSA-TRE-1860 United EO/EG III Project J Reference No.: | SSA-NSH-
TRE-1140 THE FOLLOWING : o COPIES (C) = ORIGINAL (2) u ELECTRONIC ARE
TRANSMITTED FOR: mw APPROVAL o REVIEW o INFORMATION o CONSTRUCTION o
REFERENCE o FINAL SPECIALIST DISCIPLINE : m PROJECT MANAGER ao PROCESS ao
MECHANICAL(S) a MECHANICAL(R) o PIPING a CIVIL o ARCHI. & STRUCTURE o PROCESS
CONTROL o ELECTRICAL o FIRE FIGHTING o HVAC o EHSS a CATHODIC PROTECTION co
PROCUREMENT a CONSTRUCTION ao COMMISSIONING a QA/QC co OTHERS AREA /
LOCATION o ISBL a OSBL o COMMON Sr. 5 Review No. Document Number Rev. Title Clase
01 | 60-CON-NSH-MS-C-0040 H Method Statement for Backfilling of 132” CW Line
Notes:
/ RAJEEV GEORGE Project Manager United EO/EG Ill Project
u Please acknowledge the receipt on the duplicate and return.
Received Stamp
1/1
2. DEFINITIONS
3. REFERENCES
4. GENERAL
5. ORGANIZATION CHART
8. WORK PROCEDURE
9. INSPECTION
10. SAFETY
No part of this document or the information it contains may be reproduced or transmitted
in any form a 34> i iH or by any means electronic or mechanical, including photocopying,
recording, or by any information storage and retrieval system, without permission in
writing from SABIC or Samsung Engineering.
united SoETT> samsens oatgll es pall dupa
REE AA NASSER S. AL-HAJRI CORPORATION
Auli sabia
Doc. No 60-CON-NSH-MS-C-0040 METHOD STATEMENT FOR Revision No H BACKFILLING
OF 132” CW LINE Revision Date 19-Sep-2019 Page 7 of 9
8.2.2
8.2.3
8.2.4
8.2.5
8.2.6
8.2.7
8.2.8
8.2.9
approved third party and witnessed by SSA/PMT. Up-to ground water level dewatered
water will be used or as agreed united/SSA.
Haunch area shall perform the mock-up test in presence of SSA/PMT to ensure the proper
backfilling and to achieve the required compaction density as per SES requirements.
The ground water will be used for compaction purpose up-to ground water level.
Backfilling will be carried out by long boom excavator, bobcat, and loader from the access
area (south area).
The shoring material will be removed from the north side of CW line 132”. The shoring
removal activity shall be witnessed by SSA/PMT and a checklist shall be ticked and signed.
The granular soil material shall be used above 300mm from Top of the pipe. It will be
compacted to a firm and stable condition using an appropriate compacting device. The
compaction density shall be achieved per SES requirements.
Backfilling will proceed symmetrically on both sides of the pipeline and in between the
pipelines.
During the backfilling work, disturbed/deformed soil condition near shoring shall be
checked and reported at site.
Disturbed/deformed soil shall be reinstated as original condition with SES requirements.
8.3 Backfilling method of Area -1 & 2
8.3.1
8.3.2
8.3.3
8.3.4
Backfilling shall be done from south side only as the north area is restricted for access due
to existing 132” U/G CW line.
Long boom excavator shall be placed on south side of 132” CW line.
The joints shall be kept exposed for inspection during hydro test as per SES requirements.
Where existing pipe rack is nearer to the north of the 132” line, it is not possible to work
with the long-boom excavator. Therefore, Bobcat will be used to transfer the soil close to
the location of the excavated area and these areas will be back filled manually.
Garipgll
united
No part of this document or the information it contains may be reproduced or transmitted
in any form or by any means electronic or mechanical, including photocopying, recording,
or by any information storage and retrieval system, without permission in writing from
SABIC or Samsung Engineering.
eT samsuns . Goat) dyes pal Asst Ga
SAUDI ARABIA NASSER S. AL-HAJRI CORPORATION