OIL AND NATURAL GAS CORPORATION Ltd.

EVENING DRILLING REPORTS DTD: 11TH MARCH 2020 /1800 HRS /NRS.
1. S/BHUSHAN = WO_24#K (WO_24#11)/119 DAYS (SINCE SPUDDING)/ PT DAYS-4/2717/2717/2607(REVISED TD)/NIL. 0600-1200: REPLACED BURST HOSE OF RGA. TESTED – OK. 1200-1500: POOH
2 STANDS OF 6 ½” D/C UP TO 50M. MADE UP TEST ASSEMBLY. TESTED FLEX BHA AT 5500 PSI – PRESS NOT HOLDING. R/DN TEST ASSEMBLY. 1500-1600: CONTINUE POOH 1 STAND OF 6 ½” D/C UP TO
33M. MADE UP TEST ASSEMBLY. TESTED AT 5500 PSI – FOUND OK. R/DN TEST ASSEMBLY. 1600-1800: IDENTIFIED LEAK & REJECTED ONE STAND OF 6 ½” D/C & ONE SINGLE OF 6 ½” D/C. CONTINUE
RIH 02 STANDS + 2 SINGLES OF 6 ½” D/C UP TO 100M. FURTHER RIH IP. NOTE – POT WATER STOCK VERY-VERY CRITICAL. BOTH WATER MAKERS NOT WORKING. BOTH C-BAND PHONE NOT WORKING
FROM 13.00 HRS OF 10.03.2020. DRILL PARA: NIL BIT DETAILS –NIL. LITHOLOGY: NA. MUD PARA: MW-9.6ppg, Visc-56, (1425 M-2552 M), SEA WATER (0-1425 M). ANCHOR TENSION– 1#: 55 T, 2#:56
T, 3#: 32 T, 4#: 48 T, 5#: 52 T, 6#: 36T, 7#: 55T, 8#:65 T. WEATHER PARA– WX-WIND- 270°/08 KNOTS, ROLL-0.5°, PITCH-0.9°, HEAVE-0.7M, SWELL- 260°/1 M, BARO-1009 MB, SHIP HEADING-
224°. POB: 118 (ONGC- 44 + CONT- 74), SBB –NIL, ACCIDENT-NIL. URGENT REQUIREMENT – POT WATER- 200 MT (STOCK NIL), DW-200 MT (STOCK NIL), FUEL OIL-100KL, DA CYLINDER, OSV TO
BACKLOAD 11 NO 7” L-80 CASING PIPES TO NHAVA, 18 NOS OF 6 ½” DC FROM NHAVA STO NO- 4920442394. NITIN NANDANWAR/ROBI SIKDAR/ABDUL WAHID/MAQBOOL AHMAD
2. S/GAURAV = WI_9#2/15 DAYS/WOJ/BRINE PREPARATION. 0600-0800: WELL UNDER OBSERVATION. STHP- 240 PSI, SCHP- 270 PSI. 0800-1200: C/O FORWARD CIRCULATION FOR TWO CYCLE. KEPT
WELL UNDER OBSERVATION FOR ONE HOUR IN OPEN CONDITION. OBSVD CONTINUOUS FLOW FROM TUBING & ANNULUS. WELL UNDER OBSERVATION IN CLOSED CONDITION. MEAN WHILE RECEIVED
SALT FOR BRINE. 1200-1800: M/A & PREPARATION OF BRINE IP. REMARKS: 1) PHONE NO- 26562989 & 26562995 ARE NOT WORKING. URG.REQ: 1) SALT FOR BRINE VIA OSV CELESTIAL. 2) BACK LOAD
BOAT FOR TOWING GEARS FOR INSPECTION & CERTIFICATION. 3) 2 7/8”SLIP & ELEVATOR, X/O 3 ½” IFB X 2 7/8” IFP FROM VICTORY DRILLER. 4) 4 ¾” FISHING JAR FROM SAGAR UDAY. 5) 30” CSG
ELEVATOR, 30” CUL BUSH, 30” CSG SLIP, 9 5/8” CSG TONG JAWS & 26” STABILIZER FROM S/SHAKTI. ACCIDENT- NIL. POB- 49+40=89. FSBB-SAGAR FORTUNE. =R.B.CHIMNANI/ MATA KUDADA/GOVIND
KUMAR.
3. S/JYOTI = B_55A#2/PREP FOR RIG MOVE/2 DAYS: 06:00-18:00 LIFTED 9 5/8” CSG TO RIG FLOOR. R/UP 9 5/8” CSG HANDLING TOOLS. M/A TO POOH 9 5/8” CSG. OBSD 2 JTS OF 9 5/8” CSGS
SIGNIFICANTLY TIGHT, HAD TO CUT FROM PIN END FOR L/DN. TOTAL JTS P/O & L/DN (3 FJS & 4 CUT PCS). R/DN 9 5/8” CSG HANDLING TOOLS. N/DN WING VALVES OF ‘B’ SECTION. OPENED STUDS
B/W ‘A’ SEC & ‘B’ SEC. N/DN ‘B’ SECTION. M/A FOR SURFACE CHECK OF 8 1/8” CSG CUTTER IS IP. NOTE: 1) CLEANING OF MUD PIT -1 IS IP. U/R: PW-150MT, DW-150MT (STOCK NIL), SCHL CSG
CUTTER FROM SAGAR UDAY: 81229834, BLB FOR DRILL PIPES FOR NDT, ONGC EMPTY GAS CYLS & MISC LIFTS, IFT OF MUD CHEMICALS FROM S JYOTI TO D S FORTUNE (DN: 81229913). POB: 78
(ONGC-42+SERVICES-36), ACCIDENT:-NIL, SBB: HALUL-27, R.C. KHAILKHURA/RAKESH RANJAN.
4. S/KIRAN = B_192#S/26 DAYS/OBJ-1(2417M-2414M) =0600-1800: P/O DST STRING FROM 1968 M TO 225 M. FURTHER P/O & L/DN OF EXPRO DST BHA IS IN PROGRESS. NOTE: ONGC DA STOCK
NIL SINCE 22/02/2020, REQ.URGENTLY.WELL FLUID: BRINE-9 PPG.POB: 48/41, SBB: ASL BAGULA, ACCIDENT: NIL =AMARENDRAKUMAR/S.SARDAR/A.PRABHAKARAN/MANISH SHARMA.
5. S/RATNA = GOM NOT YET SUBMITTED UN DOCKING PLAN. M/A FOR STAND BY PUMP FOR SEA WATER FROM SHORE SUPPLY IN PROG RIG DOWN B/OUT TONG PULLEY. MPI OF B/OUT TONG PULLEY
ASSEMBLY AND AFT SIDE AIR WINCH PULLEY ASSEMBLY IS IN PROGRESS. MECH DPR. 1) DESANDER PUMP: - REMOVED CASING, IMPELLER, OBSERVED PLAY IN THE BEARING SO REMOVED SHAFT AND
BEATING ALSO, FURTHER WORK IN PROGRESS. 2) CRANE (S):- GREASING CARRIED OUT, LO CHECKED 3) CRANE (FWD):- ITS BOOM AND AUX WINCH OPERATIONS GOT HAMPERED SO
TROUBLESHOOTING WAS CARRIED OUT AND MADE IT OPERATIONAL. 4. COMPRESSOR 2: TOP UP HLP68 IN ITS OIL TANK. 5. STP: FOUND IT’S TOP AND SIDE PLATE IN BAD CONDITION SO FABRICATED
ITS SIDE PLATE WITH MOUNTING BOLTS AND GET WELDED NEAR LEVEL SWITCH SENSOR. FURTHER MAINTANENCE IS IN PROGRESS. POB:69 ACC: NIL LAALU/AKHIL
6. S/SHAKTI = CA#C/29/2130/1530/1534/ 13 3/8" CASING & CEMENTATION JOB: 0600-1030: M/UP CIRCULATING HEAD AND ESTABLISHED CIR. CIRCULATED OUT CUTTINGS AND CLEARED HOLE.
ADDED ONE SINGLE 13 3/8" CSG PIPE AND LOWERED IT UPTO 1525 M AND CASING RESTED ON 20" MLS. CONNECTED CMTG HEAD AND ESTABLISHED CIR. 1030-1300: CC MUD PRIOR TO CEMENTATION
JOB. 1300-1600: C/OUT CEMENTATION AS PER PLAN. PUMPED PREFLUSH 50 BBL, CEMENT SLURRY 250 BBL (15.2 PPG) AND DISPLACED SLURRY WITH 739 BBL OF MUD (10.8 PPG). PLUG HIT AT 1500
PSI. CHECKED NRV, OK. CLOSED ANN.BOP FOR 06 HRS. 1600-1800: WOC. MEANTIME, C/OUT GEN MAINT. JOB AT D/FLOOR. MW-10.8 PPG, VIS-45, PH-9.0. TOTAL NO. OF CSG LOWERED - 131 NOS. F/S-
1525 M, F/C-1501 M, MLS LANDING RING - 78.6 M. NOTE: 1) 'C' BAND PHONE NOT WORKING. 2) PAGING SYSTEM AT SOME PLACES NOT WORKING. 3) COMPR-1 OUT OF ORDER. U/R: 1) PW-200 MT. 2)
DW-200 T. 3) BAR-75 T. 4) 4 1/16" G-VALVE REPAIR KIT. POB: 82. ACCIDENT-NIL. SBB: HALUL-27, DISTANCE: 5 NM = M.K.GUPTA/ DIJO/ BHARAT=
7. S/UDAY = D_1#D2/DAY-6/RIG MOVE PREPARATION : 0600-1800- CARRIED OUT TORQUING OF JACKING MOTORS,LOWERED HULL TO 18 FT AIR GAP, WOW TO CONNECT TUGS AND DO
WTI.M/TIME COGM. WX PARA: WINDS-300/20 KTS, SWELL-300/2.5 MTR. NOTE: 1) C-BAND PHONE NOT WORKING PROPERLY.2) RIG AIR DRYER UNIT IS OUT OF ORDER SINCE OCT, 2019; RIG
EQUIPMENT ARE SUFFERING. 3) TDS AUTO BRAKE FUNCTION NOT WORKING. SBB-G S ASMI & SUBHAPRADA. POB-75(ONGC-52+SERVICES-23), ACCIDENTNIL=V.JAIN/RAVI
8. S/VIJAY = MBSO53NAC#A/04DAYS/ DE-ANCHORING: 0600-1800: AHB OFFSHORE ENERGY REPORTED @ 0915 HRS AT LOCATION FOR ANCHOR HANDLING JOB. TRANSFERRED CREW OF BOTH AHBs
TO RIG AND C/O PRE-JOB SAFETY MEETING ON BOARD PRIOR TO RESUME DE-ANCHORING JOB. TRANSFERRED ANCHOR JEWELLARY TO BOTH THE AHBs. AHB O/E PREPARED HER DECK AND
APPROACHED FOR PENDANT WIRE OF ANCHOR#3, RECEIVED CHASER PENDANT. RIG HEAVED IN ANCHOR WIRE#3, AHB O/E CHASED BACK ANCHOR WIRE#3 AND ON LOCATION AT ANCHOR#3. ABH
L/SANDRA PREPARED HER DECK AND APPROACHED FOR PENDANT WIRE OF ANCHOR#7. PASSING CHASER PENDANT#7 TO AHB. L/SANDRA IP. M/WHILE (1) CLEARING OF ALL SHAKER TANKS IP.
(2)COLLAPSED ALL RTs. UR REQ: 1) BARITE=100MT 2) FUEL OIL=150KL.3) ANCHOR CHAINS-08NOS (880M LENGTH).4) RISERS 70’ FLOATATION =03NOS, 70’SLEEK=02NOS & 50’SLEEK =02NOS. 5)
30”LP WELL HEAD=1NO. 6)20”HPWH=1NO. 7)30”CASING JOINTS=01NO. 8)20”CASING JOINT=1NO.9)20”AND 30”CSG GUIDE SHOE-1 NO. 10) PGB+04 POSTER-1 NO. WX: HEADING:046˚, WIND:
330˚/10K, SWELL:300˚/ 0.8 m, ROLL:1.0˚, PITCH:1.0˚, HEAVE:0.8 m,BARO:1009,TEMP:25˚C, CURRENT-215x1, VIS:5 NM, SKY- CLR. AT: 1- 48, 2- 47, 3-65, 4- 40, 5- 55, 6- 62, 7- 61, 8-65. POB:
91(O-35,C-56), A=NIL,SBB= OFFSHORE ENERGY & LADY SANDRA.= S.S.PUROHIT/VINOD SWAMINATHAN
CONTRACT RIGS
1. ABAN-III = R_7A#3/20 DAYS/2737 M/2550 M/1410M/ 18M / M/UP RSS+LWD ASSY IIP.0600-0800: DRLD / CLRD 12-1/4” HOLE WITH HLB RSS + LWD ASLY F/1392M TO 1410M. OBSD CONT ANGLE
DROPPING & UNABLE BUILD / HOLD THE ANGLE TO MAINTAIN HOLE PROFILE, INFORMED TO BASE & DECIDED FOR POOH CHECK TOOLS. PUMPED HI-WT ALTERNATE DRLD STD & REAMED ONCE. 0800-
0900: C&C MUD PRIOR TO POOH @ 800 GPM / 1890PSI.0900-1030: POOH 12-1/4” BIT WITH HLB RSS + LWD ASLYF/1410M TO 1009M, OBSD NO T/PULL. 1030-1300: POOH F/1009M TO 724M SGL BY SGL
30 JTS & L/DN FOR NDT. 1300-1430: CONT POOH F/724M TO 37 M. ART D/JAR @ 1400 HRS. 1430-1600: L/DN RADIOACTIVE SOURCE & DOWNLOADED LWD DATA. 1600-1730: POOH & R/BACK LWD
ASSY. L/DN 12 ¼” BIT AND RSS. P/O BIT CONDITION: 1-1-WT-T-X-I-CT-DTF.1730-1800: M/A & P/UP NEW RSS WITH LWD ASLY IIP.LAST SURVEY: MDKB: 1401.62 M / INCL: 62.03 °/ AZM: 166.93 °/
TVDKB-1004.22 M.DRLG PARA: WOB-15-20KLBS, RPM-130, GPM-760, SPP-1800PSI, TQ-2-9 KFTLBS.BIT DETAILS: 12-1/4”PDC (NEW), TYPE-GTE56MKOs, SL-13420600, NOZZLE-5X14 & 2X16, MTG-203M,
HRS-12. WELL FLUID: SOBM, WT-9.5PPG, VIS-60, PV/YP 26/23, GEL 15/24, OWR 69/31, SOLID 12%, LIME-2.0PPB, HTHP-6.8 ML, ES-495, WPS-158380PPM, CL-48000. UR: (1) FUEL-75KL (2) PREMIX -300
BBL (3) DW-100 MT (4) BENTONITE-10 MT (5) ‘C’ SEC WH-01, X-MASTREE-01 & 9-5/8” CSG F/NHAVA (6) W/FORD CDS FOR 9-5/8” CSG. BACK LOAD BOAT FOR: 04-JTS 20” CSG TO NHAVA, DN-81230003.
ACCIDENT: NIL. POB: 86 NOS (ONGC-9, ONGC SERV-18, ABAN CREW-42, ABAN SEV-03, CATERING-14). SBB-ABS AMELIA (DIST-07NM). F .A. KHAN / SENAPATI / V. KUMAR/ SANDEEP
2. ABAN -1V = SJ#3/10/2180 M/WOJ/RIH 8-1/2” SLICK ASSY 0600-0730: M/UP 8-1/2” PDC BIT WITH BHA & RIH UPTO 84M. 0730-1430: P/UP & M/UP 72 SGLS 5-1/2” DP & RIH UPTO 744M (TOTAL
SGL-72). 1430-1800: CONT RIH 8-1/2” PDC BIT ASSY WITH 5-1/2” DP STDS F/744M TO 2007M. FRIP. NOTE: 1) LUBRICATED B-SEC WITH 15PPG MUD. 2) DRIFTED ALL TUBULARS. 3) STATIC LOSS-
60BPH. WELL FLUID: 8.6 PPG BRINE. U/R: 1) D/W- 100 MT. POB: 74 (ONGC-4, ABAN-45, ABAN EXTRA-4, ONGC SERVICES-7, CATERING-14). SBB: S/FORTUNE– 7NM. ACCIDENT: NIL / H.CHAUHAN/
YUVRAJ/ DNYANESHWAR
3. ABAN ICE = BH#V/25/2167 /1377/ 1377M (SECTION TD)/-/ 0600-1030: CONT POOH FROM 1024 M TO 490M (INSIDE SHOE) NO RESTRICTION IN OPEN HOLE. FLOW CHECK AT SHOE –OK. CONT
POOH TO SURFACE.L/D BIT .RETRIEVED TOTCO BARREL. SURVEY READING – 1/4°DEG. 1030-1530: REPAIRED TRAVELLING BLOCK DOLLY ROLLER. 1530-1700: R/UP & M/UP 13 3/8" CASING HANGER
WITH CEMENT RUBBER PLUGS & RACK IN DERRICK. 1700-1800: RIH JET SUB TO WH. JETTED WELL HEAD AREA. M/UP WBRT WITH STRING FURTHER RIH WITH WBRT TO RETRIEVE NSP IS I/P PRIOR TO
P/UP 13-3/8” CASING SHOE. PULLED OUT 17-1/2”PDC BIT GRADING: 1-1-CT-G-X-I-WT-TD. MUD PARA: M/WT=10.5PPG, VIS=56. UR DW=200MT. WX: WIND=320°/4-6 KTS, SWELL=0.5-1M, ROLL=0.5°,
HEAVE= 0.5M, BARO=1011. ACC: NIL. SBB: NIL. POB: 97 (ONGC-4, ONGC SER 13, CONTRACT-80)/ NAVEEN TRIVEDI / S P SINGH/G BALACHANDAR
4. CE THORNTON = B_59#P1/ 81 DAYS/ CTU POOH- 0600-1100: CONTD WUO WITH FREE CHOKE THRU STD BURNER BOOM. OBSD NO ACTIVITY.1100-1230: RIH CT UPTO 1200M WITHOUT PUMPING.
STARTED N2 PUMPING @1200M, PR: 600-1000 PSI, RATE: 3-5 GPM. OBSD TRACES OF OIL & GAS+WATER+N2. 1230-1400: FURTHER RIH CT WITH N2 PUMPING TO 1951M, OBSD INTERMITTENT
WATER+ TRACES OF OIL.1400-1700: CONT RIH CT UPTO 2500 M WITH N2 PUMPING. OBSD INTERMITTENT FLOW OF OIL TRACES+WATER+FEEBLE GAS.FLARED THE SAME. FTHP= 0-40 PSI,
SSSV=3600PSI, H2S= 0-35 PPM, SALINITY= 36293 PPM AS NaCl, PH=7. 1700-1800: POOH CT FROM 2500M TO 2000M, STOPPED N2 PUMPING.POOH CT IIP.NOTE: 1. ONE SHORT DEPLOYMENT.POB: 87
(ONGC 11+SERV 14, SHELF 45+ SER 3+ CATR 14). SBB: NIL, NEAR BY P/F (SLQ, SHP & NQ) MORE THAN 21 NM FAR FROM RIG LOCATION, A/NIL=S K SRIVASTAVA / SHAIKH/ SARDAR/ AAKASH/
KAPIL/DILIP.
5. DEEP DRILLER 8= DDW#D6/120 DAYS/5714 M/4785 M/4786 M/ 13⅜”X9⅞” ANNULUS PRESSURE CONTROL/. 0600-0700: PUMPED THRU KILL LINE & RETURN THRU CHOKE. TOTAL PUMPED 40 BBL &
RETURN 42 BBL. (GAIN OF 2 BBL 15.5 PPG MUD).0700-0730: CLOSED CHOKE. WUO. M/W FLUSHED MGS, CHANGED LIQUID SEAL. PRESSURE BUILD UP TO 125 PSI. 0730-0830: BLEED OFF GAS.
PUMPED THRU KILL LINE & RETURN THRU CHOKE. TOTAL PUMPED 40 BBL & RETURN 40 BBL. 0830-0900: WELL OPEN TO MGS. 0900-0930: WELL DIVERTED TO OVERBOARD LINE. FOUND GAS COMING
CONTINUOUSLY. 0930-1030: WELL OPEN TO MGS. 1030-1130: PUMPED THRU KILL LINE & RETURN THRU CHOKE. TOTAL PUMPED 30 BBL & RETURN 30 BBL. 1130-1300: WELL OPEN TO MGS. 1300-1330:
PUMPED THRU KILL LINE & RETURN THRU CHOKE. TOTAL PUMPED 40 BBL & RETURN 40 BBL. 1330-1530: WELL OPEN TO MGS. 1530-1630: PUMPED THRU KILL LINE & RETURN THRU CHOKE. TOTAL
PUMPED 35 BBL & RETURN 35 BBL. 1630-1800: WELL OPEN TO MGS. REMARKS: 1) CUMULATIVE 16.0 PPG WB MUD PUMPED- 145 BBL. 2) CUMULATIVE 17.5 PPG WB MUD PUMPED- 371 BBL. 3)
CUMULATIVE VOLUME OF MUD RETURN- 129 BBL. NOTE: SAP NOT WORKING. WELL FLUID (SOBM): MW 14.0 PPG, VIS- 84 SEC. BULK/MAT RECEIVED: NIL. U.REQ: SAP MODEM. P.O.B: 80(ONGC-5,
GSPC-NIL, ONGC SERVICES-17, ABAN-44, ABAN SERVICES-NIL, CATERING-14). S/B BOAT: G S PRACHI. A/F/NM: 0/0/1= SHAMIM/ JAYANTAJIT BARUAH/NGN RAO/ PRABHAKAR/ SANJEET
6. D.S. FORTUNE= RIG MOVE TO B_66#D/DAY-19. 0600-0700: ATTEMPT TO ENGAGE C/CAP NO SUCCESS.0700-0830: POOH & L/DN RUNNING TOOL OBSV NO DAMAGE ON RUNNING TOOL.0830-
1230:M/UP IMPRESSION BLK& X/O AND RIH TO 56 MTR, DIVERS GUIDED STRING INTO 30” CONDUCTOR, CONTD RIH TO 71MTR TOOK IMPRESSIONS. POOH TO SURFACE AND L/DN THE SAME.1230-
1800: M/UP RUNNING TOOL WITHOUT CENRALIZER & X/O AND RIH TO 56 MTR, DIVERS GUIDED STRING INTO 30” CONDUCTOR CONTD RIH TO 71MTR.ENGAGED CORROSION CAP, GOT +VE
INDICATION,POOH TO SURFACE, RECOVERED AND L/DN CORROSION CAP P/UP & M/UP DIVERTER STRING TO FLUSH 20” MLS TOP I/P.BULK: HSD-153KL, DW-50 MT, P/W-67 MT, BARITE-176 MT,
N/CMT-59MT, BLENDED CMT-40.5M. UR: 1) DW 300MT. 2) POT WATER 200MT. 3) MUD CHEMICALS F/NHAVA (STO NO. 4920441735). 4) BOAT FOR IFT OF MUD CHEMICALS FROM SAGAR JYOTI TO DS
FORTUNE (DN - 81229913). POB: 65 (ONGC-04, SERV-4, JAGSON-44, JAGSON SERV-0, CAT-13). ACCIDENT-NIL.SBB: SCI NALANDA 16 KN/MILE/VENKATESH/AMOL/MENAK SINGH.
7. D.S. FOSSIL= BA#1Z_MUM/32DAYS/MILLING OF 20” CSG. 0600-1800: CONTD MILLING 20” CSG WITH WEATHER FORD MILLING ASSY F/93.50M TO 98.85 M. FURTHER MILLING IP. MILLING PARA:
GPM-690, PR-565PSI, WOB: 8-12 KIPS, RPM-90, TQ: 6-8 LBFT. WELL FLUID: GEL MUD, MW-8.7PPG, VIS-115SEC. UR: (1) BASE OIL-300BLS, (2) 6” TCR BIT (117) – 1 NO. (3) D/WATER 100 MT, (4) 1⅞”
STUDS-12NOS. POB: 66(ONGC-2 SVS-05 JAGSON-45, CATERING-14). SBB: PFS SUPPLIER (1.5NM). A/NIL. S SARAVANAN/DHIMAN.
8. DISCOVERY-1 = B_147A#2/ DRLG-5TH DAY / 2778 M (REV WELL TD) / 1600 M / 579 M / 171 M / FDIIP: 0600-0730: C & C TILL SHAKER HOLDING AT 800 GPM. 0730-0930: DRLD CMT, CSG SHOE
FROM 381 M TO 406 M WITH 17½” HLB RSS DIR ASSY & CLEARED UPTO 408 M. 0930-1800:COMMENCE DRLG 17½” HOLE WITH HLB RSS+MWD ASSY. DRLD FORM FROM 408 M TO 579 M. PUMP 30 BBL
HI-VIS PILL, DOWNLOAD DATA & RECORD SURVEY AS PER REQMT. FDIIP.WELL FLUID (SOBM): MW-9.9 PPG, VIS-90 SEC, PV/YP-40/24, GEL0/10-17/27, R6/R3: 15/14, ES-320 V, HTHP-9.0 CC, OWR-
66/34, EXCESS LIME-2.03 PPB, CL-50,000, WPS-165,310 PPM, SOLIDS-14%LAST SURVEY DATA (RKB): MD-528.75 M, INC-27.26°, AZI-299.77°, TVD-511.38 M, VS-96.52 M, DLS-2.51˚.BIT DETAILS:
17½” RR PDC, MAKE-HDBS, TYPE: SFE56, SL. NO.13236124, NOZZLE: 1x15, 2x14, 4x16, BIT MTRS / HRS: 171 M / 5.75 HR.DRLG PARA: WOB: 04-05 KLBS, FLOW RATE: 900 GPM, SPP: 1320 PSI, RPM:
120, DRLG TQ: 03-05 KLBS-FT, DRAG UP/DN: 151/140 KLBS. LITHOLOGY: CLAYSTONE OFFLINE JOBS: WH TEAM TESTED PROCESS LINE TOP SIDE FACILITIES OF 10” WELL FLUID TRUNK LINE SHUT
DOWN VALVE & PIG BARREL ISOLATION VALVE BY UTILISING WELL PR OF WELL NO._B_147A#1 (STHP-1850 PSI).NOTE: OSV GS ROHINI ALONGSIDE DELIVERING HSD CONSTRAINT: (1) BACKLOAD
BOAT FOR 7 LIFTS URGENT REQMT:(1) SOBM-600 BBL FROM JINDAL STAR (2) PREMIX 500 BBL (3) SOBM (MI) ENGR-01 (4) HSD-100 KL (STO#4910738035) (5) 13⅜” CSG-1850 MTR
(STO#4920442803) (6) BARYTE -50 MT (7) NEAT CEMENT-50 MT (8) BLB FOR 2⅞” PROD TOOLS TO PTYS NHAVA-3 LIFT (DN#81228618) (9) CONTRACTORS CARGO-03 LIFTS. POB: 80 (ONGC-04, ONGC
SERV-13, WH TEAM-03, JDIL-46, CATERING-14). SBB: PFS SUPPLIER AT 18 NM. WEATHER: WIND SPEED: 08-10 KTS / 340˚, SWELL: 1.0 M / 340˚. A/NIL = SHEKHAR / KUSHAL / SHASHI / NISHANT
9. ESSAR WILDCAT = G_4#AG/ RM: 11 DAYS/ DE-ANCHROING AT G-1-AJ/0600-1800: RIG STANDBY FOR M.O.D CLEARANCE PRIOR TO COMMENCE DE-ANCHORING OF PRIMARY ANCHORS. NOTE: DE-
ANCHORING STARTED @2245HR ON 03/03/2020; ANCHORS RECOVERED & SECURED: (#7, #6, #2, and #3). ANCHORS YET TO RECOVER (#1,#4,#5,#8)./ W/PARA(GS VIDYA): CURRENT-225°/1.0KTS,
SWELL-210°/0.5 M, WIND-220°/10 KTS, BARO-1014, TEMP-28°C, SKY-PARTLY CLEAR, VIS 7-8 NM./ ANCHOR TENSION: #1: 80T, #2: NA, #3: NA, #4: 85T, #5: 90T,#6: NA, #7:NA, #8: 85T. / POB: 92
(ONGC-03, ONGC SERVICES-5, ESSAR-70, CATERING- 14). / ACCIDENT: NIL./ SBB/AHV: GS VIMLA & GS VIDYA /= JAIM P JOHN /BINOY MAVILA/N. MURTHY.
10. F G Mc CLINTOCK= NLM_13#2H/18/2103M/1863M/M/UP 6” DIR BHA: 0600-0930: CONTD. POOH SLICK ASSY F/1634 M TO SURFACE. 0930-1300: P/UP & M/UP 8½” BIT, 9⅝” CSG-SCRAPPER &
RIH SCRAPPER ASSY F/SURFACE TO 1829 M (SCRAPE WELL F/1650M TO 1829 M THRICE). 1300-1400: C&C MUD. 1400-1730: FLOW CHECK, WELL STATIC. POOH 9⅝” SCRAPPER ASSY F/1829 M TO
SURFACE. BREAK & L/DN BIT, 9⅝” SCRAPPER. 1730-1800: P/UP & M/UP HLB GEO PILOT WITH 6” PDC BIT IP. BIT DETAILS: RR 6” PDC, HDBS, SR NO-13242002, NOZZLE-5X13, TYPE-MME55. WELL
FLUID: HGS-NDDF, MW-7.9PPG, VIS-51 SEC. NOTE: NLM_13#1H HANDED OVER TO NEELAM PLATFORM @1530 HRS ON 10.03.2020. UR: (1) DW-100 MT (2) HSD-100KL (3) PRODUCTION ITEM FROM
OSV GS DHRITI (4) COMPLETION ITEM FROM EMERALD. IFT: EXPRO W/L 4 LIFTS TO HSB PLATFORM POB: 74 (ONGC: 05, ONGC SERVICES: 05, SHELF: 47, SHELF SERVICES: 03, CATERING: 14). SBB:
OFFSHORE ADVENTURE (4.5 NM). ACC: NIL = D.S.RATHORE/ SOURAV/ ASHISH.
11. GREATDRILL CHAAYA = B_134A#1Z/35/ WUO: 0600-1000: CONTD FLOWBACK OF LS WITH GAS INJECTION (GIP 700PSI). OBSD WELL FLOWING LITTLE WATER IN RETURN. SS IN CLOSED
POSTION (STHP ‘0’PSI). 1000-1500: CLOSED L/STRING FOR PRESSURE BUILD UP. 1500-1800: OPEN LS TO STBD BURNER BOOM (GIP 850PSI, STHP-650PSI). OBSERVED WATER AND GAS IN RETURN
AND WELL PRESSURE BECAME 0 PSI. FURTHER NO ACTIVITY. WELL UNDER OBSERVATION. SS UNDER CLOSED CONDITION (STHP-‘0’ PSI). CLOSED LS FOR OBSERVATION. M/WHILE PLACING OF CTU AT
PROPER PLACE FOR ACTIVATION JOB I/P. U/R: 1) DRILL WATER: 75MT. 2) BLB TO SEND 7” RTTS PKR T/NHAVA. (RDN: 81229388). 3) IFT HLS WIRE LINE 1LIFT TO SD-5 (DN:81230128).4) IFT HLS WIRE
LINE 10LIFTS TO ABAN 3(81230134). 5) 30” CASING 175M F/NHAVA (DN: 81227542). 6) IFT OF 600 BBL SOBM F/JINDAL STAR. SBB: NB PRASAD/ 9NM. POB: 82 (ONGC: 09, ONGC SERVICES: 09, GIL:
50, CTRG: 14). A/N= J M KATAKY/JAIVEER/ GAURAV/PREM KUMAR.
12. GREATDRILL CHETNA = B_220#A/74/4030M/3996M/PT-86/ABDN. 0600-1230:- CONT POOH & L/DN 5-1/2” DP IN SGLS FROM 1333 M TO 177 M. (TOTAL SGLS L/DN-147). 1230-1330:- CONT POOH
8 ½” SLICK BHA FROM 177 M TO SURFACE. B/OUT & L/DN JAR, BIT SUB & BIT.1330-1630:- RIH WITH 3-1/2” & 5-1/2” OEDP UPTO 1600 M. 1630-1800:- SPOT AND BALANCE 100 M HI VIS PILL AT 1600
M .POOH FROM 1600 M TO 1500 M. C & C WITH 9.5 PPG MUD AT 1500 M PRIOR TO CMT PLUG JOB IS IN PROGRESS.. MUD PARA: GEL POLYMER MUD, MW-9.5, VIS-45 SEC, pH: 9.0. BULK STOCK: 1)
P/W: 231MT. 2) FUEL: 107KL (USABLE- 87KL). 3) D/W: 53MT. 4) BARITE: 82MT. 5) NEAT CMT: 54MT. 6) BLEND CEMENT: 65MT. UR: 1) FUEL: 100KL. 2) SLINGS-01PLT. POB: 74 (ONGC-4, ONGC
SERVICES-9, GIL-46, GIL SERVICES-01, SODEXO-14). ACCIDENT: NIL. SBB: NIL. R K CHAUHAN / AVINASH/MAITY.
13. GREATDRILL CHITRA = WI_6#I2YH / 41D / 2250 / PIPE BREAKING: 0600-1200: CONTD WELL FLOW BACK. OBSVD WELL IS FLOWING OIL-50% @ FTHP-100 PSI & GIP- 1000 PSI THRU FREE
CHOKE. WELL DIVERTED & HANDED OVER TO MHN PLATFORM @ 1100 HRS WITH OIL-50%, FTHP-100 PSI, GIP-950 PSI AND SALINITY- 28476 PPM AS NACL. REMOVED FLOW S/LINE FROM XMT &
INSTALLED BULL PLUG.1200-1800: PIPE BREAKING: B/OFF & L/DN 162 SGLS ~ 54 STDS OF 5-1/2” DP. F/BREAK OFF D/P STDS IN IP.UR- 1] TUG BOATS- 3 NOS ON 13-MAR-2020 FOR RIG MOVE; BLB
FOR : 1] X-MAS TREE (DN- 81229122); 2] 30” CSG- 1NO , 20” CSG- 1 NO ( DN- 81229863); 3] 7” LINER (10 NO /DN-81229879); 4] HALB 6” DIR TOOL TO NHAVA (8 LIFT/ DN-81227450); 5]
PRODUCTION ITEMS TO NHAVA, 03 BUNDLES TBGS + 06 PALLETS (D.NO-81229904, 81229919 & 81229907). POB: 72 (ONGC-5; ONGC SERV- NIL; CONT-67). ACCIDENT: NIL SBB: SCI PANNA @ 5 NM .
== S.SIDDIQUE / RAMESH / OM PRAKASH.
14. HARVEY H.WARD = R_12#F/138DAYS/P-53/3780/3300(REV TD)/OBJ-IV/0600-1800: CONTD WELL OPENED THRU 24/64” CHOKE & GRADUALLY INCREASED TO 28/64”.WELL FLOWING GAS & OIL
IN SURGES FTHP: 20-60 PSI, FTHT-87⁰F, OIL API-39.4, BS&W-NIL, H2S-NIL. FLOW BACK FOR PR STABLIZATION IP. POB: 88 (ONGC-05, ONGC SERVICES-18, SHELF-51, CAT-14). A/NIL. SBB: ABS
AMELIA/RAHUL GUPTA/HIMANSHU/SUBHOJIT/M B POL
15. JINDAL EXPLORER = B192_1#8/DAY 15/2526/2355(RTD)/ WOC. 0600-1000: CONTD LOWER 9-5/8” CASING (L-80, 47 PPF, PREMIUM) FROM 2000 M TO 2355 M (TOTAL 191 JTS). KEPT F/SHOE
@2355 M & F/COLLAR @ 2329 M. 1000-1200: CIRCULATION BEFORE CEMENTATION JOB. 1200-1500: PUMPED SACRIFICIAL MUD (380 BBLS) & 50 BBLS SPACER. R/UP CMT LINE. DROP BOTTOM PLUG.
PUMPED 133 BBLS (15.8 PPG) CEMENT SLURRY & DROPPED TOP PLUG. DISPLACED CEMENT WITH SEA WATER. BUMPED PLUG AT 1800 PSI. BLEED OFF PRESSURE & CHECK NRV-OK. 1500-1800: WOC
IN BOP CLOSED CONDITION. NOTE: RIG MAY WAIT FOR D/W FOR PREPARATION OF HGS MUD. U/R: (1) DW-200 MT, (2) BLB 10 LIFTS 12-1/4” HLB DD TOOLS, DN-81230131. (3) 8-1/2” DD TOOLS
FROM BOAT CELETIAL. (4) HGS-60 JB, (5) BARYTE 50 MT. POB: 82 (ONGC-6, SERV-13, JINDAL-45, JINDAL SERV-4 & CAT-14). SBB: ASL BAGULA, A/NIL. RN PRASAD/ DM DHAKATE/SHAKTI.
16. JINDAL STAR = B_23AA#1Z/38DAYS/3428M/3198M/RIH/0600-0900: CNTD W/DN F/2262M & TAG H/TOP @2580M. 0900-1030: PUMPED 25 BBLS HI-VIS PILL & CIRC OUT @ 500GPM/785PSI.
1030-1200: POOH 8-1/2" BIT WITH CLEAN OUT ASSY F/2580M TO 2036M. 1200-1300: TROUBLE SHOOTING TDS (OIL LEAKAGE, REPAIR SAME). 1300-1700: POOH 8-1/2" BIT WITH CLEAN OUT ASSY
F/2036M TO SURFACE. B/OFF & L/DN SAME. 1700-1800: P/U & M/U 6" BIT WITH 6" STAB AT 30' ASSY & RIH UPTO 115M. FRIIP. WELL FLUID: (GEL POLYMER MUD)-MW-9.3, VISCOSITY-54. UR: 1) HSD-
70KL, 2) 4-3/4” PBL SUB (DN: 81230188), 3) 5” LINER CSG - 550M (STO-4920442737), 4) 3-1/2” MONOBLOCK X-MAS TREE (STO-4920442738), 5) 4-3/4" PBL TOOL WITH BALL KIT FROM NHAVA TO
JINDAL STAR. IFT: 1) 6" PDC BIT TRANSFER FROM HARVEY H WARD TO JINDAL STAR (DN-81230002) BLB: 1) 9-5/8” CSG-14 JTS TO NHAVA (DN-81229864) POB: 77 (ONGC-11, SERV-09, JINDAL-43,
CAT-14). SBB: NIL. A KUSHWAHA/ S A MAZUMDER/ V K PATHAK/ QASEEM/ PRATHIMON
17. JT ANGEL = SS#5Z/30 DAYS/2210 M/1654 M/23 M/INCREASING MUD WT.0600-0800: CONT DRILLED 8.5” DIR HOLE F/1631 M TO 1649 M. 0800-1130: INCREASED MUD WEIGHT F/9.3 PPG TO 9. 9
PPG. OBSD, NO LOSS. 1130-1500: FLOW CHECK AND TRY TO P/OUT TO RECORD PRESSURE POINT, OBSD 25 KIPS OVER PULL. PREPARED AND PUMP 40 BBL LUBRICATED PILL & CIRCULATE OUT. 1500-
1530: FLOW CHECK FOR 07 MIN AND TRY TO P/OUT, OBSD STRING GOT STUCK. TRY TO RELEASE WITH 30 KIPS OVERPULL, NO SUCCESS. WORK ON STRING AND RELEASE WITH 18 KLB-FT TORQUE.
1530-1630: C & C MUD. 1630-1700: DRILLED 8.5” DIR HOLE F/1649 M TO 1654 M. 1700-1800: INCREASING MUD WT F/9.9 PPG TO 10.5 PPG IP. LAST SURVEY: MD: 1580.46 M, INC: 31.25 DEG, AZI:
304.36 DEG, TVD: 1440.82 M, VSEC: 502.08. DRILL PARA: WOB- 20-25 KIPS, RPM- 80, GPM- 400, PRES- 1290 PSI, TQ- 8-10 KFT.LBS. BIT DETAILS: MAKE- BAKER, SN- 5305689, TYPE- KM524, JET-
2X14, 2X18, BIT HRS- 1.5, CUM BIT HRS- 13.5, BIT METERAGE- 23 M, CUM BIT METERAGE- 182 M. MUD PARA: GEL POLYMER, MW- 10.3 PPG, VIS- 46. B/STOCK: HSD-95 KL, D/WATER- 30 MT, BARITE-
108 MT, CEMENT- 41 MT. UR: (1) DRILL WATER- 100 MT (2) 300 BBL OF SOBM PREMIX AND 300 BBL OF 9-9.5 PPG SOBM ON 12.03.2020 AT MORNING AFTER C/OVER TO SOBM. (3) BLB FOR HLS DD
TOOL 4 LIFTS TO NHAVA (DN: 81229220). (3) BLB FOR 20 LIFTS F/JTA TO NHAVA. (5) BLB FOR 01 BASCKET OF ECP (02 NOS) F/JTA TO NHAVA (DN- 81230305). POB: 84 (ONGC- 02, ONGC SERV- 09,
SHELF- 46, SHELF SERV- 13, CATERING- 14). SBB: SAGAR FORTUNE @04 NM. ACCIDENT: NIL. PC KARMAKAR/ANIL WADE.

18. OLINDA STAR= KGD982NA_G1_D#AA / DOL-58 / 4528 / 3330 / 2903/ - / (CEMENT SQUEEZE JOB #2) 0600-0645: CONTD POOH SLICK BHA F/68M TO SURFACE. B/OFF AND L/DN BIT. 0645-
0930: SLIP & CUT DRILL LINE 33M. 0930-1030: P/UP, 3-1/2" MULE SHOE & RIH ON 3- 1/2" DP F/ SURFACE TO 291M. 1030-1545: RIH 3-1/2" CMT STINGER ON 5-7/8"DP F/291M TO 2903M & TAG
BOTTOM. 1545-1730: CIRCULATED PRIOR TO CEMENT SQUEEZE JOB W/700 GPM, 3310PSI. 1730-1800: M/UP SES STD FOR PRESSURE TESTING IN PROGRESS. M/PARA (SOBM): MW: 13.5 PPG, VISC:
90, PV/YP: 73/24, GEL 0/10: 14/25, RPM 6/3: 13/11, HTHP FL: 4.2ML, SOLID: 27%, OWR: 68/32, ES: 420, CHLORIDES: 29000 MG/LIT, EX LIME: 2.0 PPB. BG GAS: 0.02-0.05%.WX/PARA: WIND-
10KTS/230°, CURRENT-1.8KTS/176°, SWELL-0.5MTR, BARO-1012MB, TEMP-30°C, SEA-SLT, VIS-6NM; ANCHORTENSIONS: SA#1: 97T, PA#2: 96T, PA#3: 116T, SA#4: 86T, SA#5: 101T, PA#6: 115T,
PA#7: 88T, SA#8: 101T; A-NIL. SBB: LEWEK FULMAR / LEWEK ATLAS; POB: 120-(ONGC-4, ONGC-SVC-21, and QGOG-95). UMANG SONKER/SACHIN KUMAR / SUMAN BHATTACHARYA/PALTU MANDAL.
19. PLATINUM EXPLORER = R1E#AA/35/2281.5/2325 EXT TD/9 5/8 / 10 ¾” CSG SHOE @ 1944M/WOC. 0600-0630: CONTINUE WITH DRAW WORKS BRAKE TEST. UNHANG BLOCKS. 0630-1100:
WOC. 1100-1230: RIGGED UP FOR WIRELINE. P/UP & M/UP TOOL STRING SBT-VDL-GR-CCL. 1230-1430: RIH WITH WIRELINE TOOL STRING TO FLOAT COLLAR. 1430-1600: RECORD REPEAST PASS
FROM 1903M, RECORD MAIN PASS FROM FLOAT COLLAR TO 1705M. 1600-1800: POOH WIRELINE TOOL STRING TO SURFACE (OBSERVED CMT NOT BONDED) BRK & LAY DOWN TOOL STRING IS IN
PROGRESS. MUD PARA: MW-9.5 PPG/ VISC- 97, PV/YP- 51/20, GEL- 10/15/19, FL 3.6ML, SOLIDS-9% SALINITY 40000, OWR-67:33, ES 407. WX PARA: WIND- 08KTS/220°, CURRENT- 35T/255°, ROLL-
02 DEG, PITCH-0.2 DEG, HEAVE-0.2M, SWELL- 1.0M. POB: 129 (ONGC-2), ACCIDENT: NIL, ST BY/BOAT- NIL= SURINDER KUMAR/ALI MOHAMMED DAR.
20. RONTAPPMEYER = R_9A#4/26DAYS/3300M/RIH 8 ½”HLB DIR ASSLY IP. 0600-0700: CNTD PR TEST OF 13 5/8” BOP@250PSI/4000PSI. OK. B/OFF & L/DN TEST ASSLY. 0700-1400: RIH 5 STDS
OF 6 5/8” HWDP, B/OFF & L/DN 15 SGLS. RIH 15 JTS OF 5 ½”HWDP + 36 JTS OF 5” DP SGL BY SGL TO 485M (DRIFT ALL TUBULARS & FLUSH). 1400-1500: P/UP & M/UP 6 ¾” PBL TOOL. TEST PBL TOOL
(ACTIVATE @50PSI & DE-ACTIVATE @2100PSI). OK. 1500-1600: POOH F/485M TO SURFACE. 1600-1800: P/UP & M/UP RSS-LWD-MWD ASSLY & RIH TO 29M. FURTHER RIH IN PROG. UR: 1) SOBM
PREMIX-300BBL 2) NEAT CMT-20MT BLB: HLS LOGGING UNIT-07 LIFTS (DN-81229940) SBB-ABS AMELIA/ALONGSIDE. ACC-NIL. POB: 92 (ONGC-03, ONGC SER-14, P/F SER-02, SHELF-47 + 12 (EXTRA)
& CTRG-14)/ D S JAIN/MUKESH
21. SSV LOUISIANA = CHN#BAA/73DAYS/PT: 11DAYS/3225M/3225M/ POOH DUMMY LANDING STRING / 0600-0730: POOH WIRELINE TOOLSTRING GR-CCL FROM 2396M TO SURFACE. 0730-0900:
UNSEAT DUMMY FLUTED HANGER FROM WB & P/O FROM 2528M TO 2524M. B/OFF & L/OUT TIW & PUP JT. RIG DN BAKER WIRELINE SHEAVE, PAD EYE & 50’ BAILS. 0900-1700: POOH WET 4-1/2” TBG
LANDING STRING WITH TCP-DST BHA FROM 2524M TO 1680M. 1700-1800: CONT POOH F/ 1680M TO 1666M & L/DN DUMMY FLUTED HANGER IS IN PROGRESS. / WELL FLUID: BRINE (CACL2): 10.0 PPG,
VIS: 27SEC, CL- 165000 MG/L, PH - 11 / W/PARA: CURRENT: 1.6 KTS-226°; SWELL: 0.7 M-150°; WINDS: 8 KTS-220°/ POB: TOTAL=145, ONGC=3; ONGC SERVICES=38, UER=104 / SBB:-EVI MARIA /
A: - NIL / PRIYARANJAN / ARVIND JAIN / VIVEK VENUGOPAL.
22. SUNDOWNER-5 = NO# 5Z/ 03 DAY. 0600-1100: CONT WORKING ON STRING BETWEEN 40 KIPS TO 120 KIPS. 1100-1200: APPLIED PULL UPTO 160 KIPS (OVERPULL- 90 KIPS), IN STEPS OF 10
KIPS, WITH MEASUREMENT OF STRETCH/10 KIPS, TO OBSERVE EFFECTIVE PULL TRANSFER ON PKR. PKR NOT RELEASED. 1200-1800: WAITING FOR HLS LOGGING UNITS & CREW FOR TBG CUTTING
JOB. MEANTIME, CONT WORK ON STRING WITHIN SAFE LIMITS. REMARKS: 1. BSNL PHONE IS DEAD FROM LAST 02 DAYS. 2. SBB MV KAMET SENT TO PICK THE LOGGING UNITS FROM RIG SAGAR
GAURAV. U/R: HLS LOGGING UNITS FOR TENTATIVE TBG CUTTING JOB AT WELL NO #5Z. POB: 38 (ONGC – 03, NABORS– 29, SODEXO-06). A/NIL. SBB: MV KAMET. K K PANT, SAMRAT
23. SUNDOWNER-7 = HSC#1Z (DAY 5) 0600-1800: WAITING FOR NABORS DP. NOTE: 1) BOAT ALLOTED FOR DP BUT NABORS DP NOT AVAILABLE AT NHAVA YARD.HSD: 8.4 KL SBB: HEERA SBB NB
PRASAD SHARED WITH SD7. U/R: 1) D/WATER-50 MT ACC: NIL POB: 41 (ONGC-03, ONGC SER- 05, NABORS-27, SODEXO-06). YASIR/GAMIT
24. TRIDENT 12 = IW#5Z/59/3275 M/WELL UNDER PERF.JOB: 0600-0830: P/O FROM 1005 M TO SURFACE. B/OFF 6” STAB, BIT AND L/DN SAME. 0830-0900: P/UP & LOWERED SHOOTING NIPPLE
WITH DUAL PACK OFF & SPACE OUT. 0900-1000: R/UP HLS W/L SHEAVES &TOOLS. 1000-1030: TESTED DUAL PACK OFF WITH SHOOTING NIPPLE AT 2000 PSI.FOUND O.K. 1030-1330: HLS PREPARED
PERF. GUN OF 4 ½” O.D.5 SPF & ARMED. FITTED AND TESTED TRACTOR. FOUND O.K. C/OUT HOT CHECK PROCEDURE. 1330-1500: LOWERED PERF.GUN#01 UP TO 1080 M. 1500-1800: R/I WITH
TRACTOR TOOL FROM 1080 M TO 2900 M. FURTHER LOWERING OF GUN IS IN PROGRESS. WELL FLUID: BRINE.MW-8.6 PPG. U/REQ: 1) B/L BOAT REQUIRED FOR CSG AND OTHER ITEMS.2) PROD.ITEM
FROM G.D. CHITRA VIDE DN: 81229907.3) HLS W/L ITEMS (A) FROM DISCOVERY-01 VIDE DN# 81230129. (B)FROM NHAVA VIDE DN#81230311. POB: 74 (ONGC-04, ONGC SERV-08, SHELF DRLG-45,
SHELF EXTRA-04, CATERING-13). SBB: SAGAR FORTUNE – 9.20 NM (SOUTH FIELD PROD. BOAT). ACCIDENT: NIL= PARTHASARATHI/ RAJEEV / R.C. SINGH.
25. VALIANT DRILLER = HK#10H/4D/1968/1651/1050/CMT DRILLING.0600-1200: WELL HK#11H KEPT CLOSED FOR DIVERSION (M/W M/UP TEST ASSY & TESTED@2000 PSI; TESTED 21 ¼” BOP
(L/RAM, ANN BOP, FOSV, LOWER & UPPER IBOP, CHOKE- KILL HCR & MANUAL VALVES, CHOKE-KILL HOSES @250/1500PS FOR 5 MIN/10 MIN, BLIND/SHEAR RAM @ 250 /1500 PSI FOR 5 MIN/10
MIN).1200-1230: WELL HK#11H OPENED TO STBD FLARE BOOM; OBSD 40% OIL & WELL FLUID WITH FREE CHOKE (FTHP-1000PSI, GIP-950PSI); WELL HK#11H HANDED OVER TO HEERA PLATFORM
@1230 HRS.1230-1400: AT WELL HK #10H P/U, M/U & RIH 17 ½” DRLG ASSY UPTO 20 M; F/TESTED 8” PBL SUB (ACTIVATED@40 PSI,DEACTIVATED@2300 PSI); B/OFF PBL SUB.1400-1800: CONT RIH
17 ½” ASSY F/20 M TO 279M; TAGGED CMT @ 279M W/10 KIPS; TESTED 20” CASING @ 500 PSI-OK.WELL FLUID (SEA WATER) : WT-8.6PPG.IFT: (1) 01-LIFT HLB LIFT (17 ½” TOOLS) F/ABAN-3 TO
VAL DRILLER/DN-81229969 ; (2) 02- HLB LIFTS F/RTM TO VAL DRILLER /DN-81229978.BACKLOAD (NHAVA) : (1) 3-LIFTS DDSPL/DN-81227478,81223400,8122859002; (2) 5-BAKER TO NHAVA /DN-
81230163. UR: (1) FUEL-100KL; (2) D/W-100 MT; (3) 03-HLB LIFTS FROM NHAVA /DN-81229925.POB: 70 (ONGC-4, SERVICES-8, CONTRACTOR-44, CATERING-14).ACC-NIL; SBB: NB PRASAD.T S
KUMPAWAT/ GAJANAN / RAHUL.
26. VICTORY DRILLER = N_14#12H/53DAYS/2855M/2855M (TD)/ -/ RIH 3 1/2" UPPER COMPLETION 0600-1130: RELEASED SETTING TOOL & POOH F/2523M TO SURFACE. SERVICE & L/DN SETTING
TOOL. 1130-1200: R/UP 3 ½” TBG HANDLING EQUIPMENT. 1200-1400: M/UP 5 STD OF 3 1/2" EUE TBG & RACK BACK. 1400-1800: P/UP & M/UP LTSA, MMG 3 & RIH WITH 3 ½” EUE TBG (9.3 PPF, L-80)
IN SINGLES TO 690 M (TOTAL JTS 71). FRIP. NOTE: DRIFTED ALL TBG WITH 2 7/8" RABBIT.WELL FLUID: 8.6PPG FILTERED BRINE. U/R: IFT: 1) FRACSEAL LCM - 07 LIFTS (DN#81230282) TO JTA, 2) MI
CHEMICALS 19JB & 18PLTS (DN#81230283) TO VIRTUE-I, 3) 2 7/8" DP HANDLING TOOLS TO SAGAR GAURAV. BLB: 1) SCHL DD UNIT & TOOLS 04 LIFTS (DN#81229982), 2) SOBM-700BBL (7.5PPG).
POB: 70 [ONGC- 05, ONGC SER- 04, DDSPL- 47, CATERING-14]. SBB: SCI PANNA. ACC: NIL. K DURAIRAJ/PALASH/A N MADHAVAN.
27. VIRTUE -1 = WI_4#6ZH/50DAYS/2780M (REV)/2780M/7”H/TOP-1452M/ERD PKR-2351M/ 0600-0700:CONTD CIRCULATED HI VIS TILL HOLE CLEAN.0700-0900:STABBED IN LTSA INTO ERD
PACKER.SPACED OUT D/P.M/U X/O & FOSV WITH DRILL STRING.0900-1800:ARRANGED DECK SPACE TO ACCOMMODATE CTU EQUIPMENTS.PLACED CTU EQUIPTS ON C/DECK.CONNECTED HOSES.R/UP
CTU BOP.FUNCTION TEST BOP,INJECTOR AND REEL.STAB IN 1.25” COIL TUBING INTO INJECTOR IS IP.WELL FLUID: BRINE MW-9.4 PPG. REMARK: 1) INTERNET IS NOT WORKING PROPERLY.U/R: (1)
BLB FOR CONTRACTOR MATERIAL (LIFTS 18) DN # 81228683, BLB FOR SCHLUM. D.D.TOOLS(8-1/2”) WITH LOGGING UNIT (LIFTS 6) DN # 81228235, BLB FOR BAKER LOGGING TOOLS (LIFTS 10) DN #
81229678 TO REDUCE DECK CONGESTION WITH HLB CTU EQUIPTS & PRODUCTION TBGS 2) HSD-100KL 3)D/W-100MT 4) SOBM F/G D CHITRA FOR NEXT WELL. POB: 74 (ONGC-5, ONGC SERVICES-9,
JINDAL-46, CATERING-14) SBB: SCI PANNA. (04 NM F/ RIG) A/NIL. GUHAROY/ MONDAL / ASHISH NAYAK.

END OF REPORTS