S.

NO BAY 400kv PENDING WORK

402,
403,404,
405,406
407,408
INTERLOCKS,METERING,SYNCH CHECK,CB CLOSING,
1 CVT SELECTION,AUTORECLOSER

INTERLOCKS,METERING,SYNCH CHECK,CB CLOSING,


2 401,409,411 CVT SELECTION,AUTORECLOSER
TIME TAKEN

10 days

4 days
S.NO BAY

201,202,
204,205,
208,209
210,211

2 203,206,207
400kv PENDING WORK TIME TAKEN

RELAY SIGNAL TESTING


INTERLOCKS,METERING,SYNCH CHECK,CB
CLOSING,
CVT SELECTION,AUTORECLOSER 20 days

INTERLOCKS,METERING,SYNCH CHECK,CB
CLOSING,
CVT SELECTION,RELAY SIGNAL TESTING 6 days