Prac01-Creating Project, Calendar, Activities, WBS
Prac01-Creating Project, Calendar, Activities, WBS
CONTENTS
Section 1. Setting-up calendar....................................................................................................2
Section 2. Adding holidays (Exceptions).....................................................................................2
Section 3. Setting project defaults..............................................................................................3
Section 4. Creating new tasks.....................................................................................................3
Section 5. Auto-scheduling tasks................................................................................................4
Section 6. Setting predecessors..................................................................................................5
Section 7. Creating WBS.............................................................................................................6
Section 8. Changing relationship types......................................................................................7
Section 9. Adding Lead/Lag........................................................................................................8
Exercise............................................................................................................................................8
Section 1.1.SECTION 2.
Section 1. SETTING-UP CALENDAR
Before starting to create activities in a project, the project calendar needs to be set. The project
calendar defines the working days and working hours. Any special holidays can also be set in
the calendar.
Step 1. Go to Project menu and select Change Working Time.
Step 2. Click on Create New Calendar.
Step 3. Rename the calendar as “XYZ Infra – Mumbai”.
Step 4. In Make a copy of, select a base calendar from already entered holidays can be
inherited. Select default Standard calendar.
Step 5. Go to Work Weeks tab in the bottom window.
Step 6. Click on Details.
Step 7. Notice that, Monday to Friday the worktime is scheduled from 8 am to 5 pm with
an hour break from 12 noon.
Step 8. Assume a 6-days working week. Select Saturday, select Set day(s) to these
specific working times.
Step 9. Enter following details:
From To
1 8:00 AM 12:00 PM
2 1:00 PM 5:00 PM
Step 10. Click Ok.
Step 3. To copy same details in all the activities, select the Task Mode column.
Method 3 – Auto-linking tasks in the order they are created in the task list
Step 1. Select all tasks.
Step 2. Go to Home>>Link Tasks. Or press Ctrl+F2.
Note - Adding a sub-task inside a summary task, makes the summary task lose its own duration.
The duration of the summary task is calculated from the durations and relationships of the sub-
tasks.
Step 2. Create following WBS:
Section 8. CHANGING RELATIONSHIP TYPES
There can be four types of relationship between tasks – Finish-to-Start (FS), Start-to-Start (SS),
Finish-to-Finish (FF), Start-to-finish (SF).
Step 1. To change the relationship type, in the predecessor column write the
predecessor number followed by the relationship type.
Or
Double-click on the successor activity, go to Predecessor tab, select the
predecessor and change the relationship type.
Section 9. ADDING LEAD/LAG
Step 11. Lead/Lag can be added by adding lag days in the predecessor column. A positive
value means lag, whereas a negative value denotes lead.
EXERCISE
1) Add a holiday on 14th February 2019 for Valentine’s day.
2) Add a recurring holiday on 25th December every year for Christmas.
3) Change the project start date to 10th February 2019.
4) Add an SS relationship from Columns of Tower A to Footing of Tower B.
5) Add a lag of 2 days between Columns and Beams & Slabs.
6) Add 3 tasks – Masonry (4 days), Plaster(2 days), Painting(2 days) under Walls.