Professional Documents
Culture Documents
CHAPTER 4 PRICING AND TARIFF OF ELECTRICITY Latest PDF
CHAPTER 4 PRICING AND TARIFF OF ELECTRICITY Latest PDF
Chapter 4
Pricing & Tariff of Electricity
The new electricity tariff will be put in place in line with the
Government’s aspiration towards gradually phasing out energy subsidies
through the Subsidy Rationalisation Programme.
Prior to that, the last review was carried out in 1st June 2011
The electricity tariff rate are based upon the following guidelines:
• The amount of energy consumed (kWh)
• The maximum demand at which energy is consumed (kW)
• Peak / off-Peak period
• The power factor of the load
• The connected load
1
5
16
Main
Components
Other
Components
Notes:
1. CLC =
Connected Load
Charge
2. KWTBB=
Kumpulan Wang
Tenaga Boleh
Baharu
3. CLC, PF and
1% for Late
Payment are
penalty charges
“COMMERCIAL SUPPLY”
means the supply of energy from the Company's supply lines to all
commercial premises including office block, shop, go down, restaurant,
school, hotel, boarding house, farms, estate, port, broadcasting and
telecommunication installation, cinemas and entertainment locations,
military and Government installations and hospital, and any supply used
in the construction or building activities, but excluding private dwellings
and industrial premises.
“INDUSTRIAL SUPPLY”
means supply of energy to industrial operation such as manufacturing,
quarrying, mining, shipbuilding business, and to consumers who utilize
energy for the purpose of pumping water, in whose premises electric
motors and plants are used in connection therewith and the total
wattage of lamps and air-conditionings installed for purpose of office
use shall not exceed twenty per cent (20%) of the total wattage of all
electric equipment installed
“CO-GENERATOR”
means a generator who that uses a single primary energy source to sequentially
generate two different forms of useful energy for its own use at an efficiency
rate of more than 70%. Services offered to co-generators are:
Top-up supply: The additional supply required by a Co-generator who that
does not produce sufficient electricity for its own use.
Standby supply: The supply that TNB provides to a Co-generator in the
event that the Co-generator does not generate electricity due to plant failure
or planned shutdown for maintenance.
“MAXIMUM DEMAND”
the largest number of kilowatt-hours supplied during any thirty minutes period
in a month.
“MONTH”
means the period between two successive meter readings, meters are
normally read at intervals of approximately thirty days
Tariff rates for Top-up and Standby Services (only for Co-generators)
CLC CALCULATION
Nevertheless, for the first 3 years, the CLC will be based on staggered percentage to assist
consumer during the initial stage of their operation.
The method in determining Reference Maximum Demand* for calculating CLC are as
follows:
YEAR REFERENCE MAXIMUM DEMAND*
1 0% x 75% x Declared Maximum Demand(CLC exempted for the first year only)
2 50% x 75% x [Declared MD or Highest Recorded MD, whichever is higher]
3 75% x 75% x [Declared MD or Highest Recorded MD, whichever is higher]
4 100% x 75% x [Declared MD or Highest Recorded MD, whichever is higher]
5 100% x 75% x [Declared MD or Highest Recorded MD, whichever is higher
6 100% x 75% x Declared MD or Highest Recorded MD, whichever is higher]
2 10,000kW 50% x 75% x 10,000kW = 3,750kW 5,000kW No penalty. AMD > RMD
4 10,000kW 100% x 75% x 10,000kW = 7,500kW 7,500kW No penalty. AMD > RMD
5 10,000kW 100% x 75% x 10,000kW = 7,500kW 8,000kW No penalty. AMD > RMD
6 10,000kW 100% x 75% x 10,000kW = 7,500kW 8,000kW No penalty. AMD > RMD
Few activities could be carried out by customers that assist in reducing MD charges such as:
Practicing demand side management such as peak shift i.e. shifting their peak operation/consumption to off
peak period as MD charges is not applicable during off-peak period for customer with peak/off-peak tariff
Opting for any promotional scheme offered by TNB relating to MD such as Sunday Tariff Rider Scheme
(STR).
Starts your motor/equipment in stages or during off-peak period
Consumption Detail:
MD Peak = 1,811kW
Off-Peak Hours Peak Hours Off- MD Off-Peak = 1,254kW
(10pm-8am) (8am-10pm) Peak
Hours
Peak = 575,453kWh
(10pm Off-Peak = 320,668kWh
-8am)
For all kWh during the peak period sen/kWh 36.5 575,453 210,040.35 57.8%
For all kWh during the off-peak 320,668 71,829.63 19.8%
sen/kWh 22.4
period
The minimum monthly charge is RM600.00 Total Bill 363,546.08 100.0%
RM 89.00/330 = 26.97cents/kWh
RM 169.68/530 = 32.01cents/kWh
In other words, the cost also depends on the highest active power
(kW) drawn from the line.
TNB has to cater for the highest required demand at all time to
ensure sufficient supply to customer
To understand the reason for this dual rate structure, consider the
following example.
Factory A
720,000 kWh @ 28.8 cents/kWh = RM 207,360.00
Demand 1000kW @ 25.3 RM/kW = RM 25,300.00
Total bill for the month = RM 232,660.00
Factory B
720,000 kWh @ 28.8 cents/kWh = RM 207,360.00
Demand 3000kW @ 25.3 RM/kW = RM 75,900.00
Total bill for the month = RM 283,260.00
32.3 cents/kWh
38.34 cents/kWh
The steadier the power drawn, the less cost paid for the
energy used !!
Satu Bulan
77,380 not
charged for
billing
However, the high start-up power does not last long enough to
warrant the installation of correspondingly large equipment by the
utility company.
The answer depends upon several factors. But the period is usually
taken to be 10, 15, or 30 minutes.
a) According to the graph, the average power (or demand) between 7.00
and 7.30 is 2MW. Consequently, pointer 1 continues to indicate 2MW at
7.30am and pointer 2 stays where it was at 3MW.
b) The average power or demand between 7.30 and 8.00 is equal to the
energy divided by time.
AD = (7MW x 5 min + 2MW x 5 min + 4MW x 20min) = 4.17MW
30 min
During this 30-min interval, both pointers gradually moves to 4.17MW.
• Foreign exchange
• Finance cost
• Extraordinary items
You are an existing TNB customer under the C1, E1, or E1s
tariff.
Your have been receiving electricity supply from TNB for at least
one (1) month.
Your latest Load Factor is higher than the average Load Factor
over six (6) months prior to your application.
You do not have an outstanding amount not more than the total
deposit/bank guarantee paid. Otherwise this outstanding
amount must be settled before applying.
You are an existing TNB customer under the E1, E1s, E2, E2s,
E3, or E3s tariff.
You do not have an outstanding amount not more than the total
deposit/bank guarantee paid. Otherwise this
outstanding amount must be settled before your application can
be considered.
Power factor is the ratio of the active power P to the apparent power S.
In an electric power system, a load with low power factor draws more current
than a load with a high power factor, for the same amount of useful power
transferred.
The higher currents increase the energy lost (I2R) in the distribution
system, and require larger wires and other equipment
Most electrical utilities require that the power factor of their industrial
clients be 90% or more, in order to benefit from the minimum rate.
This capacitors may supply part, or all, of the reactive power required by
the plant.
old P
new
Qold Qnew
+ QC
Sold Snew
TNB imposes on all industrial & LPC to maintain their power factor to no
less than 0.85
For all TARIFFs except A and G, the consumers shall use their best
endeavors to obtain highest possible PF in the operation of any of their
electrical installations.
(2) Below 0.75 (0.75>PF) lagging, in addition to the charge payable under
(1) above, a supplementary charge of 3% of the bill for that month for
each 0.01 unit below 0.75 lagging PF will be added to the bill for that
month.
In some cases the customer has no choice but must comply with the
minimum power factor specified by the utility company.
a) Unity (PF = 1)
b) 85% lagging
To raise the power factor to unity, we have to supply all the reactive power
absorbed by the load (228kVAr).
Because the load still draws 228kVAr but the line now supply only
121kVAr, the difference must come from the capacitors.
By installing the single-phase capacitor bank, the line current drops from
250A to 168A, which represents decrease of 33%.
Its follows that the wire I2R loss and voltage drop on the supply line will
be greatly reduced.
Furthermore, the power factor rises from 60% to 89% which will
significantly reduce the monthly electricity bill.
2. Benefits to customers
1% to 6% reduction in demand and energy
consumption from power factor management program
Reduce the electricity bill
Stabilize incoming line voltage
Reduce internal line loss and heat buildup
Increase the operating life of motors
Increase the available capacity of incoming supply lines
and transformers
Reading
ID Number Previous Bill Current Bill Usage Unit
M AC0800010 0.00 388,018.00 388,018.00 kVA
M AC0800010 0.00 5,184.83 5,184.83 kW
M AC0800010 0.00 1,456,533.00 1,456,533.00 kWh
Charge
PRKR Unit Price Cost
Consumption tar.C1U 1,456,533.00 0.312 454,438.30
Consumption MD.C1U 5,184.83 25.90 134,287.16
Calculation :
Measurement
IEC 61000-4-7 Voltage Flicker
IEC 61000-4-15 Harmonic Measurement
IEC 61000-4-30 Measurement Accuracy (“Class A”, “Class S”)
IEC 62052/3-11, 22, 23 Energy Accuracy (“Class 0.2S”, “Class 0.5S”)
Frequency
Voltage Variations
Voltage Flicker
Voltage Dip
Interruptions
Temporary Overvoltage
Transients
Unbalance
Harmonics
Interharmonics
BEKP 4853 Energy Utilization and Conservation 143
HARMONICS
+ =
sin( 5 x ) sin( 5 x )
f ( x ) sin( x ) f ( x) f ( x ) sin( x )
5 5
100 ( V 2 V 3 ..... V n )
2 2 2
THD(V) (%)
V 1
.....
2 2 2
THD(I)
100 ( I 2 I
3 I n
)
(%)
I 1
.....
2 2 2
TDD(I)
100 ( I 2 I 3 I n
)
(%)
I max demand