MS Chain LINK Fence
MS Chain LINK Fence
SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 1 of 12
DISCIPLINE: CIVIL
REMARKS:
00 March 22, Reference Leo R. Najera Moises M. Tabura Engr. Ehab Adeeb
2020
PM
Rev Date Description Prepared by: Signed Checked by: Signed Noted by: Signed
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 1
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 2 of 12
Table of Contents
1.0 INTRODUCTION 3
2.3 Materials 4
3.0 INSTALLATION 6
4.0 DEFINITIONS 8
5.0 REFERENCES 8
11 ABBREVIATIONS 12
12 ATTACHMENTS 13
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 2
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 3 of 12
1.0 INTRODUCTION
The purpose of this Method Statement and methodology is to describe the procedures that Abdul
Mohsen AH Al-Tamimi Partners Co. will adopt in the production, transportation, installation and
quality inspection of Type IV Saudi Aramco Chain Link Fence in Aramco’s South Ghawar UR
Early Works & TCF, located at South Ghawar, Eastern Province, KSA.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 3
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 4 of 12
2. The equipment to be used will be inspected by Safety Responsible for Safety SA standard
inspected daily.
The Work will be carried out in stages in accordance with the following procedures:
2.4.1 Survey works to carry out to ensure that specific location and distances of each line posts
must be on the right positioning identified as the specific location.
2.4.2. Trench excavation to conduct using Light equipment (JCB) to expedite the excavation
on the designated location.
2.4.3. Excavation at 1097mm depth by 250mm opening to accommodate the total length of each
type IV & V pre-cast concrete post.
2.4.4 Clearing will follow on total length of excavated location and should be compacted using
machine operated plate compactor prior to proceed backfilling of general fill materials at a
initial lift of 600mm.
2.4.5. Watering compaction method will be next work and re-compact the first lift.
2.4.6. Initial installed post will keep recorded for installation to commence by approved and
witnessed by Al Tamimi Responsible and SAPID Responsible officially.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 4
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 5 of 12
2.4.7. Second lift of 600mm will proceed repeat the sequence as stated in item 2.4.4.
2.4.8. Third and last Lift of 600mm will follow as per sequence stated in item 2.4.7.
2.4.9. Bore Holing using auger drill a diameter 250mm and 300mm base on the approved IFC
drawings on each location required to accommodate the size of 250mm x 1097mm x size of
type IV Chain Link Fence line posts, 300mm for Posts and for required diameter for Gates
following Saudi Aramco standard drawing respectively.
2.4.10. Pre installation will be recorded to verify and check the specific location and distance
each line posts with a given survey points.
2.4.11. Surface preparation, clearing the construction work area according to line and grade,
cleaning of the entire location and easy access of all needed equipment for the installation of
post.
2.4.12. Pre-casted and pre-painted (Bituminous) Line posts will erect to the prepared pre-
excavated compacted and Bore holed location of posts will follow and repeat the sequence up to
the last line of post to the corner post.
2.4.1.1 Laying out and fixation of Galvanized 250 mm diameter Pipe approved materials
supplied by SA approved supplier with PVC schedule 80 spacer v-cut in 75mm ties in the
bottom of Galvanized Iron pipe to eliminate dis-allignment while concrete pouring is ongoing in
fabrication yard.
2.4.1.3 After concrete hardened and achieve desirable hardness, preparation of concrete surface
finishing shall be made immediately.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 5
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 6 of 12
2.4.1.4 Pouring / casting concrete using mechanical pump in fabrication yard area delimited.
Pouring sequence shall be done continuously to expedite workers on finishing stage the top
concrete surface using manually operated hand tolls on the top required slope finished concrete
each line post.
2.4.1.5 Formworks shall have wood bracing ample supports to avoid movement of newly
concreted pre-cast post.
2.4.1.6 Formworks shall remain until concrete achieved hardness, alignment of pre-painted
applied approved epoxy coated G.I pipes shall maintain the verticality.
3.0. INSTALLATION
3.1 Pre-casted and pre-painted Line post in fabrication yard will be conducted prior to
transporting in specific project site location.
3.2 Make the necessary preparation for concrete pouring the mason tools, concrete vibrator
hessians polyethylene sheets, clean water and curing compound for concrete curing must be
provided at site. The use of PPE's Personal Protection Equipment shall also be imposed to
all personnel.
3.3 Proper access for Boom truck for transporting and erection location should be arranged
ahead of time an advance notice must be given to site and Construction Responsible about
scheduled installation so that they can plan their work thoroughly and give way for other
next activities.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 6
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 7 of 12
001 Chapter 10.Tag showing the casting date shall be placed on the portion done for easy
identifying curing duration.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 7
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 8 of 12
3.2.1.0 Earthwork shall be carried out as per required level and slope.
3.2.1.1Compaction of filled materials on erected posts location shall be done prior to start
placing fixation Chain Link fabric.
4.0 DEFINITION :
Client : Saudi Aramco
Project: South Ghawar UR Early Works & TCF
Location: South Ghawar, Eastern Province, KSA
Sub-Contractor: Abdul Mohsen AH Al-Tamimi Partners Co.
Method Statement: A written document that explains the planned execution methods to control
the work at various stages.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 8
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 9 of 12
The Safety Responsible review prior to the start of work, the Safe Work Plan that must be
implemented and abide by during site Preparation.
6.5 Inspection
Al-Tamimi Project in Charge Responsible and SAPID Representative shall carry out the
necessary inspections in all activities shall be based on standard drawing given by client
Representative and Project Specifications listed in under references of this Method Statement.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 9
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 10 of 12
7.0 Quality
At all stages of this work, the quality of work plan shall be implemented and make sure that there
will be no deviation, shall institute testing and provision of the report based on the standards set
by client representative thru Aramco standard.
9.1.1 All equipment used for inspecting, measuring and testing of process control shall be
registered, controlled and shall check the document as per specification and standard.
9.1.2 All equipment shall signed certificate issued by the company performing the assurance.
Any rejected equipment shall be removed from service by the Engineer and shall not be used
until has been repaired, records shall show:
Equipment reference/serial number & model
Description
Manufacturer of supplier
Date of last certificate and name of person or company who signed and issue
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 10
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 11 of 12
10.1Safety Officer shall carry out the safety site inspections to ensure that safety requirements
laid out in safety work plan are followed during the survey work. Safety Supervisor shall review
safe work plan and safety action plan and secure Work Permit (if necessary) prior to start of the
work. Personal protection shall be provided to all personnel involved in the job.
10.2 Barricades shall be set up around the sites. Warning signs shall be posted to caution other
personnel on site of the ongoing work. The Material Safety Data Sheet (MSDS) of a hazardous
material shall be available whenever in use at site.
10.3 Health , Safety and Environment issues shall be guided by AL-Tamimi project safety policy
and Aramco Standards.
10.6 Safety Tool Box and talk shall be conducted to conscientise the operatives of the risk
involved before commencing the activity.
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 11
Doc. SGEW XXX
Revision 00
ABDUL MOHSEN A.H. AL
Date March 22, 2020
TAMIMI Partners Co.
Page No. Page 12 of 12
11.0 Abbreviations
MS - Method Statement
IFC - Issued For Construction
ACI - American Concrete Institute
ASTM - American Society of Testing Materials
MSDS - Material Safety Data Sheet
SAMSS - Saudi Aramco Material Standard Specification
SAES - Saudi Aramco Engineering Standard
SAEP - Saudi Aramco Engineering Procedure
NGL - Natural Grade Line
PPE- - Personal Protective Equipment
12. Attachment
Method Statement Installation of Type IV & V Chain Link Perimeter Fence Page 12