Professional Documents
Culture Documents
Rate Analysis
Rate Analysis
7 Good quality local chimney made brick work in cement sand cum
mortar (1:4) in perfect line, level and finishing including ,
curing, raking out green mortar from joints and cleaning the
brick face before stopping the work and proper bonding with
existing masonry all complete as per drawing, specification and
instruction by the Engineer.
8 Providing and laying flat brick soling with voids filled with sand sqm
in foundation in line and level all complete as per drawing,
specification and instruction by the Engineer.
A Labor Unit Rate Amount
Skilled labour 0.05 MD 775.00 38.75
Unskilled labour 0.10 MD 465.00 46.50
Total A 85.25
B Material
Brick 42.00 nos 10.62 446.04
Sand 0.07 cum 1900.00 134.90
Total B 580.94
Total A + B 666.19
Overhead 15% 0.15 99.93
Total cost 766.12
9 Providing, mixing and laying P.C.C. in 1:1.5:3 ratio for cum
foundation, flooring, beam with stone aggregate 20 mm down
with proper compaction and completion to perfect line, level and
finishing including proper curing all complete as per drawing,
specification and instruction by the Engineer.
10 Providing, mixing and laying PCC in 1:2:4 with aggregate upto cum
20 mm for foundation and walls all complete as per drawing,
specification and instruction by the engineer.
13 Cement plaster works over on walls, with cement sand mix (1:4) sqm
and 12.5 mm thick or as per existing plaster thickness in perfect
line, level and plumb, making grooves on boundary of existing
plaster and new plaster including cleaning and wetting the
surface and curing all complete as per specification and
instruction by the Engineer.
19 Supplying and fixing clay tile works as per specification all sqm
complete.
A Labor Unit Rate Amount
Skilled labour 0.05 MD 775.00 38.75
Unskilled labour 0.15 MD 465.00 69.75
Total A 108.50
B Material
Machine made tile 18.4 nos. 18.00 331.20
Total B 331.20
Total A + B 439.70
Overhead 15% 0.15 65.96
Total cost 505.66
20 Supply, making and fixing of sal wood frame of good quality sal cum
wood for doors, windows frame size 120 mm x 100 mm finished
size as per drawing and specification all complete.
A Labor Unit Rate Amount
Skilled labour 34.00 MD 775.00 26,350.00
Unskilled labour 3.40 MD 465.00 1,581.00
Total A 27,931.00
B Material
Sal wood 1.10 cum 162449.00 178,693.90
hold fast 92.00 nos 17.29 1,590.28
screw 184.00 nos 2.06 379.04
Total B 180,663.22
Total A + B 208,594.22
Overhead 15% 0.15 31,289.13
Total cost 239,883.35
21 Suplying an Injecting Epoxy grout chemicals ( filler, mortar, m
fuels) after cleaniong and surface preparation as per
manufacturer's specification all complete.
Unit Rate Amount
Epox injection materials, equipment and personnel 1.00 11412.00 11,412.00
Total 11,412.00
Overhead 15% 0.15 1,711.80
Total cost 13,124.00
22 Providing, fitting and fixing woods for shoring and supports for sqm
trenching works as per specification and instruction by the
Engineer.
A Labor Unit Rate Amount
Skilled labour 0.005 MD 775.00 3.88
Unskilled labour 0.010 MD 465.00 4.65
Total A 8.53
B Material
Kamsal wood 0.0416 sqm 1,434.66 59.68
Shore and props 0.00254 Cum 33,721.05 85.65
Total B 145.33
Total A + B 153.86
Overhead 0.15 23.08
Total cost 176.94
b/ k|lt j=dL=sf]
19,828.70 Ö ?= 8,832.38
2.25
b/ k|lt j=dL=sf]
7,685.93 Ö ?= 768.59
10.00
50 m
b/ k|lt j=dL=sf]
1,432.65 Ö ?= 143.26
10.00
Snf] cu|fv sf7sf] k|m]ddf
j} tkm{ 7f]sL ˆnz vfkf agfO{ hf]8\g] .
@ x @=)%* Ö @=@$% j=ld= lnOPsf]
PsfO{ b/ k|lt PsfO{ /sd
hjfg 775.00 5,425.00
hjfg 465.00 325.50
3=dL= 214,673.03 7,427.68