For the construction of a two-storey residential building at Coconut
Highlands Subdivision
You are hereby notified to commence work in accordance with the
agreement dated January 2, 2019 on or before January 4, 2019 and you are to complete the work within 365 calendar days from the receipt of this notice. A notice of Start of Construction and all required pre-construction documents must be submitted to the Public Body no later than one (1) day prior to commencement of work.
Sincerely,
Hanna Mae M. Mata
ACCEPTANCE OF NOTICE Acknowledged by: Engr. Ernest Adrian Co Signature: Date: January 3, 2019