SECTION:A RESEARCH WORKS
1.0 Centrally Sponsored Research Schemes under National 1
Hydrology Project
2.0 Hydraulic Research Work for States 1
3.0 Geo- Technical Investigation for state 11
4.0 Deputy Director's Office work 11
5.0 Road Research Division 1 & 4 research work 11
6.0 Soil Drainage And Reclamation Circle 14
7.0 Dam Safety Organization 14
SECTION:B Test conducted on various material
Tests conducted on various materials - ANNEXURE-I 17
Field Investigation by soil drainage and reclamation circle - 21
ANNEXURE-II
Field test Activities Conducted by various divisions- ANNEXURE-III 23
Details of tests performed- ANNEXURE-IV 24
Soil investigation & testing Reports- ANNEXURE-V 25
SECTION:C
Special creditable work ANNEXURE-I 28
SECTION: D
1.0 Sub Soil Water Table reports (S.S.W.T.) by S.D.R. circle. 30
2.0 Deputation to Symposium/Conference/Seminar 32
workshop/training etc. attended by GERI Officer during year
2018-19
3.0 Workshop/ Seminars / Training / Organised by GERI during 33
the year- 2018-19
3.1.1 4 Training to personnel at Staff Training Center, Gandhinagar
4.0 Technical Forum Organised by GERI 34
5.0 Equipment procured during 2018-19 34
6.0 Visit by Dignitaries 34
7.0 Library Publication 35
8.0 Budget provision and expenditure during year 36
SECTION:E
Research Personnel 37
INTRODUCTION

Gujarat Engineering Research Institute (GERI) is one of the leading research


institutes of the country. It has the distinction of being adjudged as one of the best
research stations of the country as evidenced by honors bestowed upon it by CBIP
in the year 1989. GERI is working under Narmada Water Resources, Water Supply
& Kalpasar Department. The Institute aims at providing research and development
inputs to the activities of the Gujarat State in the field of water resources, irrigation
and roads & buildings. To this end it has its activities centered on construction
materials, soil, rocks, grouting materials etc. The activities are for investigations,
testing, consultancy, training, and quality control in addition to R & D as stated
above. It extends facilities to Government of Gujarat/ inter-state Government,
public and private sector bodies in the above different activities.

Making a humble beginning as sub division in 1950, GERI developed into a


research division in 1957. By 1960 when the Gujarat State was formed, it attained
the status of state research institute with 3 divisions as materials, soil-mechanics
and highway engineering.
Then onwards GERI progressively expanded its activities in the subsequent
decades and has now blossomed into 13 divisions.

A Director who is of the rank of a Chief Engineer heads the Institute. There
are three posts of Joint Director/Superintending Engineer manned by the officers
who are of the rank of Superintending Engineer, Joint Director (Roads) looks after
the works of Roads and buildings wing. Joint Director (Irrigation) looks after the
works of Irrigation wing, & the work of inspections of safety of all completed dams
of the state which is done by Executive Engineer (civil) & Executive Engineer
(Mech.) under Dam Safety Organisation, Superintending Engineer; Soil, Drainage
and Reclamation Circle looks after the works of Soil Survey wing.

Research work is organized in various divisions by the respective Research


Officers who are of the rank of Executive Engineer including Geologist (Senior-
Class-I officer) of Engineering Geology Division. Suitable technical and scientific
staff assist them. In addition to main laboratories at Vadodara, the institute has
regional research/testing divisions at Surat, Rajkot and Gandhinagar.
Under each regional division, set up of district laboratories are also there.
PRELUDE

It gives me immense pleasure in presenting this Annual Report of Gujarat


Engineering Research Institute (GERI) for the year 2018-2019.
GERI is a premier R & D Institute of Government of Gujarat working under
Narmada Water Resources, Water Supply and Kalpsar Department. It is entrusted
with the work of Research, Investigation, Testing, Consultancy & Training in
Various disciplines of civil engineering which includes Soil Mechanics, Material
Testing, Geo mechanics Grouting Technology, Engineering Geology, Remote
Sensing, Seismology, Hydraulic Model Studies, Sedimentation Surveys, Road &
Traffic Engineering, Dam Safety, Soil surveys etc.
On research side, GERI had carried out research study by Road Research
division for Study of black Spot in Vadodara City & ‘Y’ intersection at Anand
junction, Gujarat. Also, model study for 4 hydraulics structures completed and 6
hydraulics structures have been carried out and is in progress during the year.
Total 117604 samples were tested in various laboratories of GERI during the
year. Dam Safety Organisation of GERI has inspected 70 large dams and 52 gated
dams and recommended safety measures to the project authorities. Over and
above, DSRP- I and II have visited 25 dams for reviewing their safety and remedies
for long term measure
During the year about 16.07 lac ha GCA pre & post irrigation survey has
been carried out by Soil Drainage Reclamation Circle under GERI. To enrich and
update the technical knowledge of state engineer/ scientists, GERI has organized 1
Technical Forum, 5 workshops/one-day Seminar. Also GERI personnel have
attended 6Training programs. During the year 51 new books were added in GERI
library.
The Annual Report presented here is a nutshell of activities of the institute
carried out during the year 2018-2019. I wish to place on record, sincere and hard
efforts made by each one in GERI, for doing appreciable work. Suggestions and
comments on the works reported herein are most welcome.

K. A. Keshvani
Chief Engineer & Director,
GERI, Vadodara.
SECTION-A

RESEARCH WORKS

1.0 A . Centrally Sponsored Research Schemes

 Project on ‘Establishment of 10 New Seismological observatories in


peninsular shield region".

Seismic monitoring in the seismological observatory established at


Dharoi project, north Gujarat, under World Bank Aided DST, New Delhi’s
project, is being carried out. The data is being online transmitted to National
Geophysical Research Institute, Hyderabad through VSAT communication
system, for further analysis and studies.

B. National Hydrology Project

Ministry of Water Resources, River Development and Ganga Rejuvenation


(MoWRGD), Govt. of India has taken up National Hydrology Project Phase-III,
which is now called NHP, with financial assistance of World Bank. Since inception
of Hydrology Project Phase – I (1998) GERI is continuously monitoring surface
water quality of 180 locations of major rivers and reservoirs of Gujarat State. There
are 2 GERI laboratories at Vadodara and Gandhinagar working for Hydrology
Project. Yearly average 500 water samples with different parameters are tested in
these 2 laboratories. Three Purpose Driven studies are also going on under NHP
III.
2.0 Hydraulic Research Work for State

1.0 General
Narmada Hydraulic Division at Gotri, Vadodara carries out Model Study which
includes Hydraulic Assessment of Irrigation structures like Dams, Spillways,
Weirs, Barrages, Study of Erosion of Bridges and River Banks by flood, Study of
Alignment and Performance of New Bridges, Canals and Canal Structures by
way of Hydraulic Model tests. The following assignments of Model Studies are
being taken up:
AA (A) Study of Narmada Basin Hydraulic Models
(1) (1) The Bhadbhut Barrage on Narmada river
(2) (2) Model study for revised design flood on comprehensive (3D) model for
(3) Bank Protection work by Gabions around Parking Plot near View Poin-1
(4) in Downstream of Sardar Sarovar Dam.
(5)
1
(6) (B) Study of Sabarmati Basin Hydraulic Models
(1) Protection work on Banks of River Sabarmati at village Kasindra.
(2) Floor Protection works of Lakroda Barrage on composite model.
(3) Model Study work of Hirpura Barrage Project on river Sabarmati.
(C) Hydraulic model studies for tail channel of Ukai spillway for Protection
Works of Divide Bund.
(D) Flood protection work on banks of River Hathmati at village Moti Damoi
Near Himmatnagar.
(E) Model Study work of Purna Tidal Regulator on river Purna.
(F) Sectional & Composite model studies of Vaghrech Recharge project,
Dist: Navsari
(G) Sectional & Composite Model study of Parwan Dam, across Parwan river in
Jhalawar dist., Rajsthan

Model Study Works Carried Out During the year 2018-19:


(A) Sectional model studies (2D) and Composite (3D) of Parwan dam, across
Parwan river in Jhalawar Dist., Rajasthan.

Water Resources Department of Rajasthan has envisaged a scheme of


irrigation and water supply by constructing a dam across the Parwan River, a
tributary of the river Kali Sindh which in turn is a tributary of river Chambal,
near village Akwad Kalan in Jhalawar District, Rajasthan. As per directives
given by Central Water Commission, the Water Resources Department
engaged Gujarat Engineering Research Institute (GERI) to conduct Physical
Model study of the Parwan Dam for assessing the hydraulic performance of
energy dissipation, upstream water levels and qualitative scour in the
downstream side on the sectional (2D) model and the study of flow pattern,
upstream & downstream water levels with reference to banks, performance of
training walls and river training works on the banks on the comprehensive
(3D) model.
Based on the data given 2D model had been constructed and run for
various discharges. Performance of the model run had been studied and
report for the same had been submitted.
Based on the data given 3D model had been constructed and run for
various discharges. Performance of the model run had been studied.

2
Officers from Irrigation Department of Rajasthan, Central Water Commission,
New Delhi and HCC during their visit to GERI.

SECTIONAL MODEL REPRESENTING TWO SPANS IN OPERATIVE CONDITION

3
(B) Study Of Narmada Basin Hydraulic Models
(1) Bhadbhut barrage On Narmada River (Kalpasar Dept)

4
(a) 3 - D COMPOSITE MODEL STUDIES OF BHADBHUT BARRAGE

Various studies have been carried out on 3-D model with horizontal
scale 1:250 & vertical scale 1:50. The reports of the studies had been already
submitted to the Kalpsar department.
During the year 2018-19, the model had been run during the
Technical Visits of Higher officers from Kalpsar Department and Bidders
interested in the said work, visit of members of Khatri Samiti, Visit of Officers
from CWPRS, Pune and other Higher Authorities from Gandhinagar.

(C) Study of Sabarmati Basin Hydraulic Models


(1) Composite Model Study of Bank Protection work on River Sabarmati at
village Kasindra
Superintending Engineer, Ahmadabad Irrigation Project Circle,
Ahmadabad has suggested to carry out the Composite Model study of Bank
protection work at Village Kasindra.
In this context Reproduction of Topography work as per revised data
received had been completed and requisite runs for model study had been
also taken. Final report of the said study had been submitted.
(2) Floor Protection works of Lakroda Barrage on Composite Model

Fig –Extension and depression of downstream apron as suggested by CDO


5
Reproduction of Topography & Construction of 3D Model Structure as per
data given had been completed. Model runs for different discharges had been
taken and different alternates of downstream apron size and design had also
been carried out. Study report for the said study had been submitted.

(3) Model Study Work of Hirpura Barrage Project on river Sabarmati, Tal:
Vijapur, Dist; Mahesana
Proposal with topographical and design data received from
Superintending Engineer, Sujalam Suflam Circle-2, Kherva, Mahesana for
2D and 3D model study work of Hirpura barrage project on river Sabarmati.
By Analyzing the Data, 3D model had been reproduced on model tray
with the G.S.S. 1:80. Calibration and Validation of model had also been
carried out.

(D) Hydraulic Model studies for Tail Channel of Ukai Spillway for Protection
Works of Divide Bund.

During the past moderate floods considerable scour in the river bed along
the guide bund, close to the nose and excessive erosion on the nose portion
itself was observed. This divide bund is an important component of tail
channel which divert the flood from left side to the main stream of river. The
damage to the nose of divide bund was the cause of concern to the project
authorities to protect it from further damages in subsequent years in low to
moderate floods as these floods are likely to be released frequently in tail
channel.

6
Fig - Damage along the guide bund, close to the nose of Divide bund

Fig - Construction of rigid bed in the close reach of divide bund


7
Fig- Flow pattern along the guide bund, close to the nose of Divide bund

CDO had suggested to carry out the model studies with rigid bed in the
close reach of divide bund so as to resemble non erodible river bed condition
close to the bund in the tail channel for observing the performance of
protection work. The topography of the river bed was further transformed to
rigid bed close to the bund as shown in the photograph. The protection work
at the damaged nose portion of guide bund was modified as per the
drawings supplemented with the revised proposal of CDO vide letter no-
CDO/D/Ukai dam/Damage devide bund restoration/27 dated 8/5/2017.
The model was operated from 2 Lakh cusec to 12 lakh cusec flood
with this proposal. The observations of velocities and flow pattern were taken
along divide bund and tail channel for each discharge run close to the divide
bund on non-erodible bed. The report covering the model observations for
performance of protection work at various discharges on rigid bed model had
been submitted.

8
(E) Flood Protection work on banks of River Hathmati at village Moti Damoi
near Himmatnagar.
Reproduction of topography on model tray on the basis of data
given had been completed. Construction of bank profile had also been
completed. Calibration and Validation of model had been carried out.
Model had been run for various Discharges and Observations of water
levels, velocities and scour at various Q had been taken.
(F) Model Study work of Tidal Project on river Purna, Tal.Jalalpor, Dist:
Navsari
Construction of model tray had been completed. By analyzing the given
data, River Topography 4 km. on U/S and 11 km. on D/S had been
reproduced on model tray. The further study is stopped as project authority
have decided to put the project on hold.
(G) Composite model studies of Vaghrech Recharge Project, Dist: Navsari

Construction of model tray with Kaveri river and Ambika river profile
along with reproduction of topography and structure had been completed.
Study with different alternatives of discharges had been carried out. Report
for the same had been submitted.

River model without structure

9
Fig- Proposed Structural and bank protection work in Kaveri river near village
Vaghrech

Fig- Water profile in both Ambika river and Kaveri river

10
3.0 GEOTECHNICAL INVESTIGATION FOR STATE.

Sr. NAME OF THE TALUKA WORK DONE


No. PROJECT DISTRICT
PANAM PROJECT CIRCLE, GODHARA

1 Dhamnod check Shehra Geological investigation report based


dam (New) Panchmahals on 5 drill holes, 50 running meters, is
prepared, finalized and submitted to
Ex,Engr. Panam Project Dn, Godhara
and SE (G), CDO G’nagar. Vide this
office letter No. 251,Dtd : 06/08/2018.

4.0 Deputy Director's Office:


Collection, Compilation & Submission of Annual Report 2017-18 of GERI to
get approval from office of the Joint Director (Irrigation), GERI, Vadodara. After
getting approval the same was uploaded on GERI website. All administrative as
well as financial activity of GERI is being carried out centrally by this office.
For recruitment of Scientific cadre (minimum qualification Graduate in
Science / Diploma in any stream) on out sourcing basis e-Tender has been
published.

5.0 ROAD RESEARCH DIVISION 1 & 4.

(A) Abstract of state sponsored Research Scheme under progress.

1.0 Study of Black spot in Vadodara City


Scope & Objectives:
The main objective is to identify the black spots on study stretch and to suggest the
remedial measures and ensure safety. The short term low cost remedial measures
to minimize the number of accidents will be prepared for smooth movement of
traffic. Field work has been completed and preparation of report is in progress.
1. INTRODUCTION:
 Black spots are locations having concentration of road accidents. Black
spots can be improved through the application of accident investigation and
prevention techniques.

11
2. Purpose of study:
This study is to identify the black spot in Baroda city, in the other word
accident prone location in the city. The FIR recorded from the two police
station of given root of Baroda city have been collected from 2016 to
2018.The FIR data was compiled and identify the black spot in city. Places
where more than regular accidents occur in particular road junctions are
termed as black spot. Finding out the reasons/causes for those accidents
and to suggest remedial measures in order to reduce and if possible to
eliminate the causes which contribute to the accidents.
3.SCOPE AND OBJECTIVES:
To develop a methodology to identify the most vulnerable accident stretch
along the National Highway. The results from the case study can be used for
better assessment of roadway section for future considerations. Similarly the
black spot studies on Alkapuri Garnala –Ambedkar cicle-Chakli circle-
Manisha circle was taken up.
The following points & deficiencies were observed at various black spot:
 Most of the location no zebra crossing for the pedestrian.
 Illegal parking on the road minimizing the road width for traffic which also
causes the accident.
 Present condition of road not good.
 No. of gaps at very short distance on divider/median.
 Height of plants on divider/median is more than permissible.
 Lack of signal & sign board.
Remedial measures for improvement:
 Gaps for crossing may be restricted upto certain length in the area of . V-
Mart, Raj-Laxmi society, Sir Sayaji Gruh exit, Akota sub-registrate office,
Reliance mall Exit, Binanagar Patel farm, Taksha complex.
  Proper maintenance of road surface, signals, signs, etc .
  Implementation of rumble strips & effective speed breakers.
 Remove unwanted plants on divider/median.
CONCLUSION:
 In this study it is observed that, as per accident data collected in route 1 near
Aklapuri Garnala, Circuit house, Chakli circle, Baroda Heart hospital,
Rajlaxmi soc, Malhar point, Havmore circle, Banker hospital, Kalash circle,
Cow circle, Akota bridge & route 2 Manisha circle, Tube company, Rajvee
Tower, Toran complex (way to ward no.6), Devdeepnagar soc.,Reliance mall
exit, Akshar chowk have been identified as black spot.
 As a precautionary measure, to aware the public, informatory sign boards
may be placed at suitable location to take precaution in driving for safety &
security to avoid accidents, injury & loss of life. Statistical data may be
highlighted with catch lines for added safety.

12
2.0 A Case Study of “Y” Intersection” @ Anand junction,Gujarat.

Objective:

 To reduce the conflicts at major to major road approach intersection.


 An intersection where all roadways join or cross at the same level.
 To provide minimum and maximum clearance to the exit and entry
respectively.
 Provide speed change lanes (Acceleration and Deceleration lanes)

 JUNCTION AND ROAD INVENTORY:


Intersection under consideration is (1) Kheda-Mhemedabad-Mhudha-
Dakor-Umreth-Bhalej-Anand-Vadtal Road –SH-60 and (2) Anand-Bhalej-
Dakor Road Crossing Expressway and approaching Expressway on
either side towards Ahmedabad & towards Vadodara. This junction is
located on Anand town side, approaching the Expressway and towards
village Samarkha. It is located at about 1.2 km from Anand-Samarkha
Chokdi towards Expressway. Hence, at this intersection having a conflict
of traffic from either side. And No of Accidents measure @ this junction.
In particular, the traffic from Samarkha and other villages approaching
Anand is to be guided properly to avoid the conflict at intersection. Data
is collected from R&B(state) Div,Anand.

 SCOPE OF WORK:
As the NH-48 (from Ahmedabad to Vadodara) and Express Way (NE-1)
roads through Ahmedabad to Vadodara where traffic is crossing on both the
roads in both directions. At present, traffic approaching junction is having
heavy traffic with all type of vehicles, and it is increasing at a faster rate. At
Present Y-Intersection shows the link of the Anand SH-60 to NE-1
(Vadodara-Ahmedabad Express way) Road and connecting to samarkha
Approach Road. In case study of Y-junction, we consider Two Different type
of case.

SUMMARY: -
 Intersection has been design considering rotary junction looking to the
present geometry of the site and the present traffic scenario and the data
available from the Division of State R&B Department of Anand.
 The details and standard design of the Junction can be coherently done for
considering NH-48 and NE-1 through traffic along with Local/Rural traffic.
 All the three roads are widening to 4-lane looking to the rise /increase in the
traffic in future.
 All three roads are provided with 5 mt wide median.
 Elliptical Rotary Island is provided, looking present geometry of the
intersection.
 Rotary Island and other features are designed as per site situation and IRC:
65-1976.
13
 The AutoCAD Drawing of the ‘Y’ intersection @Anand junction is prepared.
 Road Furniture & features are provided as per guidance of IRC:67-2012.
 By providing designing this rotary junction, not only the number of accidents
will reduce but it will provide easy and smooth maneuverability and transfer
and showing in fuel and time of traveling.

Position: Final Report is submitted to the concern department after scrutiny


of higher authorities.

6.00 SOIL DRAINAGE AND RECLAMATION CIRCLE:

This circle is engaged in different types of soil survey in irrigation command areas
for major and medium irrigation project of the state. Pre-irrigation surveys are
needed at project appraisal stage. Post-irrigation investigations are carried out after
execution of the project.
At present 41 major and medium irrigation schemes are under observation for sub
soil water table and quality, twice in a year i.e. pre & post monsoon, covering 16.07
lakhs ha. G.C.A.
During the year 2018-19 this circle has carried out soil survey and sub soil water
table observations work in different irrigation projects and its details are as
Annexure II.

7.0 DAM SAFETY ORGANISATION


The Dam Safety Organization(DSO), GERI jointly deals with other offices of
dam authorities for 632 large dams. As per new definition by ICOLD for large dam
483 dams are classified as large dam ( As per CWC criteria ) DSO, GERI deals
with pre monsoon inspection of dams as per list of dams furnished by OSD ( IP
),Gandhinagar and accordingly Inspection reports are furnished to concern dam
authorities for dam safety in respect of Civil, Mechanical and Electrical aspects
assessing hazard potential and determining priority for repairs and suggesting
remedial measures in consultation of CDO, Gandhinagar to restore & improve
them. Dam Safety Organization (DSO) acts as a link 1) for updating NRLD as per
the details received from the dam authority. 2) For updating & compilation of detail
viz, Instrumentation, Seismic Zone 3) For preparation of emergency action plan
(EAP) for large Dams.
Dam Safety Organization (DSO) publishes annual report on health status of
all the dams inspecting, incorporating the activities of dam safety organization every
year. It also acts as a link between Central Water Commission (CWC) and owners
of dams for onward transmission of the matters & policies reviewed from CWC.
14
1. The details of large dams inspected during the year 2018

Sr. Type of Nos of Inspection of Dam by Nos of Dam Inspected


No. Dams respective wing during year 2018- with irrigation Mechanical
19 Circle 1-2
By Civil By Mech.& Elect. By Civil wings of DSO
Wing Wing gated dams)
1. Large 55 52 15
Dams
(As per
CWC
guideline)

2 The proposal of pre-monsoon inspection of Ajwa, Pratappura & feeder


channel for the year 2018 is received from VMSS, Executive Engineer, water
supply (Project), VMSS, Vadodara office letter in vernacular no. 0415, dated.21 -1-
19. But, the payment of previous year towards inspection is yet not paid to GERI,
Vadodara by VMSS till today even after repeated reminders.
The Central Water Commission (CWC), Government of India has
suggested a Dam Safety Review Panel (DSRP) at state level through the country to
serve the purpose of safety inspection of important dams.
There are 632 dams in Gujarat state which are required to be reviewed for
their safety and regular performance. Every year 60 dams are required to be
inspected so that each dam is inspected once in 10 years. Keeping in view the
seriousness of the need of safety inspections of the dams and follow up action.
Government of Gujarat has formed two panels having 1 (one) chairman & 7
(Seven) members each inspection of dam of Gujarat & to review the safety vide
Government of Gujarat Resolution no. GEN-2008-IB-(9)/M.I. Cell-K-I,
Dtd.30.08.2018. Looking to the necessity and scope of work, additional members
included in DSRP team vide Gr dtd. 31/12/2018 and 06/03/2019.
Both the DSRP team have visited 25 dams for reviewing their safety and
remedies for long term measure up to 31 st March 2019.
List of Dams Visited by DSRP Team
Draft Final Report
Sr.No. Projects Date of Visit Panel
Report
28/12/2018 DSRP 1 15/03/2019 12/04/2019
1 Kadana
29/12/2018 DSRP 2
02/01/2019 DSRP 2 04/05/2019
2 Ukai
03/01/2019 DSRP 1

15
3 Panam 10/01/2019 DSRP 1 15/03/2019 12/04/2019
4 Bhadar-1 10/01/2019 DSRP 2 03/05/2019
5 Hiran-1 11/01/2019 DSRP 2 15/05/2019
6 Machhundri 12/01/2019 DSRP 2 15/05/2019
7 Watrak 17/01/2019 DSRP 1 27/03/2019 12/04/2019
8 Mazam 18/01/2019 DSRP 1 22/03/2019 12/04/2019
9 Karjan 12/02/2019 DSRP 1 22/04/2019 22/05/2019
10 Sukhi 13/02/2019 DSRP 1 04/06/2019 01/08/2019
11 Dharoi 13/02/2019 DSRP 2
12 Deo 14/02/2019 DSRP 1 03/07/2019
13 Mukteshwar 15/02/2019 DSRP 2 20/05/2019
14 Dantiwada 16/02/2019 DSRP 2 20/06/2019
15 Damanganga 18/02/2019 DSRP 1 13/05/2019 30/07/2019
16 Jhuj 19/02/2019 DSRP 1 29/06/2019
17 Kakadiamba 20/02/2019 DSRP 1 20/05/2019 01/08/2019
18 Ver-II 21/02/2019 DSRP 1 20/06/2019 01/08/2019
19 Sipu 15/03/2019 DSRP 2 11/06/2019
20 Shetrunji 15/03/2019 DSRP 1 29/04/2019 22/05/2019
21 Meshwo 15/03/2019 DSRP 2 20/05/2019
22 Guhai 16/03/2019 DSRP 2 11/06/2019
23 Vartu-II 27/03/2019 DSRP 2 08/05/2019
24 Sani 28/03/2019 DSRP 2 03/05/2019
25 Umiya Sagar 30/03/2019 DSRP 2 08/05/2019

16
SECTION B
1.1 Tests conducted on various materials are as under.
Annexure I
S.No Materials / Test Total No. of test conducted during the year 2018-2019

SM Dn. MT Dn GM Dn RRD-1 RRD-4 SGRD NGRD SRD, SDR,


Surat G'nagar Rajkot Circle
1 2 3 4 5 6 7 8 9 10 11
1 Aggregate/coarse aggregate - 458 - - 1490 3837 9271 - -

2 Aggregate/Fine aggregate - 360 - - 1208 2588 - -

3 Asphalt 1149 - -
4 Binder content - - - - - 22 41 1483 -

5 Bitumen (Core Density) - - - - - 182 - -


6 Bitumen Mix - - - - - - - 670 -
7 Bitumen Mix Design - - - 6 - - - 108 -

8 Bricks/Air Bricks - 231 - - - 325 798 508 -


9 Lime Stone - 12 - - - - - - -
10 C.C.Block - - - - - - - 235 -
11 C. C. Cube - 2495 - - - 11090 20148 15702 -
12 C.M. Cube - - - - - - - 77 -

17
S.No Materials / Test Total No. of test conducted during the year 2018-2019

SM Dn. MT Dn GM Dn RRD-1 RRD-4 SGRD NGRD SRD, SDR,


Surat G'nagar Rajkot Circle
1 2 3 4 5 6 7 8 9 10 11
13 Cement(chemical) - 31 - - - - - - -
14 Cement(physical) - 682 - - - 1210 1497 1935 -
15 Core sample/ Core density & - - - - - 90 53 - -
B.C.
16 Conc. Mix Design - 254 - - - 237 219 297 -
17 Curing compound - 46 - - - - - -
18 Density & Porosity - - 7 - - - - -
19 Emulsion - - - 8 - - - - -
20 Flush door -
21 Geo Synthetic 2 - - - - - - - -
22 GSBM design - - - - - 66 - - -
23 Metal - 13 - - - - - 7091 -
24 Mix design (Asphalt) - - - - - 50 24 - -
25 Marshal Mould - - - - - 34 305 - -
26 Paint - - - - - - - - -
27 Rubble/Stone - 36 - - - 33 54 190 -
28 Sand - 18 - - - - 2076 -
29 Soil 552 - 197 692 342 493 10

18
S.No Materials / Test Total No. of test conducted during the year 2018-2019

SM Dn. MT Dn GM Dn RRD-1 RRD-4 SGRD NGRD SRD, SDR,


Surat G'nagar Rajkot Circle
1 2 3 4 5 6 7 8 9 10 11
30 Soil Road (Murrum) - - - - - 288 1718 347 -
31 Soil (Chemical) - 93 - - - - - -
32 Slake Durability - - 19 - - - - - -
33 Steel - 1787 - - - 1498 2787 2788 -
34 Rock/Core 24
35 Timber - 9 - - 11 42 - -
36 Tiles - -
37 True Specific gravity - - 27 - - - - - -
38 Unconfined comp. strength - - 26 - - - - - -
test
39 Viscosity Grade Bitumen (VG) - - - 277 - - - - -

40 Water - 281 - - - - 330 - 11108


41 Water / Hydrology water - 313 - - - - - - -
sample
42 Water Absorption - - 27 - - - - - -
43 WMM design - - - - 47 - - -
44 Wood - - - - - - - 81 -

19
S.No Materials / Test Total No. of test conducted during the year 2018-2019

SM Dn. MT Dn GM Dn RRD-1 RRD-4 SGRD NGRD SRD, SDR,


Surat G'nagar Rajkot Circle
1 2 3 4 5 6 7 8 9 10 11
45 Triaxial Test - - 10 - - - - - -
46 Mix Design for Plastic - - - - - - - - -
Concrete(Grouting Lab)
47 Modified Bitumen - - - 1 - - - - -
48 Chemical leaching 53
49 Concrete ( Core) 70
50 Porosity Test 7
51 Cement Mortar 2
Total 554 7242 124 489 1490 20922 41366 34105 11118
Grand Total 117410

1..2 Petrological Laboratory Unit

Sr. Particulars No. of sample


No. tested
1 Rock Megascopic & Microscopic examination 167
2 Petrographic analysis of crushed fine Aggregates 27

20
Annexure II
Field Investigation by soil drainage and reclamation circle: -
(A) Pre/ Post Irrigation Soil Survey (D.S.S / Reco. S.S etc.)
TABLE
Work done during
Sr. Name of
Type of Work Total area in ha. the Year 2018-19
No project
(Area in ha.)
1. 2. 3. 4. 5.

---- NIL ---

(B) Sub Soil Water Table Observations: -

Twice in a year i.e. Pre & Post Monsoon (2018-19)

Sr. Name of Type of Work Total area in Work done during the
No project ha. Year 2018-19
(Area in ha)
1. 2. 3. 3. 3.
(1) Machhu S.S.W.T. 18211 18211
(2) Brahmani " 17600 17600
(3) Demi-II " 4765 4765
(4) Aji - II " 3150 3150
(5) Vartu " 3500 3500
(6) Ghee " 2833 2833
(7) Sasoi " 5250 5250
(8) Moj " 12146 12146
(9) Kalubhar " 6050 6050
(10) Damanganga " 77935 77935
(11) Juj " 8950 8950
(12) Kelia " 5599 5599
(13) Ukai L.B.C " 116918 116918
(14) Kakarapar " 302783 302783
(15) Lakhigam " 1061 1061
(16) Ukai R.B.C " 85873 85873
(17) Karjan " 79724 79724
(18) Pigut " 2227 2227
(19) Ver-II " 7590 7590
(20) Mahi R.B.C " 270000 270000
21
Sr. Name of Type of Work Total area in Work done during the
No project ha. Year 2018-19
(Area in ha)
(21) Rani " 2150 2150
(22) Fatewadi " 129555 129555
(23) Hathmati " 49530 49530
(24) Kharikat " 24282 24282
(25) Meswo " 12788 12788
(26) Waidy " 2820 2820
(27) Sabarmati " 97424 97424
(28) Watrak " 25910 25910
(29) Mazam " 8000 8000
(30) Dantiwada " 81000 81000
(31) Mukteshwar " 11302 11302
(32) Sipu " 17937 17937
(33) Lakaroda " 3600 3600
(34) Panam " 58272 58272
(35) K.L.B.C " 15500 15500
(36) Bhadar(p) " 15500 15500
(37) Huduf " 8772 8772
(38) Machhnala " 3944 3944
(39) Umaria " 4148 4148
(40) Kabutari " 2230 2230
(41) Edalwada " 1612 1612
Total........ 16,07,945

22
Annexure III

Field test activity conducted by various divisions during year 2018-2019


as under
 Soil Mechanics Division done 31 core cutter, 75 Drilling work supervision
on Existing Structures.

 88 Collection of U/D samples by Shelby on Check Dam/ Earthen Dam and


existing structure. 38 SPT on Check Dam/ Earthen Dam and existing
structure..

 South Gujarat Research Division done 27 SPT.17 Disturbed sample.


Supervision – 221.00mt. (Only Supervision - depth of 08
Boreholes).Shelby 65 Nos.
 North Gujarat Research Division done 3 job (4SBC). (Annexure IV)

 S.D.R. circle done 3 Field test on soil.


 Road Research Division – 5 Retro Reflectivity test done at Bharuch
Dehgam road 200km to 211/300km (SH-6) under safe corridor
Demonstration program (GSHDP) of sec Gujarat State Highway Project.
 Benklement Beam Deflection Test done on Vadodara-Padra-Jambusar
Road at chainage km. 8/400 to 15/000.

23
Annexure IV
Sr. Name of Work Details of Tests Performed Safe Bearing
No.
Capacity
1 Construction of New Govt. 1 Grain size analysis 27.0 t/m2
Boys Hostel for S.C. at 2 Atterberg limits
Sector-15. Gandhinagar 3 FDD-FMC
4 Specific gravity
5 Swelling Index
6 Box shear
7 Triaxial
8 Consolidation
2 Construction of Palundra 1 Grain size analysis For Abutment
Checkdam across Meshwo 2 Atterberg limits 18.0 t/m2
river near village Palundra, 3 FDD-FMC
Ta. Dahegam, Dist. 4 Specific gravity For Body Wall
Gandhinagar 5 Box Shear 8.0 t/m2
6 Triaxial
7 Consolidation
3 Construction of Multi Storied 1 Grain size analysis 20.0 t/m2
Building for State level 2 Atterberg limits
Consolidation office at 3 FDD-FMC
Sector-14, Gandhinagar 4 Specific gravity
5 Box Shear
6 Triaxial
7 Consolidation
4 Construction of R.C.C. 1 Grain size analysis 11.0 t/m2
Frame Structure Building in 2 Atterberg limits
Gymkhana at Sector-19, 3 FDD-FMC
Gandhinagar. 4 Specific gravity
5 Box Shear
6 Triaxial
7 Consolidation

24
Annexure V
Soil investigation & testing reporting work done as under

Research reports
Specification for mechanically woven, Double twisted hexagonal wire mesh
Gabions, Revet mattresses and Rock fall netting with galvanized steel wire or
galvanized steel wire with PVC coating.
(A) Investigation and testing reports:

Sr. Name of Work done for the year 2018-19 Testing


No. Activities
performed
1 Construction of flood protection wall on village Motinaroli Ta. Manglor 16
Dist.Surat
2 Repairing and Renovation of D-1 /R of Main Canal and M-2/R of 17
main canal of Dami-2 Irrigation Scheme.
3 Methada Bandhara A/C river Bagad near village Methada Ta. Talaja 18
Dist. Bhavnager
4 Testing of Soil Sample for UGPL system of sub minor for Irri. 02
Through Kundies in chak wall from SSP.
5 Const. of Pipe Canal ch. 05 to 17960 mt and pipe canal of minor 22
M12, M2R,M3T, and M4T for Machu III, water reservoir project.
6 Und-1 Irri. Scheme, Testing of soil sample for 04
7 Satruji Bandhara a/c river Satrunji near village Sartanpur Ta.Talaja 12
Dist. Bhavnager
8 Testing of building material const. of shed in plot no 125-126 @ Por 1
Raman gamdi Industrial Estate. Dist. Vadodara
9 Widening of pathway and development of tourist facilities at 3
Pavagadh. Dist. Panchmahal
10 Testing of soil sample Kherva- Visnager, M S Pipe line project. 6
11 Const. of bridge a/c river Narmada Village Dabhoi-Sinor-Malsar 176
12 Renovation to Bavka (Navapura) village tank Ta. & Dis; Dahod 1
13 Construction of open jail at.Danteswer Vadodara. 1
14 Testing of soil samples consruction of Additional building for Aadersh 1
Nivasi school Limkheda.
15 Construction of Flood protection wall at village Kosadi. Ta.Mangrol 123
Dist; Surat
16 Work of Toe wall pitching at bamangam village tank near harigen vas 1
Ta.KARAJAN
17 Strengthening of earthen bandh of shree por timbi M.I. tank Ta. 6
Waghodiya
18 Restoration & Repairing in sansoli minor of 34/R Distributary of PMC 1
19 Testing of soil samples for Pharmacy building at PDR Dist. 1
Vadodara
20 Construction of Palasva(Gaun) Bandha near village palaswa Ta. 108
Raper Dis. Kuchchh
21 Renovation to tikaria village tank Ta.Jalod Dis; Dahod 2
22 Construction of command control room at PHO VADODARA. 1
25
23 Providing protection to inner slopes between ch.3050 to 3500m or 2
8/R distry or LBMC1
24 Testing of soil material talav beautification (Bandheli Talav) Chaklasi 1
25 Strengthening of causeway no.2 ta. Jodia T R scheme 1-2 & 3 at 13
village Jodia Dis Jamnagar
26 Construction of new vilage Tank at village Tamachiya mali falia Ta 2
Dis: DAHOD
27 Construction for lift irrigation MS pipeline project for Transmission of 2
400 cusecs of water no. Machhammala Dn no 3
28 Construction of Bagger home (Dinning hall) at varasiya VADODARA 1
command control room at PHO VADODARA.
29 Construction of Judicial staff quarter ( cat. C-2 unit cat.B-4 unit & cat 1
A-2 unit ) at Dhanpur Ta Dhanpur Dis DAHOD Bagger home
(Dinning hall) at varasiya VADODARA command control room at
PHO VADODARA.
30 Construction of VRB on Escape canal at ch.56325 mt of shedhi 1
branch canal at crossing of ratanpura-sarasavni road at ratanpur
31 Construction of miyagam ( Guneri ) Bandhara Ta Lakhapat Dis 64
KACHCHH.
32 Construction of bridge cross naramada river on Dabhoi-shinor- 90
malsar road ( SH-161) Dia VADODARA.
33 Renovation to zari-buzarge baba dev village tank Ta. Garbada & 2
Dis; Dahod
34 Safe Stage to Bhe(Handia) village tank Ta.Garbada Dis : DAHOD 2
35 Construction of shed at Danateswer vadodara (G.S.POLICE HOU COR. 1
LTD )
36 Construction of New Court building at Halol Dos Panchamahal. 1
37 Additional drilling work of shetrunjee bandhara across rover 190
shetrunjee near village satarampur Ta:Talaja Dis: BHAVANAGAR
38 Construction of shed of cow shed at open jail Danateswer vadodara 1
(G.S.POLICE HOU COR. LTD )
39 Construction of safe stage work to khangela (Gadarel falia) village 2
tank DAHOD
40 Construction of additional workshop & theary rooms at ITI VASAD. 1
41 Construction of Rural Polis station at Desar. 1
42 Construction of PSQ Cat-B-24 C-01 units at Desar Dis: vadodara 1
43 Construction of Homegurd training center at Jarod. Dis: VADODARA 1
44 Construction of NEW COURT BUilding AT Anklav Dis: AANAD. 1
45 Construction of development of wadhwan ird sanctury at Wadhwan 1
Ta.DABHOI.
B . Investigation and testing under progress :

1 Construction of PSC-2 ,B-40 Phase II , SRP Lalbag , Vadodara


2 Safe stage to Limdabar village Tank. Dahod .
3 Satruji Bandhara a/c river Satrunji near village Sartanpur Ta.Talaja Dist.
Bhavnager
4 Malashri Tridal regulatory scheme , Bhavnager
5 Const. of Development of Wadhavana bird of Wadhavana Ta. Dabhoi
6 Construction of Palaswa Bandhara Ta. Raper
26
7 Const. of new Court building at Anklaav dist. Anand.
8 The work of carrying out Non-Destructive Test (NDT) for divide wall of sump at
Dudhrej Scheme, Dist. Surendranagar under Senior Manager(C), GWSSB,
Surendranagar

27
SECTION C

ANNEXURE-I

Special creditable work done :

(i) Important works of concrete mix designs carried out at C&C Lab., MT
Dn. GERI, Vadodara

1. Concrete Mix Design for pre stressed concrete grade M-45

2. Concrete Mix Design for pre stressed concrete grade M-45 with high
performance characteristics

3. Concrete Mix Design for high performance characteristics for pumpable


concrete.

4. Concrete Mix Design for high performance characteristics for trimmie concrete.

5 Research work for self-Compacting Concrete as per EFNARC guide lines


(European Standards Guide lines) is taken on hand at C&C Lab., MT Dn. GERI,
Vadodara. Trials for the same are taken and work is under progress during the
year 2018-19.

The following Important projects for which CMD is prepared.

 Construction of High level major bridge of Unchh river on Bhindol-saloj-


Ambaji road
 Construction of major bridge at Chavad –Lathi- Amreli road at Village
Lathi
 Construction of high level major bridge in place of existing submersible
bridge on kharo river .Dist.Amreli.
 Construction of new ROB inplace of LC 17 at samlaya- Jarod road
 EPC contractor for lift irrigation , MS pipe line project for transmission of
400 Cusecs water from Kadana reservoir to Adalwada da.
 Construction of flyover of Gnda Circle to Manisha Cross Road at
Vadoara.
 Sauni Yojna phase-II link 4 , Package 5 Amreli.
 Construction of bridge on Khari river on kheda dholka road.

(ii) Consultancy offered By GERI

 Advice regarding arresting seepage of Indira Sagar Dam of NHDC, Khandwa


(M.P.)
 GERI Team comprising of (1) Shri U. C. Shukla RO(I/C) (2) Shri R.M. Jain,
ARO and (3) Shri J.M. Shah, JSA was carrying out Non-Destructive Test
(NDT) for cement concrete as consultants of GERI. On retirement of
Shri U. C. Shukla RO(I/C) and Shri R.M. Jain, ARO at the end of September
2018, Shri. R. J. Soni, R.O.(I/C) and Shri. C.J. Shah, A.R.O.(I/C) are
included in this team. The team guides the field officers carrying out Non-
Destructive Test (NDT) for cement concrete
28
(iii) Petrological Laboratory, Engineering Geology division, GERI

It is a unique and only laboratory of its kind in Gujarat where Megascopic &
Microscopic examination of rock (precise mineralogical composition &
texture is studied to identify the rock) is done and Petrological analysis of
aggregates (coarse as well as fine) is carried out to decide its suitability for
intended use by determining the quantity of chemically deleterious and
innocuous present in the sample

29
SECTION –D

Sub Soil Water Table (S,S,W.T.) Reports of the following Irrigation Projects
are Published.

Sr.No. Name of Project Report for the year Date of published


1 2 3 4
1 Ukai RBC 2017-18 20-02-2019
2 Kelia 2017-18 26-02-2019
3 Ver-II 2017-18 06-03-2019
4 Lakhigam 2017-18 16-03-2019
5 Rami 2017-18 16-03-2019
6 Ukai RBC 2017-18 20-03-2019
7 Kakarpur 2017-18 20-03-2019
8 Mahi RBC 2017-18 26-03-2019
9 Damanganga 2017-18 26-03-2019
10 Jhuj 2017-18 26-03-2019
11 Hathmati 2017-18 26-03-2019
12 Meshwo 2017-18 26-03-2019
13 Sipu 2017-18 26-03-2019
14 Waidy 2017-18 26-03-2019
15 Dantiwada 2017-18 26-03-2019
16 Mukteshwar 2017-18 26-03-2019
17 Fatewadi 2017-18 26-03-2019
18 Kharicut 2017-18 26-03-2019
19 Lakroda 2017-18 26-03-2019
20 Sabarmati 2017-18 26-03-2019
21 Watrak 2017-18 26-03-2019
22 Mazam 2017-18 26-03-2019
23 Bhadar(P) 2017-18 26-03-2019
24 Edalwada 2017-18 26-03-2019
25 Hadaf 2017-18 26-03-2019
26 Kabutari 2017-18 26-03-2019
27 Kadana LBC 2017-18 26-03-2019
28 Machhannala 2017-18 26-03-2019

30
Sr.No. Name of Project Report for the year Date of published
1 2 3 4
29 Panam 2017-18 26-03-2019
30 Umaria 2017-18 26-03-2019
31 Machhu 2017-18 28-03-2019
32 Brahmani 2017-18 28-03-2019
33 Demi-II 2017-18 28-03-2019
34 Aji-III 2017-18 28-03-2019
35 Vartu 2017-18 28-03-2019
36 Ghee 2017-18 28-03-2019
37 Sasoi 2017-18 28-03-2019
38 Moj 2017-18 28-03-2019
39 Kalubhar 2017-18 28-03-2019
40 Karjan 2017-18 28-03-2019
41 pigut 2017-18 28-03-2019

Executive Summary (S.S.W.T.) by S.D.R. circle.

Sr.No. Name of Project Report for the year Date of published


1 2 3 4
1 Machhu 2017-18 25-09-2018
2 Brahmani 2017-18 25-09-2018
3 Demi-II 2017-18 25-09-2018
4 Aji-III 2017-18 25-09-2018
5 Vartu 2017-18 25-09-2018
6 Ghee 2017-18 25-09-2018
7 Sasoi 2017-18 25-09-2018
8 Moj 2017-18 25-09-2018
9 Kalubhar 2017-18 25-09-2018
10 Hathmati 2017-18 28-11-2018
11 Meshwo 2017-18 28-11-2018
12 Sipu 2017-18 28-11-2018
13 Waidy 2017-18 28-11-2018
14 Dantiwada 2017-18 28-11-2018
15 Mukteshwar 2017-18 28-11-2018
31
Sr.No. Name of Project Report for the year Date of published
1 2 3 4
16 Fatewadi 2017-18 28-11-2018
17 Kharicut 2017-18 28-11-2018
18 Lakroda 2017-18 28-11-2018
19 Sabarmati 2017-18 28-11-2018
20 Watrak 2017-18 28-11-2018
21 Mazam 2017-18 28-11-2018
22 Bhadar(P) 2017-18 28-11-2018
23 Edalwada 2017-18 28-11-2018
24 Hadaf 2017-18 28-11-2018
25 Kabutari 2017-18 28-11-2018
26 Kadana LBC 2017-18 28-11-2018
27 Machhannala 2017-18 28-11-2018
28 Panam 2017-18 28-11-2018
29 Umaria 2017-18 28-11-2018
30 Karjan 2017-18 07-02-2019
31 Pigut 2017-18 07-02-2019
32 Ukai RBC 2017-18 07-02-2019
33 Kelia 2017-18 07-02-2019
34 Ver-II 2017-18 07-02-2019
35 Lakhigam 2017-18 07-02-2019
36 Rami 2017-18 07-02-2019
37 Ukai RBC 2017-18 07-02-2019
38 Kakarpur 2017-18 07-02-2019
39 Mahi RBC 2017-18 07-02-2019
40 Damanganga 2017-18 07-02-2019
41 Jhuj 2017-18 07-02-2019

2.0 Deputation to Symposium/Conference/Seminar workshop/training etc.


attended by GERI Officer during year 2018-19

1. Modul-1 Administrative on 23-4-18 to 27-4-18 attended by Shri. H.D.Rathwa ,(RO i/c)


2. Instrumentation and Seismic analysis of Gravity Dams with software application on
14-5-18 to 18-5-18 attended by Shri. R.J.Soni (ARO II)

32
3. Software application in Geotechnical Investigation. on 6-10-2018 to 7-10-2018
attended by Shri R.S.Vasava ,(RO i/c) , Shri H.D.Vakil (ARO III ), @ IGS Chapter
Vadodara.
4. Role of Geotechnical Engineering in Infra Structure Development in Civil Engineering
Practice. On 15-2-2019 attended all Staff up to JSA.
5.
Dam Instrumentation Rehabilitation of Existing Dam. On 7-3-19 to 8-3-19 by
Shri. R.J.Soni (ARO II) at CWPRS Pune
6.
Software Application in Geotechnical Engineering(SAGE-18),Organised By Indian
Geotechnical Society Chapter By Shri Bineeta S. Deshmukh

Training to Personnel at STC, Gandhinagar.

Sr. Subject Place Name of officer Period


No. who attended
Train the trainer of STC,Gandhinagar Chitraben 24.092018 to
Road Safety Audit . Chudasama,A.E 26.09.2018
Miss M.M.Vyas
A.R.O..

3.0 Workshop/ Seminars / Training / Organised by GERI during the year- 2018-19
Sr. Period Place Subject Name of officers who
No attended.
1 March -19 At Training of direct Chitraben
GERI,vadodara Recruit Class I and II chudasama A.E and
( appointment Humaben Siddiqui
Through GPSC)
2 12.02.19 to At NCBS Meeting & Shri P.B. Chaudhari
14.02.19 Bhuvneshwar ICAS Workshop Research Officer
3 04.06.18 to At SVNIT, Surat One Week Short Shri M. T. Kachiya
08.06.18 Term Training on Asstt.Research
Flood Analysis & Officer and
Modelling Shri P.J. Jani
Asstt. Engineer
4 04.06.18 to At WALMI, Flow Measurement & Smt. D.N .Pradhan
08.06.18 Anand Measuring Devises Asstt. Engineer and
at WALMI, Anand Shri P.J. Jani
Asstt. Engineer
5 01.02.2019 At Geri, Role of Ge- technical All staff of JSA level
Vadodara Engineering In Of M.T. dn.
infrastructural
Development by Prof
Amit Prashant &
Saurabh Vyas, IIT,
Gnadhinagar

33
4.0 Technical Forum Organised by GERI
S.No Subject Date Speakers
1 Role of Geotechnical Engineering in 15-02-2019 GERI, Vadodara
Infra Structure Development in Civil
Engineering Practice

5.0 Equipment procured during the year.


 Automatic Compaction Machine 01 No.
 Automatic Binder Content Machine 01 NO
 Humidity Chamber 01 No.
 CBR Mould 24 No
 Electronic Balance 01 No.
 Digital Oven 01 No.
6.0 Visit by Dignitaries to Field Hydraulic Laboratory, GERI, Gotri,
Vadodara During the 01/04/2018 to 31/03/2019

S.N Date Visitors


1 30/05/2018 Visit of officers from CWPRS, Pune - 2D/3D Bhadbhut Barrage Model.
2 02/06/2018 Visit of officers from Gandhinagar - 2D/3D Bhadbhut Barrage Model.
3 21/06/2018 Visit of officers from CWPRS, Pune - ATG of TAPI Model.
4 22/06/2018 Visit of officers from CWPRS, Pune - ATG of TAPI Model.
5 06/07/2018 Visit of 50 Students and staff from Polytechnic college, Bhavnagar.
6 23/07/2018 Visit of officers from HCC and W.R. Department Rajasthan - Parwan
2D model.
7 30/07/2018 Visit of Chief Engineer & other officers & staff from Kalpsar Project and
other members interested in Bid of Bhadbhut Model
8 06/08/2018 Visit of officers from Kalpsar Department, Gandhinagar - 2D/3D
Bhadbhut Barrage Model.
9 24/08/2018 Visit of 46 Students and staff from Gujarat Power Engineering And
Research Institute, Mehsana
10 28/08/2018 Visit of officers from CWC, New Delhi, HCC and W.R. Department
Rajasthan - Parwan 2D model.
11 30/08/2018 Visit of Chief Engineers & Superintending Engineers from SSNNL and
other Design Engineers from Dam Design office and Consultants –
Run of 3D Model of Sardar Sarovar Project for bank protection near
view point.
12 26/09/2018 Visit of Members of Khatri Samiti – Bhadbhut Barrage Model, Tapi
Model and SSP model.

34
13 04/10/2018 Visit of Chief Engineers & Superintending Engineers from SSNNL and
other Design Engineers from Dam Design office and Consultants –
Run of 3D Model of Sardar Sarovar Project for bank protection near
view point.
14 18/01/2019 Visit of 56 Students and staff from HJD Institute of Technical
Education & Research, Kera, Katchh.
15 29/01/2019 Visit of officers from HCC and W.R. Department Rajasthan - Parwan
2D model.
16 08/02/2019 Visit of officers from CDO, Gandhinagar and Project official – Hirpura
3D model
17 12/02/2019 Visit of Design Engineers from Dam Design office and Consultants –
Run of 3D Model of Sardar Sarovar Project for bank protection near
view point.
18 11/03/2019 Visit of officers from CDO, Gandhinagar and Project official – Moti
Demai 3D model
19 27/03/2018 Visit of officers from HCC and W.R. Department Rajasthan - Parwan
2D model.
20 28/03/2019 Visit of Chief Engineer & officers from Kalpsar Project and other
members interested in Bid of Bhadbhut Model - 3D Bhadbhut Barrage
Model.
21 29/03/2019 Visit of Chief Engineer & officers from Kalpsar Project and other
members interested in Bid of Bhadbhut Model - 3D Bhadbhut Barrage
Model.

7.0 Library publication:

(a) Nos. of books Procured

Indian authors- : 41 nos.


Foreign authors- : 02 nos.

(b) Nos. of journals/periodicals subscribed:


Indian - 08 nos
List of Indian Journals
1. Indian journal of Geosynthetics & ground improvement
2. ISRM
3. INCOLD
4. SMART Highways
5. Water & Energy International
6. Geosynthetics
7. Science Report
8. Journal of Rock Mechanics and Tunneling
35
8.0 Budget provision and expenditure for the year 2018 - 2019 (Rs. In lacs.)

Sr. Head of Account FMG Expenditure


No. Plan Non-Plan Plan Non-Plan
1. 2701 Major & Medium Irr. 725.26 - 725.10 -
80 General
004 Research Plan
2. 2701 Major & Medium Irr. - 1482.60 - 1377.94
001 Dir. & Adm.
01 Dir. Non Plan
3. 2701 Major & Medium Irr. - 146.69 - 145.68
001 Dir. & Adm.
02 Adm. Non Plan
(Sedimentation/Dam
safety)
4. 5054 Co. on R & R 150 - 149.09 -
80 General
800 Other Expdr.
Planning & Res. Plan
5. 3054 R & B - 912.58 - 828.66
001 Dir & Adm.
(02) Adm. Non Plan
6. Demand No.84 - 344.68 - 321.08
2059 P,W
053 M & E State Division
W/C Salary (NP)

Total 875.26 2886.55 874.19 2673.36

Total revenue = Rs. 29.60 crore

36
SECTION-E

1.0 Research Personnel.

Following officers were working in GERI during 2018-2019 for the period
shown against them.

Name Designation Qualification Period


Shri K. A. Keshvani Director & C. E. B. E. (Civil) 1.04.18 to 31.03.19
Shri P. B. Chaudhri J.D.(Irrigation) B. E. (Civil) 1.04.18 to 31.03.19
(I/C)
Shri P. K. Nalvaya J. D. (Roads) B. E. (Civil) 1.04.18 to 31.03.19
Shri C. G. Dave Dy. Director (I/C) M.Sc(Geology) 1.04.17 to 31.06.18
Shri Milan Kachhia Dy. Director (I/C) B.E. (Civil) 1.07.18 to 31.03.19
Shri C. R. Thakkar A.R.O. (Civil) B.E. (Civil) 1.04.18 to 31.03.19
Material Testing Division
ShriU.C.Shukla R.O.(I/C) B.E. (Civil) 1.04.18 to30.09.18
Shri R.J.Soni R.O.(I/C) B.E. (Civil) 30.09.18 to 31.03.19
Shri R. M. Jain A.R.O. B.E. (Civil) 1.0418 to 30.09.18
Shri A,N. Luhana A.R.O. M.Sc. 1.04.18 to 31.08.18
Shri K.R.Patel A.R.O. B.E.Civil 1.09.18 to 31.03.19
Shri R.J. Soni A.R.O.(I/C) B.E.Civil 1.09.18 to 31.03.19
Shri C.J.shah A.R.O.(I/C) B.E.Civil 1.1118 to 31.03.19
Geomechanics Division
Shri M.C.Patel R. O. M.Sc. (Chem.) 1.04.18 to 13.05.18

Shri R.M.Vasava R. O. . I/C D.C.E. (Civil) 13-05-18 to 20-05-18


Shri M.C.Patel R. O. M.Sc. (Chem.) 20-05-18 to 31-05-18
Shri H.D.Rathwa R. O. . I/C B.E. (Civil) 31-05-18 to 27-06-18
Shri P.C.Shah R. O. . I/C M.Sc. (Chem.) 27-06-18 to 10-08-18
Shri S.J.Rajan R. O. . I/C B.E. (Civil) 10-08-18 to 04-09-18
Shri H.D.Vakil R. O. . I/C B.E. (Civil) 04-09-18 to 18-09-18
Shri S.J.Rajan R. O. . I/C B.E. (Civil) 18-09-18 to 12-11-18
Shri H.D.Vakil R. O. . I/C B.E. (Civil) 12-11-18 to 26-11-18
Shri S.J.Rajan R. O. . I/C B.E. (Civil) 26-11-18 to 31-03-18
Shri D.B.Galgale A.R.O B E (Civil) 1-04-18 to 30-06-18
Shri S.J.Rajan A.R.O. B E (Civil) 01-07-18 to 31-03-18
Soil Mechanics Division
Shri. H. D. Rathwa R. O. ( I/C ) B. E. (Civil) 01-04-18 to 28-6-18
Shri. R.S.Vasava R. O. ( I/C ) D.C.E 29-4-18 to 31-3-19
Shri. R.S.Vasava A.R.O. - I D.C.E. 1-04-18 to 31-3-19
Shri. R.J.Soni A.R.O. - II B. E. (Civil) 1.04.18 to 31.03.19
Shri. H. D. Rathwa A.R.O. – III B. E. (Civil) 1-04-18 to 28-6-19
Shri. S.J.Rajan A.R.O. – III (I/C) B. E. (Civil) 29-6-18 to 31-7-18
Shri. H.D.Vakil A.R.O. – III B. E. (Civil) 1-8-18 to 31-3-19
Engineering Geology
Shri C.G. Dave Geologist (Sr.) M.Sc. 1.04.18 to 30.06.18
(I/C) (Geology)
37
Name Designation Qualification Period
Shri Sanjay Geologist (Sr.) M.Sc. Tech. 1.07.18 to 31.03.19
Srivastava (I/C) (Geophysics)
Ms.Beenal N. Rathod Geologist (II) I/C M.Sc. 1.08.18 to 30.11.18
(Geology)
Ms.Beenal N. Rathod Geologist (II) M.Sc. 1.12.18 to 31.03.19
(Geology)
Shri Sanjay A.R.O. M.Sc. Tech. 1.04.18 to 31.03.19
Srivastava (Geophysics)
Road Research Division 1
Shri R.T.Rrohit R.O. (I/C) M.Tech. 01.04.18 to 05.07.18
Shri Y. N. Shah R.O. (I/C) D.C.E. 06.07.18 to 01.01.19
Shri M.B.Patel R.O. (I/C) D.C.E. 02.01.19 to 31.03.19
Shri D.R.Khanna A.R.O B.E.(Civil) 8.04.18 To 28.06.18
Miss M.M.Vyas A.R.O. (I/C) B.E. (Civil) 29.06.17To 09.09.19
Shri S.N.Patel A.R.O. D.C.E. 10.09.18 to 28.02.19
Shri D.M.Rohila A.R.O B.E.(Civil) 1.04.18 to 31.03.19
Shri H.D.Charan A.R.O. (I/C) B.E. (Civil) 01.04.18 to 11.09.18
Shri M. B.Patel A.R.O D.C.E. 12.09.18 to 31.03.19
Road Research Division 4
Shri R.T. Rohit R. O. M.Tech. 1.04.18 to 05.07.18
Shri V.R.Parikh R.O.( I/C) B.E.(Civil) 06.07.18 to 11.12.18
Shri.C.K.Soni R.O.(I/C) M.Tech. 12.12.18 to 31.03.19
Shri A.G.Panchal A.R.O. B.E.(Civil) 06.09.18 to 31.10.18
Shri.C.K.Soni A.R.O. M.Tech. 05.12.18 to 31.03.19
Humaben . Siddiqui A.R.O (I/C) B.E. (Civil) 1.04.18 to 06.07.18
Chitraben A.R.O. (I/C) B.E. (Civil) 1.04.18 to 05.09.18
Chudasama
Miss M.M.Vyas A.R.O. B.E. (Civil) 31.08.18 to 31.03.19
Binitaben Deshmukh A.E. B.E. (Civil) 01.04.18 to 12.09.18
Dam Safety Organisation
Shri P.N.Nagpal Ex. Engr.(C)(I/C) B. E. (civil) 1.04.18to 30.06.2018

Shri R. J.Soni Ex. Engr.(C)(I/C) B. E. (civil) 1.07.18to 31.08.2018


Shri.C.R.Thakkar Ex. Engr(C) (I/C) B. E. (civil) 01.09.18 to 31.03.19

Shri.V.R.Parikh D.E.E(C) unit O B E (Civil) 01.04.18 to 31.03.19

Shri P.N.Nagpal D.E.E(C) unit N B. E. (civil) 1.04.18to 30.06.2018


Shri.U.R.patel D.E.E(C) unit N B. E. (civil) 01.07.18 to31.07.18
38
Name Designation Qualification Period
Shri K.R.Patel D.E.E(C) I/CunitN B. E. (civil 01.08.18 to 14.11.18

Shri C.J.Shah D.E.E(C) unit N B. E. (civil 15.11.18 to 31.03.19

Shri S.N.Shah A.A.E. D.C.E. 01.04.18 to 31.03.19


Shri D.B.Galgale Ex. Engr. (M) I/C B. E. (civil 01.04.18 to 30.06.18

Shri P.B.Chaudhary Ex. Engr. (M) I/C B. E. (civil 01.07.18 to 31.03.19


Shri R.M.Verma Ex.Engr(Elect) B. E. (civil 01.04.18 to 16.07.18

Shri R. J. Soni Ex.Engr(Elect) I/C B. E. (civil 17.07.18 to 31.08.18


Shri C.R.Thakkar Ex.Engr(Elect) I/C B. E. (civil 01.09.18 to 31.03.19
Hydraulics Division, Gotri
Shri P.B. Chaudhari R.O B.E. (Civil) 01.04.18 to 31.03.19
Shri M. Khan A.R.O. I M.E. (Civil) 01.04.18 to 06.08.19
Shri A.J.Chauhan A.R.O. I B.E. (Civil) 07.08.18 to 31.03.19
Shri Sanjay Shrivastav A.R.O. II M.Tech 01.04.18 to 12.12.18
(Geophysics)
Shri Y.N.Shah A.R.O. II D.C.E. 12.12.18 to 31.03.19
Shri M.T. Kachhiya A.R.O. III B.E. (Civil) 01.04.18 to 31.03.19
Narmada Hydraulic Division, Gotri
Shri M .T. Kachhia R.O. B.E. (Civil) 1.04.18 to 06.07.18
Shri P B Chaudhari R.O. B.E. (Civil) 7.07.18 to 31.03.19
Shri R.S.Contractor A.R.O. B.E. (Civil) 1.04.18 to 31.03.19
Shri P.C.Shah A.R.O. MSC (stat) 1.04.18 to 10.08.18
Shri Y.N.Shah A.R.O. D.C.E. 11.08.18 to 31.03.19
North Gujarat Research Division, Gandhinagar
Shri D. D. Patel R.O. (I/C) B.E. (Civil) 1.04.18 to 31.03.19
Shri D.T. Patel A.R.O. (I/C) D.C.E. 1.04.18 to 22.11.18
S.S.D.1
Shri K.J.Desai A.R.O. S.S.D.1 B.E. (Civil) 23.11.18 to 31.03.19
Shri M.M. Patel A.R.O. (I/C) B.Sc. (Agri.) 1.04.18 to 30.06.18
S.S.D.2
Shri M.I. Patel A.R.O. (I/C) B.E. (Civil) 1.07.18 to 04.09.18
S.S.D.2
Shre K.B.Vala A.R.O. (I/C) D.C.E. 05.09.18 to 10.10.18
S.S.D.2
Shri M.I. Patel A.R.O. S.S.D.2 B.E. (Civil) 11.10.18 to 11.12.18
Shri K.J.Desai A.R.O ( I/C). B.E. (Civil) 12.12.18 to 23.12.18
S.S.D.2
Shri M.I. Patel A.R.O. S.S.D.2 B.E. (Civil) 24.12.18 to 31.03.19
Shri S. A. Lala A.R.O. (I/C) B.E. (Civil) 01.04.18 to 04.08.18
M.T.Sub Dn.
Shri M.I. Patel A.R.O. (I/C) B.E. (Civil) 05.08.18 to 04.09.18
M.T.Sub Dn.
39
Name Designation Qualification Period
Shri S.J. Bhalani A.R.O. (I/C) B.E. (Civil) 05.09.18 to 26.09.18
M.T.Sub Dn.
Shri S. A. Lala A.R.O. M.T.Sub B.E. (Civil) 26.09.18 to 31.03.19
Dn.
Shri D. D. Patel A.R.O. R R Sub B.E. (Civil) 1.04.18 to 31.03.19
Dn.
Shri N. S. Patel A.R.O.W.Q.T. B.E. (Civil) 1.04.18 to 31.10.18
Sub Dn.
Shri S.J. Bhalani A.R.O B.E. (Civil) 01.11.18 to 31.12.18
(I./C.)W.Q.T.
Sub Dn.
Shri M.I. Patel A.R.O. (I/C) B.E. (Civil) 01.01.19 to 31.03.19
W.Q.T. Sub Dn.
Smt. R. M. Kulkarni A.R.O. Dist. Lab B.E. (Civil) 1.04.18 to 31.03.19
Ahmedabad
Shri R. N. Patel A.R.O. Dist. Lab. B.E. (Civil) 1.04.18 to 29.06.18
Himatnagar
Shri V.M.Soni A.R.O. (I/C)Dist. B.E. (Civil) 30.06.18 to 31.03.19
Lab. Himatnagar
Shri H. B. Shah A.R.O. Dist. Lab. B.E. (Civil) 1.04.18 to 31.08.18
Nadiad
Shri J.S.Christian A.R.O. (I/C) Dist. D.C.E. 1.09.18 to 31.03.19
Lab. Nadiad
Shri R. N. Patel A.R.O (I/C)Dist. B.E. (Civil) 1.04.18 to 29.06.18
Lab. Bhuj
Shri. S. N. Patel A.R.O (I/C) B.E. (Civil) 30.06.18 to 25.11.18
Dist. Lab. Bhuj
Shri S. A. Lala A.R.O (I/C) B.E. (Civil) 26.11.18 to 31.03.19
Dist. Lab. Bhuj
Shri. S. N. Patel A.R.O. Dist. Lab. B.E. (Civil) 1.04.18 to 28.02.19
Mehsana
Shri K.J.Desai A.R.O (I/C) Dist. B.E. (Civil) 01.03.19 to 31.03.19
. Lab. Mehsana
Shri S. S. Shah A.R.O (I/C) Dist. D.C.E. 01.04.18 to 30.11.18
Lab Godhra
Shri H.A. Gadhvi A.R.O. Dist. B.E. (Civil) 01.12.18 to 31.03.19
Lab Godhra
Shri. S. N. Patel A.R.O.(I/C) Dist. B.E. (Civil) 1.04.18 to 26.11.18
Lab. P’npur
Shri S.A.Lala A.R.O.(I/C) Dist. B.E. (Civil) 26.11.18 to 31.03.18
Lab. P’npur
South Gujarat Research Division, Surat
Shri V. B. Kedaria R.O. (I/C) B.E. (Civil) 01.04.18 to 11.05.18
Shri G. A. Chaudhari R.O. (I/C) B.E. (Civil) 12.05.18 to 20.05.18
Shri V. B. Kedaria R.O. (I/C) B.E. (Civil) 21.05.18 to 03.12.18
Shri M.R.Vala R.O. (I/C) B.E. (Civil) 01.12.18 to 16.12.18
Shri V. B. Kedaria R.O. (I/C) B.E. (Civil) 17.12.18 to 06.02.19

40
Name Designation Qualification Period
Shri M.R.Vala R.O. (I/C) B.E. (Civil) 07.02.19 to 17.02.19
Shri V. B. Kedaria R.O. (I/C) B.E. (Civil) 18.02.19 to 31.03.19
Shri G. A. Chaudhari A.R.O. M.T. B.E. (Civil) 01.04.18 to 30.10.18
Shri V. B. Kedaria A.R.O. ( I/C) B.E. (Civil) 31.10.18 to 11.11.18
M.T.
Shri G. A. Chaudhari A.R.O. M.T. B.E. (Civil) 12.11.18 to 11.01.19
Shri V. B. Kedaria A.R.O. ( I/C) B.E. (Civil) 12.01.19 to 16.01.19
M.T.
Shri V. B. Kedaria A.R.O. M.T. B.E. (Civil) 17.01.19 to 06.02.19
Shri M.R.Vala A.R.O. ( I/C) B.E. (Civil) 07.02.19 to 17.02.19
M.T.
Shri V. B. Kedaria A.R.O. M.T. B.E. (Civil) 18.02.19 to 31.03.19
Shri D.G.Sangdod A.R.O. (I/C) D.C.E. 01.04.18 to 31.08.18
RRD
Shri M.R.Vala A.R.O. R.R.D. B.E. (Civil) 1.09.18 to 11.11.18
Shri D.G.Sangdod A.R.O. (I/C) D.C.E. 12.11.18 to 18.11.18
RRD
Shri M.R.Vala A.R.O. R.R.D. B.E. (Civil) 19.11.18 to 31.03.19
Shri V. B. Kedaria A.R.O. S.M. B.E. (Civil) 01.04.18 to 11.05.18
Shri G. A. Chaudhari A.R.O. (I/C.) B.E. (Civil) 12.05.18 to 20.05.18
S.M.
Shri V. B. Kedaria A.R.O. S.M. B.E. (Civil) 21.05.18 to 03.12.18
Shri G. A. Chaudhari A.R.O. (I/C.) B.E. (Civil) 04.12.18 to 16.12.18
S.M.
Shri V. B. Kedaria A.R.O. S.M. B.E. (Civil) 17.12.18 to 06.02.19
Shri M.R.Vala A.R.O. (I/C)S.M. B.E. (Civil) 07.02.19 to 17.02.19
Shri V. B. Kedaria A.R.O. S.M. B.E. (Civil) 18.02.19 to 31.03.19
Shri G. A. Chaudhari A.R.O. (I/C.) B.E. (Civil) 01.04.18 to 31.10.18
Soil ( R & B )
Shri V. B. Kedaria A.R.O. Soil ( R B.E. (Civil) 01.11.18 to 11.11.18
&B)
Shri G. A. Chaudhari A.R.O. (I/C.) B.E. (Civil) 12.11.18 to 11.01.19
Soil ( R & B )
Shri M.R.Vala A.R.O. (I/C.) B.E. (Civil) 21.01.19 to 31.01.19
Soil ( R & B )
Shri G. A. Chaudhari A.R.OSoil ( R & B.E. (Civil) 01.02.19 to 31.03.19
B)
Shri B. C. Patel A.R.O. (I/C) D.C.E. 01.04.18 to 06.08.18
Lab, Bharuch
Shri I.N.Pathan A.R.O. Lab, B.E. (Civil) 07.08.18 to 31.10.18
Bharuch
Smt. B.K.Mehwala A.R.O. Lab, B.E. (Civil) 03.10.18 to 31.03.19
Bharuch

41
Name Designation Qualification Period
Shri V. B. Kedaria A.R.O. (I/C) B.E. (Civil) 01.04.18 to 11.05.18
Lab,Valsad
Shri G. A. Chaudhari A.R.O. (I/C) B.E. (Civil) 12.05.18 to 20.05.18
Lab,Valsad
Shri V. B. Kedaria A.R.O. (I/C) B.E. (Civil) 21.05.18 to 18.07.18
Lab,Valsad
Shri G. A. Chaudhari A.R.O. B.E. (Civil) 19.07.18 to 31.03.19
Lab,Valsad
Suarastra Research Division, Rajkot
Shri R.R.Lathigara R.O. (I/C) B.E Civil 01.04.18 to 01.8.18
11.10.18 to 18.10.18
12.02.19 to 24.02.19
Shri N.N.Surani R.O. (I/C) B.E.Civil 02.08.18 to 10.10.18
19.10.18 to 11.02.19
25.02.19 to 31.03.19
Shri R.R.Lathigara A.R.O. B.E.Civil 01.04.18 to 31.03.19
N.N.Surani A.R.O. B.E.Civil 01.04.18 to 31.03.19
S.M.Makadiya A.R.O. B.E.Civil 01.04.18 to 31.03.19
P. B Patel A.R.O B.E Civil 01.04.18 to 31.03.19
S.D. & R. Circle, Vadodara
Shri M. C. Patel S.E. Add. M.Sc. 01.04.18 to 31.05.18
Charge
Shri P.B. Chaudhary S.E. Add. B.E. (Civil) 01.06.18 to 31.03.19
Charge
Shri S. N. Panchal P.S. to SE.SDR D.C.E. 01.04.18 to 31.03.19
SOIL SURVEY DIVISION SURAT
Shri I.H.Khokhar S. S.O. M.Sc.(Org.Che 01.04.18 to 31.03.19
m)
SOIL SURVEY SUB DIVISION SURAT
Shri Abdul Hamid Dy. S.S.O. M.Sc.(Tech.) 01.04.18 to 30.11.18
Geography
Shri P.D.Patel Dy.S.S.O. D.C.E. 01.12.18 to 31.03.18
(Look after)
SOIL SURVEY SUB DIVISION VALSAD
Shri P.D.Patel Dy.S.S.O. D.C.E. 01.04.17 to 31.03.18
(Look after)
SOIL SURVEY SUB DIVISION BHARUCH
Shri R.G.Shah Dy.S.S.O.( I/C) D.C.E. 01.04.18 to 28.02.19
Shri S.M.Vasava Dy.S.S.O.( I/C) D.C.E. 01.03.19 to 31.03.19
SOIL SURVEY SUB DIVISION VADODARA
Shri R.G.Shah Dy.S.S.O. D.C.E. 01.04.18 to 28.02.19
Shri S.M.Vasava Dy.S.S.O.( I/C) D.C.E. 01.03.19 to 31.03.19
SOIL SURVEY DIVISION RAJKOT
Shri I.H.Khokhar D. S.O. M.Sc.(Org.Che 01.04.18 to 10.04.18
m)
Shri Abdul Hamid Dy. S.S.O. Add. M.Sc.(Tech.) 11.04.18 to 30.11.18
Charge Geography
Shri I.H.Khokhar D. S.O. M.Sc.(Org.Che 01.12.18 to 31.03.19
m)
SOIL SURVEY SUB DIVISION RAJKOT
42
Name Designation Qualification Period
Shri R.R.Patel Dy.S.S.O. ( I/C) D.C.E. 01.04.18 to 15.10.18
Shri R.B.Sagathiya Dy.S.S.O. ( I/C) B.E. (Civil) 16.10.18 to 31.03.19
SOIL SURVEY SUB DIVISION JAMNAGAR
Shri P.J.Zala Dy.S.S.O. D.C.E. 01.04.18 to 31.03.19
SOIL SURVEY SUB DIVISION BHAVNAGAR
Shri P.J.Zala Dy.S.S.O. D.C.E. 01.04.18 to 31.03.19
SOIL SURVEY SUB DIVISION JUNAGDH
Shri R.R.Patel Dy.S.S.O. ( I/C) D.C.E. 01.04.18 to 15.10.18
Shri R.B.Sagathiya Dy.S.S.O. ( I/C) B.E. (Civil) 16.10.18 to 31.03.19
SOIL SURVEY DIVISION GHANDHINAGAR
Shri I.H.Khokhar S. S. O. M.Sc. 01.04.87 to 31.03.19
(Org.Chem)
SOIL SURVEY SUB DIVISION GHANDHINAGAR
Shri M.R.Patel Dy.S.S.O. D.E (Civil). 01.04.18 to 07.03.19
Shri M.A.Gheree Dy.S.S.O. D.E (Civil). 08.03.19 to 31.03.19
SOIL SURVEY SUB DIVISION MAHESANA
Shri M.P.Patel Dy.S.S.O. ( I/C) D.C.E. 01.04.18 to 31.07.18
Shri S.R.Parmar Dy.S.S.O. ( I/C) D.C.E. 01.08.18 to 11.11.18
Shri B.V.Shah Dy.S.S.O. ( I/C) D.C.E. 11.11.18 to 31.03.19
SOIL SURVEY DIVISION PALANPUR
Shri M.M.Trivedi Dy.S.S.O. (I/C) D.E (Civil). 01.04.18 to 31.03.19
SOIL SURVEY DIVISION GODHARA
Shri K.B.Damor Dy.S.S.O. (I/C) 01.04.18 to 31.03.19

43

You might also like