S. No. Item Description Start Date End Date Payment Required (PKR) Payment Purpose Payment Date No. of Days Required

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 3

Payment Payment Payment No.

of Days
S. No. Item Description Required (PKR) purpose Date Required Start Date End Date

Block Making (7500 blocks) 208,285 CEB blocks 25/3/2020 20 25/3/2020 13/4/2020
Total 20

A- Boundry wall 29/4/2020 3/5/2020


Foundation
Excavation 232,975 1/4/2020 5 1/4/2020 8/4/2020
stone
Stone blast 4 8/4/2020 11/4/2020
Concrete
Block masonry (Foundation) 128,850 block and 10/4/2020 4 11/4/2020 14/4/2020
labor
DPC 2 14/4/2020 15/4/2020
Plaster (SRC foundation) 2 15/4/2020 16/4/2020

Plaster and
Block Masonry (Wall) 61,750 labor 19/4/2020 6 16/4/2020 21/4/2020

Bamboo Fence 4 21/4/2020 24/4/2020


Plaster (wall) 5 24/4/2020 28/4/2020
Backfill 2 28/4/2020 29/4/2020
Boundry wall fence 5 29/4/2020 3/5/2020
Total 39

A- Goat/Chicken Farm
Excavation 294250 foundation 4 21/4/2020 24/4/2020
Stone blast 2 24/4/2020 25/4/2020
Block masonry (Foundation) 135600 masonry 4 25/4/2020 29/4/2020
DPC 1 29/4/2020 30/4/2020
Plaster (SRC foundation) 3 30/4/2020 2/5/2020
Block Masonry (Wall) 8 2/5/2020 9/5/2020
Backfill ring beam 5 9/5/2020 13/5/2020
Stone soling for floor 3 13/5/2020 15/5/2020
Screed 3 15/5/2020 17/5/2020
Lintel 1 17/5/2020 17/5/2020
Concrete ring beam 32800 ring beam 5 17/5/2020 21/5/2020
Block Masonry (pitch wall) 3 21/5/2020 23/5/2020
Bamboo vertical post 2 23/5/2020 24/5/2020
Bamboo rafters 3 24/5/2020 26/5/2020
Doors installation 2 26/5/2020 27/5/2020
Windows installation 2 27/5/2020 28/5/2020
Corrugated sheets installation 6 28/5/2020 3/6/2020
CC floor 2 3/6/2020 4/6/2020
Paint 10 4/6/2020 13/6/2020
Electrical works 7 13/6/2020 19/6/2020

Total 1,094,510 76