Course Description

The course on Power Plant Design covers the theoretical study of the engineering aspects in the design and installation of power plants that are generally employed
for power generation in the Philippines, starting from load analysis, economics, determination of capacity, electric energy rates, the various types of power plants
utilizing the energy sources and their components/auxiliaries.

This course is to be taken by upper class mechanical engineering students after the course on Internal Combustion Engines and Steam Power Engineering.
PRE-REQUISITE:

ME 416 Internal Combustion Engines


ME 421 Machine Design 2

GENERAL OBJECTIVE:
The course on Power Plant Design is one of the major areas in the practice of mechanical engineering. In view of this, the goal of teaching is for upper class
students to acquire the working knowledge of the engineering aspects of power plant operation and design.

REQUIREMENTS:

Written examinations
Assignments

REFERENCES

Morse, Frederick T. Power Plant Engineering. MKS units.

Faires, Virgil Moring and Clifford Max Simmong. Thermodynamics. 6th ed.
El-Wakil, M. M. Power Plant Technology. 1984

Potter, Philip J. Power Plant Theory and Design. 2nd ed. 1959

Obert. Internal Combustions Engines.

INSTRUCTIONAL OBJECTIVES CONCEPTS/TOPICS LEARNING EVALUATION


STRATEGIES/ACTIVITIES
1.1 Distinguish between the power Energy and the power plant Classroom work will be devoted to A train weighing 4150 MT is pulled up
plant for electric generation and lectures and board work presentations. a 2% grade. The coefficient of kinetic
that for the industrial plant. friction is 0.012. Determine the power
1.2 Identify and recognize the various Energy sources for power generation in KW when the train is moving up at
energy sources for power 1. Fuels 40km/hr.?
generation. 2. Flowing streams of water
3. Ocean tides and waves
4. Winds
5. Solar rays
6. Geothermal heat
7. Atomic nuclei
2.1 Understand the function of the The variable load problem Lecture and discussion and board work A 50 MW power plant has an average
components of an electric power presentation load of 3,550 kw and a load factor of
system. Terms and factors 42%. Define load factor and determine
2.2 Understand the implications of - Demand factor the reserve over peak load.
load curves and load duration curves. - Diversity factor
2.3 Comprehend the various terms and - Load factor
factors in connection with power plant - Capacity factor
problems. - Use factor
- Utilization factor
- Hot reserve
- Spinning reserve
- Run of rivers
- Reserve equipment
3.1 Understand the implications of the Power plant economics Classroom lectures and discussions, A distribution transform supplies a
terms: Franchise, forced outages and boar work presentations. group of general power customers
readiness to serve. having a connected load of 186 kw.
3.2 Identify the conditions to be The public utility power plant elements Demand factor = 0.75 If the load
satisfied in making rates. of electric energy cost factor for the group will average 45%
3.3 Figure out the elements of electric - fixed elements and energy sells P6.012 per kw hr.
energy rates. - energy elements What will be the monthly (30 day)
- customer elements income from energy delivered through
- investor profits this transformer? Assume average
Rate forms motor efficiency 75%.
4.1 Examine the power plant The power plant building general Class lectures and board work A coal fired steam boiler uses 3000
equipment layout considering relevant design presentations. kg/hr of coal. Air required for
factors. combustion is 15.5 kg/kg of coal at Pb
4.2 Identify the factors considered in Chimney design = 98.2 kPa. The flow gas temperature
chimney design. - draft of 285 C with an average MW =30.
4.3 Identify the factors considered in - mechanical draft Assume an ash loss of 11 % and an
the design of machinery foundation. - stability allowable gas velocity of 7.5 m/s, find
4.4 Identify the factors considered in the diameter of the chimney.
the design of cooling towers. Machine foundation
- machine weight
- foundation weight
- soil bearing capacity
- machine vibration
- setting

Cooling tower
- atmospheric cooling tower
- mechanical draft cooling tower
- evaporative coolers
5.1 Make a schematic diagram of a Diesel power plant Class lecture and discussion Determine the brake power of the
diesel power plant showing all the engine having eb=35% and uses
major components. 25APl fuel with a fuel consumption of
5.2 Solve engine performance Engine performance equations: Board work presentation 40 kg/hr.
parameters including volumetric  Volumetric efficiency
efficiency, piston speed, indicated  Piston speed Determine the S.G. of fuel oil having a
power, brake power and thermal  Indicated power heating value of 44989.2kd/kg.
efficiency.  Brake power
5.3 Relate the terms:  Thermal efficiency
Supercharging, dual fuel diesel
engines, opposed piston engine. Supercharging dual-fuel diesel
opposed pistons scavenging
6.1 Relate the water power systems Hydro power plant Class lecture and discussion In a hydro power plant the tail water is
and structures. at 480 m elevation. The net head is 27
6.2 Identify the kinds of hydraulic Turbine types: m. and head loss is 4% of the gross
turbines and their applications. . Impulsive turbine head. What is the headwater
. Reaction turbine elevation?
. Axia flow turbine
7.1 Distinguish the open cycle gas Gas turbines Class lecture and discussion An air standard Bray ton cycle has air
turbine from the closed cycle. Open cycle gas turbines leaving the high temperature heat
7.2 Determine the efficiency of the gas Closed cycle gas turbines exchanger at 850 C and leaving the
turbine. Efficiencies turbine at 310 c. What is the thermal
Regeneration efficiency?
Reheating, Later cooling