Professional Documents
Culture Documents
Second Division: Tciahc
Second Division: Tciahc
On May 19, 1997, MCWD entered into a Water Supply WHEREFORE[,] premises considered, judgment is
Contract 7 (the Contract) with MRII wherein it was agreed that the latter hereby rendered as follows:
would supply MCWD with potable water, in accordance with the World Health
1. Ordering the reformation of Clause 17 of the
Organization (WHO) standard or the Philippine national standard, with a
Water Supply Contract to read:
minimum guaranteed annual volume. 8 DcAaSI
17[.] Price Escalation and/or De-
On March 15, 2004, MRII filed a Complaint 9 against MCWD with the
Escalation shall be based on the parametric
Construction Industry Arbitration Commission (CIAC), citing the arbitration
formula:
clause (Clause 18) 10 of the Contract. The case was docketed as CIAC Case
No. 12-2004. In the said complaint, MRII sought the reformation of Clause 17 17.1 Power Rate Price
of the Contract, or the Price Escalation/De-Escalation Clause, in order to Adjustment/Power Cost
include Capital Cost Recovery in the price escalation formula, and to have Adjustment
Current Power Rate - Base Power Ratex30% of base final and executory until the foregoing
selling price of water amounts shall have been fully paid[.]
—————————————————————————
———————— 3. Claimant Mactan Rock Industries, Inc. and
Base Power Rate Metropolitan Cebu Water District shall
share equally the cost of arbitration.
17.2 Consumer Price Index (CPI)
Adjustment/Operating Cost SO ORDERED. 19
Adjustment:
Decision of the CA in CA-G.R. SP
Current CPI - Base CPIx40% of base selling price of No. 85579— Petition for certiorari
water under Rule 65 with the Court of
————————————————————————— Appeals questioning the jurisdiction
— of the CIAC
Base CPI Meanwhile, on October 28, 2005, the CA in its decision 20 in the
17.3 Capital Cost Recovery Adjustment: First Petition upheld the jurisdiction of the CIAC over the case. The CA held
that when parties agree to settle their disputes arising from or connected with
Current Peso toBase Peso to US$ construction contracts, the CIAC acquires primary
US$ Exchange Rate - Exchange Ratex30% of base jurisdiction. 21 Citing Philrock, Inc. v. Construction Industry Arbitration
selling price of water Commission, 22 the CA stated that the CIAC may resolve not only the merits
————————————————————————— of such controversies, but may also award damages, interest, attorney's fees,
——————— and expenses of litigation, when appropriate. 23
Base Peso to US$ Exchange Rate
Second, the CA held that the claims in question fall under the
Price escalation shall be reckoned from jurisdiction of the CIAC. Thus:
January 1999 when the water was first
delivered by Mactan Rock Industries, Inc. . . . Section 4 of Executive Order No. 1008,
to the MCWD facilities in Mactan. The otherwise known as the Construction Industry Arbitration
base CPI, base US$ Exchange Rate and Law delineates CIAC's jurisdiction as "original and
the Base Power Rate shall be the exclusive jurisdiction over disputes arising from, or
prevailing rate in January 1999, while the connected with, contracts entered into by parties involved
Base Selling Price of water shall mean the in construction in the Philippines, whether the disputes
1996 rate per cubic meter of water as arise before or after the completion of the contract, or after
provided for in the Water Supply abandonment thereof." Moreover, Section 5 (k) of Republic
Contract. aITDAE Act No. 9184 otherwise known as [the] Government
Procurement Reform Act expressly defines "infrastructure
2. Ordering Respondent Metropolitan Cebu project" as including "water supply[,]" construction,
Water District to pay Claimant, Mactan rehabilitation[,] demolition, repair, restoration and
Rock Industries, Inc[.] under the reformed maintenance. CDAHaE
Clause 17 of the Water Supply Contract,
the net amount of Php12,126,296.70 plus Consistent with the above-mentioned policy of
legal interest of six percent (6%) per encouraging alternative dispute resolution methods, courts
annum from the (sic) March 15, 2004, the should liberally construe arbitration clauses. Provided such
date of filling (sic) of the case with the clause is susceptible of an interpretation that covers the
Construction Industry Arbitration asserted dispute, an order to arbitrate should be granted.
Commission, the rate increased to twelve Any doubt should be resolved in favor of arbitration. It is to
percent (12%) per annum from the date be highlighted that the dispute in the case at bar arose
the herein Decision have (sic) become from the parties' incongruent positions with regard to
clause 17 of the Water Supply Contract[,] specifically the Finally, the CA stressed that "factual findings of administrative
price escalation/adjustment. The instant case involves agencies which are deemed to have acquired expertise in matters within their
technical discrepancies that are better left to an arbitral respective jurisdictions are generally accorded not only respect but even
body that has expertise in those areas. Nevertheless, in finality when supported by substantial evidence." 29
any event, the inclusion of an arbitration clause in a
contract does not ipso facto divest the courts of jurisdiction MCWD filed a motion for reconsideration but it was denied in the CA
to pass upon the findings of arbitral bodies, because the Resolution dated March 30, 2006.
awards are still judicially reviewable under certain Thus, this petition.
conditions. 24 (Citations omitted.)
ISSUES
MCWD's motion for reconsideration of the decision in the First
Petition was still pending when it filed the petition for review 25 under Rule MCWD raises the following issues in its petition for review:
43 (Second Petition) appealing the decision of the CIAC. The motion for MAY THE CONSTRUCTION INDUSTRY [ARBITRATION]
reconsideration was eventually denied in a Resolution 26 dated May 3, 2006. COMMISSION EXERCISE JURISDICTION OVER
MCWD did not appeal from the denial of the motion. It, thus, became final DISPUTES ARISING FROM A WATER SUPPLY
and executory. 27 CONTRACT?
Decision of the CA in CA-G.R. CEB MAY A PARTY, WHO IS A SIGNATORY TO THE
SP. No. 00623 — Petition for review WATER SUPPLY CONTRACT[,] IN EFFECT
under Rule 43 appealing the decision SUBMITTING ITSELF TO THE JURISDICTION OF THE
of the CIAC CONSTRUCTION INDUSTRY ARBITRATION
Aggrieved by the CIAC Decision, MCWD filed a petition for review COMMISSION, QUESTION THE JURISDICTION OF
under Rule 43 with the CA which was docketed as CA-G.R. CEB SP. No. [THE] CIAC?
00623.
DOES THE CONSTRUCTION INDUSTRY ARBITRATION
The CA, however, dismissed the petition in its Decision dated COMMISSION HAVE THE (SIC) JURISDICTION OVER A
February 20, 2006. The Court therein stated that the issue of jurisdiction had COMPLAINT PRAYING FOR A REFORMATION OF A
already been resolved by the 18th Division in the First Petition, where the CA WATER SUPPLY CONTRACT?
upheld the jurisdiction of the CIAC over Arbitration Case No. 12-2004.
MAY THE COURT OF APPEALS REFUSE TO RENDER
Citing jurisprudence, the CA also ruled that there being an arbitration A [SIC] JUDGMENT ON AN ISSUE BECAUSE THIS
clause in the Contract, the action for reformation of contract instituted by HAS BEEN ALREADY SETTLED IN A DECISION
MRII in this case fell squarely within the jurisdiction of the CIAC, not the RENDERED BY ANOTHER DIVISION OF THE COURT
courts. In relation to this, the CA noted that the present rule is that courts will OF APPEALS IN A PETITION FOR CERTIORARI, EVEN
look with favor upon amicable agreements to settle disputes through IF THE SAID DECISION HAS NOT YET
arbitration, and will only interfere with great reluctance to anticipate or nullify BEEN (SIC) FINAL DUE TO A TIMELY FILING OF A
the action of the arbitrator. MCWD being a signatory and a party to the Water MOTION FOR RECONSIDERATION? 30 HAaScT
Supply Contract, it cannot escape its obligation under the arbitration
clause. 28 AHSEaD RULING OF THE COURT
Creation of the CIAC
The CA also held that the CIAC did not err in finding that the Water
Supply Contract is clear on the matter of the reckoning period for the The Construction Industry Arbitration Commission (CIAC) was
computation of the escalation cost from January 9, 1999, or the first day of created in 1985 under Executive Order (E.O.) No. 1008 (Creating an
delivery of water. Moreover, the CA found that the CIAC did not err in ruling Arbitration Machinery for the Philippine Construction Industry), in recognition
that the contract be reformed to include Capital Cost Recovery in the of the need to establish an arbitral machinery that would expeditiously settle
parametric formula for price escalation. Neither did it err in holding that the construction industry disputes. The prompt resolution of problems arising
Capital Cost Recovery shall be 30% of the Base Selling Price of water as a from, or connected to, the construction industry was considered necessary
consequence of the reformation of Clause 17. and vital for the fulfillment of national development goals, as the construction
industry provided employment to a large segment of the national labor force, MCWD never appealed the case. Thus, the decision of the CA in the First
and was a leading contributor to the gross national product. 31 Petition became final and executory. AETcSa
Under Section 4 of E.O. No. 1008, the CIAC's jurisdiction was The question now is whether such final and executory decision is
specifically delineated as follows: binding such that courts are generally precluded from passing judgment on
the issue of jurisdiction in the present petition.
SECTION 4. Jurisdiction. — The CIAC shall
have original and exclusive jurisdiction over disputes The Court finds in the affirmative.
arising from, or connected with, contracts entered into by
parties involved in construction in the Philippines, whether This Court has held time and again that a final and executory
the disputes arise before or after the completion of the judgment, no matter how erroneous, cannot be changed, even by this Court.
contract, or after the abandonment or breach thereof. Nothing is more settled in law than that once a judgment attains finality, it
These disputes may involve government or private thereby becomes immutable and unalterable. It may no longer be modified in
contracts. For the Board to acquire jurisdiction, the parties any respect, even if such modification is meant to correct what is perceived
to a dispute must agree to submit the same to voluntary to be an erroneous conclusion of fact or law, and regardless of whether the
arbitration. modification is attempted to be made by the court rendering it or by the
highest court of the land. 35
The jurisdiction of the CIAC may include but is not
limited to violation of specifications for materials and In its Decision in the First Petition, the CA affirmed the arbitral body's
workmanship; violation of the terms of agreement; finding in CIAC Case No. 12-2004 that the case was within its jurisdiction.
interpretation and/or application of contractual provisions; Such decision having become final, it is beyond the jurisdiction of this Court,
amount of damages and penalties; commencement time or any court or body, for that matter, to review or modify, even supposing for
and delays; maintenance and defects; payment default of the sake of argument, that it is indeed erroneous.
employer or contractor and changes in contract cost. Also, the parties apparently characterized the Contract as one
Excluded from the coverage of this law are involving construction, as its arbitration clause specifically refers disputes,
disputes arising from employer-employee relationships controversies or claims arising out of or relating to the Contract or the breach,
which shall continue to be covered by the Labor Code of termination or validity thereof, if the same cannot be settled amicably, to an
the Philippines. (Underscoring supplied) arbitration tribunal, in accordance with E.O. No. 1008, or the Construction
Industry Arbitration Law:
The jurisdiction of the CIAC as a quasi-judicial body is confined to
construction disputes, 32 that is, those arising from, or connected to, V.DISPUTES AND JURISDICTION:
contracts involving "all on-site works on buildings or altering structures from 18. Any dispute, controversy or claim arising out
land clearance through completion including excavation, erection and of or relating to this contract or the breach, termination or
assembly and installation of components and equipment." 33 The CIAC has invalidity thereof, if the same cannot be settled amicably,
jurisdiction over all such disputes whether the dispute arises before or after may be submitted for arbitration to an Arbitration Tribunal
the completion of the contract. 34 in accordance with Executive Order No. 1008 dated 4
Whether the CIAC has jurisdiction February 1985, otherwise known as the Construction
over the dispute Industry Arbitration Law and the place of arbitration shall
be the City of Cebu, Philippines, otherwise said dispute or
As earlier stated, following the denial of its motion to dismiss by controversy arising out of the contract or breach thereof
CIAC, MCWD filed the First Petition with the CA, which decided in favor of shall be submitted to the court of law having jurisdiction
MRII and upheld the jurisdiction of the CIAC. thereof in the city where MCWD is located. 36
Not being in conformity, MCWD filed a motion for reconsideration. Had the parties been of the mutual understanding that the Contract
was not of construction, they could have instead referred the matter to
While the said motion was pending with the CA, MCWD filed the
arbitration citing Republic Act (R.A.) No. 876, or The Arbitration Law. Having
Second Petition with the same court. Eventually, the motion was denied, and
been passed into law in 1953, the said statute was already in existence at the
time the contract was entered into, and could have been applied to arbitration determining whether the cause of action in the second case existed at the
proceedings other than those specifically within the arbitral jurisdiction of the time of the filing of the first case. 40
CIAC.
In the First Petition, MCWD argued that the CIAC's issuance of its
Whether the CA erred in refusing to Order 41 dated May 28, 2004 was tainted with grave abuse of discretion
render judgment on the issue of amounting to excess or lack of jurisdiction. Thus, MCWD stated in its
jurisdiction prayer: IDTSaC
On a related matter, MCWD also raises the issue of whether the 19th WHEREFORE, in light of the premises laid down,
Division of the CA, Cebu City, erred in refusing to render judgment on the petitioner most respectfully prays:
issue of jurisdiction raised in the Second Petition on the ground that it had
already been settled by the 18th Division in its decision in the First Petition, 1. Upon the filing of this Petition, a Writ
even if the 18th Division decision had not yet become final due to a timely of Preliminary Injunction or restraining order be
filing of a motion for reconsideration. issued forthwith, enjoining the respondent from
proceeding with the hearing of the case until
The Court rules in the negative. cSITDa further orders from the Honorable Court of
Appeals;
The 19th Division was correct in refusing to render judgment on the
issue of jurisdiction as, at that time, the issue was still pending before another 2. After consideration, petitioner also
division of the CA. prays that the Order dated May 28, 2004, denying
petitioner's motion to dismiss be declared without
Litis pendentia is predicated on the principle that a party should not
force and effect;
be allowed to vex another more than once regarding the same subject matter
and for the same cause of action. It is founded on the public policy that the 3. Petitioner also prays that the
same subject matter should not be the subject of controversy in courts more Construction Industry Arbitration Commission be
than once, in order that possible conflicting judgments may be avoided for barred from hearing the case filed by Mactan Rock
the sake of the stability of the rights and status of persons, and also to avoid Industries, Inc., private respondent herein.
the costs and expenses incident to numerous suits. 37
Other measures of relief, which are just and
With the two petitions then pending before the CA, all the elements equitable under the foregoing premise are also prayed
of litis pendentia were present, that is, identity of the parties in the two for. 42
actions, substantial identity in the causes of action and in the reliefs sought
by the parties, and identity between the two actions such that any judgment The Second Petition, on the other hand, raised the following issues:
that may be rendered in one case, regardless of which party is successful,
a. Whether or not the Arbitral Tribunal of CIAC
would amount to res judicata in the other. 38
gravely erred in taking and exercising jurisdiction over the
In both cases, MCWD was the petitioner and MRII, the respondent. complaint filed by the respondent;
Although they differ in form, in essence, the two cases involved a common
b. Whether or not the Arbitral Tribunal of CIAC
issue, that is, MCWD's challenge to the jurisdiction of the CIAC over the
gravely erred in reforming Clause 17 of the Contract;
arbitration proceedings arising from the Water Supply Contract between the
petitioner and respondent. c. Whether or not the same tribunal gravely
committed an error in considering Capital Cost Recovery
To determine whether there is identity of the rights asserted and
Adjustment in awarding in favor of the complainant, when
reliefs prayed for, grounded on the same facts and bases, the following tests
the same is extraneous to the provisions of the
may be utilized: (1) whether the same evidence would support and sustain
contract; 43
both the first and the second causes of action, also known as the "same
evidence" test; or (2) whether the defenses in one case may be used to Thus, it prayed:
substantiate the complaint in the other. 39 Also fundamental is the test of
WHEREFORE, PREMISES CONSIDERED, it is
most respectfully prayed of the Honorable Court that a
Judgment be issued reversing the findings of the Arbitral In the Second Petition, in support of the issue of jurisdiction, MCWD
Tribunal of the Construction Industry Arbitration again relied on Section 4 of E.O. No. 1008 and Section 1, Article III of the
Commission in its Decision dated April 14, 2005, as far as Rules of Procedure Governing Construction Arbitration. It also brought to fore
the order of reformation of the water supply contract and in the alleged faulty conclusion of MRII that a water supply contract is
granting the monetary award. ICTacD subsumed under the definition of an infrastructure project under LOI 1186. 47
It is further prayed that the decision rendered by In its Comment, MRII reiterated and adopted its arguments before
the Arbitral Tribunal be declared invalid for want of the CIAC, and insisted that the undertaking contemplated by the parties was
jurisdiction to arbitrate and to order the reformation of the one of infrastructure and of works, as distinguished from "mere supply from
water supply contract; off-the-shelf or from mere services." 48 Section 1 of LOI No. 1186, to define
"infrastructure" and Section 5 (k) of R.A. No. 9184 to include "water supply,"
It is also prayed that the decision awarding money were again cited. In support of its arguments, MRII cited anew MCWD's pro-
to the respondent be strike (sic) down as erroneous and forma Water Supply Contract, Specifications (in its Invitation to Submit
without legal basis for lack of jurisdiction by the Arbitral Proposal), pronouncements at the Pre-Bid Conference, Addendum No. 1,
Tribunal, which rendered the Decision. and MRII's Technical and Financial Proposals. MRII further extensively
It is also prayed that a Temporary Restraining reproduced the content of the joint affidavit of Messrs. Antonio P. Tompar
Order and a Writ of Preliminary Injunction be issued at the and Lito R. Maderazo, MRII's President/CEO and Financial Manager,
outset, ordering the stay of execution pending the respectively. 49
resolution of the issues raised in the Petition. Given that the same arguments were raised on the matter of CIAC
Other measures of relief, which are just and jurisdiction, the parties thus relied on substantially the same evidence in both
equitable, are also prayed for. 44 petitions. MCWD annexed to both petitions copies of the Water Supply
Contract, the complaint filed by MRII with the CIAC, and its Answer to the
In both cases, the parties also necessarily relied on the same laws said complaint. On the other hand, MRII presented Addendum No. 1 to the
and arguments in support of their respective positions on the matter of Water Supply Contract and its Technical and Financial Proposals.
jurisdiction.
Moreover, the first cause of action in the Second Petition, that is, the
In the First Petition, in support of its argument, that the CIAC had no CIAC's having assumed jurisdiction, allegedly unlawfully, over the dispute
jurisdiction to arbitrate the causes of action raised by MRII, MCWD cited the arising from the Water Supply Contract, obviously existed at the time the First
portions of the Contract on the obligations of the water supplier, E.O. No. Petition was filed, as the latter case dealt with the jurisdiction of the CIAC
1008 (specifically Section 4 on jurisdiction), the Rules of Procedure over the complaint filed.
Governing Construction Arbitration (Section 1, Article III). It also alleged that
in issuing the order denying its motion to dismiss, the CIAC misread the Finally, any judgment that may be rendered in the First Petition on
provisions of LOI No. 1186 and R.A. No. 9184 on the definition of an the matter of whether the CIAC has jurisdiction over the arbitration
infrastructure project. 45 proceedings, regardless of which party was successful, would amount to res
judicata in the Second Petition, insofar as the issue of jurisdiction is
MRII, however, opined that the CIAC had jurisdiction over the concerned. In fact, what MCWD should have done was to appeal to the Court
complaint and, therefore, correctly denied petitioner's motion to dismiss. MRII after the denial of its motion for reconsideration in the First Petition. For not
argued that certiorari was not a proper remedy in case of denial of a motion having done so, the decision therein became final and, therefore,
to dismiss and that the claims fell squarely under CIAC's original and immutable. ETHaDC
exclusive jurisdiction. MRII, in support of its position, cited Section 1 of LOI
No. 1186 and Section 5 (k) of R.A. No. 9184. MRII further proposed that, as Thus, following the above discussion, the 19th Division was correct
shown by MCWD's pro-forma Water Supply Contract, Specifications, in refusing to render judgment on the issue of jurisdiction in the Second
Invitation to Submit Proposal, Pre-Bid Conference minutes, Addendum No. 1, Petition.
and MRII's Technical and Financial Proposals, the undertaking contemplated Whether the CIAC had jurisdiction
by the parties is one of infrastructure and of works, rather than one of supply to order the reformation of the Water
or mere services. 46 CDHSac Supply Contract
The jurisdiction of courts and quasi-judicial bodies is determined by administrative discretion, such as that of the HLURB, the sole regulatory
the Constitution and the law. 50 It cannot be fixed by the will of the parties to body for housing and land development. It was further pointed out that the
the dispute, nor can it be expanded or diminished by stipulation or extent to which an administrative agency may exercise its powers depends
agreement. 51 The text of Section 4 of E.O. No. 1008 is broad enough to on the provisions of the statute creating such agency.
cover any dispute arising from, or connected with, construction contracts,
whether these involve mere contractual money claims or execution of the The ponencia further quoted from C.T. Torres Enterprises, Inc. v.
works. This jurisdiction cannot be altered by stipulations restricting the nature Hibionada: 56
of construction disputes, appointing another arbitral body, or making that The argument that only courts of justice can
body's decision final and binding. 52 adjudicate claims resoluble under the provisions of the
Thus, unless specifically excluded, all incidents and matters relating Civil Code is out of step with the fast-changing times.
to construction contracts are deemed to be within the jurisdiction of the CIAC. There are hundreds of administrative bodies now
Based on the previously cited provision outlining the CIAC's jurisdiction, it is performing this function by virtue of a valid authorization
clear that with regard to contracts over which it has jurisdiction, the only from the legislature. This quasi-judicial function, as it is
matters that have been excluded by law are disputes arising from employer- called, is exercised by them as an incident of the principal
employee relationships, which continue to be governed by the Labor Code of power entrusted to them of regulating certain activities
the Philippines. Moreover, this is consistent with the policy against split falling under their particular expertise.
jurisdiction. In the Solid Homes case for example the Court
In fact, in National Irrigation Administration v. Court of Appeals, 53 it affirmed the competence of the Housing and Land Use
was held that the CIAC had jurisdiction over the dispute, and not the contract. Regulatory Board to award damages although this is an
Therefore, even if the contract preceded the existence of the CIAC, since the essentially judicial power exercisable ordinarily only by the
dispute arose when the CIAC had already been constituted, the arbitral board courts of justice. This departure from the traditional
was exercising current, and not retroactive, jurisdiction. In the same case, it allocation of governmental powers is justified by
was held that as long as the parties agree to submit to voluntary arbitration, expediency, or the need of the government to respond
regardless of what forum they may choose, their agreement will fall within the swiftly and competently to the pressing problems of the
jurisdiction of the CIAC, such that, even if they specifically choose another modern world.
forum, the parties will not be precluded from electing to submit their dispute In Bagunu v. Spouses Aggabao, 57 the Court ruled that the RTC
to the CIAC because this right has been vested upon each party by law. must defer the exercise of its jurisdiction on related issues involving the same
This is consistent with the principle that when an administrative subject matter properly within its jurisdiction, such as the distinct cause of
agency or body is conferred quasi-judicial functions, all controversies relating action for reformation of contracts involving the same property, since the
to the subject matter pertaining to its specialization are deemed to be DENR assumed jurisdiction over the lot in question, pursuant to its
included within its jurisdiction since the law does not sanction a split of mandate. DSAICa
jurisdiction, as stated in Peña v. Government Service Insurance System. 54 In National Housing Authority v. First United Constructors
In Peña, the Court held that although the complaint for specific Corporation, 58 the Court held that there was no basis for the exclusion of
performance, annulment of mortgage, and damages filed by the petitioner claims for business losses from the jurisdiction of the CIAC because E.O. No.
against the respondent included title to, possession of, or interest in, real 1008 "excludes from the coverage of the law only those disputes arising from
estate, it was well within the jurisdiction of the Housing and Land Use employer-employee relationships which are covered by the Labor Code,
Regulatory Board (HLURB), a quasi-judicial body, as it involved a claim conveying an intention to encompass a broad range of arbitrable issues
against the subdivision developer, Queen's Row Subdivision, Inc., as well as within the jurisdiction of CIAC." 59 Section 4 provides that "(t)he jurisdiction
the Government Service Insurance System (GSIS). SDTIaE of the CIAC may include but is not limited to . . .," underscoring the expansive
character of the CIAC's jurisdiction. Very clearly, the CIAC has jurisdiction
This case was later cited in Badillo v. Court of Appeals, 55 where the over a broad range of issues and claims arising from construction disputes,
Court concluded that the HLURB had jurisdiction over complaints for including but not limited to claims for unrealized profits and opportunity or
annulment of title. The Court also held that courts will not determine a business losses. What E.O. No. 1008 emphatically excludes is only disputes
controversy where the issues for resolution demand the exercise of sound arising from employer-employee relationships. 60
Where the law does not delineate, neither should we. Neither the by the Respondent on evidence already admitted prior to
provisions of the Civil Code on reformation of contracts nor the law creating such belated appearance.
the CIAC exclude the reformation of contracts from its jurisdiction.
Jurisprudence further dictates that the grant of jurisdiction over related and Thus, under the CIAC Rules, even without the participation of one of the
incidental matters is implied by law. Therefore, because the CIAC has been parties in the proceedings, the CIAC is still required to proceed with the
held to have jurisdiction over the Contract, it follows that it has jurisdiction to hearing of the construction dispute. 61
order the reformation of the Contract as well. This Court has held that the CIAC has jurisdiction over a dispute
Whether MCWD can validly refuse arising from a construction contract even though only one of the parties
to participate in the arbitration requested for arbitration. 62 In fact, in Philrock, Inc. v. Construction Industry
proceedings Arbitration Commission, 63 the Court held that the CIAC retained jurisdiction
even if both parties had withdrawn their consent to arbitrate.
In light of the finality of the CA decision on the matter of jurisdiction,
the only remaining issue to be disposed of is whether the CIAC could In this case, there being a valid arbitration clause mutually stipulated
proceed with the case even if the MCWD refused to participate in the by the parties, they are both contractually bound to settle their dispute
arbitration proceedings. through arbitration before the CIAC. MCWD refused to participate, but this
should not affect the authority of the CIAC to conduct the proceedings, and,
The Court rules in the affirmative. Though one party can refuse to thereafter, issue an arbitral award.
participate in the arbitration proceedings, this cannot prevent the CIAC from
proceeding with the case and issuing an award in favor of one of the parties. Now, with the CIAC decision being questioned by MCWD, the Court
takes a cursory reading of the said decision. It reveals that the conclusions
Section 4.2 of the Revised Rules of Procedure Governing arrived at by CIAC are supported by facts and the law. Article 1359 of the
Construction Arbitration (CIAC Rules) specifically provides that where the Civil Code states that when there has been a meeting of the minds of the
jurisdiction of the CIAC is properly invoked by the filing of a Request for parties to a contract, but their true intention is not expressed in the instrument
Arbitration in accordance with CIAC Rules, the failure of a respondent to purporting to embody the agreement by reason of mistake, fraud, inequitable
appear, which amounts to refusal to arbitrate, will not stay the proceedings, conduct or accident, one of the parties may ask for the reformation of the
notwithstanding the absence of the respondent or the lack of participation of instrument to the end that such true intention may be expressed. The CIAC,
such party. In such cases, the CIAC is mandated to appoint the arbitrator/s in in this case, found that the parametric formula for price escalation reflected in
accordance with the Rules, and the arbitration proceedings shall continue. the Water Supply Contract involved two items: Power Rate Price Adjustment
The award shall then be made after receiving the evidence of the (30% of the base selling price of water) and Consumer Price Index
claimant. AaCcST Adjustment (40% of the base selling price of water). The remaining 30% of
the selling price of water, which should have been for Capital Cost Recovery,
In such a case, all is not lost for the party who did not participate.
was inadvertently left out in this parametric formula. Thus, the Contract
Even after failing to appear, a respondent is still given the opportunity, under
should be reformed accordingly to reflect the intention of the parties to
the CIAC Rules, to have the proceedings reopened and be allowed to
include in the price escalation formula the Capital Cost Recovery Adjustment.
present evidence, although with the qualification that this is done before an
These conclusions were affirmed by the CA in the assailed decision of
award is issued:
February 20, 2006. CcSTHI
4.2.1 In the event that, before award, the
As noted by MCWD in its reply, however, the dispositive portion of
Respondent who had not earlier questioned the jurisdiction
the CIAC decision reforming the price escalation formula is inconsistent with
of the Tribunal, appears and offers to present his evidence,
what was stated in the body of the decision. The formula contained in the
the Arbitral Tribunal may, for reasons that justifies (sic) the
body of the decision is as follows:
failure to appear, reopen the proceedings, require him to
file his answer with or without counterclaims, pay the fees, PRICE ADJUSTMENT COMPUTATION
where required under these Rules, and allow him to Based on Reformed Clause 17 of the Water Supply
present his evidence, with limited right to cross examine Contract
witnesses already in the discretion of the Tribunal.
Evidence already admitted shall remain. The Tribunal shall 1. Power Cost Adjustment:
decide the effect of such controverting evidence presented
xxx xxx xxx ————————————————————————————
————
Current Power Rate - Base Power Ratex30% of Base Selling Base Forex
Price of water
———————————————————————————— xxx xxx xxx 64
—————— The dispositive portion of the decision, however, reads:
Base Power Rate
xxx xxx xxx WHEREFORE[,] premises considered, judgment is
hereby rendered as follows:
2. Operating Cost Adjustment — Local
1. Ordering the reformation of Clause 17 of the
xxx xxx xxx Water Supply Contract to read:
Current CPI - Base CPIx30% of 40% of Base Selling Price of 17[.] Price Escalation and/or De-
Water Escalation shall be based on the
———————————————————————————— parametric formula:
——
Base CPI 17.1 Power Rate Price
Adjustment/Power Cost Adjustment
xxx xxx xxx
Current Power Rate - Base Power Ratex30% of Base
3. Operating Cost Adjustment — Foreign Selling Price of water
—————————————————————————
xxx xxx xxx
—————————
Current Forex - Base Forexx70% of 40% of Base Selling Price of Base Power Rate
Water 17.2 Consumer Price Index (CPI)
———————————————————————————— Adjustment/Operating (sic) Cost
———— Adjustment:
Base Forex
Current CPI - Base CPIx40% of Base Selling Price of
Water
xxx xxx xxx —————————————————————————
——
4. Capital Cost Adjustment — Local
Base CPI
xxx xxx xxx 17.3 Capital Cost Recovery Adjustment:
Current CPI - Base CPIx30% of 30% of Base Selling Price of Current Peso toBase Peso to US$
Water US$ Exchange Rate - Exchange Rate x 30% of base
———————————————————————————— selling price of water
—— —————————————————————————
Base CPI ————————
xxx xxx xxx Base Peso to US$ Exchange Rate
5. Capital Cost Adjustment — Foreign The general rule is that where there is a conflict between the fallo, or
the dispositive part, and the body of the decision or order, the fallo prevails
xxx xxx xxx on the theory that the fallo is the final order and becomes the subject of
execution, while the body of the decision merely contains the reasons or
Current Forex - Base Forexx70% of 30% of Base Selling Price conclusions of the court ordering nothing. However, where one can clearly
of Water
and unquestionably conclude from the body of the decision that there was a Current Power Rate - Base Power Ratex30% of base
mistake in the dispositive portion, the body of the decision will prevail. 65 selling price of water
—————————————————————————
Following the reasoning of the CIAC in this case, there are three ————————
components to price adjustment: (1) Power Cost Adjustment (30% of the Base Power Rate
base selling price of water); (2) Operating Cost Adjustment (40% of the base
selling price of water); and (3) Capital Cost Adjustment (30% of the base 17.2 Consumer Price Index
selling price of water). (CPI)
Adjustment/Operating
In turn, the second component — Operating Cost Adjustment — is Cost Adjustment:
computed based on Local Operating Cost Adjustment (30%), and Foreign
Operating Cost Adjustment (70%). Current CPI - Base CPIx30% of 40% of base selling
price of water
Capital Cost Adjustment, on the other hand, is composed of Local —————————————————————————
Capital Cost Adjustment (30%), and Foreign Capital Cost Adjustment (70%). ————
Base CPI
This is consistent with the formula set forth in the body of the CIAC
decision. If the formula in the dispositive portion were to be followed, 17.3 Capital Cost Recovery
Operating Cost Adjustment would be computed with the Local Operating Adjustment:
Cost Adjustment representing the entire 40% of the base selling price of
Current Peso toBase Peso to
water instead of just 30% of the Operating Cost Adjustment. Moreover, if the
US$ Exchange Rate - Exchange Ratex70% of 30% of
Capital Cost Recovery Adjustment were to be computed based solely on
base selling
Foreign Capital Cost Recovery Adjustment, it would represent the entire 30%
price of water
of the base selling price of water, and not just 70% of the Capital Cost
—————————————————————————
Recovery Adjustment. The omission of the marked portions of the formula as
————
stated in the body of the CIAC decision represents substantial changes to the
Base Peso to US$ Exchange Rate
formula for price escalation. It is thus clear that the formula as stated in the
body of the decision should govern. aTcSID Price escalation shall be reckoned from
January 1999 when the water was first
WHEREFORE, the petition is DENIED. The Decision and Resolution delivered by Mactan Rock Industries, Inc.
of the Court of Appeals in C.A.-G.R. CEB SP. No. 00623 are AFFIRMED with to the MCWD facilities in Mactan. The
the modification that the formula for the computation of the Capital Cost base CPI, base US$ Exchange Rate and
Recovery Adjustment in the fallo of the CIAC decision should be amended to the Base Power Rate shall be the
read as follows: prevailing rate in January 1999, while the
WHEREFORE, premises considered, judgment is Base Selling Price of water shall mean the
hereby rendered as follows: 1996 rate per cubic meter of water as
provided for in the Water Supply
1. Ordering the reformation of Clause 17 of the Contract. cCaATD
Water Supply Contract to read:
2. Ordering Respondent Metropolitan Cebu
17. Price Escalation and/or De- Water District to pay Claimant, Mactan
Escalation shall be based on the Rock Industries, Inc. under the reformed
parametric formula: Clause 17 of the Water Supply Contract,
the net amount of Php12,126,296.70 plus
17.1. Power Rate Price legal interest of six percent (6%) per
Adjustment/Power Cost annum from March 15, 2004, the date of
Adjustment filing of the case with the Construction
Industry Arbitration Commission, and
twelve percent (12%) per annum from the
date this Decision becomes final and
executory, until the foregoing amounts
shall have been fully paid.
3. Claimant Mactan Rock Industries, Inc. and
Metropolitan Cebu Water District shall
share the cost of arbitration equally.
SO ORDERED.
FIRST DIVISION On May 24, 2000, RCBC entered into a Share Purchase
Agreement 5 (SPA) with Equitable-PCI Bank, Inc. (EPCIB), George L.
Go and the individual shareholders 6 of Bankard, Inc. (Bankard) for the
[G.R. No. 196171. December 10, 2012.] sale to RCBC of 226,460,000 shares (Subject Shares) of Bankard,
constituting 67% of the latter's capital stock. After completing payment of
RCBC CAPITAL CORPORATION, petitioner, vs. BANCO the contract price (P1,786,769,400), the corresponding deeds of sale
DE ORO UNIBANK, INC., respondent. over the subject shares were executed in January 2001. ITcCaS
The dispute between the parties arose sometime in May 2003
when RCBC informed EPCIB and the other selling shareholders of an
[G.R. No. 199238. December 10, 2012.] overpayment of the subject shares, claiming there was an overstatement
of valuation of accounts amounting to P478 million and that the sellers
BANCO DE ORO UNIBANK, INC., petitioner, vs. COURT violated their warranty under Section 5 (g) of the SPA. 7
OF APPEALS and RCBC CAPITAL As no settlement was reached, RCBC commenced arbitration
CORPORATION, respondents. proceedings with the ICC-ICA in accordance with Section 10 of the SPA
which states:
Section 10. Arbitration. —
DECISION
Should there be any dispute arising between the
parties relating to this Agreement including the
interpretation or performance hereof which cannot be
VILLARAMA, JR., J p: resolved by agreement of the parties within fifteen (15)
days after written notice by a party to another, such matter
Before the Court are two consolidated petitions separately filed shall then be finally settled by arbitration under the Rules
by the parties in an arbitration case administered by the International of Conciliation and Arbitration of the International Chamber
Chamber of Commerce-International Court of Arbitration (ICC-ICA) of Commerce in force as of the time of arbitration, by three
pursuant to the arbitration clause in their contract. arbitrators appointed in accordance with such rules. The
venue of arbitration shall be in Makati City, Philippines and
The Case the arbitration proceedings shall be conducted in the
In G.R. No. 196171, a petition for review under Rule 45 of English language. Substantive aspects of the dispute shall
the 1997 Rules of Civil Procedure, as amended, RCBC Capital be settled by applying the laws of the Philippines. The
Corporation (RCBC) seeks to reverse the Court of Appeals (CA) decision of the arbitrators shall be final and binding upon
Decision 1 dated December 23, 2010 in CA-G.R. SP No. 113525 which the parties hereto and the expenses of arbitration
reversed and set aside the June 24, 2009 Order 2 of the Regional Trial (including without limitation the award of attorney's fees to
Court (RTC) of Makati City, Branch 148 in SP Proc. Case No. M-6046. the prevailing party) shall be paid as the arbitrators shall
determine. 8
In G.R. No. 199238, a petition for certiorari under Rule 65,
Banco De Oro Unibank, Inc. (BDO) assails the Resolution 3 dated In its Request for Arbitration 9 dated May 12, 2004, Claimant
September 13, 2011 in CA-G.R. SP No. 120888 which denied BDO's RCBC charged Bankard with deviating from and contravening generally
application for the issuance of a stay order and/or temporary restraining accepted accounting principles and practices, due to which the financial
order (TRO)/preliminary injunction against the implementation of the Writ statements of Bankard prior to the stock purchase were far from fair and
of Execution 4 dated August 22, 2011 issued by the Makati City RTC, accurate, and resulted in the overpayment of P556 million. For this
Branch 148 in SP Proc. Case No. M-6046. violation of sellers' representations and warranties under the SPA, RCBC
sought its rescission, as well as payment of actual damages in the
Factual Antecedents
amount of P573,132,110, legal interest on the purchase price until actual
restitution, moral damages and litigation and attorney's fees, with However, despite reminders from the ICC-ICA, Respondents refused to
alternative prayer for award of damages in the amount of at least pay their share in the advance cost fixed by the ICC-ICA. On December
P809,796,082 plus legal interest. 16, 2004, the ICC-ICA informed the parties that if Respondents still failed
to pay its share in the advance cost, it would apply Article 30 (4) of the
In their Answer, 10 EPCIB, Go and the other selling individual
ICC Rules and request the Arbitration Tribunal to suspend its work and
shareholders (Respondents) denied RCBC's allegations contending that
set a new time limit, and if such requested deposit remains unpaid at the
RCBC's claim is one for overpayment or price reduction under Section 5
expiry thereof, the counterclaims would be considered
(h) of the SPA which is already time-barred, the remedy of rescission is
withdrawn. 15 ECDAcS
unavailable, and even assuming that rescission is permitted by the SPA,
RCBC failed to file its claim within a reasonable time. They further In a fax-letter dated January 4, 2005, the ICC-ICA invited RCBC
asserted that RCBC is not entitled to its alternative prayer for damages, to pay the said amount in substitution of Respondents. It also granted an
being guilty of laches and failing to set out the details of the breach as extension until January 17, 2005 within which to pay the balance of the
required under Section 7 of the SPA. A counterclaim for litigation advance cost (US$175,000). RCBC replied that it was not willing to
expenses and costs of arbitration in the amount of US$300,000, as well shoulder the share of Respondents in the advance on costs but
as moral and exemplary damages, was likewise raised by the nevertheless requested for a clarification as to the effect of such refusal
Respondents. ASTIED to substitute for Respondents' share. 16
RCBC submitted a Reply 11 to the aforesaid Answer. On March 10, 2005, the ICC-ICA instructed the Arbitration
Tribunal to suspend its work and granted the parties a final time-limit of
Subsequently, the Arbitration Tribunal was constituted. Mr. Neil
15 days to pay the balance of the advance on costs, failing which the
Kaplan was nominated by RCBC; Justice Santiago M. Kapunan (a retired
claims shall be considered withdrawn, without prejudice to their
Member of this Court) was nominated by the Respondents; and Sir Ian
reintroduction at a later date in another proceeding. The parties were
Barker was appointed by the ICC-ICA as Chairman.
advised that if any of them objects to the measure, it should make a
On August 13, 2004, the ICC-ICA informed the parties that they request in writing within such period. 17 For the same reason of non-
are required to pay US$350,000 as advance on costs pursuant to Article receipt of the balance of the advance cost, the ICC-ICA issued
30 (3) of the ICC Rules of Arbitration (ICC Rules). RCBC paid its share of Procedural Order No. 3 for the adjournment of the substantive hearings
US$107,000, the balance remaining after deducting payments of and granting the Respondents a two-month extension within which to
US$2,500 and US$65,000 it made earlier. Respondents' share of the submit their brief of evidence and witnesses.
advance on costs was thus fixed at US$175,000.
RCBC objected to the cancellation of hearings, pointing out that
Respondents filed an Application for Separate Advances on Respondents have been given ample time and opportunity to submit their
Costs 12 dated September 17, 2004 under Article 30 (2) of the ICC brief of evidence and prepare for the hearings and that their request for
Rules, praying that the ICC fix separate advances on the cost of the postponement serves no other purpose but to delay the proceedings. It
parties' respective claims and counterclaims, instead of directing them to alleged that Respondents' unjustified refusal to pay their share in the
share equally on the advance cost of Claimant's (RCBC) claim. advance on costs warrants a ruling that they have lost standing to
Respondents deemed this advance cost allocation to be proper, pointing participate in the proceedings. It thus prayed that Respondents be
out that the total amount of RCBC's claim is substantially higher — more declared as in default, the substantive hearings be conducted as
than 40 times — the total amount of their counterclaims, and that it would originally scheduled, and RCBC be allowed to submit rebuttal evidence
be unfair to require them to share in the costs of arbitrating what is and additional witness statements. 18
essentially a price issue that is now time-barred under the SPA.
On December 15, 2005, the ICC-ICA notified the parties of its
On September 20, 2004, the ICC-ICA informed Respondents decision to increase the advances on costs from US$350,000 to
that their application for separate advances on costs was premature US$450,000 subject to later readjustments, and again invited the
pending the execution of the Terms of Reference (TOR). 13 The TOR Respondents to pay the US$100,000 increment within 30 days from
was settled by the parties and signed by the Chairman and Members of notice. Respondents, however, refused to pay the increment, insisting
the Arbitral Tribunal by October 11, 2004. On December 3, 2004, 14 the that RCBC should bear the cost of prosecuting its own claim and that
ICC-ICA denied the application for separate advances on costs and compelling the Respondents to fund such prosecution is inequitable.
invited anew the Respondents to pay its share in the advance on costs.
Respondents reiterated that it was willing to pay the advance on costs for share of the costs advance. What relief, if any, would
their counterclaim. 19 HTScEI have to be then determined by the Tribunal after
having heard submissions from the
On December 27, 2005, the ICC-ICA advised that it was not
Respondents. cSHIaA
possible to fix separate advances on costs as explained in its December
3, 2004 letter, and again invited Respondents to pay their share in the 5. I should be pleased if the Claimant will advise the
advance on costs. Respondents' response contained in the letter dated Tribunal of its intention in relation to the costs advance. If
January 6, 2006 was still the same: it was willing to pay only the separate the costs are not paid, the arbitration cannot
advance on costs of their counterclaim. 20 In view of Respondents' proceed. 22 (Italics in the original; emphasis supplied)
continuing refusal to pay its equal share in the advance on costs and
increment, RCBC wrote the ICC-ICA stating that the latter should compel RCBC paid the additional US$100,000 under the second
the Respondents to pay as otherwise RCBC will be prejudiced and the assessment to avert suspension of the Arbitration Tribunal's
inaction of the ICC-ICA and the Arbitration Tribunal will detract from the proceedings.
effectiveness of arbitration as a means of settling disputes. In Upon the commencement of the hearings, the Arbitration
accordance with Article 30 (4) of the ICC Rules, RCBC reiterated its Tribunal decided that hearings will be initially confined to issues of
request to declare the Respondents as in default without any personality liability (liability phase) while the substantial issues will be heard on a
to participate in the proceedings not only with respect to their later date (quantum phase).
counterclaims but also to the claim of RCBC. 21
Meanwhile, EPCIB's corporate name was officially changed to
Chairman Ian Barker, in a letter dated January 25, 2006, stated Banco De Oro (BDO)-EPCIB after its merger with BDO was duly
in part: approved by the Securities and Exchange Commission. As such, BDO
xxx xxx xxx assumed all the obligations and liabilities of EPCIB under the SPA.
2. The Tribunal has no power under the ICC Rules to On September 27, 2007, the Arbitration Tribunal rendered a
order the Respondents to pay the advance on costs Partial Award 23 (First Partial Award) in ICC-ICA Case No.
sought by the ICC or to give the Claimant any relief 13290/MS/JB/JEM, as follows:
against the Respondents' refusal to pay. The ICC 15AWARD AND DIRECTIONS
Rules differ from, for example, the Rules of the LCIA
(Article 24.3) which enables a party paying the share of 15.1 The Tribunal makes the following
costs which the other party has refused to pay, to declarations by way of Partial Award:
recover "that amount as a debt immediately due from
(a) The Claimant's claim is not time-barred under
the defaulting party."
the provisions of this SPA.
3. The only sanction under the ICC Rules is contained
(b) The Claimant is not estopped by its conduct or
within Article 30 (4). Where a request for an advance on
the equitable doctrine of laches from
costs has not been complied with, after consultation with
pursuing its claim.
the Tribunal, the Secretary-General may direct the
Tribunal to suspend its work. After expiry of a time limit, (c) As detailed in the Partial Award, the Claimant
all claims and counterclaims are then considered as has established the following breaches by
withdrawn. This provision cannot assist a Claimant who the Respondents of clause 5(g) of the
is anxious to litigate its claim. Such a Claimant has to SPA:
pay the sums requested (including the Respondents'
share) if it wishes the arbitration to proceed. i) the assets, revenue and net worth of
Bankard were overstated by
4. It may be possible for a Claimant in the course of reason of its policy on and
the arbitral hearing (or whenever costs are being recognition of Late Payment Fees;
considered by the Tribunal) to make submissions
based on the failure of the Respondents to pay their
ii) reported receivables were higher than While RCBC paid Respondents' share in the increment
their realisable values by reason (US$130,000), it reiterated its plea that Respondents be declared as in
of the 'bucketing' method, thus default and the counterclaims deemed as withdrawn. 29
overstating Bankard's assets;
Chairman Barker's letter dated December 18, 2007 states in
and cDACST
part: aHECST
iii) the relevant Bankard statements were xxx xxx xxx
inadequate and misleading in that
their disclosures caused readers 8. Contrary to the Complainant's view, the Tribunal has no
to be misinformed about jurisdiction to declare that the Respondents have
Bankard's accounting policies on no right to participate in the proceedings
revenue and receivables. concerning the claim. Article 30(4) of the ICC
Rules applies only to any counterclaim of the
(d) Subject to proof of loss the Claimant is entitled Respondents.
to damages for the foregoing breaches.
9. The Tribunal interprets the Claimant's latest letter as
(e) The Claimant is not entitled to rescission of the an application by the Claimant to the Tribunal
SPA. for the issue of a partial award against the
(f) All other issues, including any issue relating Respondents in respect of their failure to pay
to costs, will be dealt with in a further their share of the ICC's requests for advance
or final award. on costs.
15.2 A further Procedural Order will be necessary 10. I should be grateful if the Claimant would confirm that
subsequent to the delivery of this Partial Award to deal this is the situation. If so, the Claimant should
with the determination of quantum and in particular, propose a timetable for which written submissions
whether there should be an Expert appointed by the should be made by both parties. This is an
Tribunal under Article 20(4) of the ICC Rules to assist the application which can be considered by the
Tribunal in this regard. Tribunal on written submissions. 30 (Emphasis
supplied)
15.3 This Award is delivered by a majority of the
Tribunal (Sir Ian Barker and Mr. Kaplan). Justice Kapunan RCBC, in a letter dated December 26, 2007, confirmed the
is unable to agree with the majority's conclusion on the Arbitration Tribunal's interpretation that it was applying for a partial award
claim of estoppel brought by the against Respondents' failure to pay their share in the advance on
Respondents. 24 (Emphasis supplied) costs. 31
On October 26, 2007, RCBC filed with the Makati City RTC, Meanwhile, on January 8, 2008, the Makati City RTC, Branch
Branch 148 (SP Proc. Case No. M-6046) a motion to confirm the First 148 issued an order in SP Proc. Case No. M-6046 confirming the First
Partial Award, while Respondents filed a motion to vacate the same. Partial Award and denying Respondents' separate motions to vacate and
to suspend and inhibit Barker and Kaplan. Respondents' motion for
ICC-ICA by letter 25 dated October 12, 2007 increased the reconsideration was likewise denied. Respondents directly filed with this
advance on costs from US$450,000 to US$580,000. Under this third Court a petition for review on certiorari under Rule 45, docketed as G.R.
assessment, RCBC paid US$130,000 as its share on the increment. No. 182248 and entitled Equitable PCI Banking Corporation v. RCBC
Respondents declined to pay its adjudged total share of US$290,000 on Capital Corporation. 32 In our Decision dated December 18, 2008, we
account of its filing in the RTC of a motion to vacate the First Partial denied the petition and affirmed the RTC's ruling confirming the First
Award. 26 The ICC-ICA then invited RCBC to substitute for Respondents Partial Award.
in paying the balance of US$130,000 by December 21, 2007. 27 RCBC
complied with the request, making its total payments in the amount of On January 18, 2008, the Arbitration Tribunal set a timetable for
US$580,000. 28 the filing of submission by the parties on whether it should issue a
Second Partial Award in respect of the Respondents' refusal to pay an In his letter dated March 13, 2008, Chairman Barker advised the
advance on costs to the ICC-ICA. parties, as follows:
In compliance, RCBC filed on February 7, 2008 an Application 1. The Tribunal acknowledges the Respondents' response
for Reimbursement of Advance on Costs Paid, praying for the issuance to the Claimant's application for a Partial Award,
of a partial award directing the Respondents to reimburse its payment in based on the Respondents' failure to pay their
the amount of US$290,000 representing Respondents' share in the share of the costs, as requested by the
Advance on Costs and to consider Respondents' counterclaim for actual ICC. aESTAI
damages in the amount of US$300,000, and moral and exemplary
damages as withdrawn for their failure to pay their equal share in the 2. The Tribunal notes that neither party has referred to
advance on costs. RCBC invoked the plain terms of Article 30 (2) and (3) an article by Mat[t]hew Secomb on this very
to stress the liability of Respondents to share equally in paying the subject which appears in the ICC Bulletin Vol.
advance on costs where the Arbitration Tribunal has fixed the 14 No. 1 (Spring 2003). To assist both sides and
same. 33 ICAcHE to ensure that the Tribunal does not consider
material on which the parties have not been given
Respondents, on the other hand, filed their Opposition 34 to the an opportunity to address, I attach a copy of this
said application alleging that the Arbitration Tribunal has lost its article, which also contains reference to other
objectivity in an unnecessary litigation over the payment of Respondents' scholarly works on the subject.
share in the advance costs. They pointed out that RCBC's letter merely
asked that Respondents be declared as in default for their failure to pay 3. The Tribunal will give each party seven days within
advance costs but the Arbitration Tribunal, while denying the request which to submit further written comments as a
offered an alternative to RCBC: a Partial Award for Respondents' share consequence of being alerted to the above
in the advance costs even if it was clear from the language of RCBC's authorities. 35 (Additional emphasis supplied)
December 11, 2007 letter that it had no intention of litigating for the The parties complied by submitting their respective comments.
advance costs. Chairman Barker, after ruling earlier that it cannot grant
RCBC's request to declare the Respondents as having no right to RCBC refuted Respondents' allegation of partiality on the part of
participate in the proceedings concerning the claim, interpreted RCBC's Chairman Barker and reiterated the prayer in its application for
letter as an application for the Arbitration Tribunal to issue a partial award reimbursement of advance on costs paid to the ICC-ICA. RCBC
in respect of such refusal of Respondents to pay their share in the contended that based on Mr. Secomb's article, whether the "contractual"
advance on costs, and subsequently directed the parties to make or "provisional measures" approach is applied, the Arbitration Tribunal is
submissions on the matter. Aside from violating their right to due process vested with jurisdiction and authority to render an award with respect to
and to be heard by an impartial tribunal, Respondents also argued that in said reimbursement of advance cost paid by the non-defaulting party. 36
issuing the award for advance cost, the Arbitration Tribunal decided an
Respondents, on the other hand, maintained that RCBC's
issue beyond the terms of the TOR.
application for reimbursement of advance cost has no basis under the
Respondents also emphasized that the parties agreed on a two- ICC Rules. They contended that no manifest injustice can be inferred
part arbitration: the first part of the Tribunal's proceedings would from an act of a party paying for the share of the defaulting party as this
determine Respondents' liability, if any, for alleged violation of Section 5 scenario is allowed by the ICC Rules. Neither can a partial award for
(g) and (h) of the SPA; and the second part of the proceedings would advance cost be justified under the "contractual approach" since the
determine the amounts owed by one party to another as a consequence matter of costs for arbitration is between the ICC and the parties, not the
of a finding of liability or lack thereof. An award for "reimbursement of Arbitration Tribunal and the parties. An arbitration tribunal can issue
advances for costs" clearly falls outside the scope of either proceedings. decisions on costs only for those costs not fixed by the ICC. 37
Neither can the Tribunal justify such proceedings under Article 23 of the
Respondents reiterated their position that Article 30 (3) envisions
ICC Rules (Conservatory and Interim Measures) because that provision
a situation whereby a party would refuse to pay its share on the advance
does not contemplate an award for the reimbursement of advance on
on costs and provides a remedy therefor — the other party "shall be free
costs in arbitration cases. Respondents further asserted that since the
to pay the whole of the advance on costs." Such party's reimbursement
advances on costs have been paid by the Claimant (RCBC), the main
for payments of the defaulting party's share depends on the final arbitral
claim and counterclaim may both be heard by the Arbitration Tribunal.
award where the party liable for costs would be determined. This is the the substituted payments. Such conduct of Chairman Barker is
only remedy provided by the ICC Rules. 38 prejudicial and proves his evident partiality in favor of RCBC. CSIHDA
On May 28, 2008, the Arbitration Tribunal rendered the Second RCBC filed its Opposition, 43 asserting that the Arbitration
Partial Award, 39 as follows: DEHcTI Tribunal had jurisdiction to consider Respondents' counterclaim as
withdrawn, the same having been abandoned by not presenting any
7AWARD
computation or substantiation by evidence, their only computation relates
7.1 Having read and considered the submissions of both only to attorney's fees which are simply cost of litigation properly brought
parties, the Tribunal AWARDS, DECLARES AND at the conclusion of the arbitration. It also pointed out that the Arbitration
ORDERS as follows: Tribunal was empowered by the parties' arbitral clause to determine the
manner of payment of expenses of arbitration, and that the Second
(a) The Respondents are forthwith to pay to the Partial Award was based on authorities and treatises on the mandatory
Claimant the sum of US$290,000. and contractual nature of the obligation to pay advances on costs.
(b) The Respondents' counterclaim is to be In its Reply, 44 EPCIB contended that RCBC had the option to
considered as withdrawn. agree to its proposal for separate advances on costs but decided against
it; RCBC's act of paying the balance of the advance cost in substitution of
(c) All other questions, including interest and EPCIB was for the purpose of having EPCIB defaulted and the latter's
costs, will be dealt with in a subsequent counterclaim withdrawn. Having agreed to finance the arbitration until its
award. 40 completion, RCBC is not entitled to immediate reimbursement of the
The above partial award was received by RCBC and amount it paid in substitution of EPCIB under an interim award, as its
Respondents on June 12, 2008. right to a partial or total reimbursement will have to be determined under
the final award. EPCIB asserted that the matter of reimbursement of
On July 11, 2008, EPCIB filed a Motion to Vacate Second Partial advance cost paid cannot be said to have properly arisen during
Award 41 in the Makati City RTC, Branch 148 (SP Proc. Case No. M- arbitration. EPCIB reiterated that Chairman Barker's interpretation of
6046). On July 10, 2008, RCBC filed in the same court a Motion to RCBC's December 11, 2007 letter as an application for interim award for
Confirm Second Partial Award. 42 reimbursement is tantamount to a promise that the award will be issued
EPCIB raised the following grounds for vacating the Second in due course.
Partial Award: (a) the award is voidab initio having been rendered by the After a further exchange of pleadings, and other motions seeking
arbitrators who exceeded their power or acted without it; and (b) the relief from the court in connection with the arbitration proceedings
award was procured by undue means or issued with evident partiality or (quantum phase), the Makati City RTC, Branch 148 issued the
attended by misbehavior on the part of the Tribunal which resulted in a Order 45 dated June 24, 2009 confirming the Second Partial Award and
material prejudice to the rights of the Respondents. EPCIB argued that denying EPCIB's motion to vacate the same. Said court held that since
there is no express agreement either in the SPA or the ICC Rules for the parties agreed to submit any dispute under the SPA to arbitration and
such right of reimbursement. There is likewise no implied agreement to be bound by the ICC Rules, they are also bound to pay in equal
because from the ICC Rules, the only inference is that the parties agreed shares the advance on costs as provided in Article 30 (2) and (3). It
to await the dispositions on costs liability in the Final Award, not before. noted that RCBC was forced to pay the share of EPCIB in substitution of
On the ruling of the Arbitration Tribunal that Respondents' the latter to prevent a suspension of the arbitration proceedings, while
application for costs are not counterclaims, EPCIB asserted that this is EPCIB's non-payment seems more like a scheme to delay such
contrary to Philippine law as it is basic in our jurisdiction that proceedings. On the Arbitration Tribunal's ruling on EPCIB's
counterclaims for litigation expenses, moral and exemplary damages are counterclaim, no error was committed in considering it withdrawn for
proper counterclaims, which rule should be recognized in view of Section failure of EPCIB to quantify and substantiate it with supporting evidence.
10 of the SPA which provides that "substantive aspects of the dispute As to EPCIB's claim for attorney's fees, the RTC agreed that these
shall be settled by applying the laws of the Philippines." Finally, EPCIB should be brought only at the close of arbitration.
takes issue with Chairman Barker's interpretation of RCBC's December EPCIB moved to reconsider the June 24, 2009 Order and for the
11, 2007 letter as an application for a partial award for reimbursement of voluntary inhibition of the Presiding Judge (Judge Oscar B. Pimentel) on
the ground that EPCIB's new counsel represented another client in Experts' fees P7,082,788.55
another case before him in which said counsel assailed his conduct and Costs of without prejudice meeting P22,571.45
had likewise sought his inhibition. Both motions were denied in the Joint Costs of arbitration hearings P553,420.66
Order 46 dated March 23, 2010. cDHAaT Costs of transcription service P483,597.26
—————————
On April 14, 2010, EPCIB filed in the CA a petition for
————
review 47 with application for TRO and/or writ of preliminary injunction
Total P8,144,377.62
(CA-G.R. SP No. 113525) in accordance with Rule 19, Section 4 of the
===========
Special Rules of Court on Alternative Dispute Resolution 48 (Special
(e) The Respondents are to pay to the Claimant
ADR Rules). EPCIB assailed the Makati City RTC, Branch 148 in
the sum of P7,000,000 for party-and-party
denying its motion to vacate the Second Partial Award despite (a) said
legal costs.
award having been rendered in excess of jurisdiction or power, and
contrary to public policy; (b) the fact that it was issued with evident (f) The Counterclaims of the Respondents are all
partiality and serious misconduct; (c) the award deals with a dispute not dismissed.
contemplated within the terms of submission to arbitration or beyond the
scope of such submission, which therefore ought to be vacated pursuant (g) All claims of the Claimant are dismissed, other
to Article 34 of the UNCITRAL Model Law; and (d) the Presiding Judge than those referred to above.
having exhibited bias and prejudice against BDO and its counsel as 15.2 Justice Kapunan does not agree with the majority of
confirmed by his pronouncements in the Joint Order dated March 23, the members of the Tribunal and has issued a
2010 in which, instead of recusing himself, he imputed malice and dissenting opinion. He has refused to sign this
unethical conduct in the entry of appearance of Belo Gozon Elma Award. 50
Asuncion and Lucila Law Offices in SP Proc. Case No. M-6046, which
warrants his voluntary inhibition. On July 1, 2010 BDO filed in the Makati City RTC a Petition to
Vacate Final Award Ad Cautelam, 51 docketed as SP Proc. Case No. M-
Meanwhile, on June 16, 2010, the Arbitration Tribunal issued the
6995, which was raffled to Branch 65.
Final Award, 49 as follows:
On July 28, 2010, RCBC filed with the Makati City RTC, Branch
15AWARD
148 (SP Proc. Case No. M-6046) a Motion to Confirm Final
15.1 The Tribunal by a majority (Sir Ian Barker & Mr. Award. 52 BDO filed its Opposition with Motion to Dismiss 53 on grounds
Kaplan) awards, declares and adjudges as follows: that a Petition to Vacate Final Award Ad Cautelam had already been
filed in SP Proc. Case No. M-6995. BDO also pointed out that RCBC did
(a) the Respondents are to pay damages to the not file the required petition but instead filed a mere motion which did not
Claimant for breach of the sale and go through the process of raffling to a proper branch of the RTC of
purchase agreement for Bankard shares Makati City and the payment of the required docket/filing fees. Even
in the sum of P348,736,920.29. assuming that Branch 148 has jurisdiction over RCBC's motion to
(b) The Respondents are to pay to the Claimant confirm final award, BDO asserted that RCBC had filed before the
the sum of US$880,000 in respect of the Arbitration Tribunal an Application for Correction and Interpretation of
costs of the arbitration as fixed by the ICC Award under Article 29 of the ICC Rules, which is irreconcilable with its
Court. Motion to Confirm Final Award before said court. Hence, the Motion to
Confirm Award was filed precipitately. TICDSc
(c) The Respondents are to pay to the Claimant
On August 18, 2010, RCBC filed an Omnibus Motion in SP Proc.
the sum of US$582,936.56 for the fees
Case No. M-6995 (Branch 65) praying for the dismissal of BDO's Petition
and expenses of Mr. Best.
to Vacate Final Award or the transfer of the same to Branch 148 for
(d) The Respondents are to pay to the Claimant consolidation with SP Proc. Case No. M-6046. RCBC contended that
their expenses of the arbitration as BDO's filing of its petition with another court is a blatant violation of the
follows: cDCIHT Special ADR Rules and is merely a subterfuge to commit forum-
shopping. BDO filed its Opposition to the Omnibus Motion. 54
On October 28, 2010, Branch 65 issued a Resolution 55 denying Commerce Court of Arbitration Reference
RCBC's omnibus motion and directing the service of the petition to No. 13290/MS/JB/JEM.
RCBC for the latter's filing of a comment thereon. RCBC's motion for
reconsideration was likewise denied in the said court's Order dated SO ORDERED. 59
December 15, 2010. RCBC then filed its Opposition to the Petition to RCBC filed a motion for reconsideration but the CA denied the
Vacate Final Award Ad Cautelam. same in its Resolution 60 dated March 16, 2011. On April 6, 2011, it filed
Meanwhile, on November 10, 2010, Branch 148 (SP Proc. Case a petition for review on certiorari in this Court (G.R. No. 196171).
No. M-6046) issued an Order 56 confirming the Final Award "subject to On February 25, 2011, Branch 65 rendered a Decision 61 in SP
the correction/interpretation thereof by the Arbitral Tribunal pursuant to Proc. Case No. M-6995, as follows:
the ICC Rules and the UNCITRAL Model Law," and denying BDO's
Opposition with Motion to Dismiss. WHEREFORE, premises considered, the Final
Award dated June 16, 2010 in ICC Ref. No.
On December 30, 2010, George L. Go, in his personal capacity 13290/MS/JB/JEM is hereby VACATED with cost against
and as attorney-in-fact of the other listed shareholders of Bankard, Inc. in the respondent.
the SPA (Individual Shareholders), filed a petition in the CA, CA-G.R. SP
No. 117451, seeking to set aside the above-cited November 10, 2010 SO ORDERED. 62
Order and to enjoin Branch 148 from further proceeding in SP Proc.
Case No. M-6046. By Decision 57 dated June 15, 2011, the CA In SP Proc. Case No. M-6046, Branch 148 issued an
dismissed the said petition. Their motion for reconsideration of the said Order 63 dated August 8, 2011 resolving the following motions: (1)
decision was likewise denied by the CA in its Resolution 58 dated Motion for Reconsideration filed by BDO, Go and Individual Shareholders
December 14, 2011. of the November 10, 2010 Order confirming the Final Award; (2) RCBC's
Omnibus Motion to expunge the motion for reconsideration filed by Go
On December 23, 2010, the CA rendered its Decision in CA-G.R. and Individual Shareholders, and for execution of the Final Award; (3)
SP No. 113525, the dispositive portion of which states: Motion for Execution filed by RCBC against BDO; (4) BDO's Motion for
Leave to File Supplement to the Motion for Reconsideration; and (5)
WHEREFORE, premises considered, the following
Motion for Inhibition filed by Go and Individual Shareholders. Said Order
are hereby REVERSED and SET ASIDE:
decreed:
1. the Order dated June 24, 2009 issued in SP WHEREFORE, premises considered, it is hereby
Proc. Case No. M-6046 by the Regional ORDERED, to wit: IcaEDC
Trial Court of Makati City, Branch 148,
insofar as it denied the Motion to Vacate 1. Banco De Oro's Motion for Reconsideration,
Second Partial Award dated July 8, 2008 Motion for Leave to File Supplement to Motion for
and granted the Motion to Confirm Second Reconsideration, and Motion to Inhibit are DENIED for
Partial Award dated July 10, 2008; cACEaI lack of merit.
2. the Joint Order dated March 23, 2010 issued in 2. RCBC Capital's Motion to Expunge, Motion to
SP Proc. Case No. M-6046 by the Execute against Mr. George L. Go and the Bankard
Regional Trial Court of Makati City, Shareholders, and the Motion to Execute against Banco
Branch 148, insofar as it denied the De Oro are hereby GRANTED.
Motion for Reconsideration dated July 28,
2009 relative to the motions concerning 3. The damages awarded to RCBC Capital
the Second Partial Award immediately Corporation in the amount of PhP348,736,920.29 is
mentioned above; and subject to an interest of 6% per annum reckoned from the
date of RCBC Capital's extra-judicial demand or from May
3. the Second Partial Award dated May 28, 2008 5, 2003 until the confirmation of the Final Award. Likewise,
issued in International Chamber of this compounded amount is subject to 12% interest per
annum from the date of the confirmation of the Final Award
until its satisfaction. The costs of the arbitration amounting judgment debt or the property to be levied upon. In any case, with the
to US$880,000.00, the fees and expenses of Mr. Best posting of a bond by BDO, Branch 148 has no jurisdiction to implement
amounting to US$582,936.56, the Claimant's expenses of the appealed orders as it would pre-empt the CA from exercising its
the arbitration amounting to PhP8,144,377.62, and the review under Rule 19 of the Special ADR Rules after BDO had perfected
party-and-party legal costs amounting to PhP7,000,000.00 its appeal. BDO stressed that the bond posted by RCBC was for a
all ruled in favor of RCBC Capital Corporation in the Final measly sum of P3,000,000.00 to cause execution pending appeal of a
Award of the Arbitral Tribunal dated June 16, 2010 are monetary award that may reach P631,429,345.29. RCBC also failed to
subject to 12% legal interest per annum, also reckoned adduce evidence of "good cause" or "good reason" to justify discretionary
from the date of the confirmation of the Final Award until its execution under Section 2 (a), Rule 39 of the Rules of Court.
satisfaction.
BDO further contended that the writ of execution should be
4. Pursuant to Section 40 of R.A. No. 9285, quashed for having been issued with grave abuse of discretion
otherwise known as the Alternative Dispute Resolution Act amounting to lack or excess of jurisdiction as Branch 148 modified the
of 2004 in relation to Rule 39 of the Rules of Court, since Final Award at the time of execution by imposing the payment of
the Final Award have been confirmed, the same shall be interests though none was provided therein nor in the Order confirming
enforced in the same manner as final and executory the same.
decisions of the Regional Trial Court, let a writ of execution During the pendency of CA-G.R. SP No. 120888, Branch 148
be issued commanding the Sheriff to enforce this instant continued with execution proceedings and on motion by RCBC
Order confirming this Court's Order dated November 10, designated/deputized additional sheriffs to replace Sheriff Flora who was
2010 that judicially confirmed the June 16, 2010 Final supposedly physically indisposed. 68 These court personnel went to the
Award. offices/branches of BDO attempting to serve notices of garnishment and
SO ORDERED. 64 to levy the furniture, fixtures and equipment. EcAHDT
Immediately thereafter, RCBC filed an Urgent Motion for On September 12, 2011, BDO filed a Very Urgent Motion to Lift
Issuance of a Writ of Execution. 65 On August 22, 2011, after approving Levy and for Leave to Post Counter-Bond 69 before Branch 148 praying
the execution bond, Branch 148 issued a Writ of Execution for the for the lifting of the levy of BDO Private Bank, Inc. (BPBI) shares and the
implementation of the said court's "Order dated August 8, 2011 cancellation of the execution sale thereof scheduled on September 15,
confirming the November 10, 2010 Order that judicially confirmed the 2011, which was set for hearing on September 14, 2011. BDO claimed
June 16, 2010 Final Award . . . ." 66 aDcHIS that the levy was invalid because it was served by the RTC Sheriffs not
to the authorized representatives of BPBI, as provided under Section 9
BDO then filed in the CA, a "Petition for Review (With Application (b), Rule 39 in relation to Section 7, Rule 57 of the Rules of Court stating
for a Stay Order or Temporary Restraining Order and/or Writ of that a notice of levy on shares of stock must be served to the president
Preliminary Injunction," docketed as CA-G.R. SP No. 120888. BDO or managing agent of the company which issued the shares. However,
sought to reverse and set aside the Orders dated November 10, 2010 BDO was advised by court staff that Judge Sarabia was on leave and the
and August 8, 2011, and any writ of execution issued pursuant thereto, case could not be set for hearing.
as well as the Final Award dated June 16, 2010 issued by the Arbitration
Tribunal. In its Opposition to BDO's application for injunctive relief, RCBC
prayed for its outright denial as BDO's petition raises questions of fact
In its Urgent Omnibus Motion 67 to resolve the application for a and/or law which call for the CA to substitute its judgment with that of the
stay order and/or TRO/writ of preliminary injunction, and to quash the Arbitration Tribunal, in patent violation of applicable rules of procedure
Writ of Execution dated August 22, 2011 and lift the Notices of governing domestic arbitration and beyond the appellate court's
Garnishment dated August 22, 2011, BDO argued that the assailed jurisdiction. RCBC asserted that BDO's application has become moot
orders of execution (Writ of Execution and Notice of Garnishment) were and academic as the writ of execution was already implemented and/or
issued with indecent haste and despite the non-compliance with the enforced. It also contended that BDO has no clear and unmistakable
procedures in Special ADR Rules of the November 10, 2010 Order right to warrant injunctive relief because the issue of jurisdiction was
confirming the Final Award. BDO was not given sufficient time to respond already ruled upon in CA-G.R. SP No. 117451 which dismissed the
to the demand for payment or to elect the method of satisfaction of the petition filed by Go and the Individual Shareholders of Bankard
questioning the authority of Branch 148 over RCBC's motion to confirm PARTIAL AWARD IN PATENT CONTRAVENTION OF
the Final Award despite the earlier filing by BDO in another branch of the THE SPECIAL ADR RULES WHICH EXPRESSLY
RTC (Branch 65) of a petition to vacate the said award. PROHIBITS THE COURTS, IN AN APPLICATION TO
VACATE AN ARBITRAL AWARD, FROM DISTURBING
On September 13, 2011, BDO, to avert the sale of the BPBI
THE FINDINGS OF FACT AND/OR
shares scheduled on September 15, 2011 and prevent further disruption
INTERPRE[TA]TION OF LAW OF THE ARBITRAL
in the operations of BDO and BPBI, paid under protest by tendering a
TRIBUNAL. 71
Manager's Check in the amount of P637,941,185.55, which was
accepted by RCBC as full and complete satisfaction of the writ of BDO raises the following arguments in G.R. No. 199238:
execution. BDO manifested before Branch 148 that such payment was
made without prejudice to its appeal before the CA. 70 THE COURT OF APPEALS COMMITTED GRAVE
ABUSE OF DISCRETION AMOUNTING TO LACK OR
On even date, the CA denied BDO's application for a stay order EXCESS OF JURISDICTION IN PERFUNCTORILY
and/or TRO/preliminary injunction for non-compliance with Rule 19.25 of DENYING PETITIONER BDO'S APPLICATION FOR
the Special ADR Rules. The CA ruled that BDO failed to show the STAY ORDER, AND/OR TEMPORARY RESTRAINING
existence of a clear right to be protected and that the acts sought to be ORDER AND PRELIMINARY INJUNCTION DESPITE
enjoined violated any right. Neither was BDO able to demonstrate that THE EXISTENCE AND CONCURRENCE OF ALL THE
the injury to be suffered by it is irreparable or not susceptible to ELEMENTS FOR THE ISSUANCE OF SAID
mathematical computation. PROVISIONAL RELIEFS EICScD
BDO did not file a motion for reconsideration and directly filed A. PETITIONER BDO HAS CLEAR AND UNMISTAKABLE
with this Court a petition for certiorari with urgent application for writ of RIGHTS TO BE PROTECTED BY THE
preliminary mandatory injunction (G.R. No. 199238). ISSUANCE OF THE INJUNCTIVE RELIEF
The Petitions PRAYED FOR, WHICH, HOWEVER, WERE
DISREGARDED BY PUBLIC RESPONDENT
In G.R. No. 196171, RCBC set forth the following grounds for the WHEN IT DENIED PETITIONER BDO'S PRAYER
reversal of the CA Decision dated December 23, 2010: FOR ISSUANCE OF A STAY ORDER AND/OR
I. TRO
THE COURT OF APPEALS ACTED CONTRARY TO B. PETITIONER BDO'S RIGHT TO DUE PROCESS AND
LAW AND PRIOR RULINGS OF THIS HONORABLE EQUAL PROTECTION OF THE LAW WAS
COURT AND COMMITTED REVERSIBLE ERROR IN GROSSLY VIOLATED BY THE RTC-MAKATI
VACATING THE SECOND PARTIAL AWARD ON THE CITY BRANCH 148, THE DEPUTIZED SHERIFFS
BASIS OF CHAIRMAN BARKER'S ALLEGED AND RESPONDENT RCBC CAPITAL, WHICH
PARTIALITY, WHICH IT CLAIMS IS INDICATIVE OF VIOLATION WAS AIDED BY PUBLIC
BIAS CONSIDERING THAT THE ALLEGATIONS RESPONDENT'S INACTION ON AND
CONTAINED IN BDO/EPCIB'S PETITION FALL SHORT EVENTUAL DENIAL OF THE PRAYER FOR
OF THE JURISPRUDENTIAL REQUIREMENT THAT STAY ORDER AND/OR TRO
THE SAME BE SUPPORTED BY CLEAR AND C. DUE TO THE ACTS AND ORDERS OF RTC BRANCH
CONVINCING EVIDENCE. IaEHSD 148, PETITIONER BDO SUFFERED
II. IRREPARABLE DAMAGE AND INJURY, AND
THERE WAS DIRE AND URGENT NECESSITY
THE COURT OF APPEALS ACTED CONTRARY TO FOR THE ISSUANCE OF THE INJUNCTIVE
LAW AND PRIOR RULINGS OF THIS HONORABLE RELIEF PRAYED FOR WHICH PUBLIC
COURT AND COMMITTED REVERSIBLE ERROR RESPONDENT DENIED IN GRAVE ABUSE OF
WHEN IT REVERSED THE ARBITRAL TRIBUNAL'S DISCRETION 72
FINDINGS OF FACT AND LAW IN THE SECOND
Essentially, the issues to be resolved are: (1) whether there is Republic Act No. 876. Any other ground raised against a
legal ground to vacate the Second Partial Award; and (2) whether BDO is domestic arbitral award shall be disregarded by the
entitled to injunctive relief in connection with the execution proceedings regional trial court.
in SP Proc. Case No. M-6046.
Rule 11.4 of the Special ADR Rules sets forth the grounds for
In their TOR, the parties agreed on the governing law and rules vacating an arbitral award:
as follows:
Rule 11.4. Grounds. — (A) To vacate an arbitral
Laws to be Applied award. — The arbitral award may be vacated on the
following grounds:
13 The Tribunal shall determine the issues to be resolved
in accordance with the laws of the Republic of the a. The arbitral award was procured through
Philippines. corruption, fraud or other undue means;
Procedure to be Applied b. There was evident partiality or corruption in
the arbitral tribunal or any of its members;
14 The proceedings before the Tribunal shall be governed
by the ICC Rules of Arbitration (1 January 1998) c. The arbitral tribunal was guilty of misconduct or
and the law currently applicable to arbitration in any form of misbehavior that has materially prejudiced the
the Republic of the Philippines. 73 rights of any party such as refusing to postpone a hearing
upon sufficient cause shown or to hear evidence pertinent
As stated in the Partial Award dated September 27, 2007,
and material to the controversy;
although the parties provided in Section 10 of the SPA that the arbitration
shall be conducted under the ICC Rules, it was nevertheless arbitration d. One or more of the arbitrators was disqualified
under Philippine law since the parties are both residents of this country. to act as such under the law and willfully refrained from
The provisions of Republic Act No. 876 74 (RA 876), as amended by disclosing such disqualification; or cDEHIC
Republic Act No. 9285 75 (RA 9285) principally applied in the arbitration
between the herein parties. 76 aCSDIc e. The arbitral tribunal exceeded its powers, or
so imperfectly executed them, such that a complete, final
The pertinent provisions of R.A. 9285 provide: and definite award upon the subject matter submitted to
SEC. 40. Confirmation of Award. — The them was not made.
confirmation of a domestic arbitral award shall be The award may also be vacated on any or all of
governed by Section 23 of R.A. 876. the following grounds:
A domestic arbitral award when confirmed shall be a. The arbitration agreement did not exist, or is
enforced in the same manner as final and executory invalid for any ground for the revocation of a contract or is
decisions of the Regional Trial Court. otherwise unenforceable; or
The confirmation of a domestic award shall be b. A party to arbitration is a minor or a person
made by the regional trial court in accordance with the judicially declared to be incompetent.
Rules of Procedure to be promulgated by the Supreme
Court. xxx xxx xxx
xxx xxx xxx In deciding the petition to vacate the arbitral
award, the court shall disregard any other ground than
SEC. 41. Vacation Award. — A party to a those enumerated above. (Emphasis supplied)
domestic arbitration may question the arbitral award with
the appropriate regional trial court in accordance with the Judicial Review
rules of procedure to be promulgated by the Supreme
At the outset, it must be stated that a review brought to this Court
Court only on those grounds enumerated in Section 25 of
under the Special ADR Rules is not a matter of right. Rule 19.36 of said
Rules specified the conditions for the exercise of this Court's The applicable standard for judicial review of arbitral awards in
discretionary review of the CA's decision. this jurisdiction is set forth in Rule 19.10 which states:
Rule 19.36. Review discretionary. — A review by Rule 19.10. Rule on judicial review on arbitration
the Supreme Court is not a matter of right, but of sound in the Philippines. — As a general rule, the court can only
judicial discretion, which will be granted only for serious vacate or set aside the decision of an arbitral tribunal upon
and compelling reasons resulting in grave prejudice to a clear showing that the award suffers from any of the
the aggrieved party. The following, while neither infirmities or grounds for vacating an arbitral award
controlling nor fully measuring the court's discretion, under Section 24 of Republic Act No. 876 or under
indicate the serious and compelling, and necessarily, Rule 34 of the Model Law in a domestic arbitration, or for
restrictive nature of the grounds that will warrant the setting aside an award in an international arbitration under
exercise of the Supreme Court's discretionary Article 34 of the Model Law, or for such other grounds
powers, when the Court of Appeals: provided under these Special Rules.
a. Failed to apply the applicable standard or xxx xxx xxx
test for judicial review prescribed in these Special
ADR Rules in arriving at its decision resulting in The court shall not set aside or vacate the award
substantial prejudice to the aggrieved party; acCETD of the arbitral tribunal merely on the ground that the arbitral
tribunal committed errors of fact, or of law, or of fact and
b. Erred in upholding a final order or decision law, as the court cannot substitute its judgment for that of
despite the lack of jurisdiction of the court that rendered the arbitral tribunal. (Emphasis supplied) DAaHET
such final order or decision;
The above rule embodied the stricter standard in deciding
c. Failed to apply any provision, principle, policy or appeals from arbitral awards established by jurisprudence. In the case
rule contained in these Special ADR Rules resulting in of Asset Privatization Trust v. Court of Appeals, 77 this Court held:
substantial prejudice to the aggrieved party; and
As a rule, the award of an arbitrator cannot be set
d. Committed an error so egregious and harmful to aside for mere errors of judgment either as to the law or as
a party as to amount to an undeniable excess of to the facts. Courts are without power to amend or overrule
jurisdiction. merely because of disagreement with matters of law or
facts determined by the arbitrators. They will not review the
The mere fact that the petitioner disagrees with the findings of law and fact contained in an award, and will not
Court of Appeals' determination of questions of fact, of law undertake to substitute their judgment for that of the
or both questions of fact and law, shall not warrant the arbitrators, since any other rule would make an award the
exercise of the Supreme Court's discretionary power. The commencement, not the end, of litigation. Errors of law and
error imputed to the Court of Appeals must be fact, or an erroneous decision of matters submitted to the
grounded upon any of the above prescribed grounds judgment of the arbitrators, are insufficient to invalidate an
for review or be closely analogous thereto. award fairly and honestly made. Judicial review of an
arbitration is, thus, more limited than judicial review of a
A mere general allegation that the Court of
trial. 78
Appeals has committed serious and substantial error or
that it has acted with grave abuse of discretion resulting in Accordingly, we examine the merits of the petition before us
substantial prejudice to the petitioner without indicating solely on the statutory ground raised for vacating the Second Partial
with specificity the nature of such error or abuse of Award: evident partiality, pursuant to Section 24 (b) of the Arbitration Law
discretion and the serious prejudice suffered by the (RA 876) and Rule 11.4 (b) of the Special ADR Rules.
petitioner on account thereof, shall constitute sufficient
ground for the Supreme Court to dismiss outright the Evident Partiality
petition. (Emphasis supplied) Evident partiality is not defined in our arbitration laws. As one of
the grounds for vacating an arbitral award under the Federal Arbitration
Act (FAA) in the United States (US), the term "encompasses both an possible bias," 84 and that underlying such standard is "the premise that
arbitrator's explicit bias toward one party and an arbitrator's inferred bias any tribunal permitted by law to try cases and controversies not only
when an arbitrator fails to disclose relevant information to the parties." 79 must be unbiased but also must avoid even the appearance of
bias." 85 In a separate concurring opinion, Justice White joined by
From a recent decision 80 of the Court of Appeals of Oregon, we
Justice Marshall, remarked that "[t]he Court does not decide today that
quote a brief discussion of the common meaning of evident partiality:
arbitrators are to be held to the standards of judicial decorum of Article III
To determine the meaning of "evident partiality," judges, or indeed of any judges." 86 He opined that arbitrators should not
we begin with the terms themselves. The common automatically be disqualified from an arbitration proceeding because of a
meaning of "partiality" is "the inclination to favor one business relationship where both parties are aware of the relationship in
side." Webster's Third New Int'l Dictionary 1646 advance, or where the parties are unaware of the circumstances but the
(unabridged ed 2002); see also id. (defining "partial" as relationship is trivial. However, in the event that the arbitrator has a
"inclined to favor one party in a cause or one side of a "substantial interest" in the transaction at hand, such information must be
question more than the other: biased, predisposed" disclosed. HSDIaC
(formatting in original)). "Inclination," in turn, means "a
Subsequent cases decided by the US Court of Appeals Circuit
particular disposition of mind or character: propensity,
Courts adopted different approaches, given the imprecise standard of
bent" or "a tendency to a particular aspect, state,
evident partiality in Commonwealth Coatings.
character, or action." Id. at 1143 (formatting in
original); see also id. (defining "inclined" as "having In Morelite Construction Corp. v. New York District Council
inclination, disposition, or tendency"). ECcTaS Carpenters Benefit Funds, 87 the Second Circuit reversed the judgment
of the district court and remanded with instructions to vacate the
The common meaning of "evident" is "capable of arbitrator's award, holding that the existence of a father-son relationship
being perceived esp[ecially] by sight: distinctly visible: between the arbitrator and the president of appellee union provided
being in evidence: discernable[;] . . . clear to the strong evidence of partiality and was unfair to appellant construction
understanding: obvious, manifest, apparent." Id. at 789 contractor. After examining prior decisions in the Circuit, the court
(formatting in original); see also id. (stating that synonyms concluded that —
of "evident" include "apparent, patent, manifest, plain,
clear, distinct, obvious, [and] palpable" and that, "[s]ince . . . we cannot countenance the promulgation of a
evident rather naturally suggests evidence, it may standard for partiality as insurmountable as "proof of actual
imply the existence of signs and indications that must bias" — as the literal words of Section 10 might suggest.
lead to an identification or inference" (formatting in Bias is always difficult, and indeed often impossible, to
original)). (Emphasis supplied) "prove." Unless an arbitrator publicly announces his
partiality, or is overheard in a moment of private
Evident partiality in its common definition thus implies "the admission, it is difficult to imagine how "proof" would be
existence of signs and indications that must lead to an identification or obtained. Such a standard, we fear, occasionally would
inference" of partiality. 81 Despite the increasing adoption of arbitration in require that we enforce awards in situations that are clearly
many jurisdictions, there seems to be no established standard for repugnant to our sense of fairness, yet do not yield "proof"
determining the existence of evident partiality. In the US, evident of anything.
partiality "continues to be the subject of somewhat conflicting and
inconsistent judicial interpretation when an arbitrator's failure to disclose If the standard of "appearance of bias" is too
prior dealings is at issue." 82 low for the invocation of Section 10, and "proof of
actual bias" too high, with what are we left? Profoundly
The first case to delineate the standard of evident partiality in aware of the competing forces that have already been
arbitration proceedings was Commonwealth Coatings Corp. v. discussed, we hold that "evident partiality" within the
Continental Casualty Co., et al. 83 decided by the US Supreme Court in meaning of 9 U.S.C. § 10 will be found where a
1968. The Court therein addressed the issue of whether the requirement reasonable person would have to conclude that an
of impartiality applies to an arbitration proceeding. The plurality opinion arbitrator was partial to one party to the
written by Justice Black laid down the rule that the arbitrators must arbitration. . . . 88 (Emphasis supplied)
disclose to the parties "any dealings that might create an impression of
In Apperson v. Fleet Carrier Corporation, 89 the Sixth Circuit reimbursement and the withdrawal of BDO's counterclaims
agreed with the Morelite court's analysis, and accordingly held that to prior to Chairman Barker's December 18, 2007 letter, it is
invalidate an arbitration award on the grounds of bias, the challenging baffling why it is only in the said letter that RCBC's
party must show that "a reasonable person would have to conclude that prayer was given a complexion of being an application
an arbitrator was partial" to the other party to the arbitration. for a partial award. To the Court, the said letter
signaled a preconceived course of action that the
This "myriad of judicial interpretations and approaches to evident
relief prayed for by RCBC will be granted. HaTISE
partiality" resulted in a lack of a uniform standard, leaving the courts "to
examine evident partiality on a case-by-case basis." 90 The case at bar That there was an action to be taken beforehand is
does not present a non-disclosure issue but conduct allegedly showing confirmed by Chairman Barker's furnishing the parties with
an arbitrator's partiality to one of the parties. TAHCEc a copy of the Secomb article. This article ultimately
EPCIB/BDO, in moving to vacate the Second Partial Award favored RCBC by advancing its cause. Chairman
claimed that the Arbitration Tribunal exceeded its powers in deciding the Barker makes it appear that he intended good to be
issue of advance cost not contemplated in the TOR, and that Chairman done in doing so but due process dictates the cold
Barker acted with evident partiality in making such award. The RTC held neutrality of impartiality. This means that "it is not
that BDO failed to substantiate these allegations. On appeal, the CA enough . . . [that] cases [be decided] without bias and
likewise found that the Arbitration Tribunal did not go beyond the favoritism. Nor is it sufficient that . . . prepossessions [be
submission of the parties because the phrasing of the scope of the rid of]. [A]ctuations should moreover inspire that belief."
agreed issues in the TOR ("[t]he issues to be determined by the Tribunal These put into the equation, the furnishing of the Secomb
are those issues arising from the said Request for Arbitration, Answer article further marred the trust reposed in Chairman
and Reply and such other issues as may properly arise during the Barker. The suspicion of his partiality on the subject matter
arbitration") is broad enough to accommodate a finding on the liability deepened. Specifically, his act established that he had pre-
and the repercussions of BDO's failure to share in the advances on formed opinions.
costs. Section 10 of the SPA also gave the Arbitration Tribunal authority Chairman Barker's providing of copies of the said
to decide how the costs should be apportioned between them. text is easily interpretable that he had prejudged the matter
However, the CA found factual support in BDO's charge of before him. In any case, the Secomb article tackled bases
partiality, thus: upon which the Second Partial Award was founded. The
subject article reflected in advance the disposition of
On the issue on evident partiality, the rationale in the ICC arbitral tribunal. The award can definitely be
the American case of Commonwealth Coatings Corp. v. viewed as an affirmation that the bases in the Secomb
Continental Cas. Co. appears to be very prudent. article were adopted earlier on. To the Court, actuations of
In Commonwealth, the United States Supreme Court arbitrators, like the language of judges, "must be guarded
reasoned that courts "should . . . be even more scrupulous and measured lest the best of intentions be misconstrued."
to safeguard the impartiality of arbitrators than judges,
since the former have completely free rein to decide the xxx xxx xxx 91 (Emphasis supplied)
law as well as the facts, and are not subject to appellate
We affirm the foregoing findings and conclusion of the appellate
review" in general. This taken into account, the Court
court save for its reference to the obiter in Commonwealth Coatings that
applies the standard demanded of the conduct of
arbitrators are held to the same standard of conduct imposed on judges.
magistrates by analogy. After all, the ICC Rules require
Instead, the Court adopts the reasonable impression of
that an arbitral tribunal should act fairly and impartially.
partiality standard, which requires a showing that a reasonable person
Hence, an arbitrator's conduct should be beyond
would have to conclude that an arbitrator was partial to the other party to
reproach and suspicion. His acts should be free from
the arbitration. Such interest or bias, moreover, "must be direct, definite
the appearances of impropriety.
and capable of demonstration rather than remote, uncertain, or
An examination of the circumstances claimed to speculative." 92 When a claim of arbitrator's evident partiality is made,
be illustrative of Chairman Barker's partiality is indicative of "the court must ascertain from such record as is available whether the
bias. Although RCBC had repeatedly asked for
arbitrators' conduct was so biased and prejudiced as to destroy the "contractual approach" discussed by Secomb. True enough, RCBC in
fundamental fairness." 93 HICSTa its Application for Reimbursement of Advance Costs Paid utilized said
approach as it singularly focused on Article 30 (3) 97 of the ICC Rules
Applying the foregoing standard, we agree with the CA in finding
and fiercely argued that BDO was contractually bound to share in the
that Chairman Barker's act of furnishing the parties with copies of
advance costs fixed by the ICC. 98 But whether under the "contractual
Matthew Secomb's article, considering the attendant circumstances, is
approach" or "provisional approach" (an application must be treated as
indicative of partiality such that a reasonable man would have to
an interim measure of protection under Article 23 [1] rather than
conclude that he was favoring the Claimant, RCBC. Even before the
enforcement of a contractual obligation), both treated in the Secomb
issuance of the Second Partial Award for the reimbursement of advance
article, RCBC succeeded in availing of a remedy which was not
costs paid by RCBC, Chairman Barker exhibited strong inclination to
expressly allowed by the Rules but in practice has been resorted to by
grant such relief to RCBC, notwithstanding his categorical ruling that the
parties in international commercial arbitration proceedings. It may also be
Arbitration Tribunal "has no power under the ICC Rules to order the
mentioned that the author, Matthew Secomb, is a member of the ICC
Respondents to pay the advance on costs sought by the ICC or to give
Secretariat and the "Counsel in charge of the file", as in fact he signed
the Claimant any relief against the Respondents' refusal to pay." 94 That
some early communications on behalf of the ICC Secretariat pertaining
Chairman Barker was predisposed to grant relief to RCBC was shown by
to the advance costs fixed by the ICC. 99 This bolstered the impression
his act of interpreting RCBC's letter, which merely reiterated its plea to
that Chairman Barker was predisposed to grant relief to RCBC by issuing
declare the Respondents in default and consider all counterclaims
a partial award.
withdrawn — as what the ICC Rules provide — as an application to the
Arbitration Tribunal to issue a partial award in respect of BDO's failure to Indeed, fairness dictates that Chairman Barker refrain from
share in the advance costs. It must be noted that RCBC in said letter did suggesting to or directing RCBC towards a course of action to advance
not contemplate the issuance of a partial order, despite Chairman the latter's cause, by providing it with legal arguments contained in an
Barker's previous letter which mentioned the possibility of granting relief article written by a lawyer who serves at the ICC Secretariat and was
upon the parties making submissions to the Arbitration Tribunal. involved or had participation — insofar as the actions or
Expectedly, in compliance with Chairman Barker's December 18, 2007 recommendations of the ICC — in the case. Though done purportedly to
letter, RCBC formally applied for the issuance of a partial award ordering assist both parties, Chairman Barker's act clearly violated Article 15 of
BDO to pay its share in the advance costs. the ICC Rules declaring that "[i]n all cases, the Arbitral Tribunal shall act
fairly and impartially and ensure that each party has a reasonable
Mr. Secomb's article, "Awards and Orders Dealing with the
opportunity to present its case." Having pre-judged the matter in dispute,
Advance on Costs in ICC Arbitration: Theoretical Questions and
Chairman Barker had lost his objectivity in the issuance of the Second
Practical Problems" 95 specifically dealt with the situation when one of
Partial Award.
the parties to international commercial arbitration refuses to pay its share
on the advance on costs. After a brief discussion of the provisions of ICC In fine, we hold that the CA did not err in concluding that the
Rules dealing with advance on costs, which did not provide for issuance article ultimately favored RCBC as it reflected in advance the disposition
of a partial award to compel payment by the defaulting party, the author of the Arbitral Tribunal, as well as "signalled a preconceived course of
stated: action that the relief prayed for by RCBC will be granted." This
conclusion is further confirmed by the Arbitral Tribunal's pronouncements
4. As we can see, the Rules have certain mechanisms to
in its Second Partial Award which not only adopted the "contractual
deal with defaulting parties. Occasionally, however,
approach" but even cited Secomb's article along with other references,
parties have sought to use other methods to tackle the
thus: CScaDH
problem of a party refusing to pay its part of the advance
on costs. These have included seeking an order or 6.1 It appears to the Tribunal that the issue posed by this
award from the arbitral tribunal condemning the application is essentially a contractual one. . . .
defaulting party to pay its share of the advance on costs.
Such applications are the subject of this xxx xxx xxx
article. 96 acSECT 6.5 Matthew Secomb, considered these points in the
By furnishing the parties with a copy of this article, Chairman article in 14 ICC Bulletin No. 1 (2003) which was
Barker practically armed RCBC with supporting legal arguments under sent to the parties. At Para. 19, the learned author
quoted from an ICC Tribunal (Case No. 11330) as that there is an urgent and paramount necessity for the writ to prevent a
follows: serious damage. 105
"The Arbitral Tribunal concludes that the Rule 19.22 of the Special ADR Rules states:
parties in arbitrations conducted under Rule 19.22. Effect of appeal. — The appeal shall not stay
the ICC Rules have a mutually binding the award, judgment, final order or resolution sought to be
obligation to pay the advance on costs reviewed unless the Court of Appeals directs otherwise
as determined by the ICC Court, based upon such terms as it may deem just.
on Article 30-3 ICC Rules which — by
reference — forms part of the parties' We find no reversible error or grave abuse of discretion in the
agreement to arbitration under such CA's denial of the application for stay order or TRO upon its finding that
Rules." 100 BDO failed to establish the existence of a clear legal right to enjoin
execution of the Final Award confirmed by the Makati City RTC, Branch
The Court, however, must clarify that the merits of the parties' 148, pending resolution of its appeal. It would be premature to address
arguments as to the propriety of the issuance of the Second Partial on the merits the issues raised by BDO in the present petition
Award are not in issue here. Courts are generally without power to considering that the CA still has to decide on the validity of said court's
amend or overrule merely because of disagreement with matters of law orders confirming the Final Award. But more important, since BDO had
or facts determined by the arbitrators. They will not review the findings of already paid P637,941,185.55 in manager's check, albeit under protest,
law and fact contained in an award, and will not undertake to substitute and which payment was accepted by RCBC as full and complete
their judgment for that of the arbitrators. A contrary rule would make an satisfaction of the writ of execution, there is no more act to be enjoined.
arbitration award the commencement, not the end, of litigation. 101 It is
the finding of evident partiality which constitutes legal ground for vacating Settled is the rule that injunctive reliefs are preservative
the Second Partial Award and not the Arbitration Tribunal's application of remedies for the protection of substantive rights and interests. Injunction
the ICC Rules adopting the "contractual approach" tackled in Secomb's is not a cause of action in itself, but merely a provisional remedy, an
article. adjunct to a main suit. When the act sought to be enjoined has
become fait accompli, the prayer for provisional remedy should be
Alternative dispute resolution methods or ADRs — like denied. 106
arbitration, mediation, negotiation and conciliation — are encouraged by
this Court. By enabling parties to resolve their disputes amicably, they Thus, the Court ruled in Go v. Looyuko 107 that when the events
provide solutions that are less time-consuming, less tedious, less sought to be prevented by injunction or prohibition have already
confrontational, and more productive of goodwill and lasting happened, nothing more could be enjoined or prohibited. Indeed, it is a
relationship. 102 Institutionalization of ADR was envisioned as "an universal principle of law that an injunction will not issue to restrain the
important means to achieve speedy and impartial justice and declog performance of an act already done. This is so for the simple reason that
court dockets." 103 The most important feature of arbitration, and indeed, nothing more can be done in reference thereto. A writ of injunction
the key to its success, is the public's confidence and trust in the integrity becomes moot and academic after the act sought to be enjoined has
of the process. 104 For this reason, the law authorizes vacating an already been consummated. ADTCaI
arbitral award when there is evident partiality in the arbitrators. aAcHCT WHEREFORE, premises considered, the petition in G.R. No.
Injunction Against Execution 199238 is DENIED. The Resolution dated September 13, 2011 of the
of Arbitral Award Court of Appeals in CA-G.R. SP No. 120888 is AFFIRMED.
Before an injunctive writ can be issued, it is essential that the The petition in G.R. No. 196171 is DENIED. The Decision dated
following requisites are present: (1) there must be a right inesse or the December 23, 2010 of the Court of Appeals in CA-G.R. SP No. 113525
existence of a right to be protected; and (2) the act against which is hereby AFFIRMED.
injunction to be directed is a violation of such right. The onus probandi is SO ORDERED.
on movant to show that there exists a right to be protected, which is
directly threatened by the act sought to be enjoined. Further, there must
be a showing that the invasion of the right is material and substantial and
SECOND DIVISION 1. The period of the lease is for twenty-five (25)
years, 10 or until the 25th of May 2000;
[G.R. No. 198075. September 4, 2013.] 2. The amount of rent to be paid by FKI for the first twenty-
five (25) years is P40,126.00 per annum. 11
KOPPEL, INC. (formerly known as KPL AIRCON, The Deed of Donationalso stipulated that the lease over the subject
INC.), petitioner, vs. MAKATI ROTARY CLUB property is renewable for another period of twenty-five (25) years "upon
FOUNDATION, INC., respondent. mutual agreement" of FKI and the respondent. 12 In which case, the amount
of rent shall be determined in accordance with item 2 (g) of the Deed of
Donation, viz.:
DECISION g. The rental for the second 25 years shall be the
subject of mutual agreement and in case of disagreement
the matter shall be referred to a Board of three Arbitrators
appointed and with powers in accordance with the
PEREZ, J p: Arbitration Law of the Philippines, Republic Act 878, whose
function shall be to decide the current fair market value of
This case is an appeal 1 from the Decision 2 dated 19 August 2011 the land excluding the improvements, provided, that, any
of the Court of Appeals in C.A.-G.R. SP No. 116865. increase in the fair market value of the land shall not
exceed twenty five percent (25%) of the original value of
The facts:
the land donated as stated in paragraph 2(c) of this Deed.
The Donation The rental for the second 25 years shall not exceed three
percent (3%) of the fair market value of the land excluding
Fedders Koppel, Incorporated (FKI), a manufacturer of air-
the improvements as determined by the Board of
conditioning products, was the registered owner of a parcel of land located at
Arbitrators. 13
Km. 16, South Superhighway, Parañaque City (subject land). 3 Within the
subject land are buildings and other improvements dedicated to the business In October 1976, FKI and the respondent executed an Amended
of FKI. 4 Deed of Donation 14 that reiterated the provisions of the Deed of Donation,
including those relating to the lease of the subject land.
In 1975, FKI 5 bequeathed the subject land (exclusive of the
improvements thereon) in favor of herein respondent Makati Rotary Club Verily, by virtue of the lease agreement contained in the Deed of
Foundation, Incorporated by way of a conditional donation. 6 The respondent Donation and Amended Deed of Donation, FKI was able to continue in its
accepted the donation with all of its conditions. 7 On 26 May 1975, FKI and possession and use of the subject land.
the respondent executed a Deed of Donation 8 evidencing their
consensus. DHcSIT 2000 Lease Contract
Two (2) days before the lease incorporated in the Deed of
The Lease and the Amended Deed of Donation
Donation and Amended Deed of Donation was set to expire, or on 23 May
One of the conditions of the donation required the respondent to 2000, FKI and respondent executed another contract of lease (2000 Lease
lease the subject land back to FKI under terms specified in their Deed of Contract) 15 covering the subject land. In this 2000 Lease Contract, FKI and
Donation. 9 With the respondent's acceptance of the donation, a lease respondent agreed on a new five-year lease to take effect on the 26th of May
agreement between FKI and the respondent was, therefore, effectively 2000, with annual rents ranging from P4,000,000 for the first year up to
incorporated in the Deed of Donation. P4,900,000 for the fifth year. 16
Pertinent terms of such lease agreement, as provided in the Deed of
Donation, were as follows:
The 2000 Lease Contract also contained an arbitration clause wherein FKI, with the conformity of the respondent, formally assigned all of
enforceable in the event the parties come to disagreement about its interests and obligations under the Amended Deed of Donation and
the "interpretation, application and execution" of the lease, viz.: EcAHDT the 2005 Lease Contract in favor of petitioner. EDcICT
19. Governing Law — The provisions of this [2000 The following year, petitioner discontinued the payment of the rent
Lease Contract] shall be governed, interpreted and and "donation" under the 2005 Lease Contract.
construed in all aspects in accordance with the laws of the
Republic of the Philippines. Petitioner's refusal to pay such rent and "donation" emanated from
its belief that the rental stipulations of the 2005 Lease Contract, and even of
Any disagreement as to the interpretation, the 2000 Lease Contract, cannot be given effect because they violated one
application or execution of this [2000 Lease Contract] of the "material conditions" of the donation of the subject land, as stated in
shall be submitted to a board of three (3) arbitrators the Deed of Donation and Amended Deed of Donation. 26
constituted in accordance with the arbitration law of
the Philippines. The decision of the majority of the According to petitioner, the Deed of Donation and Amended Deed of
arbitrators shall be binding upon [FKI and Donation actually established not only one but two (2) lease agreements
respondent]. 17 (Emphasis supplied) between FKI and respondent, i.e., one lease for the first twenty-five (25)
years or from 1975 to 2000, and another lease for the next twenty-five (25)
2005 Lease Contract years thereafter or from 2000 to 2025. 27 Both leases are material conditions
of the donation of the subject land.
After the 2000 Lease Contract expired, FKI and respondent agreed
to renew their lease for another five (5) years. This new lease (2005 Lease Petitioner points out that while a definite amount of rent for the
Contract) 18 required FKI to pay a fixed annual rent of P4,200,000. 19 In second twenty-five (25) year lease was not fixed in the Deed of
addition to paying the fixed rent, however, the 2005 Lease Contract also Donation and Amended Deed of Donation, both deeds nevertheless
obligated FKI to make a yearly "donation" of money to the prescribed rules and limitations by which the same may be determined. Such
respondent. 20 Such donations ranged from P3,000,000 for the first year up rules and limitations ought to be observed in any succeeding lease
to P3,900,000 for the fifth year. 21 agreements between petitioner and respondent for they are, in themselves,
material conditions of the donation of the subject land. 28
Notably, the 2005 Lease Contract contained an arbitration clause
similar to that in the 2000 Lease Contract, to wit: In this connection, petitioner cites item 2 (g) of the Deed of
Donation and Amended Deed of Donation that supposedly limits the amount
19. Governing Law — The provisions of this [2005
of rent for the lease over the second twenty-five (25) years to only "three
Lease Contract] shall be governed, interpreted and
percent (3%) of the fair market value of the [subject] land excluding the
construed in all aspects in accordance with the laws of the
improvements." 29
Republic of the Philippines.
For petitioner then, the rental stipulations of both the 2000 Lease
Any disagreement as to the interpretation,
Contract and 2005 Lease Contract cannot be enforced as they are clearly, in
application or execution of this [2005 Lease Contract]
view of their exorbitant exactions, in violation of the aforementioned threshold
shall be submitted to a board of three (3) arbitrators
in item 2 (g) of the Deed of Donation and Amended Deed of Donation.
constituted in accordance with the arbitration law of
Consequently, petitioner insists that the amount of rent it has to pay thereon
the Philippines. The decision of the majority of the
is and must still be governed by the limitations prescribed in the Deed of
arbitrators shall be binding upon [FKI and
Donation and Amended Deed of Donation. 30 cIECaS
respondent]. 22 (Emphasis supplied)
The Demand Letters
The Assignment and Petitioner's Refusal to Pay
On 1 June 2009, respondent sent a letter (First Demand Letter) 31 to
From 2005 to 2008, FKI faithfully paid the rentals
petitioner notifying the latter of its default "per Section 12 of the [2005 Lease
and "donations" due it per the 2005 Lease Contract. 23 But in June of 2008,
Contract]" and demanding for the settlement of the rent and "donation" due
FKI sold all its rights and properties relative to its business in favor of herein
for the year 2009. Respondent, in the same letter, further intimated of
petitioner Koppel, Incorporated. 24 On 29 August 2008, FKI and petitioner
cancelling the 2005 Lease Contract should petitioner fail to settle the said
executed an Assignment and Assumption of Lease and Donation 25 —
obligations. 32 Petitioner received the First Demand Letter on 2 June and, therefore, the refusal to comply therewith
2009. 33 does not give rise to an action for unlawful
detainer. 47
On 22 September 2009, petitioner sent a reply 34 to respondent
expressing its disagreement over the rental stipulations of the 2005 Lease 2. Assuming that the MeTC was able to acquire
Contract — calling them "severely disproportionate," jurisdiction, it may not exercise the same until the
"unconscionable" and "in clear violation to the nominal rentals mandated by disagreement between the parties is first referred
the Amended Deed of Donation." In lieu of the amount demanded by the to arbitration pursuant to the arbitration clause of
respondent, which purportedly totaled to P8,394,000.00, exclusive of the 2005 Lease Contract. 48
interests, petitioner offered to pay only P80,502.79, 35 in accordance with
the rental provisions of the Deed of Donation and Amended Deed of 3. Assuming further that the MeTC has jurisdiction that it
Donation. 36 Respondent refused this offer. 37 can exercise, ejectment still would not lie as
the 2005 Lease Contract is void ab initio. 49 The
On 25 September 2009, respondent sent another letter (Second stipulation in the 2005 Lease Contract requiring
Demand Letter) 38 to petitioner, reiterating its demand for the payment of the petitioner to give yearly "donations" to respondent
obligations already due under the 2005 Lease Contract. The Second is a simulation, for they are, in fact, parts of the
Demand Letter also contained a demand for petitioner to "immediately rent. 50 Such grants were only denominated
vacate the leased premises" should it fail to pay such obligations within as "donations" in the contract so that the
seven (7) days from its receipt of the letter. 39 The respondent warned of respondent — a non-stock and non-profit
taking "legal steps" in the event that petitioner failed to comply with any of corporation — could evade payment of the taxes
the said demands. 40 Petitioner received the Second Demand Letter on 26 otherwise due thereon. 51
September 2009. 41
In due course, petitioner and respondent both submitted their
Petitioner refused to comply with the demands of the respondent. position papers, together with their other documentary
Instead, on 30 September 2009, petitioner filed with the Regional Trial Court evidence. 52 Remarkably, however, respondent failed to submit the Second
(RTC) of Parañaque City a complaint 42 for the rescission or cancellation of Demand Letter as part of its documentary evidence.
the Deed of Donation and Amended Deed of Donation against the
respondent. This case is currently pending before Branch 257 of the RTC, Rulings of the MeTC, RTC and Court of Appeals
docketed as Civil Case No. CV 09-0346. On 27 April 2010, the MeTC rendered judgment 53 in favor of the
petitioner. While the MeTC refused to dismiss the action on the ground that
The Ejectment Suit the dispute is subject to arbitration, it nonetheless sided with the petitioner
On 5 October 2009, respondent filed an unlawful detainer with respect to the issues regarding the insufficiency of the respondent's
case 43 against the petitioner before the Metropolitan Trial Court (MeTC) of demand and the nullity of the 2005 Lease Contract. 54 The MeTC thus
Parañaque City. The ejectment case was raffled to Branch 77 and was disposed: DcCIAa
docketed as Civil Case No. 2009-307. DTEScI
WHEREFORE, judgment is hereby rendered
On 4 November 2009, petitioner filed an Answer with Compulsory dismissing the case . . ., without pronouncement as to
Counterclaim. 44 In it, petitioner reiterated its objection over the rental costs.
stipulations of the 2005 Lease Contract for being violative of the material
conditions of the Deed of Donation and Amended Deed of Donation. 45 In SO ORDERED. 55
addition to the foregoing, however, petitioner also interposed the following The respondent appealed to the Regional Trial Court (RTC). This
defenses: appeal was assigned to Branch 274 of the RTC of Parañaque City and was
1. The MeTC was not able to validly acquire jurisdiction docketed as Civil Case No. 10-0255.
over the instant unlawful detainer case in view of On 29 October 2010, the RTC reversed 56 the MeTC and ordered
the insufficiency of respondent's the eviction of the petitioner from the subject land:
demand. 46 The First Demand Letter did not
contain an actual demand to vacate the premises
WHEREFORE, all the foregoing duly considered, still did not file a formal application before the
the appealed Decision of the Metropolitan Trial Court, MeTC so as to render such arbitration clause
Branch 77, Parañaque City, is hereby reversed, judgment operational. 62 At any rate, the MeTC would not
is thus rendered in favor of the plaintiff-appellant and be precluded from exercising its jurisdiction over
against the defendant-appellee, and ordering the latter — an action for unlawful detainer, over which, it has
exclusive original jurisdiction. 63
(1) to vacate the lease[d] premises made subject of the
case and to restore the possession thereof to the 3. The 2005 Lease Contract must be sustained as a valid
plaintiff-appellant; contract since petitioner was not able to adduce
any evidence to support its allegation that the
(2) to pay to the plaintiff-appellant the amount of Nine same is void. 64 There was, in this case, no
Million Three Hundred Sixty Two Thousand Four evidence that respondent is guilty of any tax
Hundred Thirty Six Pesos (P9,362,436.00), evasion. 65
penalties and net of 5% withholding tax, for the
lease period from May 25, 2009 to May 25, 2010 Aggrieved, the petitioner appealed to the Court of Appeals.
and such monthly rental as will accrue during the
pendency of this case; On 19 August 2011, the Court of Appeals affirmed 66 the decision of
the RTC:
(3) to pay attorney's fees in the sum of P100,000.00 plus
appearance fee of P3,000.00; WHEREFORE, the petition is DENIED. The
assailed Decision of the Regional Trial Court of Parañaque
(4) and costs of suit. City, Branch 274, in Civil Case No. 10-0255 is AFFIRMED.
As to the existing improvements belonging to xxx xxx xxx
the defendant-appellee, as these were built in good
faith, the provisions of Art. 1678 of the Civil Code shall SO ORDERED. 67
apply. Hence, this appeal. ACEIac
SO ORDERED. 57 DCcHAa On 5 September 2011, this Court granted petitioner's prayer for the
The ruling of the RTC is premised on the following ratiocinations: issuance of a Temporary Restraining Order 68 staying the immediate
implementation of the decisions adverse to it.
1. The respondent had adequately complied with the
requirement of demand as a jurisdictional OUR RULING
precursor to an unlawful detainer Independently of the merits of the case, the MeTC, RTC and Court of
actions. 58 The First Demand Letter, in substance, Appeals all erred in overlooking the significance of the arbitration clause
contains a demand for petitioner to vacate when it incorporated in the 2005 Lease Contract. As the Court sees it, that is a fatal
mentioned that it was a notice "per Section 12 of mistake.
the [2005 Lease Contract]." 59 Moreover, the
issue of sufficiency of the respondent's demand For this reason, We grant the petition.
ought to have been laid to rest by the Second Present Dispute is Arbitrable Under the
Demand Letter which, though not submitted in Arbitration Clause of the 2005 Lease
evidence, was nonetheless admitted by petitioner Agreement Contract
as containing a "demand to eject" in its Answer
with Compulsory Counterclaim. 60 Going back to the records of this case, it is discernable that the
dispute between the petitioner and respondent emanates from the rental
2. The petitioner cannot validly invoke the arbitration stipulations of the 2005 Lease Contract. The respondent insists upon the
clause of the 2005 Lease Contract while, at the enforceability and validity of such stipulations, whereas, petitioner, in
same time, impugn such contract's substance, repudiates them. It is from petitioner's apparent breach of
validity. 61 Even assuming that it can, petitioner
the 2005 Lease Contract that respondent filed the instant unlawful detainer 1. The disagreement between the petitioner and
action. respondent is non-arbitrable as it will inevitably
touch upon the issue of the validity of the 2005
One cannot escape the conclusion that, under the foregoing Lease Contract. 71 It was submitted that one of
premises, the dispute between the petitioner and respondent arose from the reasons offered by the petitioner in justifying its
the application or execution of the 2005 Lease Contract. Undoubtedly, such failure to pay under the 2005 Lease Contract was
kinds of dispute are covered by the arbitration clause of the 2005 Lease the nullity of such contract for being contrary to law
Contract to wit: and public policy. 72 The Supreme Court,
19. Governing Law — The provisions of this [2005 in Gonzales v. Climax Mining, Ltd., 73 held
Lease Contract] shall be governed, interpreted and that "the validity of contract cannot be subject of
construed in all aspects in accordance with the laws of the arbitration proceedings" as such questions
Republic of the Philippines. are "legal in nature and require the application and
interpretation of laws and jurisprudence which is
Any disagreement as to the interpretation, necessarily a judicial function." 74
application or execution of this [2005 Lease Contract]
shall be submitted to a board of three (3) arbitrators 2. The petitioner cannot validly invoke the arbitration
constituted in accordance with the arbitration law of clause of the 2005 Lease Contract while, at the
the Philippines. The decision of the majority of the same time, impugn such contract's validity. 75
arbitrators shall be binding upon [FKI and 3. Even assuming that it can invoke the arbitration clause
respondent]. 69 (Emphasis supplied) whilst denying the validity of the 2005 Lease
The arbitration clause of the 2005 Lease Contract stipulates Contract, petitioner still did not file a formal
that "any disagreement" as to the "interpretation, application or execution" of application before the MeTC so as to render such
the 2005 Lease Contract ought to be submitted to arbitration. 70 To the mind arbitration clause operational. 76 Section 24 of
of this Court, such stipulation is clear and is comprehensive enough so as to Republic Act No. 9285 requires the party seeking
include virtually any kind of conflict or dispute that may arise from the 2005 arbitration to first file a "request" or an application
Lease Contract including the one that presently besets petitioner and therefor with the court not later than the
respondent. preliminary conference. 77
The application of the arbitration clause of the 2005 Lease 4. Petitioner and respondent already underwent Judicial
Contract in this case carries with it certain legal effects. However, before Dispute Resolution (JDR) proceedings before the
discussing what these legal effects are, We shall first deal with the RTC. 78 Hence, a further referral of the dispute to
challenges posed against the application of such arbitration clause. HcSCED arbitration would only be circuitous. 79 Moreover,
an ejectment case, in view of its summary nature,
Challenges Against the Application of the already fulfills the prime purpose of arbitration, i.e.,
Arbitration Clause of the 2005 Lease to provide parties in conflict with an expedient
Contract method for the resolution of their
Curiously, despite the lucidity of the arbitration clause of the 2005 dispute. 80 Arbitration then would no longer be
Lease Contract, the petitioner, as well as the MeTC, RTC and the Court of necessary in this case. 81
Appeals, vouched for the non-application of the same in the instant case. A None of the arguments have any merit.
plethora of arguments was hurled in favor of bypassing arbitration. We now
address them. First. As highlighted in the previous discussion, the disagreement
between the petitioner and respondent falls within the all-encompassing
At different points in the proceedings of this case, the following terms of the arbitration clause of the 2005 Lease Contract. While it may be
arguments were offered against the application of the arbitration clause of conceded that in the arbitration of such disagreement, the validity of
the 2005 Lease Contract: the 2005 Lease Contract, or at least, of such contract's rental stipulations
would have to be determined, the same would not render such disagreement
non-arbitrable. The quotation from Gonzales that was used to justify the the ruling was the limitation that was placed by R.A. No. 7942 upon the
contrary position was taken out of context. A rereading of Gonzales would fix jurisdiction of the PA-MGB as an arbitral body. Gonzales rejected the
its relevance to this case. AcIaST complaint for arbitration because the issue raised therein is not a mining
dispute per R.A. No. 7942 and it is for this reason, and only for this reason,
In Gonzales, a complaint for arbitration was filed before the Panel of that such issue is rendered non-arbitrable before the PA-MGB. As stated
Arbitrators of the Mines and Geosciences Bureau (PA-MGB) seeking the beforehand, R.A. No. 7942 clearly limited the jurisdiction of the PA-MGB only
nullification of a Financial Technical Assistance Agreement and other mining to mining disputes. 87
related agreements entered into by private parties. 82 Grounds invoked for
the nullification of such agreements include fraud and Much more instructive for our purposes, on the other hand, is the
unconstitutionality. 83 The pivotal issue that confronted the Court then was recent case of Cargill Philippines, Inc. v. San Fernando Regal Trading,
whether the PA-MGB has jurisdiction over that particular arbitration Inc. 88 In Cargill, this Court answered the question of whether issues
complaint. Stated otherwise, the question was whether the complaint for involving the rescission of a contract are arbitrable. The respondent
arbitration raises arbitrable issues that the PA-MGB can take cognizance of. in Cargill argued against arbitrability, also citing therein Gonzales. After
dissecting Gonzales, this Court ruled in favor of arbitrability. 89 Thus, We
Gonzales decided the issue in the negative. In holding that the PA- held:
MGB was devoid of any jurisdiction to take cognizance of the complaint for
arbitration, this Court pointed out to the provisions of R.A. No. 7942, or the Respondent contends that assuming that the existence
Mining Act of 1995, which granted the PA-MGB with exclusive original of the contract and the arbitration clause is conceded,
jurisdiction only over mining disputes, i.e., disputes involving "rights to mining the CA's decision declining referral of the parties' dispute
areas," "mineral agreements or permits," and "surface owners, occupants, to arbitration is still correct. It claims that its complaint in
claimholders or concessionaires" requiring the technical knowledge and the RTC presents the issue of whether under the facts
experience of mining authorities in order to be resolved. 84 Accordingly, alleged, it is entitled to rescind the contract with
since the complaint for arbitration in Gonzales did not raise mining damages; and that issue constitutes a judicial question
disputes as contemplated under R.A. No. 7942 but only issues relating to the or one that requires the exercise of judicial function and
validity of certain mining related agreements, this Court held that such cannot be the subject of an arbitration proceeding.
complaint could not be arbitrated before the PA-MGB. 85 It is in this context Respondent cites our ruling in Gonzales, wherein we
that we made the pronouncement now in discussion: held that a panel of arbitrator is bereft of jurisdiction over
the complaint for declaration of nullity/or termination of
Arbitration before the Panel of Arbitrators is proper only the subject contracts on the grounds of fraud and
when there is a disagreement between the parties as to oppression attendant to the execution of the addendum
some provisions of the contract between them, which contract and the other contracts emanating from it, and
needs the interpretation and the application of that that the complaint should have been filed with the
particular knowledge and expertise possessed by regular courts as it involved issues which are judicial in
members of that Panel. It is not proper when one of the nature.
parties repudiates the existence or validity of such
contract or agreement on the ground of fraud or Such argument is misplaced and respondent cannot
oppression as in this case. The validity of the contract rely on the Gonzales case to support its
cannot be subject of arbitration proceedings. argument. 90 (Emphasis ours)
Allegations of fraud and duress in the execution of a
contract are matters within the jurisdiction of the ordinary Second. Petitioner may still invoke the arbitration clause of the 2005
courts of law. These questions are legal in nature and Lease Contract notwithstanding the fact that it assails the validity of such
require the application and interpretation of laws and contract. This is due to the doctrine of separability. 91 EcTCAD
jurisprudence which is necessarily a judicial Under the doctrine of separability, an arbitration agreement is
function. 86 (Emphasis supplied) CDTHSI considered as independent of the main contract. 92 Being a separate
The Court in Gonzalesdid not simply base its rejection of the contract in itself, the arbitration agreement may thus be invoked regardless of
complaint for arbitration on the ground that the issue raised therein, i.e., the the possible nullity or invalidity of the main contract. 93
validity of contracts, is per se non-arbitrable. The real consideration behind
Once again instructive is Cargill, wherein this Court held that, as a Rule 4.3. Contents of request. — The request for referral
further consequence of the doctrine of reparability, even the very party who shall be in the form of a motion, which shall state that the
repudiates the main contract may invoke its arbitration clause. 94 dispute is covered by an arbitration agreement.
Third. The operation of the arbitration clause in this case is not at all Apart from other submissions, the movant shall attach to
defeated by the failure of the petitioner to file a formal "request" or his motion an authentic copy of the arbitration
application therefor with the MeTC. We find that the filing of agreement.
a "request" pursuant to Section 24 of R.A. No. 9285 is not the sole means by
which an arbitration clause may be validly invoked in a pending suit. The request shall contain a notice of hearing addressed
to all parties specifying the date and time when it would
Section 24 of R.A. No. 9285 reads: be heard. The party making the request shall serve it
upon the respondent to give him the opportunity to file a
SEC. 24. Referral to Arbitration. — A court before comment or opposition as provided in the immediately
which an action is brought in a matter which is the succeeding Rule before the hearing. [Emphasis ours;
subject matter of an arbitration agreement shall, if at italics original]
least one party so requests not later that the pre-trial
conference, or upon the request of both parties Attention must be paid, however, to the salient wordings of Rule 4.1.
thereafter, refer the parties to arbitration unless it finds It reads: "[a] party to a pending action filed in violation of the arbitration
that the arbitration agreement is null and void, agreement . . . may request the court to refer the parties to arbitration in
inoperative or incapable of being performed. [Emphasis accordance with such agreement."
ours; italics original]
In using the word "may" to qualify the act of filing a "request" under
The "request" referred to in the above provision is, in turn, implemented Section 24 of R.A. No. 9285, the Special ADR Rules clearly did not intend to
by Rules 4.1 to 4.3 of A.M. No. 07-11-08-SC or the Special Rules of limit the invocation of an arbitration agreement in a pending suit
Court on Alternative Dispute Resolution (Special ADR Rules): solely via such "request." After all, non-compliance with an arbitration
agreement is a valid defense to any offending suit and, as such, may even be
RULE 4: REFERRAL TO ADR
raised in an answer as provided in our ordinary rules of
Rule 4.1. Who makes the request. — A party to a procedure. 95 HIaTDS
pending action filed in violation of the arbitration
In this case, it is conceded that petitioner was not able to file a
agreement, whether contained in an arbitration clause or
separate "request" of arbitration before the MeTC. However, it is equally
in a submission agreement, may request the court to
conceded that the petitioner, as early as in its Answer with Counterclaim, had
refer the parties to arbitration in accordance with such
already apprised the MeTC of the existence of the arbitration clause in
agreement. cCHITA
the 2005 Lease Contract 96 and, more significantly, of its desire to have the
Rule 4.2. When to make request. — (A) Where the same enforced in this case. 97 This act of petitioner is enough valid
arbitration agreement exists before the action is filed. — invocation of his right to arbitrate.
The request for referral shall be made not later than the
Fourth. The fact that the petitioner and respondent already
pre-trial conference. After the pre-trial conference, the
underwent through JDR proceedings before the RTC, will not make the
court will only act upon the request for referral if it is
subsequent conduct of arbitration between the parties unnecessary or
made with the agreement of all parties to the case.
circuitous. The JDR system is substantially different from arbitration
(B)Submission agreement. — If there is no existing proceedings.
arbitration agreement at the time the case is filed but the
The JDR framework is based on the processes of mediation,
parties subsequently enter into an arbitration agreement,
conciliation or early neutral evaluation which entails the submission of a
they may request the court to refer their dispute to
dispute before a "JDR judge" who shall merely "facilitate
arbitration at any time during the proceedings.
settlement" between the parties in conflict or make a "non-binding evaluation
or assessment of the chances of each party's case." 98 Thus in JDR, the
JDR judge lacks the authority to render a resolution of the dispute that is
binding upon the parties in conflict. In arbitration, on the other hand, the action or proceeding until an arbitration has been
dispute is submitted to an arbitrator/s — a neutral third person or a group of had in accordance with the terms of the agreement:
thereof — who shall have the authority to render a resolution binding upon Provided, That the applicant for the stay is not in default
the parties. 99 in proceeding with such arbitration. [Emphasis supplied]
Clearly, the mere submission of a dispute to JDR proceedings R.A. No. 9285
would not necessarily render the subsequent conduct of arbitration a mere
surplusage. The failure of the parties in conflict to reach an amicable Section 24. Referral to Arbitration. — A court before
settlement before the JDR may, in fact, be supplemented by their resort to which an action is brought in a matter which is the
arbitration where a binding resolution to the dispute could finally be achieved. subject matter of an arbitration agreement shall, if at
This situation precisely finds application to the case at bench. least one party so requests not later that the pre-trial
conference, or upon the request of both parties
Neither would the summary nature of ejectment cases be a valid thereafter, refer the parties to arbitration unless it finds
reason to disregard the enforcement of the arbitration clause of the 2005 that the arbitration agreement is null and void,
Lease Contract. Notwithstanding the summary nature of ejectment cases, inoperative or incapable of being performed. [Emphasis
arbitration still remains relevant as it aims not only to afford the parties an supplied] CSAcTa
expeditious method of resolving their dispute. CIScaA
It is clear that under the law, the instant unlawful detainer action
A pivotal feature of arbitration as an alternative mode of dispute should have been stayed; 101 the petitioner and the respondent should have
resolution is that it is, first and foremost, a product of party autonomy or the been referred to arbitration pursuant to the arbitration clause of the 2005
freedom of the parties to "make their own arrangements to resolve their own Lease Contract. The MeTC, however, did not do so in violation of the law —
disputes." 100 Arbitration agreements manifest not only the desire of the which violation was, in turn, affirmed by the RTC and Court of Appeals on
parties in conflict for an expeditious resolution of their dispute. They also appeal.
represent, if not more so, the parties' mutual aspiration to achieve such
resolution outside of judicial auspices, in a more informal and less The violation by the MeTC of the clear directives under R.A. Nos.
antagonistic environment under the terms of their choosing. Needless to 876 and 9285 renders invalid all proceedings it undertook in the ejectment
state, this critical feature can never be satisfied in an ejectment case no case after the filing by petitioner of its Answer with Counterclaim — the point
matter how summary it may be. when the petitioner and the respondent should have been referred to
arbitration. This case must, therefore, be remanded to the MeTC and be
Having hurdled all the challenges against the application of the suspended at said point. Inevitably, the decisions of the MeTC, RTC and the
arbitration clause of the 2005 Lease Agreement in this case, We shall now Court of Appeals must all be vacated and set aside.
proceed with the discussion of its legal effects.
The petitioner and the respondent must then be referred to
Legal Effect of the Application of the arbitration pursuant to the arbitration clause of the 2005 Lease Contract.
Arbitration Clause
This Court is not unaware of the apparent harshness of the Decision
Since there really are no legal impediments to the application of the that it is about to make. Nonetheless, this Court must make the same if only
arbitration clause of the2005 Contract of Lease in this case, We find that the to stress the point that, in our jurisdiction, bona fide arbitration agreements
instant unlawful detainer action was instituted in violation of such clause. The are recognized as valid; 102 and that laws, 103 rules and regulations 104 do
Law, therefore, should have governed the fate of the parties and this suit: exist protecting and ensuring their enforcement as a matter of state policy.
Gone should be the days when courts treat otherwise valid arbitration
R.A. No. 876
agreements with disdain and hostility, if not outright "jealousy," 105 and then
Section 7. Stay of civil action. — If any suit or get away with it. Courts should instead learn to treat alternative means of
proceeding be brought upon an issue arising out of an dispute resolution as effective partners in the administration of justice and, in
agreement providing for the arbitration thereof, the court the case of arbitration agreements, to afford them judicial
in which such suit or proceeding is pending, upon being restraint. 106 Today, this Court only performs its part in upholding a once
satisfied that the issue involved in such suit or disregarded state policy.
proceeding is referable to arbitration, shall stay the
Civil Case No. CV 09-0346
This Court notes that, on 30 September 2009, petitioner filed with the Let a copy of this Decision be served to Branch 257 of the RTC of
RTC of Parañaque City, a complaint 107 for the rescission or cancellation of Parañaque for its consideration and, possible, application to Civil Case No.
the Deed of Donation and Amended Deed of Donation against the CV 09-0346.
respondent. The case is currently pending before Branch 257 of the RTC,
docketed as Civil Case No. CV 09-0346. IcTaAH No costs.
This Court recognizes the great possibility that issues raised in Civil SO ORDERED.
Case No. CV 09-0346 may involve matters that are rightfully arbitrable per
the arbitration clause of the 2005 Lease Contract. However, since the
records of Civil Case No. CV 09-0346 are not before this Court, We can
never know with true certainty and only speculate.
In this light, let a copy of this Decision be also served to Branch 257
of the RTC of Parañaque for its consideration and, possible, application to
Civil Case No. CV 09-0346.
WHEREFORE, premises considered, the petition is
hereby GRANTED. Accordingly, We hereby render a Decision:
1. SETTING ASIDE all the proceedings undertaken by
the Metropolitan Trial Court, Branch 77, of
Parañaque City in relation to Civil Case No. 2009-
307 after the filing by petitioner of its Answer with
Counterclaim;
2. REMANDING the instant case to the
MeTC, SUSPENDED at the point after the filing by
petitioner of its Answer with Counterclaim;
3. SETTING ASIDE the following:
a. Decision dated 19 August 2011 of the Court of
Appeals in C.A.-G.R. SP No. 116865,
b. Decision dated 29 October 2010 of the Regional
Trial Court, Branch 274, of Parañaque City
in Civil Case No. 10-0255,
c. Decision dated 27 April 2010 of the Metropolitan
Trial Court, Branch 77, of Parañaque City
in Civil Case No. 2009-307; and
4. REFERRING the petitioner and the respondent to
arbitration pursuant to the arbitration clause of
the 2005 Lease Contract, repeatedly included in
the 2000 Lease Contract and in the 1976
Amended Deed of Donation. CIDaTc
SECOND DIVISION acquire jurisdiction over Consolidated Iron because it was a foreign
corporation that had never transacted business in the Philippines.
Likewise, they argued that the RTC had no jurisdiction over the subject
[G.R. No. 220546. December 7, 2016.] matter because of an arbitration clause in the TPAA. AScHCD
On December 19, 2012, the RTC ordered the consolidation of
LUZON IRON DEVELOPMENT GROUP CORPORATION the two cases. 7 Subsequently, Luzon Iron and Consolidated Iron filed
AND CONSOLIDATED IRON SANDS, their Special Appearance and Supplement to Motions to Dismiss, 8 dated
LTD., petitioners, vs. BRIDESTONE MINING AND January 31, 2013, seeking the dismissal of the consolidated cases. The
DEVELOPMENT CORPORATION and ANACONDA petitioners alleged that Bridestone and Anaconda were guilty of forum
MINING AND DEVELOPMENT shopping because they filed similar complaints before the Department of
CORPORATION, respondents. Environment and Natural Resources (DENR), Mines and Geosciences
Bureau, Regional Panel of Arbitrators against Luzon Iron.
The RTC Orders
DECISION
In its March 18, 2013 Order, the RTC denied the motions to
dismiss, as well as the supplemental motion to dismiss, finding that
MENDOZA, J p: Consolidated Iron was doing business in the Philippines, with Luzon Iron
This petition for review on certiorari with prayer for the issuance as its resident agent. The RTC ruled that it had jurisdiction over the
of a writ of preliminary injunction and/or temporary restraining subject matter because under clause 14.8 of the TPAA, the parties could
order (TRO) seeks to reverse and set aside the September 8, 2015 go directly to courts when a direct and/or blatant violation of the
Decision 1 of the Court of Appeals (CA) in CA-G.R. SP No. 133296, provisions of the TPAA had been committed. The RTC also opined that
which affirmed the March 18, 2013 2 and September 18, 2013 3 Orders the complaint filed before the DENR did not constitute forum shopping
of the Regional Trial Court, Branch 59, Makati City (RTC), in the because there was neither identity of parties nor identity of reliefs sought.
consolidated case for rescission of contract and damages. Luzon Iron and Consolidated Iron moved for reconsideration, but
The Antecedents the RTC denied their motion in its September 18, 2013 Order.
On October 25, 2012, respondents Bridestone Mining and Undaunted, they filed their petition for review with prayer for the
Development Corporation (Bridestone) and Anaconda Mining and issuance of a writ of preliminary injunction and/or TRO before the CA.
Development Corporation (Anaconda) filed separate complaints before The CA Ruling
the RTC for rescission of contract and damages against petitioners
Luzon Iron Development Group Corporation (Luzon Iron) and In its September 8, 2015 Decision, the CA affirmed the March
Consolidated Iron Sands, Ltd. (Consolidated Iron), docketed as Civil 18, 2013 and September 18, 2013 RTC Orders in denying the motions to
Case No. 12-1053 and Civil Case No. 12-1054, respectively. Both dismiss and the supplemental motions to dismiss. It agreed that the court
complaints sought the rescission of the Tenement Partnership and acquired jurisdiction over the person of Consolidated Iron because the
Acquisition Agreement (TPAA) 4 entered into by Luzon Iron and summons may be validly served through its agent Luzon Iron,
Consolidated Iron, on one hand, and Bridestone and Anaconda, on the considering that the latter was merely the business conduit of the former.
other, for the assignment of the Exploration Permit Application of the The CA also sustained the jurisdiction of the RTC over the subject matter
former in favor of the latter. The complaints also sought the return of the opining that the arbitration clause in the TPAA provided for an exception
Exploration Permits to Bridestone and Anaconda. 5 where parties could directly go to court.
Thereafter, Luzon Iron and Consolidated Iron filed their Special Further, the CA also disregarded the averment of forum
Appearance with Motion to Dismiss 6 separately against Bridestone's shopping, explaining that in the complaint before the RTC, both
complaint and Anaconda's complaint. Both motions to dismiss presented Consolidated Iron and Luzon Iron were impleaded but in the complaint
similar grounds for dismissal. They contended that the RTC could not
before the DENR only the latter was impleaded. It stated that there was acquired jurisdiction over the person of Consolidated Iron. They posited
no identity of relief and no identity of cause of action. that Consolidated Iron was doing business in the Philippines as Luzon
Iron was merely its conduit. Thus, they insisted that summons could be
Hence, this appeal raising the following:
served to Luzon Iron as Consolidated Iron's agent. Likewise, they denied
that they were guilty of forum shopping as the issues and the reliefs
prayed for in the complaints before the RTC and the DENR differed.
ISSUES
Further, the respondents asserted that the trial court had
jurisdiction over the complaints because the TPAA itself allowed a direct
I resort before the courts in exceptional circumstances. They cited
WHETHER THE COURT OF APPEALS ERRED IN paragraph 14.8 thereof as basis explaining that when a direct and/or
RULING THAT THE TRIAL COURT ACQUIRED blatant violation of the TPAA had been committed, a party could go
JURISDICTION OVER THE PERSON OF directly to the courts. They faulted the petitioners in not moving for the
CONSOLIDATED IRON; referral of the case for arbitration instead of merely filing a motion to
II dismiss. They added that actions that are subject to arbitration
WHETHER THE COURT OF APPEALS ERRED IN agreement were merely suspended, and not dismissed. AcICHD
RULING THAT THE TRIAL COURT HAS
JURISDICTION OVER THE SUBJECT MATTER OF Reply of Petitioners
THE CONSOLIDATED CASES; AND In their Reply, 11 dated April 29, 2016, the petitioners stated that
III Consolidated Iron was not necessarily doing business in the Philippines
WHETHER THE COURT OF APPEALS ERRED IN by merely establishing a wholly-owned subsidiary in the form of Luzon
RULING THAT BRIDESTONE/ANACONDA WERE Iron. Also, they asserted that Consolidated Iron had not been validly
NOT GUILTY OF FORUM SHOPPING. 9 served the summons because Luzon Iron is neither its resident agent nor
Petitioners Luzon Iron and Consolidated Iron insist that the RTC its representative in the Philippines. The petitioners explained that Luzon
has no jurisdiction over the latter because it is a foreign corporation Iron, as a wholly-owned subsidiary, had a separate and distinct
which is neither doing business nor has transacted business in the personality from Consolidated Iron.
Philippines. They argue that there could be no means by which the trial The petitioners explained that Paragraph 14.8 of the TPAA
court could acquire jurisdiction over the person of Consolidated Iron should not be construed as an authority to directly resort to court action
under any mode of service of summons. The petitioners claim that the in case of a direct and/or blatant violation of the TPAA because such
service of summons to Consolidated Iron was defective because the interpretation would render the arbitration clause nugatory. They
mere fact that Luzon Iron was a wholly-owned subsidiary of Consolidated contended that, even for the sake of argument, the judicial action under
Iron did not establish that Luzon Iron was the agent of Consolidated Iron. the said provisions was limited to issues or matters which were inexistent
They emphasize that Consolidated Iron and Luzon Iron are two distinct in the present case. They added that a party was not required to file a
and separate entities. formal request for arbitration before an arbitration clause became
The petitioners further assert that the trial court had no operational. Lastly, they insisted that the respondents were guilty of
jurisdiction over the consolidated cases because of the arbitration clause forum shopping in simultaneously filing complaints before the trial court
set forth in the TPAA. They reiterate that Luzon Iron and Consolidated and the DENR.
Iron were guilty of forum shopping because their DENR complaint
contained similar causes of action and reliefs sought. They stress that
the very evil sought to be prevented by the prohibition on forum shopping The Court's Ruling
had occurred when the DENR and the RTC issued conflicting orders in
dismissing or upholding the complaints filed before them.
The petition is impressed with merit.
Position of Respondents
Filing of complaints
In their Comment/Opposition, 10 dated January 7, 2016, before the RTC and the
respondents Bridestone and Anaconda countered that the RTC validly DENR is forum shopping
Forum shopping is committed when multiple suits involving the described herein can possibly constitute direct
same parties and the same causes of action are filed, either contempt. 15 [Emphases supplied]
simultaneously or successively, for the purpose of obtaining a favorable
There is forum shopping when the following elements are
judgment through means other than appeal or certiorari. 12 The
present: (a) identity of parties, or at least such parties representing the
prohibition on forum shopping seeks to prevent the possibility that
same interests in both actions; (b) identity of rights asserted and reliefs
conflicting decisions will be rendered by two tribunals. 13
prayed for, the relief being founded on the same facts; and (c) the
In Spouses Arevalo v. Planters Development Bank, 14 the Court identity of the two preceding particulars, such that any judgment
elaborated that forum shopping vexed the court and warranted the rendered in the other action will, regardless of which party is successful,
dismissal of the complaints. Thus: amounts to res judicata in the action under consideration. 16 All the
above-stated elements are present in the case at bench.
Forum shopping is the act of litigants who
repetitively avail themselves of multiple judicial remedies First, there is identity of parties. In both the complaints before the
in different fora, simultaneously or successively, all RTC and the DENR, Luzon Iron was impleaded as defendant while
substantially founded on the same transactions and the Consolidated Iron was only impleaded in the complaint before the RTC.
same essential facts and circumstances; and raising Even if Consolidated Iron was not impleaded in the DENR complaint, the
substantially similar issues either pending in or already element still exists. The requirement is only substantial, and not absolute,
resolved adversely by some other court; or for the identity of parties; and there is substantial identity of parties when there
purpose of increasing their chances of obtaining a is community of interest between a party in the first case and a party in
favorable decision, if not in one court, then in the second case, even if the latter was not impleaded in the other
another. The rationale against forum-shopping is that case. 17 Consolidated Iron and Luzon Iron had a common interest under
a party should not be allowed to pursue the TPAA as the latter was a wholly-owned subsidiary of the former.
simultaneous remedies in two different courts, for to
Second, there is identity of causes of action. A reading of the
do so would constitute abuse of court processes
complaints filed before the RTC and the DENR reveals that they had
which tends to degrade the administration of justice,
almost identical causes of action and they prayed for similar reliefs as
wreaks havoc upon orderly judicial procedure, and
they ultimately sought the return of their respective Exploration Permit on
adds to the congestion of the heavily burdened
the ground of the alleged violations of the TPAA committed by the
dockets of the courts.
petitioners. 18 In Yap v. Chua, 19 the Court ruled that identity of causes
xxx xxx xxx of action did not mean absolute identity. TAIaHE
What is essential in determining the Hornbook is the rule that identity of causes of
existence of forum-shopping is the vexation caused action does not mean absolute identity; otherwise, a
the courts and litigants by a party who asks different party could easily escape the operation of res judicata by
courts and/or administrative agencies to rule on changing the form of the action or the relief sought. The
similar or related causes and/or grant the same or test to determine whether the causes of action are
substantially similar reliefs, in the process creating identical is to ascertain whether the same evidence
the possibility of conflicting decisions being will sustain both actions, or whether there is an
rendered upon the same issues. identity in the facts essential to the maintenance of
the two actions. If the same facts or evidence would
xxx xxx xxx
sustain both, the two actions are considered the
We emphasize that the grave evil sought to be same, and a judgment in the first case is a bar to the
avoided by the rule against forum-shopping is the subsequent action. Hence, a party cannot, by varying
rendition by two competent tribunals of two separate and the form of action or adopting a different method of
contradictory decisions. To avoid any confusion, this presenting his case, escape the operation of the
Court adheres strictly to the rules against forum principle that one and the same cause of action shall not
shopping, and any violation of these rules results in be twice litigated between the same parties or their
the dismissal of a case. The acts committed and privies. xxx 20 [Emphases supplied]
In the case at bench, both complaints filed before resident agent, service may, with leave
different fora involved similar facts and issues, the resolution of which of court, be effected out of the
depends on analogous evidence. Thus, the filing of two separate Philippines through any of the following
complaints by the petitioners with the RTC and the DENR clearly means:
constitutes forum shopping. a) By personal service coursed
through the appropriate court in
It is worth noting that the very evil which the prohibition against
the foreign country with the
forum shopping sought to prevent had happened — the RTC and the
assistance of the Department of
DENR had rendered conflicting decisions. The trial court ruled that it had
Foreign Affairs;
jurisdiction notwithstanding the arbitration clause in the TPAA. On the
b) By publication once in a
other hand, the DENR found that it was devoid of jurisdiction because
newspaper of general circulation
the matter was subject to arbitration.
in the country where the
Summons were not defendant may be found and by
validly served serving a copy of the summons
and the court order by
Section 12 of Rule 14 of the Revised Rules of Court provides registered mail at the last known
that "[w]hen the defendant is a foreign private juridical entity which address of the defendant;
has transacted business in the Philippines, service may be made on c) By facsimile or any
its resident agent designated in accordance with law for that purpose, or, recognized electronic means
if there be no such agent, on the government official designated by law to that could generate proof of
that effect, or on any of its officers or agents within the Philippines." service; or
The Rule on Summons, as it now reads, thus, makes the d) By such other means as the
question whether Consolidated Iron was "doing business in the court may in its discretion
Philippines" irrelevant as Section 12, Rule 14 of the Rules of Court was direct."
broad enough to cover corporations which have "transacted business in The petitioners are mistaken in arguing that it cannot be served
the Philippines." summons because under Section 15, Rule 14 of the Rules of Court,
In fact, under the present legal milieu, the rules on service of extrajudicial service of summons may be resorted to only when the
summons on foreign private juridical entities had been expanded as it action is in rem or quasi in rem and not when the action is in personam.
recognizes additional modes by which summons may be served. A.M. The premise of the petitioners is erroneous as the rule on extraterritorial
No. 11-3-6-SC 21 thus provides: service of summons provided in Section 15, Rule 14 of the Rules of
Court is a specific provision dealing precisely with the service of
Section 12, Rule 14 of the Rules of Court is summons on a defendant which does not reside and is not found in the
hereby amended to read as follows: Philippines. 22 On the other hand, Section 12, Rule 14 thereof,
"SEC. 12. Service upon foreign private specifically applies to a defendant foreign private juridical entity which
juridical entity. — When the defendant is had transacted business in the Philippines. Both rules may provide for
a foreign private juridical entity which similar modes of service of summons, nevertheless, they should only be
has transacted business in the applied in particular cases, with one applicable to defendants which do
Philippines, service may be made on its not reside and are not found in the Philippines and the other to foreign
resident agent designated in accordance private juridical entities which had transacted business in the Philippines.
with law for that purpose, or, if there be In the case at bench, it is crystal clear that Consolidated Iron
no such agent, on the government transacted business in the Philippines as it was a signatory in the TPAA
official designated by law to that effect, that was executed in Makati. Hence, as the respondents argued, it may
or on any of its officers or agents within be served with the summons in accordance with the modes provided
the Philippines. under Section 12, Rule 14 of the Rules of Court.
If the foreign private juridical entity is not
registered in the Philippines or has no
In Atiko Trans, Inc. v. Prudential Guarantee and Assurance, its alleged agent corporation with respect to the transaction in question
Inc., 23 the Court elucidated on the means by which summons could be as a general allegation of agency will not suffice. 26 In other words, the
served on a foreign juridical entity, to wit: cDHAES allegations of the complaint taken as whole should be able to convey that
the subsidiary is but a business conduit of the principal or that by reason
On this score, we find for the petitioners. Before
of fraud, their separate and distinct personality should be
it was amended by A.M. No. 11-3-6-SC, Section 12 of
disregarded. 27 A wholly-owned subsidiary is a distinct and separate
Rule 14 of the Rules of Court reads:
entity from its mother corporation and the fact that the latter exercises
SEC. 12. Service upon foreign private control over the former does not justify disregarding their separate
juridical entity. — When the defendant is personality. It is true that under the TPAA, Consolidated Iron wielded
a foreign private juridical entity which great control over the actions of Luzon Iron under the said agreement.
has transacted business in the This, nonetheless, does not warrant the conclusion that Luzon Iron was a
Philippines, service may be made on its mere conduit of Consolidated Iron. In Pacific Rehouse Corporation v.
resident agent designated in accordance CA, 28 the Court ruled:
with law for that purpose, or, if there be
Albeit the RTC bore emphasis on the alleged
no such agent, on the government
control exercised by Export Bank upon its subsidiary E-
official designated by law to that effect,
Securities, "[c]ontrol, by itself, does not mean that the
or on any of its officers or agents within
controlled corporation is a mere instrumentality or a
the Philippines.
business conduit of the mother company. Even control
Elucidating on the above provision of the Rules over the financial and operational concerns of a
of Court, this Court declared in Pioneer International, subsidiary company does not by itself call for
Ltd. v. Guadiz, Jr. that when the defendant is a foreign disregarding its corporate fiction. There must be a
juridical entity, service of summons may be made upon: perpetuation of fraud behind the control or at least a
fraudulent or illegal purpose behind the control in order
1. Its resident agent designated in accordance to justify piercing the veil of corporate fiction. Such
with law for that purpose; fraudulent intent is lacking in this case. 29 [Emphasis
2. The government official designated by law to supplied]
receive summons if the corporation does
not have a resident agent; or, In the case at bench, the complaint merely contained a general
3. Any of the corporation's officers or agents statement that Luzon Iron was the resident agent of Consolidated Iron,
within the Philippines. 24 [Emphasis and that it was a wholly-owned subsidiary of the latter. There was no
supplied] allegation showing that Luzon Iron was merely a business conduit of
Consolidated Iron, or that the latter exercised control over the former to
The Court, however, finds that Consolidated Iron was not the extent that their separate and distinct personalities should be set
properly served with summons through any of the permissible modes aside. Thus, Luzon Iron cannot be deemed as an agent of Consolidated
under the Rules of Court. Indeed, Consolidated Iron was served with Iron in connection with the third mode of service of summons.
summons through Luzon Iron. Such service of summons, however, was
defective. To reiterate, the Court did not acquire jurisdiction over
Consolidated Iron because the service of summons, coursed through
It is undisputed that Luzon Iron was never registered before the Luzon Iron, was defective. Luzon Iron was neither the resident agent nor
Securities and Exchange Commission (SEC) as Consolidated Iron's the conduit or agent of Consolidated Iron.
resident agent. Thus, the service of summons to Consolidated Iron
through Luzon Iron cannot be deemed a service to a resident On the abovementioned procedural issues alone, the dismissal
agent 25 under the first mode of service. of the complaints before the RTC was warranted. Even granting that the
complaints were not procedurally defective, there still existed enough
Likewise, the respondents err in insisting that Luzon Iron could reason for the trial court to refrain from proceeding with the case.
be served summons as an agent of Consolidated Iron, it being a wholly-
owned subsidiary of the latter. The allegations in the complaint must Controversy must be
clearly show a connection between the principal foreign corporation and referred for arbitration
The petitioners insisted that the RTC had no jurisdiction over the justice and declog court dockets. As such, the State
subject matter because under Paragraph 15.1 of the TPAA, any dispute shall provide means for the use of ADR as an
out of or in connection with the TPAA must be resolved by arbitration. efficient tool and an alternative procedure for the
The said provision provides: resolution of appropriate cases. Likewise, the State
shall enlist active private sector participation in the
If, for any reasonable reason, the Parties cannot
settlement of disputes through ADR. This Act shall be
resolve a material fact, material event or any dispute
without prejudice to the adoption by the Supreme Court
arising out of or in connection with this TPAA, including
of any ADR system, such as mediation, conciliation,
any question regarding its existence, validity or
arbitration, or any combination thereof as a means of
termination, within 90 days from its notice, shall be
achieving speedy and efficient means of resolving cases
referred to and finally resolved by arbitration in
pending before all courts in the Philippines which shall
Singapore in accordance with the Arbitration Rules of the
be governed by such rules as the Supreme Court may
Singapore International Arbitration Centre ("SIAC
approve from time to time.
Rules") for the time being in force, which rules are
deemed to be incorporated by reference in this clause Our policy in favor of party autonomy in
15.1. 30 resolving disputes has been reflected in our laws as
early as 1949 when our Civil Code was approved.
The RTC, as the CA agreed, countered that Paragraph 14.8 of
Republic Act No. 876 later explicitly recognized the
the TPAA allowed the parties to directly resort to courts in case of a
validity and enforceability of parties' decision to submit
direct and/or blatant violation of the provisions of the TPAA. Paragraph
disputes and related issues to arbitration.
14.8 stated:
Arbitration agreements are liberally
Each Party agrees not to commence or procure
construed in favor of proceeding to arbitration. We
the commencement of any challenge or claim, action,
adopt the interpretation that would render effective
judicial or legislative enquiry, review or other
an arbitration clause if the terms of the agreement
investigation into the sufficiency, validity, legality or
allow for such interpretation. 33 [Emphases supplied]
constitutionality of (i) the assignments of the Exploration
Permit Applications(s) (sic) to LIDGC, (ii) any other Thus, consistent with the state policy of favoring arbitration, the
assignments contemplated by this TPAA, and/or (iii) present TPAA must be construed in such a manner that would give life to
or (sic) any agreement to which the Exploration Permit the arbitration clause rather than defeat it, if such interpretation is
Application(s) may be converted, unless a direct and/or permissible. With this in mind, the Court views the interpretation
blatant violation of the provisions of the TPAA has been forwarded by the petitioners as more in line with the state policy favoring
committed. 31 arbitration. cTDaEH
In Bases Conversion Development Authority v. DMCI Project Paragraphs 14.8 and 15.1 of the TPAA should be harmonized in
Developers, Inc., 32 the Court emphasized that the State favored such a way that the arbitration clause is given life, especially since such
arbitration, to wit: construction is possible in the case at bench. A synchronized reading of
the abovementioned TPAA provisions will show that a claim or action
The state adopts a policy in favor of
raising the sufficiency, validity, legality or constitutionality of: (a) the
arbitration. Republic Act No. 9285 expresses this policy:
assignments of the EP to Luzon Iron; (b) any other assignments
SEC. 2. Declaration of Policy. — It is hereby contemplated by the TPAA; or (c) any agreement to which the EPs may
declared the policy of the State to actively promote party be converted, may be instituted only when there is a direct and/or blatant
autonomy in the resolution of disputes or the freedom of violation of the TPAA. In turn, the said action or claim is commenced by
the parties to make their own arrangements to resolve proceeding with arbitration, as espoused in the TPAA.
their disputes. Towards this end, the State shall
The Court disagrees with the respondents that Paragraph 14.8 of
encourage and actively promote the use of
the TPAA should be construed as an exception to the arbitration clause
Alternative Dispute Resolution (ADR) as an
where direct court action may be resorted to in case of direct and/or
important means to achieve speedy and impartial
blatant violation of the TPAA occurs. If such interpretation is to be
espoused, the arbitration clause would be rendered inutile as practically action filed in violation of the arbitration agreement xxx
all matters may be directly brought before the courts. Such construction may request the court to refer the parties to arbitration in
is anathema to the policy favoring arbitration. accordance with such agreement."
A closer perusal of the TPAA will also reveal that paragraph 14 In using the word "may" to qualify the act of
and all its sub-paragraphs are general provisions, whereas paragraphs filing a "request" under Section 24 of R.A. No. 9285,
15 and all its sub-clauses specifically refer to arbitration. When general the Special ADR Rules clearly did not intend to limit
and specific provisions are inconsistent, the specific provision shall be the invocation of an arbitration agreement in a
paramount and govern the general provision. 34 pending suit solely via such "request." After all, non-
compliance with an arbitration agreement is a valid
The petitioners' failure to refer the case for arbitration, however,
defense to any offending suit and, as such, may even be
does not render the arbitration clause in the TPAA inoperative.
raised in an answer as provided in our ordinary rules of
In Koppel, Inc. v. Makati Rotary Club Foundation, Inc. (Koppel), 35 the
procedure.
Court explained that an arbitration clause becomes operative,
notwithstanding the lack of a formal request, when a party has appraised In this case, it is conceded that petitioner was
the trial court of the existence of an arbitration clause, viz.: not able to file a separate "request" of arbitration before
the MeTC. However, it is equally conceded that the
xxx The operation of the arbitration clause in this
petitioner, as early as in its Answer with
case is not at all defeated by the failure of the
Counterclaim, had already apprised the MeTC of the
petitioner to file a formal "request" or application
existence of the arbitration clause in the 2005 Lease
therefor with the MeTC. We find that the filing of
Contract and, more significantly, of its desire to have the
a "request" pursuant to Section 24 of RA. No. 9285
same enforced in this case. This act of petitioner is
is not the sole means by which an arbitration clause may
enough valid invocation of his right to arbitrate.
be validly invoked in a pending suit.
xxx 36 [Emphases supplied; italics in the original]
Section 24 of R.A. No. 9285 reads:
SEC. 24. Referral to Arbitration. — A court before which It is undisputed that the petitioners Luzon Iron and Consolidated
an action is brought in a matter which is the subject Iron never made any formal request for arbitration. As expounded
matter of an arbitration agreement shall, if at least one in Koppel, however, a formal request is not the sole means of invoking
party so requests not later that the pre-trial conference, an arbitration clause in a pending suit. Similar to the said case, the
or upon the request of both parties thereafter, refer the petitioners here made the RTC aware of the existence of the arbitration
parties to arbitration unless it finds that the arbitration clause in the TPAA as they repeatedly raised this as an issue in all their
agreement is null and void, inoperative or incapable of motions to dismiss. As such, it was enough to activate the arbitration
being performed. clause and, thus, should have alerted the RTC in proceeding with the
The "request" referred to in the above provision is, in case.
turn, implemented by Rules 4.1 to 4.3 of A.M. No. 07-11-
Moreover, judicial restraint should be exercised pursuant to the
08-SC or the Special Rules of Court on Alternative
competence-competence principle embodied in Rule 2.4 of the Special
Dispute Resolution (Special ADR Rules):
Rules of Court on Alternative Dispute Resolution. 37 The said provision
RULE 4: REFERRAL TO ADR
reads:
Rule 4.1. Who makes the request. — A party to a
pending action filed in violation of the arbitration RULE 2.4. Policy Implementing Competence-
agreement, whether contained in an arbitration clause or Competence Principle. — The arbitral tribunal shall be
in a submission agreement, may request the court to accorded the first opportunity or competence to rule on
refer the parties to arbitration in accordance with such the issue of whether or not it has the competence or
agreement. jurisdiction to decide a dispute submitted to it for
xxx xxx xxx decision, including any objection with respect to the
existence or validity of the arbitration agreement. When
Attention must be paid, however, to the salient
a court is asked to rule upon issue/s affecting the
wordings of Rule 4.1. It reads: "[a] party to a pending
competence or jurisdiction of an arbitral tribunal in a
dispute brought before it, either before or after the
arbitral tribunal is constituted, the court must
exercise judicial restraint and defer to the
competence or jurisdiction of the arbitral tribunal by
allowing the arbitral tribunal the first opportunity to
rule upon such issues. cSaATC
Where the court is asked to make a
determination of whether the arbitration agreement is
null and void, inoperative or incapable of being
performed, under this policy of judicial restraint, the court
must make no more than a prima facie determination of
that issue.
Unless the court, pursuant to such prima
facie determination, concludes that the arbitration
agreement is null and void, inoperative or incapable of
being performed, the court must suspend the action
before it and refer the parties to arbitration pursuant to
the arbitration agreement. [Emphasis supplied]
Generally, the action of the court is stayed if the matter raised
before it is subject to arbitration. 38 In the case at bench, however, the
complaints filed before the RTC should have been dismissed considering
that the petitioners were able to establish the ground for their dismissal,
that is, violating the prohibition on forum shopping. The parties,
nevertheless, are directed to initiate arbitration proceedings as provided
under Paragraph 15.1 of the TPAA.
WHEREFORE, the petition is GRANTED. The September 8,
2015 Decision of the Court of Appeals in CA-G.R. SP No. 133296,
affirming the March 18, 2013 and September 18, 2013 Orders of the
Regional Trial Court, Branch 59, Makati City, is hereby SET ASIDE. The
complaints in Civil Case Nos. 12-1053 and 12-1054 are DISMISSED.
The parties, however, are ORDERED to commence arbitration
proceedings pursuant to Paragraph 15.1 of the Tenement Partnership
and Acquisition Agreement.
SO ORDERED.
FIRST DIVISION petitioner before the Regional Trial Court of Quezon City, Branch 222 (RTC),
docketed as Case No. Q-07-60321. 12
[G.R. No. 212081. February 23, 2015.] Upon motion of respondent, the case was subsequently referred to
arbitration pursuant to the arbitration clause of the Consultancy
Agreement, 13 which petitioner did not oppose. 14 As a result, Atty. Alfredo
DEPARTMENT OF ENVIRONMENT AND NATURAL
F. Tadiar, Architect Armando N. Alli, and Construction Industry Arbitration
RESOURCES (DENR), petitioner, vs. UNITED
Commission (CIAC) Accredited Arbitrator Engr. Ricardo B. San Juan were
PLANNERS CONSULTANTS, INC. (UPCI), respondent.
appointed as members of the Arbitral Tribunal. The court-referred arbitration
was then docketed as Arbitration Case No. A-001. 15
During the preliminary conference, the parties agreed to adopt the
DECISION CIAC Revised Rules Governing Construction Arbitration 16 (CIAC Rules) to
govern the arbitration proceedings. 17 They further agreed to submit their
respective draft decisions in lieu of memoranda of arguments on or before
PERLAS-BERNABE, J p: April 21, 2010, among others. 18
On the due date for submission of the draft decisions, however, only
Assailed in this petition for review on certiorari 1 is the respondent complied with the given deadline, 19 while petitioner moved for
Decision 2 dated March 26, 2014 of the Court of Appeals (CA) in CA-G.R. SP the deferment of the deadline which it followed with another motion for
No. 126458 which dismissed the petition for certiorari filed by petitioner the extension of time, asking that it be given until May 11, 2010 to submit its draft
Department of Environment and Natural Resources (petitioner). decision. 20
The Facts In an Order 21 dated April 30, 2010, the Arbitral Tribunal denied
petitioner's motions and deemed its non-submission as a waiver, but
declared that it would still consider petitioner's draft decision if submitted
On July 26, 1993, petitioner, through the Land Management Bureau before May 7, 2010, or the expected date of the final award's
(LMB), entered into an Agreement for Consultancy Services 3 (Consultancy promulgation. 22 Petitioner filed its draft decision 23 only on May 7, 2010.
Agreement) with respondent United Planners Consultants, Inc. (respondent)
in connection with the LMB's Land Resource Management Master Plan The Arbitral Tribunal rendered its Award 24 dated May 7, 2010
Project (LRMMP). 4 Under the Consultancy Agreement, petitioner committed (Arbitral Award) in favor of respondent, directing petitioner to pay the latter
to pay a total contract price of P4,337,141.00, based on a predetermined the amount of (a) P2,285,089.89 representing the unpaid progress billings,
percentage corresponding to the particular stage of work accomplished. 5 In with interest at the rate of 12% per annum from the date of finality of the
December 1994, respondent completed the work required, which petitioner Arbitral Award upon confirmation by the RTC until fully
formally accepted on December 27, 1994. 6 However, petitioner was able to paid; (b) P2,033,034.59 as accrued interest thereon; (c) P500,000.00 as
pay only 47% of the total contract price in the amount of exemplary damages; and (d) P150,000.00 as attorney's fees. 25 It also
P2,038,456.30. 7 IcSEAH ordered petitioner to reimburse respondent its proportionate share in the
arbitration costs as agreed upon in the amount of P182,119.44. 26
On October 25, 1994, the Commission on Audit (COA) released the
Technical Services Office Report 8 (TSO) finding the contract price of the Unconvinced, petitioner filed a motion for reconsideration, 27 which
Agreement to be 84.14% excessive. 9 This notwithstanding, petitioner, in a the Arbitral Tribunal merely noted without any action, claiming that it had
letter dated December 10, 1998, acknowledged its liability to respondent in already lost jurisdiction over the case after it had submitted to the RTC its
the amount of P2,239,479.60 and assured payment at the soonest possible Report together with a copy of the Arbitral Award. 28
time. 10
Consequently, petitioner filed before the RTC a Motion for
For failure to pay its obligation under the Consultancy Agreement Reconsideration 29 dated May 19, 2010 (May 19, 2010 Motion for
despite repeated demands, respondent instituted a Complaint 11 against Reconsideration) and a Manifestation and Motion 30 dated June 1, 2010
(June 1, 2010 Manifestation and Motion), asserting that it was denied the Dissatisfied, it filed on September 10, 2012 a petition
opportunity to be heard when the Arbitral Tribunal failed to consider its draft for certiorari 48 before the CA, docketed as CA-G.R. SP No. 126458,
decision and merely noted its motion for reconsideration. 31 It also denied averring in the main that the RTC acted with grave abuse of discretion in
receiving a copy of the Arbitral Award by either electronic or registered confirming and ordering the execution of the Arbitral Award.
mail. 32 For its part, respondent filed an opposition thereto and moved for the
confirmation 33 of the Arbitral Award in accordance with the Special Rules of The CA Ruling
Court on Alternative Dispute Resolution (Special ADR Rules). 34
In an Order 35 dated March 30, 2011, the RTC merely noted In a Decision 49 dated March 26, 2014, the CA dismissed
petitioner's aforesaid motions, finding that copies of the Arbitral Award the certiorari petition on two (2) grounds, namely: (a) the petition essentially
appear to have been sent to the parties by the Arbitral Tribunal, including the assailed the merits of the Arbitral Award which is prohibited under Rule
OSG, contrary to petitioner's claim. On the other hand, the RTC confirmed 19.7 50 of the Special ADR Rules; 51 and (b) the petition was filed out of
the Arbitral Award pursuant to Rule 11.2 (A) 36 of the Special ADR Rules time, having been filed way beyond 15 days from notice of the RTC's July 9,
and ordered petitioner to pay respondent the costs of confirming the award, 2012 Order, in violation of Rule 19.28 52 in relation to Rule 19.8 53 of said
as prayed for, in the total amount of P50,000.00. From this order, petitioner Rules which provide that a special civil action for certiorari must be filed
did not file a motion for reconsideration. before the CA within 15 days from notice of the judgment, order, or
resolution sought to be annulled or set aside (or until July 27, 2012).
Thus, on June 15, 2011, respondent moved for the issuance of a writ
of execution, to which no comment/opposition was filed by petitioner despite Aggrieved, petitioner filed the instant petition.
the RTC's directive therefor. In an Order 37 dated September 12, 2011, the
RTC granted respondent's motion. 38 The Issue Before the Court
Petitioner moved to quash 39 the writ of execution, positing that
The core issue for the Court's resolution is whether or not the CA
respondent was not entitled to its monetary claims. It also claimed that the
erred in applying the provisions of the Special ADR Rules, resulting in the
issuance of said writ was premature since the RTC should have first resolved
dismissal of petitioner's special civil action for certiorari.
its May 19, 2010 Motion for Reconsideration and June 1, 2010 Manifestation
and Motion, and not merely noted them, thereby violating its right to due
process. 40 The Court's Ruling
b. Reversing the arbitral tribunal's preliminary Execution is fittingly called the fruit and end of suit and the life of the
determination upholding its jurisdiction; law. A judgment, if left unexecuted, would be nothing but an empty victory for
the prevailing party. 73
c. Denying the request to refer the dispute to arbitration;
While it appears that the Special ADR Rules remain silent on the
d. Granting or refusing an interim relief; procedure for the execution of a confirmed arbitral award, it is the Court's
considered view that the Rules' procedural mechanisms cover not only
e. Denying a petition for the appointment of an arbitrator;
aspects of confirmation but necessarily extend to a confirmed award's
f. Confirming, vacating or correcting a domestic arbitral execution in light of the doctrine of necessary implication which states that
award; every statutory grant of power, right or privilege is deemed to include all
incidental power, right or privilege. In Atienza v. Villarosa, 74 the doctrine
g. Suspending the proceedings to set aside an was explained, thus:
international commercial arbitral award and
referring the case back to the arbitral tribunal; No statute can be enacted that can provide all the
details involved in its application. There is always an
h. Allowing a party to enforce an international commercial omission that may not meet a particular situation. What is
arbitral award pending appeal; thought, at the time of enactment, to be an all-embracing
i. Adjourning or deferring a ruling on whether to set aside, legislation may be inadequate to provide for the unfolding
recognize and or enforce an international of events of the future. So-called gaps in the law develop
commercial arbitral award; as the law is enforced. One of the rules of statutory
construction used to fill in the gap is the doctrine of
j. Allowing a party to enforce a foreign arbitral award necessary implication. The doctrine states that what is
pending appeal; and implied in a statute is as much a part thereof as that which
is expressed. Every statute is understood, by
k. Denying a petition for assistance in taking evidence. implication, to contain all such provisions as may be
(Emphasis supplied) necessary to effectuate its object and purpose, or to
make effective rights, powers, privileges or
jurisdiction which it grants, including all such
collateral and subsidiary consequences as may be
fairly and logically inferred from its terms. Ex Order dated July 9, 2012, or on September 10, 2012, 81 said petition was
necessitate legis. And every statutory grant of power, clearly dismissible. 82
right or privilege is deemed to include all incidental
power, right or privilege. This is so because the greater III.
includes the lesser, expressed in the maxim, in eo plus sit,
simper inest et minus. 75 (Emphases supplied) Discounting the above-discussed procedural considerations, the
As the Court sees it, execution is but a necessary incident to the Court still finds that the certiorari petition had no merit. AIaDcH
Court's confirmation of an arbitral award. To construe it otherwise would Indeed, petitioner cannot be said to have been denied due process
result in an absurd situation whereby the confirming court previously applying as the records undeniably show that it was accorded ample opportunity to
the Special ADR Rules in its confirmation of the arbitral award would later ventilate its position. There was clearly nothing out of line when the Arbitral
shift to the regular Rules of Procedure come execution. Irrefragably, a court's Tribunal denied petitioner's motions for extension to file its submissions
power to confirm a judgment award under the Special ADR Rules should be having failed to show a valid reason to justify the same or in rendering the
deemed to include the power to order its execution for such is but a collateral Arbitral Award sans petitioner's draft decision which was filed only on the day
and subsidiary consequence that may be fairly and logically inferred from the of the scheduled promulgation of final award on May 7, 2010. 83 The
statutory grant to regional trial courts of the power to confirm domestic touchstone of due process is basically the opportunity to be heard. Having
arbitral awards. been given such opportunity, petitioner should only blame itself for its own
All the more is such interpretation warranted under the principle procedural blunder.
of ratio legis est anima which provides that a statute must be read according On this score, the petition for certiorari in CA-G.R. SP No. 126458
to its spirit or intent, 76 for what is within the spirit is within the statute was likewise properly dismissed.
although it is not within its letter, and that which is within the letter but not
within the spirit is not within the statute. 77 Accordingly, since the Special
ADR Rules are intended to achieve speedy and efficient resolution of IV.
disputes and curb a litigious culture, 78 every interpretation thereof should be
made consistent with these objectives. Nevertheless, while the Court sanctions the dismissal by the CA of
the petition for certiorari due to procedural infirmities, there is a need to
Thus, with these principles in mind, the Court so concludes that the explicate the matter of execution of the confirmed Arbitral Award against the
Special ADR Rules, as far as practicable, should be made to apply not only petitioner, a government agency, in the light of Presidential Decree No. (PD)
to the proceedings on confirmation but also to the confirmed award's 1445 84 otherwise known as the "Government Auditing Code of the
execution. Philippines."
Further, let it be clarified that — contrary to petitioner's stance — Section 26 of PD 1445 expressly provides that execution of money
resort to the Rules of Court even in a suppletory capacity is not allowed. Rule judgment against the Government or any of its subdivisions, agencies and
22.1 of the Special ADR Rules explicitly provides that "[t]he provisions of the instrumentalities is within the primary jurisdiction of the COA, to wit:
Rules of Court that are applicable to the proceedings enumerated in Rule 1.1
of these Special ADR Rules have either been included and incorporated in SEC. 26. General jurisdiction. — The authority
these Special ADR Rules or specifically referred to herein." 79 Besides, and powers of the Commission shall extend to and
Rule 1.13 thereof provides that "[i]n situations where no specific rule is comprehend all matters relating to auditing procedures,
provided under the Special ADR Rules, the court shall resolve such matter systems and controls, the keeping of the general accounts
summarily and be guided by the spirit and intent of the Special ADR Rules of the Government, the preservation of vouchers pertaining
and the ADR Laws." thereto for a period of ten years, the examination and
inspection of the books, records, and papers relating
As above-mentioned, the petition for certiorari permitted under the to those accounts; and the audit and settlement of the
Special ADR Rules must be filed within a period of fifteen (15) days from accounts of all persons respecting funds or property
notice of the judgment, order or resolution sought to be annulled or set received or held by them in an accountable capacity,
aside. 80 Hence, since petitioner's filing of its certiorari petition in CA-G.R. as well as the examination, audit, and settlement of all
SP No. 126458 was made nearly two months after its receipt of the RTC's debts and claims of any sort due from or owing to the
Government or any of its subdivisions, agencies and
instrumentalities. The said jurisdiction extends to all
government-owned or controlled corporations, including
their subsidiaries, and other self-governing boards,
commissions, or agencies of the Government, and as
herein prescribed, including non-governmental entities
subsidized by the government, those funded by donation
through the government, those required to pay levies or
government share, and those for which the government
has put up a counterpart fund or those partly funded by the
government. (Emphases supplied)
From the foregoing, the settlement of respondent's money claim is
still subject to the primary jurisdiction of the COA despite finality of the
confirmed arbitral award by the RTC pursuant to the Special ADR
Rules. 85 Hence, the respondent has to first seek the approval of the COA of
their monetary claim. This appears to have been complied with by the latter
when it filed a "Petition for Enforcement and Payment of Final and Executory
Arbitral Award" 86 before the COA. Accordingly, it is now the COA which has
the authority to rule on this latter petition.
WHEREFORE, the petition is DENIED. The Decision dated March
26, 2014 of the Court of Appeals in CA-G.R. SP No. 126458 which dismissed
the petition for certiorari filed by petitioner the Department of Environment
and Natural Resources is hereby AFFIRMED.
SO ORDERED.
FIRST DIVISION of technical and advisory or management services to the
respondent, 8 effective for five years, or from January 4, 1999 until
December 31, 2003. 9 On the same date, the respondent, pursuant to
[G.R. No. 160071. June 6, 2016.] Clause 6 of the TSA, 10 submitted a Side Letter, 11 the relevant portions
of which stated:
ANDREW D. FYFE, RICHARD T. NUTTALL, and For and in consideration of the services to be faithfully
RICHARD J. WALD, petitioners, vs. PHILIPPINE performed by Regent Star in accordance with the terms
AIRLINES, INC., respondent. and conditions of the Agreement, the Company agrees
to pay Regent Star as follows:
1.1 Upon execution of the Agreement,
DECISION Four Million Seven Hundred Thousand
US Dollars (US$4,700,000.00),
representing advisory fees for two (2)
years from the date of signature of the
BERSAMIN, J p: Agreement, with an additional amount of
This case concerns the order issued by the Regional Trial Court not exceeding One Million Three
granting the respondent's application to vacate the adverse arbitral Hundred Thousand US Dollars
award of the panel of arbitrators, and the propriety of the recourse from (US$1,300,000.00) being due and
such order. demandable upon Regent Star's notice
to the Company of its engagement of an
The Case individual to assume the position of CCA
Under review are the resolutions promulgated in C.A.-G.R. No. under the Agreement;
71224 entitled Andrew D. Fyfe, Richard T. Nuttall and Richard J. Wald v. xxx xxx xxx
Philippine Airlines, Inc. on May 30, 2003 1 and September 19,
2003, 2 whereby the Court of Appeals (CA) respectively granted the In addition to the foregoing, the
respondent's Motion to Dismiss Appeal (without Prejudice to the Filing of Company agrees as follows:
Appellee's Brief) and denied the petitioners' Motion for Reconsideration. xxx xxx xxx
Antecedents In the event of a full or partial
In 1998, the respondent underwent rehabilitation proceedings in termination of the Agreement for
the Securities and Exchange Commission (SEC), 3 which issued an whatever reason by either the Company
order dated July 1, 1998 decreeing, among others, the suspension of all or a Senior Technical Adviser/Regent
claims for payment against the respondent. 4 To convince its creditors to Star prior to the end of the term of the
approve the rehabilitation plan, the respondent decided to hire technical Agreement, the following penalties are
advisers with recognized experience in the airline industry. This led the payable by the terminating party:
respondent through its then Director Luis Juan K. Virata to consult with A. During the first 2 years
people in the industry, and in due course came to meet Peter W. Foster,
formerly of Cathay Pacific Airlines. 5 Foster, along with Michael R. 1. Senior Company Adviser (CCA) - US$800,000.00
Scantlebury, negotiated with the respondent on the details of a proposed 2. Senior Commercial Adviser (SCA) - 800,000.00
technical services agreement. 6 Foster and Scantlebury subsequently
organized Regent Star Services Ltd. (Regent Star) under the laws of the 3. Senior Financial Adviser (FSA) - 700,000.00
British Virgin Islands. 7 On January 4, 1999, the respondent and Regent 4. Senior Ground Services and
Star entered into a Technical Services Agreement (TSA) for the delivery Training Adviser (SAG) - 500,000.00
5. Senior Engineering and Senior Engineering and
Maintenance Adviser (SAM) - 500,000.00 Maintenance Adviser - 500,000.00
–––––––––––––––
TOTAL US$3,300,000.00
xxx xxx xxx
=============
For the avoidance of doubt, it is
understood and agreed that in the event
that the terminating party is an individual There is, therefore, due to RSS from PAL the
Senior Technical Adviser the liability to amount of US$3,300,000.00 by way of stipulated
pay such Termination Amount to the penalties.
Company shall rest with that individual
party, not with RSS. Similarly, if the However, RSS has been paid by PAL advance
terminating party is the Company, the "advisory fee for two (2) years from date of signature of
liability to the aggrieved party shall be the Agreement" the amount of US$5,700,000. Since
the individual Senior Technical Adviser, RSS has rendered advisory services from 4 January to
not to RSS. 12 31 July 1999, or a period of seven months, it is entitled
to retain only the advisory fees for seven months. This is
Regent Star, through Foster, conformed to the terms stated in computed as follows:
the Side Letter. 13 The SEC approved the TSA on January 19, 1999. 14
US$5,700,000 = US$237,500/month x 7 = US$1,662,500
In addition to Foster and Scantlebury, Regent Star engaged the
petitioners in respective capacities, specifically: Andrew D. Fyfe as ––––––––––––
Senior Ground Services and Training Adviser; Richard J. Wald as Senior 24 months
Maintenance and Engineering Adviser; and Richard T. Nuttall as Senior
Commercial Adviser. The petitioners commenced to render their services
to the respondent immediately after the TSA was executed. 15 The remaining balance of the advance advisory
On July 26, 1999, the respondent dispatched a notice to Regent fee, which corresponds to the unserved period of 17
Star terminating the TSA on the ground of lack of confidence effective months, or US$4,037,500, should be refunded by RSS
July 31, 1999. 16 In its notice, the respondent demanded the offsetting of to PAL.
the penalties due to the petitioners with the two-year advance advisory Off-setting the amount of US$3,300,000 due
fees it had paid to Regent Star, thus: from PAL to RSS against the amount of US$4,037,500
The side letter stipulates that "[i]n the event of a due from RSS to PAL, there remains a net balance of
full or partial termination of the Agreement for whatever US$737,500 due and payable to PAL. Please settle this
reason by either the Company or a Senior Technical amount at your early convenience, but not later than
Adviser/Regent Star prior to the end of the term of the August 15, 1999. 17
Agreement, the following penalties are payable by the On June 8, 1999, the petitioners, along with Scantlebury and
terminating party:" CAIHTE Wald, wrote to the respondent, through its President and Chief Operating
During the first 2 years: Officer, Avelino Zapanta, to seek clarification on the status of the TSA in
view of the appointment of Foster, Scantleburry and Nuttall as members
Senior Company Adviser - US$800,000.00 of the Permanent Rehabilitation Receiver (PRR) for the respondent. 18 A
Senior Commercial Adviser - 800,000.00 month later, Regent Star sent to the respondent another letter expressing
Senior Financial Adviser - 700,000.00 disappointment over the respondent's ignoring the previous letter, and
denying the respondent's claim for refund and set-off. Regent Star then
Senior Ground Services and
proposed therein that the issue be submitted to arbitration in accordance
Training Adviser - 500,000.00 with Clause 14 19 of the TSA. 20
Thereafter, the petitioners initiated arbitration proceedings in the Agreement. Hence when PAL signed the Agreement
Philippine Dispute Resolution Center, Inc. (PDRCI) pursuant to the TSA. with RSS, it was for all intents and purposes an
Agreement signed individually with the Senior Technical
Ruling of the PDRCI
Advisers including the Complainants. The RSS and the
After due proceedings, the PDRCI rendered its decision ordering five (5) Senior Technical Advisers should be treated as
the respondent to pay termination penalties, 21 viz.: one and the same,
On issue No. 1 we rule that the Complainants The Arbitration Tribunals is not convinced.
are entitled to their claim for termination penalties.
xxx xxx xxx
When the PAL terminated the Technical
PAL cannot refuse to pay Complainants their
Services Agreement on July 26, 1999 which also
termination penalties by setting off against the unserved
resulted in the termination of the services of the senior
period of seventeen (17) months of their advance
technical advisers including those of the Complainants
advisory fees as the Agreement and the Side Letter
it admitted that the termination penalties in the amount
clearly do not allow refund. This Arbitration Tribunal
of US$3,300,000.00 as provided in the Letter dated
cannot read into the contract, which is the law between
January 4, 1999 are payable to the Senior Technical
the parties, what the contract does not provide or what
Advisers by PAL. . . . . PAL's admission of its liability to
the parties did not intend. It is basic in contract
pay the termination penalties to the complainants was
interpretation that contracts that are not ambiguous are
made also in its Answer. PAL's counsel even stipulated
to be interpreted according to their literal meaning
during the hearing that the airline company admits that it
and should not be interpreted beyond their obvious
is liable to pay Complainants the termination
intendment. . . . . The penalties work as security for the
penalties. . . . .
Complainants against the uncertainties of their work at
However, PAL argued that although it is liable to PAL whose closure was a stark reality they were facing.
pay termination penalties the Complainants are not (TSN Hearing on April 27, 2000, pp. 48-49) This would
entitled to their respective claims because considering not result in unjust enrichment for the Complainants
that PAL had paid RSS advance "advisory fees for two because the termination of the services was initiated by
(2) years" in the total amount of US$5,700,000.00 and PAL itself without cause. In fact, PAL admitted that at the
RSS had rendered advisory services for only seven (7) time their services were terminated the Complainants
months from January 4, 1999 to July 31, 1999 that would were performing well in their respective assigned
entitle RSS to an (sic) advisory fees of only works. 22 . . . .
US$1,662,500.00 and therefore the unserved period of
PAL also presented hypothetical situations and
17 months equivalent to US$4,037,500.00 should be
certain computations that it claims would result to an
refunded. And setting off the termination penalties of
"injustice" to PAL which would then "lose a very
US$3,300,000.00 due RSS from PAL against the
substantial amount of money" if the claimed refund is not
amount of US$4,037,500.00 still due PAL from RSS
allowed. PAL had chosen to pre-terminate the services
there would remain a net balance of US$737,500.00 still
of the complainants and must therefore pay the
due PAL from RSS and/or the Senior Technical Advisers
termination penalties provided in the Side Letter. If it
which the latter should pay pro-rata as follows: Peter W.
finds itself losing "substantial" sums of money because
Forster, the sum of US$178,475.00; Richard T. Nuttall,
of its contractual commitments, there is nothing this
the sum of US$178,475.00; Michael R. Scantlebury; the
Arbitration Tribunal can do to remedy the situation.
sum of US$156,350.00, Andrew D. Fyfe, the sum of
Jurisprudence teaches us that neither the law nor the
US$111,362.50; and Richard J. Wald the sum of
courts will extricate a party from an unwise or
US$111,362.50. RSS is a special company which the
undesirable contract that he or she entered into with all
Senior Technical Advisers had utilized for the specific
the required formalities and with full awareness of its
purpose of providing PAL with technical advisory
services they as a group had contracted under the
consequences. (Opulencia vs. Court of Appeals, 293 enough to confer jurisdiction upon the Court over the
SCRA 385 (1998) 23 adverse party.
Decision of the RTC It is not disputed that complainants were duly
served by personal delivery with copies of the application
Dissatisfied with the outcome, the respondent filed its Application
to vacate. In fact, they have appeared through counsel
to Vacate Arbitral Award in the Regional Trial Court, in Makati City
and have filed pleadings. In line with this ruling, the
(RTC), docketed as SP Proc. M-5147 and assigned to Branch
objection that the application to vacate does not state a
57, 24 arguing that the arbitration decision should be vacated in view of
cause of action against complainants must necessarily
the July 1, 1998 order of the SEC placing the respondent under a state of
fall inasmuch as this present case is a special
suspension of payment pursuant to Section 6 (c) of Presidential Decree
proceeding (Sec. 22, Arbitration Law), and Section 3 (a),
No. 902-A, as amended by P.D. No. 1799. 25
Rule 1 of the 1997 Rules of Civil Procedure is
The petitioners countered with their Motion to Dismiss, 26 citing inapplicable here. 30
the following grounds, namely: (a) lack of jurisdiction over the persons of
On whether or not the application to vacate was an appropriate
the petitioners due to the improper service of summons; (b) the
remedy under Sections 24 and 26 of the Arbitration Law, and whether or
application did not state a cause of action; and (c) the application was an
not the July 1, 1998 order of the SEC deprived the Panel of Arbitrators of
improper remedy because the respondent should have filed an appeal in
the authority to hear the petitioners' claim, the RTC held:
the CA pursuant to Rule 43 of the Rules of Court. 27
The rationale for the suspension is to enable the
On March 7, 2001, the RTC granted the respondent's Application
rehabilitation receiver to exercise his powers without any
to Vacate Arbitral Award, 28 disposing:
judicial or extra-judicial interference that might unduly
WHEREFORE, the subject arbitral award dated hinder the rescue of the distressed corporation. . . . . PD
September 29, 2000 is hereby vacated and set aside, No. 902-A does not provide for the duration of the
without prejudice to the complainants' filing with the SEC suspension; therefore, it is deemed to be effective during
rehabilitation receiver of PAL their subject claim for the entire period that the corporate debtor is under SEC
appropriate adjudication. The panel of arbitrators receivership.
composed of lawyers Beda Fajardo, Arturo de Castro
There is no dispute that PAL is under
and Bienvenido Magnaye is hereby ordered discharged
receivership (Exhibits "1" and "2"). In its Order dated 1
on the ground of manifest partiality. DETACa
July 1998, the SEC declared that "all claims for payment
No pronouncement as to cost and attorney's against PAL are deemed suspended." This Order
fees. effectively deprived all other tribunals of jurisdiction to
hear and decide all actions for claims against PAL for the
SO ORDERED. 29 duration of the receivership.
Anent jurisdiction over the persons of the petitioners, the RTC xxx xxx xxx
opined:
Unless and until the SEC lifts the Order dated 1
On the objection that the Court has not acquired July 1998, the Panel of Arbitrators cannot take
jurisdiction over the person of the complainants because cognizance of complainant' claims against PAL without
summonses were not issued and served on them, the violating the exclusive jurisdiction of the SEC. The law
Court rules that complainants have voluntarily submitted has granted SEC the exclusive jurisdiction to pursue the
themselves to the jurisdiction of the Court by praying the rehabilitation of a private corporation through the
Court to grant them affirmative relief, i.e., that the Court appointment of a rehabilitation receiver (Sec. 6 (d), PD
confirm and declare final and executory the subject No. 902-A, as amended by PD 1799). "exclusive
arbitral award. Moreover, under Sections 22 and 26 of jurisdiction precludes the idea of co-existence and refers
the Arbitration Law (R.A. 876), an application or petition to jurisdiction possessed to the exclusion of others. . . . .
to vacate arbitral award is deemed a motion and service Thus, "(I)nstead of vexing the courts with suits against
of such motion on the adverse party or his counsel is
the distressed firm, they are directed to file their claims The petitioners moved for reconsideration, 38 but the CA denied
with the receiver who is the duly appointed officer of the their motion. 39
SEC. . . . . 31
Hence, this appeal by the petitioners.
After their motion for reconsideration 32 was denied, 33 the
Issues
petitioners appealed to the CA by notice of appeal.
The petitioners anchor this appeal on the following grounds,
Resolution of the CA
namely:
The respondent moved to dismiss the appeal, 34 arguing against
I
the propriety of the petitioners' remedy, and positing that Section 29 of
the Arbitration Law limited appeals from an order issued in a proceeding SECTION 29 OF THE ARBITRATION LAW, WHICH
under the Arbitration Law to a review on certiorari upon questions of LIMITS THE MODE OF APPEAL FROM THE ORDER
law. 35 OF A REGIONAL TRIAL COURT IN A PROCEEDING
MADE UNDER THE ARBITRATION LAW TO A
On May 30, 2003, the CA promulgated the now assailed
PETITION FOR REVIEW ON CERTIORARI UNDER
resolution granting the respondent's Motion to Dismiss Appeal. 36 It
RULE 45 OF THE RULES, IS UNCONSTITUTIONAL
declared that the appropriate remedy against the order of the RTC
FOR UNDULY EXPANDING THE JURISDICTION OF
vacating the award was a petition for review on certiorari under Rule
THIS HONORABLE COURT WITHOUT THIS
45, viz.:
HONORABLE COURT'S CONCURRENCE;
The term "certiorari" in the aforequoted provision
II
refers to an ordinary appeal under Rule 45, not the
special action of certiorari under Rule 65. As Section 29 THE COURT OF APPEALS HAD JURISDICTION OVER
proclaims, it is an "appeal." This being the case, the THE CA APPEAL BECAUSE:
proper forum for this action is, under the old and the new
A.
rules of procedure, the Supreme Court. Thus, Section
2(c) of Rule 41 of the 1997 Rules of Civil Procedure THIS HONORABLE COURT HAS PREVIOUSLY
states that, UPHELD THE EXERCISE BY THE COURT OF
APPEALS OF JURISDICTION OVER AN APPEAL
"In all cases where only
INVOLVING QUESTIONS OF FACT OR OF MIXED
questions of law are raised or involved,
QUESTIONS OF FACT AND LAW FROM A REGIONAL
the appeal shall be to the Supreme
TRIAL COURT'S ORDER VACATING AN ARBITRAL
Court by petition for review on certiorari
AWARD
in accordance with Rule 45."
B.
Furthermore, Section 29 limits the appeal to
"questions of law," another indication that it is referring to WHERE, AS IN THIS CASE, THE ISSUES ON APPEAL
an appeal by certiorari under Rule 45 which, indeed, is CONCERNED THE ABSENCE OF EVIDENCE AND
the customary manner of reviewing such issues. LACK OF LEGAL BASIS TO SUPPORT THE
REGIONAL TRIAL COURT'S ORDER VACATING THE
Based on the foregoing, it is clear that
ARBITRAL AWARD, GRAVE MISCHIEF WOULD
complainants-in-arbitration/appellants filed the wrong
RESULT IF THE REGIONAL TRIAL COURT'S
action with the wrong forum.
BASELESS FINDINGS OF FACT OR MIXED FINDINGS
WHEREFORE, premises considered, the Motion OF FACT ARE PLACED BEYOND APPELLATE
to Dismiss Appeal (Without Prejudice to the Filing of REVIEW; AND
Appellee's Brief) is GRANTED and the instant appeal is
C.
hereby ordered DISMISSED.
THE COURT OF APPEALS' DISMISSAL OF THE CA
SO ORDERED. 37
APPEAL WOULD IN EFFECT RESULT IN THE
AFFIRMATION OF THE REGIONAL TRIAL COURT'S seek affirmative relief because under Section 20, Rule 14 of the Rules of
EXERCISE OF JURISDICTION, OVER PERSONS Court their objection to the personal jurisdiction of the court was not a
UPON WHOM IT FAILED TO VALIDLY ACQUIRE voluntary appearance even if coupled with other grounds for a motion to
SUCH JURISDICTION AND OF APPELLATE dismiss.
JURISDICTION OVER THE PDRCI ARBITRAL AWARD
In riposte, the respondent avers that the petition for review
EVEN IF SUCH APPELLATE POWER IS
on certiorari should be denied due course because of the defective
EXCLUSIVELY LODGED WITH THE COURT OF
verification/certification signed by the petitioners' counsel; and that the
APPEALS UNDER RULE 43 OF THE RULES aDSIHc
special powers of attorney (SPAs) executed by the petitioners in favor of
III their counsel did not sufficiently vest the latter with the authority to
execute the verification/certification in their behalf.
INSTEAD OF DISMISSING THE CA APPEAL
OUTRIGHT, THE COURT OF APPEALS SHOULD On the merits, the respondent maintains that: (a) the
HAVE SHORTENED THE PROCEEDINGS AND term certiorari used in Section 29 of the Arbitration Law refers to a
EXPEDITED JUSTICE BY EXERCISING ORIGINAL petition for review under Rule 45 of the Rules of Court; (b) the
JURISDICTION OVER THE APPLICATION TO VACATE constitutional challenge against Section 29 of the Arbitration Law was
PURSUANT TO RULE 43 OF THE RULES, belatedly made; (c) the petitioners' claim of lack of jurisdiction on the part
ESPECIALLY CONSIDERING THAT THE PARTIES of the RTC should fail because an application to vacate an arbitral award
HAD IN FACT ALREADY FILED THEIR RESPECTIVE under Sections 22 and 26 of the Arbitration Law is only required to be in
BRIEFS AND THE COMPLETE RECORDS OF BOTH the form of a motion; and (d) the complete record of the arbitration
THE RTC APPLICATION TO VACATE AND THE PDRCI proceedings submitted to the RTC sufficiently proved the manifest
ARBITRATION WERE ALREADY IN ITS POSSESSION; partiality and grave abuse of discretion on the part of the panel of
AND arbitrators.
IV To be resolved are: (a) whether or not the petition for review
should be dismissed for containing a defective verification/certification;
IN THE EVENT THAT AN APPEAL FROM AN ORDER
and (b) whether or not the CA erred in dismissing the appeal of the
VACATING AN ARBITRAL AWARD MAY BE MADE
petitioners for being an inappropriate remedy.
ONLY IN CERTIORARI PROCEEDINGS AND ONLY
TO THE SUPREME COURT, THE COURT OF Ruling of the Court
APPEALS SHOULD NOT HAVE DISMISSED THE CA
We deny the petition for review on certiorari.
APPEAL, BUT IN THE HIGHER INTEREST OF
JUSTICE, SHOULD HAVE INSTEAD ENDORSED THE I
SAME TO THIS HONORABLE COURT, AS WAS DONE
There was sufficient compliance with the rule on
IN SANTIAGO V. GONZALES. 40
verification and certification against forum shopping
The petitioners contend that an appeal from the order arising
The respondent insists that the verification/certification attached
from arbitration proceedings cannot be by petition for review
to the petition was defective because it was executed by the petitioners'
on certiorari under Rule 45 of the Rules of Court because the appeal
counsel whose authority under the SPAs was only to execute the
inevitably involves mixed questions of law and fact; that their appeal in
certification of non-forum shopping; and that the signing by the counsel
the CA involved factual issues in view of the RTC's finding that the panel
of the certification could not also be allowed because the Rules of
of arbitrators had been guilty of evident partiality even without having
Court and the pertinent circulars and rulings of the Court require that the
required the respondent to submit independent proof thereon; that the
petitioners must themselves execute the same. ATICcS
appropriate remedy was either a petition for certiorari under Rule 65 of
the Rules of Court, or an ordinary appeal under Rule 41 of the Rules of The insistence of the respondent is unwarranted. The SPAs
Court, conformably with the rulings in Asset Privatization Trust v. Court individually signed by the petitioners vested in their counsel the authority,
of Appeals 41 and Adamson v. Court of Appeals, 42 respectively; and among others, "to do and perform on my behalf any act and deed
that the CA erroneously upheld the RTC's denial of their Motion to relating to the case, which it could legally do and perform, including any
Dismiss Appeal on the basis of their counsel's voluntary appearance to appeals or further legal proceedings." The authority was sufficiently
broad to expressly and specially authorize their counsel, Atty. Ida Appealing the RTC order
Maureen V. Chao-Kho, to sign the verification/certification on their behalf. vacating an arbitral award
The purpose of the verification is to ensure that the allegations The petitioners contend that the CA gravely erred in dismissing
contained in the verified pleading are true and correct, and are not the their appeal for being an inappropriate remedy, and in holding that a
product of the imagination or a matter of speculation; and that the petition for review on certiorari under Rule 45 was the sole remedy under
pleading is filed in good faith. 43 This purpose was met by the Section 29 of the Arbitration Law. They argue that the decision of the
verification/certification made by Atty. Chao-Kho in behalf of the RTC involving arbitration could be assailed either by petition
petitioners, which pertinently stated that: for certiorari under Rule 65, as held in Asset Privatization Trust, or by an
ordinary appeal under Rule 41, as opined in Adamson.
2. Petitioners caused the preparation of the
foregoing Petition for Review on Certiorari, and have The petitioners are mistaken.
read and understood all the allegations contained
Firstly, the assailed resolution of the CA did not expressly
therein. Further, said allegations are true and correct
declare that the petition for review on certiorari under Rule 45 was the
based on their own knowledge and authentic records in
sole remedy from the RTC's order vacating the arbitral award. The CA
their and the Firm's possession. 44
rather emphasized that the petitioners should have filed the petition for
The tenor of the verification/certification indicated that the review on certiorari under Rule 45 considering that Section 29 of the
petitioners, not Atty. Chao-Kho, were certifying that the allegations were Arbitration Law has limited the ground of review to "questions of law."
true and correct based on their knowledge and authentic records. At any Accordingly, the CA correctly dismissed the appeal of the petitioners
rate, a finding that the verification was defective would not render the because pursuant to Section 2, 49 Rule 41 of the Rules of Court an
petition for review invalid. It is settled that the verification was merely a appeal of questions of law arising in the courts in the first instance is by
formal requirement whose defect did not negate the validity or efficacy of petition for review on certiorari under Rule 45.
the verified pleading, or affect the jurisdiction of the court. 45
It is noted, however, that since the promulgation of the assailed
We also uphold the efficacy of the certification on non-forum decision by the CA on May 30, 2003, the law on the matter underwent
shopping executed by Atty. Chao-Kho on the basis of the authorization changes. On February 4, 2004. Republic Act No. 9285 (Alternative
bestowed under the SPAs by the petitioners. The lawyer of the party, in Dispute Resolution Act of 2004) was passed by Congress, and was
order to validly execute the certification, must be "specifically authorized" approved by the President on April 2, 2004. Pursuant to Republic Act No.
by the client for that purpose. 46 With the petitioners being non-residents 9285, the Court promulgated on September 1, 2009 in A.M. No. 07-11-
of the Philippines, the sworn certification on non-forum shopping by Atty. 08-SC the Special Rules of Court on Alternative Dispute
Chao-Kho sufficiently complied with the objective of ensuring that no Resolution, which are now the present rules of procedure governing
similar action had been brought by them or the respondent against each arbitration. Among others, the Special Rules of Court on Alternative
other, to wit: Dispute Resolution requires an appeal by petition for review to the CA of
the final order of the RTC confirming, vacating, correcting or modifying a
5. Significantly, Petitioners are foreign residents
domestic arbitral award, to wit:
who reside and are presently abroad. Further, the Firm is
Petitioners' sole legal counsel in the Philippines, and Rule 19.12 Appeal to the Court of Appeals. — An appeal
hence, is in a position to know that Petitioners have no to the Court of Appeals through a petition for review
other cases before any court o[r] tribunal in the under this Special Rule shall only be allowed from the
Philippines; 47 following orders of the Regional Trial Court:
In this regard, we ought not to exact a literal compliance with a. Granting or denying an interim measure of protection;
Section 4, Rule 45, in relation to Section 2, Rule 42 of the Rules of b. Denying a petition for appointment of an arbitrator;
Court, that only the party himself should execute the certification. After
all, we have not been shown by the respondent any intention on the part c. Denying a petition for assistance in taking evidence;
of the petitioners and their counsel to circumvent the requirement for the d. Enjoining or refusing to enjoin a person from divulging
verification and certification on non-forum shopping. 48 confidential information;
II
e. Confirming, vacating or correcting/modifying a on Adamson to buttress their resort to the erroneous remedy was
domestic arbitral award; misplaced. TIADCc
f. Setting aside an international commercial arbitration We remind that the petitioners cannot insist on their chosen
award; remedy despite its not being sanctioned by the Arbitration Law. Appeal
g. Dismissing the petition to set aside an international as a remedy is not a matter of right, but a mere statutory privilege to be
commercial arbitration award even if the court exercised only in the manner and strictly in accordance with the
does not decide to recognize or enforce such provisions of the law. 53
award; III
h. Recognizing and/or enforcing an international Panel of Arbitrators had no jurisdiction
commercial arbitration award; to hear and decide the petitioners' claim
i. Dismissing a petition to enforce an international The petitioners' appeal is dismissible also because the arbitration
commercial arbitration award; panel had no jurisdiction to hear their claim. The RTC correctly opined
j. Recognizing and/or enforcing a foreign arbitral award; that the SEC's suspension order effective July 1, 1998 deprived the
arbitration panel of the jurisdiction to hear any claims against the
k. Refusing recognition and/or enforcement of a foreign
respondent. The Court has clarified in Castillo v. Uniwide Warehouse
arbitral award;
Club, Inc. 54 why the claim for payment brought against a distressed
l. Granting or dismissing a petition to enforce a deposited corporation like the respondent should not prosper following the issuance
mediated settlement agreement; and of the suspension order by the SEC, regardless of when the action was
m. Reversing the ruling of the arbitral tribunal upholding its filed, to wit:
jurisdiction. Jurisprudence is settled that the suspension of
Although the Special Rules of Court on Alternative Dispute proceedings referred to in the law uniformly applies to all
Resolution provides that the appropriate remedy from an order of the actions for claims filed against a corporation, partnership
RTC vacating a domestic arbitral award is an appeal by petition for or association under management or receivership,
review in the CA, not an ordinary appeal under Rule 41 of the Rules of without distinction, except only those expenses incurred
Court, the Court cannot set aside and reverse the assailed decision on in the ordinary course of business. In the oft-cited case
that basis because the decision was in full accord with the law or rule in of Rubberworld (Phils.) Inc. v. NLRC, the Court noted
force at the time of its promulgation. that aside from the given exception, the law is clear and
males no distinction as to the claims that are suspended
The ruling in Asset Privatization Trust v. Court of once a management committee is created or a
Appeals 50 cannot be the governing rule with respect to the order of the rehabilitation receiver is appointed. Since the law makes
RTC vacating an arbitral award. Asset Privatization Trust justified the no distinction or exemptions, neither should this
resort to the petition for certiorari under Rule 65 only upon finding that Court. Ubi lex non distinguit nec nos distinguere
the RTC had acted without jurisdiction or with grave abuse of discretion debemos. Philippine Airlines, Inc. v. Zamora declares
in confirming the arbitral award. Nonetheless, it is worth reminding that that the automatic suspension of an action for claims
the petition for certiorari cannot be a substitute for a lost appeals. 51 against a corporation under a rehabilitation receiver or
management committee embraces all phases of the suit,
Also, the petitioners have erroneously assumed that the appeal
that is, the entire proceedings of an action or suit and not
filed by the aggrieved party in Adamson v. Court of Appeals 52 was an
just the payment of claims.
ordinary one. Adamson concerned the correctness of the ruling of the
CA in reversing the decision of the trial court, not the propriety of the The reason behind the imperative nature of a
remedy availed of by the aggrieved party. Nor did Adamson expressly suspension or stay order in relation to the creditors
declare that an ordinary appeal could be availed of to assail the RTC's claims cannot be downplayed, for indeed the
ruling involving arbitration. As such, the petitioners' reliance indiscriminate suspension of actions for claims
intends to expedite the rehabilitation of the
distressed corporation by enabling the management award was filed or delivered "as prescribed by law for the service upon
committee or the rehabilitation receiver to effectively an attorney in an action."
exercise its/his powers free from any judicial or
V
extrajudicial interference that might unduly hinder or
prevent the rescue of the debtor company. To allow Issue of the constitutionality of the
such other actions to continue would only add to the Arbitration Law is devoid of merit
burden of the management committee or
The constitutionality of Section 29 of the Arbitration Law is being
rehabilitation receiver, whose time, effort and
challenged on the basis that Congress has thereby increased the
resources would be wasted in defending claims
appellate jurisdiction of the Supreme Court without its advice and
against the corporation, instead of being directed
concurrence, as required by Section 30, Article VI of the 1987
toward its restructuring and rehabilitation.
Constitution, to wit:
At this juncture, it must be conceded that the
Section 30. No law shall be passed increasing
date when the claim arose, or when the action was
the appellate jurisdiction of the Supreme Court as
filed, has no bearing at all in deciding whether the
provided in this Constitution without its advice and
given action or claim is covered by the stay or
concurrence.
suspension order. What matters is that as long as
the corporation is under a management committee The challenge is unworthy of consideration. Based on the tenor
or a rehabilitation receiver, all actions for claims and text of Section 30, Article VI of the 1987 Constitution, the prohibition
against it, whether for money or otherwise, must against increasing the appellate jurisdiction of the Supreme Court without
yield to the greater imperative of corporate revival, its advice and concurrence applies prospectively, not retrospectively.
excepting only, as already mentioned, claims for Considering that the Arbitration Law had been approved on June 19,
payment of obligations incurred by the corporation 1953, and took effect under its terms on December 19, 1953, while the
in the ordinary course of business. 55 (Bold emphasis Constitution was ratified only on February 2, 1987, Section 29 of the
supplied) Arbitration Law could not be declared unconstitutional.
IV WHEREFORE, the Court DENIES the petition for review
on certiorari for lack of merit; AFFIRMS the resolution promulgated on
The requirement of due process was observed
May 30, 2003 by the Court of Appeals in CA-G.R. CV No. 71224;
The petitioners' challenge against the jurisdiction of the RTC on and ORDERS the petitioners to pay the costs of suit.
the ground of the absence of the service of the summons on them also
SO ORDERED.
fails.
Under Section 22 56 of the Arbitration Law, arbitration is deemed
a special proceeding, by virtue of which any application should be made
in the manner provided for the making and hearing of motions, except as
otherwise expressly provided in the Arbitration Law.
The RTC observed that the respondent's Application to Vacate
Arbitral Award was duly served personally on the petitioners, who then
appeared by counsel and filed pleadings. The petitioners countered with
their Motion to Dismiss vis-à-vis the respondent's application, specifying
therein the various grounds earlier mentioned, including the lack of
jurisdiction over their persons due to the improper service of summons.
Under the circumstances, the requirement of notice was fully complied
with, for Section 26 57 of the Arbitration Law required the application to
be served upon the adverse party or his counsel within 30 days after the
SECOND DIVISION despite Shangri-La's default. 5 According to BF Corporation, Shangri-La
misrepresented that it had funds to pay for its obligations with BF
Corporation, and the delay in payment was simply a matter of delayed
[G.R. No. 174938. October 1, 2014.] processing of BF Corporation's progress billing statements. 6
BF Corporation eventually completed the construction of the
GERARDO LANUZA, JR. AND ANTONIO O.
buildings. 7 Shangri-La allegedly took possession of the buildings while still
OLBES, petitioners, vs. BF CORPORATION, SHANGRI-
owing BF Corporation an outstanding balance. 8
LA PROPERTIES, INC., ALFREDO C. RAMOS, RUFO B.
COLAYCO, MAXIMO G. LICAUCO III, AND BENJAMIN BF Corporation alleged that despite repeated demands, Shangri-La
C. RAMOS, respondents. refused to pay the balance owed to it. 9 It also alleged that the Shangri-La's
directors were in bad faith in directing Shangri-La's affairs. Therefore, they
should be held jointly and severally liable with Shangri-La for its obligations
as well as for the damages that BF Corporation incurred as a result of
DECISION Shangri-La's default. 10
On August 3, 1993, Shangri-La, Alfredo C. Ramos, Rufo B. Colayco,
Maximo G. Licauco III, and Benjamin C. Ramos filed a motion to suspend the
LEONEN, J p: proceedings in view of BF Corporation's failure to submit its dispute to
arbitration, in accordance with the arbitration clause provided in its contract,
Corporate representatives may be compelled to submit to arbitration quoted in the motion as follows: 11
proceedings pursuant to a contract entered into by the corporation they
represent if there are allegations of bad faith or malice in their acts 35. Arbitration
representing the corporation.
(1) Provided always that in case any dispute or
This is a Rule 45 petition, assailing the Court of Appeals' May 11, difference shall arise between the Owner
2006 decision and October 5, 2006 resolution. The Court of Appeals affirmed or the Project Manager on his behalf and
the trial court's decision holding that petitioners, as directors, should submit the Contractor, either during the progress
themselves as parties to the arbitration proceedings between BF Corporation or after the completion or abandonment of
and Shangri-La Properties, Inc. (Shangri-La). the Works as to the construction of this
Contract or as to any matter or thing of
In 1993, BF Corporation filed a collection complaint with the Regional whatsoever nature arising thereunder or in
Trial Court against Shangri-La and the members of its board of directors: connection therewith (including any matter
Alfredo C. Ramos, Rufo B. Colayco, Antonio O. Olbes, Gerardo Lanuza, Jr., or thing left by this Contract to the
Maximo G. Licauco III, and Benjamin C. Ramos. 1 discretion of the Project Manager or the
withholding by the Project Manager of any
BF Corporation alleged in its complaint that on December 11, 1989
certificate to which the Contractor may
and May 30, 1991, it entered into agreements with Shangri-La wherein it
claim to be entitled or the measurement
undertook to construct for Shangri-La a mall and a multilevel parking
and valuation mentioned in clause 30(5)
structure along EDSA. 2
(a) of these Conditions or the rights and
Shangri-La had been consistent in paying BF Corporation in liabilities of the parties under clauses 25,
accordance with its progress billing statements. 3 However, by October 26, 32 or 33 of these Conditions), the
1991, Shangri-La started defaulting in payment. 4 owner and the Contractor hereby agree to
exert all efforts to settle their differences or
BF Corporation alleged that Shangri-La induced BF Corporation to dispute amicably. Failing these efforts
continue with the construction of the buildings using its own funds and credit then such dispute or difference shall be
referred to arbitration in accordance with Petitioners filed their comment on Shangri-La's and BF Corporation's
the rules and procedures of the Philippine motions, praying that they be excluded from the arbitration proceedings for
Arbitration Law. being non-parties to Shangri-La's and BF Corporation's agreement. 24
xxx xxx xxx On July 28, 2003, the trial court issued the order directing service of
demands for arbitration upon all defendants in BF Corporation's
(6) The award of such Arbitrators shall be final and
complaint. 25 According to the trial court, Shangri-La's directors were
binding on the parties. The decision of the
interested parties who "must also be served with a demand for arbitration to
Arbitrators shall be a condition precedent
give them the opportunity to ventilate their side of the controversy, safeguard
to any right of legal action that either party
their interest and fend off their respective positions." 26 Petitioners' motion
may have against the
for reconsideration of this order was denied by the trial court on January 19,
other. . . . 12 (Underscoring in the original)
2005. 27 SIcEHD
On August 19, 1993, BF Corporation opposed the motion to suspend
Petitioners filed a petition for certiorari with the Court of Appeals,
proceedings. 13
alleging grave abuse of discretion in the issuance of orders compelling them
In the November 18, 1993 order, the Regional Trial Court denied the to submit to arbitration proceedings despite being third parties to the contract
motion to suspend proceedings. 14 between Shangri-La and BF Corporation. 28
On December 8, 1993, petitioners filed an answer to BF In its May 11, 2006 decision, 29 the Court of Appeals dismissed
Corporation's complaint, with compulsory counterclaim against BF petitioners' petition for certiorari. The Court of Appeals ruled that Shangri-La's
Corporation and cross-claim against Shangri-La. 15 They alleged that they directors were necessary parties in the arbitration proceedings. 30 According
had resigned as members of Shangri-La's board of directors as of July 15, to the Court of Appeals:
1991. 16
[They were] deemed not third-parties to the
After the Regional Trial Court denied on February 11, 1994 the contract as they [were] sued for their acts in representation
motion for reconsideration of its November 18, 1993 order, Shangri-La, of the party to the contract pursuant to Art. 31 of the
Alfredo C. Ramos, Rufo B. Colayco, Maximo G. Licauco III, and Benjamin Corporation Code, and that as directors of the defendant
Ramos filed a petition for certiorari with the Court of Appeals. 17 corporation, [they], in accordance with Art. 1217 of the Civil
Code, stand to be benefited or injured by the result of the
On April 28, 1995, the Court of Appeals granted the petition arbitration proceedings, hence, being necessary parties,
for certiorari and ordered the submission of the dispute to arbitration. 18 they must be joined in order to have complete adjudication
of the controversy. Consequently, if [they were] excluded
Aggrieved by the Court of Appeals' decision, BF Corporation filed a
as parties in the arbitration proceedings and an arbitral
petition for review on certiorari with this court. 19 On March 27, 1998, this
award is rendered, holding [Shangri-La] and its board of
court affirmed the Court of Appeals' decision, directing that the dispute be
directors jointly and solidarily liable to private respondent
submitted for arbitration. 20
BF Corporation, a problem will arise, i.e., whether
Another issue arose after BF Corporation had initiated arbitration petitioners will be bound by such arbitral award, and this
proceedings. BF Corporation and Shangri-La failed to agree as to the law will prevent complete determination of the issues and
that should govern the arbitration proceedings. 21 On October 27, 1998, the resolution of the controversy. 31
trial court issued the order directing the parties to conduct the proceedings in
The Court of Appeals further ruled that "excluding petitioners in the
accordance with Republic Act No. 876. 22
arbitration proceedings . . . would be contrary to the policy against multiplicity
Shangri-La filed an omnibus motion and BF Corporation an urgent of suits." 32
motion for clarification, both seeking to clarify the term, "parties," and whether
The dispositive portion of the Court of Appeals' decision reads:
Shangri-La's directors should be included in the arbitration proceedings and
served with separate demands for arbitration. 23 WHEREFORE, the petition is DISMISSED. The
assailed orders dated July 28, 2003 and January 19, 2005
of public respondent RTC, Branch 157, Pasig City, in Civil Code. 50 Section 31 makes directors solidarily liable for fraud, gross
Case No. 63400, are AFFIRMED. 33 negligence, and bad faith. 51 Petitioners are not really third parties to the
agreement because they are being sued as Shangri-La's representatives,
The Court of Appeals denied petitioners' motion for reconsideration under Section 31 of the Corporation Code. 52
in the October 5, 2006 resolution. 34
BF Corporation further argued that because petitioners were
On November 24, 2006, petitioners filed a petition for review of the impleaded for their solidary liability, they are necessary parties to the
May 11, 2006 Court of Appeals decision and the October 5, 2006 Court of arbitration proceedings. 53 The full resolution of all disputes in the arbitration
Appeals resolution. 35 proceedings should also be done in the interest of justice. 54
The issue in this case is whether petitioners should be made parties In the manifestation dated September 6, 2007, petitioners informed
to the arbitration proceedings, pursuant to the arbitration clause provided in the court that the Arbitral Tribunal had already promulgated its decision on
the contract between BF Corporation and Shangri-La. July 31, 2007. 55 The Arbitral Tribunal denied BF Corporation's claims
Petitioners argue that they cannot be held personally liable for against them. 56 Petitioners stated that "[they] were included by the Arbitral
corporate acts or obligations. 36 The corporation is a separate being, and Tribunal in the proceedings conducted . . . notwithstanding [their] continuing
nothing justifies BF Corporation's allegation that they are solidarily liable with objection thereto. . ." 57 They also stated that "[their] unwilling participation in
Shangri-La. 37 Neither did they bind themselves personally nor did they the arbitration case was done ex abundante ad cautela, as manifested
undertake to shoulder Shangri-La's obligations should it fail in its therein on several occasions." 58 Petitioners informed the court that they
obligations. 38 BF Corporation also failed to establish fraud or bad faith on already manifested with the trial court that "any action taken on [the Arbitral
their part. 39 Tribunal's decision] should be without prejudice to the resolution of [this]
case." 59
Petitioners also argue that they are third parties to the contract
between BF Corporation and Shangri-La. 40 Provisions including arbitration Upon the court's order, petitioners and Shangri-La filed their
stipulations should bind only the parties. 41 Based on our arbitration laws, respective memoranda. Petitioners and Maximo G. Licauco III, Alfredo C.
parties who are strangers to an agreement cannot be compelled to Ramos, and Benjamin C. Ramos reiterated their arguments that they should
arbitrate. 42 not be held liable for Shangri-La's default and made parties to the arbitration
proceedings because only BF Corporation and Shangri-La were parties to
Petitioners point out that our arbitration laws were enacted to the contract.
promote the autonomy of parties in resolving their disputes. 43 Compelling
them to submit to arbitration is against this purpose and may be tantamount In its memorandum, Shangri-La argued that petitioners were
to stipulating for the parties. 44 impleaded for their solidary liability under Section 31 of the Corporation
Code. Shangri-La added that their exclusion from the arbitration proceedings
Separate comments on the petition were filed by BF Corporation, will result in multiplicity of suits, which "is not favored in this jurisdiction." 60 It
and Maximo G. Licauco III, Alfredo C. Ramos and Benjamin C. Ramos. 45 pointed out that the case had already been mooted by the termination of the
arbitration proceedings, which petitioners actively participated
Maximo G. Licauco III, Alfredo C. Ramos, and Benjamin C. Ramos in. 61 Moreover, BF Corporation assailed only the correctness of the Arbitral
agreed with petitioners that Shangri-La's directors, being non-parties to the Tribunal's award and not the part absolving Shangri-La's directors from
contract, should not be made personally liable for Shangri-La's acts. 46 Since liability. 62
the contract was executed only by BF Corporation and Shangri-La, only they
should be affected by the contract's stipulation. 47 BF Corporation also failed BF Corporation filed a counter-manifestation with motion to
to specifically allege the unlawful acts of the directors that should make them dismiss 63 in lieu of the required memorandum.
solidarily liable with Shangri-La for its obligations. 48
In its counter-manifestation, BF Corporation pointed out that since
Meanwhile, in its comment, BF Corporation argued that the courts' "petitioners' counterclaims were already dismissed with finality, and the
ruling that the parties should undergo arbitration "clearly contemplated the claims against them were likewise dismissed with finality, they no longer
inclusion of the directors of the corporation[.]" 49 have any interest or personality in the arbitration case. Thus, there is no
longer any need to resolve the present Petition, which mainly questions the
BF Corporation also argued that while petitioners were not parties to inclusion of petitioners in the arbitration proceedings." 64 The court's decision
the agreement, they were still impleaded under Section 31 of the Corporation
in this case will no longer have any effect on the issue of petitioners' inclusion domiciled or where the dispute occurred. It is true that
in the arbitration proceedings. 65 there are authorities which hold that "a clause in a contract
providing that all matters in dispute between the parties
The petition must fail. shall be referred to arbitrators and to them alone, is
The Arbitral Tribunal's decision, absolving petitioners from liability, contrary to public policy and cannot oust the courts of
and its binding effect on BF Corporation, have rendered this case moot and jurisdiction" (Manila Electric Co. vs. Pasay Transportation
academic. Co., 57 Phil., 600, 603), however, there are authorities
which favor "the more intelligent view that arbitration,
The mootness of the case, however, had not precluded us from as an inexpensive, speedy and amicable method of
resolving issues so that principles may be established for the guidance of the settling disputes, and as a means of avoiding
bench, bar, and the public. In De la Camara v. Hon. Enage, 66 this court litigation, should receive every encouragement from
disregarded the fact that petitioner in that case already escaped from prison the courts which may be extended without
and ruled on the issue of excessive bails: DAcaIE contravening sound public policy or settled law" (3
Am. Jur., p. 835). Congress has officially adopted the
While under the circumstances a ruling on the modern view when it reproduced in the new Civil Code
merits of the petition for certiorari is not warranted, still, as the provisions of the old Code on Arbitration. And only
set forth at the opening of this opinion, the fact that this recently it approved Republic Act No. 876 expressly
case is moot and academic should not preclude this authorizing arbitration of future disputes. 72 (Emphasis
Tribunal from setting forth in language clear and supplied)
unmistakable, the obligation of fidelity on the part of lower
court judges to the unequivocal command of the In view of our policy to adopt arbitration as a manner of settling
Constitution that excessive bail shall not be required. 67 disputes, arbitration clauses are liberally construed to favor arbitration. Thus,
in LM Power Engineering Corporation v. Capitol Industrial Construction
This principle was repeated in subsequent cases when this court Groups, Inc., 73 this court said:
deemed it proper to clarify important matters for guidance. 68
Being an inexpensive, speedy and amicable
Thus, we rule that petitioners may be compelled to submit to the method of settling disputes, arbitration — along with
arbitration proceedings in accordance with Shangri-La and BF Corporation's mediation, conciliation and negotiation — is encouraged by
agreement, in order to determine if the distinction between Shangri-La's the Supreme Court. Aside from unclogging judicial
personality and their personalities should be disregarded. dockets, arbitration also hastens the resolution of disputes,
This jurisdiction adopts a policy in favor of arbitration. Arbitration especially of the commercial kind. It is thus regarded as
allows the parties to avoid litigation and settle disputes amicably and more the "wave of the future" in international civil and
expeditiously by themselves and through their choice of arbitrators. commercial disputes. Brushing aside a contractual
agreement calling for arbitration between the parties would
The policy in favor of arbitration has been affirmed in our Civil be a step backward.
Code, 69 which was approved as early as 1949. It was later institutionalized
by the approval of Republic Act No. 876, 70 which expressly authorized, Consistent with the above-mentioned policy of
made valid, enforceable, and irrevocable parties' decision to submit their encouraging alternative dispute resolution methods,
controversies, including incidental issues, to arbitration. This court courts should liberally construe arbitration clauses.
recognized this policy in Eastboard Navigation, Ltd. v. Ysmael and Company, Provided such clause is susceptible of an
Inc.: 71 interpretation that covers the asserted dispute, an
order to arbitrate should be granted. Any doubt should
As a corollary to the question regarding the be resolved in favor of arbitration. 74 (Emphasis
existence of an arbitration agreement, defendant raises the supplied)
issue that, even if it be granted that it agreed to submit its
dispute with plaintiff to arbitration, said agreement is void A more clear-cut statement of the state policy to encourage
and without effect for it amounts to removing said dispute arbitration and to favor interpretations that would render effective an
from the jurisdiction of the courts in which the parties are arbitration clause was later expressed in Republic Act No. 9285: 75
SEC. 2. Declaration of Policy. — It is hereby individual with a personality that is distinct and separate from other persons
declared the policy of the State to actively promote party including its stockholders, officers, directors, representatives, 77 and other
autonomy in the resolution of disputes or the freedom of juridical entities.
the party to make their own arrangements to resolve their
disputes. Towards this end, the State shall encourage The law vests in corporations rights, powers, and attributes as if they
and actively promote the use of Alternative Dispute were natural persons with physical existence and capabilities to act on their
Resolution (ADR) as an important means to achieve own. 78 For instance, they have the power to sue and enter into transactions
speedy and impartial justice and declog court dockets. or contracts. Section 36 of the Corporation Code enumerates some of a
As such, the State shall provide means for the use of ADR corporation's powers, thus: ScaHDT
as an efficient tool and an alternative procedure for the Section 36. Corporate powers and capacity. —
resolution of appropriate cases. Likewise, the State shall Every corporation incorporated under this Code has the
enlist active private sector participation in the settlement of power and capacity:
disputes through ADR. This Act shall be without prejudice
to the adoption by the Supreme Court of any ADR system, 1. To sue and be sued in its corporate name;
such as mediation, conciliation, arbitration, or any
combination thereof as a means of achieving speedy and 2. Of succession by its corporate name for the
efficient means of resolving cases pending before all period of time stated in the articles of incorporation and the
courts in the Philippines which shall be governed by such certificate of incorporation;
rules as the Supreme Court may approve from time to 3. To adopt and use a corporate seal;
time.
4. To amend its articles of incorporation in
xxx xxx xxx accordance with the provisions of this Code;
SEC. 25. Interpretation of the Act. — In 5. To adopt by-laws, not contrary to law, morals, or
interpreting the Act, the court shall have due regard to public policy, and to amend or repeal the same in
the policy of the law in favor of arbitration. Where accordance with this Code;
action is commenced by or against multiple parties, one or
more of whom are parties who are bound by the arbitration 6. In case of stock corporations, to issue or sell
agreement although the civil action may continue as to stocks to subscribers and to sell treasury stocks in
those who are not bound by such arbitration agreement. accordance with the provisions of this Code; and to admit
(Emphasis supplied) members to the corporation if it be a non-stock
corporation;
Thus, if there is an interpretation that would render effective an
arbitration clause for purposes of avoiding litigation and expediting resolution 7. To purchase, receive, take or grant, hold,
of the dispute, that interpretation shall be adopted. convey, sell, lease, pledge, mortgage and otherwise deal
with such real and personal property, including securities
Petitioners' main argument arises from the separate personality and bonds of other corporations, as the transaction of the
given to juridical persons vis-à-vis their directors, officers, stockholders, and lawful business of the corporation may reasonably and
agents. Since they did not sign the arbitration agreement in any capacity, necessarily require, subject to the limitations prescribed by
they cannot be forced to submit to the jurisdiction of the Arbitration Tribunal law and the Constitution;
in accordance with the arbitration agreement. Moreover, they had already
resigned as directors of Shangri-La at the time of the alleged default. 8. To enter into merger or consolidation with other
corporations as provided in this Code;
Indeed, as petitioners point out, their personalities as directors of
Shangri-La are separate and distinct from Shangri-La. 9. To make reasonable donations, including those
for the public welfare or for hospital, charitable, cultural,
A corporation is an artificial entity created by fiction of law. 76 This scientific, civic, or similar purposes: Provided, That no
means that while it is not a person, naturally, the law gives it a distinct corporation, domestic or foreign, shall give donations in aid
personality and treats it as such. A corporation, in the legal sense, is an
of any political party or candidate or for purposes of This court incorporated these rulings in Agan, Jr. v. Philippine
partisan political activity; International Air Terminals Co., Inc. 83 and Stanfilco Employees v. DOLE
Philippines, Inc., et al. 84
10. To establish pension, retirement, and other
plans for the benefit of its directors, trustees, officers and As a general rule, therefore, a corporation's representative who did
employees; and not personally bind himself or herself to an arbitration agreement cannot be
forced to participate in arbitration proceedings made pursuant to an
11. To exercise such other powers as may be agreement entered into by the corporation. He or she is generally not
essential or necessary to carry out its purpose or purposes considered a party to that agreement.
as stated in its articles of incorporation. (13a)
However, there are instances when the distinction between
Because a corporation's existence is only by fiction of law, it can only personalities of directors, officers, and representatives, and of the
exercise its rights and powers through its directors, officers, or agents, who corporation, are disregarded. We call this piercing the veil of corporate fiction.
are all natural persons. A corporation cannot sue or enter into contracts
without them. Piercing the corporate veil is warranted when "[the separate
personality of a corporation] is used as a means to perpetrate fraud or an
A consequence of a corporation's separate personality is that illegal act, or as a vehicle for the evasion of an existing obligation, the
consent by a corporation through its representatives is not consent of the circumvention of statutes, or to confuse legitimate issues." 85 It is also
representative, personally. Its obligations, incurred through official acts of its warranted in alter ego cases "where a corporation is merely a farce since it is
representatives, are its own. A stockholder, director, or representative does a mere alter ego or business conduit of a person, or where the corporation is
not become a party to a contract just because a corporation executed a so organized and controlled and its affairs are so conducted as to make it
contract through that stockholder, director or representative. merely an instrumentality, agency, conduit or adjunct of another
Hence, a corporation's representatives are generally not bound by corporation." 86
the terms of the contract executed by the corporation. They are not When corporate veil is pierced, the corporation and persons who are
personally liable for obligations and liabilities incurred on or in behalf of the normally treated as distinct from the corporation are treated as one person,
corporation. such that when the corporation is adjudged liable, these persons, too,
Petitioners are also correct that arbitration promotes the parties' become liable as if they were the corporation.
autonomy in resolving their disputes. This court recognized in Heirs of Among the persons who may be treated as the corporation itself
Augusto Salas, Jr. v. Laperal Realty Corporation 79 that an arbitration clause under certain circumstances are its directors and officers. Section 31 of the
shall not apply to persons who were neither parties to the contract nor Corporation Code provides the instances when directors, trustees, or officers
assignees of previous parties, thus: may become liable for corporate acts:
A submission to arbitration is a contract. As such, Sec. 31. Liability of directors, trustees or
the Agreement, containing the stipulation on arbitration, officers. — Directors or trustees who willfully and
binds the parties thereto, as well as their assigns and knowingly vote for or assent to patently unlawful acts of the
heirs. But only they. 80 (Citations omitted) corporation or who are guilty of gross negligence or bad
Similarly, in Del Monte Corporation-USA v. Court of Appeals, 81 this faith in directing the affairs of the corporation or acquire
court ruled: any personal or pecuniary interest in conflict with their duty
as such directors or trustees shall be liable jointly and
The provision to submit to arbitration any dispute severally for all damages resulting therefrom suffered by
arising therefrom and the relationship of the parties is part the corporation, its stockholders or members and other
of that contract and is itself a contract. As a rule, contracts persons.
are respected as the law between the contracting parties
and produce effect as between them, their assigns and When a director, trustee or officer attempts to
heirs. Clearly, only parties to the Agreement . . . are bound acquire or acquires, in violation of his duty, any interest
by the Agreement and its arbitration clause as they are the adverse to the corporation in respect of any matter which
only signatories thereto. 82 (Citation omitted) has been reposed in him in confidence, as to which equity
imposes a disability upon him to deal in his own behalf, he corporate veil, the corporate representatives are treated as the corporation
shall be liable as a trustee for the corporation and must itself and should be held liable for corporate acts. The corporation's distinct
account for the profits which otherwise would have personality is disregarded, and the corporation is seen as a mere
accrued to the corporation. (n) aggregation of persons undertaking a business under the collective name of
the corporation.
Based on the above provision, a director, trustee, or officer of a
corporation may be made solidarily liable with it for all damages suffered by Hence, when the directors, as in this case, are impleaded in a case
the corporation, its stockholders or members, and other persons in any of the against a corporation, alleging malice or bad faith on their part in directing the
following cases: affairs of the corporation, complainants are effectively alleging that the
directors and the corporation are not acting as separate entities. They are
a) The director or trustee willfully and knowingly voted for alleging that the acts or omissions by the corporation that violated their rights
or assented to a patently unlawful corporate act; are also the directors' acts or omissions. 90 They are alleging that contracts
b) The director or trustee was guilty of gross negligence or executed by the corporation are contracts executed by the directors.
bad faith in directing corporate affairs; and Complainants effectively pray that the corporate veil be pierced because the
cause of action between the corporation and the directors is the
c) The director or trustee acquired personal or pecuniary same. EADSIa
interest in conflict with his or her duties as director
or trustee. In that case, complainants have no choice but to institute only one
proceeding against the parties. Under the Rules of Court, filing of multiple
Solidary liability with the corporation will also attach in the following suits for a single cause of action is prohibited. Institution of more than one
instances: suit for the same cause of action constitutes splitting the cause of action,
which is a ground for the dismissal of the others. Thus, in Rule 2:
a) "When a director or officer has consented to the
issuance of watered stocks or who, having Section 3. One suit for a single cause of action.
knowledge thereof, did not forthwith file with the — A party may not institute more than one suit for a single
corporate secretary his written objection cause of action. (3a)
thereto"; 87
Section 4. Splitting a single cause of action; effect
b) "When a director, trustee or officer has contractually of. — If two or more suits are instituted on the basis of the
agreed or stipulated to hold himself personally and same cause of action, the filing of one or a judgment upon
solidarily liable with the corporation"; 88 and the merits in any one is available as a ground for the
dismissal of the others. (4a)
c) "When a director, trustee or officer is made, by specific
provision of law, personally liable for his corporate It is because the personalities of petitioners and the corporation may
action." 89 later be found to be indistinct that we rule that petitioners may be compelled
to submit to arbitration.
When there are allegations of bad faith or malice against corporate
directors or representatives, it becomes the duty of courts or tribunals to However, in ruling that petitioners may be compelled to submit to the
determine if these persons and the corporation should be treated as one. arbitration proceedings, we are not overturning Heirs of Augusto
Without a trial, courts and tribunals have no basis for determining whether Salas wherein this court affirmed the basic arbitration principle that only
the veil of corporate fiction should be pierced. Courts or tribunals do not have parties to an arbitration agreement may be compelled to submit to arbitration.
such prior knowledge. Thus, the courts or tribunals must first determine
whether circumstances exist to warrant the courts or tribunals to disregard In that case, this court recognized that persons other than the main
the distinction between the corporation and the persons representing it. The party may be compelled to submit to arbitration, e.g., assignees and heirs.
determination of these circumstances must be made by one tribunal or court Assignees and heirs may be considered parties to an arbitration agreement
in a proceeding participated in by all parties involved, including current entered into by their assignor because the assignor's rights and obligations
representatives of the corporation, and those persons whose personalities are transferred to them upon assignment. In other words, the assignor's
are impliedly the same as the corporation. This is because when the court or rights and obligations become their own rights and obligations. In the same
tribunal finds that circumstances exist warranting the piercing of the
way, the corporation's obligations are treated as the representative's
obligations when the corporate veil is pierced.
Moreover, in Heirs of Augusto Salas, this court affirmed its policy
against multiplicity of suits and unnecessary delay. This court said that "to
split the proceeding into arbitration for some parties and trial for other parties
would "result in multiplicity of suits, duplicitous procedure and unnecessary
delay." 91 This court also intimated that the interest of justice would be best
observed if it adjudicated rights in a single proceeding. 92 While the facts of
that case prompted this court to direct the trial court to proceed to determine
the issues of that case, it did not prohibit courts from allowing the case to
proceed to arbitration, when circumstances warrant.
Hence, the issue of whether the corporation's acts in violation of
complainant's rights, and the incidental issue of whether piercing of the
corporate veil is warranted, should be determined in a single proceeding.
Such finding would determine if the corporation is merely an aggregation of
persons whose liabilities must be treated as one with the corporation.
However, when the courts disregard the corporation's distinct and
separate personality from its directors or officers, the courts do not say that
the corporation, in all instances and for all purposes, is the same as its
directors, stockholders, officers, and agents. It does not result in an absolute
confusion of personalities of the corporation and the persons composing or
representing it. Courts merely discount the distinction and treat them as one,
in relation to a specific act, in order to extend the terms of the contract and
the liabilities for all damages to erring corporate officials who participated in
the corporation's illegal acts. This is done so that the legal fiction cannot be
used to perpetrate illegalities and injustices.
Thus, in cases alleging solidary liability with the corporation or
praying for the piercing of the corporate veil, parties who are normally treated
as distinct individuals should be made to participate in the arbitration
proceedings in order to determine if such distinction should indeed be
disregarded and, if so, to determine the extent of their liabilities.
In this case, the Arbitral Tribunal rendered a decision, finding that BF
Corporation failed to prove the existence of circumstances that render
petitioners and the other directors solidarily liable. It ruled that petitioners and
Shangri-La's other directors were not liable for the contractual obligations of
Shangri-La to BF Corporation. The Arbitral Tribunal's decision was made with
the participation of petitioners, albeit with their continuing objection. In view of
our discussion above, we rule that petitioners are bound by such decision.
WHEREFORE, the petition is DENIED. The Court of Appeals'
decision of May 11, 2006 and resolution of October 5, 2006 are AFFIRMED.
SO ORDERED
SECOND DIVISION interests in Bankard, representing 226,460,000 shares, for the price of
PhP1,786,769,400. To expedite the purchase, RCBC agreed to dispense
with the conduct of a due diligence audit on the financial status of
[G.R. No. 182248. December 18, 2008.] Bankard.
Under the SPA, RCBC undertakes, on the date of contract
EQUITABLE PCI BANKING execution, to deposit, as downpayment, 20% of the purchase price, or
CORPORATION, 1 GEORGE L. GO, PATRICK D. GO, PhP357,353,880, in an escrow account. The escrowed amount, the SPA
GENEVIEVE W.J. GO, FERDINAND MARTIN G. stated, should be released to petitioners on an agreed-upon release date
ROMUALDEZ, OSCAR P. LOPEZ-DEE, RENE J. and the balance of the purchase price shall be delivered to the share
BUENAVENTURA, GLORIA L. TAN-CLIMACO, ROGELIO buyers upon the fulfillment of certain conditions agreed upon, in the form
S. CHUA, FEDERICO C. PASCUAL, LEOPOLDO S. of a manager's check.
VEROY, WILFRIDO V. VERGARA, EDILBERTO V.
JAVIER, ANTHONY F. CONWAY, ROMULAD U. DY The other relevant provisions of the SPA are:
TANG, WALTER C. WESSMER, and ANTONIO N. Section 5. Sellers' Representations and
COTOCO, petitioners, vs. RCBC CAPITAL Warranties. —
CORPORATION, respondent.
The SELLERS jointly and severally represent
and warrant to the BUYER that:
10.45 Whatever the status of Mr. Rubio's and Mr. So is Coca-Cola. As lessee, Coca-Cola Bottlers was well aware
Legaspi's enquiries in late 2000, the Claimant was of the nature and situation of the land relative to its intended use prior to
quite entitled to commission subsequent reports the signing of the contract. Its subsequent assertion that the land was not
from Dr. Laya and Dr. Echanis and, on the basis of suited for the purpose it was leased was, therefore, cast aside for being
unmeritorious. Such circumstance does not obtain in the instant case.
There was no prior due diligence audit conducted by RCBC, it having
relied, as earlier stated, on the warranties of petitioners with regard to the
financial condition of Bankard under Sec. 5 (g). As such, Sec. 5 (g)
guaranteed RCBC that it could file a claim for damages for any mistakes
in the AFS and UFS of Bankard. Clearly, Coca-Cola also cannot be
applied to the instant case.
It becomes evident from all of the foregoing findings that the
ICC-ICA is not guilty of any manifest disregard of the law on estoppel. As
shown above, the findings of the ICC-ICA in the Partial Award are well-
supported in law and grounded on facts. The Partial Award must be
upheld.
We close this disposition with the observation that a member of
the three-person arbitration panel was selected by petitioners, while
another was respondent's choice. The respective interests of the parties,
therefore, are very much safeguarded in the arbitration proceedings. Any
suggestion, therefore, on the partiality of the arbitration tribunal has to be
dismissed. DCcSHE
WHEREFORE, the instant petition is hereby DENIED. The
assailed January 8, 2008 and March 17, 2008 Orders of the RTC,
Branch 148 in Makati City are hereby AFFIRMED.
Costs against petitioners.
SO ORDERED.
SECOND DIVISION Spouses Stroem subsequently rescinded the agreement. 9 They
then hired an independent appraiser to evaluate the progress of the
construction project. 10
[G.R. No. 204689. January 21, 2015.]
Appraiser Asian Appraisal Company, Inc.'s evaluation resulted in the
following percentage of completion: 47.53% of the residential building,
STRONGHOLD INSURANCE COMPANY,
65.62% of the garage, and 13.32% of the swimming pool, fence, gate, and
INC., petitioner, vs. SPOUSES RUNE and LEA
land development. 11
STROEM, respondents.
On April 5, 2001, Stronghold sent a letter to Asis-Leif requesting that
the company settle its obligations with the Spouses Stroem. No response
was received from Asis-Leif. 12
DECISION
On September 12, 2002, the Spouses Stroem filed a Complaint (with
Prayer for Preliminary Attachment) 13 for breach of contract and for sum of
money with a claim for damages against Asis-Leif, Ms. Cynthia Asis-Leif, and
LEONEN, J p: Stronghold. 14 Only Stronghold was served summons. Ms. Cynthia Asis-Leif
allegedly absconded and moved out of the country. 15
For resolution is a Petition for Review 1 under Rule 45 of the Rules
of Court assailing the Decision 2 dated November 20, 2012 of the Court of On July 13, 2010, the Regional Trial Court rendered a judgment in
Appeals in CA-G.R. CV No. 96017. The Court of Appeals affirmed the favor of the Spouses Stroem. The trial court ordered Stronghold to pay the
Decision 3 of the Regional Trial Court of Makati, Branch 133 in Civil Case Spouses Stroem P4,500,000.00 with 6% legal interest from the time of first
No. 02-1108 for collection of a sum of money. demand. 16 The dispositive portion of the trial court Decision reads: acTDCI
This case involves the proper invocation of the Construction Industry WHEREFORE, finding plaintiffs' cause of action to
Arbitration Committee's (CIAC) jurisdiction through an arbitration clause in a be sufficiently established being supported by evidence on
construction contract. The main issue here is whether the dispute — liability records, judgement is hereby rendered in favor of the
of a surety under a performance bond — is connected to a construction plaintiff spouses Rune and Lea Stroem and against the
contract and, therefore, falls under the exclusive jurisdiction of the CIAC. defendant Stronghold Insurance Company Incorporated
ordering the latter to pay the plaintiff the sums of:
Spouses Rune and Lea Stroem (Spouses Stroem) entered into an
Owners-Contractor Agreement 4 with Asis-Leif & Company, Inc. (Asis-Leif) 1) Php4,500,000.00 with six (6%) percent legal
for the construction of a two-storey house on the lot owned by Spouses interest from the time of first demand and
Stroem. The lot was located at Lot 4A, Block 24, Don Celso Tuason Street, interest due shall earn legal interest from
Valley Golf Subdivision, Barangay Mayamot, Antipolo, Rizal. 5 the time of judicial demand until fully paid.
On November 15, 1999, pursuant to the agreement, Asis-Leif 2) Php35,000.00 by way of attorney's fees and
secured Performance Bond No. LP/G(13)83056 in the amount of other litigation expenses.
P4,500,000.00 from Stronghold Insurance Company, Inc.
Defendant is further ordered to pay the costs of
(Stronghold). 6 Stronghold and Asis-Leif, through Ms. Ma. Cynthia Asis-Leif,
this suit.
bound themselves jointly and severally to pay the Spouses Stroem the
agreed amount in the event that the construction project is not completed. 7 SO ORDERED. 17
Asis-Leif failed to finish the project on time despite repeated Both Stronghold and the Spouses Stroem appealed to the Court of
demands of the Spouses Stroem. 8 Appeals. 18
The Court of Appeals affirmed with modification the trial court's Stroem's Motion for Partial Reconsideration of the Court of Appeals Decision
Decision. It increased the amount of attorney's fees to P50,000.00. 19 dated November 20, 2012. 32
The dispositive portion of the Court of Appeals Decision reads: More importantly, the Owners-Contractor Agreement is "separate
and distinct from the Bond. The parties to the Agreement are ALB/Ms. Asis-
WHEREFORE, the appeal of Stronghold Leif and Spouses Stroem, while the parties to the Bond are Spouses Stroem
Company, Inc[.] is DISMISSED, while the appeal of and Stronghold. The considerations for the two contracts are likewise distinct.
spouses Rune and Lea Stroem is PARTLY GRANTED. Thus, the arbitration clause in the Agreement is binding only on the parties
The November 27, 2009 Decision of the Regional Trial thereto, specifically ALB/Ms. Asis-Leif and Spouses Stroem[.]" 33
Court of Makati City
is AFFIRMED with MODIFICATION that the award of Contrary to Stronghold's argument, Spouses Stroem argues that
attorney's fees is increased to P50,000.00. stronghold is liable for the full amount of the performance bond. The terms of
the bond clearly show that Stronghold is liable as surety. 34 Verily, notice to
SO ORDERED. 20 Stronghold is not required for its liability to attach. 35
On March 20, 2013, this court required the Spouses Stroem to The issues for consideration are:
submit their Comment on the Petition. 21
(1) Whether the dispute involves a construction contract;
We noted the Spouses Stroem's Comment on July 31, 2013. 22 We
also required Stronghold to file its Reply to the Comment, 23 which was (2) Whether the CIAC has exclusive jurisdiction over the
noted on December 9, 2013. 24 controversy between the parties;
Stronghold argues that the trial court did not acquire jurisdiction over (3) Whether the Regional Trial Court should have
the case and, therefore, the Court of Appeals committed reversible error dismissed the petition outright as required by law
when it upheld the Decision of the Regional Trial Court. 25 The lower courts and jurisprudence and referred the matter to the
should have dismissed the case in view of the arbitration clause in the CIAC; and
agreement and considering that "[Republic Act No. 876] explicitly confines
the court's authority only to pass upon the issue of whether there is [an] (4) Whether petitioner Stronghold Insurance Company,
agreement . . . providing for arbitration. In the affirmative, the statute ordains Inc. is liable under Performance Bond No.
that the court shall issue an order 'summarily directing the parties to proceed LP/G(13)83056. SDAaTC
with the arbitration in accordance with the terms thereof.'" 26 (a) Whether petitioner Stronghold Insurance
Moreover, "the stipulations in said Agreement are part and parcel of Company, Inc. is only liable as to the
the conditions in the bond. Were it not for such stipulations in said extent of any additional cost for the
agreement, [Stronghold] would not have agreed to issue a bond in favor of completion of the project due to any
the Spouses Stroem. The parties to the bond are ALB/Ms. Asis-[L]eif, increase in prices for labor and materials.
Spouses Stroem and [Stronghold] such that ALB/Ms. Asis-[L]eif never (b) Whether the case involves ordinary suretyship
ceased to be a party to the surety agreement." 27 or corporate suretyship.
In any case, Stronghold's liability under the performance bond is After considering the parties' arguments and the records of this case,
limited only to additional costs for the completion of the project. 28 In this court resolves to deny the Petition.
addition, the Court of Appeals erred in holding that Stronghold changed its
theory with regard to the notice requirement 29 and in modifying the trial
On forum-shopping
court's award of attorney's fees. 30
On the other hand, the Spouses Stroem argue that Stronghold Respondents argue that petitioner committed forum shopping;
committed forum shopping warranting dismissal of the case. 31 According to hence, the case should have been dismissed outright.
the Spouses Stroem, Stronghold deliberately committed forum shopping
when it filed the present petition despite the pendency of the Spouses Records show that petitioner received a copy of the Decision of the
Court of Appeals on December 5, 2012. 36 Petitioner did not file a Motion for
Reconsideration of the assailed Decision. It filed before this court a Motion unethical practice of pursuing simultaneous remedies in different forums,
for Extension of Time to File Petition for Review requesting an additional which "wreaks havoc upon orderly judicial procedure." 46 Failure to comply
period of 30 days from December 20, 2012 or until January 19, 2013 to file with the rule is a sufficient ground for the dismissal of the
the Petition. 37 petition. 47 aEcHCD
Respondents filed their Motion for Partial Reconsideration of the Records show that petitioner's duly authorized officer certified the
Court of Appeals Decision on December 11, 2012. 38 They sought the following on January 21, 2013:
modification of the Decision as to the amounts of moral damages, exemplary
damages, attorney's fees, and costs of the suit. 39 4. I further certify that: (a) I have not commenced
any other action or proceeding involving the same issues
Respondents alleged in their Comment that as early as January 9, in the Supreme Court, Court of Appeals, or any other
2013, petitioner received a copy of the Court of Appeals' Resolution requiring tribunal or agency; (b) to the best of my knowledge, no
Comment on the Motion for Partial Reconsideration. 40 Still, petitioner did such action or proceeding is pending in the Supreme
not disclose in its Verification and Certification Against Forum Shopping the Court, the Court of Appeals or different Divisions thereof,
pendency of respondents' Motion for Partial Reconsideration. 41 or any tribunal or agency; (c) if I should thereafter learn
that a similar action or proceeding has been filed or is
For its part, petitioner claims that it did not commit forum shopping. It pending before the Supreme Court, the Court of Appeals,
fully disclosed in its Petition that what it sought to be reviewed was the or different Divisions thereof, or any other tribunal or
Decision dated November 20, 2012 of the Court of Appeals. "Petitioner agency, I undertake to promptly inform the aforesaid courts
merely exercised its available remedy with respect to the Decision of the and such tribunal or agency of the fact within five (5) days
Court of Appeals by filing [the] Petition." 42 What the rules mandate to be therefrom. 48
stated in the Certification Against Forum Shopping is the status of "any other
action." This other action involves the same issues and parties but is an Petitioner failed to carry out its duty of promptly informing this court
entirely different case. of any pending action or proceeding before this court, the Court of Appeals,
or any other tribunal or agency. This court cannot countenance petitioner's
Indeed, petitioner is guilty of forum shopping. disregard of the rules.
There is forum shopping when: This court has held before that:
as a result of an adverse opinion in one forum, a party [u]ltimately, what is truly important to consider in
seeks a favorable opinion (other than by appeal determining whether forum-shopping exists or not is
or certiorari) in another. The principle applies not only the vexation caused the courts and parties-litigant by a
with respect to suits filed in the courts but also in party who asks different courts and/or administrative
connection with litigations commenced in the courts agencies to rule on the same or related causes and/or to
while an administrative proceeding is grant the same or substantially the same reliefs, in the
pending[.] 43 (Citation omitted) process creating the possibility of conflicting decisions
This court has enumerated the elements of forum-shopping: "(a) being rendered by the different fora upon the same
identity of parties, or at least such parties as represent the same interests in issue. 49 (Emphasis supplied)
both actions; (b) identity of rights asserted and reliefs prayed for, the reliefs On this basis, this case should be dismissed.
being founded on the same facts; and (c) the identity with respect to the two
preceding particulars in the two cases is such that any judgment rendered in
On arbitration and the CIAC's
the pending cases, regardless of which party is successful, amount to res
jurisdiction
judicata in the other case." 44
Rule 42, Section 2 45 in relation to Rule 45, Section 4 of the Rules of Petitioner changed the theory of its case since its participation in the
Court mandates petitioner to submit a Certification Against Forum Shopping trial court proceedings. It raised the issue of lack of jurisdiction in view of an
and promptly inform this court about the pendency of any similar action or arbitration agreement for the first time.
proceeding before other courts or tribunals. The rule's purpose is to deter the
Generally, parties may not raise issues for the first time on The Commission shall continue to exercise original and
appeal. 50 Such practice is violative of the rules and due process and is exclusive jurisdiction over construction disputes although
frowned upon by the courts. However, it is also well-settled that jurisdiction the arbitration is "commercial" pursuant to Section 21 of
can never be waived or acquired by estoppe1. 51 Jurisdiction is conferred by this Act. (Emphasis supplied)
the Constitution or by law. 52 "Lack of jurisdiction of the court over an action
or the subject matter of an action cannot be cured by the silence, by In Heunghwa Industry Co., Ltd. v. DJ Builders Corporation, 55 this
acquiescence, or even by express consent of the parties." 53 court held that "there are two acts which may vest the CIAC with jurisdiction
over a construction dispute. One is the presence of an arbitration clause in a
Section 4 of Executive Order No. 1008 54 is clear in defining the construction contract, and the other is the agreement by the parties to submit
exclusive jurisdiction of the CIAC: the dispute to the CIAC." 56
SECTION 4. Jurisdiction — The CIAC shall have This court has ruled that when a dispute arises from a construction
original and exclusive jurisdiction over disputes arising contract, the CIAC has exclusive and original jurisdiction. 57 Construction
from, or connected with, contracts entered into by parties has been defined as referring to "all on-site works on buildings or altering
involved in construction in the Philippines, whether the structures, from land clearance through completion including excavation,
dispute arises before or after the completion of the erection and assembly and installation of components and equipment." 58
contract, or after the abandonment or breach thereof.
These disputes may involve government or private In this case, there is no dispute as to whether the Owners-Contractor
contracts. For the Board to acquire jurisdiction, the parties Agreement between Asis-Leif and respondents is a construction contract.
to a dispute must agree to submit the same to voluntary Petitioner and respondents recognize that CIAC has jurisdiction over
arbitration. disputes arising from the agreement.
The jurisdiction of the CIAC may include but is not What is at issue in this case is the parties' agreement, or lack
limited to violation of specifications for materials and thereof, to submit the case to arbitration. Respondents argue that petitioner is
workmanship; violation of the terms of agreement; not a party to the arbitration agreement. Petitioner did not consent to
interpretation and/or application of contractual time and arbitration. It is only respondent and Asis-Leif that may invoke the arbitration
delays; maintenance and defects; payment, default of clause in the contract.
employer or contractor and changes in contract This court has previously held that a performance bond, which is
cost. ACcHIa meant "to guarantee the supply of labor, materials, tools, equipment, and
Excluded from the coverage of this law are disputes necessary supervision to complete the project[,]" 59 is significantly and
arising from employer-employee relationships which substantially connected to the construction contract and, therefore, falls
shall continue to be covered by the Labor Code of the under the jurisdiction of the CIAC. 60
Philippines. (Emphasis supplied) Prudential Guarantee and Assurance, Inc. v. Anscor Land,
Similarly, Section 35 of Republic Act No. 9285 or the Alternative Inc. 61 involved circumstances similar to the present case.
Dispute Resolution Act of 2004 states: In Prudential, property owner Anscor Land, Inc. (ALI) entered into a contract
for the construction of an eight-unit townhouse located in Capitol Hills,
SEC. 35. Coverage of the Law. — Construction disputes Quezon City with contractor Kraft Realty and Development Corporation
which fall within the original and exclusive jurisdiction of (KRDC). 62 KRDC secured the completion of the construction project
the Construction Industry Arbitration Commission (the through a surety and performance bond issued by Prudential Guarantee and
"Commission") shall include those between or among Assurance, Inc. (PGAI). 63
parties to, or who are otherwise bound by, an arbitration
agreement, directly or by reference whether such parties The delay in the construction project resulted in ALI's termination of
are project owner, contractor, subcontractor, quantity the contract and claim against the performance bond. 64 "ALI [subsequently]
surveyor; bondsman or issuer of an insurance policy in a commenced arbitration proceedings against KRDC and PGAI in the
construction project. CIAC." 65 PGAI, however, argued that it was not a party to the construction
contract. 66
The CIAC ruled that PGAI was not liable under the performance obligation or undertaking in favor of another party, called the obligee." 71 In
bond. 67 Upon review, the Court of Appeals held that PGAI was jointly and the same vein, a performance bond is "designed to afford the project owner
severally liable with KRDC under the performance bond. 68 security that the . . . contractor, will faithfully comply with the requirements of
the contract . . . and make good [on the] damages sustained by the project
PGAI appealed the Court of Appeals Decision and claimed that CIAC owner in case of the contractor's failure to so perform." 72
did not have jurisdiction over the performance bond. 69 This court
ruled: SITCcE It is settled that the surety's solidary obligation for the performance of
the principal debtor's obligation is indirect and merely
A guarantee or a surety contract under Article secondary. 73 Nevertheless, the surety's liability to the "creditor or promisee
2047 of the Civil Code of the Philippines is an accessory of the principal is said to be direct, primary and absolute; in other words, he is
contract because it is dependent for its existence upon the directly and equally bound with the principal." 74
principal obligation guaranteed by it.
Verily, "[i]n enforcing a surety contract, the 'complementary-
In fact, the primary and only reason behind the contracts-construed-together' doctrine finds application. According to this
acquisition of the performance bond by KRDC was to principle, an accessory contract must be read in its entirety and together with
guarantee to ALI that the construction project would the principal agreement." 75 Article 1374 of the Civil Code provides:
proceed in accordance with the contract terms and
conditions. In effect, the performance bond becomes liable ART. 1374. The various stipulations of a contract shall
for the completion of the construction project in the event be interpreted together, attributing to the doubtful ones
KRDC fails in its contractual undertaking. that sense which may result from all of them taken
jointly.
Because of the performance bond, the
construction contract between ALI and KRDC is Applying the "complementary-contracts-construed-together" doctrine,
guaranteed to be performed even if KRDC fails in its this court in Prudential held that the surety willingly acceded to the terms of
obligation. In practice, a performance bond is usually a the construction contract despite the silence of the performance bond as to
condition or a necessary component of construction arbitration:
contracts. In the case at bar, the performance bond was so
connected with the construction contract that the former In the case at bar, the performance bond was
was agreed by the parties to be a condition for the latter to silent with regard to arbitration. On the other hand, the
push through and at the same time, the former is reliant on construction contract was clear as to arbitration in the
the latter for its existence as an accessory contract. event of disputes. Applying the said doctrine, we rule that
the silence of the accessory contract in this case could
Although not the construction contract itself, the only be construed as acquiescence to the main contract.
performance bond is deemed as an associate of the main The construction contract breathes life into the
construction contract that it cannot be separated or performance bond. We are not ready to assume that the
severed from its principal. The Performance Bond is performance bond contains reservations with regard to
significantly and substantially connected to the some of the terms and conditions in the construction
construction contract that there can be no doubt it is the contract where in fact it is silent. On the other hand, it is
CIAC, under Section 4 of EO No. 1008, which has more reasonable to assume that the party who issued the
jurisdiction over any dispute arising from or connected with performance bond carefully and meticulously studied the
it. 70 (Emphasis supplied, citations omitted) construction contract that it guaranteed, and if it had
reservations, it would have and should have mentioned
At first look, the Owners-Contractor Agreement and the performance them in the surety contract. 76 (Emphasis
bond reference each other; the performance bond was issued pursuant to the supplied) EAcIST
construction agreement.
This court, however, cannot apply the ruling in Prudential to the
A performance bond is a kind of suretyship agreement. A suretyship present case. Several factors militate against petitioner's claim.
agreement is an agreement "whereby a party, called the surety, guarantees
the performance by another party, called the principal or obligor, of an
The contractual stipulations in this case and in Prudential are Article 1
different. The relevant provisions of the Owners-Contractor Agreement in this CONTRACT DOCUMENTS
case state:
1.1 The following shall form part of this Contract and
ARTICLE 5. THE CONTRACT DOCUMENTS. — together with this Contract, are known as the
"Contract Documents":
The following documents prepared by
the CONTRACTOR shall constitute an integral part of this a. Bid Proposal
contract as fully as if hereto attached or herein stated,
except as otherwise modified by mutual agreement of xxx xxx xxx
parties, and attached to this agreement. d. Notice to proceed
Attachment 5.1 Working Drawings xxx xxx xxx
Attachment 5.2 Outline Specifications j. Appendices A & B (respectively, Surety Bond for
Performance and, Supply of Materials by
Attachment 5.3 Bill of Quantities the Developer) 78 (Emphasis
Attachment 5.4 CONTRACTOR Business supplied) DHIcET
License This court in Prudential held that the construction contract expressly
xxx xxx xxx incorporated the performance bond into the contract. 79 In the present case,
Article 7 of the Owners-Contractor Agreement merely stated that a
ARTICLE 7. PERFORMANCE (SURETY) BOND. — performance bond shall be issued in favor of respondents, in which case
petitioner and Asis-Leif Builders and/or Ms. Ma. Cynthia Asis-Leif shall pay
7.1 Within 30 days of the signing of this P4,500,000.00 in the event that Asis-Leif fails to perform its duty under the
agreement, CONTRACTOR shall provide to OWNERS a Owners-Contractor Agreement. 80 Consequently, the performance bond
performance bond, issued by a duly licensed authority merely referenced the contract entered into by respondents and Asis-Leif,
acceptable to the OWNERS, and equal to the amount which pertained to Asis-Leif's duty to construct a two-storey residence
of PHP4,500,000.00 (Four Million and Five Hundred building with attic, pool, and landscaping over respondents' property. 81
Thousand Philippine Pesos), with the OWNERS as
beneficiary. To be clear, it is in the Owners-Contractor Agreement that the
arbitration clause is found. The construction agreement was signed only by
7.2 The performance bond will guarantee the respondents and the contractor, Asis-Leif, as represented by Ms. Ma.
satisfactory and faithful performance by Cynthia Asis-Leif. It is basic that "[c]ontracts take effect only between the
the CONTRACTOR of all provisions stated within this parties, their assigns and heirs[.]" 82 Not being a party to the construction
contract. agreement, petitioner cannot invoke the arbitration clause. Petitioner, thus,
ARTICLE 8. ARBITRATION. — cannot invoke the jurisdiction of the CIAC.
8.1 Any dispute between the parties hereto Moreover, petitioner's invocation of the arbitration clause
which cannot be amicably settled shall be finally defeats the purpose of arbitration in relation to the construction
settled by arbitration in accordance with the provision business. The state has continuously encouraged the use of dispute
of Republic Act 876, of The Philippines, as amended resolution mechanisms to promote party autonomy. 83 In LICOMCEN,
by the Executive Order 1008 dated February 4, Incorporated v. Foundation Specialists, Inc., 84 this court upheld the CIAC's
1985. 77 (Emphasis in the original) jurisdiction in line with the state's policy to promote arbitration:
In contrast, the provisions of the construction contract The CIAC was created through Executive Order
in Prudential provide: No. 1008 (E.O. 1008), in recognition of the need to
establish an arbitral machinery that would expeditiously
settle construction industry disputes. The prompt resolution
of problems arising from or connected with the
construction industry was considered of necessary and
vital for the fulfillment of national development goals, as
the construction industry provides employment to a large
segment of the national labor force and is a leading
contributor to the gross national product. 85 (Citation
omitted)
However, where a surety in a construction contract actively
participates in a collection suit, it is estopped from raising jurisdiction later.
Assuming that petitioner is privy to the construction agreement, we cannot
allow petitioner to invoke arbitration at this late stage of the proceedings
since to do so would go against the law's goal of prompt resolution of cases
in the construction industry.
WHEREFORE, the petition is DENIED. The case is DISMISSED.
Petitioner's counsel is STERNLY WARNED that a repetition or similar
violation of the rule on Certification Against Forum Shopping will be dealt with
more severely.
SO ORDERED.
SECOND DIVISION 16. If any dispute arise hereunder which cannot be settled
by mutual accord between the parties to such
dispute, then that dispute shall be referred to
[G.R. No. 173137. January 11, 2016.] arbitration. The arbitration shall be held in
whichever place the parties to the dispute decide
BASES CONVERSION DEVELOPMENT and failing mutual agreement as to a location
AUTHORITY, petitioner, vs. DMCI PROJECT within twenty-one (21) days after the occurrence of
DEVELOPERS, INC., respondent. the dispute, shall be held in Metro Manila and shall
be conducted in accordance with the Philippine
Arbitration Law (Republic Act No. 876)
[G.R. No. 173170. January 11, 2016.] supplemented by the Rules of Conciliation and
Arbitration of the International Chamber of
Commerce. All award of such arbitration shall be
NORTH LUZON RAILWAYS final and binding upon the parties to the dispute. 5
CORPORATION, petitioner, vs. DMCI PROJECT
DEVELOPERS, INC., respondent. BCDA organized and incorporated Northrail. 6 Northrail was
registered with the Securities and Exchange Commission on August 22,
1995. 7
BCDA invited investors to participate in the railroad project's
DECISION
financing and implementation. Among those invited were D.M. Consunji,
Inc. and Metro Pacific Corporation. 8
On February 8, 1996, the Joint Venture Agreement was
LEONEN, J p: amended to include D.M. Consunji, Inc. and/or its nominee as
An arbitration clause in a document of contract may extend to party. 9 Under the amended Joint Venture Agreement, D.M. Consunji,
subsequent documents of contract executed for the same purpose. Inc. shall be an additional investor of Northrail. 10 It shall subscribe to
Nominees of a party to and beneficiaries of a contract containing an 20% of the increase in Northrail's authorized capital stock. 11
arbitration clause may become parties to a proceeding initiated based on On February 8, 1996, BCDA and the other parties to the Joint
that arbitration clause. HTcADC Venture Agreement, including D.M. Consunji, Inc. and/or its nominee,
On June 10, 1995, Bases Conversion Development Authority entered into a Memorandum of Agreement. 12 Under this agreement,
(BCDA) entered into a Joint Venture Agreement 1 with Philippine the parties agreed that the initial seed capital of P600 million shall be
National Railways (PNR) and other foreign corporations. 2 infused to Northrail. 13 Of that amount, P200 million shall be D.M.
Consunji, Inc.'s share, which shall be converted to equity upon Northrail's
Under the Joint Venture Agreement, the parties agreed to privatization. 14 Later, D.M. Consunji, Inc.'s share was increased to P300
construct a railroad system from Manila to Clark with possible extensions million. 15
to Subic Bay and La Union and later, possibly to Ilocos Norte and Nueva
Ecija. 3 BCDA shall establish North Luzon Railways Corporation Upon BCDA and Northrail's request, 16 DMCI Project
(Northrail) for purposes of constructing, operating, and managing the Developers, Inc. (DMCI-PDI) deposited P300 million into Northrail's
railroad system. 4 The Joint Venture Agreement contained the following account with Land Bank of the Philippines. 17 The deposit was made on
provision: August 7, 1996 18 for its "future subscription of the Northrail shares of
stocks." 19 In Northrail's 1998 financial statements submitted to the
ARTICLE XVI Securities and Exchange Commission, this amount was reflected as
ARBITRATION "Deposits for Future Subscription." 20 At that time, Northrail's application
to increase its authorized capital stock was still pending with the
Securities and Exchange Commission. 21
In letters 22 dated April 4, 1997, D.M. Consunji, Inc. informed In a January 19, 2005 letter, 33 DMCI-PDI reiterated the request
PNR and the other parties that DMCI-PDI shall be its designated for the refund of its P300 million deposit for future Northrail subscription.
nominee for all the agreements it entered and would enter with On March 18, 2005, BCDA denied 34 DMCI-PDI's request:
them in connection with the railroad project. Pertinent portions of the
We regret to say that we are of the position that the
letters provide:
P300 [million] contribution should not be returned to
[I]n order to formalize the inclusion of [DMCI Project DMCI for the following reasons:
Developers, Inc.] as a party to the JVA and MOA, DMCI
a. the P300 million was in the nature of a
would like to notify all the parties that it is designating
contribution, not deposits for future
PDI as its nominee in both agreements and such other
subscription; and
agreements that may be signed by the parties in
furtherance of or in connection with the PROJECT. By b. DMCI, as a joint venture partner, must share in
this nomination, all the rights, obligations, warranties and profits and losses. 35
commitments of DMCI under the JVA and MOA shall
On August 17, 2005, 36 DMCI-PDI served a demand for
henceforth be assumed performed and delivered by
arbitration to BCDA and Northrail, citing the arbitration clause in the June
PDI. 23 (Emphasis supplied) aScITE
10, 1995 Joint Venture Agreement. 37 BCDA and Northrail failed to
Later, Northrail withdrew from the Securities and Exchange respond. 38
Commission its application for increased authorized capital
DMCI-PDI filed before the Regional Trial Court of Makati 39 a
stock. 24 Moreover, according to DMCI-PDI, BCDA applied for Official
Petition to Compel Arbitration 40 against BCDA and Northrail, pursuant
Development Assistance from Obuchi Fund of Japan. 25 This required
to the alleged arbitration clause in the Joint Venture
Northrail to be a 100% government-owned and controlled corporation. 26
Agreement. 41 DMCI-PDI prayed for "an order directing the parties to
On September 27, 2000, DMCI-PDI started demanding from proceed to arbitration in accordance with the terms and conditions of the
BCDA and Northrail the return of its P300 million deposit. 27 DMCI-PDI agreement." 42
cited Northrail's failure to increase its authorized capital stock as reason
BCDA filed a Motion to Dismiss 43 on the ground that there was
for the demand. 28 BCDA and Northrail refused to return the
no arbitration clause that DMCI-PDI could enforce since DMCI-PDI was
deposit 29 for the following reasons:
not a party to the Joint Venture Agreement containing the arbitration
a) At the outset, DMCI PDI/FBDC's participation in Northrail was clause. 44 Northrail filed a separate Motion to Dismiss 45 on the ground
as a joint venture partner and co-investor in the Manila that the court did not have jurisdiction over it and that DMCI-PDI had no
Clark Rapid Railway Project, and as such, was granted cause for arbitration against it. 46
corresponding representation in the Northrail Board.
In the Decision 47 dated February 9, 2006, the trial court denied
b) DMCI PDI/FBDC was privy to all the deliberations of the BCDA's and Northrail's Motions to Dismiss and granted DMCI-PDI's
Northrail Board and participated in the decisions made Petition to Compel Arbitration. The dispositive portion of the decision
and policies adopted to pursue the project. reads:
c) DMCI PDI/FBDC had full access to the financial statements of WHEREFORE, the petition is granted. The
Northrail and was regularly informed of the corporation's parties are ordered to present their dispute to arbitration
financial condition. 30 in accordance with Article XVI of the Joint Agreement.
Upon BCDA's request, the Office of the Government Corporate SO ORDERED. 48
Counsel (OGCC) issued Opinion No. 116, Series of 2001 31 on June 27,
The trial court ruled that the arbitration clause in the Joint
2001. The OGCC stated that "since no increase in capital stock was
Venture Agreement should cover all subsequent documents including the
implemented, it is but proper to return the investments of both FBDC and
amended Joint Venture Agreement and the Memorandum of Agreement.
DMCI[.]" 32
The three (3) documents constituted one contract for the formation and
funding of Northrail. 49
The trial court also ruled that even though DMCI-PDI was not a It turned out that such application was rendered impossible by the
signatory to the Joint Venture Agreement and the Memorandum of alleged loan requirement that Northrail be wholly owned by the
Agreement, it was an assignee of D.M. Consunji, Inc.'s rights. Therefore, government and by Northrail's withdrawal from the Securities and
it could invoke the arbitration clause in the Joint Venture Exchange Commission of its application for an increase in authorized
Agreement. 50 HEITAD capital stock. 66
In an Order 51 dated June 9, 2006, the trial court denied BCDA DMCI-PDI also argued that it is an assignee and nominee of
and Northrail's Motion for Reconsideration of the February 9, 2006 trial D.M. Consunji, Inc., which is a party to the contracts. Therefore, it is also
court Decision. a party to the arbitration clause. 67
BCDA filed a Rule 45 Petition before this court, assailing the DMCI-PDI contended that the arbitration agreement extended to
February 9, 2006 trial court Order granting DMCI-PDI's Petition to all documents relating to the project. 68 Even though the agreement was
Compel Arbitration and the June 9, 2006 Order denying BCDA and expressed only in the Joint Venture Agreement, its effect extends to the
Northrail's Motion for Reconsideration. 52 amendment to the Joint Venture Agreement and Memorandum of
Agreement. 69
The issue in this case is whether DMCI-PDI may compel BCDA
and Northrail to submit to arbitration. DMCI-PDI emphasized that BCDA had always recognized it as
D.M. Consunji's assignee in its correspondences with the OGCC and
BCDA argued that only the parties to an arbitration agreement
with the President of DMCI, Mr. Isidro Consunji. 70 In those letters,
can be bound by that agreement. 53 The arbitration clause that DMCI-
BCDA described DMCI-PDI's participation as being the "joint venture
PDI sought to enforce was in the Joint Venture Agreement, to which
partner . . . and co-investor in the Manila Clark Rapid Railway
DMCI-PDI was not a party. 54 There was also no evidence that the right
Project[.]" 71 Hence, it is now estopped from denying its personality in
to compel arbitration under the Joint Venture Agreement was assigned to
this case. 72 ATICcS
DMCI-PDI. 55 Assuming that there was such an assignment, BCDA did
not consent to or recognize it. 56 Therefore, the trial court's conclusion We rule for DMCI-PDI.
that DMCI-PDI was D.M. Consunji, Inc.'s assignee had no basis. 57 In
I
BCDA's view, DMCI-PDI had no right to compel BCDA to submit to
arbitration. 58 The state has a policy in favor of arbitration
BCDA also argued that the trial court decided the Motion to At the outset, we must state that BCDA and Northrail invoked the
Dismiss in violation of the parties' right to due process. The trial court correct remedy. Rule 45 is applicable when the issues raised before this
should have conducted a hearing so that the parties could have court involved purely questions of law. In Villamor v. Balmores: 73
presented their respective positions on the issue of assignment. The trial
[t]here is a question of law "when there is doubt
court merely accepted DMCI-PDI's allegations, without basis. 59
or controversy as to what the law is on a certain [set] of
In a separate Petition for Review, 60 Northrail argued that it facts." The test is "whether the appellate court can
cannot be compelled to submit itself to arbitration because it was not a determine the issue raised without reviewing or
party to the arbitration agreement. 61 evaluating the evidence." Meanwhile, there is a question
of fact when there is "doubt . . . as to the truth or
Northrail also argued that DMCI-PDI cannot initiate an action to
falsehood of facts." The question must involve the
compel BCDA and Northrail to arbitration because DMCI-PDI itself was
examination of probative value of the evidence
not a party to the arbitration agreement. DMCI-PDI was not D.M.
presented. 74
Consunji, Inc.'s assignee because BCDA did not consent to that
assignment. 62 BCDA and Northrail primarily ask us to construe the arbitration
clause in the Joint Venture Agreement. They assert that the clause does
In its Comment 63 on BCDA's Petition, DMCI-PDI argued that
not bind DMCI-PDI and Northrail. This issue is a question of law. It does
Rule 45 was a wrong mode of appeal. 64 The issues raised by BCDA did
not require us to examine the probative value of the evidence presented.
not involve questions of law. 65
The prayer is essentially for this court to determine the scope of an
DMCI-PDI pointed out that BCDA breached their agreement arbitration clause.
when it failed to apply the P300 million deposit to Northrail subscriptions.
Arbitration is a mode of settling disputes between should be granted. Any doubt should be resolved in
parties. 75 Like many alternative dispute resolution processes, it is a favor of arbitration. 83
product of the meeting of minds of parties submitting a pre-defined set of
This manner of interpreting arbitration clauses is made explicit in
disputes. They agree among themselves to a process of dispute
Section 25 of Republic Act No. 9285:
resolution that avoids extended litigation.
SEC. 25. Interpretation of the Act. — In interpreting the
The state adopts a policy in favor of arbitration. Republic Act No.
Act, the court shall have due regard to the policy of the
9285 76 expresses this policy:
law in favor of arbitration. Where action is commenced
SEC. 2. Declaration of Policy. — It is hereby by or against multiple parties, one or more of whom are
declared the policy of the State to actively promote party parties to an arbitration agreement, the court shall refer
autonomy in the resolution of disputes or the freedom of to arbitration those parties who are bound by the
the parties to make their own arrangements to resolve arbitration agreement although the civil action may
their disputes. Towards this end, the State shall continue as to those who are not bound by such
encourage and actively promote the use of Alternative arbitration agreement.
Dispute Resolution (ADR) as an important means to
Hence, we resolve the issue of whether DMCI-PDI may compel
achieve speedy and impartial justice and declog court
BCDA and Northrail to submit to arbitration proceedings in light of the
dockets. As such, the State shall provide means for the
policy in favor of arbitration.
use of ADR as an efficient tool and an alternative
procedure for the resolution of appropriate cases. BCDA and Northrail assail DMCI-PDI's right to compel them to
Likewise, the State shall enlist active private sector submit to arbitration based on the assumption that DMCI-PDI was not a
participation in the settlement of disputes through ADR. party to the agreement containing the arbitration clause.
This Act shall be without prejudice to the adoption by the
Three documents — (a) Joint Venture Agreement, (b) amended
Supreme Court of any ADR system, such as mediation,
Joint Venture Agreement, and (c) Memorandum of Agreement —
conciliation, arbitration, or any combination thereof as a
represent the agreement between BCDA, Northrail, and D.M. Consunji,
means of achieving speedy and efficient means of
Inc. Among the three documents, only the Joint Venture Agreement
resolving cases pending before all courts in the
contains the arbitration clause. DMCI-PDI was allegedly not a party to
Philippines which shall be governed by such rules as the
the Joint Venture Agreement.
Supreme Court may approve from time to time.
(Emphasis supplied) To determine the coverage of the arbitration clause, the relation
among the three documents and DMCI-PDI's involvement in the
Our policy in favor of party autonomy in resolving disputes has
execution of these documents must first be understood.
been reflected in our laws as early as 1949 when our Civil Code was
approved. 77 Republic Act No. 876 78 later explicitly recognized the The Joint Venture Agreement was executed by BCDA, PNR, and
validity and enforceability of parties' decision to submit disputes and some foreign corporations. 84 The purpose of the Joint Venture
related issues to arbitration. 79 Agreement was for the construction of a railroad system from Manila to
Clark with a possible extension to Subic Bay and later to San Fernando,
Arbitration agreements are liberally construed in favor of
La Union, Laoag, Ilocos Norte, and San Jose, Nueva Ejica. 85 Under the
proceeding to arbitration. 80 We adopt the interpretation that would
Joint Venture Agreement, BCDA agreed to incorporate Northrail, which
render effective an arbitration clause if the terms of the agreement allow
shall have an authorized capital stock of P5.5 billion. 86 The parties
for such interpretation. 81 In LM Power Engineering Corporation v.
agreed that BCDA/PNR shall have a 30% equity with Northrail. 87 Other
Capitol Industrial Construction Groups, Inc., 82 this court said: TIADCc
Filipino partners shall have a total of 50% equity, while foreign partners
Consistent with the above-mentioned policy of shall have at most 20% equity. 88 Pertinent provisions of the Joint
encouraging alternative dispute resolution methods, Venture Agreement are as follows:
courts should liberally construe arbitration clauses.
JOINT VENTURE AGREEMENT
Provided such clause is susceptible of an interpretation
that covers the asserted dispute, an order to arbitrate KNOW ALL MEN BY THESE PRESENTS:
This Joint Venture Agreement (JVA) made and ARTICLE I
executed at Makati, Metro Manila, this __ day of June
DEFINITION OF TERMS
1995 by and between:
xxx xxx xxx
The BASES CONVERSION DEVELOPMENT
AUTHORITY . . . hereinafter referred to as BASECON; 1.5 "PROJECT" means the construction,
operation and management of a double-
The PHILIPPINE NATIONAL RAILWAYS . . .;
track railway system from Manila to Clark
The following corporations collectively referred to as with an extension to Subic Bay, and a
the Foreign Group: possible extension to San Fernando, La
Union, as the second phase, and finally to
a) CONSTRUCCIONES Y AUXILIAR DE
Laoag, Ilocos Norte and to San Jose,
FERROCARRILES, S.A. . . .;
Nueva Ecija, as the third phase of the
b) ENTRECANALES Y TAVORA, SA . . .; PROJECT.
c) CUBIERTAS MZOV, S.A. . . .; 1.6 "North Luzon Railways Corporation
d) COBRA, S.A. . . . ; and (NORTHRAIL)["] means the joint venture
corporation to be established in
e) Others who may later participate in the JVA. accordance with Article II hereof.
- and - xxx xxx xxx
EUROMA DEVELOPMENT CORPORATION . . . ARTICLE II
WITNESSETH: THE NORTH LUZON RAILROAD CORPORATION
xxx xxx xxx 2.1 BASECON shall establish and incorporate in
WHEREAS, a project identified pursuant to the accordance with the laws of the Republic
aforesaid policy is the establishment of a Premier of the Philippines a corporation to be
International Airport Complex located at the former Clark known as NORTH LUZON RAILWAYS
Air Base as expressed in Executive Order 174 s. 1994 in CORPORATION (NORTHRAIL) with an
order to accommodate the expected heavy flow of initial capitalization of one hundred million
passenger and cargo traffic to and from the Philippines, pesos (P100,000,000.00).
to start the development of the Northern Luzon Grid and 2.2 NORTHRAIL shall eventually have an
to accelerate the development of Central Luzon and authorized capital stock of FIVE BILLION
finally to decongest Metro Manila of its vehicular FIVE HUNDRED MILLION PESOS (P5.5
traffic; AIDSTE Billion) divided into 55,000,000 shares
with par value of P100 per share.
xxx xxx xxx
xxx xxx xxx
WHEREAS, in order to implement and provide
such a mass transit and access system, the parties ARTICLE III
hereto agreed to construct a double-trac[k] railway
system from Manila to Clark with a possible extension to PURPOSE OF NORTHRAIL
Subic Bay and later to San Fernando, La Union, as the A. PRIMARY PURPOSE
second phase, and finally to Laoag, Ilocos Norte and to
San Jose, Nueva Ecija, as the third phase of the project, 3.1 To construct, operate and manage a railroad
hereinafter referred to as the PROJECT; system to serve Northern and Central
Luzon; and to develop, construct, manage,
xxx xxx xxx own, lease; sublease and operate
establishments and facilities of all kinds Chamber of Commerce. All award of such
related to the railroad system; arbitration shall be final and binding upon
the parties to the dispute.
xxx xxx xxx
ARTICLE XVII
ARTICLE IV
ASSIGNMENT
PARTICIPATION/TRANSFER/ENCUMBRANCE OF
SHARES 17.1 No party to this Agreement may assign,
transfer or convey this Agreement, create
4.1 NORTHRAIL shall increase its authorized
or incur any encumbrance of its rights or
capital stock upon the subscription
any part of its rights and obligations
thereon by the parties to this JVA in
hereunder or any shares of stocks of
accordance with the following equity
NORTHRAIL to any person, firm or
proportion/participation:
corporation without the prior written
Foreign Group up to 20% consent of the other parties or except as
Euroma/Filipino partners 50% provided in the Articles of Incorporation
and By-Laws of NORTHRAIL and this
BASECON/PNR 30% Agreement.
17.2 This Agreement shall inure to the benefit of
and be binding upon the parties hereto
xxx xxx xxx and their respective successors and
4.4 The shares owned by Filipino stockholders permitted assignees and designees or
including BASECON, PNR, EUROMA nominees whenever possible. 89
Development Corporation and hereinafter The Joint Venture Agreement was amended on February 8,
to be owned by Filipino corporations shall 1996 90 to include D.M. Consunji, Inc. and/or its nominee as
not be less than sixty percent (60%) at any party. 91 The participations of the parties in Northrail were also
given time. AaCTcI modified. 92 Pertinent provisions of the amended Joint Venture
xxx xxx xxx Agreement are reproduced as follows:
ARTICLE XVI This Amendment to the Joint Venture Agreement dated
10th of June 1995 (the Agreement) made and executed
ARBITRATION at ______________, Metro Manila, on this 8th day of
16. If any dispute arise hereunder which cannot be February 1996 by and among:
settled by mutual accord between the BASES CONVERSION
parties to such dispute, then that dispute DEVELOPMENT AUTHORITY . . .
shall be referred to arbitration. The hereinafter referred to as BASECON;
arbitration shall be held in whichever place
the parties to the dispute decide and with
failing mutual agreement as to a location PHILIPPINE NATIONAL
within twenty-one (21) days after the RAILWAYS . . .
occurrence of the dispute, shall be held in
Metro Manila and shall be conducted in and
accordance with the Philippine Arbitration The following corporations collectively referred to as
Law (Republic Act No. 876) as the FOREIGN GROUP:
supplemented by the Rules of Conciliation
and Arbitration of the International
CONSTRUCCIONES Y AUXILIAR DE BASECON/PNR up to 30%
FERROCARRILES, S.A. . . .;
Others 40%
ENTRECANALES Y TAVORA,
S.A. . . .;
This is a petition for review on certiorari of the Court of The contract also authorized TEAM to sublease the property.
Appeals' (CA) decision in CA-G.R. SP. No. 112384 that reversed an TEAM subleased the property to Capitol Publishing House (Capitol) on
arbitral award and dismissed the arbitral complaint for lack of December 2, 1996 after notifying Fruehauf.
merit. 1 The CA breached the bounds of its jurisdiction when it reviewed On May 2003, TEAM informed Fruehauf that it would not be
the substance of the arbitral award outside of the permitted grounds renewing the lease. 6
under the Arbitration Law. 2
On May 31, 2003, the sublease between TEAM and Capitol
expired. However, Capitol only vacated the premises on March 5, 2005.
Brief Factual Antecedents In the meantime, the master lease between TEAM and Fruehauf expired
on June 9, 2003.
In 1978, Fruehauf Electronics Philippines On March 9, 2004, Fruehauf instituted SP Proc. No.
Corp. (Fruehauf) leased several parcels of land in Pasig City to Signetics 11449 before the Regional Trial Court (RTC) for "Submission of an
Filipinas Corporation (Signetics) for a period of 25 years (until May 28, Existing Controversy for Arbitration." 7 It alleged: (1) that when the lease
2003). Signetics constructed a semiconductor assembly factory on the expired, the property suffered from damage that required extensive
land on its own account. renovation; (2) that when the lease expired, TEAM failed to turn over the
premises and pay rent; and (3) that TEAM did not restore the property to
In 1983, Signetics ceased its operations after the Board of its original condition as required in the contract. Accordingly, the parties
Investments (BOI) withdrew the investment incentives granted to are obliged to submit the dispute to arbitration pursuant to the stipulation
electronic industries based in Metro Manila. in the lease contract.
In 1986, Team Holdings Limited (THL) bought Signetics. THL The RTC granted the petition and directed the parties to comply
later changed its name to Technology Electronics Assembly and with the arbitration clause of the contract. 8
Management Pacific Corp. (TEAM).
Pursuant to the arbitration agreement, the dispute was referred received rentals from Capitol, TEAM can deduct these from its
to a three-member arbitration tribunal. TEAM and Fruehauf appointed liability. 16 Nevertheless, the award of rent and damages was without
one member each while the Chairman was appointed by the first two prejudice to TEAM's right to seek redress from its sub-lessee, Capitol. 17
members. The tribunal was formally constituted on September 27, 2004
With respect to the improvements on the land, the tribunal
with retired CA Justice Hector L. Hofileña, as chairman, retired CA
viewed the situation from two perspectives:
Justice Mariano M. Umali and Atty. Maria Clara B. Tankeh-Asuncion as
members. 9 HEITAD First, while the Contract admitted that Fruehauf was only leasing
the land and not the buildings and improvements thereon, it nevertheless
The parties initially submitted the following issues to the tribunal
obliged TEAM to deliver the buildings, installations and other
for resolution: 10
improvements existing at the inception of the lease upon its
1. Whether or not TEAM had complied with its obligation to expiration. 18
return the leased premises to Fruehauf after the
The other view, is that the MOA and the Contract recognized that
expiration of the lease on June 9, 2003.
TEAM owned the existing improvements on the property and considered
1.1. What properties should be returned and in what
them as separate from the land for the initial 15-year term of the
condition?
lease. 19 However, Fruehauf had a vested right to become the owner of
2. Is TEAM liable for payment of rentals after June 9, 2003?
these improvements at the end of the 15-year term. Consequently, the
2.1. If so, how much and for what period?
contract specifically obligated TEAM not to remove, transfer, destroy, or
3. Is TEAM liable for payment of real estate taxes, insurance,
in any way alienate or encumber these improvements without prior
and other expenses on the leased premises after June 9,
written consent from Fruehauf. 20 TIADCc
2003?
4. Who is liable for payment of damages and how much? Either way, TEAM had the obligation to deliver the existing
5. Who is liable for payment of attorney's fees and how much? improvements on the land upon the expiration of the lease. However,
there was no obligation under the lease to return the premises as a
Subsequently, the following issues were also submitted for
"complete, rentable, and fully facilitized electronics plant." 21 Thus,
resolution after TEAM proposed 11 their inclusion:
TEAM's obligation was to vacate the leased property and deliver to
1. Who is liable for the expenses of arbitration, including Fruehauf the buildings, improvements, and installations (including the
arbitration fees? machineries and equipment existing thereon) in the same condition as
2. Whether or not TEAM has the obligation to return the when the lease commenced, save for what had been lost or impaired by
premises to Fruehauf as a "complete, rentable, and fully the lapse of time, ordinary wear and tear, or any other inevitable
facilitized electronic plant." ATICcS cause. 22
The Arbitral Award 12
The tribunal found TEAM negligent in the maintenance of the
On December 3, 2008, the arbitral tribunal awarded Fruehauf: premises, machineries, and equipment it was obliged to deliver to
(1) 8.2 million pesos as (the balance of) unpaid rent from June 9, 2003 Fruehauf. 23 For this failure to conduct the necessary repairs or to notify
until March 5, 2005; and (2) 46.8 million pesos as damages. 13 Fruehauf of their necessity, the tribunal held TEAM accountable for
damages representing the value of the repairs necessary to restore the
The tribunal found that Fruehauf made several demands for the
premises to a condition "suitable for the use to which it has been
return of the leased premises before and after the expiration of the
devoted" less their depreciation expense. 24
lease 14 and that there was no express or implied renewal of the lease
after June 9, 2003. It recognized that the sub-lessor, Capitol, remained in On the other issues, the tribunal held that TEAM had no
possession of the lease. However, relying on the commentaries of Arturo obligation to pay real estate taxes, insurance, and other expenses on the
Tolentino on the subject, the tribunal held that it was not enough for leased premises considering these obligations can only arise from a
lessor to simply vacate the leased property; it is necessary that he place renewal of the contract. 25 Further, the tribunal refused to award
the thing at the disposal of the lessor, so that the latter can receive it attorney's fees, finding no evidence that either party acted in bad
without any obstacle. 15 faith. 26 For the same reason, it held both parties equally liable for the
expenses of litigation, including the arbitrators' fees. 27 cSEDTC
For failing to return the property to Fruehauf, TEAM remained
liable for the payment of rents. However, if it can prove that Fruehauf
TEAM moved for reconsideration 28 which the tribunal Section 29. Appeals. — An appeal may be taken from
denied. 29 Thus, TEAM petitioned the RTC to partially vacate or modify an order made in a proceeding under this Act, or from a
the arbitral award. 30 It argued that the tribunal failed to properly judgment entered upon an award through certiorari
appreciate the facts and the terms of the lease contract. proceedings, but such appeals shall be limited to
questions of law. The proceedings upon such appeal,
The RTC Ruling
including the judgment thereon shall be governed by the
On April 29, 2009, the RTC 31 found insufficient legal Rules of Court in so far as they are applicable.
grounds under Sections 24 and 25 of the Arbitration Law to modify or
It concluded that the appeal contemplated under the law is an
vacate the award. 32 It denied the petition and CONFIRMED the arbitral
appeal by certiorari limited only to questions of law. 47
award. 33 TEAM filed a Notice of Appeal.
The CA continued that TEAM failed to substantiate its claim as to
On July 3, 2009, 34 the RTC refused to give due course to the
the "evident miscalculation of figures." It further held that disagreement
Notice of Appeal because according to Section 29 35 of the Arbitration
with the arbitrators' factual determinations and legal conclusions does not
Law, an ordinary appeal under Rule 41 is not the proper mode of appeal
empower courts to amend or overrule arbitral judgments. 48 AaCTcI
against an order confirming an arbitral award. 36 AIDSTE
However, the CA amended its decision on October 25, 2012
TEAM moved for reconsideration but the RTC denied the motion
upon a motion for reconsideration. 49
on November 15, 2009. 37 Thus, TEAM filed a petition
for certiorari 38 before the CA arguing that the RTC gravely abused its The CA held that Section 29 of the Arbitration Law does not
discretion in: (1) denying due course to its notice of appeal; and (2) preclude the aggrieved party from resorting to other judicial
denying the motion to partially vacate and/or modify the arbitral remedies. 50 Citing Asset Privatization Trust v. Court of Appeals, 51 the
award. 39 CA held that the aggrieved party may resort to a petition
for certiorari when the RTC to which the award was submitted for
TEAM argued that an ordinary appeal under Rule 41 was the
confirmation has acted without jurisdiction, or with grave abuse of
proper remedy against the RTC's order confirming, modifying, correcting,
discretion and there is no appeal, nor any plain, speedy remedy in the
or vacating an arbitral award. 40 It argued that Rule 42 was not available
course of law. 52
because the order denying its motion to vacate was not rendered in the
exercise of the RTC's appellate jurisdiction. Further, Rule 43 only applies The CA further held that the mere filing of a notice of appeal is
to decisions of quasi-judicial bodies. Finally, an appeal under Rule 45 to sufficient as the issues raised in the appeal were not purely questions of
the Supreme Court would preclude it from raising questions of fact or law. 53 It further cited Section 46 of the Alternative Dispute
mixed questions of fact and law. 41 Resolution (ADR) Law: 54
TEAM maintained that it was appealing the RTC's order denying SEC. 46. Appeal from Court Decisions on Arbitral
its petition to partially vacate/modify the award, not the arbitral award Awards. — A decision of the regional trial court
itself. 42 Citing Rule 41, Section 13 of the Rules of Court, the RTC's confirming, vacating, setting aside, modifying or
authority to dismiss the appeal is limited to instances when it was filed correcting an arbitral award may be appealed to the
out of time or when the appellant fails to pay the docket fees within the Court of Appeals in accordance with the rules of
reglementary period. 43 procedure to be promulgated by the Supreme Court.
The losing party who appeals from the judgment of the
TEAM further maintained that the RTC gravely abused its
court confirming an arbitral award shall be required by
discretion by confirming the Arbitral Tribunal's award when it evidently
the appellant court to post counterbond executed in favor
had legal and factual errors, miscalculations, and ambiguities. 44
of the prevailing party equal to the amount of the award
The petition was docketed as CA-G.R. SP. No. 112384. in accordance with the rules to be promulgated by the
Supreme Court. 55
The CA decision 45
However, the CA made no further reference to A.M. No. 07-11-
The CA initially dismissed the petition. 46 As the RTC did, it cited 08-SC, the Special Rules of Court on Alternative Dispute
Section 29 of the Arbitration Law: Resolution (Special ADR Rules) which govern the appeal procedure.
The CA further revisited the merits of the arbitral award and grounds to vacate or modify the award. 67 It insists that the RTC's
found several errors in law and in fact. It held: (1) that TEAM was not misappreciation of the facts from a patently erroneous award warranted
obliged to pay rent because it was Capitol, not TEAM, that remained in an appeal under Rule 41. 68
possession of the property upon the expiration of the lease; 56 and (2)
TEAM reiterates that it "disagreed with the arbitral award
that Fruehauf was not entitled to compensation for the repairs on the
mainly on questions of fact and not only on questions of law,"
buildings because it did not become the owner of the building until after
specifically, "on factual matters relating to specific provisions in the
the expiration of the lease. 57 EcTCAD
contract on ownership of structures and improvements thereon,
Also citing Tolentino, the CA opined: (1) that a statement by the and the improper award of rentals and penalties." 69 Even assuming
lessee that he has abandoned the premises should, as a general rule, that it availed of the wrong mode of appeal, TEAM posits that its appeal
constitute sufficient compliance with his duty to return the leased should still have been given due course in the interest of substantial
premises; and (2) that any new arrangement made by the lessor with justice. 70 HESIcT
another person, such as the sub-lessor, operates as a resumption of his
TEAM assails the inconsistencies of Fruehauf's position as to the
possession. 58
available legal remedies against an arbitral award. 71 However, it
On the issue of damages, the CA held that TEAM can never be maintains that Section 29 of the Arbitration Law does not foreclose other
liable for the damages for the repairs of the improvements on the legal remedies (aside from an appeal by certiorari) against the RTC's
premises because they were owned by TEAM itself (through its order confirming or vacating an arbitral award pursuant to Insular
predecessor, Signetics) when the lease commenced. 59 Savings Bank and ABS-CBN Broadcasting Corporation v. World
Interactive Network Systems (WINS) Japan Co., Ltd. 72
The CA REVERSED AND SET ASIDE the arbitral award
and DISMISSED the arbitral complaint for lack of merit. 60
This CA action prompted Fruehauf to file the present petition for The Issues
review.
This case raises the following questions:
The Arguments 1. What are the remedies or the modes of appeal against an
unfavorable arbitral award?
2. What are the available remedies from an RTC decision
Fruehauf argues that courts do not have the power to substitute
confirming, vacating, modifying, or correcting an arbitral
their judgment for that of the arbitrators. 61 It also insists that an ordinary
award?
appeal is not the proper remedy against an RTC's order confirming,
3. Did the arbitral tribunal err in awarding Fruehauf damages for
vacating, correcting or modifying an arbitral award but a petition for
the repairs of the building and rental fees from the
review on certiorari under Rule 45. 62
expiration of the lease?
Furthermore, TEAM's petition before the CA went beyond the
permissible scope of certiorari — the existence of grave abuse of
discretion or errors jurisdiction — by including questions of fact and law Our Ruling
that challenged the merits of the arbitral award. 63
However, Fruehauf inconsistently argues that the remedies The petition is meritorious. caITAC
against an arbitral award are (1) a petition to vacate the award, (2) a
petition for review under Rule 43 raising questions of fact, of law, or Arbitration is an alternative mode of dispute resolution outside
mixed questions of fact and law, or (3) a petition for certiorari under Rule of the regular court system. Although adversarial in character,
65. 64 Fruehauf cites an article from the Philippine Dispute Resolution arbitration is technically not litigation. It is a voluntary process in which
Center 65 and Insular Savings Bank v. Far East Bank and Trust, Co. 66 one or more arbitrators — appointed according to the parties' agreement
or according to the applicable rules of the Alternative Dispute
TEAM counters that the CA correctly resolved the substantive Resolution (ADR) Law — resolve a dispute by rendering an
issues of the case and that the arbitral tribunal's errors were sufficient
award. 73 While arbitration carries many advantages over court litigation, proceedings, arbitration is meant to be an end, not the beginning, of
in many ways these advantages also translate into its disadvantages. litigation. 78 Thus, the arbitral award is final and binding on the parties
by reason of their contract — the arbitration agreement. 79
Resort to arbitration is voluntary. It requires consent from both
parties in the form of an arbitration clause that pre-existed the An Arbitral Tribunal does not exercise
dispute or a subsequent submission agreement. This written quasi-judicial powers
arbitration agreement is an independent and legally enforceable contract
Quasi-judicial or administrative adjudicatory power is the power:
that must be complied with in good faith. By entering into an arbitration
(1) to hear and determine questions of fact to which legislative policy is to
agreement, the parties agree to submit their dispute to an arbitrator (or
apply, and (2) to decide in accordance with the standards laid down by
tribunal) of their own choosing and be bound by the latter's resolution.
the law itself in enforcing and administering the same law. 80 Quasi-
However, this contractual and consensual character means judicial power is only exercised by administrative agencies — legal
that the parties cannot implead a third-party in the proceedings even if organs of the government.
the latter's participation is necessary for a complete settlement of the
Quasi-judicial bodies can only exercise such powers and
dispute. The tribunal does not have the power to compel a person to
jurisdiction as are expressly or by necessary implication conferred upon
participate in the arbitration proceedings without that person's consent. It
them by their enabling statutes. 81 Like courts, a quasi-judicial body's
also has no authority to decide on issues that the parties did not submit
jurisdiction over a subject matter is conferred by law and exists
(or agree to submit) for its resolution.
independently from the will of the parties. As government organs
As a purely private mode of dispute resolution, arbitration necessary for an effective legal system, a quasi-judicial tribunal's legal
proceedings, including the records, the evidence, and the arbitral award, existence continues beyond the resolution of a specific dispute. In other
are confidential 74 unlike court proceedings which are generally public. words, quasi-judicial bodies are creatures of law. TCAScE
This allows the parties to avoid negative publicity and protect their
As a contractual and consensual body, the arbitral tribunal does
privacy. Our law highly regards the confidentiality of arbitration
not have any inherent powers over the parties. It has no power to issue
proceedings that it devised a judicial remedy to prevent or prohibit the
coercive writs or compulsory processes. Thus, there is a need to resort
unauthorized disclosure of confidential information obtained
to the regular courts for interim measures of protection 82 and for the
therefrom. 75
recognition or enforcement of the arbitral award. 83
The contractual nature of arbitral proceedings affords the parties
The arbitral tribunal acquires jurisdiction over the parties and the
substantial autonomy over the proceedings. The parties are free to
subject matter through stipulation. Upon the rendition of the final award,
agree on the procedure to be observed during the proceedings. 76 This
the tribunal becomes functus officio and — save for a few
lends considerable flexibility to arbitration proceedings as compared to
exceptions 84 — ceases to have any further jurisdiction over the
court litigation governed by the Rules of Court. ICHDca
dispute. 85 The tribunal's powers (or in the case of ad hoc tribunals, their
The parties likewise appoint the arbitrators based on very existence) stem from the obligatory force of the arbitration
agreement. There are no other legal requirements as to the competence agreement and its ancillary stipulations. 86 Simply put, an arbitral
or technical qualifications of an arbitrator. Their only legal qualifications tribunal is a creature of contract.
are: (1) being of legal age; (2) full-enjoyment of their civil rights; and (3)
Deconstructing the view that arbitral
the ability to read and write. 77 The parties can tailor-fit the tribunal's
tribunals are quasi-judicial agencies
composition to the nature of their dispute. Thus, a specialized
dispute can be resolved by experts on the subject. We are aware of the contrary view expressed by the late Chief
Justice Renato Corona in ABS-CBN Broadcasting Corporation v. World
However, because arbitrators do not necessarily have a
Interactive Network Systems (WINS) Japan Co., Ltd. 87
background in law, they cannot be expected to have the legal mastery of
a magistrate. There is a greater risk that an arbitrator might misapply the The ABS-CBN Case opined that a voluntary arbitrator is a
law or misappreciate the facts en route to an erroneous decision. "quasi-judicial instrumentality" of the government 88 pursuant to Luzon
Development Bank v. Association of Luzon Development Bank
This risk of error is compounded by the absence of an effective
Employees, 89 Sevilla Trading Company v. Semana, 90 Manila Midtown
appeal mechanism. The errors of an arbitral tribunal are not subject to
Hotel v. Borromeo, 91 and Nippon Paint Employees Union-Olalia v.
correction by the judiciary. As a private alternative to court
Court of Appeals. 92 Hence, voluntary arbitrators are included in the In the Insular Savings Bank case, the lis mota of the case was
Rule 43 jurisdiction of the Court of Appeals: the RTC's jurisdiction over an appeal from an arbitral award. The parties
to the arbitration agreement agreed that the rules of the arbitration
SECTION 1. Scope. —This Rule shall apply to appeals
provider 97 — which stipulated that the RTC shall have jurisdiction to
from judgments or final orders of the Court of Tax
review arbitral awards — will govern the proceedings. 98 The Court
Appeals and from awards, judgments, final orders or
ultimately held that the RTC does not have jurisdiction to review the
resolutions of or authorized by any quasi-judicial agency
merits of the award because legal jurisdiction is conferred by law, not by
in the exercise of its quasi-judicial functions. Among
mere agreement of the parties. cSaATC
these agencies are the Civil Service Commission,
Central Board of Assessment Appeals, Securities and In both cases, the pronouncements as to the remedies against
Exchange Commission, Office of the President, Land an arbitral award were unnecessary for their resolution. Therefore, these
Registration Authority, Social Security Commission, Civil are obiter dicta — judicial comments made in passing which are not
Aeronautics Board, Bureau of Patents, Trademarks and essential to the resolution of the case and cannot therefore serve as
Technology Transfer, National Electrification precedents. 99
Administration, Energy Regulatory Board, National
Second, even if we disregard the obiter dicta character of both
Telecommunications Commission, Department of
pronouncements, a more careful scrutiny deconstructs their legal
Agrarian Reform under Republic Act No. 6657,
authority.
Government Service Insurance System, Employees
Compensation Commission, Agricultural Inventions The ABS-CBN Case committed the classic fallacy of
Board, Insurance Commission, Philippine Atomic Energy equivocation. It equated the term "voluntary arbitrator" used in Rule 43,
Commission, Board of Investments, Construction Section 1 and in the cases of Luzon Development Bank v. Association of
Industry Arbitration Commission, and voluntary Luzon Development Bank Employees, Sevilla Trading Company v.
arbitrators authorized by law. 93 (emphasis Semana, Manila Midtown Hotel v. Borromeo, and Nippon Paint
supplied) cTDaEH Employees Union-Olalia v. Court of Appeals with the term
"arbitrator/arbitration tribunal."
Citing Insular Savings Bank v. Far East Bank and Trust
Co., 94 the ABS-CBN Case pronounced that the losing party in an The first rule of legal construction, verba legis, requires that,
arbitration proceeding may avail of three alternative remedies: (1) a wherever possible, the words used in the Constitution or in the statute
petition to vacate the arbitral award before the RTC; (2) a petition for must be given their ordinary meaning except where technical terms are
review with the CA under Rule 43 of the Rules of Court raising questions employed. 100 Notably, all of the cases cited in the ABS-CBN
of fact, of law, or of both; and (3) a petition for certiorari under Rule 65 Case involved labor disputes.
should the arbitrator act beyond its jurisdiction or with grave abuse of
The term "Voluntary Arbitrator" does not refer to an ordinary
discretion. 95
"arbitrator" who voluntarily agreed to resolve a dispute. It is a technical
At first glance, the logic of this position appears to be sound. term with a specific definition under the Labor Code:
However, a critical examination of the supporting authorities would show
Art. 212. Definitions. — xxx
that the conclusion is wrong.
14. "Voluntary Arbitrator" means any person accredited
First, the pronouncements made in the ABS-CBN Case and in by the Board as such or any person named or
the Insular Savings Bank Case (which served as the authority for the designated in the Collective Bargaining Agreement by
ABS-CBN Case) were both obiter dicta. the parties to act as their Voluntary Arbitrator, or one
chosen with or without the assistance of the National
In the ABS-CBN Case, we sustained the CA's dismissal of the
Conciliation and Mediation Board, pursuant to a
petition because it was filed as an "alternative petition for review under
selection procedure agreed upon in the Collective
Rule 43 or petition for certiorari under Rule 65." 96 We held that it was
Bargaining Agreement, or any official that may be
an inappropriate mode of appeal because a petition for review and a
authorized by the Secretary of Labor and Employment to
petition for certiorari are mutually exclusive and not alternative or
act as Voluntary Arbitrator upon the written request and
successive.
agreement of the parties to a labor dispute. 101
Voluntary Arbitrators resolve labor disputes and grievances All things considered, there is no legal authority supporting the
arising from the interpretation of Collective Bargaining position that commercial arbitrators are quasi-judicial bodies.
Agreements. 102 These disputes were specifically excluded from the
What are remedies from a final domestic
coverage of both the Arbitration Law 103 and the ADR Law. 104 cHDAIS
arbitral award?
Unlike purely commercial relationships, the relationship between
The right to an appeal is neither a natural right nor an
capital and labor are heavily impressed with public interest. 105 Because
indispensable component of due process; it is a mere statutory privilege
of this, Voluntary Arbitrators authorized to resolve labor disputes have
that cannot be invoked in the absence of an enabling statute. Neither the
been clothed with quasi-judicial authority.
Arbitration Law nor the ADR Law allows a losing party to appeal from the
On the other hand, commercial relationships covered by our arbitral award. The statutory absence of an appeal mechanism reflects
commercial arbitration laws are purely private and contractual in nature. the State's policy of upholding the autonomy of arbitration proceedings
Unlike labor relationships, they do not possess the same compelling and their corresponding arbitral awards.
state interest that would justify state interference into the autonomy of
This Court recognized this when we enacted the Special Rules
contracts. Hence, commercial arbitration is a purely private system of
of Court on Alternative Dispute Resolution in 2009: 112
adjudication facilitated by private citizens instead of government
instrumentalities wielding quasi-judicial powers. Rule 2.1. General policies. — It is the policy of the State
to actively promote the use of various modes of ADR
Moreover, judicial or quasi-judicial jurisdiction cannot be
and to respect party autonomy or the freedom of the
conferred upon a tribunal by the parties alone. The Labor Code itself
parties to make their own arrangements in the resolution
confers subject-matter jurisdiction to Voluntary Arbitrators. 106
of disputes with the greatest cooperation of and the least
Notably, the other arbitration body listed in Rule 43 — the intervention from the courts. xxx
Construction Industry Arbitration Commission (CIAC) — is also a The Court shall exercise the power of judicial review as
government agency 107 attached to the Department of Trade and provided by these Special ADR Rules. Courts shall
Industry. 108 Its jurisdiction is likewise conferred by statute. 109 By intervene only in the cases allowed by law or these
contrast, the subject-matter jurisdiction of commercial arbitrators is Special ADR Rules. 113
stipulated by the parties. xxx xxx xxx
Rule 19.7. No appeal or certiorari on the merits of an
These account for the legal differences between "ordinary" or
arbitral award. — An agreement to refer a dispute to
"commercial" arbitrators under the Arbitration Law and the ADR Law, and
arbitration shall mean that the arbitral award shall be
"voluntary arbitrators" under the Labor Code. The two terms
final and binding. Consequently, a party to an arbitration
are not synonymous with each other. Interchanging them with one
is precluded from filing an appeal or a petition
another results in the logical fallacy of equivocation — using the same
for certiorari questioning the merits of an arbitral
word with different meanings.
award. 114 (emphasis supplied)
Further, Rule 43, Section 1 enumerates quasi-judicial tribunals
More than a decade earlier in Asset Privatization Trust v.
whose decisions are appealable to the CA instead of the RTC. But where
Court of Appeals, we likewise defended the autonomy of arbitral awards
legislation provides for an appeal from decisions of
through our policy of non-intervention on their substantive
certain administrative bodies to the CA, it means that such bodies are
merits: cEaSHC
co-equal with the RTC in terms of rank and stature, logically placing
them beyond the control of the latter. 110 As a rule, the award of an arbitrator cannot be set aside
for mere errors of judgment either as to the law or as to
However, arbitral tribunals and the RTC are not co-equal bodies
the facts. Courts are without power to amend or
because the RTC is authorized to confirm or to vacate (but not reverse)
overrule merely because of disagreement with
arbitral awards. 111 If we were to deem arbitrators as included in the
matters of law or facts determined by the arbitrators.
scope of Rule 43, we would effectively place it on equal footing with the
They will not review the findings of law and fact
RTC and remove arbitral awards from the scope of RTC review. DHITCc
contained in an award, and will not undertake to
substitute their judgment for that of the arbitrators,
since any other rule would make an award the (d) the arbitrators exceeded their powers, or so imperfectly
commencement, not the end, of litigation. Errors of law executed them, that a mutual, final and definite award
and fact, or an erroneous decision of matters submitted upon the subject matter submitted to them was not
to the judgment of the arbitrators, are insufficient to made. 117
invalidate an award fairly and honestly made. Judicial
The award may also be vacated if an arbitrator who was
review of an arbitration is, thus, more limited than judicial
disqualified to act willfully refrained from disclosing his disqualification to
review of a trial. 115
the parties. 118 Notably, none of these grounds pertain to the
Nonetheless, an arbitral award is not absolute. Rule 19.10 of the correctness of the award but relate to the misconduct of arbitrators.
Special ADR Rules — by referring to Section 24 of the Arbitration Law
The RTC may also set aside the arbitral award based on Article
and Article 34 of the 1985 United Nations Commission on International
34 of the UNCITRAL Model Law. These grounds are reproduced in
Trade Law (UNCITRAL) Model Law — recognizes the very limited
Chapter 4 of the Implementing Rules and Regulations (IRR) of the 2004
exceptions to the autonomy of arbitral awards:
ADR Act:
Rule 19.10. Rule on judicial review on arbitration in
(i) the party making the application furnishes proof that:
the Philippines. — As a general rule, the court can only
(aa) a party to the arbitration agreement was
vacate or set aside the decision of an arbitral tribunal
under some incapacity; or the said
upon a clear showing that the award suffers from any of
agreement is not valid under the law to
the infirmities or grounds for vacating an arbitral
which the parties have subjected it or,
award under Section 24 of Republic Act No. 876 or
failing any indication thereon, under the
under Rule 34 of the Model Law in a domestic
law of the Philippines; or
arbitration, or for setting aside an award in an
(bb) the party making the application was not
international arbitration under Article 34 of the Model
given proper notice of the appointment of
Law, or for such other grounds provided under these
an arbitrator or of the arbitral proceedings
Special Rules.
or was otherwise unable to present his
If the Regional Trial Court is asked to set aside an
case; or
arbitral award in a domestic or international
(cc) the award deals with a dispute not
arbitration on any ground other than those provided
contemplated by or not falling within the
in the Special ADR Rules, the court shall entertain such
terms of the submission to arbitration, or
ground for the setting aside or non-recognition of the
contains decisions on matters beyond the
arbitral award only if the same amounts to a violation
scope of the submission to arbitration,
of public policy.
provided that, if the decisions on matters
The court shall not set aside or vacate the award of
submitted to arbitration can be separated
the arbitral tribunal merely on the ground that the
from those not so submitted, only the part
arbitral tribunal committed errors of fact, or of law,
of the award which contains decisions on
or of fact and law, as the court cannot substitute its
matters not submitted to arbitration may
judgment for that of the arbitral tribunal. 116
be set aside; or SaCIDT
The grounds for vacating a domestic arbitral award under (dd) the composition of the arbitral tribunal or the
Section 24 of the Arbitration Law contemplate the following scenarios: arbitral procedure was not in accordance
with the agreement of the parties, unless
(a) when the award is procured by corruption, fraud, or other
such agreement was in conflict with a
undue means; or
provision of ADR Act from which the
(b) there was evident partiality or corruption in the arbitrators or
parties cannot derogate, or, failing such
any of them; or
agreement, was not in accordance with
(c) the arbitrators were guilty of misconduct that materially
ADR Act; or
prejudiced the rights of any party; or CTIEac
(ii) The Court finds that:
(aa) the subject-matter of the dispute is not b. Where the arbitrators have awarded upon a matter not
capable of settlement by arbitration submitted to them, not affecting the merits of the
under the law of the Philippines; or decision upon the matter submitted;
(bb) the award is in conflict with the public c. Where the arbitrators have omitted to resolve an issue
policy of the Philippines. 119 submitted to them for resolution; or
d. Where the award is imperfect in a matter of form not affecting
Chapter 4 of the IRR of the ADR Act applies particularly to
the merits of the controversy, and if it had been a
International Commercial Arbitration. However, the abovementioned
commissioner's report, the defect could have been
grounds taken from the UNCITRAL Model Law are specifically made
amended or disregarded by the Court. 123
applicable to domestic arbitration by the Special ADR Rules. 120
A losing party is likewise precluded from resorting
Notably, these grounds are not concerned with the correctness
to certiorari under Rule 65 of the Rules of Court. 124 Certiorari is a
of the award; they go into the validity of the arbitration agreement or the
prerogative writ designed to correct errors of jurisdiction committed by a
regularity of the arbitration proceedings.
judicial or quasi-judicial body. 125 Because an arbitral tribunal is not a
These grounds for vacating an arbitral award are exclusive. government organ exercising judicial or quasi-judicial powers, it is
Under the ADR Law, courts are obliged to disregard any other grounds removed from the ambit of Rule 65. AHDacC
invoked to set aside an award:
Not even the Court's expanded certiorari jurisdiction under the
SEC. 41. Vacation Award. — A party to a domestic Constitution 126 can justify judicial intrusion into the merits of arbitral
arbitration may question the arbitral award with the awards. While the Constitution expanded the scope
appropriate regional trial court in accordance with the of certiorari proceedings, this power remains limited to a review of the
rules of procedure to be promulgated by the Supreme acts of "any branch or instrumentality of the Government." As a purely
Court only on those grounds enumerated in Section 25 private creature of contract, an arbitral tribunal remains outside the scope
of Republic Act No. 876. Any other ground raised of certiorari.
against a domestic arbitral award shall be
Lastly, the Special ADR Rules are a self-contained body of rules.
disregarded by the regional trial court. 121
The parties cannot invoke remedies and other provisions from the Rules
Consequently, the winning party can generally expect the of Court unless they were incorporated in the Special ADR Rules:
enforcement of the award. This is a stricter rule that makes Article
Rule 22.1. Applicability of Rules of Court. — The
2044 122 of the Civil Code regarding the finality of an arbitral award
provisions of the Rules of Court that are applicable to
redundant. cHECAS
the proceedings enumerated in Rule 1.1 of these Special
As established earlier, an arbitral award is not appealable via ADR Rules have either been included and
Rule 43 because: (1) there is no statutory basis for an appeal from the incorporated in these Special ADR Rules or
final award of arbitrators; (2) arbitrators are not quasi-judicial bodies; and specifically referred to herein.
(3) the Special ADR Rules specifically prohibit the filing of an appeal to In Connection with the above proceedings, the Rules of
question the merits of an arbitral award. Evidence shall be liberally construed to achieve the
objectives of the Special ADR Rules. 127
The Special ADR Rules allow the RTC to correct or modify an
arbitral award pursuant to Section 25 of the Arbitration Law. However, Contrary to TEAM'S position, the Special ADR Rules actually
this authority cannot be interpreted as jurisdiction to review the merits of forecloses against other remedies outside of itself. Thus, a losing party
the award. The RTC can modify or correct the award only in the following cannot assail an arbitral award through a petition for review under Rule
cases: 43 or a petition for certiorari under Rule 65 because these remedies are
not specifically permitted in the Special ADR Rules.
a. Where there was an evident miscalculation of figures or an
evident mistake in the description of any person, thing or In sum, the only remedy against a final domestic arbitral award is
property referred to in the award; to file petition to vacate or to modify/correct the award not later than thirty
(30) days from the receipt of the award. 128 Unless a ground to vacate
has been established, the RTC must confirm the arbitral award as a correcting an arbitral award. Thus, there is no merit in the CA's ruling that
matter of course. the RTC gravely abused its discretion when it refused to give due course
to the notice of appeal. aCIHcD
The remedies against an order
confirming, vacating, correcting, or The correctness or incorrectness
modifying an arbitral award of the arbitral award
Once the RTC orders the confirmation, vacation, or We have deliberately refrained from passing upon the merits of
correction/modification of a domestic arbitral award, the aggrieved party the arbitral award — not because the award was erroneous — but
may move for reconsideration within a non-extendible period of fifteen because it would be improper. None of the grounds to vacate an arbitral
(15) days from receipt of the order. 129 The losing party may also opt to award are present in this case and as already established, the merits of
appeal from the RTC's ruling instead. the award cannot be reviewed by the courts.
Under the Arbitration Law, the mode of appeal was via petition Our refusal to review the award is not a simple matter of putting
for review on certiorari: procedural technicalities over the substantive merits of a case; it goes
into the very legal substance of the issues. There is no law granting the
Section 29. Appeals. — An appeal may be taken from
judiciary authority to review the merits of an arbitral award. If we were to
an order made in a proceeding under this Act, or from a
insist on reviewing the correctness of the award (or consent to the CA's
judgment entered upon an award
doing so), it would be tantamount to expanding our jurisdiction without
through certiorari proceedings, but such appeals shall
the benefit of legislation. This translates to judicial legislation — a breach
be limited to questions of law. The proceedings upon
of the fundamental principle of separation of powers.
such appeal, including the judgment thereon shall be
governed by the Rules of Court in so far as they are The CA reversed the arbitral award — an action that it has no
applicable. 130 IDSEAH power to do — because it disagreed with the tribunal's factual findings
and application of the law. However, the alleged incorrectness of the
The Arbitration Law did not specify which Court had jurisdiction
award is insufficient cause to vacate the award, given the State's policy
to entertain the appeal but left the matter to be governed by the Rules of
of upholding the autonomy of arbitral awards.
Court. As the appeal was limited to questions of law and was described
as "certiorari proceedings," the mode of appeal can be interpreted as an The CA passed upon questions such as: (1) whether or not
Appeal by Certiorari to this Court under Rule 45. TEAM effectively returned the property upon the expiration of the lease;
(2) whether or not TEAM was liable to pay rentals after the expiration of
When the ADR Law was enacted in 2004, it specified that the
the lease; and (3) whether or not TEAM was liable to pay Fruehauf
appeal shall be made to the CA in accordance with the rules of
damages corresponding to the cost of repairs. These were the same
procedure to be promulgated by this Court. 131 The Special ADR Rules
questions that were specifically submitted to the arbitral tribunal for its
provided that the mode of appeal from the RTC's order confirming,
resolution. 134
vacating, or correcting/modifying a domestic arbitral award was through a
petition for review with the CA. 132 However, the Special ADR Rules The CA disagreed with the tribunal's factual determinations and
only took effect on October 30, 2009. legal interpretation of TEAM's obligations under the contract —
particularly, that TEAM's obligation to turn over the improvements on the
In the present case, the RTC disallowed TEAM's notice of appeal
land at the end of the lease in the same condition as when the lease
from the former's decision confirming the arbitral award on July 3, 2009.
commenced translated to an obligation to make ordinary repairs
TEAM moved for reconsideration which was likewise denied on
necessary for its preservation. 135
November 15, 2009. In the interim, the Special ADR Rules became
effective. Notably, the Special ADR Rules apply retroactively in light of its Assuming arguendo that the tribunal's interpretation of the
procedural character. 133 TEAM filed its petition for certiorari soon after. contract was incorrect, the errors would have been simple errors of
law. It was the tribunal — not the RTC or the CA — that had jurisdiction
Nevertheless, whether we apply Section 29 of the Arbitration
and authority over the issue by virtue of the parties' submissions; the
Law, Section 46 of the ADR Law, or Rule 19.12 of the Special ADR
CA's substitution of its own judgment for the arbitral award cannot be
Rules, there is no legal basis that an ordinary appeal (via notice of
more compelling than the overriding public policy to uphold the autonomy
appeal) is the correct remedy from an order confirming, vacating, or
of arbitral awards. Courts are precluded from disturbing an arbitral
tribunal's factual findings and interpretations of law. 136 The CA's ruling mechanism — and found that its benefits (both legal and economic)
is an unjustified judicial intrusion in excess of its jurisdiction — a judicial outweighed the disadvantages. Without a showing that any of the
overreach. 137 cHaCAS grounds to vacate the award exists or that the same amounts to a
violation of an overriding public policy, the award is subject to
Upholding the CA's ruling would weaken our alternative dispute
confirmation as a matter of course. 140 DACcIH
resolution mechanisms by allowing the courts to "throw their weight
around" whenever they disagree with the results. It erodes the obligatory WHEREFORE, we GRANT the petition. The CA's decision
force of arbitration agreements by allowing the losing parties to "forum in CA-G.R. SP. No. 112384 is SET ASIDE and the RTC's
shop" for a more favorable ruling from the judiciary. order CONFIRMING the arbitral award in SP. Proc. No.
11449 is REINSTATED. aICcHA
Whether or not the arbitral tribunal correctly passed upon the
issues is irrelevant. Regardless of the amount of the sum involved in a SO ORDERED.
case, a simple error of law remains a simple error of law. Courts are
precluded from revising the award in a particular way, revisiting the
tribunal's findings of fact or conclusions of law, or otherwise encroaching
upon the independence of an arbitral tribunal. 138 At the risk of
redundancy, we emphasize Rule 19.10 of the Special ADR Rules
promulgated by this Court en banc:
Rule 19.10. Rule on judicial review on arbitration in the
Philippines. — As a general rule, the court can only
vacate or set aside the decision of an arbitral
tribunal upon a clear showing that the award suffers
from any of the infirmities or grounds for vacating an
arbitral award under Section 24 of Republic Act No.
876 or under Rule 34 of the Model Law in a domestic
arbitration, or for setting aside an award in an
international arbitration under Article 34 of the Model
Law, or for such other grounds provided under these
Special Rules.
If the Regional Trial Court is asked to set aside an
arbitral award in a domestic or international arbitration on
any ground other than those provided in the Special
ADR Rules, the court shall entertain such ground for the
setting aside or non-recognition of the arbitral
award only if the same amounts to a violation of
public policy.
The court shall not set aside or vacate the award of
the arbitral tribunal merely on the ground that the
arbitral tribunal committed errors of fact, or of law,
or of fact and law, as the court cannot substitute its
judgment for that of the arbitral tribunal.
In other words, simple errors of fact, of law, or of fact and law
committed by the arbitral tribunal are not justiciable errors in this
jurisdiction. 139
TEAM agreed to submit their disputes to an arbitral tribunal. It
understood all the risks — including the absence of an appeal
FIRST DIVISION On September 16, 1996, Mabuhay, IDHI, and Sembcorp entered
into a Shareholders' Agreement 8 (Agreement) setting out the terms and
conditions governing their relationship in connection with a planned
[G.R. No. 212734. December 5, 2018.] business expansion of WJSC and WJNA. Sembcorp decided to invest in
the said corporations. As a result of Sembcorp's acquisition of shares,
MABUHAY HOLDINGS Mabuhay and IDHI's shareholding percentage in the said corporations
CORPORATION, petitioner, vs. SEMBCORP LOGISTICS were reduced, as follows: 9
LIMITED, respondent.
WJSC WJNA
Mabuhay 45.5% 45.5%
IDHI 19.5% 19.5%
DECISION Sembcorp 35.0% 35.0%
Pursuant to Article 13 of the Agreement, Mabuhay and IDHI
voluntarily agreed to jointly guarantee that Sembcorp would receive a
TIJAM, J p: minimum accounting return of US$929,875.50 (Guaranteed Return) at
the end of the 24th month following the full disbursement of the
This is an appeal from the Decision 1 dated November 19, 2013 Sembcorp's equity investment in WJNA and WJSC. They further agreed
and the Resolution 2 dated June 3, 2014 of the Court of Appeals (CA) in that the Guaranteed Return shall be paid three (3) months from the
CA-G.R. CV No. 92296, reversing and setting aside the Decision of the completion of the special audits of WJSC and WJNA as per Article 13.3
Regional Trial Court (RTC) 3 of Makati City, Branch 149, in SP Proc. No. of the Agreement. 10
M-6064. The Agreement included an arbitration clause, viz.:
Article XIX. APPLICABLE LAW; ARBITRATION
Facts of the Case 19.1 This Agreement and the validity and
performance thereof shall be governed by the laws of the
Petitioner Mabuhay Holdings Corporation (Mabuhay) and Republic of the Philippines.
Infrastructure Development & Holdings, Inc. (IDHI) are corporations duly 19.2 Any dispute, controversy or claim arising
organized and existing under the Philippine Laws. 4 out of or relating to this Agreement, or a breach thereof,
Respondent Sembcorp Logistics Limited (Sembcorp), formerly other than intra-corporate controversies, shall be finally
known as Sembawang Maritime Limited, is a company incorporated in settled by arbitration in accordance with the rules of
the Republic of Singapore. 5 conciliation and arbitration of the International Chamber
of Commerce by one arbitrator with expertise in the
On January 23, 1996, Mabuhay and IDHI incorporated Water Jet matter at issue appointed in accordance with said rules.
Shipping Corporation (WJSC) in the Philippines to engage in the venture The arbitration proceeding including the rendering of the
of carrying passengers on a common carriage by inter-island fast ferry. award shall take place in Singapore and shall be
On February 5, 1996, they also incorporated Water Jet Netherlands conducted in the English Language. This arbitration shall
Antilles, N.V. (WJNA) in Curasao, Netherlands. 6 Their respective survive termination of this Agreement. Judgment upon
shareholding percentage are as follows: 7 the award rendered may be entered in any court having
jurisdiction or application may be made to such court for
WJSC WJNA
a judicial acceptance of the award and an order of
Mabuhay 70% 70% enforcement, as the case may be. 11
IDHI 30% 30%
On December 6, 1996, Sembcorp effected full payment of its 3. A reimbursement of half of the costs of
equity investment. Special audits of WJNA and WJSC were then carried arbitration fixed by the ICC Court at US$57,000 or the
out and completed on January 8, 1999. Said audits revealed that WJSC aggregate half of which amount to US$28,500 together
and WJNA both incurred losses. 12 with an interest at the rate of 12% per annum calculated
from the date of this Final Award until the said amount is
On November 26, 1999, Sembcorp requested for the payment of
actually and completely paid by [Mabuhay] to
its Guaranteed Return from Mabuhay and IDHI. Mabuhay admitted its
[Sembcorp]. 17
liability but asserted that since the obligation is joint, it is only liable for
fifty percent (50%) of the claim or US$464,937.75. 13 Consequently, on April 14, 2005, Sembcorp filed a Petition for
Recognition and Enforcement of a Foreign Arbitral Award 18 before the
On February 24, 2000, Sembcorp sent a Final Demand to
RTC of Makati City, Branch 149. 19
Mabuhay to pay the Guaranteed Return. Mabuhay requested for three
(3) months to raise the necessary funds but still failed to pay any amount Mabuhay filed an Opposition citing the following grounds for non-
after the lapse of the said period. 14 enforcement under Article V of the 1958 Convention on the Recognition
and Enforcement of Foreign Arbitral Awards (New York Convention): (1)
On December 4, 2000, Sembcorp filed a Request for Arbitration
the award deals with a conflict not falling within the terms of the
before the International Court of Arbitration of the International Chamber
submission to arbitration; (2) the composition of the arbitral authority was
of Commerce (ICC) in accordance with the Agreement and sought the
not in accordance with the agreement of the parties; and (3) recognition
following reliefs:
or enforcement of the award would be contrary to the public policy of the
(1) payment of the sum of US$929,875.50; Philippines. 20
(2) alternatively, damages; Mabuhay argued that the dispute is an intra-corporate
controversy, hence, excluded from the scope of the arbitration clause in
(3) interest on the above sum at such rate as the Arbitral the Agreement. It alleged that on March 13, 1997, Sembcorp became the
Tribunal deems fit and just; controlling stockholder of IDHI by acquiring substantial shares of stocks
(4) cost of the arbitration; and through its nominee, Mr. Pablo N. Sare (Sare). Mabuhay thus claimed
that it has already been released from the joint obligation with IDHI as
(5) Such further and/or other relief as the Arbitral Tribunal deems Sembcorp assumed the risk of loss when it acquired absolute ownership
fit and just. 15 over the aforesaid shares. Moreover, Mabuhay argued that the
On April 20, 2004, a Final Award 16 was rendered by Dr. Anan appointment of Dr. Chantara-Opakorn was not in accordance with the
Chantara-Opakorn (Dr. Chantara-Opakorn), the Sole Arbitrator appointed arbitral clause as he did not have the expertise in the matter at issue,
by the ICC. The dispositive portion of the award reads: which involved application of Philippine law. Finally, Mabuhay argued
that the imposition of twelve percent (12%) interest from the date of the
The Sole Arbitrator hereby decides that the Sole Final Award was contrary to the Philippine law and jurisprudence. 21
Arbitrator has jurisdiction over the parties' dispute and
directs [Mabuhay] to make the following payments to
[Sembcorp]: Ruling of the RTC
1. Half of the Guaranteed Return or an amount
of US$464,937.75 (Four Hundred Sixty-Four Thousand
In a Decision 22 dated May 23, 2008, the RTC dismissed the
Nine Hundred Thirty-Seven and Point Seventy-Five US
petition and ruled that the Final Award could not be enforced.
Dollars);
The RTC ruled that the "simple contractual payment obligation"
2. Interest at the rate of 12% per annum on the
of Mabuhay and IDHI to Sembcorp had been rescinded and modified by
said amount of US$464,937.75 calculated from the date
the merger or confusion of the person of IDHI into the person of
of this Final Award until the said amount of
Sembcorp. As a result, said obligation was converted into an intra-
US$464,937.75 is actually and completely paid by
corporate matter. 23
[Mabuhay] to [Sembcorp]; and
The RTC also ruled on the issue of the lack of expertise of the to establish a ground for refusing the enforcement of the Final Award
Sole Arbitrator. Thus, the dispositive portion of its Decision reads: under our applicable laws and jurisprudence on arbitration?
WHEREFORE, premises considered, this court
finds in favor of the defendant Mabuhay Holdings
Our Ruling
Corporation, hence it hereby DISMISSED the petition for
the recognition and enforcement of the subject Arbitral
Award for the simple reason that it was issued in We deny the petition.
violation of the agreement. Moreover, this court cannot
recognize the Arbitral Award because it was not the work I. Governing Laws
of an expert as required under the agreement. Finally, An assiduous analysis of the present case requires a prefatory
the payment obligation in interest of 12% per annum on determination of the rules and other legal authorities that would govern
the US Dollar Amounts ($464,937.75 and $28,500) as the subject arbitration proceedings and award.
ordered by the Sole Arbitrator is contrary to law and
existing jurisprudence, hence void. Thus, it cannot be The arbitration proceedings between the parties herein were
enforced by this Court. conducted in Singapore and the resulting Final Award was also rendered
therein. As such, the Final Award is a "foreign arbitral award" or an
Cost de oficio. award made in a country other than the Philippines. 29
SO ORDERED. 24 The Philippines is among the first signatories of the 1958
Aggrieved, Sembcorp appealed to the CA via a Notice of Appeal Convention on the Recognition and Enforcement of Foreign Arbitral
under Rule 41 of the Rules of Court. 25 Awards (New York Convention) and acceded to the same as early as
1967. 30 Singapore, on the other hand, became a Contracting State in
1986. 31 The New York Convention aims to provide common legislative
standards for the recognition of arbitration agreements and court
Ruling of the CA
recognition and enforcement of foreign and non-domestic arbitral
awards. Thus, the New York Convention primarily governs the
On November 19, 2013, the CA promulgated its recognition and enforcement of foreign arbitral awards by our courts. 32
Decision 26 reversing and setting aside the RTC Decision.
In addition, as a member of the United Nations Commission in
The CA noted that the Final Award already settled the factual International Trade Law (UNCITRAL), the Philippines also adopted the
issue on whether Sembcorp acquired the adverted shares of stock in UNCITRAL Model Law 33 (Model Law) as the governing law on
IDHI. Thus, RTC's contrary findings constituted an attack on the merits of international commercial arbitrations. Hence, when the Congress
the Final Award. In sum, the CA held that the court shall not disturb the enacted Republic Act No. 9285 or the Alternative Dispute Resolution Act
arbitral tribunal's determination of facts and/or interpretation of the law. It of 2004 34 (ADR Act), it incorporated the Model Law in its entirety.
recognized the Final Award and remanded the case to the RTC for
Sections 19 and 42 of the ADR Act expressly provided for the
proper execution. 27
applicability of the New York Convention and the Model Law in our
Undaunted, Mabuhay moved for the reconsideration of the CA jurisdiction, viz.:
Decision but the same was denied in a Resolution 28 dated June 3,
SEC. 19. Adoption of the Model Law on
2014.
International Commercial Arbitration. — International
Hence, this petition. commercial arbitration shall be governed by the Model
Law on International Commercial Arbitration (the "Model
Law") adopted by the United Nations Commission on
Issue International Trade Law on June 21, 1985 (United
Nations Document A/40/17) and recommended
approved on December 11, 1985, copy of which is
The core issue for resolution is whether the RTC correctly hereto attached as Appendix "A".
refused to enforce the Final Award. Stated differently, was Mabuhay able
xxx xxx xxx appeal. Mabuhay's argument hinges on Rule 19.12 of the Special ADR
Rules, as follows:
SEC. 42. Application of the New York
Convention. — The New York Convention shall Rule 19.12. Appeal to the Court of Appeals. —
govern the recognition and enforcement of arbitral An appeal to the Court of Appeals through a petition
awards covered by the said Convention. for review under this Special Rule shall only be allowed
from the following final orders of the Regional Trial
The recognition and enforcement of such arbitral
Court:
awards shall be filled (sic) with regional trial court in
accordance with the rules of procedure to be xxx xxx xxx
promulgated by the Supreme Court. Said procedural
k. Refusing recognition and/or enforcement of a
rules shall provide that the party relying on the award or
foreign arbitral award; (Emphasis supplied)
applying for its enforcement shall file with the court the
original or authenticated copy of the award and the xxx xxx xxx
arbitration agreement. If the award or agreement is not
Mabuhay thus contends that filing a petition for review and not a
made in any of the official languages, the party shall
notice of appeal is the proper remedy to contest the RTC's refusal to
supply a duly certified translation thereof into any of such
enforce the Final Award.
languages.
The Court notes, however, that the Special ADR Rules took
The applicant shall establish that the country in
effect in 2009. Sembcorp's notice of appeal was filed only in 2008. The
which foreign arbitration award was made is a party to
ADR Act, which was already in effect at that time, did not specify the
the New York Convention.
proper remedy of appeal from the RTC to the CA. It merely provides that
xxx xxx xxx (Emphasis ours) "a decision of the regional trial court confirming, vacating, setting aside,
modifying or correcting an arbitral award may be appealed to the CA in
Five years after the enactment of the ADR Act, the Department
accordance with the rules of procedure to be promulgated by the
of Justice issued the ADR Act's Implementing Rules and Regulations
Supreme Court." 38
(IRR), 35 and the Supreme Court issued the Special Rules of Court on
Alternative Dispute Resolution 36 (Special ADR Rules). These two rules, The Special ADR Rules shall retroactively apply to all pending
in addition to the ADR Act incorporating the New York Convention and cases provided that no vested rights are impaired or prejudiced. 39 In
the Model Law, are our arbitration laws. this case, Sembcorp filed a notice of appeal in accordance with Section 2
of Rule 41 40 as it is the only applicable rule existing at that time.
In addition to our arbitration laws, our courts, in recognizing or
Sembcorp had a vested right to due process in relying on the said rule.
enforcing a foreign arbitral award, shall also take into consideration the
Consequently, the CA had jurisdiction to act on Sembcorp's appeal.
laws applied by the arbitral tribunal. These may comprise the substantive
law of the contract and the procedural rules or the rules governing the We now discuss the Court's jurisdiction to entertain the instant
conduct of arbitration proceedings. petition. The Court's review of a CA Decision is discretionary and limited
to specific grounds provided under the Special ADR Rules. Thus:
As agreed upon by the parties herein under the arbitral clause in
their Agreement, the substantive law of the contract is the Philippine law Rule 19.36. Review discretionary. — A review
and the procedural rules are the ICC Rules. During the filing of the by the Supreme Court is not a matter of right, but of
request for Arbitration, the ICC Rules in effect was the ICC Rules of sound judicial discretion, which will be granted only for
Arbitration 1998. 37 Considering that the essence of arbitration is party serious and compelling reasons resulting in grave
autonomy, the Court shall refer to the said Rules for purposes of prejudice to the aggrieved party. The following, while
examining the procedural infirmities raised by the parties to the neither controlling nor fully measuring the court's
arbitration. discretion, indicate the serious and compelling, and
necessarily, restrictive nature of the grounds that will
II. Jurisdiction
warrant the exercise of the Supreme Court's
Mabuhay argues that the CA seriously erred in not dismissing discretionary powers, when the Court of Appeals:
outright the appeal of Sembcorp as it had no jurisdiction to act on the
a. Failed to apply the applicable reversal or modification of the judgment, final order, or
standard or test for judicial review resolution sought to be reviewed, it may give due course
prescribed in these Special ADR to the petition; otherwise, it shall dismiss the same.
Rules in arriving at its decision
xxx xxx xxx
resulting in substantial prejudice to
the aggrieved party; Rule 19.24. Subject of appeal restricted in
certain instance. — If the decision of the Regional Trial
b. Erred in upholding a final order or
Court refusing to recognize and/or enforce, vacating
decision despite the lack of jurisdiction
and/or setting aside an arbitral award is premised on a
of the court that rendered such final
finding of fact, the Court of Appeals may inquire only
order or decision;
into such fact to determine the existence or non-
c. Failed to apply any provision, existence of the specific ground under the
principle, policy or rule contained in arbitration laws of the Philippines relied upon by the
these Special ADR Rules resulting in Regional Trial Court to refuse to recognize and/or
substantial prejudice to the aggrieved enforce, vacate and/or set aside an award. Any such
party; and inquiry into a question of fact shall not be resorted to for
the purpose of substituting the court's judgment for that
d. Committed an error so egregious and
of the arbitral tribunal as regards the latter's ruling on the
harmful to a party as to amount to an
merits of the controversy. (Emphasis ours)
undeniable excess of jurisdiction.
Here, Mabuhay did not specifically raise any of the grounds
The mere fact that the petitioner disagrees with
under Rule 19.36 above in its petition before this Court. Nonetheless,
the Court of Appeals' determination of questions of fact,
considering the dearth of jurisprudence on enforcement of foreign arbitral
of law or both questions of fact and law, shall not warrant
awards and the fact that the CA reversed the RTC decision, the Court
the exercise of the Supreme Court's discretionary power.
exercises its discretion to review the CA decision solely for purposes of
The error imputed to the Court of Appeals must be
determining whether the CA applied the aforecited standard of judicial
grounded upon any of the above prescribed grounds for
review.
review or be closely analogous thereto.
III. Grounds for Refusing Enforcement or Recognition
A mere general allegation that the Court of
Appeals has committed serious and substantial error or We now delve into the core of the issue — whether there is a
that it has acted with grave abuse of discretion resulting ground for the RTC to refuse recognition and enforcement of the Final
in substantial prejudice to the petitioner without Award in favor of Sembcorp.
indicating with specificity the nature of such error or
Our jurisdiction adopts a policy in favor of arbitration. 41 The
abuse of discretion and the serious prejudice suffered by
ADR Act and the Special ADR Rules both declare as a policy that the
the petitioner on account thereof, shall constitute
State shall encourage and actively promote the use of alternative dispute
sufficient ground for the Supreme Court to dismiss
resolution, such as arbitration, as an important means to achieve speedy
outright the petition. (Emphasis ours)
and impartial justice and declog court dockets. 42 This pro-arbitration
In relation to the applicable standard or test for judicial review by policy is further evidenced by the rule on presumption in favor of
the CA in arriving at its decision, the Special ADR Rules further provide: enforcement of a foreign arbitral award under the Special ADR
Rules, viz.:
Rule 19.20. Due course. — If upon the filing of a
comment or such other pleading or documents as may Rule 13.11. Court action. — It is presumed that
be required or allowed by the Court of Appeals or upon a foreign arbitral award was made and released in
the expiration of the period for the filing thereof, and on due course of arbitration and is subject to
the basis of the petition or the records, the Court of enforcement by the court.
Appeals finds prima facie that the Regional Trial
Court has committed an error that would warrant
The court shall recognize and enforce a foreign be separated from those not so
arbitral award unless a ground to refuse recognition or submitted, that part of the award which
enforcement of the foreign arbitral award under this rule contains decisions on matters submitted
is fully established. to arbitration may be recognized and
enforced; or
The decision of the court recognizing and
enforcing a foreign arbitral award is immediately (d) The composition of the
executory. arbitral authority or the arbitral
procedure was not in accordance
In resolving the petition for recognition and
with the agreement of the parties, or,
enforcement of a foreign arbitral award in accordance
failing such agreement, was not in
with these Special ADR Rules, the court shall either [a]
accordance with the law of the country
recognize and/or enforce or [b] refuse to recognize and
where the arbitration took place; or
enforce the arbitral award. The court shall not disturb
the arbitral tribunal's determination of facts and/or (e) The award has not yet
interpretation of law. (Emphasis ours) become binding on the parties, or has
been set aside or suspended by a
Under Article V of the New York Convention, the grounds for
competent authority of the country in
refusing enforcement and recognition of a foreign arbitral award are:
which, or under the law of which, that
1. Recognition and enforcement of the award award was made.
may be refused, at the request of the party against
2. Recognition and enforcement of an arbitral
whom it is invoked, only if that party furnishes to the
award may also be refused if the competent authority in
competent authority where the recognition and
the country where recognition and enforcement is sought
enforcement is sought, proof that:
finds that:
(a) The parties to the agreement
(a) The subject matter of the
referred to in article II were, under the
difference is not capable of settlement
law applicable to them, under some
by arbitration under the law of that
incapacity, or the said agreement is not
country; or
valid under the law to which the parties
have subjected it or, failing any (b) The recognition or
indication thereon, under the law of the enforcement of the award would be
country where the award was made; or contrary to the public policy of that
country. (Emphasis ours)
(b) The party against whom the
award is invoked was not given proper The aforecited grounds are essentially the same grounds
notice of the appointment of the enumerated under Section 36 43 of the Model Law. The list is exclusive.
arbitrator or of the arbitration Thus, Section 45 of the ADR Act provides:
proceedings or was otherwise unable to
SEC. 45. Rejection of a Foreign Arbitral
present his case; or
Award. — A party to a foreign arbitration proceeding
(c) The award deals with a may oppose an application for recognition and
difference not contemplated by or not enforcement of the arbitral award in accordance with the
falling within the terms of the procedural rules to be promulgated by the Supreme
submission to arbitration, or it Court only on those grounds enumerated under
contains decisions on matters beyond Article V of the New York Convention. Any other
the scope of the submission to ground raised shall be disregarded by the regional
arbitration, provided that, if the decisions trial court. (Emphasis ours)
on matters submitted to arbitration can
In Our jurisdiction, We have incorporated the grounds appointment upon a proposal of a National Committee of
enumerated under the New York Convention in our arbitration laws. the ICC that it considers to be appropriate. If the Court
Article 4.36, Rule 6 44 of the IRR and Rule 13.4 45 of the Special ADR does not accept the proposal made, or if the National
Rules reiterated the exact same exclusive list of grounds. Committee fails to make the proposal requested within
the time limit fixed by the Court, the Court may repeat its
After a careful review of the case, We find that Mabuhay failed to
request or may request a proposal from another National
establish any of the grounds for refusing enforcement and recognition of
Committee that it considers to be appropriate.
a foreign arbitral award. We discuss the grounds raised by Mabuhay in
seriatim: xxx xxx xxx
A. The arbitral authority, composed 5. The sole arbitrator or the chairman of the
of Dr. Chatara-Opakorn as the sole Arbitral Tribunal shall be of a nationality other than
arbitrator, was constituted in those of the parties. However, in suitable
accordance with the arbitration circumstances and provided that neither of the parties
agreement. objects within the time limit fixed by the Court, the sole
arbitrator or the chairman of the Arbitral Tribunal may be
The first ground raised by Mabuhay is Article V (1) (d) of the New chosen from a country of which any of the parties is a
York Convention, i.e., that the composition of the arbitral authority was national. (Emphasis ours)
not in accordance with the agreement of the parties. Mabuhay and
In accordance with the aforecited rules, Dr. Chantara-Opakorn
Sembcorp stipulated in their Agreement that the sole arbitrator must
was appointed upon the proposal of the Thai National Committee.
have "expertise in the matter at issue." Since they also agreed that the
validity and the performance of the Agreement shall be governed by the It bears stressing that the pro-arbitration policy of the State
Philippine law, Mabuhay argues that the phrase "expertise in the matter includes its policy to respect party autonomy. Thus, Rule 2.3 of the
at issue" necessarily means expertise in the Philippine law. Dr. Chatara- Special ADR Rules provides that "the parties are free to agree on the
Opakorn, a Thai national, does not possess any educational degree or procedure to be followed in the conduct of arbitral proceedings." The
training in Philippine law. procedure to be followed on the appointment of arbitrator are among the
procedural rules that may be agreed upon by the parties.
The Agreement provides, however, that the arbitrator with
expertise in the matter at issue shall be appointed in accordance with the Moreover, under Rule 7.2 of the Special ADR Rules, a challenge
ICC Rules. The ICC, thus, is the appointing authority agreed upon by the to the appointment of an arbitrator may be raised in court only when the
parties. The "appointing authority" is the person or institution named in appointing authority fails or refuses to act on the challenge within such
the arbitration agreement as the appointing authority; or the regular period as may be allowed under the applicable rule or in the absence
arbitration institution under whose rule the arbitration is agreed to be thereof, within thirty (30) days from receipt of the request, that the
conducted. 46 Where the parties have agreed to submit their dispute to aggrieved party may renew the challenge in court. This is clearly not the
institutional arbitration rules, and unless they have agreed to a different case for Mabuhay as it was able to challenge the appointment of Dr.
procedure, they shall be deemed to have agreed to procedure under Chantara-Opakorn in accordance with Article 11 of the ICC Rules, but
such arbitration rules for the selection and appointment of arbitrators. 47 the ICC Court rejected the same. 48 As such, the Court shall not
entertain any challenge to the appointment of arbitrator disguised as a
The pertinent rules in the ICC Arbitration Rules of 1998 provide:
ground for refusing enforcement of an award.
Article 9 — Appointment and Confirmation of the
At any rate, Mabuhay's contention that the sole arbitrator must
Arbitrators
have the expertise on Philippine law fails to persuade. If the intent of the
parties is to exclude foreign arbitrators due to the substantive law of the
contract, they could have specified the same considering that the ICC
xxx xxx xxx Rules provide for appointment of a sole arbitrator whose nationality is
other than those of the parties.
3. Where the Court is to appoint a sole arbitrator B. The dispute is not an intra-
or the chairman of an Arbitral Tribunal, it shall make the corporate controversy, hence,
included in the scope of disputes the negative. The pertinent portion of the Final Award is reproduced as
submitted to arbitration. follows:
x x x Indeed, during the cross-examination of Mr.
Under Article V (1) (c) of the New York Convention, the court
Chay, he admitted that there was no transfer of shares
may refuse enforcement of a foreign arbitral award when the award deals
from IDHI to the Claimant [p. 130 of Transcript of
with a difference not contemplated by or not falling within the terms of the
Proceedings]:
submission to arbitration. Mabuhay argues that the dispute is an intra-
corporate controversy which is expressly excluded from the scope of xxx xxx xxx
disputes submitted to arbitration under the Agreement. In essence,
During the re-examination of Mr. Chay by the
Mabuhay attacks the jurisdiction of the arbitral tribunal to hear the
Respondent's counsel, he again admitted that the
dispute as it did not fall within the terms of submission to arbitration.
transfer of the shares from IDHI to the Claimant has not
The CA correctly applied the Kompetenz-Kompetenz principle taken effect [p. 155 of Transcript of Proceedings]:
expressly recognized under Rule 2.2 of the Special ADR Rules, viz.:
xxx xxx xxx
The Special ADR Rules recognize the principle
It is clear that the Claimant's claim is neither
of competence-competence, which means that the
premised on allegations of mismanagement of WJNA
arbitral tribunal may initially rule on its own jurisdiction,
and WJSC, nor on who manages or controls or who has
including any objections with respect to the existence or
the right to manage or control WJNA and WJSC, nor is it
validity of the arbitration agreement or any condition
a claim to effect the transfer of the share, nor an action
precedent to the filing of a request for arbitration.
for registration of the shares transfer [sic] already
The Special ADR Rules expounded on the implementation of the transferred from IDHI to the Claimant in the books of
said principle: WJNA and WJSC. The nature of the Claimant's claim is
not intrinsically connected with the regulation of the
Rule 2.4. Policy implementing competence-
corporation. The Claimant's claim in this arbitration is
competence principle. — The arbitral tribunal shall be
straightforward: that the Respondent agreed, under a
accorded the first opportunity or competence to rule on
contract, to make payment of certain amount of money
the issue of whether or not it has the competence or
to the Claimant upon the occurrence of a specified
jurisdiction to decide a dispute submitted to it for
event; that the said event occurred but the Respondent
decision, including any objection with respect to the
refused to pay such amount of money to the Claimant;
existence or validity of the arbitration agreement. When
that the Claimant filed the Request in order to enforce
a court is asked to rule upon issue/s affecting the
the payment. Accordingly, the Sole Arbitrator is of the
competence or jurisdiction of an arbitral tribunal in a
opinion that the dispute in this arbitration is not an
dispute brought before it, either before or after the
intra-corporate controversy, and, hence, it is not
arbitral tribunal is constituted, the court must exercise
excluded from arbitration under Article 19.2 of the
judicial restraint and defer to the competence or
Shareholders' Agreement. 49 (Emphasis ours)
jurisdiction of the arbitral tribunal by allowing the
arbitral tribunal the first opportunity to rule upon Again, the Special ADR Rules specifically provides that in
such issues. (Emphasis ours) resolving the petition for recognition and enforcement of a foreign arbitral
award, the court shall not disturb the arbitral tribunal's determination of
To recall, the Agreement provides that "(a)ny dispute,
facts and/or interpretation of law. 50
controversy or claim arising out of or relating to this Agreement, or
breach thereof, other than intra-corporate controversies, shall be finally Yet, the RTC, in its decision dismissing the petition of Sembcorp,
settled by arbitration. . ." declared that "it is undisputed that the shares of stocks of IDHI in WJNA
and WJSC were actually owned by [Sembcorp] before the filing of the
Among the issues settled in the Final Award is whether the
request for arbitration" 51 without providing any factual basis for such
dispute is an intra-corporate controversy. Dr. Chantara-Opakorn ruled in
conclusion which directly contradicts the arbitral tribunal's findings.
Even granting that the court may rule on the issue of whether the x x x At any rate, courts should not rashly extend
dispute is an intra-corporate controversy, Mabuhay's argument is the rule which holds that a contract is void as against
premised on the factual issue of whether Sembcorp indeed acquired the public policy. The term "public policy" is vague and
shares of IDHI. Mabuhay failed to establish such fact before the arbitral uncertain in meaning, floating and changeable in
tribunal. The RTC, on the other hand, concluded that Sembcorp acquired connotation. It may be said, however, that, in general, a
the subject shares but failed to explain the basis for such conclusion. In contract which is neither prohibited by law nor
the absence of sufficient evidence that Sembcorp acquired the shares of condemned by judicial decision, nor contrary to public
IDHI, the Court finds no cogent reason to disturb the arbitral tribunal's morals, contravenes no public policy. In the absence of
ruling in favor of the latter's jurisdiction over the dispute. express legislation or constitutional prohibition, a court,
in order to declare a contract void as against public
C. Enforcement of the award
policy, must find that the contract as to the consideration
would not be contrary to public
or thing to be done, has a tendency to injure the
policy of the Philippines.
public, is against the public good, or contravenes
some established interests of society, or is
Under Article V (2) (b) of the New York Convention, a court may inconsistent with sound policy and good morals, or
refuse to enforce an award if doing so would be contrary to the public tends clearly to undermine the security of individual
policy of the State in which enforcement is sought. Neither the New York rights, whether of personal liability or of private
Convention nor the mirroring provisions on public policy in the Model Law property. 58 (Emphasis ours)
and Our arbitration laws provide a definition of "public policy" or a
standard for determining what is contrary to public policy. Due to An older case, Ferrazzini v. Gsell, 59 defined public policy for
divergent approaches in defining public policy in the realm of purposes of determining whether that part of the contract under
international arbitration, public policy has become one of the most consideration is against public policy:
controversial bases for refusing enforcement of foreign arbitral
By "public policy," as defined by the courts in the
awards. 52
United States and England, is intended that principle of
Most arbitral jurisdictions adopt a narrow and restrictive the law which holds that no subject or citizen can
approach in defining public policy pursuant to the pro-enforcement policy lawfully do that which has a tendency to be injurious
of the New York Convention. The public policy exception, thus, is "a to the public or against the public good, which may
safety valve to be used in those exceptional circumstances when it would be termed the "policy of the law," or "public policy in
be impossible for a legal system to recognize an award and enforce it relation to the administration of the law." Public policy is
without abandoning the very fundaments on which it is based." 53 An the principle under which freedom of contract or private
example of a narrow approach adopted by several jurisdictions 54 is that dealing is restricted by law for the good of the public. In
the public policy defense may only be invoked "where enforcement [of determining whether a contract is contrary to public
the award] would violate the forum state's most basic notions of morality policy the nature of the subject matter determines the
and justice." 55 Thus, in Hong Kong, an award obtained by fraud was source from which such question is to be solved.
denied enforcement by the court on the ground that fraud is contrary to (Emphasis ours and citation omitted)
Hong Kong's "fundamental notions of morality and justice." 56 In
In light of the foregoing and pursuant to the State's policy in favor
Singapore, also a Model Law country, the public policy ground is
of arbitration and enforcement of arbitral awards, the Court adopts the
entertained by courts only in instances where upholding the award is
majority and narrow approach in determining whether enforcement of an
"clearly injurious to the public good or . . . wholly offensive to the ordinary
award is contrary to Our public policy. Mere errors in the interpretation of
reasonable and fully informed member of the public." 57
the law or factual findings would not suffice to warrant refusal of
In Our jurisdiction, the Court has yet to define public policy and enforcement under the public policy ground. The illegality or immorality of
what is deemed contrary to public policy in an arbitration case. However, the award must reach a certain threshold such that, enforcement of the
in an old case, the Court, through Justice Laurel, elucidated on the term same would be against Our State's fundamental tenets of justice and
"public policy" for purposes of declaring a contract void: morality, or would blatantly be injurious to the public, or the interests of
the society.
We now discuss the pertinent claims of Mabuhay in relation to and exemplary damages. The pertinent portion of the CA Decision is
public policy. reproduced as follows:
i. Violation of partnership law Turning now to Sembcorp's prayer for the award
of attorney's fees and exemplary damages, We find the
Mabuhay contends that it entered into a joint venture, which is
same bereft of legal and factual bases. Article 2208 of
akin to a particular partnership, with Sembcorp. Applying the laws on
the Civil Code allows attorney's fees to be awarded if the
partnership, the payment of the Guaranteed Return to Sembcorp is a
claimant is compelled to litigate with third persons or to
violation of Article 1799 60 of the Civil Code, as it shields the latter from
incur expenses to protect his interest by reason of an
sharing in the losses of the partnership. Ergo, enforcement of the Final
unjustified act or omission of the party from whom it is
Award would be contrary to public policy as it upholds a void stipulation.
sought, there must be a showing that the losing party
The restrictive approach to public policy necessarily implies that acted willfully or in bad faith and practically compelled
not all violations of the law may be deemed contrary to public policy. It is the claimant to litigate and incur litigation expenses.
not uncommon for the courts in Contracting States of the New York Meanwhile, in order to obtain exemplary damages under
Convention to enforce awards which does not conform to their domestic Article 2232 of the Civil Code, the claimant must prove
laws. 61 that the assailed actions of the defendant are not just
wrongful, but also wanton, fraudulent, reckless,
At any rate, Mabuhay's contention is bereft of merit. The joint oppressive or malevolent.
venture between Mabuhay, IDHI, and Sembcorp was pursued under the
Joint Venture Corporations, WJSC and WJNA. By choosing to adopt a Indeed, Sembcorp was compelled to file the
corporate entity as the medium to pursue the joint venture enterprise, the instant appeal. However, such fact alone is insufficient to
parties to the joint venture are bound by corporate law principles under justify an award of attorney's fees and exemplary
which the entity must operate. 62 Among these principles is the limited damages when there is no sufficient showing of MHC's
liability doctrine. The use of a joint venture corporation allows the co- [Mabuhay] bad faith in refusing to abide by the
venturers to take full advantage of the limited liability feature of the provisions of the Final Award. To Us, MHC's [Mabuhay]
corporate vehicle which is not present in a formal partnership persistent acts in rejecting Sembcorp's claim proceed
arrangement. 63 In fine, Mabuhay's application of Article 1799 is from an erroneous conviction in the righteousness of its
erroneous. cause. 65
ii. Imposition of interest We affirm the aforecited findings of the CA. However, We find no
conflict between the fallo and the ratio decidendi of the CA Decision.
Mabuhay argues that the twelve percent (12%) annual interest The fallo of the CA Decision includes "[n]o pronouncement as to cost."
from the date of the Final Award is also contrary to the Philippine law and The CA also reversed and set aside the RTC Decision in its entirety. As
jurisprudence. To reiterate, the only ground for refusing enforcement of a such, even the pronouncement of the RTC as to costs is set aside.
foreign arbitral award is when enforcement of the same would be Accordingly, We find no merit in Mabuhay's prayer for a statement in the
contrary to public policy. dispositive portion expressly stating that it is not liable for attorney's fees
Mere incompatibility of a foreign arbitral award with domestic and exemplary damages.
mandatory rules on interest rates does not amount to a breach of public On a final note, We implore the lower courts to apply the ADR
policy. However, some jurisdictions refused to recognize and enforce Act and the Special ADR Rules accordingly. Arbitration, as a mode of
awards, or the part of the award which was considered to be contrary to alternative dispute resolution, is undeniably one of the viable solutions to
public policy, where they considered that the awarded interest was the longstanding problem of clogged court dockets. International
unreasonably high. 64 In this case, the twelve percent (12%) interest rate arbitration, as the preferred mode of dispute resolution for foreign
imposed under the Final Award is not unreasonably high or companies, would also attract foreign investors to do business in the
unconscionable such that it violates our fundamental notions of justice. country that would ultimately boost Our economy. In this light, We uphold
IV. Attorney's Fees the policies of the State favoring arbitration and enforcement of arbitral
awards, and have due regard to the said policies in the interpretation of
Mabuhay avers that the dispositive portion of the CA Decision Our arbitration laws.
failed to include its finding that Mabuhay is not liable for attorney's fees
WHEREFORE, the Petition is hereby DENIED. The November
19, 2013 Decision and the June 3, 2014 Resolution of the Court of
Appeals in CA-G.R. CV No. 92296 are AFFIRMED.
SO ORDERED.
SECOND DIVISION money remittance, value-added taxes, dynamic fuel charge, trucking
costs, interests, and penalties ensued between the parties.
On May 11, 2011, in an effort to settle their commercial dispute,
[G.R. No. 216600. November 21, 2016.] FedEx and Air21 agreed to submit themselves to arbitration before the
Philippine Dispute Resolution Center (PDRC). Thus, on June 24, 2011,
FEDERAL EXPRESS CORPORATION and RHICKE S. FedEx filed its Notice of Arbitration. On October 3, 2011, the Arbitral
JENNINGS, petitioners, vs. AIRFREIGHT 2100, INC. and Tribunal was constituted.
ALBERTO D. LINA, respondents. As part of the arbitration proceedings, Jennings, John Lumley
Holmes (Holmes), the Managing Director of SPAC Legal of FedEx; and
David John Ross (Ross), Senior Vice President of Operations, Middle
DECISION East, India and Africa, executed their respective statements 5 as
witnesses for FedEx. Ross and Holmes deposed that Federal Express
MENDOZA, J p: Pacific, Inc., a subsidiary of FedEx, used to have an IFF license to
engage in the business of freight forwarding in the Philippines. This
Before the Court is a Petition for Review on Certiorari 1 under license, however, was suspended pending a case in court filed by Merit
Rule 45 of the Rules of Court filed by Federal Express International, Inc. (Merit) and Ace Logistics, Inc. (Ace), both freight
Corporation (FedEx) and Rhicke S. Jennings (Jennings), assailing the forwarding companies, which questioned the issuance of the IFF to
January 20, 2015 Decision 2 of the Court of Appeals (CA) in CA-G.R. SP FedEx. Absent the said license, FedEx executed the GSP contracts with
No. 135835, which affirmed the May 7, 2014 Order 3 of the Regional Air21 to be able to conduct its business in the Philippines. Ross and
Trial Court, Branch 70, Pasig City (RTC), dismissing its petition for the Holmes, in their individual statements, averred that Merit and Ace were
issuance of a confidentiality/protective order. either owned or controlled by Air21 employees or persons connected
FedEx is a foreign corporation doing business in the Philippines with the Lina Group of Companies, which included Air21.
primarily engaged in international air carriage, logistics and freight Jennings, in his cross-examination, was identified as the source
forwarding, while Jennings serves as its Managing Director for the of the information that Merit and Ace were Air21's proxies and was asked
Philippines and Indonesia. Respondent Airfreight 2100 (Air21) is a if he had any written proof of such proxy relationship. 6 He answered in
domestic corporation likewise involved in the freight forwarding business, the negative. In his re-direct examination, he was made to expound on
while Alberto Lina (Lina) is the Chairman of its Board of Directors. the supposed proxy relationship between Merit, Ace and Air21. 7 He
The Antecedents responded that Merit and Ace were just very small companies with
meager resources, yet they were able to finance and file a case to
FedEx, having lost its International Freight oppose the grant of IFF license to FedEx. Jennings also disclosed that
Forwarder's (IFF) license to engage in international freight forwarding in one of the directors of Ace was a friend of Lina and that Lorna Orbe, the
the Philippines, executed various Global Service President of Merit, was the former "boss" of Lito Alvarez, who was also
Program (GSP) contracts with Air21, an independent contractor, to associated with Air21.
primarily undertake its delivery and pick-up services within the country. 4
Feeling aggrieved by those statements, Lina for himself and on
Under the GSP arrangement, the packages sent by FedEx behalf of Air21, filed a complaint for grave slander against Jennings
customers from abroad would be picked up at a Philippine airport and before the Office of the City Prosecutor in Taguig City. 8 Lina claimed
delivered by Air21 to its respective consignees. Conversely, packages that the defamatory imputation of Jennings that Merit and Ace were
from Philippine clients would be delivered by Air21 to the airport and Air21's proxies brought dishonor, discredit and contempt to his name and
turned over to FedEx for shipment to consignees abroad. As stipulated in that of Air21. Lina quoted certain portions of the written statements of
the GSP contracts, Air21 guaranteed that all shipments would be cleared Holmes and Ross and the Transcript of Stenographic Notes (TSN) of the
through customs in accordance with Philippine law. In the April 25, 2013 arbitration hearing reflecting Jennings' testimony to
implementation of these contracts, however, several issues relating to support his complaint. HSAcaE
Consequently, FedEx and Jennings (petitioners) filed their A.
Petition for Issuance of a Confidentiality/Protective Order with Application THE COURT OF APPEALS FAILED TO APPLY, OR
for Temporary Order of Protection and/or Preliminary Injunction before OTHERWISE MISAPPLIED, SECTIONS 3(H) AND 23
the RTC alleging that all information and documents obtained in, or OF THE ADR ACT.
related to, the arbitration proceedings were confidential. 9 FedEx B.
asserted that the testimony of Jennings, a witness in the arbitration THE COURT OF APPEALS FAILED TO APPLY RULE
proceedings, should not be divulged and used to bolster the complaint- 10.5 OF THE SPECIAL ADR RULES.
affidavit for grave slander as this was inadmissible in evidence. C.
THE TEST APPLIED BY THE COURT OF APPEALS
On January 16, 2014, the RTC granted petitioners' application
FOR DETERMINING CONFIDENTIALITY OF
for the Temporary Order of Protection.
INFORMATION IS NOT SANCTIONED BY AND IS
Meanwhile, on February 3, 2014, the arbitral tribunal rendered INCONSISTENT WITH THE ADR ACT AND THE
an award in favor of FedEx. SPECIAL ADR RULES.
D.
Subsequently, in the assailed Order, dated May 7, 2014, the THE ASSAILED DECISION RESULTS TO
RTC denied FedEx's petition for lack of merit, stating that the statements SUBSTANTIAL PREJUDICE TO PETITIONERS.
and arbitration documents were not confidential information. It went on to E.
state that "[t]he statement and 'Arbitration Documents' which purportedly THE ASSAILED DECISION DEFEATS PUBLIC
consists the crime of Grave Slander under Articles 353 and 358 of the POLICY ON CONFIDENTIALITY OF THE RECORDS
Revised Penal Code are not in any way related to the subject under OF AND COMMUNICATIONS MADE IN THE COURSE
Arbitration." The RTC further wrote that "a crime cannot be protected by OF ARBITRATION. 13
the confidentiality rules under ADR. The said rules should not be used as
a shield in the commission of any crime." Thus, it disposed: FedEx argues that the Jennings' statements were part of the (a)
records and evidence of Arbitration (Section 23); (b) witness statements
WHEREFORE, in view of the foregoing, the made therein (Section 3 [h] [3]); and (c) communication made in a
Petition for Issuance of a Confidentiality/Protective Order dispute resolution proceedings (Section 3 [h] [1]). 14 They, thus, averred
is hereby DENIED for lack of merit. that Jennings' oral statements made during the April 25, 2013 arbitration
The case is hereby DISMISSED. hearing and the TSN of the hearings, conducted on April 22 and 25,
2013, form part of the records of arbitration and must, therefore, be
SO ORDERED. 10 considered confidential information.
Dissatisfied, petitioners challenged the RTC order before the For said reason, petitioners assert that Rule 10.5 of the Special
CA via a petition for review. Alternative Dispute Resolution (ADR) Rules, allowing for the issuance of
On January 20, 2015, the CA denied the petition. In its assailed a confidentiality/protective order, was completely disregarded by the CA
decision, the CA explained that the declarations by Jennings were not when it denied the petition filed by FedEx as a result of Lina divulging
confidential as they were not at all related to the subject of mediation as what were supposed to be confidential information from ADR
the arbitration proceedings revolved around the parties' claims for sum of proceedings.
money. 11 Thus, the CA ruled that "statements made without any Petitioners also claim that in ruling that Jennings' statements
bearing on the subject proceedings are not confidential in nature." It must were not confidential information, by applying the test of relevance that
be emphasized that other declarations given therein, if relative to the "statements made without any bearing on the subject proceedings are
subject of mediation or arbitration, are certainly confidential." 12 not confidential in nature," the CA used a "test" that had no basis in law
Hence, this present petition before the Court. and whose application in its petition amounted to judicial legislation. 15
Respondent Air21 and Lina (respondents), in their
Comment, 16 essentially countered that:
GROUNDS IN SUPPORT OF THE PETITION
While the Alternative Dispute Resolution Act of
2004 (the "ADR Law") confers communications made
during arbitration the privilege against disclosure, motions manifestations, witness statements,
otherwise known as the confidentiality principle, to assist reports filed or submitted in an arbitration or for
the parties in having a speedy, efficient and impartial expert evaluation. [Emphases Supplied]
resolution of their disputes, said privilege cannot be
The said list is not exclusive and may include other information
invoked to shield any party from criminal responsibility.
as long as they satisfy the requirements of express confidentiality or
The privilege is not absolute. The ADR Law does not
implied confidentiality. 18
exist in a vacuum without regard to other existing
jurisprudence and laws, particularly the Revised Penal Plainly, Rule 10.1 of A.M. No. 07-11-08-SC or the Special Rules
Code. Otherwise, we will permit a dangerous situation of Court on Alternative Dispute Resolution (Special ADR Rules) allows
where arbitration proceedings will be used by an "[a] party, counsel or witness who disclosed or who was compelled to
unscrupulous disputant as a venue for the commission of disclose information relative to the subject of ADR under circumstances
crime, which cannot be punished by the simple that would create a reasonable expectation, on behalf of the source, that
invocation of the privilege. Such an absurd interpretation the information shall be kept confidential xxx the right to prevent such
of our laws cannot be deemed to be the underlying will of information from being further disclosed without the express written
our Congress in framing and enacting our law on consent of the source or the party who made the disclosure." Thus, the
arbitration. To be sure, a crime cannot be protected or rules on confidentiality and protective orders apply when:
extinguished through a bare invocation of the
1. An ADR proceeding is pending;
confidentiality rule. 17
2. A party, counsel or witness disclosed information or was
otherwise compelled to disclose information;
3. The disclosure was made under circumstances that would
The Court's Ruling
create a reasonable expectation, on behalf of the source,
that the information shall be kept confidential; HESIcT
The crucial issue in this case is whether the testimony of 4. The source of the information or the party who made the
Jennings given during the arbitration proceedings falls within the ambit of disclosure has the right to prevent such information from
confidential information and, therefore, covered by the mantle of a being disclosed;
confidentiality/protection order. 5. The source of the information or the party who made the
disclosure has not given his express consent to any
The Court finds the petition meritorious. disclosure; and
Section 3 (h) of Republic Act (R.A.) No. 9285 or the Alternative 6. The applicant would be materially prejudiced by an
Dispute Resolution of 2004 (ADR Act) defines confidential information as unauthorized disclosure of the information obtained, or to
follows: be obtained, during the ADR proceeding.
"Confidential information" means any Gauged by the said parameters, the written statements of
information, relative to the subject of mediation or witnesses Ross, Holmes and Jennings, as well as the latter's oral
arbitration, expressly intended by the source not to be testimony in the April 25, 2013 arbitration hearing, both fall under Section
disclosed, or obtained under circumstances that would 3 (h) [1] and [3] of the ADR Act which states that "communication, oral or
create a reasonable expectation on behalf of the source written, made in a dispute resolution proceedings, including any
that the information shall not be disclosed. It shall memoranda, notes or work product of the neutral party or non-party
include (1) communication, oral or written, made in a participant, as defined in this Act; and (3) pleadings, motions,
dispute resolution proceedings, including any manifestations, witness statements, reports filed or submitted in an
memoranda, notes or work product of the neutral party arbitration or for expert valuation," constitutes confidential information.
or non-party participant, as defined in this Act; (2) an oral Notably, both the parties and the Arbitral Tribunal had agreed to
or written statement made or which occurs during the Terms of Reference (TOR) that "the arbitration proceedings should
mediation or for purposes of considering, conducting, be kept strictly confidential as provided in Section 23 of the ADR Act and
participating, initiating, continuing of reconvening Article 25-A 19 of the PDRCI Arbitration Rules (Arbitration Rules) and
mediation or retaining a mediator; and (3) pleadings, that they should all be bound by such confidentiality requirements."
The provisions of the ADR Act and the Arbitration Rules confined to the discussion of the core issues in the arbitral dispute. By
repeatedly employ the word "shall" which, in statutory construction, is definition, "relative" simply means "connected to," which means that
one of mandatory character in common parlance and in ordinary parties in arbitration proceedings are encouraged to discuss openly their
signification. 20 Thus, the general rule is that information disclosed by a grievances and explore the circumstances which might have any
party or witness in an ADR proceeding is considered privileged and connection in identifying the source of the conflict in the hope of finding a
confidential. better alternative to resolve the parties' dispute. An ADR proceeding is
aimed at resolving the parties' conflict without court intervention. It was
In evaluating the merits of the petition, Rule 10.8 of the Special
not designed to be strictly technical or legally confined at all times. By
ADR Rules mandates that courts should be guided by the principle that
mutual agreement or consent of the parties to a controversy or dispute,
confidential information shall not be subject to discovery and shall be
they acquiesce to submit their differences to arbitrators for an informal
inadmissible in any adversarial proceeding, to wit:
hearing and extra-judicial determination and resolution. Usually, an ADR
Rule 10.8. Court action. — If the court finds the petition hearing is held in private and the decision of the persons selected to
or motion meritorious, it shall issue an order enjoining a comprise the tribunal will take the place of a court judgment. This avoids
person or persons from divulging confidential the formalities, delays and expenses of an ordinary litigation. Arbitration,
information. as envisioned by the ADR Act, must be taken in this perspective.
In resolving the petition or motion, the courts shall be
Verily, it is imperative that legislative intent or spirit be the
guided by the following principles applicable to all ADR
controlling factor, the leading star and guiding light in the application and
proceedings: Confidential information shall not be
interpretation of a statute. 22 If a statute needs construction, the
subject to discovery and shall be inadmissible in any
influence most dominant in that process is the intent or spirit of the
adversarial proceeding, whether judicial or quasi judicial.
act. 23 A thing which is within the intent of the lawmaker is as much
However, evidence or information that is otherwise
within the statute as if within the letter; and a thing which is within the
admissible or subject to discovery does not become
letter of the statute is not within the statute unless within the intent of the
inadmissible or protected from discovery solely by
lawmakers. 24 In other words, a statute must be read according to its
reason of its use therein.
spirit or intent and legislative intent is part and parcel of the statute. It is
Article 5.42 of the Implementing Rules and the controlling factor in interpreting a statute. Any interpretation that
Regulations (IRR) 21 of the ADR Act likewise echoes that arbitration contradicts the legislative intent is unacceptable.
proceedings, records, evidence and the arbitral award and other
In the case at bench, the supposed questionable statements
confidential information are privileged and confidential and shall not be
surfaced when FedEx's suspended IFF license was discussed during the
published except [i] with the consent of the parties; or [ii] for the limited
arbitration hearing. In fact, when Jennings was asked by Arbitrator
purpose of disclosing to the court relevant documents where resort to the
Panga to expound on how the opposition of Ace and Merit could be
court is allowed. Given that the witness statements of Ross, Holmes and
related to the ongoing arbitration, Jennings replied that, to his mind, it
Jennings, and the latter's arbitration testimony, fall within the ambit of
was indicative of the leverage that Air21 had over FedEx as it was able
confidential information, they must, as a general rule, remain confidential.
to withhold large sums of money and siphon their joint plans from being
Although there is no unbridled shroud of confidentiality on information
properly established. Whether the information disclosed in the arbitration
obtained or disclosed in an arbitration proceeding, the presence of the
proceeding would be given weight by the tribunal in the resolution of their
above criteria must be apparent; otherwise, the general rule should be
dispute is a separate matter. Likewise, the relevance or materiality of the
applied. Here in this case, only a perceived imputation of a wrongdoing
said statements should be best left to the arbitrators' sound appreciation
was alleged by the respondents. caITAC
and judgment. Even granting that the weight of the said statements was
In denying the said application for confidentiality/protection order, not fundamental to the issues in the arbitration process, nevertheless,
the RTC and the CA did not consider the declarations contained in the they were still connected to, and propounded by, a witness who relied
said witness statements and arbitration testimony to be related to the upon the confidentiality of the proceedings and expect that his responses
subject of arbitration and, accordingly, ruled that they could not be be reflected.
covered by a confidentiality order.
Arbitration, being an ADR proceeding, was primarily designed to
The Court does not agree. Suffice it to say that the phrase be a prompt, economical and amicable forum for the resolution of
"relative to the subject of mediation or arbitration" need not be strictly disputes. It guarantees confidentiality in its processes to encourage
parties to ventilate their claims or disputes in a less formal, but Thus, the claimed slanderous statements by Jennings during the
spontaneous manner. It should be emphasized that the law favors arbitration hearing are deemed confidential information and the veil of
settlement of controversies out of court. Thus, a person who participates confidentiality over them must remain.
in an arbitration proceeding is entitled to speak his or her piece without
WHEREFORE, the petition is GRANTED. The January 20, 2015
fear of being prejudiced should the process become unsuccessful.
Decision of the Court of Appeals (CA), in CA-G.R. SP No. 135835,
Hence, any communication made towards that end should be regarded
is REVERSED and SET ASIDE.
as confidential and privileged.
The Petition for the Issuance of a Confidentiality/Protective Order
To restate, the confidential nature of the arbitration proceeding is
filed by Federal Express Corporation and Rhicke S. Jennings is
well-entrenched in Section 23 of the ADR Act:
hereby GRANTED. ICHDca
SEC. 23. Confidentiality of Arbitration
SO ORDERED.
Proceedings. — The arbitration proceedings, including
the records, evidence and the arbitral award, shall be
considered confidential and shall not be published
except (1) with the consent of the parties, or (2) for the
limited purpose of disclosing to the court of relevant
documents in cases where resort to the court is allowed
herein. Provided, however, that the court in which the
action or the appeal is pending may issue a protective
order to prevent or prohibit disclosure of documents or
information containing secret processes, developments,
research and other information where it is shown that the
applicant shall be materially prejudiced by an authorized
disclosure thereof.
If Lina had legal grounds to suspect that Jennings committed
slanderous remarks even before the arbitration proceeding commenced,
then he must present evidence independent and apart from some quoted
portions of the arbitration documents.
It must be stressed that the very soul of an arbitration proceeding
would be rendered useless if it would be simply used as an avenue for
evidence gathering or an entrapment mechanism to lure the other
unsuspecting party into conveying information that could be potentially
used against him in another forum or in court.
Ultimately, the RTC and the CA failed to consider the fact that an
arbitration proceeding is essentially a unique proceeding that is non-
litigious in character where the parties are bound by a different set of
rules as clearly encapsulated under the Special ADR Rules. Inevitably,
when Lina cited portions of the said arbitration documents, he violated
their covenant in the TOR to resolve their dispute through the arbitration
process and to honor the confidentiality of the said proceeding. To
disregard this commitment would impair the very essence of the ADR
proceeding. By itself, this would have served as a valid justification for
the grant of the confidentiality/protection order in favor of FedEx and
Jennings.
THIRD DIVISION On October 29, 2009, Power filed a request for arbitration in the
CIAC invoking the arbitration clause of the Contract of Service reading as
follows:
[G.R. No. 211504. March 8, 2017.]
15. ARBITRATION COMMITTEE — All disputes,
controversies or differences, which may arise between
FEDERAL BUILDERS, INC., petitioner, vs. POWER the parties herein, out of or in relation to or in connection
FACTORS, INC., respondent. with this Agreement, or for breach thereof shall be
settled by the Construction Industry Arbitration
Commission (CIAC) which shall have original and
DECISION exclusive jurisdiction over the aforementioned
disputes. 5
On November 20, 2009, Atty. Vivencio Albano, the counsel of
Federal, submitted a letter to the CIAC manifesting that Federal agreed
BERSAMIN, J p: to arbitration and sought an extension of 15 days to file its answer, which
request the CIAC granted.
An agreement to submit to voluntary arbitration for purposes of
vesting jurisdiction over a construction dispute in the Construction On December 16, 2009, Atty. Albano filed his withdrawal of
Industry Arbitration Commission (CIAC) need not be contained in the appearance stating that Federal had meanwhile engaged another
construction contract, or be signed by the parties. It is enough that the counsel. 6
agreement be in writing. Federal, represented by new counsel (Domingo, Dizon,
The Case Leonardo and Rodillas Law Office), moved to dismiss the case on the
ground that CIAC had no jurisdiction over the case inasmuch as the
Federal Builders Inc. (Federal) appeals to reverse the decision Contract of Service between Federal and Power had been a mere draft
promulgated on August 12, 2013, 1 whereby the Court of Appeals (CA) that was never finalized or signed by the parties. Federal contended that
affirmed the adverse decision rendered on May 12, 2010 by the in the absence of the agreement for arbitration, the CIAC had no
Construction Industry Arbitration Commission (CIAC) with modification of jurisdiction to hear and decide the case. 7
the total amount awarded. 2
On February 8, 2010, the CIAC issued an order setting the case
Antecedents for hearing, and directing that Federal's motion to dismiss be resolved
after the reception of evidence of the parties. 8
Federal was the general contractor of the Bullion Mall under a
construction agreement with Bullion Investment and Development Federal did not thereafter participate in the proceedings until the
Corporation (BIDC). In 2004, Federal engaged respondent Power CIAC rendered the Final Award dated May 12, 2010, 9 disposing:
Factors, Inc. (Power) as its subcontractor for the electric works at the
In summary: Respondent Federal Builders, Inc.
Bullion Mall and the Precinct Building for P18,000,000.00. 3
is hereby ordered to pay claimant Power Factors, Inc.
On February 19, 2008, Power sent a demand letter to Federal the following sums:
claiming the unpaid amount of P11,444,658.97 for work done by Power
for the Bullion Mall and the Precinct Building. Federal replied that its 1. Unpaid balance on the original contract P4,276,614.75;
outstanding balance under the original contract only amounted to
2. Unpaid balance on change order nos. 1, 2, 3,
P1,641,513.94, and that the demand for payment for work done by
4, 5, 6, 7, 8, & 9 3,006,970.32;
Power after June 21, 2005 should be addressed directly to
BIDC. 4 Nonetheless, Power made several demands on Federal to no 3. Interest to May 13, 2010 1,686,149.94;
avail.
4. Attorney's Fees 250,000.00; Contract of Service; and that Federal's contention that its former
counsel's act of manifesting its consent to the arbitration stipulated in the
5. Cost of Arbitration 149,503.86; draft Contract of Service did not bind it was inconsequential on the issue
of jurisdiction. 12
P9,369,238.87
Concerning the amounts awarded, the CA opined that the CIAC
should not have allowed the increase based on labor-cost escalation
The foregoing amount shall earn legal interest at
because of the absence of the agreement between the parties on such
the rate of 6% per annum from the date of this Final
escalation and because there was no authorization in writing allowing the
Award until this award becomes final and executory,
adjustment or increase in the cost of materials and labor. 13
Claimant shall then be entitled to 12% per annum until
the entire amount is fully satisfied by Respondent. After the CA denied Federal's motion for reconsideration on
February 19, 2004, 14 Federal has come to the Court on appeal.
Federal appealed the award to the CA insisting that the CIAC
had no jurisdiction to hear and decide the case; and that the amounts Issue
thereby awarded to Power lacked legal and factual bases.
The issues to be resolved are: (a) whether the CA erred in
On August 12, 2013, the CA affirmed the CIAC's decision with upholding CIAC's jurisdiction over the present case; and (b) whether the
modification as to the amounts due to Power, 10 viz.: CA erred in holding that Federal was liable to pay Power the amount of
WHEREFORE, the CIAC Final Award dated 12 P7,140,728.07.
May 2010 in CIAC Case No. 31-2009 is Ruling of the Court
hereby AFFIRMED with MODIFICATION. As modified,
FEDERAL BUILDERS, INC. is ordered to pay POWER The appeal is bereft of merit.
FACTORS, INC. the following: 1.
1. Unpaid balance on the original contract P4,276,614.75; The parties had an effective agreement
to submit to voluntary arbitration;
2. Unpaid balance on change orders 2,864,113.32;
hence, the CIAC had jurisdiction
3. Attorney's Fees 250,000.00; The need to establish a proper arbitral machinery to settle
4. Cost of Arbitration 149,503.86; disputes expeditiously was recognized by the Government in order to
promote and maintain the development of the country's construction
industry. With such recognition came the creation of the CIAC through
The interest to be imposed on the net award Executive Order No. 1008 (E.O. No. 1008), also known as The
(unpaid balance on the original contract and change Construction Industry Arbitration Law. Section 4 of E.O. No. 1008
order) amounting to P7,140,728.07 awarded to POWER provides:
FACTORS, INC. shall be six (6%) per annum, reckoned
from 4 July 2006 until this Decision becomes final and Sec. 4. Jurisdiction. — The CIAC shall have
executory. Further, the total award due to POWER original and exclusive jurisdiction over disputes arising
FACTORS, INC. shall be subjected to an interest of from, or connected with, contracts entered into by parties
twelve percent (12%) per annum computed from the time involved in construction in the Philippines, whether the
this judgment becomes final and executory, until full dispute arises before or after the completion of the
satisfaction. contract, or after the abandonment or breach thereof.
These disputes may involve government or private
SO ORDERED. 11 contracts. For the Board to acquire jurisdiction, the
Anent jurisdiction, the CA explained that the CIAC Revised parties to a dispute must agree to submit the same
Rules of Procedure stated that the agreement to arbitrate need not be to voluntary arbitration. x x x
signed by the parties; that the consent to submit to voluntary arbitration
was not necessary in view of the arbitration clause contained in the
Under the CIAC Revised Rules of Procedure Governing national labor force aside from its being a leading contributor to the gross
Construction Arbitration (CIAC Revised Rules), all that is required for the national product. 16
CIAC to acquire jurisdiction is for the parties of any construction contract
Worthy to note is that the jurisdiction of the CIAC is over the
to agree to submit their dispute to arbitration. 15 Also, Section 2.3 of
dispute, not over the contract between the parties. 17 Section 2.1, Rule 2
the CIAC Revised Rules states that the agreement may be reflected in
of the CIAC Revised Rules particularly specifies that the CIAC has
an arbitration clause in their contract or by subsequently agreeing to
original and exclusive jurisdiction over construction disputes, whether
submit their dispute to voluntary arbitration. The CIAC Revised
such disputes arise from or are merely connected with the construction
Rules clarifies, however, that the agreement of the parties to submit their
contracts entered into by parties, and whether such disputes
dispute to arbitration need not be signed or be formally agreed upon in
arise before or after the completion of the contracts. Accordingly, the
the contract because it can also be in the form of other modes of
execution of the contracts and the effect of the agreement to submit to
communication in writing, viz.:
arbitration are different matters, and the signing or non-signing of one
RULE 4 — EFFECT OF AGREEMENT TO does not necessarily affect the other. In other words, the formalities of
ARBITRATE the contract have nothing to do with the jurisdiction of the CIAC.
SECTION 4.1. Submission to CIAC jurisdiction — An Federal contends that there was no mutual consent and no
arbitration clause in a construction contract or a meeting of the minds between it and Power as to the operation and
submission to arbitration of a construction dispute shall binding effect of the arbitration clause because they had rejected the
be deemed an agreement to submit an existing or draft service contract.
future controversy to CIAC jurisdiction,
The contention of Federal deserves no consideration.
notwithstanding the reference to a different arbitration
institution or arbitral body in such contract or submission. Under Article 1318 of the Civil Code, a valid contract should
have the following essential elements, namely: (a) consent of the
4.1.1 When a contract contains a clause for the
contracting parties; (b) object certain that is the subject matter of the
submission of a future controversy to arbitration, it is not
contract; and (c) cause or consideration. Moreover, a contract does not
necessary for the parties to enter into a submission
need to be in writing in order to be obligatory and effective unless the law
agreement before the Claimant may invoke the
specifically requires so. Pursuant to Article 1356 18 and Article
jurisdiction of CIAC.
1357 19 of the Civil Code, contracts shall be obligatory in whatever form
4.1.2 An arbitration agreement or a submission to they may have been entered into, provided that all the essential
arbitration shall be in writing, but it need not be requisites for their validity are present. Indeed, there was a contract
signed by the parties, as long as the intent is clear between Federal and Power even if the Contract of Service was
that the parties agree to submit a present or future unsigned. Such contract was obligatory and binding between them by
controversy arising from a construction contract to virtue of all the essential elements for a valid contract being present.
arbitration. It may be in the form of exchange of
It clearly appears that the works promised to be done by Power
letters sent by post or by telefax, telexes, telegrams,
were already executed albeit still incomplete; that Federal paid Power
electronic mail or any other mode of communication.
P1,000,000.00 representing the originally proposed downpayment, and
The liberal application of procedural rules as to the form by the latter accepted the payment; and that the subject of their dispute
which the agreement is embodied is the objective of the CIAC Revised concerned only the amounts still due to Power. The records further show
Rules. Such liberality conforms to the letter and spirit of E.O. No. 1008 that Federal admitted having drafted the Contract of Services containing
itself which emphasizes that the modes of voluntary dispute resolution the following clause on submission to arbitration, to wit:
like arbitration are always preferred because they settle disputes in a
15. ARBITRATION COMMITTEE — All disputes,
speedy and amicable manner. They likewise help in alleviating or
controversies or differences, which may arise between
unclogging the judicial dockets. Verily, E.O. No. 1008 recognizes that the
the Parties herein, out of or in relation to or in connection
expeditious resolution of construction disputes will promote a healthy
with this Agreement, or for breach thereof shall be
partnership between the Government and the private sector as well as
settled by the Construction Industry Arbitration
aid in the continuous growth of the country considering that the
Commission (CIAC) which shall have original and
construction industry provides employment to a large segment of the
exclusive jurisdiction over the aforementioned favor of arbitration. 26 In this connection, the CA correctly observed that
disputes. 20 the act of Atty. Albano in manifesting that Federal had agreed to the form
of arbitration was unnecessary and inconsequential considering the
With the parties having no issues on the provisions or parts of
recognition of the value of the Contract of Service despite its being an
the Contract of Service other than that pertaining to the downpayment
unsigned draft.
that Federal was supposed to pay, Federal could not validly insist on the
lack of a contract in order to defeat the jurisdiction of the CIAC. As earlier 2.Amounts as modified by the CA are correct
pointed out, the CIAC Revised Rules specifically allows any written mode
of communication to show the parties' intent or agreement to submit to We find no reversible error regarding the amounts as modified by
arbitration their present or future disputes arising from or connected with the CA. Power did not sufficiently establish that the change or increase of
their contract. the cost of materials and labor was to be separately determined and
approved by both parties as provided under Article 1724 of the Civil
The CIAC and the CA both found that the parties had disagreed Code. As such, Federal should not be held liable for the labor cost
on the amount of the downpayment. On its part, Power indicated after escalation.
receiving and reviewing the draft of the Contract of Service that it wanted
30% as the downpayment. Even so, Power did not modify anything else WHEREFORE, the Court AFFIRMS the decision promulgated on
in the draft, and returned the draft to Federal after signing it. It was August 12, 2013; and ORDERS the petitioner to pay the costs of suit.
Federal that did not sign the draft because it was not amenable to the SO ORDERED.
amount as modified by Power. It is notable that the arbitration clause
written in the draft of Federal was unchallenged by the parties until their
dispute arose.
Moreover, Federal asserted the original contract to support its
claim against Power. If Federal would insist that the remaining amount
due to Power was only P1,641,513.94 based on the original
contract, 21 it was really inconsistent for Federal to rely on the draft when
it is beneficial to its side, and to reject its efficacy and existence just to to
relieve itself from the CIAC's unfavorable decision.
The agreement contemplated in the CIAC Revised Rules to vest
jurisdiction of the CIAC over the parties' dispute is not necessarily an
arbitration clause to be contained only in a signed and finalized
construction contract. The agreement could also be in a separate
agreement, or any other form of written communication, as long as their
intent to submit their dispute to arbitration is clear. The fact that a
contract was signed by both parties has nothing to do with the jurisdiction
of the CIAC, and this is the explanation why the CIAC Revised
Rules itself expressly provides that the written communication or
agreement need not be signed by the parties.
Although the agreement to submit to arbitration has been
expressly required to be in writing and signed by the parties therein by
Section 4 22 of Republic Act No. 876 (Arbitration Law), 23 the
requirement is conspicuously absent from the CIAC Revised Rules,
which even expressly allows such agreement not to be signed by the
parties therein. 24 Brushing aside the obvious contractual agreement in
this case warranting the submission to arbitration is surely a step
backward. 25 Consistent with the policy of encouraging alternative
dispute resolution methods, therefore, any doubt should be resolved in
THIRD DIVISION Although the Contractor's Agreement contained no date of the
units' turnover, it allowed Charter Chemical to choose the units for
offsetting under an offsetting scheme:
[G.R. No. 198849. August 7, 2019.]
1. Compensation:
CAMP JOHN HAY DEVELOPMENT xxx xxx xxx
CORPORATION, petitioner, vs. CHARTER CHEMICAL b. Off-setting against Two (2) Units —
AND COATING CORPORATION, respondent. Studio Type at Suite 2A. Total amount
shall be based on the final unit[s]
chosen by the Contractor. 9
DECISION Charter Chemical chose Units 102 and 104 studio type in the
second phase of Camp John Hay Suites. 10 aScITE
At the time the Contractor's Agreement was signed in 2001, the
LEONEN, J p: actual construction of the Camp John Hay Suites had not yet
commenced. 11
Rescission under Article 1191 of the Civil Code is the proper Later on, the contract price was reduced to P13,239,734.16, for
remedy when a party breaches a reciprocal obligation. Because each which Camp John Hay Development paid P7,339,734.16. The balance of
case has its own distinct circumstances, this Court's power to fix a period P5,900,000.00 was ought to be settled by offsetting the price of the two
of an obligation under Article 1197 is discretionary and should be (2) studio units. 12
exercised only if there is just cause.
In 2003, Charter Chemical completed the painting works, after
This resolves a Petition for Review on Certiorari 1 assailing the which Camp John Hay Development issued a Final Inspection and
May 13, 2011 Decision 2 and September 30, 2011 Resolution 3 of the Acceptance Certificate belatedly on May 30, 2005. Charter Chemical
Court of Appeals in CA-G.R. SP No. 108335. The Court of Appeals demanded the execution of the deed of sale and delivery of the titles of
affirmed the March 30, 2009 Final Award 4 in CIAC Case No. 19-2008 the two (2) units in September 2004, with a follow-up in April 2005. 13 In
issued by the Construction Industry Arbitration Commission, which found June 2005, Camp John Hay Development and Charter Chemical
that Charter Chemical and Coating Corporation (Charter Chemical) is executed contracts to sell. The uniform contracts state in part:
entitled to the payment of the monetary equivalent of two (2) units in
Camp John Hay Suites in the total amount of P5,900,000.00 and [P]ossession of the Unit shall be delivered by Seller to
attorney's fees in the amount of P590,000.00. 5 Buyer within a reasonable period of time from the date of
completion of the Unit either by (a) serving written Notice
Camp John Hay Development Corporation (Camp John Hay of Completion to the Buyer or (b) by delivering to the
Development) is the investment arm of a consortium engaged in the Buyer the Limited Warranty Deed covering the Unit. The
construction of the Camp John Hay Manor in Baguio City. 6 delivery of the Notice of Completion or the Limited
In January 2001, Camp John Hay Development entered into a Warranty Deed shall constitute constructive delivery of
Contractor's Agreement 7 with Charter Chemical, the company awarded the Unit and immediately thereafter the risk of loss to the
to complete the interior and exterior painting works of unit 2E of the Unit and all obligations and assessments provided in this
Camp John Hay Manor for the contract price of P15,500,000.00. This Contract, the Project Plan and Declaration of
was inclusive of the price of two (2)-studio type units at Camp John Hay Restrictions, the Articles of Incorporation and By-Laws of
Suites, the total amount of which would be based on the units chosen by the Association, and the House Rules, shall pertain to
Charter Chemical. 8 Buyer. 14
In August 2005, Camp John Hay Development issued
certifications to Charter Chemical that the two (2) units were fully paid
under their offsetting scheme. However, the units were not delivered 1. Claimant is entitled to its claim for the
because the construction of Camp John Hay Suites was not yet monetary equivalent of the two (2) units CJH Suites in
complete. 15 the total sum of Php5,900,000.00.
Camp John Hay Development had initially estimated that the 2. Claimant is not entitled to its claim for
construction would be completed by 2006. In a Lease exemplary damages.
Agreement 16 executed on October 19, 1996, Camp John Hay
3. Claimant is entitled to its claim for attorney's
Development and Bases Conversion and Development Authority
fees for the sum of Php590,000.00 which is 10% of the
provided for a period of three and a half (3.5) years from the execution of
total monetary value for the two (2) units CJH Suites of
the Lease Agreement to complete the various physical components in
Php5,900,000.00 which had not been delivered by
Camp John Hay. When this timetable was not followed due to alleged
respondent. HEITAD
mutual delays and force majeure, they entered into at least four (4) more
amendments to the Lease Agreement. Two (2) of these, the July 18, 4. The Court should not fix the period for the
2003 and July 1, 2008 Memoranda of Agreement, covered the revision of delivery of the subject units as provided for in Article
the Project Implementation Plan providing the targeted completion dates 1197 of the Civil Code because the reciprocal nature of
of the various facilities in Camp John Hay. 17 the contract itself provides for the period of their delivery.
Moreover, CIAC can fix the period if necessary. 25
Under the July 18, 2003 revision, Camp John Hay Development
and Bases Conversion and Development Authority estimated that the Camp John Hay Development filed before the Court of Appeals a
second phase of the Camp John Hay Suites would be completed by the Petition for Review 26 under Rule 43 of the Rules of Court. It argued that
end of the second quarter of 2006. 18 Admitting various unforeseen the arbitral tribunal did not have jurisdiction over the dispute because the
events, Camp John Hay Development again failed to complete its arbitration clause had been superseded by a subsequent dispute
construction. Under the July 1, 2008 revision, the Camp John Hay Suites resolution clause contained in the contracts to sell. 27 It further asserted
was estimated to be completed by 2012. 19 that it had neither agreed on the completion date of the two (2) units nor
admitted that the units were to be completed within three (3) years from
Due to the subsisting construction delay, Charter Chemical,
2003 or 2005. 28 Instead, it asked for a fixing of the term or period when
through counsel, wrote Camp John Hay Development, demanding that it
the units would be completed. 29
transfer the units or pay the value of these units in the sum of
P6,996,517.48. 20 In its May 13, 2011 Decision, 30 the Court of Appeals affirmed
the arbitral tribunal's award. It held that the arbitration clause in the
When it felt that further demands would be futile, Charter
Contractor's Agreement was neither modified nor superseded by the
Chemical, on June 12, 2008, filed before the Construction Industry
contracts to sell, which were merely devices by which to transfer
Arbitration Commission a Request for Arbitration 21 under the arbitration
possession and title over the units to Charter Chemical. The Contractor's
clause in the Contractor's Agreement.
Agreement, it noted, remained the principal covenant. 31
In its March 30, 2009 Final Award, 22 the Construction Industry
The Court of Appeals also ruled that Camp John Hay
Arbitration Commission ordered Camp John Hay Development to pay the
Development was already in delay when Charter Chemical demanded
amounts of P5,900,000.00, the monetary value of the two (2) units in
the transfer of units on August 3, 2007. When Charter Chemical finished
Camp John Hay Suites, and P590,000.00 as attorney's fees. 23
the work in 2003, a timetable based on the 2003 Memorandum of
The arbitral tribunal ruled that Charter Chemical was entitled to Agreement between Camp John Hay Development and Bases
its claim for the value of the two (2) units because Camp John Hay Conversion and Development Authority stated that the units would be
Development failed to deliver the units within the targeted completion completed by 2006. This showed that there was a definite time for the
date. 24 completion of the units. Although Charter Chemical was an outsider to
this agreement, it was "equivalent to an announcement to all concerned
The Final Award read:
that the units would be completed at such and such a date." 32
On the basis of the evidence the Arbitration
On June 3, 2011, Camp John Hay Development filed a Motion
Tribunal finds and so holds that:
for Reconsideration, but it was denied by the Court of Appeals in its
September 30, 2011 Resolution. 33
Camp John Hay Development received the September 30, 2011 MISCELLANEOUS PROVISION
Resolution on October 7, 2011. 34 Before the lapse of the original 15-day
xxx xxx xxx
period, it filed on October 21, 2011 a Motion for Extension of Time to File
Petition for Review under Rule 45, asking for a period of 30 days from 4. Venue — All actions involving this Contract
October 22, 2011, or until November 21, 2011, within which to file the shall be instituted only in the proper courts of Pasig City,
Petition. 35 This Motion for Extension was granted by this Court. 36 Metro Manila to the exclusion of all other courts. 49
On November 23, 2011, Camp John Hay Development filed a From the dispute resolution clause, petitioner points out that
Petition for Review on Certiorari. 37 Charter Chemical filed its disputes must be adjudicated by the proper courts of Pasig City, to the
Comment 38 on February 6, 2012 and, in turn, Camp John Hay exclusion of all other courts. The contracts to sell also effectively
Development filed its Reply 39 on May 16, 2012. removed the parties' dispute outside the ambit of a construction dispute
since they are not the construction contracts contemplated by Executive
Petitioner contends that there is no specific date determined for
Order No. 1008, or the Construction Industry Arbitration Law. 50
the completion or delivery of the two (2) units in any of its contracts with
respondent. It argues that the action filed should have been for the fixing Petitioner further contests the award of attorney's fees to
of a period under Articles 1191 40 and 1197 41 of the Civil Code, and not respondent, maintaining that neither the Court of Appeals nor the arbitral
an action for the rescission of the contract. 42 tribunal has specified the factual basis for it. It argues that the award of
attorney's fees is not justified when both tribunals denied respondent's
According to petitioner, both the arbitral tribunal and the Court of
claim for exemplary damages and when petitioner has not been found to
Appeals erred in ruling that the Contractor's Agreement between
have acted in bad faith. Respondent, it points out, also failed to present
petitioner and respondent had a definite timetable based on the
any official receipt to support its claim for attorney's fees. 51
Memorandum of Agreement between petitioner and the Bases
Conversion and Development Authority. Moreover, petitioner argues that On the other hand, respondent argues that the Court of Appeals'
the determination of whether there is an agreed completion date must be and the arbitral tribunal's decisions, entitling respondent to the monetary
based on the agreement between petitioner and respondent in their equivalent of the units for offsetting, should be respected and accorded
contract. Thus, when the Court of Appeals resorted to a separate great weight and finality. Respondent points out that it only agreed to bid
agreement different from the Contractor's Agreement, it recognized that for the painting works because Interpro, Inc., petitioner's project
the parties had never actually agreed on a specific completion date. 43 manager, assured that under the Master Development Plan, the units
would be available for occupancy two (2) to three (3) years from
Petitioner relies on Article 1311 44 of the Civil Code, which
negotiations, or sometime in 2003. 52
states that "contracts take effect only between the parties who execute
them." 45 It also points out that respondent did not rely on the Master Respondent further argues that since petitioner was already
Development Plan in the Memorandum of Agreement, maintaining that delayed in delivering the units in 2007, the arbitral tribunal and the Court
its representative admitted having never seen the Master Development of Appeals correctly applied Article 1191 of the Civil Code, awarding
Plan when he signed the agreement. 46 Petitioner also notes that at the indemnity for damages to respondent. 53
time of the execution of the Contractor's Agreement, respondent had not
Moreover, respondent claims that the arbitral tribunal correctly
yet selected the two (2) units as part of its compensation for its painting
acquired jurisdiction over the dispute because the relationship of the
works. Petitioner argues that the date of delivery was not specified in the
parties was born out of the Contractor's Agreement. 54 The Contractor's
contracts to sell, which merely indicated that the delivery would be "within
Agreement provided the arbitration clause in case of any dispute. The
a reasonable time from the date of completion of the subject
contracts to sell "cannot be considered to have superseded the
units." 47 ATICcS
Contractor's Agreement" 55 because they are merely preparatory
Additionally, petitioner claims that the arbitral tribunal had no contracts required for the processing of the titles of the units. 56
jurisdiction over the Complaint. It asserts that the contracts to sell
Lastly, respondent claims that the award of attorney's fees was
executed following the Contractor's Agreement contain a different mode
justified, as petitioner's unwarranted delay and unjustified refusal to settle
of dispute resolution. 48 The contracts to sell provide the following
the matter brought about its filing of the Complaint before the arbitral
clause:
tribunal. 57
ARTICLE XIV
For this Court's resolution are the following issues:
First, whether or not the Court of Appeals erred in ruling that the which shall continue to be covered by the Labor Code of
Construction Industry Arbitration Commission has jurisdiction over the the Philippines.
dispute despite the existence of a dispute resolution clause;
For the Construction Industry Arbitration Commission to acquire
Second, whether or not the Court of Appeals correctly rescinded jurisdiction, the law merely requires that the parties agree to submit to
the obligation under Article 1191 of the Civil Code and whether or not a voluntary arbitration any dispute arising from construction contracts.
period should be fixed under Article 1197 of the Civil Code; and
In HUTAMA-RSEA Joint Operations, Inc. v. Citra Metro Manila
Finally, whether or not the Court of Appeals erred in affirming the Tollways Corporation: 61
award of attorney's fees to respondent Charter Chemical and Coating
Under Section 1, Article III of the CIAC Rules, an
Corporation.
arbitration clause in a construction contract shall be
The Petition is denied. deemed as an agreement to submit an existing or future
controversy to CIAC jurisdiction, "notwithstanding the
I
reference to a different arbitration institution or arbitral
The Construction Industry Arbitration Commission was created body in such contract. . . ." . . .
under Executive Order No. 1008 to establish an arbitral machinery that
. . . The arbitration clause in the construction
will "settle expeditiously problems arising from, or connected with,
contract ipso facto vested the CIAC with jurisdiction.
contracts in the construction industry." 58 It has jurisdiction over
This rule applies, regardless of whether the parties
"construction disputes between or among parties to an arbitration
specifically choose another forum or make reference to
agreement, or those who are otherwise bound by the latter, directly or by
another arbitral body. Since the jurisdiction of CIAC is
reference." 59 Its purpose is to encourage the early and expeditious
conferred by law, it cannot be subjected to any condition;
settlement of disputes in the construction industry, recognizing that it is
nor can it be waived or diminished by the stipulation, act
necessary to avert delays in the resolution of construction industry
or omission of the parties, as long as the parties agreed
disputes, which is important to attain the national development
to submit their construction contract dispute to
goals. 60 TIADCc
arbitration, or if there is an arbitration clause in the
Section 4 of the Construction Industry Arbitration Law lays down construction contract. The parties will not be precluded
the jurisdiction of the Construction Industry Arbitration Commission: from electing to submit their dispute to CIAC, because
this right has been vested in each party by law.
SECTION 4. Jurisdiction. — The CIAC shall
have original and exclusive jurisdiction over disputes xxx xxx xxx
arising from, or connected with, contracts entered into by
It bears to emphasize that the mere existence of
parties involved in construction in the Philippines,
an arbitration clause in the construction contract is
whether the dispute arises before or after the completion
considered by law as an agreement by the parties to
of the contract, or after the abandonment or breach
submit existing or future controversies between them to
thereof. These disputes may involve government or
CIAC jurisdiction, without any qualification or condition
private contracts. For the Board to acquire jurisdiction,
precedent. To affirm a condition precedent in the
the parties to a dispute must agree to submit the same to
construction contract, which would effectively suspend
voluntary arbitration.
the jurisdiction of the CIAC until compliance therewith,
The jurisdiction of the CIAC may include but is would be in conflict with the recognized intention of the
not limited to violation of specifications for materials and law and rules to automatically vest CIAC with jurisdiction
workmanship; violation of the terms of agreement; over a dispute should the construction contract contain
interpretation and/or application of contractual time and an arbitration clause. 62 (Citations omitted)
delays; maintenance and defects; payment, default of
Arbitration of construction disputes through the Construction
employer or contractor and changes in contract cost.
Industry Arbitration Commission was incorporated into the general
Excluded from the coverage of this law are statutory framework on alternative dispute resolution through Republic
disputes arising from employer-employee relationships Act No. 9285, or the Alternative Dispute Resolution Act of
2004. 63 Chapter 6, Section 34 of this law explicitly referenced the that covers the asserted dispute, an order to arbitrate
Construction Industry Arbitration Law, while Section 35 affirmed the should be granted. Any doubt should be resolved in
Construction Industry Arbitration Commission's jurisdiction: favor of arbitration. 67 (Citations omitted)
CHAPTER 6 Here, petitioner and respondent agreed to submit to arbitration
any dispute arising from the construction contract, as clearly stipulated in
Arbitration of Construction Disputes
their Contractor's Agreement. The arbitration clause should, thus, be
SECTION 34. Arbitration of Construction given primacy in accordance with the State's policy to favor arbitration. It
Disputes: Governing Law. — The arbitration of follows that if there is any doubt as to what provision should be given
construction disputes shall be governed by Executive effect, this Court will rule in favor of the arbitration clause.
Order No. 1008, otherwise known as the Construction
Moreover, the contracts to sell, containing a contrary dispute
Industry Arbitration Law.
resolution clause, did not supersede the arbitration clause. The case
SECTION 35. Coverage of the Law. — records show that the contracts to sell are not inconsistent with the
Construction disputes which fall within the original and Contractor's Agreement. They are merely devices to facilitate the transfer
exclusive jurisdiction of the Construction Industry of ownership of the two (2) units to respondent — an offshoot of the
Arbitration Commission (the "Commission") shall include offsetting scheme provision in the Contractor's Agreement.
those between or among parties to, or who are otherwise
While the contracts to sell and the Contractor's Agreement both
bound by, an arbitration agreement, directly or by
refer to the transfer of the two (2) units to respondent, the contracts to
reference whether such parties are project owner,
sell are pro-forma contracts provided by petitioner in selling the Camp
contractor, subcontractor, fabricator, project manager,
John Hay Suites units. There is no intent to supersede the Contractor's
design professional, consultant, quantity surveyor,
Agreement, which remains the principal contract between petitioner and
bondsman or issuer of an insurance policy in a
respondent.
construction project. AIDSTE
Petitioner erred in claiming that because the contracts to sell are
The Commission shall continue to exercise
not construction contracts, they effectively removed the parties' dispute
original and exclusive jurisdiction over construction
outside the ambit of a construction dispute. On the contrary, the subject
disputes although the arbitration is "commercial"
of the contracts to sell still falls within the jurisdiction of the Construction
pursuant to Section 21 of this Act.
Industry Arbitration Commission. Section 4 of the Construction Industry
Arbitration, "[b]eing an inexpensive, speedy[,] and amicable Arbitration Law states that its jurisdiction includes "payment [and] default
method of settling disputes . . . is encouraged by the Supreme of employer or contractor[.]" Here, the main dispute concerning the
Court." 64 If any doubt will arise, it "should be resolved in favor of contracts to sell all boils down to the issue of payment of the two (2) units
arbitration." 65 for the services rendered by respondent. Hence, the units' transfer as
payment to respondent still falls under the jurisdiction of the arbitral
In LM Power Engineering Corp. v. Capitol Industrial Construction tribunal.
Groups, Inc., 66 this Court explained the rationale behind this policy:
This dispute is better left to the expertise of the Construction
Aside from unclogging judicial dockets, arbitration also Industry Arbitration Commission, a quasi-judicial body with the technical
hastens the resolution of disputes, especially of the expertise to resolve disputes outside the expertise of regular
commercial kind. It is thus regarded as the "wave of the courts. 68 Aptly, it should adjudicate and determine the claims and rights
future" in international civil and commercial disputes. of petitioner and respondent with respect to the construction contract and
Brushing aside a contractual agreement calling for all its incidents.
arbitration between the parties would be a step
backward. It is worth noting that this dispute has been ongoing for over a
decade now. Despite numerous meetings and negotiations prior to
Consistent with the above-mentioned policy of respondent's filing of a Complaint before the arbitral tribunal, no amicable
encouraging alternative dispute resolution methods, settlement had been reached. Disregarding the proceedings that took
courts should liberally construe arbitration clauses. place before the lower tribunals and requiring the parties to submit the
Provided such clause is susceptible of an interpretation
dispute before the trial court would be merely dilatory at this point. It may seek rescission and, in the absence of any just
would only entail additional expenses and unnecessary delays for both cause for the court to determine the period of
parties. compliance, the court shall decree the
rescission. 72 (Citations omitted)
II
"Resolution grants the injured party the option to pursue, as
Rescission on account of breach of reciprocal obligations is
principal actions, either a rescission or specific performance of the
provided under Article 1191 of the Civil Code:
obligation, with payment of damages in either case." 73
ARTICLE 1191. The power to rescind
Rescission of the contract is sanctioned here. Under the
obligations is implied in reciprocal ones, in case one of
contract, petitioner and respondent have reciprocal obligations.
the obligors should not comply with what is incumbent
Respondent, for its part, was bound to render painting services for
upon him. AaCTcI
petitioner's property. This was completed by respondent in 2003, after
The injured party may choose between the which it was belatedly issued a clearance in 2005. Meanwhile, in
fulfillment and the rescission of the obligation, with the accordance with the Contractor's Agreement, petitioner paid part of the
payment of damages in either case. He may also seek contract price with the remaining balance to be paid through offsetting of
rescission, even after he has chosen fulfillment, if the two (2) Camp John Hay Suites units. However, despite incessant
latter should become impossible. demands from respondent, petitioner failed to deliver these units
because their construction had yet to be completed. The law, then, gives
The court shall decree the rescission claimed, respondent the right to seek rescission because petitioner could not
unless there be just cause authorizing the fixing of a comply with what is incumbent upon it. Petitioner, however, claims that
period. the fixing of the period under Article 1197 is the proper remedy, not
This is understood to be without prejudice to the rescission under Article 1191.
rights of third persons who have acquired the thing, in This Court disagrees. We cannot cure the deficiency here by
accordance with articles 1385 and 1388 and the fixing the period of the obligation. There is no just cause for this Court to
Mortgage Law. fix the period for the benefit of petitioner.
This provision refers to rescission applicable to reciprocal Article 1197 applies "when the obligation does not fix a period
obligations. It is invoked when there is noncompliance by one (1) of the but from its nature and circumstances it can be inferred that a period was
contracting parties in case of reciprocal obligations. "Reciprocal intended[.]" 74 This provision allows the courts to fix the duration
obligations are those which arise from the same cause, and in which "because the fulfillment of the obligation itself cannot be demanded until
each party is a debtor and a creditor of the other, such that the obligation after the court has fixed the period for compliance therewith and such
of one is dependent upon the obligation of the other. They are to be period has arrived." 75
performed simultaneously such that the performance of one is
conditioned upon the simultaneous fulfillment of the other." 69 In Deudor v. J.M. Tuason & Company, Inc.: 76
Rescission under Article 1191 will be ordered when a party to a Article 1197 is part and parcel of all obligations
contract fails to comply with his or her obligation. Rescission "is a contemplated therein. Hence, whenever a period is fixed
principal action that is immediately available to the party at the time that pursuant to said Article, the court merely enforces or
the reciprocal [obligation] was breached." 70 In Spouses Velarde v. carries out an implied stipulation in the contract in
Court of Appeals: 71 question. In fact, insofar as contracts not fixing a period
are concerned, said legal provision applies only if, from
The right of rescission of a party to an obligation the nature and circumstances surrounding the contract
under Article 1191 of the Civil Code is predicated on a involved, "it can be inferred that a period was intended"
breach of faith by the other party who violates the by the parties thereto. For this reason, the last paragraph
reciprocity between them. The breach contemplated in of Article 1197, ordains that "in every case, the courts
the said provision is the obligor's failure to comply with shall determine such period as may under the
an existing obligation. When the obligor cannot comply circumstances have been probably contemplated by the
with what is incumbent upon [him or her], the obligee
parties." In other words, in fixing said period, the Court If the contract so provided, then there was a period fixed,
merely ascertains the will of the parties and gives effect a "reasonable time"; and all that the court should have
thereto. 77 EcTCAD done was to determine if that reasonable time had
already elapsed when suit was filed. If it had passed,
As stipulated in Article 1197, this Court must determine that the
then the court should declare that petitioner had
obligation does not fix a period or that the period is made to depend upon
breached the contract, as averred in the complaint, and
the will of the debtor, but it can be inferred from its nature and the
fix the resulting damages. On the other hand, if the
circumstances that a period was intended. Then, it must be determined
reasonable time had not yet elapsed, the court perforce
what period was probably contemplated by the parties. 78
was bound to dismiss the action for being premature. But
The power of this Court to fix a period is discretionary. The in no case can it be logically held that under the plea
surrounding facts of each case must be taken into consideration in above quoted, the intervention of the court to fix the
deciding whether the fixing of a period is sanctioned. The discretion to fix period for performance was warranted, for Article 1197 is
an obligation's period is addressed to this Court's judgment and is precisely predicated on the absence of any period fixed
tempered by equitable considerations. by the parties. 82
In Central Philippine University v. Court of Appeals, 79 this Court There is no just cause for this Court to determine the period of
refused to fix a period because of the years that had already been compliance. As can be gleaned from the records of this case, the
allowed for the party to comply with the condition of the obligation. Doing obligation of petitioner to build the Camp John Hay Suites had been
so, it held, would be a mere technicality and formality, and would only dragging for years even before it entered into the Contractor's Agreement
cause further delay. This Court ruled: with respondent.
This general rule however cannot be applied The Memorandum of Agreement that petitioner executed with
considering the different set of circumstances existing in the Bases Conversion and Development Authority shows that the
the instant case. More than a reasonable period of fifty construction of the Camp John Hay Suites began in 1996. When
(50) years has already been allowed petitioner to avail of respondent demanded the units' transfer in 2007, more than 10 years
the opportunity to comply with the condition even if it be had lapsed; yet, within those years, petitioner was still not able to
burdensome, to make the donation in its favor forever complete the construction of the Camp John Hay Suites.
valid. But, unfortunately, it failed to do so. Hence, there
To tolerate petitioner's excuses would only cause more delay
is no more need to fix the duration of a term of the
and burden to respondent. Petitioner failed to forward any just cause to
obligation when such procedure would be a mere
convince this Court to set a period. It merely reasoned force majeure and
technicality and formality and would serve no purpose
mutual delays with Bases Conversion and Development Authority without
that to delay or lead to an unnecessary and expensive
offering any explanation for its alleged difficulty in building the units.
multiplication of suits. Moreover, under Art. 1191 of the
Civil Code, when one of the obligors cannot comply with To belatedly fix the period for petitioner's compliance would
what is incumbent upon him, the obligee may seek mean refusing immediate payment to respondent. Petitioner's
rescission and the court shall decree the same unless noncompliance with its obligation to deliver the two (2) units as payment
there is just cause authorizing the fixing of a period. In to respondent can no longer be excused.
the absence of any just cause for the court to determine
The law and jurisprudence are clear. When the obligor cannot
the period of the compliance, there is no more obstacle
comply with its obligation, the obligee may exercise its right to rescind
for the court to decree the rescission
the obligation, and this Court will order the rescission in the absence of
claimed. 80 (Citation omitted)
any just cause to fix the period. 83 Here, lacking any reasonable
In Gregorio Araneta, Inc. v. Philippine Sugar Estates explanation and just cause for the fixing of the period for petitioner's
Development Company, Ltd., 81 this Court held that if a reasonable noncompliance, the rescission of the obligation is justified. HSAcaE
period was agreed upon in a contract, all that the court should have done
III
was determine if that reasonable time had already elapsed:
Rescission of the obligation under Article 1191 is a declaration
that a contract is void at its inception. Its effect is to restore the parties to
their original position, insofar as practicable. Fong v. Dueñas 84 is Again, since Article 1385 of the Civil Code
illustrative: expressly and clearly states that "rescission creates the
obligation to return the things which were the object of
Rescission has the effect of "unmaking a contract, or its
the contract, together with their fruits, and the price with
undoing from the beginning, and not merely its
its interest," the Court finds no justification to sustain
termination." Hence, rescission creates the obligation to
petitioners' position that said Article 1385 does not apply
return the object of the contract. It can be carried out
to rescission under Article 1191. 90
only when the one who demands rescission can return
whatever he may be obliged to restore. To rescind is to Article 1385 of the Civil Code provides:
declare a contract void at its inception and to put an end
ARTICLE 1385. Rescission creates the
to it as though it never was. It is not merely to terminate
obligation to return the things which were the object of
it and release the parties from further obligations to each
the contract, together with their fruits, and the price with
other, but to abrogate it from the beginning and restore
its interest; consequently, it can be carried out only when
the parties to their relative positions as if no contract has
he who demands rescission can return whatever he may
been made. 85
be obliged to restore.
Mutual restitution is required in cases involving rescission under
Neither shall rescission take place when the
Article 1191. "Where a contract is rescinded, it is the duty of the court to
things which are the object of the contract are legally in
require both parties to surrender that which they have respectively
the possession of third persons who did not act in bad
received and to place each other as far as practicable in his original
faith.
situation[;] the rescission has the effect of abrogating the contract in all
parts." 86 In this case, indemnity for damages may be
demanded from the person causing the loss. (Emphasis
In Spouses Serrano v. Court of Appeals: 87
supplied)
Generally, the rule is that to rescind a contract is
Although rescission repeals the contract from its inception, it
not merely to terminate it, but to abrogate and undo it
does not disregard all the consequences that the contract has created.
from the beginning; that is, not merely to release the
What mutual rescission entails is "the return of the benefits that each
parties from further obligations to each other in respect
party may have received as a result of the contract." 91
to the subject of the contract, but to annul the contract
and restore the parties to the relative positions which Here, it is clear that only petitioner benefited from the contract.
they would have occupied if no such contract had ever Respondent has already performed the painting works in 2003, and it
been made. Rescission necessarily involves a was accepted by petitioner as satisfactory. Since this service cannot be
repudiation of the contract and a refusal of the moving undone and petitioner has already enjoyed the value of the painting
party to be further bound by it. 88 (Citation omitted) services over the years, respondent is entitled to the payment of the
painting services with interest in accordance with Articles 1191 and 2210
This Court has explained that restitution under Article 1385 of the
of the Civil Code. 92 The interest shall be computed from the date of
Civil Code equally applies for rescission under Article 1191. In Laperal v.
extrajudicial demand by respondent on August 3, 2007 in accordance
Solid Homes, Inc.: 89
with Article 1169 93 of the Civil Code and this Court's ruling in Nacar v.
Despite the fact that Article 1124 of the old Civil Gallery Frames. 94
Code from whence Article 1191 was taken, used the
IV
term "resolution," the amendment thereto (presently,
Article 1191) explicitly and clearly used the term Generally, the parties may stipulate the recovery of attorney's
"rescission." Unless Article 1191 is subsequently fees, but in the absence of such, Article 2208 of the Civil Code
amended to revert back to the term "resolution," this enumerates instances when these fees may still be
Court has no alternative but to apply the law, as it is recovered: 95 HESIcT
written.
ARTICLE 2208. In the absence of stipulation, attorney's fees under Article 2208 demands factual,
attorney's fees and expenses of litigation, other than legal, and equitable justification. Even when a claimant is
judicial costs, cannot be recovered, except: compelled to litigate with third persons or to incur
expenses to protect his rights, still attorney's fees may
(1) When exemplary damages are
not be awarded where no sufficient showing of bad faith
awarded;
could be reflected in a party's persistence in a case other
(2) When the defendant's act or than an erroneous conviction of the righteousness of his
omission has compelled the plaintiff to cause. 97 (Citations omitted)
litigate with third persons or to incur
The grant of attorney's fees depends on the evaluation of each
expenses to protect his interest;
case and is within this Court's discretion. Attorney's fees may be
(3) In criminal cases of malicious awarded if a party was forced to litigate and incur expenses to protect its
prosecution against the plaintiff; right and interest due to another party's unjustified act or omission. 98
(4) In case of a clearly unfounded civil Here, we agree with the findings of the Construction Industry
action or proceeding against the plaintiff; Arbitration Commission and the Court of Appeals. Respondent is entitled
to the award of attorney's fees.
(5) Where the defendant acted in gross
and evident bad faith in refusing to In awarding attorney's fees, the arbitral tribunal explained that
satisfy the plaintiff's plainly valid, just respondent was compelled to engage the services of a lawyer to recover
and demandable claim; the two (2) Camp John Hay Suites units or their monetary value; thus, it
incurred expenses to protect its interest after petitioner had breached
(6) In actions for legal support; their contract. 99 In affirming this Final Award, the Court of Appeals
(7) In actions for the recovery of wages found that respondent undeniably needed adequate legal representation
of household helpers, laborers and to recover on a clearly demandable claim, making the additional expense
skilled workers; inevitable. 100
(8) In actions for indemnity under Unmistakably, there was breach of faith. Petitioner violated the
workmen's compensation and reciprocity of its contract with respondent. This case dragged on for
employer's liability laws; years because petitioner unjustifiably refused to pay respondent's valid
claim. In the proceedings before the arbitral tribunal, petitioner even
(9) In a separate civil action to recover rejected respondent's offer to settle the dispute by paying the balance of
civil liability arising from a crime; the contract price. While petitioner enjoyed the benefit of the painting
(10) When at least double judicial costs services, respondent is forced to await payment, foregoing the use and
are awarded; value of money that have compounded over the years. caITAC
(11) In any other case where the court Clearly, petitioner's refusal to pay compelled respondent to file
deems it just and equitable that the Complaint and incur expenses in the process. Considering the years
attorney's fees and expenses of that had lapsed, during which respondent incessantly demanded
litigation should be recovered. payment, it is only equitable to award attorney's fees.
In all cases, the attorney's fees and expenses of WHEREFORE, the Petition for Review on Certiorari is DENIED.
litigation must be reasonable. (Emphasis supplied) The Court of Appeals May 13, 2011 Decision and September 30, 2011
Resolution in CA-G.R. SP No. 108335 are AFFIRMED WITH
Generally, attorney's fees cannot be recovered as part of MODIFICATION.
damages, as no premium should be placed on the right to litigate.
In ABS-CBN Broadcasting Corporation v. Court of Appeals: 96 Petitioner Camp John Hay Development Corporation is ordered
to pay respondent Charter Chemical and Coating Corporation: (1) the
[Attorney's fees] are not to be awarded every time a balance of the contract price in the amount of Five Million Nine Hundred
party wins a suit. The power of the court to award Thousand Pesos (P5,900,000.00) with interest at the rate of twelve
percent (12%) per annum from August 3, 2007 until June 30, 2013, and
six percent (6%) per annum from July 1, 2013 until its full satisfaction;
and (2) attorney's fees in the amount of Five Hundred Ninety Thousand
Pesos (P590,000.00).
SO ORDERED.