GNPOWER DINGININ LTD. CO.

CONSTRUCTION
GNPD 03 00 1 MCP 50XXX 0
MANAGEMENT

Electrical Completion (Final Inspection) Punchlist

System Title: Boiler System Number:


Sub-system Air Pre Heater
Sub-system Number:
Title:
Drawing 1
Unit:
Number:
FI&TR Number: Date: July 9, 2019

P&ID Number:

(Strikethrough if
not applicable)
System Walk Down Inspection System WTP Inspection

Defect Category
Item Disci Initiate P/L
Equipment Description
No. p d By Initiato Comm
r
MJN

Air Pre-
1 ECI Heater
Motor

Lifting crane and lifting beam for maintenance unavailable,


and inadequate platform access.

Defect Category Description: Discipline :


A - Must be corrected before system commissioning
B - Must be corrected before automated operation B = Boiler; T = Turbine; C = Civil; ECI = Electrical /
C - Must be corrected before performance/reliability test Control & Instrumentation; BoP = Balance of Plant
D - Must be corrected before commercial operation date
Mechanical Completion (Final Inspection) Punchlist Acceptance
GNPD GNPD Quality GNPD Commissioning GNPD O&M
GNPD Construction
Engineering
Name:
Position:

Signature:

Date:

GNPD 03 00 1 TEM 50130 1 - Effective Date 2019.06.19 Page 1 of 1