Analiza Transporta Dizalicom
Analiza Transporta Dizalicom
ODJEL: GRADITELJSTVO
Ak. god. 2019./2020.
Varaždin, 2020.
SADRŽAJ
1. UVOD…………………………………………………………………………………………………….2
2. SHEMATSKI PRIKAZ GRADILIŠTA…………………………………………………………….3
3. ANALIZA POTREBNIH KOLIČINA MATERIJALA
3.1. OPLATA
3.1.1. Oplata za zidove ……………………………………………………………………..4
3.1.2. Oplata za stropnu ploču ………………………………………………………….5
3.2. BETON…………………………………………………………………………………………6
3.3. ARMATURA………………………………………………………………………………….7
4. GRAĐEVINSKI STROJEVI, ALATI I OPREMA ……………………………………………..8
5. ANALIZA TRANSPORTA DIZALICOM
5.1. OPLATA ……………………………………………………………………………………..10
5.2. ARMATURA ……………………………………………………………………………….14
5.3. BETON ……………………………………………………………………………………….17
6. GRAFIKON ……………………………………………………………………………………………22
7. TROŠKOVNIK DIZALICE LIEBHERR 112 EC-H 8
7.1. OPLATA……………………………………………………………………………………..24
7.2. ARMATURA……………………………………………………………………………….26
7.3. BETON……………………………………………………………………………………….27
7.4. SVEUKUPNI TROŠAK RADA DIZALICE LIEBHERR 112 EC-H 8………..29
ZADATAK
Na temelju analize učinka dizalice isplanirati moguću dinamiku pri transportu i ugradnji
potrebnih materijala te pri betoniranju košarom vanjskih zidova i ploče jedne 4-etažne
zgrade, tlocrta prema priloženoj skici, visina jedne etaže iznosi 2.60m.
1
1. UVOD
Ovaj seminarski rad prikazuje postupak izvođenja analize, za transport dizalice, računskom
metodologijom koja se odnosi samo na proračun onih strojeva koji rade ciklički i na čiji rad
najveći učinak ima „ljudski čimbenik“.
2
2. SHEMATSKI PRIKAZ GRADILIŠTA
3
3. ANALIZA POTREBNIH KOLIČINA MATERIJALA
3.1. OPLATA
4
3.1.2. Oplata za stropnu ploču
---------------------------------------------------------------------------------------------------------------------------
Ukupna površina ploča = 6000 m2
Ukupna površina oplate = 6020 m2
Preostala površina = 20 m2
Sveukupna težina = 123 323 kg
Ukupna količina dijelova = 1749 kom
5
3.2. BETON
Pretpostavili smo da temeljna ploča postoji te izgradnja zgrade počinje od nosivih zidova
prvog kata zgrade. Otvore (vrata i prozore) riješili smo na način da smo od ukupne količine
vanjskih zidova oduzeli 10% betona. Vertikalne komunikacije (npr. stubišta i dizalo) nismo
uzimali u proračun. Nosivi sustav zgrade sastoji se samo od vanjskih nosivih zidova debljine
20cm dok unutarnjih nosivih zidova nema. Stropna ploča je debljine 20cm.
BETON:
1 etaža (zidovi + ploča):
- zidovi 2 x (50 x 2,60 x 0,20) + 2 x (30 x 2,60 x 0,20) = 83,2 m 3
-
AB stropna ploča 50 x 30 x 0,20 = 300 m3
Pošto smo dobili količinu armiranog betona potrebnog za izgradnju zgrade, a zanima nas
koliko betona trebamo za izgradnju, od ukupne kubikaže armiranog betona oduzmemo 4%
koji zauzima armatura.
TEŽINA 1m3 armiranog betona = 2500 kg/m3
KOLIČINA ARMATURE po 1m3 = 100 kg
2500 100
1% = = 25 -> postotak armature u 1m3 betona = = 4%
100 25
Pošto je 4% kubikaža armature, a armatura se računa u m, ovih 4% podijelili smo s 3 kako bi
dobili neku realnu količinu betona koji se oduzima zbog armature od ukupne količine
armiranog betona.
4%/3 = 1.333
Da bi dobili količinu betona koji je potrebno dopremiti i ugraditi na gradilište, od ukupne
količine armiranog betona oduzeli smo 4%/3.
4% od 1499,52 = 59,9808/3 = 19,9936
1499,52 – 19,9936 = 1479, 5264 m3
Za izgradnju zgrade potrebno nam je 1479,53 m3 betona.
6
3.3. ARMATURA
Kako bi dobili količinu potrebne armature za izgradnju zgrade, uzeli smo ukupnu količinu
betona koji se doprema na gradilište i pomnožili sa 100kg.
Za izgradnju zgrade potrebno nam je 147 953kg (tj. približno 148 tona) armature.
7
4. GRAĐEVINSKI STROJEVI, ALATI I OPREMA
Građevinski poduhvati tokom svoje realizacije imaju različite transportne zadatke koji se, svaki za
sebe, mogu izvršavati različitim sredstvima za koje se odlučujemo na osnovu razloga koje su
nametnule okolnosti (vrsta transporta, raspoloživa sredstva, zahtijevana dinamika, ekonomski
pokazatelji i dr.).
8
Toranjska dizalicaLIEBHERR 112 EC-H 8 sa slijedećim osnovnim podacima:
• duljina ruke L = 56,4m
• najveća nosivost Qmax = 9000kg
•max. dohvat Lmax = 55m
• dohvat pri max. nosivosti Lmax = 14,5m
• nosivost pri najvećem dohvatu Q(Lmax) = 1600kg
V0= 30 m/min
Vv= 30 m/min
Vkut = 0,5 okr/min
- vrijeme hvatanja (privezivanja) tereta (tp) od 0,65 do 2min
- vrijeme otpuštanja (odvezivanja) tereta (totp) od 0,5 do 1 min
9
5. ANALIZA TRANSPORTA DIZALICOM
5.1. OPLATA
5.1.1. ugradnja oplate za zidove 1. kata
Lv 24
R=40mtv = = = 0,80 min
V v 30
Φ 0.25
Lv= 40m – 16m = 24mtkut = = = 0.5 min
V kut 0.5
10
Vkut = 0.5 okr/min___________________________
60
kut = 90°nc = = 14.02 ciklusa/h
4.28
tp = 0.65 min ___________________________
totp = 1 minUT = nc∙Qc= 14.02 ∙ 2400 = 33 648 kg/h
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 33 648 ∙ 0.92 = 30 956 kg/h
L0 0,5
t0 = = = 0.017 min
V 0 30
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 32 280 ∙ 0.92 = 29 698 kg/h
L0 3,1
t0 = = = 0.103 min
V 0 30
11
L0 = 5.7m tc= totp + 2 ∙ (to+tv+tkut) + tp
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 31104 ∙ 0.92 = 28616 kg/h
L0 5.7
t0 = = = 0.19 min
V 0 30
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 29 928 ∙ 0.92 = 27 534 kg/h
L0 8.3
t0 = = = 0.28 min
V 0 30
12
Lv 24
R=40mtv = = = 0,80 min
V v 30
Φ 0.25
Lv= 40m – 16m = 24m tkut = = = 0.5 min
V kut 0.5
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 32 280 ∙ 0.92 = 29 698 kg/h
L0 3,1
t0 = = = 0.103 min
V 0 30
Lv 24
R=40mtv = = = 0,80 min
V v 30
Φ 0.25
Lv= 40m – 16m = 24m tkut = = = 0.5 min
V kut 0.5
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 31 104 ∙ 0.92 = 28 616 kg/h
13
L0 5.7
t0 = = = 0.19 min
V 0 30
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 29 928 ∙ 0.92 = 27 534 kg/h
L0 8.3
t0 = = = 0.28 min
V 0 30
14
tp = 0.65 min ___________________________
totp = 1 min UT = nc∙Qc= 12.05 ∙ 2400 = 28 920 kg/h
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 28 920 ∙ 0.92 = 26 607 kg/h
L0 10.9
t0 = = = 0.363 min
V 0 30
5.2. ARMATURA
5.2.1. ugradnja armature za 1. kat
Lv 31.5
R=47.5mtv = = = 1,05 min
V v 30
Φ 0.25
Lv= 47.5m – 16m = 31.5m tkut = = = 0.5 min
V kut 0.5
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 29 040 ∙ 0.92 = 26716 kg/h
L0 3,1
t0 = = = 0.103 min
V 0 30
15
Vv = 30 m/min tc = 5.13 min
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 28 080 ∙ 0.92 = 25 834 kg/h
L0 5.7
t0 = = = 0.19 min
V 0 30
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 27120 ∙ 0.92 = 24951 kg/h
L0 8.3
t0 = = = 0.28 min
V 0 30
Lv 31.5
R=47.5mtv = = = 1,05 min
V v 30
16
Φ 0.25
Lv= 47.5m – 16m = 31.5m tkut = = = 0.5 min
V kut 0.5
________________________ ___________________________
Φ = 90°/360 = 0.25 U P = UT ∙ krv = 26 280 ∙ 0.92 = 24 178 kg/h
L0 10.9
t0 = = = 0.363 min
V 0 30
5.3. BETON
17
Proračun težine tereta koji se podiže (košara za beton):
•obujam košare: Qc = V = 0.8 m3
•masa prazne košare: mk = 232 kg
•masa betona u košari: mbet = 0.70 m3∙ 2400 kg/m3 = 1680 kg
• masa pune košare: muk = 232kg + 1680kg = 1912 kg
Φ = 90°/360 = 0.25
L0 0,5
t0 = = = 0.017 min
V 0 30
18
5.3.2. ugradnja betona za zidove 2. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
Φ = 90°/360 = 0.25
L0 3,1
t0 = = = 0.103 min
V 0 30
5.3.3. ugradnja betona za zidove 3. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
19
________________________ UP = UT ∙ krv = 13.18 ∙ 0.84 = 11.07 m3/h
Φ = 90°/360 = 0.25
L0 5,7
t0 = = = 0.19 min
V 0 30
5.3.4. ugradnja betona za zidove 4. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
Φ = 90°/360 = 0.25
L0 8.3
t0 = = = 0.28 min
V 0 30
5.3.5. ugradnja betona za stropnu ploču 1. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
20
60
kut = 90° nc = = 18.35 ciklusa/h
3.27
tpr = 0.60 min ___________________________
tpu = 1 min UT = nc∙Qc= 18.35 ∙ 0.80 = 14.68 m3/h
Φ = 90°/360 = 0.25
L0 3,1
t0 = = = 0.103 min
V 0 30
5.3.6. ugradnja betona za stropnu ploču 2. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
Φ = 90°/360 = 0.25
L0 5,7
t0 = = = 0.19 min
V 0 30
5.3.7. ugradnja betona za stropnu ploču 3. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
21
L0 = 8.3m tc= tpu + 2 ∙ (to+tv+tkut) + tpr
Φ = 90°/360 = 0.25
L0 8.3
t0 = = = 0.28 min
V 0 30
5.3.8. ugradnja betona za stropnu ploču 4. kata
Lv 7
R= 23mtv = = = 0,23 min
V v 30
Φ 0.25
Lv= 23m – 16m = 7m tkut = = = 0.5 min
V kut 0.5
Φ = 90°/360 = 0.25
L0 10.9
t0 = = = 0.363 min
V 0 30
22
6. GRAFIKON
35000
30000
25000
20000
1. kat
prosječno
15000 5. kat
10000
5000
0
oplata (zidovi) oplata (ploče) armatura
23
12.5
12
11.5
1. kat
11
prosječno
4. kat
10.5
10
9.5
beton (zidovi) beton (ploče)
20
18
16
14
12
10
8 broj ciklusa 1. kata
prosječan broj ciklusa za zgradu
6
broj ciklusa 4. kata
4
2
0
i) če
) a i) ča
)
ov lo ur ov
id p at id p lo
(z a( m (z (
a at ar n n
lat l to
be
to
op op be
24
7. TROŠKOVNIK DIZALICE LIEBHERR 112 EC-H 8
- 1479.53 m3betona
- 147 953 kg armature
7.1.Ugradnja oplate
25
Transport, ugradnja oplate i pribora
kranskom dizalicom za zidove 2. kata 29 698 kg/h
Transport, ugradnja oplate i pribora
kranskom dizalicom za zidove 3. kata 28 616 kg/h
Transport, ugradnja oplate i pribora
kranskom dizalicom za zidove 4. kata 27 534 kg/h
SVEUKUPNO 116 804 kg/h
Sveukupna potrebna količina oplate za
zidove 164 364 kg
164 364 kg
= 6h
29201 kg /h
26
Prosječna količina ugradnje oplate za stropnu ploču:
112 455 kg /h
= 28 114 kg/h
4 kata
235 778 kg
=9h
28114 kg /h
27
101679 kg /h
= 25 420 kg/h
4 kata
147 953 kg
=6h
25 420 kg /h
28
Ugradnja betona za zidove 1. kata = 12.26 m3/h
45.51 m3 /h
= 11.38 m3/h
4 kata
29
Prosječna količina ugradnje betona za stropnu ploču:
45.82 m3 /h
= 11.46 m3/h
4 kata
1200 m 3
= 53 h
11.38+11.46 m3 /h