Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 8

5 YEAR AOH PLAN FOR CW & ACW PUMP

FY'2019 FY'2020 FY'2021 FY'2022 FY'2023


CW 1A Dec-19 Dec-20 Dec-21 Dec-22 Dec-23
CW 1B Feb-20 Feb-21 Feb-22 Feb-23
CW 1C Apr-20 Apr-21 Apr-22 Apr-23
CW 2A Jul-19 Jul-20 Jul-21 Jul-22 Jul-23
CW 2B Sep-19 Sep-20 Sep-21 Sep-22 Sep-23

ACW 1B Aug-19 Aug-20 Aug-21 Aug-22 Aug-23


ACW 1C Oct-19 Oct-20 Oct-21 Oct-22 Oct-23
ACW 2B Jan-20 Jan-21 Jan-22 Jan-23

NOTE : AS PER MANUAL AOH TO BE DONE FOR CW PUMP 8000 HRS


5 YEAR AOH PLAN FOR CW & ACW PUMP
Overhauling Plan Remarks
Equipment Code Equipment Name Running Hrs. ↓ (If any)
FY'2019-20 FY'2020-21 FY'2021-22 FY'2022-23 FY'2023-24
CWCWPMME01 CW PUMP 1A 36345 Dec-19 Dec-20 Dec-21 Dec-22 Dec-23

CWCWPMME02 CW PUMP 1B 38880 Feb-20 Feb-21 Feb-22 Feb-23 Feb-24

CWCWPMME03 CW PUMP 1C 23137 - Apr-20 Apr-21 Apr-22 Apr-23

CWCWPMME04 CW PUMP 2A 30020 Jul-19 Jul-20 Jul-21 Jul-22 Jul-23 Last overhauling done 8/8/2018

CWCWPMME05 CW PUMP 2B 26825 Sep-19 Sep-20 Sep-21 Sep-22 Sep-23

CWACWPME01 ACW PUMP 1B 31367 Aug-19 Aug-20 Aug-21 Aug-22 Aug-23

CWACWPME02 ACW PUMP 1C 26632 Oct-19 Oct-20 Oct-21 Oct-22 Oct-23

CWACWPME03 ACW PUMP 2B 29512 Jan-20 Jan-21 Jan-22 Jan-23 Jan-24

NOTE : AS PER MANUAL AOH TO BE DONE FOR CW & ACW PUMP AFTER 8000 RUNNING HOURS
Activities for ACW Pump -1B
Sl. No
1 Permit to work taken
2 All C&I and Electrical probe and cable removed
3 Bearing housing Oil drain
4  Motor to Pump coupling decoupled and recorded gap

5  Motor base bolt loosen and removed

6  Main Motor removed from position

7
Removed pump coupling ,keys, check nut ,Ratchet lock nut ,ratchet cover and ratchet
from shaft, motor stool piece and complete bearing housing
8
Removed discharge head flange bolt and back support flange bolt,pump base bolt
,Muff coupling, split ring and head shaft,discharge head top flange bolt,

9
Removed pump base and stuffing box ,discharge head,Muff coupling, split ring and
line shaft

10
Removed tapper column pipe,Muff coupling, split ring and line shaft,column pipe ,
11 Removed complete bowl assembly,suction bell mouth,muff coupling, split ring and
impeller shaft
12
Cleaning and painting of Taper column pipe, column pipe, Discharge head, suction bell
mouth,and bowl assembly
13 Repairing and balancing of impeller if required.
14 Impeller casing linear replacement and machining if required.
15 Pump casing repair and wear ring replacement if required
16 Replacement of Rubber bearing, shaft sleeves if required
17 complete ball assembly,suction bell mouth,muff coupling, split ring and impeller shaft ,muff
coupling, split ring and line shaft
18 Assembly of column pipe,muff coupling, split ring and line shaft
19 Assembly of Taper column pipe,muff coupling, split ring and line shaft
20 Assembly of Discharge head,stuffing box
21 Assembly of Muff coupling split ring and head shaft,pump base assembly,and bearing
housing,coupiling
22 Assembly of motor, alignment and coupling,cable connection and trial

Note: 1. If muff coupling ,shaft sleeve, flange bolts cutting then Numbers of days reduced .
2. If muff coupling shaft sleeve ,flange bolt not cutting then Numbers of days may be
increases

As there is single EOT crane thus work may be hampered as CW 2A overhauling is U/P.
Responsibiliti Day-1 Day-2 Day-3 Day-4 Day-5 Day-6 Day-7 Day-8 Day-9 Day-10
Day-11 Day-12
Activities for CW Pump -2B
Sl. No
1 Permit to work taken
2 All C&I and Electrical probe and cable removed
3 Bearing housing Oil drain
4  Motor to Pump coupling decoupled and recorded gap

5  Motor base bolt loosen and removed

6  Main Motor removed from position

7
Removed pump coupling ,keys, check nut ,Ratchet lock nut ,ratchet cover and ratchet
from shaft, motor stool piece and complete bearing housing

8
Removed discharge head flange bolt and back support flange bolt,pump base bolt
,Muff coupling, split ring and head shaft,discharge head top flange bolt,

9
Removed pump base and stuffing box ,discharge head,Muff coupling, split ring and
line shaft

10
Removed tapper column pipe,Muff coupling, split ring and line shaft,column pipe ,
11 Removed complete ball assembly,suction bell mouth,muff coupling, split ring and
impeller shaft
12
Cleaning and painting of Taper column pipe, column pipe, Discharge head, suction bell
mouth,and bowl assembly
13 Repairing and balancing of impeller if required.
14 Impeller casing linear replacement and machining if required.
15 Pump casing repair and wear ring replacement if required
16 Replacement of Rubber bearing, shaft sleeves if required
17 complete ball assembly,suction bell mouth,muff coupling, split ring and impeller shaft ,muff
coupling, split ring and line shaft
18 Assembly of column pipe,muff coupling, split ring and line shaft
19 Assembly of Taper column pipe,muff coupling, split ring and line shaft
20 Assembly of Discharge head,stuffing box
21 Assembly of Muff coupling split ring and head shaft,pump base assembly,and bearing
housing,coupiling
22 Assembly of motor, alignment and coupling,cable connection and trial

Note: 1. If muff coupling ,shaft sleeve, flange bolts cutting then Numbers of days reduced .
2. If muff coupling shaft sleeve ,flange bolt not cutting then Numbers of days may be
increases
Responsibiliti Day-1 Day-2 Day-3 Day-4 Day-5 Day-6 Day-7 Day-8 Day-9 Day-10 Day-11 Day-12
Date
Day-13 Day-14

You might also like