Professional Documents
Culture Documents
CDOT LTE ENODEB WEEKLY TRACKER 29 Jan
CDOT LTE ENODEB WEEKLY TRACKER 29 Jan
31/03/2018
31/01/2018
31/01/2018
16/03/2018
31/03/2018
31/03/2018
BBU- Board design
Platform SW Bringup Readyness
Design-documentation
16/03/2018
31/03/2018
31/03/2018
Sr.No Category Risk Description Severity
1588 v2 solution not completely analyzed .
Platform software ( 1588 protocol stack) ,
1 Technical Test configuration needs to be studied. Medium
Redundency/Availability
requirements,serviceability requirement
(MTTR) , MTBF target / supported operating
2 Technical life not available /clear. High
Frogcell :
1. Contract not signed yet.
2. RRH scope is still churning. Current
contract covers development ( HW +
Mechanics +SW), prototype , tooling costs for
3 different varients for RRH. This seem un-
8 Program realistic. High
This may create overall schedule /cost impact Need to identify an owner to study this and
on program if not closed. close before design closure. 1/30/2018
This may create overall schedule /cost impact Requested CDOT to intervene . Vendor kick-
on program if not closed. off to be scheduled.
This may create overall schedule impact on
program if not closed.
Delay in proto-1 build.
Owner Status
Comments
OPEN
CLOSE
Sr.No Category Open Item
1 Requirements
Requirement Sign-off
2 Architecture
BBU Mainboard
Processor Selection
Phy Selection
1588 Solution
BB Module
Memory sizes
Thermal Simulation
SI /PI
3 System
Power Budget and Power distribution
Compliance Plan
Bring-up
DVT
Pre-Compliance
Reliability
High level estimate
Overall FIT estimate
4 Procurement
Preliminary BOM for quote
Proto Board -Vendor quote
Proto Vendor Selection
Proto Board -PO release
Proto procurement
Target Date Owner Status
1/30/2018 OPEN
2/28/2018 OPEN
01/18 : Initial results need refinement. Electrical team shared revised power numbers.
Mechanics is open.
OPEN
CLOSE
BBU Proto-1 Schedule
REQUIREMENTS
DESIGN CONCEPT
IMPLEMENTATION
1-Jan 8-Jan 15-Jan 22-Jan
WK01 WK02 WK03 WK04
CDOT Sign-OFF
BBU Enclosure 1U
Mechanics Concept
Thermal simulation , Heat sink design.
BBU Enclosure
Detailed 3D
EMN Closure
Drawings Release
BB Module- Enclosure
Detailed 3D
EMN Closure
Drawings Release
FPGA
High level Design
Pinout and Power Estimate
Implementation
Initial Binaries available
Layout
Back Plane Board Proto-1 Activities
Target Date
Actual Plan
Sub-Activities Start Date End Date Working days#
Resources
Resources
Vignesh
Remya
Shiladitya/Vikram/Kalidoss/Avinash/Rajesh/Vinesh/Anand
Remya
Shiladitya/Remya/Vidhya
Shiladitya
Raghuram/Venkat
Raghuram/Venkat
Remya/Shiladitya
Dinesh
Dinesh
Vikram/Kalidoss/Vignesh/Shiladitya/Avinash/Rajesh/Vinesh/Anand
Dinesh
Nithin/Shiladitya
Nithin/Shiladitya
Dinesh
Vikram/Kalidoss/Vignesh/Shiladitya/Avinash/Rajesh/Vinesh/Anand
Vignesh
Vikram/Kalidoss
Hi-Q/Prodigy
Vignesh
Vikram/Kalidoss
Vikram/Kalidoss
Raghuram/Venkat
Raghuram/Venkat
Raghuram/Venkat
Resources
% completion ETA
% completion ETA
99% 17-Jan-18
80% 19-Jan-18
0% 22-Jan-18
0%
80% 17-Jan-18
80% 17-Jan-18
99% 17-Jan-18
80% 19-Jan-18
0% 22-Jan-18
0% 10-Feb-18
0% 3-Feb-18
0% 3-Feb-18
0%
% completion ETA
Remarks
Remarks
Open Items
1. Properties updation for components
2. Decision on CPRI redundancy (2 or 4 SFP+ on front haul) (need closure by 17 Jan)- we have to go with 4
SFPs
3. Logic level compatibility check for new IDT clock chip- replaces TI CDCM chip
4. Decap optimisation and footprint update
5. Derating of inductors
6. All programming headers need to be combined for space savings
7. Single net updates
8. Backplane connector update
Dependency on row 25
To be discussed
To be discussed
Remarks
Sr.No Category Description Custom
1 Board BB -TCT Yes
2 Board BB -Module Yes
3 Board BB - Backplane Yes
4 Board PSU module NO
5 Mechanics BBU Enclosure YES
6 Mechanics BBU Cabinet TBD
7 Mechanics BB Module enclosure Yes
8 Mechanics BBU FAN unit Yes
9 Mechanics PSU module enclosure
Target Date Owner Status
2/28/2018 Kalidoss
2/28/2018 Shiladitya
2/28/2018 Kalidoss
2/28/2018 Kalidoss
2/28/2018 Siva + Ajmeer
2/28/2018
2/28/2018 Siva + Ajmeer
2/28/2018 Siva + Ajmeer
Comments
OPEN
CLOSE
MS-1 MS-2 MS-3
1 Hardware
Release Note
BBU Cabinet
Test Jigs
Test Document
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Re-use of existing cabinets from CDOT to be
discussed.
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Y Y Y
Test jig development for manufacturing is not
planned.
Y Y Y
Kamjith 28-Feb-18
Kamjith 9-Mar-18
Kamjith, Harish 23-Mar-18
Harish 28-Feb-18
Kamjith, Harish 30-Mar-18
Activities Sub-Activities
CCT-BB connection
CPRI loopback related
L1 integration activities
Verification of the L1 PHY module for the latest
SDK
FPGA APIs
6-Apr-18 Harish
27-Apr-18 Harish
Remarks
many of these diag tests may be already present in SDK, need to check
need to analyze the delta between EVM and actual design impact